{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 14, 2013  
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 14, 2013 LICENSEE:     FirstEnergy Nuclear Generation, LLC FACILITY:     Davis-Besse Nuclear Power Station
 
LICENSEE: FirstEnergy Nuclear Generation, LLC  
 
FACILITY: Davis-Besse Nuclear Power Station  


==SUBJECT:==
==SUBJECT:==


==SUMMARY==
==SUMMARY==
OF THE JUNE 11, 2013, OPEN HOUSE TO DISCUSS THE 2012 DAVIS-BESSE NUCLEAR POWER STATION END-OF-CYCLE PERFORMANCE ASSESSMENT  
OF THE JUNE 11, 2013, OPEN HOUSE TO DISCUSS THE 2012 DAVIS-BESSE NUCLEAR POWER STATION END-OF-CYCLE PERFORMANCE ASSESSMENT On June 11, 2013, an open house/poster session was held at the Carroll Township Service Complex in Oak Harbor, Ohio, between the U.S. Nuclear Regulatory Commission (NRC) and the Davis-Besse Nuclear Power Station management and the public to discuss NRC activities, nuclear power issues, and Davis-Besse Nuclear Power Station performance for the period of January 1, 2012, through December 31, 2012, including discussion of activities related to the upcoming steam generator replacement. The NRC letter and meeting notice for this open house can be found in the Agencywide Documents Access and Management System (ADAMS) as ML13144A754 and ML13144A790, respectively. A list of the open house attendees who signed the attendance sheet is enclosed. The presentation that was shown during the open house can also be found in ADAMS as ML13157A064.
 
On June 11, 2013, an open house/poster session was held at the Carroll Township Service Complex in Oak Harbor, Ohio, between the U.S. Nuclear Regulatory Commission (NRC) and the Davis-Besse Nuclear Power Station management and the public to discuss NRC activities, nuclear power issues, and Davis-Besse Nuclear Power Station performance for the period of January 1, 2012, through December 31, 2012, including discussion of activities related to the  
 
upcoming steam generator replacement. The NRC letter and meeting notice for this open house can be found in the Agencywide Documents Access and Management System (ADAMS) as ML13144A754 and ML13144A790, respectively. A list of the open house attendees who signed the attendance sheet is enclosed. The presentation that was shown during the open house can also be found in ADAMS as ML13157A064.  
 
The open house/poster session consisted of the NRC listening to comments and answering questions from the public. In addition, licensee staff was present to address any end-of-cycle performance questions from the public.
The open house/poster session consisted of the NRC listening to comments and answering questions from the public. In addition, licensee staff was present to address any end-of-cycle performance questions from the public.
Sincerely,       /RA/ Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects  
Sincerely,
 
                                              /RA/
Docket No. 50-346 License No. NPF-3  
Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket No. 50-346 License No. NPF-3


==Enclosure:==
==Enclosure:==
As Stated  
As Stated cc w/encl:     Distribution via ListServTM
 
cc w/encl: Distribution via ListServ TM UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL  60532-4352 June 14, 2013
 
LICENSEE: FirstEnergy Nuclear Generation, LLC


FACILITY: Davis-Besse Nuclear Power Station  
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 14, 2013 LICENSEE:        FirstEnergy Nuclear Generation, LLC FACILITY:         Davis-Besse Nuclear Power Station


==SUBJECT:==
==SUBJECT:==
Line 49: Line 36:
OF THE JUNE 11, 2013, OPEN HOUSE TO DISCUSS THE 2012 DAVIS-BESSE NUCLEAR POWER STATION END-OF-CYCLE PERFORMANCE ASSESSMENT On June 11, 2013, an open house/poster session was held at the Carroll Township Service Complex in Oak Harbor, Ohio, between the U.S. Nuclear Regulatory Commission (NRC) and the Davis-Besse Nuclear Power Station management and the public to discuss NRC activities, nuclear power issues, and Davis-Besse Nuclear Power Station performance for the period of January 1, 2012, through December 31, 2012, including discussion of activities related to the upcoming steam generator replacement. The NRC letter and meeting notice for this open house can be found in the Agencywide Documents Access and Management System (ADAMS) as ML13144A754 and ML13144A790, respectively. A list of the open house attendees who signed the attendance sheet is enclosed. The presentation that was shown during the open house can also be found in ADAMS as ML13157A064.
OF THE JUNE 11, 2013, OPEN HOUSE TO DISCUSS THE 2012 DAVIS-BESSE NUCLEAR POWER STATION END-OF-CYCLE PERFORMANCE ASSESSMENT On June 11, 2013, an open house/poster session was held at the Carroll Township Service Complex in Oak Harbor, Ohio, between the U.S. Nuclear Regulatory Commission (NRC) and the Davis-Besse Nuclear Power Station management and the public to discuss NRC activities, nuclear power issues, and Davis-Besse Nuclear Power Station performance for the period of January 1, 2012, through December 31, 2012, including discussion of activities related to the upcoming steam generator replacement. The NRC letter and meeting notice for this open house can be found in the Agencywide Documents Access and Management System (ADAMS) as ML13144A754 and ML13144A790, respectively. A list of the open house attendees who signed the attendance sheet is enclosed. The presentation that was shown during the open house can also be found in ADAMS as ML13157A064.
The open house/poster session consisted of the NRC listening to comments and answering questions from the public. In addition, licensee staff was present to address any end-of-cycle performance questions from the public.
The open house/poster session consisted of the NRC listening to comments and answering questions from the public. In addition, licensee staff was present to address any end-of-cycle performance questions from the public.
Sincerely,             /RA/ Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket No. 50-346 License No. NPF-3  
Sincerely,
                                                    /RA/
Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket No. 50-346 License No. NPF-3


==Enclosure:==
==Enclosure:==
As Stated cc w/encl: Distribution via ListServ TM  DOCUMENT NAME:   Daviss Besse EOC 2012 Summary Publicly Available Non-Publicly Available   Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" =
As Stated cc w/encl:       Distribution via ListServTM DOCUMENT NAME:           Daviss Besse EOC 2012 Summary Publicly Available           Non-Publicly Available           Sensitive     Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" =
Copy with attach/encl "N" = No copy OFFICE RIII   RIII       NAME PSmagacz:rj JCameron DATE 06/14/13 06/14/13 OFFICIAL RECORD COPY Enclosure OPEN HOUSE PRINCIPLE ATTENDEES June 11, 2013 NRC Jamnes Cameron
Copy with attach/encl "N" = No copy OFFICE     RIII                     RIII NAME       PSmagacz:rj             JCameron DATE     06/14/13                 06/14/13 OFFICIAL RECORD COPY
 
Dave Hills Dan Kimble Elba Sanchez Jakob Steffes


FirstEnergy Nuclear Generation, LLC Ray Lieb Larry Rushing  
OPEN HOUSE PRINCIPLE ATTENDEES June 11, 2013 NRC Jamnes Cameron Dave Hills Dan Kimble Elba Sanchez Jakob Steffes FirstEnergy Nuclear Generation, LLC Ray Lieb Larry Rushing Gerald Wolf Mia Moore Ottawa County Commissioners Jim Sass Steve Arndt Others Kevin Kamps, Beyond Nuclear Roberta Redfern, Toledo Blade Rob Leidy, Ohio Department of Health Peter Hill, Ohio Emergency Management Agency Jane Ruvolo, Office of U.S. Representative Marcy Kaptur Enclosure


Gerald Wolf Mia Moore
Letter to FirstEnergy Nuclear Generation, LLC from Jamnes L. Cameron dated June 14, 2013.
 
Ottawa County Commissioners
 
Jim Sass Steve Arndt
 
Others Kevin Kamps, Beyond Nuclear Roberta Redfern, Toledo Blade Rob Leidy, Ohio Department of Health Peter Hill, Ohio Emergency Management Agency
 
Jane Ruvolo, Office of U.S. Representative Marcy Kaptur
 
Letter to FirstEnergy Nuclear Generation, LLC from Jamnes L. Cameron dated June 14, 2013.  


==SUBJECT:==
==SUBJECT:==


==SUMMARY==
==SUMMARY==
OF THE JUNE 11, 2013, OPEN HOUSE TO DISCUSS THE 2012 DAVIS-BESSE NUCLEAR POWER STATION END-OF-CYCLE PERFORMANCE ASSESSMENT  
OF THE JUNE 11, 2013, OPEN HOUSE TO DISCUSS THE 2012 DAVIS-BESSE NUCLEAR POWER STATION END-OF-CYCLE PERFORMANCE ASSESSMENT DISTRIBUTION:
 
Doug Huyck RidsNrrDorlLpl3-2 Resource RidsNrrPMDavisBesse Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPassessment.Resource@nrc.gov}}
DISTRIBUTION
: Doug Huyck  
 
RidsNrrDorlLpl3-2 Resource RidsNrrPMDavisBesse Resource RidsNrrDirsIrib Resource  
 
Chuck Casto Cynthia Pederson Steven Orth Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPassessment.Resource@nrc.gov}}

Latest revision as of 17:55, 4 November 2019

6/11/2013 - Summary of Open House to Discuss the 2012 Davis-Besse Nuclear Power Station End-Of-Cycle Performance
ML13168A242
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 06/14/2013
From: Jamnes Cameron
NRC/RGN-III/DRP/B6
To:
References
Download: ML13168A242 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 14, 2013 LICENSEE: FirstEnergy Nuclear Generation, LLC FACILITY: Davis-Besse Nuclear Power Station

SUBJECT:

SUMMARY

OF THE JUNE 11, 2013, OPEN HOUSE TO DISCUSS THE 2012 DAVIS-BESSE NUCLEAR POWER STATION END-OF-CYCLE PERFORMANCE ASSESSMENT On June 11, 2013, an open house/poster session was held at the Carroll Township Service Complex in Oak Harbor, Ohio, between the U.S. Nuclear Regulatory Commission (NRC) and the Davis-Besse Nuclear Power Station management and the public to discuss NRC activities, nuclear power issues, and Davis-Besse Nuclear Power Station performance for the period of January 1, 2012, through December 31, 2012, including discussion of activities related to the upcoming steam generator replacement. The NRC letter and meeting notice for this open house can be found in the Agencywide Documents Access and Management System (ADAMS) as ML13144A754 and ML13144A790, respectively. A list of the open house attendees who signed the attendance sheet is enclosed. The presentation that was shown during the open house can also be found in ADAMS as ML13157A064.

The open house/poster session consisted of the NRC listening to comments and answering questions from the public. In addition, licensee staff was present to address any end-of-cycle performance questions from the public.

Sincerely,

/RA/

Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket No. 50-346 License No. NPF-3

Enclosure:

As Stated cc w/encl: Distribution via ListServTM

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 14, 2013 LICENSEE: FirstEnergy Nuclear Generation, LLC FACILITY: Davis-Besse Nuclear Power Station

SUBJECT:

SUMMARY

OF THE JUNE 11, 2013, OPEN HOUSE TO DISCUSS THE 2012 DAVIS-BESSE NUCLEAR POWER STATION END-OF-CYCLE PERFORMANCE ASSESSMENT On June 11, 2013, an open house/poster session was held at the Carroll Township Service Complex in Oak Harbor, Ohio, between the U.S. Nuclear Regulatory Commission (NRC) and the Davis-Besse Nuclear Power Station management and the public to discuss NRC activities, nuclear power issues, and Davis-Besse Nuclear Power Station performance for the period of January 1, 2012, through December 31, 2012, including discussion of activities related to the upcoming steam generator replacement. The NRC letter and meeting notice for this open house can be found in the Agencywide Documents Access and Management System (ADAMS) as ML13144A754 and ML13144A790, respectively. A list of the open house attendees who signed the attendance sheet is enclosed. The presentation that was shown during the open house can also be found in ADAMS as ML13157A064.

The open house/poster session consisted of the NRC listening to comments and answering questions from the public. In addition, licensee staff was present to address any end-of-cycle performance questions from the public.

Sincerely,

/RA/

Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket No. 50-346 License No. NPF-3

Enclosure:

As Stated cc w/encl: Distribution via ListServTM DOCUMENT NAME: Daviss Besse EOC 2012 Summary Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" =

Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME PSmagacz:rj JCameron DATE 06/14/13 06/14/13 OFFICIAL RECORD COPY

OPEN HOUSE PRINCIPLE ATTENDEES June 11, 2013 NRC Jamnes Cameron Dave Hills Dan Kimble Elba Sanchez Jakob Steffes FirstEnergy Nuclear Generation, LLC Ray Lieb Larry Rushing Gerald Wolf Mia Moore Ottawa County Commissioners Jim Sass Steve Arndt Others Kevin Kamps, Beyond Nuclear Roberta Redfern, Toledo Blade Rob Leidy, Ohio Department of Health Peter Hill, Ohio Emergency Management Agency Jane Ruvolo, Office of U.S. Representative Marcy Kaptur Enclosure

Letter to FirstEnergy Nuclear Generation, LLC from Jamnes L. Cameron dated June 14, 2013.

SUBJECT:

SUMMARY

OF THE JUNE 11, 2013, OPEN HOUSE TO DISCUSS THE 2012 DAVIS-BESSE NUCLEAR POWER STATION END-OF-CYCLE PERFORMANCE ASSESSMENT DISTRIBUTION:

Doug Huyck RidsNrrDorlLpl3-2 Resource RidsNrrPMDavisBesse Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPassessment.Resource@nrc.gov