ML20135B575 | 2 December 1996 | Notice of Violation from Insp on 960922-1102.Violation Noted:Listed Instances Where Written Procedures Not Properly Implemented | |
ML20135H782 | 12 September 1985 | Exam Rept 50-458/OL-85-03 on 850729.Exam Results:Two of Five Reactor Operator Candidates & 9 of 12 Senior Reactor Operator Candidates Passed Exams | Reactor Vessel Water Level Half scram Slow transfer Overtravel |
ML20136E488 | 30 December 1985 | Insp Rept 50-458/85-67 on 850923.Violations Noted:Failure to Provide Proper Escort,Failure to Control Badge/Key Cards & Failure to Make Timely Notification.Details Withheld (Ref 10CFR73.21) | |
ML20136G501 | 5 November 1985 | Notice of Violation from Insp on 851007-11 | |
ML20136G505 | 1 November 1985 | Insp Rept 50-458/85-71 on 851007-11.Violation Noted: Procedures STP-051-4228 & STP-051-4201 Permitted Trip Setpoint to Be Calibr Outside Tech Spec Limits | |
ML20136H149 | 1 August 1985 | Notice of Violation from Insp on 850311-0517 | |
ML20137A253 | 14 November 1985 | Notice of Violation from Insp on 850930-1004 | |
ML20137A279 | 13 November 1985 | Insp Rept 50-458/85-66 on 850930-1004.Violations Noted: Failure to Update Procedures After Issuance of Temporary Change Notices & Issuance of Temporary Change Notice After Final Approval | Hydrostatic |
ML20137H947 | 8 January 1986 | Insp Rept 50-458/85-75 on 851022-25.Violation Noted: Inadequate Key Control.Insp Details Withheld (Ref 10CFR73.21) | |
ML20137J625 | 1 April 1997 | Insp Rept 50-458/97-01 on 970127-0214.No Violations Noted. Major Areas Inspected:Operations & Engineering | Reactor Vessel Water Level Half scram Squib Job Performance Measure Scram Discharge Volume Operability Determination Fire Watch Grace period Power change Unidentified leakage |
ML20137T295 | 19 November 1985 | Insp Rept 50-458/85-69 on 850916-1031.Violation Noted: Improper Use of Field Change Notices & Failure of Document Control Program | Fire Barrier |
ML20137T492 | 11 April 1997 | Notice of Violation from Insp on 970202-0315.Violation Noted:As of 970315,administrative Procedures Not Developed in Sufficient Scope to Implement Requirements of TS 5.2.2.e | Missed surveillance |
ML20137T514 | 11 April 1997 | Insp Rept 50-458/97-06 on 970202-0315.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering, Plant Support & Plant Status | High Radiation Area Past operability Enforcement Discretion Locked High Radiation Area Missed surveillance Systematic Assessment of Licensee Performance Hourly Fire Watch |
ML20137W841 | 30 September 1985 | Notice of Violation from Insp on 850616-0815 | |
ML20137W893 | 18 September 1985 | Insp Rept 50-458/85-51 on 850616-0815.Violation Noted: Attachments 1 & 2 for Electrical & Control Board Lineups Not Completed.Deviation Noted:Preoperational Test Procedure 1-PT-210 Did Not Demonstrate RHR Sys Will Inject to Vessel | Stroke time Nondestructive Examination |
ML20138G337 | 21 October 1985 | Notice of Violation from Insp on 850819-23 | |
ML20140B052 | 7 March 1986 | Notice of Violation from Insp on 860101-31 | |
ML20140B070 | 20 February 1986 | Insp Rept 50-458/86-04 on 860101-31.Violation Noted:Failure to Administratively Control Temporary Circuit Alterations & Failure to Schedule Supplemental Audit/Surveillance | |
ML20140D770 | 29 January 1986 | Notice of Violation from Insp on 850311-0810 | |
ML20140E270 | 29 January 1986 | Notice of Violation from Insp on 851201-31 | |
ML20140E285 | 29 January 1986 | Notice of Deviation from Insp on 851201-31 | |
ML20140E298 | 22 January 1986 | Insp Rept 50-458/85-81 on 851201-31.Violations Noted:Failure of Document Control Program & Inadequate Retest Following Mods or Repair.Deviation Noted:Failure to Verify Proper Diesel Generator Load Sequencing | |
ML20140E901 | 18 March 1986 | Notice of Violation from Insp on 860127-31 | |
ML20140E914 | 6 March 1986 | Insp Rept 50-458/86-05 on 860127-31.Violation Noted:Failure to Maintain Calibr Records of Gas Chromatograph While Performing Tech Spec Required Surveillance | |
ML20140H699 | 27 March 1986 | Insp Rept 50-458/86-14 on 860317-20.Violations Noted: Inadequate Corrective Action,Failure to Perform Maint Per Procedures & Inoperable Div II Diesel Generator | Coast down |
ML20141C274 | 1 April 1986 | Notice of Violation from Insp on 860127-31 | Offsite Dose Calculation Manual |
ML20141C286 | 1 April 1986 | Notice of Deviation from Insp on 860127-31 | |
ML20141C330 | 4 March 1986 | Insp Rept 50-458/86-01 on 860127-31.Violation Noted:High & Low Level Alarms on RMS-RE-126 Were Factor of Two Higher than Values Derived Using Offsite Dose Calculation Manual. Deviation Noted:Failure to Maintain Equipment Per FSAR | High Radiation Area Offsite Dose Calculation Manual |
ML20141E323 | 26 June 1997 | Notice of Violation from Insp on 970427-0607.Violation Noted:Licensee Failed to Follow Procedure EIP-2-001,in That Licensee Entered TS Limiting Condition for Operation 3.4.5 Upon Determination & Did Not Declare Unusual Event | Pressure Boundary Leakage Fire Protection Program Fire Watch Hourly Fire Watch |
ML20141G574 | 19 May 1997 | Notice of Violation from Insp on 970316-0426.Violation Noted:Three Examples Identified Where Procedures Were Not Adequately Maintained,Procedures Did Not Require Independent Verification of Activities Prescribed in ANSI 18.7-1976 | Temporary Modification |
ML20147J182 | 3 March 1988 | Notice of Violation from Insp on 871101-21.Violation Noted: One of Two Channels in One Trip Sys for RPS Initiation & Two of Four Channels for HPCS Initiation Were Inoperable When Instrument Root Valve 1RCS-V122 Closed | |
ML20148G363 | 15 March 1988 | Insp Rept 50-458/88-07 on 880222-25.Deficiencies Noted.Major Areas Inspected:Annual Emergency Preparedness Exercise | |
ML20149D345 | 4 February 1988 | Notice of Violation from Insp on 871207-10 & 20-23.Violation Noted:Procedures & Emergency Training Deemed Ineffective Due to Listed Weaknesses Being Exhibited During Training Class Sessions | |
ML20149D394 | 3 February 1988 | Insp Rept 50-458/87-30 on 871207-10 & 20-23.Violation Noted. Major Areas Inspected:Licensee Notifications,Communications & Emergency Preparedness Training Program | |
ML20149F554 | 8 August 1994 | Notice of Violation from Insp on Stated Date.Violation Noted:Maint Work Order E568208 Did Not Include Step for Installation of Jumper to Prevent Interruption of Power Supply Neutral Circuit | |
ML20149F570 | 5 August 1994 | Insp Rept 50-458/94-15 on Stated Date.Violations Noted. Major Areas Inspected:Onsite Response to Events,Operational Safety Verification,Maint & Surveillance Observations, Followup Maint & Review of LER | Reactor Vessel Water Level High Radiation Area Half scram Stroke time Deep Dose Equivalent Power-Operated Valves |
ML20149H141 | 21 July 1997 | Partially Withheld Notice of Violation from Insp on 970623-27.Violation Noted:On 970626,inspector Identified That Video Capture Sys Did Not Have Capability of Generating Audible Alarm | |
ML20149H144 | 21 July 1997 | Partially Withheld Insp Rept 50-458/97-11 on 970623-27.Major Areas Inspected:Specific Areas of Physical Security Program Including Review of Records & Repts,Testing & Maint,Vital Area Barriers & Detection Aids & Alarm Stations | |
ML20150B493 | 9 March 1988 | Notice of Violation from Insp on 880101-0215.Violation Noted:On 880121,specified Corrective Action Had Not Been Completed for Nonconforming Condition Identified by Licensee on 860412 | |
ML20150B505 | 4 March 1988 | Insp Rept 50-458/88-01 on 880101-0215.Violation Noted.Major Areas Inspected:Nrc Bulletin 87-002,10CFR21 Repts, Surveillance Test Observation,Maint Observation,Safety Sys Walkdown & Operational Safety Verification | Scram Discharge Volume |
ML20151G095 | 15 July 1988 | Notice of Violation from Insp on 880501-0630.Violation noted:at-the-controls Operator Not Cognizant as to Why Annunciator P863-75A-CO2, Fuel Bldg Supply Air Low Flow, Was Lit | |
ML20151G097 | 15 July 1988 | Insp Rept 50-458/88-13 on 880501-0630.Violation Noted.Major Areas Inspected:Previous Insp Findings,Nrc Bulletins 88-001 & 88-007,NRC Info Notices,Surveillance Test Observation, Maint Observation & Safety Sys Walkdown | Squib Liquid penetrant Inadvertent Siren Activation |
ML20151N053 | 18 December 1985 | Notice of Violation from Insp on 851021-25 | |
ML20151N079 | 11 December 1985 | Insp Rept 50-458/85-74 on 851021-25.Violation Noted:Failure to Have Required Records of Standby Liquid Control Sys Explosive Valves | |
ML20151N662 | 30 December 1985 | Notice of Violation from Insp on 851028-1101 | |
ML20151N667 | 30 December 1985 | Notice of Deviation from Insp on 851028-1101 | |
ML20151N671 | 3 December 1985 | Insp Rept 50-458/85-73 on 851028-1101.Deviation Noted:Senior Radiation Protection Technicians Not Provided W/Proper Training.Violation Noted:Qualification Matrix for Technicians Not Updated for Period in Excess of 8 Months | |
ML20151R690 | 19 April 1988 | Notice of Violation from Insp on 871102-06 & 1218.Violation Noted:Equipment Qualification File for T95 & 35 Tape Splices Used in Limitorque Smb/Sb Motor Operators Inside & Outside Containment,Did Not Adequately Support Qualification | |
ML20151R716 | 5 April 1988 | Insp Rept 50-458/87-21 on 871102-26 & 1218.Violations Noted. Major Areas Inspected:Licensee Implementation of Program for Establishing & Maintaining Qualification of Electric Equipment within Scope of 10CFR50.49 | |
ML20151X816 | 18 August 1988 | Exam Rept 50-458/OL-88-01 on 880712-13.Exam Results:Two Candidates Passed All Portions of Exam & Have Been Issued Appropriate License.One Candidate Failed Exam |