ML14087A366: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 19: Line 19:
=Text=
=Text=
{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:UNITED STATES
NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352  
                            NUCLEAR REGULATORY COMMISSION
March 28, 2014  
                                                REGION III
                                    2443 WARRENVILLE RD. SUITE 210
EA-12-009  
                                          LISLE, IL 60532-4352
                                          March 28, 2014
EA-12-009
EA-13-125
Mr. Eric McCartney
Site Vice President
NextEra Energy Point Beach, LLC
6610 Nuclear Road
Two Rivers, WI 54241
SUBJECT: POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2
            NRC 95002 SUPPLEMENTAL INSPECTION REPORT
            05000266/2014007; 05000301/2014007
Dear Mr. McCartney:
On March 6, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed a follow-up
supplemental inspection pursuant to Inspection Procedure 95002, Supplemental Inspection for
One Degraded Cornerstone or any Three White Inputs in a Strategic Performance Area, at
your Point Beach Nuclear Plant, Units 1 and 2. The enclosed report documents the results of
this inspection, which were discussed at the exit on March 6, 2014, with you and other members
of your staff.
In accordance with the NRC Reactor Oversight Process (ROP), this follow-up supplemental
inspection was performed to assess the White inspection finding for the failure of the Unit 1
Turbine Driven Auxiliary Feedwater Pump (TDAFWP) and the White inspection finding for
external wave run-up flooding. These two White findings both in the Mitigating Systems
Cornerstone placed Point Beach Unit 1 in a degraded cornerstone as of the first quarter of
2013. In addition to these two White findings we requested that you also include in your
assessment the White finding in the Emergency Preparedness (EP) Cornerstone that had been
issued on July 24, 2012. A 95001, Supplemental Inspection for One or Two Inputs in a
Strategic Performance Area, had previously been performed for the White EP finding and the
White TDAFWP finding.
The NRC staff was informed on October 29, 2013, of your readiness, as of that date for us to
conduct this supplemental inspection.
The objectives of this supplemental inspection were to: (1) provide assurance that the root
causes and the contributing causes for the risk significant issues were understood;
(2) independently assess and provide assurance that the extent of condition and extent of cause
of the individual and collective issues were identified; (3) determine if safety culture components
caused or significantly contributed to the individual or collective issues; and (4) provide
assurance that the corrective actions were or will be sufficient to address and preclude
repetition of the root and contributing causes.


EA-13-125
E. McCartney                                  -2-
The inspection consisted of an examination of activities conducted under your license as they
related to safety, compliance with the Commissions rules and regulations, and the conditions of
your operating license. The inspectors reviewed selected procedures and records, observed
activities, and interviewed personnel.
Based on the results of the inspection, the NRC determined that Point Beach had performed an
acceptable evaluation of the White EP finding and the White TDAFWP finding but had not
performed an acceptable evaluation of the White flooding finding and had not performed an
acceptable evaluation of the collective White inputs. Taken collectively the issues associated
with the White flooding finding represented a significant weakness, as discussed in Inspection
Procedure (IP) 95002, and your actions to date have not provided the assurance level required
to meet the inspection objectives. The inspection determined that your staff failed to adequately
evaluate the root causes, contributing causes, extent-of-condition, or extent-of-cause of the
safety-significant finding, and take or plan adequate corrective actions to address the root
causes, contributing causes, extent-of-condition, or extent-of-cause and to prevent recurrence
of the safety-significant finding. The White finding associated with Notice of Violation (NOV)
05000266/2013002-10 and 05000301/2013002-10 will be held open. Specific items are
discussed in additional detail in each section of the attached inspection report.
When informed of your readiness, a future inspection will be conducted to verify the corrective
actions that your staff has put in place to address and preclude a repetition of the White flooding
finding.
Based on the results of this inspection, three NRC-identified findings of very low safety
significance (Green) that involved violations of NRC requirements were identified. The NRC
identified an additional Green finding that was associated with a Severity Level IV violation of
NRC requirements evaluated through the traditional enforcement process. However, because
of their very low safety significance, and because these issues were entered into your corrective
action program, the NRC is treating these violations as non-cited violations (NCVs) in
accordance with Section 2.3.2 of the NRC Enforcement Policy.
If you contest the subject or severity of these NCVs, you should provide a response within
30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear
Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a
copy to the Regional Administrator, U.S. Nuclear Regulatory Commission - Region III,
2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement,
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector
Office at the Point Beach Nuclear Plant. In addition, if you disagree with the cross-cutting
aspect assigned to any finding in this report, you should provide a response within 30 days of
the date of this inspection report, with the basis for your disagreement, to the Regional
Administrator, Region III, and the NRC Resident Inspector at the Point Beach Nuclear Plant.
As a result of the Safety Culture Common Language Initiative, the terminology and coding of
cross-cutting aspects were revised beginning in calendar year (CY) 2014. New cross-cutting
aspects identified in CY 2014 will be coded under the latest revision to Inspection Manual
Chapter (IMC) 0310. Cross-cutting aspects identified in the last six months of 2013 using the


Mr. Eric McCartney Site Vice President
E. McCartney                                   -3-
NextEra Energy Point Beach, LLC
previous terminology will be converted to the latest revision in accordance with the
6610 Nuclear Road
cross-reference in IMC 0310. The revised cross-cutting aspects will be evaluated for
Two Rivers, WI  54241
cross-cutting themes and potential substantive cross-cutting issues in accordance with
SUBJECT:  POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2  NRC 95002 SUPPLEMENTAL INSPECTION REPORT 05000266/2014007; 05000301/2014007
IMC-0305 starting with the CY 2014 mid-cycle assessment review.
Dear Mr. McCartney:
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and
its enclosure, and your response (if any) will be available electronically for public inspection in
On March 6, 2014, the U.S. Nuclear Regulator
the NRC Public Document Room or from the Publicly Available Records System (PARS)
y Commission (NRC) completed a follow-up supplemental inspection pursuant to Inspection Procedure 95002, "Supplemental Inspection for
component of NRC's Agencywide Documents Access and Management System (ADAMS),
One Degraded Cornerstone or any Three White Inputs in a Strategic Performance Area," at your Point Beach Nuclear Plant, Units 1 and 2.  The enclosed report documents the results of this inspection, which were discussed at the exit on March 6, 2014, with you and other members
accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public
of your staff.  
Electronic Reading Room).
                                              Sincerely,
                                              /RA/
                                              Anne T. Boland, Director
                                              Division of Reactor Projects
Docket Nos. 50-266; 50-301
License Nos. DPR-24; DPR-27
Enclosure:
IR 05000266/2014007; 05000301/2014007
  w/Attachment: Supplemental Information
cc w/encl: Distribution via ListServTM


          U.S. NUCLEAR REGULATORY COMMISSION
In accordance with the NRC Reactor Oversight
                          REGION III
Process (ROP), this follow-up supplemental inspection was performed to assess the White inspection finding for the failure of the Unit 1 Turbine Driven Auxiliary Feedwater Pump (TDAFWP) and the White inspection finding for
Docket Nos:        05000266; 05000301
external wave run-up flooding.  These two White findings both in the Mitigating Systems Cornerstone placed Point Beach Unit 1 in a degraded cornerstone as of the first quarter of
License Nos:        DPR-24; DPR-27
2013. In addition to these two White findings we requested that you also include in your
Report No:          05000266/2014007; 05000301/2014007
assessment the White finding in the Emergency Preparedness (EP) Cornerstone that had been
Licensee:          NextEra Energy Point Beach, LLC
issued on July 24, 2012. A 95001, Supplemental Inspection for One or Two Inputs in a Strategic Performance Area, had previously been performed for the White EP finding and the White TDAFWP finding. The NRC staff was informed on October 29, 2013, of your readiness, as of that date for us to conduct this supplemental inspection. The objectives of this supplemental inspection were to:  (1) provide assurance that the root causes and the contributing causes for the risk significant issues were understood;
Facility:          Point Beach Nuclear Plant, Units 1 and 2
(2) independently assess and provide assurance that the extent of condition and extent of cause of the individual and collective issues were identified; (3) determine if safety culture components
Location:          Two Rivers, WI
caused or significantly contributed to the individual or collective issues; and (4) provide assurance that the corrective actions were or will be sufficient to address and preclude repetition of the root and contributing causes.  
Dates:              February 3, 2014, through March 6, 2014
 
Inspectors:        B. Bartlett, Project Engineer
E. McCartney  -2-
                    J. Beavers, Emergency Preparedness Inspector
                    R. Elliott, Acting Resident Inspector, Point Beach
The inspection consisted of an examination of activities conducted under your license as they related to safety, compliance with the Commission's rules and regulations, and the conditions of your operating license.  The inspectors reviewed selected procedures and records, observed
                    J. Jandovitz, Project Engineer
activities, and interviewed personnel.
                    K. Miller, Resident Inspector, Watts Bar
                    P. Voss, Resident Inspector, Monticello
Approved by:        J. Cameron, Chief
                    Branch 4
                    Division of Reactor Projects
                                                                      Enclosure


                                      SUMMARY OF FINDINGS
Based on the results of the inspection, the NRC determined that Point Beach had performed an
Inspection Report (IR) 05000266/2014007, 05000301/2014007; 02/03/2014 - 03/06/2014;
acceptable evaluation of the White EP finding and the White TDAFWP finding but had not
Point Beach Nuclear Plant, Units 1 and 2; Supplemental Inspection - Inspection Procedure
performed an acceptable evaluation of the White flooding finding and had not performed an acceptable evaluation of the collective White inputs.  Taken collectively the issues associated
(IP) 95002, Supplemental Inspection for One Degraded Cornerstone or any Three White Inputs
with the White flooding finding represented a significant weakness, as discussed in Inspection  
in a Strategic Performance Area.
Procedure (IP) 95002, and your actions to date have not provided the assurance level required
This inspection was conducted by three regional inspectors and three resident inspectors. The
to meet the inspection objectives.  The inspection determined that your staff failed to adequately evaluate the root causes, contributing causes, extent-of-condition, or extent-of-cause of the safety-significant finding, and take or plan adequate corrective actions to address the root
inspectors identified three NRC-identified findings of very low safety significance (Green) that
causes, contributing causes, extent-of-condition, or extent-of-cause and to prevent recurrence
involved violations of NRC requirements. The NRC identified an additional Green finding that
of the safety-significant finding.  The White finding associated with Notice of Violation (NOV) 05000266/2013002-10 and 05000301/2013002-10 will be held open.  Specific items are
was associated with a Severity Level IV violation of NRC requirements evaluated through the
discussed in additional detail in each section of the attached inspection report. When informed of your readiness, a future inspection will be conducted to verify the corrective actions that your staff has put in place to address and preclude a repetition of the White flooding finding. Based on the results of this inspection, three NRC-identified findings of very low safety significance (Green) that involved violations of NRC requirements were identified. The NRC identified an additional Green finding that was associated with a Severity Level IV violation of  
traditional enforcement process. The significance of most findings is indicated by their color
NRC requirements evaluated through the traditional enforcement process. However, because of their very low safety significance, and because these issues were entered into your corrective action program, the NRC is treating these violations as non-cited violations (NCVs) in accordance with Section 2.3.2 of the NRC Enforcement Policy. If you contest the subject or severity of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear
(Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, Significance
Regulatory Commission, ATTN:  Document Control Desk, Washington, DC 20555-0001, with a
Determination Process (SDP). Assigned cross-cutting aspects were determined using
copy to the Regional Administrator, U.S. Nuclear Regulatory Commission - Region III,
IMC 0310, Components Within the Cross-Cutting Areas. Findings for which the SDP does not
2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement,  
apply may be Green or be assigned a severity level after NRC management review. The NRCs
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector Office at the Point Beach Nuclear Plant. In addition, if you disagree with the cross-cutting aspect assigned to any finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region III, and the NRC Resident Inspector at the Point Beach Nuclear Plant. As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised beginning in calendar year (CY) 2014.  New cross-cutting
program for overseeing the safe operation of commercial nuclear power reactors is described in
aspects identified in CY 2014 will be coded under the latest revision to Inspection Manual Chapter (IMC) 0310.  Cross-cutting aspects identified in the last six months of 2013 using the  
NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.
E. McCartney -3-
Cornerstone: Mitigating Systems
The NRC staff performed this follow-up supplemental inspection in accordance with
previous terminology will be converted to the latest revision in accordance with the cross-reference in IMC 0310. The revised cross-cutting aspects will be evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC-0305 starting with the CY 2014 mid-cycle assessment review.  
Inspection Procedure 95002, Inspection for One Degraded Cornerstone or Any Three
White Inputs in a Strategic Performance Area, to continue to assess the licensees
evaluation of two White inspection findings that affected the Mitigating Systems Cornerstone.
The inspection team determined that the licensee performed an adequate evaluation of some of
the issues, but failed to perform an adequate evaluation of some issues. The inspection team
determined that the root cause evaluation for the Turbine Driven Auxiliary Feedwater Pump
(TDAFWP) appropriately evaluated the root and contributing causes, adequately addressed the
extent of condition and cause, assessed safety culture, and established corrective actions for
the risk significant performance issues. However, the inspection team determined that for the
flooding White finding that the licensee failed to appropriately evaluate the root and contributing
causes, failed to adequately address the extent of condition and cause, failed to adequately
assess safety culture, and failed to establish adequate corrective actions. In addition to
assessing the licensees evaluations, the inspection team independently performed an extent of
condition and extent of cause review of the two findings and a review of the site safety culture
as it related to the root cause evaluations. The team concluded that the licensees root cause
evaluations and corrective actions, both completed and planned, were sufficient to address the
causes and prevent recurrence for the TDAFWP White finding but had significant weaknesses
resulting in failure for the flooding White finding. The licensees implementation of corrective
actions for the TDAFWP will be reviewed during future inspections.
                                                    2


A.  NRC-Identified and Self-Revealed Findings
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and  
  * Green. The inspectors identified a finding of very low safety significance and associated
its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management
    non-citied violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Actions, in
System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).  
    that from March 13, 2013 until February 14, 2014, the licensee failed to assure that for a
    significant condition adverse to quality (SQAC), the cause of the condition was
    determined and corrective actions were taken to preclude repetition. Specifically, the
    licensees corrective actions failed to preclude repetition of an SQAC where Procedure
    PC 80 Part 7, Lake Water Level Determination, as implemented, would not protect
    safety-related equipment in the turbine building or Circulating Water Pump House
    (CWPH). After the licensee had taken corrective actions to improve the wave barrier
    procedure in response to an NRC-identified NOV, PC 80 Part 7 and other flood
    protection implementing procedures specified inadequate timelines to ensure wave
    run-up flood barriers would be installed prior to the lake level at which wave run-up could
    impact the site. Corrective actions for this issue included changing the affected
    procedures to install the wave barriers at a lower lake level, changing the lake level
    determination surveillance from monthly to weekly, and reducing the allowed installation
    time for the barriers from 3 weeks to 1 week.
    The performance deficiency was screened against the Reactor Oversight Process per
    the guidance of lMC 0612, Appendix B, and determined to be more than minor because
    the finding was associated with the Mitigating Systems Cornerstone attributes of
    Protection Against External Factors (Flood Hazard) and Procedure Quality, and
    adversely affected the cornerstone objective to ensure the availability, reliability, and
    capability of systems that respond to initiating events to prevent undesirable
    consequences (i.e. core damage). Specifically, the licensees failure to correct
    procedural deficiencies associated with flood barrier construction timelines, could
    challenge the timely installation of the barriers, which could impact the ability of
    mitigating systems to respond during an external flooding event. The inspectors
    evaluated the finding using IMC 0609, Attachment 0609.04, Tables 2 and 3, and
    Appendix A. Based on a review of Appendix A, Exhibit 2, Item 4.B, the inspectors
    determined that this issue screened as having very low safety significance (Green).
    This finding has a cross-cutting aspect in the area of problem identification and
    resolution, because the licensee failed to thoroughly evaluate issues to ensure that
    resolutions address causes and extent of conditions commensurate with their safety
    significance. (P.2)
  * Green. The inspectors identified a finding of very low safety significance and associated
    non-citied violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions,
    Procedures, and Drawings, in that from January 19, 1996 until November 25, 2013, the
    licensee failed to ensure that activities affecting quality were prescribed by documented
    procedures of a type appropriate to the circumstances to address external flooding as
    described in the Final Safety Analysis Report (FSAR). Specifically, PC 80 Part 7, Lake
    Water Level Determination directed advanced installation of concrete barriers to protect
    against deep wave action from the lake, which introduced significant unrecognized
    blockages in the natural drainage path credited in the FSAR to protect against the
    probable maximum precipitation and Turbine Building internal flooding events.
    Corrective actions for this issue included changing the procedure and FSAR to include
    actions to provide an additional flood relief path through the CWPH building and reliance
    on internal flood relief dampers for the affected flooding events.
                                                3


Sincerely, /RA/  Anne T. Boland, Director
  The performance deficiency was screened against the Reactor Oversight Process per
Division of Reactor Projects
  the guidance of lMC 0612, Appendix B, and determined to be more than minor because
Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27
  the finding was associated with the Mitigating Systems Cornerstone attributes of
  Protection Against External Factors (Flood Hazard) and Procedure Quality, and
  adversely affected the cornerstone objective to ensure the availability, reliability, and
  capability of systems that respond to initiating events to prevent undesirable
  consequences (i.e. core damage). Specifically, the licensees failure to procedurally
  control external flooding design features to ensure they would not adversely affect the
  strategy for other flooding events, could negatively impact mitigating systems ability to
  respond during external and internal flooding events. The inspectors evaluated the
  finding using IMC 0609, Attachment 0609.04, Tables 2 and 3, and Appendix A, and
  determined a detailed risk evaluation was required. Following a detailed risk evaluation,
  Region III SRAs determined that the finding had very low safety significance (Green).
  This finding has a cross-cutting aspect in the area of problem identification and
  resolution, because the licensee failed to take effective corrective actions to address
  issues in a timely manner commensurate with their safety significance. (P.3)
* Severity Level IV: The inspectors identified a finding of very low safety significance and
  associated Severity Level IV, non-citied violation of 10 CFR 50.59(d)(1), Changes, tests
  and experiments, when, on November 25, 2013, the licensee failed to perform an
  evaluation against the criteria in 10 CFR 50.59(c)(2) for a change to procedure
  PC 80 Part 7 to include actions to maintain functionality of drainage paths during
  probable maximum precipitation and turbine building flooding events. Specifically,
  PC 80 Part 7, Lake Water Level Determination was changed to include actions to open
  the CWPH rollup doors to provide an additional drainage path while wave barriers were
  in place, without fully evaluating the viability of reliance on additional flood features not
  credited for external flooding in the Current License Basis (CLB). Corrective actions for
  this issue included to updating the FSAR to describe the new flood paths, performing a
  10 CFR 50.59 screening and 10 CFR 50.59 evaluation for the new drainage path which
  had put the site outside of the CLB, revising a related functionality assessment,
  controlling external flooding areas to ensure they are clear of debris, and creating a
  procedure to install curtains on the CWPH rollup doors during periods when they were
  required to be open.
  The inspectors determined that the licensees failure to fully evaluate the viability of
  newly created flooding drainage paths as required by 10 CFR 50.59(d)(1) was a
  performance deficiency. The inspectors evaluated the performance deficiency using
  traditional enforcement in conjunction with the SDP because the performance deficiency
  had the potential to impact the regulatory process. The performance deficiency was
  screened per the guidance of lMC 0612, Appendix B, and determined to be more than
  minor because the finding was associated with the Mitigating Systems Cornerstone
  attributes of Protection Against External Factors (Flood Hazard) and Design Control, and
  adversely affected the cornerstone objective to ensure the availability, reliability, and
  capability of systems that respond to initiating events to prevent undesirable
  consequences (i.e. core damage). Specifically, the licensee did not fully demonstrate
  that the availability, reliability, and capability of mitigating systems would be maintained
  during flooding events due to the sites failure to evaluate the viability of alternate flood
  drainage paths through the CWPH. The inspectors evaluated the finding using
  IMC 0609, Attachment 0609.04, Tables 2 and 3, and Appendix A. Based on a review of
  Appendix A, Exhibit 2, Item 4.B, the inspectors determined that this issue screened as
                                              4


Enclosure: IR 05000266/2014007; 05000301/2014007   w/Attachment:  Supplemental Information cc w/encl:  Distribution via ListServ
   having very low safety significance (Green). Additionally, in accordance with
TM 
  Section 6.1.d.2 of the NRC Enforcement Policy, this violation is categorized as a
Enclosure U.S. NUCLEAR REGULATORY COMMISSION REGION III Docket Nos: 05000266; 05000301 License Nos: DPR-24; DPR-27 Report No: 05000266/2014007; 05000301/2014007 Licensee: NextEra Energy Point Beach, LLC Facility: Point Beach Nuclear Plant, Units 1 and 2 Location: Two Rivers, WI Dates: February 3, 2014, through March 6, 2014 Inspectors: B. Bartlett, Project Engineer  J. Beavers, Emergency Preparedness Inspector  R. Elliott, Acting Resident Inspector, Point Beach
  Severity Level IV because the resulting conditions were evaluated as having very low
J. Jandovitz, Project Engineer
  safety significance (Green) by the SDP. This finding has a cross-cutting aspect in the
K. Miller, Resident Inspector, Watts Bar
  area of problem identification and resolution, because the licensee failed to thoroughly
P. Voss, Resident Inspector, Monticello
  evaluate issues to ensure that resolutions address causes and extent of conditions
  commensurate with their safety significance. (P.2)
* Green. The inspectors identified a finding of very low safety significance (Green) and
  associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions,
  Procedures, and Drawings, for the failure to ensure the effectiveness review attributes
  for a significant condition adverse to quality would ensure the corrective actions would
  eliminate or reduce the recurrence rate.
  The inspectors determined that the licensees failure to establish effectiveness review
  criteria that would have identified whether the corrective action to prevent recurrence
  (CAPRs) had effectively resolved the conditions was a performance deficiency
  warranting further review. The inspectors determined that this finding was more than
  minor in accordance with IMC 0612, Appendix B, because it was affected the Mitigating
  Systems Cornerstone objective to ensure availability, reliability, and capability of
  systems that respond to initiating events to prevent undesirable consequences. If left
  uncorrected, would the performance deficiency have the potential to lead to a more
  significant safety concern? The inspectors evaluated the finding using IMC 0609,
  Appendix A. The inspectors determined the finding was of very low safety significance
  (Green) because the finding was not a deficiency affecting the design or qualification of
  a mitigating structure, system or component and did not result in a loss of operability or
  functionality. In addition, the finding did not represent a loss of system or function, did
  not represent an actual loss of function of a least a single train for longer than its
  technical specification allowed outage time, and did not represent an actual loss of
  function of one or more nontechnical specification trains of equipment designated as
  high safety-significance.
  The finding had a cross cutting aspect in the area of problem identification and
  resolution, specifically resolution, because licensee personnel failed to ensure the
  corrective actions to prevent recurrence had effective attributes. (P.2)
                                              5


  Approved by: J. Cameron, Chief
                                        REPORT DETAILS
Branch 4  
4.    OTHER ACTIVITIES
Division of Reactor Projects
      Cornerstone: Mitigating Systems
 
4OA4 Supplemental Inspection (95002)
2  SUMMARY OF FINDINGS Inspection Report (IR) 05000266/2014007, 05000301/2014007; 02/03/2014 - 03/06/2014;  Point Beach Nuclear Plant, Units 1 and 2; Supplemental Inspection - Inspection Procedure 
  a. Inspection Scope
(IP) 95002, Supplemental Inspection for One Degraded Cornerstone or any Three White Inputs  
      The NRC staff performed this follow-up supplemental inspection in accordance with
in a Strategic Performance Area. This inspection was conducted by three regional inspectors and three resident inspectors. The inspectors identified three NRC-identified findings  
      inspection procedure (IP) 95002, Inspection for One Degraded Cornerstone or Any
of very low safety significance (Green) that involved violations of NRC requirements. The NRC identified an additional Green finding that was associated with a Severity Level IV violation of NRC requirements evaluated through the  
      Three White Inputs in a Strategic Performance Area, to assess the White inspection
traditional enforcement process. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, "Significance
      finding for the failure of the Unit 1 Turbine Driven Auxiliary Feedwater Pump (TDAFWP)
Determination Process" (SDP). Assigned cross-cutting aspects were determined using  IMC 0310, "Components Within the Cross-Cutting Areas."  Findings for which the SDP does not apply may be Green or be assigned a severity level after NRC management review. The NRC's
      and the White inspection finding for external wave run-up flooding. In addition to these
program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Proce
      two White findings the licensee was requested to also include in their assessment the
ss," Revision 4, dated December 2006. Cornerstone:  Mitigating Systems
      White finding in the Emergency Preparedness (EP) Cornerstone that had been issued
The NRC staff performed this follow-up supplemental inspection in accordance with Inspection Procedure 95002, "Inspection for One Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area," to continue to assess the licensee's
      on July 24, 2012. A 95001, Supplemental Inspection for One or Two Inputs in a
evaluation of two White inspection findings that affected the Mitigating Systems Cornerstone.  
      Strategic Performance Area, had previously been performed for the White EP finding
      and the White TDAFWP finding.
      The objectives of the supplemental inspection included:
        *    To provide assurance that the root and contributing causes for the White findings
            are understood.
        *    To determine if the licensees corrective actions for risk-significant performance
            issues are sufficient to address the root and contributing causes and prevent
            recurrence.
        *    To independently assess the extent of condition and the extent of cause for
            individual and collective risk-significant performance issues.
        *    To assess the safety culture as a possible contributor.
      The inspectors reviewed the Root Cause Evaluations (RCE), in addition to other
      assessments, evaluations, and corrective action program documentation completed in
      support of and, as a result of, the RCEs. The inspectors reviewed corrective actions that
      were taken or planned to address the identified causes. The inspectors interviewed
      selected station, corporate, and contractor personnel, and held discussions with these
      individuals to verify that the root and contributing causes and the contribution of safety
      culture components were understood and that corrective actions taken or planned were
      appropriate to address the causes and preclude repetition.
      For clarity, documentation of each inspection requirement contains subsections for each
      of the two White mitigating systems findings. The White EP finding was assessed by the
      inspection team only as it related to commonalities to the other White findings and this is
      not individually discussed in this report.
      Documents reviewed during this inspection are listed in the Attachment.
                                                  6


      Inspection Results
The inspection team determined that the licensee performed an adequate evaluation of some of  
      The four attributes of IP 95002 were reviewed for each of the three White findings plus
the issues, but failed to perform an adequate evaluation of some issues. The inspection team determined that the root cause evaluation for the Turbine Driven Auxiliary Feedwater Pump (TDAFWP) appropriately evaluated the root and contributing causes, adequately addressed the  
      the common cause analysis performed by the licensee. Thus there were a total of 16
extent of condition and cause, assessed safety culture, and established corrective actions for  
      attributes that were reviewed. The inspectors concluded that for the White EP finding
the risk significant performance issues. However, the inspection team determined that for the  
      and the White TDAFWP finding that the licensee understood the root and contributing
flooding White finding that the licensee failed to appropriately evaluate the root and contributing causes, failed to adequately address the extent of condition and cause, failed to adequately assess safety culture, and failed to establish adequate corrective actions. In addition to
      causes. In addition, the inspectors performed the independent extent of condition and
assessing the licensee's evaluations, the inspection team independently performed an extent of condition and extent of cause review of the two findings and a review of the site safety culture
      extent of causes and assessed the licensees corrective actions for these two White
as it related to the root cause evaluations. The team concluded that the licensee's root cause
      findings and concluded that the licensees actions were sufficient. Finally, the inspectors
evaluations and corrective actions, both completed and planned, were sufficient to address the causes and prevent recurrence for the TDAFWP White finding but had significant weaknesses resulting in failure for the flooding White finding. The licensee's implementation of corrective
      determined that the safety culture aspects for these two White findings were adequate
actions for the TDAFWP will be reviewed during future inspections.  
      although there were safety culture components that contributed to the common cause
      analysis conclusions and that corrective actions had been taken to address these
      conclusions. Thus of the total of 16 attributes, eight were closed. The inspectors
      determined that the root causes, extent of condition, extent of cause, corrective actions
      and safety culture aspects for the White flooding finding and the common cause analysis
      (CCA) were not sufficient and remain open.
.02  Evaluation of the Inspection Requirements
02.01 Problem Identification
  a. Determine that the Evaluation Documented Who Identified the Issue (i.e., Licensee-
      Identified, Self-Revealing, or NRC-Identified) and Under What Conditions the Issue was
      Identified
      The inspectors determined that neither of the RCEs for the two White findings nor the
      CCA specifically addressed who identified the issues. The RCE for the TDAFWP White
      finding had enough information to infer that the finding was self-revealed but the RCE for
      the flooding White finding contained only a minimal inference that a NRC finding had
      been issued. The CCA had remarks similar to the flooding RCE that stated that NRC
      had issued White findings but again the inspectors had to infer how the findings were
      identified. There were no statements in any licensee documentation or as a result of
      interviews with licensee management indicating the licensee disagreed with the findings.
      The licensee clearly stated the conditions under which the issues were identified. The
      inspectors considered the failure to clearly state who identified the issue to be a
      weakness for the TDAFWP White finding but not significant enough to leave this item
      open. For the TDAFWP White finding, this aspect of IP 95002 is closed. The inspectors
      concluded that the licensee failed to clearly document who identified the issue for the
      White flooding finding and the CCA and this aspect of IP 95002 was not met.
  b. Determine that the Evaluation Documented How Long the Issues Existed and Prior
      Opportunities for Identification
      The licensees evaluation for the TDAFWP White finding documented that pump to
      turbine alignment issues had existed for many years and that each time the pump was
      determined to be out of alignment it had been restored to within allowable limits. The
      inspectors determined that the licensees evaluation was adequate with respect to
      identifying how long the issue existed and prior opportunities for identification.
                                                7


    
   The licensees evaluation for the flooding White finding documented that the change to
3  A. NRC-Identified and Self-Revealed Findings
  the methodology of protecting the site from external lake flooding had been done in
  * Green. The inspectors identified a finding of very low safety significance and associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Actions," in that from March 13, 2013 until February 14, 2014, the licensee failed to assure that for a significant condition adverse to quality (SQAC), the cause of the condition was determined and corrective actions were taken to preclude repetition. Specifically, the  
  January of 1996. The licensees evaluation also documented some prior missed
licensee's corrective actions failed to preclude repetition of an SQAC where Procedure
  opportunities to identify; however, the evaluation failed to address other significant prior
PC 80 Part 7, "Lake Water Level Determination," as implemented, would not protect
  opportunities. As discussed further in various sections of the report, the inspectors
safety-related equipment in the turbine building or Circulating Water Pump House
  observed that licensee personnel implemented corrective actions that significantly
(CWPH). After the licensee had taken corrective actions to improve the wave barrier procedure in response to an NRC-identified NOV, PC 80 Part 7 and other flood protection implementing procedures specified inadequate timelines to ensure wave 
  impacted other license basis events but failed to recognize these impacts. Thus, there
run-up flood barriers would be installed prior to the lake level at which wave run-up could
  were additional opportunities to identify which were not listed or discussed in the
impact the site. Corrective actions for this issue included changing the affected
  licensees RCE. The inspectors determined that the licensees evaluation was not
procedures to install the wave barriers at a lower lake level, changing the lake level determination surveillance from monthly to weekly, and reducing the allowed installation time for the barriers from 3 weeks to 1 week.  
  adequate with respect to identifying how long the issue existed and prior opportunities
  for identification. This aspect of IP 95002 remains open for the flooding White finding.
c. Determine that the Evaluation Documented the Plant Specific Risk Consequences, As
  Applicable, and Compliance Concerns with the Issues Both Individually and Collectively
  The risk evaluation performed by the licensee in discussions with the NRC Senior
  Reactor Analyst (SRA) prior to issuance of the TDAFWP White finding was not the one
  utilized by the licensee for the subsequent RCE. The licensees RCE, stated, in part, In
  order to quickly evaluate the safety significance of this issue, the Safety Monitor program
  was used by the probabilistic risk assessment (PRA) group. The NRC team did not
  understand the need to quickly perform a risk assessment since one had previously
  been performed and discussed with an NRC SRA. Nevertheless, the licensee chose to
  perform one, but selected a program that did not align with standard NRC significance
  determination techniques. The licensees Safety Monitor program is used to monitor on
  line risk in a moment to moment manner and use of the program to calculate the risk
  consequence for the TDAFWP failure was neither accurate nor appropriate. The team
  discussed the licensees risk significance with the NRC SRA who performed the original
  assessment and the SRA verified that the licensee had understood and agreed with the
  original NRC conclusions. The purpose of this reassessment and write-up was not
  understood either by the SRA nor the team. The inspectors also determined that the
  licensee had issued a Licensee Event Report for the failure of the TDAFWP and
  appropriately entered the failure in the Maintenance Rule database and the Performance
  Indicators. Based upon the licensees previous demonstrated knowledge and
  understanding of the risk significance of this item, the inspectors concluded that the risk
  and compliance portion was weak, but that this fundamental aspect of IP95002 had
  been met.
  The risk evaluation performed by the licensee for the flooding White finding enforcement
  conference was not accepted by the NRC although portions of the licensees
  assessment was recognized as acceptable and used to ensure the NRC position was
  accurate. Nevertheless, the licensee chose to repeat the previously determined
  unsatisfactory risk assessment in the flooding White RCE. In the NRC Final Significance
  Determination of a White Finding, dated August 9, 2013, Enclosure 2 provided an
  analysis of the licensee risk information. In this analysis the NRC disagreed with the
  licensees risk assessment in a number of significant ways, yet these disagreements
  appeared to not be factored into the licensees subsequent risk assessment documented
  in the associated RCE. The inspectors review of the flooding RCE determined that the
  licensee did not address possible compliance concerns or reportability.
                                            8


   
      During interviews, individuals directly involved in responding to the finding cited internal
The performance deficiency was screened against the Reactor Oversight Process per
      supplemental calculations, and stated that they believed there would not have been any
      consequences to the plant as a result of the finding. Interviewees stated that the
      findings risk significance came only from significant conservatisms used in the individual
      plant examination external events (IPEEE) evaluation, and not from potential plant
      consequences. Interviews with individuals not directly involved in addressing the
      flooding finding revealed that working level plant personnel were familiar with the
      flooding finding, but their awareness was focused more on the regulatory impacts, with
      minimal awareness of potential equipment impacts.
      The inspectors concluded that the licensee failed to adequately address the plant
      specific risk consequences or compliance concerns related to the flooding White finding
      and this aspect of IP 95002 was not met.
  d. Findings
      No findings were identified.
02.02 Root Cause
  a. Determine that the Problem was Evaluated Using a Systematic Methodology to Identify
      the Root and Contributing Causes
      The inspectors reviewed the licensees RCEs, CCA, and other documents related to the
      White findings. The licensee identified a total of four root causes and seven contributing
      causes using a systematic methodology. In addition, the licensees CCA identified two
      common causes and two contributing causes. The licensee utilized support-refute
      matrix, change analysis, barrier analysis, a cause and effects diagram, an event and
      causal factor chart, and a why staircase during the two root cause assessments and
      the CCA. The inspectors determined that the RCE and CCA were conducted to a level
      of detail commensurate with the significance of the issues. The licensees evaluations
      included details of each item along with supporting data and other information.
      The licensees use of systematic methodology to identify the root and contributing
      causes was determined to be adequate for the TDAFWP White finding. Due to the
      significant weaknesses identified in the licensees corrective actions, extent of condition,
      extent of cause, and root cause, the team concluded that this aspect for the flooding
      White finding was negatively impacted. This aspect of IP 95002 will remain open for the
      flooding White finding.
  b.  Determine that the Root Cause Evaluation was Conducted to a Level of Detail
      Commensurate with the Significance of the Problem
      The licensee utilized the systematic methodologies for the CCA discussed above and
      determined that the primary root causes were:
      *      Less than adequate understanding of the design and licensing basis;
      *      Corrective Action Program items with incorrect priorities;
      *      Original construction stress riser introduced to the TDAFWP;
                                                9


the guidance of lMC 0612, Appendix B, and determined to be more than minor because the finding was associated with the Mitigating Systems Cornerstone attributes of Protection Against External Factors (Flood Hazard) and Procedure Quality, and
  *      Emergency Preparedness group did not perform reviews of federal guidance;
adversely affected the cornerstone objective to ensure the availability, reliability, and  
  *      A lack of or inadequate leadership; and
capability of systems that respond to initiating events to prevent undesirable
  *      Poor technical procedure quality.
consequences (i.e. core damage). Specifically, the licensee's failure to correct
  The inspectors noted that while the licensee had poor procedure quality as a root cause
procedural deficiencies associated with flood barrier construction timelines, could challenge the timely installation of the barriers, which could impact the ability of mitigating systems to respond during an external flooding event. The inspectors  
  for the TDAFWP issue, the knowledge, skills, and abilities (KSA) of the workers was not
evaluated the finding using IMC 0609, Attachment 0609.04, Tables 2 and 3, and  
  considered as a possible root cause. For example, the TDAFWP alignment procedure
Appendix A.  Based on a review of Appendix A, Exhibit 2, Item 4.B, the inspectors
  did not require the taking of as-found data nor did the procedure require that if the data
determined that this issue screened as having very low safety significance (Green).  This finding has a cross-cutting aspect in the area of problem identification and resolution, because the licensee failed to thoroughly evaluate issues to ensure that
  was taken that it be reviewed by engineering personnel. Yet, a qualified maintenance
resolutions address causes and extent of conditions commensurate with their safety
  mechanic would have experience with the need to take such data and would know to
significance. (P.2)
  pass it along to their supervisor. The inspectors performed a search of the licensees
  CAP database to see if a trend of issues with a cause of KSA existed and did not identify
  any trends. The licensees RCEs should have discussed this aspect in sufficient detail
  so as to demonstrate that this was not a root cause.
  Despite the weakness noted above, the inspectors determined that the RCE for the
  TDAFWP White finding was conducted to a level of detail commensurate with the
  significance of the issues.
  For the flooding White finding and the CCA root cause the inspectors observed that
  problems with the quality of condition report evaluations and with Functionality
  Assessments (FA) were identified but not included as either a root cause or a
  contributing cause. The inspectors also noted that an assessment of the licensees CCA
  performed prior to the team arriving on site (Quick Hit PBSA-PBNP-13-03) had a similar
  observation and a recommendation to clearly articulate this theme. The inspectors
  determined that neither a root cause nor a contributing cause was assigned to either
  corrective action program quality or CR evaluations. One CAPR was assigned to
  improve the quality of FAs. This is discussed in more detail in Section 02.04, below.
  While corrective action program evaluation quality was a part of the issues identified, the
  failure of the licensee to either include it as a root cause or to justify why it was not a root
  cause was a significant weakness.
  The inspectors determined that this aspect of the IP 95002 criteria was not met for the
  flooding White finding and the CCA.
c. Determine that the Root Cause Evaluation Included a Consideration of Prior
  Occurrences of the Problem and Knowledge of Prior Operating Experience
  The inspectors determined that the licensees evaluation included a consideration of
  prior occurrences of the issues and industry operating experience. The RCE for the
  TDAFWP determined that a prior opportunity was missed in early 2011 during the Unit 2
  refueling outage when pipe stresses were identified on the opposite unit TDAFWP. The
  licensee determined that even though the pipe stresses were identified and corrected
  that a CR was not issued and thus the opportunity to apply this information to the next
  Unit 1 refueling outage and TDAFWP maintenance activity was missed.
  The inspectors concluded that the root cause evaluation included a review of prior and
  precursor problems and properly evaluated internal and industry operating experience.
  This aspect of the IP 95002 criteria was met for the TDAFWP finding.
                                              10


* Green.  The inspectors identified a finding of very low safety significance and associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," in that from January 19, 1996 until November 25, 2013, the licensee failed to ensure that activities affecting quality were prescribed by documented procedures of a type appropriate to the circumstances to address external flooding as
  The RCE for the White flooding finding determined that prior opportunities were missed
described in the Final Safety Analysis Report (FSAR).  Specifically, PC 80 Part 7, "Lake Water Level Determination" directed advanced installation of concrete barriers to protect
  to properly correct the deficiency. This included opportunities in 2004, when condition
against deep wave action from the lake, which introduced significant unrecognized blockages in the natural drainage path credited in the FSAR to protect against the probable maximum precipitation and Turbine Building internal flooding events.
  reports were generated questioning the adequacy of the wave run-up barriers, given the
Corrective actions for this issue included changing the procedure and FSAR to include
  1996 procedure change. This also included opportunities in 2012 where a functionality
actions to provide an additional flood relief path through the CWPH building and reliance
  assessment inappropriately contained conclusions regarding the functionality of the
on internal flood relief dampers for the affected flooding events.
  wave barriers on perceived risk. The inspectors noted that these opportunities were
4  The performance deficiency was screened against the Reactor Oversight Process per
  factored into the determination of one of the root causes. The inspectors also noted the
the guidance of lMC 0612, Appendix B, and determined to be more than minor because
  RCE discussion on industry OE and noted several instances where the causes of
the finding was associated with the Mitigating Systems Cornerstone attributes of Protection Against External Factors (Flood Hazard) and Procedure Quality, and adversely affected the cornerstone objective to ensure the availability, reliability, and  
  industry deficiencies were similar to the causal factors identified for the White flooding
capability of systems that respond to initiating events to prevent undesirable
  issue
consequences (i.e. core damage).  Specifically, the licensee's failure to procedurally
  As discussed later in this inspection report unintended consequences were introduced
control external flooding design features to ensure they would not adversely affect the  
  during the corrective actions to the White flooding finding. The failure to recognize these
strategy for other flooding events, could negatively impact mitigating systems' ability to respond during external and internal floodi
  consequences represented additional occurrences of the problem. The inspectors
ng events. The inspectors evaluated the finding using IMC 0609, Attachment 0609.04, Tables 2 and 3, and Appendix A, and  
  determined that this aspect of the IP 95002 criteria was not met for the flooding White
determined a detailed risk evaluation was required.  Following a detailed risk evaluation, Region III SRAs determined that the finding had very low safety significance (Green). 
  finding and the CCA.
This finding has a cross-cutting aspect in the area of problem identification and resolution, because the licensee failed to take effective corrective actions to address issues in a timely manner commensurate with their safety significance. (P.3)
d. Determine that the Root Cause Evaluation Addresses the Extent of Condition and the
  Extent of Cause of the Problem
  The licensees RCE included an evaluation of the extent of condition and extent of cause
  of the issues. The inspectors determined that the RCE for the TDAFWP issue was
  adequate with comments. These comments are discussed in section 02.04 of this
  report. The inspectors also noted that during an assessment of the licensees RCE that
  was performed prior to the team arriving on site (Quick Hit PBSA-PBNP-13-03) that
  deficiencies with the TDAFWP had been identified. For example, the extent of condition
  prior to the Quick Hit was limited to rotating couplings of the same make and model as
  that which had failed on the Unit 1 TDAFWP. Following a recommendation of the Quick
  Hit team, the licensee had expanded the extent of condition to include other make and
  model couplings as well as all rotating connections. Based on a review of the RCE and
  CCA and discussions with licensee management and staff personnel, the inspectors
  concluded that the evaluations for the TDAFWP White finding adequately addressed the
  extent of condition and the extent of cause. This aspect of the IP 95002 was not for the
  TDAFWP finding.
  The inspectors determined that the RCE for the flooding White finding also included an
  evaluation of the extent of condition and extent of cause but based on the NRC findings
  documented in Section 02.04 of this report the inspectors concluded that this item was
  not acceptable. For example, the RCE did not consider possible bypass paths around
  the external flooding barrier. During field walk downs, the inspectors identified two
  different drain pipes in the concrete near the CWPH which directly communicated with
  the lake shore and should have been evaluated as possible bypass paths. The
  inspectors concluded that the evaluations for the flooding White finding did not satisfy
  this aspect of the IP 95002 criteria.
e. Findings
  No findings were identified.
                                            11


  * Severity Level IV:  The inspectors identified a finding of very low safety significance and associated Severity Level IV, non-citied violation of 10 CFR 50.59(d)(1), "Changes, tests and experiments," when, on November 25, 2013, the licensee failed to perform an evaluation against the criteria in 10 CFR 50.59(c)(2) for a change to procedure 
02.03 Corrective Actions
PC 80 Part 7 to include actions to maintain functionality of drainage paths during  
  a. Determine that Appropriate Corrective Actions are Specified for Each Root and
probable maximum precipitation and turbine building flooding events. Specifically,
      Contributing Cause or that the Licensee has an Adequate Evaluation for Why No
PC 80 Part 7, "Lake Water Level Determination" was changed to include actions to open
      Corrective Actions are Necessary
the CWPH rollup doors to provide an additional drainage path while wave barriers were in place, without fully evaluating the viability of reliance on additional flood features not credited for external flooding in the Current License Basis (CLB). Corrective actions for
      The inspectors assessed the corrective actions for the RCEs and the CCA. The
this issue included to updating the FSAR to describe the new flood paths, performing a
      inspectors verified that all root causes had associated CAPRs and that all contributing
10 CFR 50.59 screening and 10 CFR 50.59 evaluation for the new drainage path which
      causes had associated corrective actions. The inspectors then performed a more
had put the site outside of the CLB, revising a related functionality assessment, controlling external flooding areas to ensure they are clear of debris, and creating a procedure to install curtains on the CWPH rollup doors during periods when they were
      detailed assessment of selected CAPRs and corrective actions. The detailed
required to be open.  
      assessment included a sample of corrective action program documents, field walk
      downs, interviews with selected licensee individuals, and reviews of the design and
      licensing basis.
      The inspectors concluded that the corrective actions for the TDAFWP finding were
      vague and needed additional clarification. As previously noted, the scope of the root
      cause was narrowly focused but this had previously been identified by an internal
      licensee review. As a result, the scope of the corrective actions had been expanded to
      include other rotating equipment connections. Additional corrective actions were
      reviewed by the inspectors with no further substantive observations. The inspectors
      concluded that the CAPRs and corrective actions for the TDAFWP met the requirements
      of IP 95002.
      During the reviews of the corrective action program documents, the inspectors noted
      that the licensee questioned whether the installation of the flood protection barriers had
      introduced unintended consequences. Specifically, the corrective action to install a
      more robust wave barrier in lieu of sandbagging efforts failed to restore compliance with
      the CLB. While the improved wave barriers provided necessary protection against wave
      action, they introduced unrecognized hazards during the probable maximum
      precipitation and turbine building internal flooding events. These barriers blocked
      natural drainage paths credited for flood relief and rendered these paths nonfunctional
      as a result of wave barrier installation. The inspectors noted that this issue was not
      recognized by the licensee until November 2013 for one of the flooding events, and
      January 2014 for the other event, and thus, the licensees interim corrective actions for
      the flooding finding were deficient between March and November 2013 due to procedure
      call-up PC 80 Part 7, which remained inadequate during this time. As a result, the
      licensee was required to add compensatory actions during wave barrier installation to
      provide additional flow paths by opening the CWPH roll-up doors.
      When developing the compensatory action to address the deficiency associated with the
      new wave barriers, the licensee failed to recognize that the new compensatory
      measures required actions outside of the CLB. Specifically, Section 2.5 Hydrology in
      the FSAR for the Maximum precipitation flood states, in part, that the topography of
      the site results in adequate natural drainage to remove this amount of water and limit
      ponding depth to prevent adversely affecting safety related equipment. The
      nonfunctional drainage paths following wave barrier installation resulted in the licensee
      having to identify an alternate path for flood water drainage flow. As a compensatory
      action, the licensee chose to open the CWPH roll-up doors, route flood waters through
      the CWPH, and relying on internal flood relief dampers to open and drain the water. The
      licensee viewed those compensatory actions as still with its CLB. As a result, the
                                                12


  inspectors determined that the licensee failed to properly screen the actions as
The inspectors determined that the licensee's failure to fully evaluate the viability of  
  compensatory measures under the requirements of 10 CFR 50.59.
newly created flooding drainage paths as required by 10 CFR 50.59(d)(1) was a performance deficiency. The inspectors evaluated the performance deficiency using traditional enforcement in conjunction with the SDP because the performance deficiency
  The inspectors noted that as a result of the failure to evaluate these actions under
had the potential to impact the regulatory process.  The performance deficiency was
  10 CFR 50.59, the licensee did not properly consider several factors associated with the
screened per the guidance of lMC 0612, Appendix B, and determined to be more than
  compensatory actions that should have been evaluated. Some of these factors included
minor because the finding was associated with the Mitigating Systems Cornerstone attributes of Protection Against External Factors (Flood Hazard) and Design Control, and adversely affected the cornerstone objective to ensure the availability, reliability, and
  flood water flow rates through the open doors, the impact of debris and slush from
capability of systems that respond to initiating events to prevent undesirable
  outside being carried into the CWPH and clogging the flood relief dampers, the impact of
consequences (i.e. core damage). Specifically, the licensee did not fully demonstrate that the availability, reliability, and capability of mitigating systems would be maintained during flooding events due to the site's failure to evaluate the viability of alternate flood drainage paths through the CWPH. The inspectors evaluated the finding using 
  the cold temperatures on the equipment in the rooms during the potentially extended
IMC 0609, Attachment 0609.04, Tables 2 and 3, and Appendix A. Based on a review of
  periods of time during which the doors could be open, and security impacts.
Appendix A, Exhibit 2, Item 4.B, the inspectors determined that this issue screened as 
  In addition, the inspectors noted the licensee failed to recognize that procedure
5  having very low safety significance (Green). Additionally, in accordance with  Section 6.1.d.2 of the NRC Enforcement Policy, this violation is categorized as a
  PC 80 Part 7, failed to account for the time necessary to ensure that the barriers would
Severity Level IV because the resulting conditions were evaluated as having very low
  be constructed before the lake reached conditions where deep wave action could impact
safety significance (Green) by the SDP. This finding has a cross-cutting aspect in the area of problem identification and resolution, because the licensee failed to thoroughly
  the site. Specifically, the licensees calculation specified that 8.2 weeks would be
evaluate issues to ensure that resolutions address causes and extent of conditions
  available after Procedure PC 80 Part 7, initiated actions to install the wave barriers
commensurate with their safety significance. (P.2)
  based on lake level.
  The inspectors reviewed EC 279455, Time Available to Respond to Threat From Rising
  Water, and the licensees lake level determination monthly surveillance, PBF-2124,
  PPCS Forebay and Pump Bay Level Alarm Setpoints, and identified several
  deficiencies. These deficiencies included non-conservative assumptions when using the
  maximum monthly rate of lake level rise, non-conservative assumptions for the lake level
  at which the site could be impacted by the waves, a non-conservative allowance to rely
  on the previous months data if no lake level data was immediately available, and an
  error in an assumption that wave barriers would be installed earlier than PC 80 Part 7,
  actually required. When the licensee corrected these inputs, the inspectors noted that
  the time available for action was significantly reduced to less than three weeks.
  The inspectors observed that PC 80 Part 7, granted three weeks allowance for activities
  to be scheduled and performed to install the wave barriers. The inspectors concluded
  that the deficiencies in the licensees timelines left them vulnerable in that actions may
  not have been initiated soon enough to protect the site from the wave run-up design
  basis event. The inspectors determined that this aspect of IP 95002 was not met for the
  flooding White finding.
b. Determine that the Corrective Actions Have Been Prioritized with Consideration of Risk-
  Significance and Regulatory Compliance
  The inspectors assessed the licensees timeliness of corrective actions for the RCEs and
  CCA associated with the risk significant issues. The inspectors noted that there were no
  formal tracking mechanisms or documentation for several of the corrective actions that
  had been previously taken prior to the completion of the RCEs and CCA. Formalized
  tracking measures would assure the actions are satisfactorily completed and allow for
  documentation of the basis for closure.
  The inspectors concluded that an appropriate schedule had been established for
  implementing and completing the corrective actions for the TDAFWP White finding. This
  aspect for the flooding White finding will remain open pending the inspectors review of
  the additional corrective actions the licensee will need to perform.
                                              13


* GreenThe inspectors identified a finding of very low safety significance (Green) and associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," for the failure to ensure the effectiveness review attributes
cDetermine that a Schedule has been Established for Implementing and Completing the
for a significant condition adverse to quality would ensure the corrective actions would
    Corrective Actions
eliminate or reduce the recurrence rate. The inspectors determined that the licensee's failure to establish effectiveness review criteria that would have identified whether the corrective action to prevent recurrence (CAPRs) had effectively resolved the conditions was a performance deficiency
    As discussed in Section 02.03.b, above, the inspectors determined that the licensee had
warranting further review. The inspectors determined that this finding was more than
    established an appropriate schedule for implementing the corrective actions for the
minor in accordance with IMC 0612, Appendix B, because it was affected the Mitigating Systems Cornerstone objective to ensure availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences.  If left
    TDAFWP White finding. The aspect for the flooding White finding will remain open
uncorrected, would the performance deficiency have the potential to lead to a more
    pending the inspectors review of the additional corrective actions that the licensee will
significant safety concern?  The inspectors evaluated the finding using IMC 0609,
    need to perform.
Appendix A. The inspectors determined the finding was of very low safety significance (Green) because the finding was not a deficiency affecting the design or qualification of a mitigating structure, system or component and did not result in a loss of operability or
d.  Determine that Quantitative or Qualitative Measures of Success Have Been Developed
functionality.  In addition, the finding did not represent a loss of system or function, did  
    for Determining the Effectiveness of the Corrective Actions to Prevent Recurrence
not represent an actual loss of function of a least a single train for longer than its
    The inspectors review of the effectiveness review (EFR) plan identified a number of
technical specification allowed outage time, and did not represent an actual loss of function of one or more nontechnical specification trains of equipment designated as high safety-significance. The finding had a cross cutting aspect in the area of problem identification and resolution, specifically resolution, because licensee personnel failed to ensure the corrective actions to prevent recurrence had effective attributes.  (P.2) 
    weaknesses. The inspectors determined that these weaknesses rose to the level of a
6  REPORT DETAILS
    finding and that the weaknesses were broad and deep enough to conclude that this
4. OTHER ACTIVITIES Cornerstone:  Mitigating Systems 4OA4 Supplemental Inspection (95002) a. Inspection Scope
    section did not meet the requirements of IP 95002. As the TDAFWP finding occurred
  The NRC staff performed this follow-up supplemental inspection in accordance with inspection procedure (IP) 95002, "Inspection for One Degraded Cornerstone or Any
    first and there had been additional time the EFR had already been substantially
Three White Inputs in a Strategic Performance Area," to assess the White inspection
    performed for this issue. The interim assessments, combined with the general quality of
finding for the failure of the Unit 1 Turbine Driven Auxiliary Feedwater Pump (TDAFWP)
    the RCE led the inspectors to conclude that this section is complete for the TDAFWP
and the White inspection finding for external wave run-up flooding. In addition to these two White findings the licensee was requested to also include in their assessment the White finding in the Emergency Preparedness (EP) Cornerstone that had been issued
    finding but remains open for the flooding White finding and the CCA.
e.  Determine that the Corrective Actions Planned or Taken Adequately Address a Notice of
    Violation that was the Basis for the Supplemental Inspection, if Applicable
    For the TDAFWP White finding, the licensee did not respond to the initial NOV because
    the corrective actions taken and planned to be taken to correct the violation, and the
    date when full compliance was achieved was already addressed on the docket in NRC
    Inspection Report 05000266/2012009. As part of the 95002 inspection, the team
    members performed a sampling of the immediate corrective actions and determined the
    full compliance had been restored. The team considered that the IP 95002 requirements
    were met for the TDAFWP White finding.
    For the flooding White finding, the licensee did not respond to the initial NOV because
    the corrective actions taken and planned to be taken to correct the violation, and the
    date when full compliance was achieved was already addressed on the docket in
    NRC Inspection Report 05000266/2013002 and 05000301/2013002 and in the
    licensees submittals dated July 10, 15, and 29, 2013. As part of the 95002 inspection,
    the team members performed a sampling of the immediate corrective actions and
    determined the full compliance had been restored. However, as stated above, the
    inspectors noted that the corrective actions resulted in unintended consequences. In
    addition, as noted previously, the inspectors identified a deficiency where insufficient
    corrective action was taken to correct PC 80 Part 7, in order to preclude repetition of the
    original significant condition adverse to quality. Thus the team concluded that the
    requirements of IP 95002 were not met for the flooding White finding.
f.  Findings
(1) Failure to Take Corrective Actions to Address External Flooding Procedure Deficiencies
    Introduction: The inspectors identified a finding of very low safety significance and an
    associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective
                                              14


on July 24, 2012.  A 95001, Supplemental Inspection for One or Two Inputs in a  
Actions, in that from March 13, 2013 until February 14, 2014, the licensee failed to
Strategic Performance Area," had previously been performed for the White EP finding and the White TDAFWP finding.  The objectives of the supplemental inspection included:
assure that for a significant condition adverse to quality (SCAQ), the cause of the
* To pro vide assurance that the root and contributing causes for the White findings are understood.
condition was determined and corrective actions were taken to preclude repetition.
* To determine if the licensee's corrective actions for risk-significant performance issues are sufficient to address the root and contributing causes and prevent recurrence.  
Specifically, the licensees corrective actions failed to preclude repetition of an SCAQ
* To independently assess the extent of condition and the extent of cause for individual and collective risk-significant performance issues.  
where Procedure PC 80 Part 7, Lake Water Level Determination, as implemented,
* To assess the safety culture as a possible contributor.  
would not protect safety-related equipment in the turbine building or CWPH. After the
The inspectors reviewed the Root Cause Evaluations (RCE), in addition to other assessments, evaluations, and corrective action program documentation completed in
licensee had taken corrective actions to improve the wave barrier procedure in response
support of and, as a result of, the RCEs. The inspectors reviewed corrective actions that  
to an NRC-identified NOV, PC 80 Part 7, and other flood protection implementing
were taken or planned to address the identified causes. The inspectors interviewed selected station, corporate, and contractor personnel, and held discussions with these individuals to verify that the root and contributing causes and the contribution of safety
procedures specified inadequate timelines to ensure wave run-up flood barriers would
culture components were understood and that corrective actions taken or planned were
be installed prior to the lake level at which wave run-up could impact the site.
appropriate to address the causes and preclude repetition.  
Description: The inspectors reviewed procedures associated with flooding as part of
their independent extent of condition and extent of cause, and review of corrective
actions to prevent recurrence. The inspectors noted the licensee failed to recognize that
procedure, PC 80 Part 7, did not grant adequate timelines to ensure that the barriers
would be constructed before the lake reached conditions where deep wave action could
impact the site. Specifically, the licensees calculation specified that 8.2 weeks would be
available after Procedure PC 80 Part 7, initiated actions to install the wave barriers
based on lake level. The inspectors observed that based on these timelines,
PC 80 Part 7 granted three weeks allowance for activities to be scheduled and
performed to install the wave barriers. Specifically, PC 80 Part 7, stated, in part,
IF corrected mean level is greater than or equal to +0.5 ft., THEN PERFORM the
following: NOTIFY maintenance to generate on demand PM (PMRQ 00059608-02) to
INSTALL barriers and sandbags as required to be completed within three weeks.
The inspectors reviewed EC 279455, Time Available to Respond to Threat From Rising
Water, and the licensees lake level determination monthly surveillance, PBF-2124,
PPCS Forebay and Pump Bay Level Alarm Setpoints, and found several deficiencies.
These deficiencies included non-conservative assumptions when using the maximum
monthly rate of lake level rise, non-conservative assumptions for the lake level at which
the site could be impacted by the waves, non-conservative allowances to rely on the
previous months data if no lake level data was immediately available, and an error in an
assumption that wave barriers would be installed earlier than PC 80 Part 7 actually
dictated. Inspectors noted that the procedure had no barriers to prevent the previous
months data from being used during multiple subsequent months. When the licensee
corrected these inputs, the inspectors noted that the time available to fully implement the
provisions of PC 80 Part 7 significantly reduced to less than the three weeks called for in
the procedure.
The inspectors concluded that these deficiencies in the licensees timelines left them
vulnerable in that actions may not be initiated soon enough to protect the site from the
wave run-up design basis event. The inspectors noted that these deficiencies
represented a failure of the licensees corrective action to preclude repetition of an
SQAC where Procedure PC 80 Part 7, Lake Water Level Determination, as
implemented, would not protect safety-related equipment in the turbine building or
CWPH.
In addition, to the PC 80 Part 7 issues associated with the timelines for barrier
installation, the inspectors found additional procedural deficiencies that should have
been identified and corrected as part of the corrective actions taken to address the
flooding NOV. PC 80 Part 7 procedural deficiencies included error traps where steps
                                          15


could be performed out of sequence (i.e. barriers installed before CWPH doors open),
For clarity, documentation of each inspection requirement contains subsections for each of the two White mitigating systems findings. The White EP finding was assessed by the inspection team only as it related to commonalities to the other White findings and this is not individually discussed in this report. Documents reviewed during this inspection are listed in the Attachment.
and a failure to include CWPH doors in robust tag-out process to ensure their open
7  Inspection Results
position was controlled. PBF-2124 procedural inadequacies included direction to install
  The four attributes of IP 95002 were reviewed for each of the three White findings plus the common cause analysis performed by the licensee. Thus there were a total of 16 attributes that were reviewed. The inspectors concluded that for the White EP finding  
jersey barriers rather than the more robust barriers associated with the licensees RCE
and the White TDAFWP finding that the licensee understood the root and contributing
corrective actions. Inspectors noted that this reference to the jersey barriers referred to
causes.  In addition, the inspectors performed the independent extent of condition and
the previous wave run-up flooding response strategy. The inspectors identified that the
extent of causes and assessed the licensee's corrective actions for these two White findings and concluded that the licensee's actions were sufficient.  Finally, the inspectors determined that the safety culture aspects for these two White findings were adequate although there were safety culture components that contributed to the common cause
same +0.5ft. installation threshold error was made in PBF-2124, as well as the licensees
analysis conclusions and that corrective actions had been taken to address these
external flooding abnormal procedure, AOP 13C.
conclusions.  Thus of the total of 16 attributes, eight were closed. The inspectors  
Licensee procedure PI-AA-204, Condition Identification and Screening Process,
determined that the root causes, extent of condition, extent of cause, corrective actions and safety culture aspects for the White flooding finding and the common cause analysis (CCA) were not sufficient and remain open.
Section 2.45 defines a Significant Condition Adverse to Quality (SCAQ) as, Failures,
malfunctions, deficiencies, deviations, defective items, abnormal occurrences, non-
conformances, or out-of control processes that significantly threatens or has
compromised nuclear safety or radiological safety, as well as any significant reportable
industrial safety or environmental (e.g., OSHA, State, etc.) issues. SCAQ issues require
corrective actions to prevent recurrence. Condition Report 01883633 identified the
White flooding finding and associated performance deficiency as an SQAC.
The inspectors also noted that the licensee completed an interim action to improve the
wave barrier and associated procedure on March 13, 2013, and a final corrective action
CAPR 01883633-22 on November 30, 2013 to implement a plant modification to
strengthen the physical external flood protection measures associated with a high lake
level wave run-up and associated procedure guidance and design documentation. The
inspectors observed that this action was credited in the licensees RCE as an action to
prevent recurrence of the original SQAC. As a result, the inspectors determined that the
licensee failed to take corrective actions to preclude repetition of an SCAQ where
Procedure PC 80 Part 7, as implemented, would not protect safety-related equipment in
the turbine building or CWPH.
Analysis: The inspectors determined that the licensees failure to take corrective actions
to address the inadequate flooding procedure was a performance deficiency, because it
was the result of the failure to meet the requirements of 10 CFR Part 50, Appendix B,
Criterion XVI; the cause was reasonably within the licensees ability to foresee and
correct; and it should have been prevented. The inspectors determined that the finding
had a cross-cutting aspect in the area of problem identification and resolution, because
the licensee failed to thoroughly evaluate issues to ensure that resolutions address
causes and extents of condition commensurate with their safety significance (P.2).
Specifically, the licensee failed to fully evaluate issues with the flooding procedure to
ensure the corrective actions they took would assure that robust protection from wave
run-up would be installed prior to reaching a lake level where deep wave action could
present a threat to the site.
The inspectors screened the performance deficiency in accordance with IMC 0612,
Power Reactor Inspection Reports, Appendix B, and determined that the issue was
more than minor because the finding was associated with the Mitigating Systems
Cornerstone attributes of Protection Against External Factors (Flood Hazard) and
Procedure Quality, and adversely affected the cornerstone objective to ensure the
availability, reliability, and capability of systems that respond to initiating events to
prevent undesirable consequences (i.e. core damage). Specifically, the licensees
failure to procedurally control external flooding design features, to ensure they would not
adversely affect the strategy for other flooding events, could negatively impact mitigating
                                              16


.02 Evaluation of the Inspection Requirements
    systems ability to respond during an external flooding event. The inspectors evaluated
02.01 Problem Identification
    the finding using IMC 0609, Attachment 0609.04, Tables 2 and 3, and Appendix A.
a. Determine that the Evaluation Documented Who Identified the Issue (i.e., Licensee-Identified, Self-Revealing, or NRC-Identified) and Under What Conditions the Issue was
    Based on a review of Appendix A, Exhibit 2, Item 4.B, the inspectors determined that this
Identified
    issue screened as having Very low safety significance (Green).
The inspectors determined that neither of the RCEs for the two White findings nor the CCA specifically addressed who identified the issues. The RCE for the TDAFWP White
    Enforcement: Title 10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Actions,"
finding had enough information to infer that the finding was self-revealed but the RCE for the flooding White finding contained only a minimal inference that a NRC finding had been issued.  The CCA had remarks similar to the flooding RCE that stated that NRC
    requires, in part, that Measures shall be established to assure that conditions adverse
had issued White findings but again the inspectors had to infer how the findings were
    to quality, such as failures, malfunctions, deficiencies, deviations, defective material and
identified. There were no statements in any licensee documentation or as a result of  
    equipment, and non-conformances are promptly identified and corrected. In the case of
interviews with licensee management indicating the licensee disagreed with the findings.  The licensee clearly stated the conditions under which the issues were identified. The inspectors considered the failure to clearly state who identified the issue to be a
    significant conditions adverse to quality, the measures shall assure that the cause of the
weakness for the TDAFWP White finding but not significant enough to leave this item
    condition is determined and corrective action taken to preclude repetition. Contrary to
open. For the TDAFWP White finding, this aspect of IP 95002 is closed.  The inspectors
    this requirement, from March 13, 2013 until February 14, 2014, the licensee failed to
concluded that the licensee failed to clearly document who identified the issue for the White flooding finding and the CCA and this aspect of IP 95002 was not met. b. Determine that the Evaluation Documented How Long the Issues Existed and Prior
    assure that for a significant condition adverse to quality, the cause of the condition was
Opportunities for Identification
    determined and corrective actions were taken to preclude repetition. Specifically, the
The licensee's evaluation for the TDAFWP White finding documented that pump to turbine alignment issues had existed for many years and that each time the pump was determined to be out of alignment it had been restored to within allowable limits. The
    licensees corrective actions failed to preclude repetition of an SCAQ where Procedure
inspectors determined that the licensee's evaluation was adequate with respect to identifying how long the issue existed and prior opportunities for identification.
    PC 80 Part 7, Lake Water Level Determination, as implemented, would not protect
 
    safety-related equipment in the turbine building or CWPH. After the licensee had taken
8  The licensee's evaluation for the flooding White finding documented that the change to the methodology of protecting the site from external lake flooding had been done in
    corrective actions to improve the wave barrier procedure in response to an NRC-
January of 1996. The licensee's evaluation also documented some prior missed opportunities to identify; however, the evaluation failed to address other significant prior opportunities. As discussed further in various sections of the report, the inspectors
    identified NOV, PC 80 Part 7 and other flood protection implementing procedures
observed that licensee personnel implemented corrective actions that significantly impacted other license basis events but failed to recognize these impacts.  Thus, there
    specified inadequate timelines to ensure wave run-up flood barriers would be installed
were additional opportunities to identify which were not listed or discussed in the
    prior to the lake level at which wave run-up could impact the site. Specifically, the
licensee's RCE.  The inspectors determined that the licensee's evaluation was not adequate with respect to identifying how long the issue existed and prior opportunities for identification.  This aspect of IP 95002 remains open for the flooding White finding. c. Determine that the Evaluation Documented the Plant Specific Risk Consequences, As Applicable, and Compliance Concerns with the Issues Both Individually and Collectively
    licensee completed an interim action to improve the wave barrier and associated
The risk evaluation performed by the licensee in discussions with the NRC Senior Reactor Analyst (SRA) prior to issuance of the TDAFWP White finding was not the one
    procedure on March 13, 2013, and a final corrective action CAPR 01883633-22 on
utilized by the licensee for the subsequent RCE. The licensee's RCE, stated, in part, "In
    November 30, 2013, to implement a plant modification to strengthen the physical
    external flood protection measures associated with a high lake level wave run-up and
    associated procedure guidance and design documentation. These actions failed to
    preclude repetition of the original SCAQ. Corrective actions for this issue included
    changing the affected procedures to install the wave barriers at a lower lake level,
    changing the lake level determination surveillance from monthly to weekly, and reducing
    the allowed installation time for the barriers from 3 weeks to 1 week. Because the
    violation was of very low safety significance and was entered into the licensees
    corrective action program (CR 01940739), this violation is being treated as an NCV,
    consistent with Section 2.3.2 of the NRC Enforcement Policy.
    (NCV 05000266/2014007-01; 05000301/2014007-01; Failure to Take Corrective
    Actions to Address External Flooding Procedure Deficiencies)
(2) Failure to Maintain External Flooding Procedure to Address All Possible CLB Floods
    Introduction: The inspectors identified a finding of very low safety significance and
    associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions,
    Procedures, and Drawings, in that from January 19, 1996 until November 25, 2013, the
    licensee failed to ensure that activities affecting quality were prescribed by documented
    procedures of a type appropriate to the circumstances to address external flooding as
    described in the Final Safety Analysis Report (FSAR). Specifically, PC 80 Part 7, Lake
    Water Level Determination directed advanced installation of concrete barriers to protect
    against deep wave action from the lake, which introduced significant unrecognized
    blockages in the natural drainage path credited in the FSAR to protect against the
    probable maximum precipitation and Turbine Building internal flooding events.
                                              17


order to quickly evaluate the safety significance of this issue, the Safety Monitor program was used by the probabilistic risk assessment (PRA) group."  The NRC team did not understand the need to quickly perform a risk assessment since one had previously been performed and discussed with an NRC SRA. Nevertheless, the licensee chose to
Description: The inspectors reviewed the licensees procedures and corrective action
perform one, but selected a program that did not align with standard NRC significance
documents and noted an important deficiency associated with procedure PC 80 Part 7.
determination techniques.  The licensee's Safe
Specifically, CR 01932698, 95002 Wave run-up protection may conflict with other
ty Monitor program is used to monitor on line risk in a moment to moment manner and use of the program to calculate the risk consequence for the TDAFWP failure was neither accurate nor appropriate. The team discussed the licensee's risk significance with the NRC SRA who performed the original assessment and the SRA verified that the licensee had understood and agreed with the
floods, was generated a few days prior to the 95002 inspection teams arrival onsite.
original NRC conclusions.  The purpose of this reassessment and write-up was not
This condition report described the concern that while wave barriers were installed near
understood either by the SRA nor the team. The inspectors also determined that the licensee had issued a Licensee Event Report for the failure of the TDAFWP and appropriately entered the failure in the Maintenance Rule database and the Performance
the CWPH, the probable maximum precipitation and turbine building flooding events
Indicators. Based upon the licensee's previous demonstrated knowledge and
could result in several feet of water at the CWPH and turbine building rollup doors due to
understanding of the risk significance of this item, the inspectors concluded that the risk
the wave barriers blocking natural site drainage paths. The inspectors noted that this
and compliance portion was weak, but that this fundamental aspect of IP95002 had
deficiency traced back to the original inappropriate action cited in the White Flooding
been met. The risk evaluation performed by the licensee for the flooding White finding enforcement conference was not accepted by the NRC although portions of the licensee's
finding, where in 1996, the licensee inappropriately deleted an AOP directing use of
assessment was recognized as acceptable and used to ensure the NRC position was accurate.  Nevertheless, the licensee chose to repeat the previously determined
sandbags at plant doorways and substituted a wave barrier installation strategy without
unsatisfactory risk assessment in the flooding White RCE. In the NRC Final Significance
recognizing the adverse impacts of the change.
Determination of a White Finding, dated August 9, 2013, Enclosure 2 provided an
The inspectors noted that the immediate corrective actions for the Flooding Apparent
analysis of the licensee risk information. In this analysis the NRC disagreed with the licensee's risk assessment in a number of significant ways, yet these disagreements appeared to not be factored into the licensee's subsequent risk assessment documented
Violation that were taken in March 2013 to improve the wave barrier described in
in the associated RCE. The inspectors' review of the flooding RCE determined that the  
PC 80 Part 7, failed to address all deficiencies that were created when sand bagging
licensee did not address possible compliance concerns or reportability.
actions were changed to wave barrier installation in 1996. While the improved wave
 
barriers provided necessary protection against wave action, they failed to address
9  During interviews, individuals directly involved in responding to the finding cited internal supplemental calculations, and stated that
unrecognized hazards during the probable maximum precipitation and turbine building
they believed there would not have been any consequences to the plant as a result of the finding. Interviewees stated that the finding's risk significance came only from significant conservatisms used in the individual plant examination external events (IPEEE) evaluation, and not from potential plant
internal flooding events. These barriers blocked natural drainage paths credited for flood
relief and rendered these paths nonfunctional as a result of wave barrier installation.
The Inspectors determined that procedure PC 80 Part 7 was inadequate until actions
were taken to modify it to provide additional flow paths for flood relief. The inspectors
noted that this issue was not recognized by the licensee until November 2013 for the
turbine building flooding event, and late January 2014 for the PMP event.
The inspectors concluded that the licensee did not adequately address the flooding
finding barrier deficiencies described in the original white flooding finding. This was
evident in the licensees interim corrective actions taken in March 2013, when the
licensee failed to restore full compliance, and did not recognize the need for providing an
additional drainage path. However, the inspectors noted that the licensee had not
implemented final corrective actions for wave barrier modification and flooding procedure
changes until November 2013, at which point steps were added to PC 80 Part 7 that
created a compensatory drainage path. As a result, the inspectors concluded that the
issue was most appropriately characterized as a failure to ensure that activities affecting
quality were prescribed by documented procedures of a type appropriate to the
circumstances to address external flooding in accordance with 10 CFR 50 Appendix B,
Criterion V. The inspectors also noted that this issue should have been readily identified
as a direct outcome of reviewing the NRC-identified finding, and it was not the result of a
thorough RCE which resulted in hidden issues surfacing.
Analysis: The inspectors determined that the licensees failure to maintain an external
flooding procedure appropriate to the circumstances to ensure the site was not
adversely impacted during CLB flooding events was a performance deficiency, because
it was the result of the failure to meet the requirements of 10 CFR Part 50, Appendix B,
Criterion V; the cause was reasonably within the licensees ability to foresee and correct;
and it should have been prevented. The inspectors determined that the finding has a
cross-cutting aspect in the area of problem identification and resolution, because the
licensee failed to take effective corrective actions to address issues in a timely manner
commensurate with their safety significance (P.3). Specifically, licensee personnel failed
to take appropriate interim corrective actions in March of 2013 when correcting a SCAQ
                                          18


consequences. Interviews with individuals not directly involved in addressing the flooding finding revealed that working level plant personnel were familiar with the
in that the interim action plan posed additional hazards to the site during design basis
flooding finding, but their awareness was focused more on the regulatory impacts, with minimal awareness of potential equipment impacts. The inspectors concluded that the licensee failed to adequately address the plant specific risk consequences or compliance concerns related to the flooding White finding and this aspect of IP 95002 was not met. d. Findings
floods.
No findings were identified. 02.02 Root Cause
The inspectors screened the performance deficiency in accordance with IMC 0612,
a. Determine that the Problem was Evaluated Using a Systematic Methodology to Identify
Power Reactor Inspection Reports, Appendix B, and determined that the issue was
the Root and Contributing Causes
more than minor because the finding was associated with the Mitigating Systems
  The inspectors reviewed the licensee's RCEs, CCA, and other documents related to the White findings. The licensee identified a total of four root causes and seven contributing causes using a systematic methodology.  In addition, the licensee's CCA identified two common causes and two contributing causes.  The licensee utilized support-refute
Cornerstone attributes of Protection Against External Factors (Flood Hazard) and
matrix, change analysis, barrier analysis, a cause and effects diagram, an event and
Procedure Quality, and adversely affected the cornerstone objective to ensure the
causal factor chart, and a "why" staircase during the two root cause assessments and  
availability, reliability, and capability of systems that respond to initiating events to
the CCA.  The inspectors determined that the RCE and CCA were conducted to a level  
prevent undesirable consequences (i.e. core damage). Specifically, the licensees
of detail commensurate with the significance of the issues.  The licensee's evaluations
failure to procedurally control external flooding design features to ensure they would not
included details of each item along with supporting data and other information. The licensee's use of systematic methodology to identify the root and contributing causes was determined to be adequate for the TDAFWP White finding.  Due to the significant weaknesses identified in the licensee's corrective actions, extent of condition, extent of cause, and root cause, the team concluded that this aspect for the flooding
adversely affect the strategy for other flooding events, could negatively impact mitigating
White finding was negatively impacted. This aspect of IP 95002 will remain open for the flooding White finding. b. Determine that the Root Cause Evaluation was Conducted to a Level of Detail Commensurate with the Significance of the Problem
systems ability to respond during external and internal flooding events.
The licensee utilized the systematic methodologies for the CCA discussed above and
The inspectors evaluated the finding in accordance with IMC 0609, Significance
determined that the primary root causes were:
Determination Process, Attachment 0609.04, Initial Characterization of Findings. The
* Less than adequate understanding of the design and licensing basis;
inspectors determined that the finding affected the Mitigating Systems Cornerstone and
* Corrective Action Program items with incorrect priorities;
evaluated the finding using Appendix A, The Significance Determination Process for
* Original construction stress riser introduced to the TDAFWP;
Findings At-Power, Exhibit 2, for the Mitigating Systems Cornerstone. In the Mitigating
 
Systems Cornerstone, the inspectors answered "Yes" to the screening question Does
10  * Emergency Preparedness group did not perform reviews of federal guidance;
the finding represent a loss of system and/or function? because an assumed turbine
* A lack of or inadequate leadership; and
building (TB) internal flooding event in a condition with the jersey barriers installed due to
* Poor technical procedure quality.  
high lake water level could ultimately result in the loss of emergency diesel generators
The inspectors noted that while the licensee had poor procedure quality as a root cause for the TDAFWP issue, the knowledge, skills, and abilities (KSA) of the workers was not considered as a possible root cause. For example, the TDAFWP alignment procedure
and other safety-related equipment. Therefore, the finding required a detailed risk
did not require the taking of as-found data nor did the procedure require that if the data
evaluation.
was taken that it be reviewed by engineering personnel.  Yet, a qualified maintenance mechanic would have experience with the need to take such data and would know to pass it along to their supervisor. The inspectors performed a search of the licensee's
The probability of the jersey barriers being installed was evaluated based on the fact that
CAP database to see if a trend of issues with a cause of KSA existed and did not identify
the jersey barriers have not been installed during the 18 years (since 1996) that the
any trends. The licensee's RCEs should have discussed this aspect in sufficient detail
jersey barriers were available for installation if high lake water level was encountered.
so as to demonstrate that this was not a root cause.
Using a statistical Bayesian update with a Jeffreys non-informative prior, the probability
Despite the weakness noted above, the inspectors determined that the RCE for the  
that the jersey barriers could have been installed was determined to be 2.63E-2.
TDAFWP White finding was conducted to a level of detail commensurate with the  
The risk evaluation was performed by Region III Senior Reactor Analysts (SRAs). The
significance of the issues.  
increase in core damage frequency (CDF) was calculated assuming scenarios
involving internal turbine building flooding events. The exposure time assumed was one
year which is the maximum allowed by the significance determination process.
For the evaluation of the risk significance, the SRAs considered TB flooding events with
three plant systems that have basically an unlimited system volume if the flooding event
is not terminated. These systems are the fire protection (FP) system, the circulating
water (CW) system, and the service water (SW) system.
To evaluate this finding, the Senior Reactor Analysts (SRAs) determined the frequency
of a pipe break (or expansion joint failure) using Electric Power Research Institute
(EPRI) Report 302000079, Pipe Rupture Frequencies for Internal Flooding Probabilistic
Risk Assessments, Revision 3. The pipe breaks of interest were determined to be
those between approximately 20,000 gpm and 36,000 gpm. The lower value of
20,000 gpm is based on the drainage capacity at the eight foot level (which is the ground
floor elevation in the TB) provided by a combination of gaps in the metal siding of the
circulating water pump house (CWPH) walkway and the storm drains still available even
with the jersey barriers installed. Pipe breaks of less than 20,000 gpm would not result
                                              19


in water accumulation on the lowest level of the TB and thus would not imperil risk
For the flooding White finding and the CCA root cause the inspectors observed that problems with the quality of condition report evaluations and with Functionality Assessments (FA) were identified but not included as either a root cause or a
significant equipment. The upper value of 36,000 gpm is based on calculation
contributing cause.  The inspectors also noted that an assessment of the licensee's CCA
2008-0024, Auxiliary Feedwater Pump Room Flood, which determined that for a
performed prior to the team arriving on site (Quick Hit PBSA-PBNP-13-03) had a similar observation and a recommendation to clearly articulate this theme.  The inspectors determined that neither a root cause nor a contributing cause was assigned to either corrective action program quality or CR evaluations.  One CAPR was assigned to
36,000 gpm TB flood rate, the TB rollup door(s) would fail at a level of 18 inches and
improve the quality of FAs.  This is discussed in more detail in Section 02.04, below. 
allow a flow of up to 36,000 gpm while maintaining the TB flood level at less than
While corrective action program evaluation quality was a part of the issues identified, the
18 inches. For the risk evaluation, a maximum TB flood rate of 36,000 gpm was thus
failure of the licensee to either include it as a root cause or to justify why it was not a root
used to represent the delta risk associated with the finding, since this is the maximum
cause was a significant weakness.
drainage flow through the failed TB rollup door(s). Any TB flood rate greater than
The inspectors determined that this aspect of the IP 95002 criteria was not met for the
36,000 gpm would cause the TB water level to exceed 18 inches if the break flow was
flooding White finding and the CCA.
not immediately terminated regardless of whether the jersey barriers were installed or
  c. Determine that the Root Cause Evaluation Included a Consideration of Prior Occurrences of the Problem and Knowledge of Prior Operating Experience
not. It was conservatively assumed that exceeding 18 inches level in the TB would
  The inspectors determined that the licensee's evaluation included a consideration of prior occurrences of the issues and industry operating experience.  The RCE for the TDAFWP determined that a prior opportunity was missed in early 2011 during the Unit 2
result in a core damage event (i.e., a conditional core damage probability (CCDP) of 1.0)
refueling outage when pipe stresses were identified on the opposite unit TDAFWP.  The
due to the loss of risk significant plant equipment.
licensee determined that even though the pipe stresses were identified and corrected
Fire Protection System
that a CR was not issued and thus the opportunity to apply this information to the next
The FP system was screened because of the relatively low maximum flood rates that
Unit 1 refueling outage and TDAFWP maintenance activity was missed. The inspectors concluded that the root cause evaluation included a review of prior and precursor problems and properly evaluated internal and industry operating experience.  This aspect of the IP 95002 criteria was met for the TDAFWP finding.
can occur with a break in the FP system. The capacity of the two fire water pumps
 
together is approximately 6,800 gpm, which is well below the drainage capacity of
11  The RCE for the White flooding finding determined that prior opportunities were missed to properly correct the deficiency.  This included opportunities in 2004, when condition
approximately 20,000 gpm at the eight foot level.
reports were generated questioning the adequacy of the wave run-up barriers, given the 1996 procedure change.  This also included opportunities in 2012 where a functionality assessment inappropriately contained conclusions regarding the functionality of the
wave barriers on perceived risk.  The inspectors noted that these opportunities were
factored into the determination of one of the root causes.  The inspectors also noted the
RCE discussion on industry OE and noted several instances where the causes of
industry deficiencies were similar to the causal factors identified for the White flooding issue 
As discussed later in this inspection report unintended consequences were introduced
during the corrective actions to the White flooding finding.  The failure to recognize these
consequences represented additional occurrences of the problem.  The inspectors determined that this aspect of the IP 95002 criteria was not met for the flooding White finding and the CCA.
 
d. Determine that the Root Cause Evaluation Addresses the Extent of Condition and the Extent of Cause of the Problem
  The licensee's RCE included an evaluation of the extent of condition and extent of cause of the issues.  The inspectors determined that the RCE for the TDAFWP issue was adequate with comments.  These comments are discussed in section 02.04 of this report.  The inspectors also noted that during an assessment of the licensee's RCE that
was performed prior to the team arriving on site (Quick Hit PBSA-PBNP-13-03) that
deficiencies with the TDAFWP had been identified.
  For example, the extent of condition prior to the Quick Hit was limited to rotating couplings of the same make and model as
that which had failed on the Unit 1 TDAFWP.  Following a recommendation of the Quick Hit team, the licensee had expanded the extent of condition to include other make and model couplings as well as all rotating connections.  Based on a review of the RCE and
CCA and discussions with licensee management and staff personnel, the inspectors
concluded that the evaluations for the TDAFWP White finding adequately addressed the
extent of condition and the extent of cause.  This aspect of the IP 95002 was not for the
 
TDAFWP finding.  The inspectors determined that the RCE for the flooding White finding also included an evaluation of the extent of condition and extent of cause but based on the NRC findings documented in Section 02.04 of this report the inspectors concluded that this item was
not acceptable.  For example, the RCE did not consider possible bypass paths around
the external flooding barrier.  During field walk downs, the inspectors identified two
different drain pipes in the concrete near the CWPH which directly communicated with the lake shore and should have been evaluated as possible bypass paths.  The inspectors concluded that the evaluations for the flooding White finding did not satisfy this aspect of the IP 95002 criteria. e. Findings
No findings were identified.
 
12  02.03 Corrective Actions
a. Determine that Appropriate Corrective Actions are Specified for Each Root and Contributing Cause or that the Licensee has an Adequate Evaluation for Why No Corrective Actions are Necessary
  The inspectors assessed the corrective actions for the RCEs and the CCA.  The inspectors verified that all root causes had associated CAPRs and that all contributing
causes had associated corrective actions.  The inspectors then performed a more detailed assessment of selected CAPRs and corrective actions.  The detailed assessment included a sample of corrective action program documents, field walk
downs, interviews with selected licensee individuals, and reviews of the design and licensing basis.  The inspectors concluded that the corrective actions for the TDAFWP finding were vague and needed additional clarification.  As previously noted, the scope of the root
cause was narrowly focused but this had previously been identified by an internal licensee review.  As a result, the scope of the corrective actions had been expanded to include other rotating equipment connections.  Additional corrective actions were
reviewed by the inspectors with no further substantive observations.  The inspectors
concluded that the CAPRs and corrective actions for the TDAFWP met the requirements
of IP 95002. During the reviews of the corrective action program documents, the inspectors noted that the licensee questioned whether the installation of the flood protection barriers had introduced unintended consequences.  Specifically, the corrective action to install a more robust wave barrier in lieu of sandbagging efforts failed to restore compliance with
the CLB.  While the improved wave barriers provided necessary protection against wave action, they introduced unrecognized hazards during the probable maximum
precipitation and turbine building internal flooding events.  These barriers blocked
natural drainage paths credited for flood relief and rendered these paths nonfunctional as a result of wave barrier installation.  The inspectors noted that this issue was not recognized by the licensee until November 2013 for one of the flooding events, and
January 2014 for the other event, and thus, the licensee's interim corrective actions for
the flooding finding were deficient between March and November 2013 due to procedure
call-up PC 80 Part 7, which remained inadequate during this time.  As a result, the licensee was required to add compensatory actions during wave barrier installation to provide additional flow paths by opening the CWPH roll-up doors.  When developing the compensatory action to address the deficiency associated with the new wave barriers, the licensee failed to recognize that the new compensatory
measures required actions outside of the CLB.  Specifically, Section 2.5 "Hydrology" in the FSAR for the Maximum precipitation flood states, in part, that "-the topography of
the site results in adequate natural drainage to remove this amount of water and limit ponding depth to prevent adversely affecting safety related equipment."  The nonfunctional drainage paths following wave barrier installation resulted in the licensee
having to identify an alternate path for flood water drainage flow.  As a compensatory
action, the licensee chose to open the CWPH roll-up doors, route flood waters through
the CWPH, and relying on internal flood relief dampers to open and drain the water.  The
licensee viewed those compensatory actions as still with its CLB.  As a result, the 
13  inspectors determined that the licensee failed to properly screen the actions as compensatory measures under the requirements of 10 CFR 50.59.  The inspectors noted that as a result of the failure to evaluate these actions under  10 CFR 50.59, the licensee did not properly consider several factors associated with the
compensatory actions that should have been evaluated.  Some of these factors included flood water flow rates through the open doors, the impact of debris and slush from outside being carried into the CWPH and clogging the flood relief dampers, the impact of
the cold temperatures on the equipment in the rooms during the potentially extended periods of time during which the doors could be open, and security impacts.  In addition, the inspectors noted the licensee failed to recognize that procedure  PC 80 Part 7, failed to account for the time necessary to ensure that the barriers would
be constructed before the lake reached conditions where deep wave action could impact the site.  Specifically, the licensee's calculation specified that 8.2 weeks would be available after Procedure PC 80 Part 7, initiated actions to install the wave barriers based on lake level. The inspectors reviewed EC 279455, "Time Available to Respond to Threat From Rising Water," and the licensee's lake level determination monthly surveillance, PBF-2124,
"PPCS Forebay and Pump Bay Level Alarm Setpoints," and identified several
deficiencies.  These deficiencies included non-conservative assumptions when using the maximum monthly rate of lake level rise, non-conservative assumptions for the lake level at which the site could be impacted by the waves, a non-conservative allowance to rely
on the previous month's data if no lake level data was immediately available, and an
error in an assumption that wave barriers would be installed earlier than PC 80 Part 7,
actually required.  When the licensee corrected these inputs, the inspectors noted that the time available for action was significantly reduced to less than three weeks. The inspectors observed that PC 80 Part 7, granted three weeks allowance for activities to be scheduled and performed to install the wave barriers.  The inspectors concluded that the deficiencies in the licensee's timelines left them vulnerable in that actions may not have been initiated soon enough to protect the site from the wave run-up design
basis event.  The inspectors determined that this aspect of IP 95002 was not met for the flooding White finding. b. Determine that the Corrective Actions Have Been Prioritized with Consideration of Risk-Significance and Regulatory Compliance
  The inspectors assessed the licensee's timeliness of corrective actions for the RCEs and CCA associated with the risk significant issues.  The inspectors noted that there were no
formal tracking mechanisms or documentation for several of the corrective actions that had been previously taken prior to the completion of the RCEs and CCA.  Formalized tracking measures would assure the actions are satisfactorily completed and allow for documentation of the basis for closure.  The inspectors concluded that an appropriate schedule had been established for implementing and completing the corrective actions for the TDAFWP White finding.  This
aspect for the flooding White finding will remain open pending the inspectors' review of the additional corrective actions the licensee will need to perform. 
14  c. Determine that a Schedule has been Established for Implementing and Completing the
Corrective Actions
  As discussed in Section 02.03.b, above, the inspectors determined that the licensee had established an appropriate schedule for implementing the corrective actions for the
TDAFWP White finding.  The aspect for the flooding White finding will remain open pending the inspectors' review of the additional corrective actions that the licensee will need to perform. d. Determine that Quantitative or Qualitat
ive Measures of Success Have Been Developed for Determining the Effectiveness of the Corrective Actions to Prevent Recurrence
  The inspectors' review of the effectiveness review (EFR) plan identified a number of weaknesses.  The inspectors determined that these weaknesses rose to the level of a
finding and that the weaknesses were broad and deep enough to conclude that this
section did not meet the requirements of IP 95002.  As the TDAFWP finding occurred
first and there had been additional time the EFR had already been substantially performed for this issue.  The interim assessments, combined with the general quality of the RCE led the inspectors to conclude that this section is complete for the TDAFWP finding but remains open for the flooding White finding and the CCA. e. Determine that the Corrective Actions Planned or Taken Adequately Address a Notice of  Violation that was the Basis for the Supplemental Inspection, if Applicable
For the TDAFWP White finding, the licensee did not respond to the initial NOV because the corrective actions taken and planned to be taken to correct the violation, and the
date when full compliance was achieved was already addressed on the docket in NRC
Inspection Report 05000266/2012009.  As part of the 95002 inspection, the team members performed a sampling of the immediate corrective actions and determined the full compliance had been restored.  The team considered that the IP 95002 requirements were met for the TDAFWP White finding. For the flooding White finding, the licensee did not respond to the initial NOV because the corrective actions taken and planned to be taken to correct the violation, and the
date when full compliance was achieved was already addressed on the docket in 
NRC Inspection Report 05000266/2013002 and 05000301/2013002 and in the licensee's submittals dated July 10, 15, and 29, 2013.  As part of the 95002 inspection, the team members performed a sampling of the immediate corrective actions and determined the full compliance had been restored.  However, as stated above, the
inspectors noted that the corrective actions resulted in unintended consequences.  In
addition, as noted previously, the inspectors identified a deficiency where insufficient
corrective action was taken to correct PC 80 Part 7, in order to preclude repetition of the original significant condition adverse to quality.  Thus the team concluded that the requirements of IP 95002 were not met for the flooding White finding.
 
f. Findings
(1) Failure to Take Corrective Actions to Address External Flooding Procedure Deficiencies
Introduction:  The inspectors identified a finding of very low safety significance and an associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion XVI, "Corrective 
15  Actions," in that from March 13, 2013 until February 14, 2014, the licensee failed to assure that for a significant condition adverse to quality (SCAQ), the cause of the
condition was determined and corrective actions were taken to preclude repetition.  Specifically, the licensee's corrective actions failed to preclude repetition of an SCAQ where Procedure PC 80 Part 7, "Lake Water Level Determination," as implemented,
would not protect safety-related equipment in the turbine building or CWPH.  After the
licensee had taken corrective actions to improve the wave barrier procedure in response
to an NRC-identified NOV, PC 80 Part 7, and other flood protection implementing
procedures specified inadequate timelines to ensure wave run-up flood barriers would
be installed prior to the lake level at which wave run-up could impact the site.
Description:  The inspectors reviewed procedures associated with flooding as part of their independent extent of condition and extent of cause, and review of corrective
actions to prevent recurrence.  The inspectors noted the licensee failed to recognize that
procedure, PC 80 Part 7, did not grant adequate timelines to ensure that the barriers
would be constructed before the lake reached conditions where deep wave action could
impact the site.  Specifically, the licensee's calculation specified that 8.2 weeks would be available after Procedure PC 80 Part 7, initiated actions to install the wave barriers based on lake level.  The inspectors observed that based on these timelines, 
PC 80 Part 7 granted three weeks allowance for activities to be scheduled and
performed to install the wave barriers.  Specifically, PC 80 Part 7, stated, in part, 
"IF corrected mean level is greater than or equal to +0.5 ft., THEN PERFORM the following: NOTIFY maintenance to generate on demand PM (PMRQ 00059608-02) to INSTALL barriers and sandbags as required to be completed within three weeks." The inspectors reviewed EC 279455, "Time Available to Respond to Threat From Rising Water," and the licensee's lake level determination monthly surveillance, PBF-2124,
"PPCS Forebay and Pump Bay Level Alarm Setpoints," and found several deficiencies. 
These deficiencies included non-conservative assumptions when using the maximum
monthly rate of lake level rise, non-conservative assumptions for the lake level at which the site could be impacted by the waves, non-conservative allowances to rely on the previous month's data if no lake level data was immediately available, and an error in an
assumption that wave barriers would be installed earlier than PC 80 Part 7 actually
dictated.  Inspectors noted that the procedure had no barriers to prevent the previous
month's data from being used during multiple subsequent months.  When the licensee
corrected these inputs, the inspectors noted that the time available to fully implement the provisions of PC 80 Part 7 significantly reduced to less than the three weeks called for in the procedure. The inspectors concluded that these deficiencies in the licensee's timelines left them vulnerable in that actions may not be initiated soon enough to protect the site from the
wave run-up design basis event.  The inspectors noted that these deficiencies
represented a failure of the licensee's corrective action to preclude repetition of an
SQAC where Procedure PC 80 Part 7, "Lake Water Level Determination," as implemented, would not protect safety-related equipment in the turbine building or CWPH. In addition, to the PC 80 Part 7 issues associated with the timelines for barrier installation, the inspectors found additional procedural deficiencies that should have
been identified and corrected as part of the corrective actions taken to address the
flooding NOV.  PC 80 Part 7 procedural deficiencies included error traps where steps 
16  could be performed out of sequence (i.e. barriers installed before CWPH doors open), and a failure to include CWPH doors in robust tag-out process to ensure their 'open'
position was controlled.  PBF-2124 procedural inadequacies included direction to install jersey barriers rather than the more robust barriers associated with the licensee's RCE corrective actions.  Inspectors noted that this reference to the jersey barriers referred to
the previous wave run-up flooding response strategy.  The inspectors identified that the
same +0.5ft. installation threshold error was made in PBF-2124, as well as the licensee's external flooding abnormal procedure, AOP 13C. Licensee procedure PI-AA-204, Condition Identification and Screening Process,  Section 2.45 defines a Significant Condition Adverse to Quality (SCAQ) as, "Failures, malfunctions, deficiencies, deviations, defective items, abnormal occurrences, non-conformances, or out-of control processes that significantly threatens or has compromised nuclear safety or radiological safety, as well as any significant reportable industrial safety or environmental (e.g., OSHA, State, etc.) issues.  SCAQ issues require corrective actions to prevent recurrence."  Condition Report 01883633 identified the White flooding finding and associated performance deficiency as an SQAC. The inspectors also noted that the licensee completed an interim action to improve the wave barrier and associated procedure on March 13, 2013, and a final corrective action CAPR 01883633-22 on November 30, 2013 to implement a plant modification to strengthen the physical external flood protection measures associated with a high lake
level wave run-up and associated procedure guidance and design documentation.  The
inspectors observed that this action was credited in the licensee's RCE as an action to
prevent recurrence of the original SQAC.  As a result, the inspectors determined that the licensee failed to take corrective actions to preclude repetition of an SCAQ where
Procedure PC 80 Part 7, as implemented, would not protect safety-related equipment in the turbine building or CWPH.
Analysis:  The inspectors determined that the licensee's failure to take corrective actions to address the inadequate flooding procedure was a performance deficiency, because it
was the result of the failure to meet the requirements of 10 CFR Part 50, Appendix B,
Criterion XVI; the cause was reasonably within the licensee's ability to foresee and correct; and it should have been prevented.  The inspectors determined that the finding had a cross-cutting aspect in the area of problem identification and resolution, because
the licensee failed to thoroughly evaluate issues to ensure that resolutions address
causes and extents of condition commensurate
with their safety significance (P.2). Specifically, the licensee failed to fully evaluate issues with the flooding procedure to
ensure the corrective actions they took would assure that robust protection from wave run-up would be installed prior to reaching a lake level where deep wave action could present a threat to the site. The inspectors screened the performance deficiency in accordance with IMC 0612, "Power Reactor Inspection Reports," Appendix B, and determined that the issue was
more than minor because the finding was associated with the Mitigating Systems
Cornerstone attributes of Protection Against External Factors (Flood Hazard) and
Procedure Quality, and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e. core damage).  Specifically, the licensee's
failure to procedurally control external flooding design features, to ensure they would not
adversely affect the strategy for other flooding events, could negatively impact mitigating 
17  systems' ability to respond during an exte
rnal flooding event.  The inspectors evaluated the finding using IMC 0609, Attachment 0609.04, Tables 2 and 3, and Appendix A.
Based on a review of Appendix A, Exhibit 2, Item 4.B, the inspectors determined that this
issue screened as having Very low safety significance (Green).
Enforcement:  Title 10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Actions," requires, in part, that "Measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and
equipment, and non-conformances are promptly identified and corrected.  In the case of
significant conditions adverse to quality, the measures shall assure that the cause of the
condition is determined and corrective action taken to preclude repetition."  Contrary to this requirement, from March 13, 2013 until February 14, 2014, the licensee failed to assure that for a significant condition adverse to quality, the cause of the condition was
determined and corrective actions were taken to preclude repetition.  Specifically, the
licensee's corrective actions failed to preclude repetition of an SCAQ where Procedure
PC 80 Part 7, "Lake Water Level Determination," as implemented, would not protect
safety-related equipment in the turbine building or CWPH.  After the licensee had taken corrective actions to improve the wave
barrier procedure in response to an NRC-identified NOV, PC 80 Part 7 and other flood protection implementing procedures
specified inadequate timelines to ensure wave run-up flood barriers would be installed
prior to the lake level at which wave run-up could impact the site.  Specifically, the
licensee completed an interim action to improve the wave barrier and associated procedure on March 13, 2013, and a final corrective action CAPR 01883633-22 on November 30, 2013, to implement a plant modification to strengthen the physical external flood protection measures associated with a high lake level wave run-up and
associated procedure guidance and design documentation.  These actions failed to
preclude repetition of the original SCAQ.  Corrective actions for this issue included
changing the affected procedures to install the wave barriers at a lower lake level, changing the lake level determination surveill
ance from monthly to weekly, and reducing the allowed installation time for the barriers from 3 weeks to 1 week.  Because the
violation was of very low safety significance and was entered into the licensee's
corrective action program (CR 01940739), this violation is being treated as an NCV,
consistent with Section 2.3.2 of the NRC Enforcement Policy. 
(NCV 05000266/2014007-01; 05000301/2014007-01; Failure to Take Corrective
Actions to Address External Flooding Procedure Deficiencies)
 
(2) Failure to Maintain External Flooding Procedure to Address All Possible CLB Floods
Introduction:  The inspectors identified a finding of very low safety significance and associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion V, "Instructions,
Procedures, and Drawings," in that from January 19, 1996 until November 25, 2013, the licensee failed to ensure that activities affecting quality were prescribed by documented procedures of a type appropriate to the circumstances to address external flooding as
described in the Final Safety Analysis Report (FSAR).  Specifically, PC 80 Part 7, "Lake Water Level Determination" directed advanced installation of concrete barriers to protect
against deep wave action from the lake, which introduced significant unrecognized
blockages in the natural drainage path credited in the FSAR to protect against the
probable maximum precipitation and Turbine Building internal flooding events.
 
18  Description
:  The inspectors reviewed the licensee's procedures and corrective action documents and noted an important deficiency associated with procedure PC 80 Part 7. 
Specifically, CR 01932698, "95002 Wave run-up protection may conflict with other floods," was generated a few days prior to the 95002 inspection team's arrival onsite.  This condition report described the concern that while wave barriers were installed near
the CWPH, the probable maximum precipitation and turbine building flooding events
could result in several feet of water at the CWPH and turbine building rollup doors due to
the wave barriers blocking natural site drainage paths.  The inspectors noted that this
deficiency traced back to the original inappropriate action cited in the White Flooding finding, where in 1996, the licensee inappropriately deleted an AOP directing use of sandbags at plant doorways and substituted a wave barrier installation strategy without recognizing the adverse impacts of the change. The inspectors noted that the immediate corrective actions for the Flooding Apparent Violation that were taken in March 2013 to improve the wave barrier described in 
PC 80 Part 7, failed to address all deficiencies that were created when sand bagging
actions were changed to wave barrier installation in 1996.  While the improved wave barriers provided necessary protection against wave action, they failed to address unrecognized hazards during the probable maximum precipitation and turbine building
internal flooding events.  These barriers blocked natural drainage paths credited for flood
relief and rendered these paths nonfunctional as a result of wave barrier installation. 
The Inspectors determined that procedure PC 80 Part 7 was inadequate until actions were taken to modify it to provide additional flow paths for flood relief.  The inspectors noted that this issue was not recognized by the licensee until November 2013 for the
turbine building flooding event, and late January 2014 for the PMP event.
 
The inspectors concluded that the licensee did not adequately address the flooding
finding barrier deficiencies described in the original white flooding finding.  This was evident in the licensee's interim corrective actions taken in March 2013, when the licensee failed to restore full compliance, and did not recognize the need for providing an
additional drainage path.  However, the inspectors noted that the licensee had not
implemented final corrective actions for wave barrier modification and flooding procedure
changes until November 2013, at which point steps were added to PC 80 Part 7 that created a compensatory drainage path.  As a result, the inspectors concluded that the issue was most appropriately characterized as a failure to ensure that activities affecting
quality were prescribed by documented procedures of a type appropriate to the
 
circumstances to address external flooding
in accordance with 10 CFR 50 Appendix B, Criterion V.  The inspectors also noted that this issue should have been readily identified
 
as a direct outcome of reviewing the NRC-identified finding, and it was not the result of a
thorough RCE which resulted in hidden issues surfacing. 
Analysis:  The inspectors determined that the licensee's failure to maintain an external flooding procedure appropriate to the circumstances to ensure the site was not
 
adversely impacted during CLB flooding events was a performance deficiency, because it was the result of the failure to meet the requirements of 10 CFR Part 50, Appendix B,
Criterion V; the cause was reasonably within the licensee's ability to foresee and correct;
and it should have been prevented.  The inspectors determined that the finding has a cross-cutting aspect in the area of problem identification and resolution, because the licensee failed to take effective corrective actions to address issues in a timely manner commensurate with their safety significance (P.3).  Specifically, licensee personnel failed to take appropriate interim corrective actions in March of 2013 when correcting a SCAQ 
19  in that the interim action plan posed additional hazards to the site during design basis floods. The inspectors screened the performance deficiency in accordance with IMC 0612, "Power Reactor Inspection Reports," Appendix B, and determined that the issue was
more than minor because the finding was associated with the Mitigating Systems Cornerstone attributes of Protection Against External Factors (Flood Hazard) and Procedure Quality, and adversely affected the cornerstone objective to ensure the
availability, reliability, and capability of systems that respond to initiating events to
prevent undesirable consequences (i.e. core damage).  Specifically, the licensee's
failure to procedurally control external flooding design features to ensure they would not adversely affect the strategy for other flooding events, could negatively impact mitigating systems' ability to respond during external and internal flooding events. The inspectors evaluated the finding in accordance with IMC 0609, "Significance Determination Process," Attachment 0609.04, "Initial Characterization of Findings." The
inspectors determined that the finding affected the Mitigating Systems Cornerstone and
evaluated the finding using Appendix A, "The Significance Determination Process for
Findings At-Power," Exhibit 2, for the Mitigating Systems Cornerstone.  In the Mitigating
Systems Cornerstone, the inspectors answered "Yes" to the screening question "Does the finding represent a loss of system and/or function?" because an assumed turbine building (TB) internal flooding event in a condition with the jersey barriers installed due to
high lake water level could ultimately result in the loss of emergency diesel generators
and other safety-related equipment.  Therefore, the finding required a detailed risk
 
evaluation.
The probability of the jersey barriers being installed was evaluated based on the fact that
the jersey barriers have not been installed during the 18 years (since 1996) that the
jersey barriers were available for installation if high lake water level was encountered. 
Using a statistical Bayesian update with a Jeffrey's non-informative prior, the probability that the jersey barriers could have been installed was determined to be 2.63E-2.
The risk evaluation was performed by Region III
Senior Reactor Analysts (SRAs).  The increase in core damage frequency (CDF) was calculated assuming scenarios involving internal turbine building floodi
ng events.  The exposure time assumed was one year which is the maximum allowed by the significance determination process.
For the evaluation of the risk significance, the SRAs considered TB flooding events with
three plant systems that have basically an un
limited system volume if the flooding event is not terminated.  These systems are the fire protection (FP) system, the circulating water (CW) system, and the service water (SW) system.
To evaluate this finding, the Senior Reactor Analysts (SRAs) determined the frequency
of a pipe break (or expansion joint failure) using Electric Power Research Institute
(EPRI) Report 302000079, "Pipe Rupture Frequencies for Internal Flooding Probabilistic
Risk Assessments," Revision 3.  The pipe breaks of interest were determined to be
those between approximately 20,000 gpm and 36,000 gpm.  The lower value of 20,000 gpm is based on the drainage capacity at the eight foot level (which is the ground floor elevation in the TB) provided by a combination of gaps in the metal siding of the
circulating water pump house (CWPH) walkway and the storm drains still available even
 
with the jersey barriers installed.  Pipe breaks of less than 20,000 gpm would not result 
20  in water accumulation on the lowest level of the TB and thus would not imperil risk significant equipment. The upper value of 36,000 gpm is based on calculation
2008-0024, Auxiliary Feedwater Pump Room Flood, which determined that for a 36,000 gpm TB flood rate, the TB rollup door(s) would fail at a level of 18 inches and allow a flow of up to 36,000 gpm while maintaining the TB flood level at less than
18 inches. For the risk evaluation, a maximum TB flood rate of 36,000 gpm was thus  
used to represent the delta risk associated with the finding, since this is the maximum  
drainage flow through the failed TB rollup door(s). Any TB flood rate greater than
36,000 gpm would cause the TB water level to exceed 18 inches if the break flow was not immediately terminated regardless of whether the jersey barriers were installed or not. It was conservatively assumed that exceeding 18 inches level in the TB would  
result in a core damage event (i.e., a conditional core damage probability (CCDP) of 1.0)  
due to the loss of risk significant plant equipment.  
 
Fire Protection System
 
The FP system was screened because of the relatively low maximum flood rates that  
can occur with a break in the FP system. The capacity of the two fire water pumps  
together is approximately 6,800 gpm, which is well below the drainage capacity of approximately 20,000 gpm at the eight foot level.  
Circulating Water System
Circulating Water System
 
The SRAs evaluated the delta risk associated with a break in the Circulating Water (CW)
The SRAs evaluated the delta risk associated with a break in the Circulating Water (CW)  
system with the jersey barriers installed. Two different failure causes were available on
system with the jersey barriers installed. Two different failure causes were available on the CW system which could result in a break of greater than 20,000 gpm: (1) a CW system expansion joint (EJ) failure, or (2)  
the CW system which could result in a break of greater than 20,000 gpm: (1) a CW
a CW system piping break. Each of these failures was evaluated separately.  
system expansion joint (EJ) failure, or (2) a CW system piping break. Each of these
 
failures was evaluated separately.
Circulating Water System Expansion Joints
Circulating Water System Expansion Joints
  In the EPRI report, the failure rate of an EJ per year was given for flood rates greater  
In the EPRI report, the failure rate of an EJ per year was given for flood rates greater
than 10,000 gpm. This value was conservatively used to represent the failure rate of an  
than 10,000 gpm. This value was conservatively used to represent the failure rate of an
EJ for a flood greater than 20,000 gpm (i.e., a flood rate that would exceed the drainage  
EJ for a flood greater than 20,000 gpm (i.e., a flood rate that would exceed the drainage
capacity at the eight foot level). There are eight EJs on the CW system in the TB. From  
capacity at the eight foot level). There are eight EJs on the CW system in the TB. From
the EPRI report, the frequency of a major flood with from a CW system EJ with a flood rate of greater than 10,000 gpm is 6.08E-6/yr/EJ. With eight EJs per Unit, the frequency of an EJ failure is 4.86E-5/yr.  
the EPRI report, the frequency of a major flood with from a CW system EJ with a flood
rate of greater than 10,000 gpm is 6.08E-6/yr/EJ. With eight EJs per Unit, the frequency
of an EJ failure is 4.86E-5/yr.
Without the jersey barriers installed, the flood water would drain out toward the CWPH
and down towards the lake with an essentially open path (i.e., essentially an unlimited
drainage rate outside the TB). With the jersey barriers installed, the drainage capacity
would be approximately 20,000 gpm at the eight foot level provided by a combination of
gaps in the metal siding of the CWPH walkway and the storm drains near the CWPH.
The drainage capacity provided by the gaps in the metal siding of the CWPH walkway
would increase as the height of the water level outside the Turbine Building increased
and would represent the majority of the drainage flow above the eight foot level. Using
the TB floor volume, the outside volume up to the jersey barriers, and the drainage rate
outside the TB (as a function of height), the licensee estimated that there was
approximately 31 minutes available to secure the CW pumps to terminate the break flow
                                          20


before exceeding a level of 18 inches in the TB. A CW system flooding event would
Without the jersey barriers installed, the flood water would drain out toward the CWPH
require the operators to enter AOP-13A, Circulating Water System Malfunction.
and down towards the lake with an essentially open path (i.e., essentially an unlimited drainage rate outside the TB).  With the jersey barriers installed, the drainage capacity would be approximately 20,000 gpm at the eight foot level provided by a combination of
Securing the CW pumps on a CW system flood event is Step 1 of the AOP. The SRAs
gaps in the metal siding of the CWPH walkway and the storm drains near the CWPH. 
used the SPAR-H method (per NUREG/CR-6883) to calculate a human error probability
The drainage capacity provided by the gaps in the metal siding of the CWPH walkway
(HEP) for the failure of the operators to terminate a CW flood event. Using SPAR-H an
would increase as the height of the water level outside the Turbine Building increased
HEP for the failure of the operators to secure the CW pumps before exceeding 18 inches
and would represent the majority of the drainage flow above the eight foot level.  Using the TB floor volume, the outside volume up to the jersey barriers, and the drainage rate outside the TB (as a function of height), the licensee  estimated that there was
level in the TB was calculated to be 0.2. This calculation assumed high stress for both
approximately 31 minutes available to secure the CW pumps to terminate the break flow 
diagnosis and action and poor ergonomics for diagnosis (since a local operator would be
21  before exceeding a level of 18 inches in the TB. A CW system flooding event would require the operators to enter AOP-13A, "Circulating Water System Malfunction.
required to identify the flood location).
Securing the CW pumps on a CW system flood event is Step 1 of the AOP. The SRAs used the SPAR-H method (per NUREG/CR-6883) to calculate a human error probability (HEP) for the failure of the operators to terminate a CW flood event. Using SPAR-H an  
Using an HEP value of 0.2 for the probability that the operators would secure the CW
HEP for the failure of the operators to secure the CW pumps before exceeding 18 inches  
pumps before exceeding 18 inches in the TB, and the probability of 2.63E-2 that the
level in the TB was calculated to be 0.2. This calculation assumed high stress for both  
jersey barriers would be installed, the result was a delta core damage frequency (CDF)
diagnosis and action and poor ergonomics for diagnosis (since a local operator would be  
of 2.56E-7/yr for an event involving a CW expansion joint failure in the turbine building.
required to identify the flood location).  
Circulating Water System Pipe Breaks
Using an HEP value of 0.2 for the probability that the operators would secure the CW  
To evaluate the CDF for CW system piping breaks, the length of large diameter CW
pumps before exceeding 18 inches in the TB, and the probability of 2.63E-2 that the  
piping in the TB (obtained from the Point Beach PRA 7.1, Internal Flooding Notebook)
jersey barriers would be installed, the result was a delta core damage frequency (CDF) of 2.56E-7/yr for an event involving a CW expansion joint failure in the turbine building.  
was used. For the CW piping random failure event, the frequency of a major flooding
Circulating Water System Pipe Breaks
event was conservatively estimated to be 7.95E-7/yr/ft, from the EPRI report. This is the
 
failure rate based on a flood rate of greater than 2000 gpm and was conservatively used
To evaluate the CDF for CW system piping breaks, the length of large diameter CW piping in the TB (obtained from the Point Beach PRA 7.1, Internal Flooding Notebook) was used. For the CW piping random failure event, the frequency of a major flooding  
to represent the failure rate of a flood greater than 20,000 gpm. Based on this piping
event was conservatively estimated to be 7.95E-7/yr/ft, from the EPRI report. This is the failure rate based on a flood rate of greater than 2000 gpm and was conservatively used  
failure rate per unit length and the lengths of CW piping obtained from the Point Beach
to represent the failure rate of a flood greater than 20,000 gpm. Based on this piping  
PRA 7.1, Internal Flooding Notebook, the frequency of a major flood event in the TB due
failure rate per unit length and the lengths of CW piping obtained from the Point Beach  
to a random CW pipe failure was evaluated to be 2.39E-5/yr. Using an HEP of 0.2
PRA 7.1, Internal Flooding Notebook, the frequency of a major flood event in the TB due to a random CW pipe failure was evaluated to be 2.39E-5/yr. Using an HEP of 0.2 (as described above) for the failure of the operators to secure the CW pumps before  
(as described above) for the failure of the operators to secure the CW pumps before
exceeding 18 inches level in the TB, and the probability of 2.63E-2 that the jersey  
exceeding 18 inches level in the TB, and the probability of 2.63E-2 that the jersey
barriers would be installed, the result was a CDF of 1.25E-7/yr. for an event involving a random CW system piping failure in the turbine building.  
barriers would be installed, the result was a CDF of 1.25E-7/yr. for an event involving a
Service Water System Pipe Breaks
random CW system piping failure in the turbine building.
 
Service Water System Pipe Breaks
To evaluate the CDF for SW system piping breaks, the length of large diameter (greater than 4 inches) SW piping in the TB was obtained from the Point Beach
To evaluate the CDF for SW system piping breaks, the length of large diameter
PRA 7.1, Internal Flooding Notebook. From the EPRI report, a failure rate of 3.57E-7/yr/ft. was obtained for SW piping with a diameter between 4 and 10 inches, and a failure rate of 6.44E-8/yr/ft. was obtained for SW piping with a diameter greater  
(greater than 4 inches) SW piping in the TB was obtained from the Point Beach
than 10 inches. The length of SW piping in the TB with a diameter between 4 and
PRA 7.1, Internal Flooding Notebook. From the EPRI report, a failure rate of
10 inches, and the length of SW piping in the TB with a diameter of greater than
3.57E-7/yr/ft. was obtained for SW piping with a diameter between 4 and 10 inches,
10 inches was obtained from the Point Beach PRA 7.1, Internal Flooding Notebook.   The piping failure rate for a major flood event in the EPRI report is based on a flood rate of greater than 2000 gpm. This failure rate was conservatively used to represent the  
and a failure rate of 6.44E-8/yr/ft. was obtained for SW piping with a diameter greater
failure rate of a flood greater than 20,000 gpm. Based on these piping failure rates per  
than 10 inches. The length of SW piping in the TB with a diameter between 4 and
unit length and the lengths of SW piping obtained from the Point Beach PRA 7.1,  
10 inches, and the length of SW piping in the TB with a diameter of greater than
Internal Flooding Notebook, the frequency of a flood event in the TB due to a random  
10 inches was obtained from the Point Beach PRA 7.1, Internal Flooding Notebook.
SW pipe failure was evaluated to be 4.40E-4/yr.  
The piping failure rate for a major flood event in the EPRI report is based on a flood rate
 
of greater than 2000 gpm. This failure rate was conservatively used to represent the
22  The pipe breaks of interest for the SW system were determined to be those between approximately 20,000 gpm and 27,000 gpm.  The lower value of 20,000 gpm is based as
failure rate of a flood greater than 20,000 gpm. Based on these piping failure rates per
stated before on the drainage capacity at the eight foot level.  The upper value of 27,000 gpm is based on the flow rate for three SW pumps at run-out flow per the Point Beach PRA 7.1, Internal Flooding Notebook.  Based on a maximum SW break of 27,000 gpm,
unit length and the lengths of SW piping obtained from the Point Beach PRA 7.1,
the maximum TB flood level would be approximately 14 inches.  This level would
Internal Flooding Notebook, the frequency of a flood event in the TB due to a random
correspond to the steady-state level at which the drainage capacity outside provided by
SW pipe failure was evaluated to be 4.40E-4/yr.
the gaps in the metal siding of the CWPH walkway and the storm drains near the CWPH would equal the assumed 27,000 gpm flood rate. The Point Beach Standardized Plant Analysis Risk (SPAR) model version 8.22 and Systems Analysis Programs for Hands on Integrated Reliability Evaluations version 8.0.9.0 software was used to obtain a delta Conditional Core Damage Probability
                                          21


(CCDP) for the event. A loss of service water (LOSW) initiating event was assumed. Using the licensee's evaluation of equipment that is lost as a function of level, all  
The pipe breaks of interest for the SW system were determined to be those between
 
approximately 20,000 gpm and 27,000 gpm. The lower value of 20,000 gpm is based as
equipment in the TB that would be submerged at or below 17 inches was assumed to fail to bound failure of equipment at 14 inches. The 1P53 Auxiliary Feedwater Pump was also assumed to fail as a surrogate to represent the loss of the power supply for the Unit 2 motor-driven AFW pump 2P53 during a Unit 2 flooding event because the SPAR model replicates Unit 1. The result was a CCDP of 1.68E-2. Based on the probability of 2.63E-2 that the jersey barriers would be installed, and the CCDP of 1.68E-2 for an event if the jersey barriers were installed, the result was a CDF of 1.94E-7/yr. for an event involving a random SW system piping failure in the turbine building.  
stated before on the drainage capacity at the eight foot level. The upper value of 27,000
gpm is based on the flow rate for three SW pumps at run-out flow per the Point Beach
PRA 7.1, Internal Flooding Notebook. Based on a maximum SW break of 27,000 gpm,
the maximum TB flood level would be approximately 14 inches. This level would
correspond to the steady-state level at which the drainage capacity outside provided by
the gaps in the metal siding of the CWPH walkway and the storm drains near the CWPH
would equal the assumed 27,000 gpm flood rate.
The Point Beach Standardized Plant Analysis Risk (SPAR) model version 8.22 and
Systems Analysis Programs for Hands on Integrated Reliability Evaluations version
8.0.9.0 software was used to obtain a delta Conditional Core Damage Probability
(CCDP) for the event. A loss of service water (LOSW) initiating event was assumed.
Using the licensees evaluation of equipment that is lost as a function of level, all
equipment in the TB that would be submerged at or below 17 inches was assumed to fail
to bound failure of equipment at 14 inches. The 1P53 Auxiliary Feedwater Pump was
also assumed to fail as a surrogate to represent the loss of the power supply for the
Unit 2 motor-driven AFW pump 2P53 during a Unit 2 flooding event because the SPAR
model replicates Unit 1. The result was a CCDP of 1.68E-2.
Based on the probability of 2.63E-2 that the jersey barriers would be installed, and the
CCDP of 1.68E-2 for an event if the jersey barriers were installed, the result was a
CDF of 1.94E-7/yr. for an event involving a random SW system piping failure in the
turbine building.
Total CDF for Internal Events
Total CDF for Internal Events
  The total CDF for internal events caused by random failures of piping and CW expansion joints is the sum of the individual delta risk values or 5.76E-7/yr.  
The total CDF for internal events caused by random failures of piping and CW
 
expansion joints is the sum of the individual delta risk values or 5.76E-7/yr.
External Event Risk Contribution
External Event Risk Contribution
  Since the resultant internal event CDF is greater than 1.0E-7/yr., an evaluation of external event contributions was obtained. Due to the nature of the performance  
Since the resultant internal event CDF is greater than 1.0E-7/yr., an evaluation of
deficiency, no fire-induced floods were credible. However, a seismic-induced flooding  
external event contributions was obtained. Due to the nature of the performance
event was considered. Using guidance from NRC's Risk Assessment Standardization  
deficiency, no fire-induced floods were credible. However, a seismic-induced flooding
Project (RASP) handbook, only the "Bin 2" seismic events were assumed to represent a  
event was considered. Using guidance from NRCs Risk Assessment Standardization
CDF. "Bin 2" was defined in the RASP handb
Project (RASP) handbook, only the Bin 2 seismic events were assumed to represent a
ook as seismic events with intensities greater than 0.3g, but less than 0.5g. Earthquakes of lesser severity are unlikely to result in large pipe failures and earthquakes of a larger magnitude could result in major  
CDF. Bin 2 was defined in the RASP handbook as seismic events with intensities
structural damage throughout the plant, which would not be representative of a  
greater than 0.3g, but less than 0.5g. Earthquakes of lesser severity are unlikely to
differential risk. The initiating event frequency of an earthquake in "Bin 2" for
result in large pipe failures and earthquakes of a larger magnitude could result in major
Point Beach was estimated to be 1.3E-5/yr. using Table 4A 1 of Section 4 of the RASP handbook.  
structural damage throughout the plant, which would not be representative of a
differential risk. The initiating event frequency of an earthquake in Bin 2 for
To estimate the seismic capacity of the CW piping and the CW EJs, an evaluation of the  
Point Beach was estimated to be 1.3E-5/yr. using Table 4A 1 of Section 4 of the RASP
seismic capacity for a similar Westinghouse plant was referenced. For this plant, it  
handbook.
stated that the CW piping and the CW EJs had high seismic capacity, and a flooding  
To estimate the seismic capacity of the CW piping and the CW EJs, an evaluation of the
assessment due to seismic concerns was screened from the assessment.  
seismic capacity for a similar Westinghouse plant was referenced. For this plant, it
 
stated that the CW piping and the CW EJs had high seismic capacity, and a flooding
23  For the SW piping in the TB, making the conservative assumption that the high confidence of low probability of failure (HCLPF) capacity for the SW piping is 0.3g, a
assessment due to seismic concerns was screened from the assessment.
failure probability of 3.9E-2 was obtained for the SW system.  It was conservatively assumed that every SW system piping failure resulted in the maximum flooding rate of 27,000 gpm.  Similar to the earlier evaluation of random SW piping failure due to internal
                                            22
events, the licensee's evaluation of equipment that is lost as a function of level was
used.  All equipment in the TB with a flood level of less than or equal to 17 inches was
assumed to fail.  The 1P53 Auxiliary Feedwater Pump was also assumed to fail as
discussed earlier.  A dual unit loss of offsite power (LOOP) initiating event was assumed to occur as a result of the seismic event, and it was conservatively assumed that the operators would fail to recover off-site power for at least 24 hours.  Also, the SW pumps
were assumed to fail-to-run.  The result was a CCDP of 0.37.  The CDF for a seismic event was estimated to be 1.84E-7/yr.


Total CDF For This Issue
For the SW piping in the TB, making the conservative assumption that the high
 
confidence of low probability of failure (HCLPF) capacity for the SW piping is 0.3g, a
The total CDF associated with the finding was obtained as the sum of the CDF for the internal events random failures of piping and CW expansion joints, and the CDF for a  
failure probability of 3.9E-2 was obtained for the SW system. It was conservatively
seismic event or 7.6E-7/yr. The dominant sequence was associated with a random CW system expansion joint failure in the TB that results in flooding that renders risk significant equipment unavailable.  
assumed that every SW system piping failure resulted in the maximum flooding rate of
 
27,000 gpm. Similar to the earlier evaluation of random SW piping failure due to internal
events, the licensees evaluation of equipment that is lost as a function of level was
used. All equipment in the TB with a flood level of less than or equal to 17 inches was
assumed to fail. The 1P53 Auxiliary Feedwater Pump was also assumed to fail as
discussed earlier. A dual unit loss of offsite power (LOOP) initiating event was assumed
to occur as a result of the seismic event, and it was conservatively assumed that the
operators would fail to recover off-site power for at least 24 hours. Also, the SW pumps
were assumed to fail-to-run. The result was a CCDP of 0.37. The CDF for a seismic
event was estimated to be 1.84E-7/yr.
Total CDF For This Issue
The total CDF associated with the finding was obtained as the sum of the CDF for the
internal events random failures of piping and CW expansion joints, and the CDF for a
seismic event or 7.6E-7/yr. The dominant sequence was associated with a random
CW system expansion joint failure in the TB that results in flooding that renders risk
significant equipment unavailable.
Large Early Release Frequency Risk Contribution
Large Early Release Frequency Risk Contribution
 
Since the total estimated change in core damage frequency was greater than 1.0E-7/yr.,
Since the total estimated change in core damage frequency was greater than 1.0E-7/yr., IMC 0609 Appendix H, "Containment Integrity Significance Determination Process" was used to determine the potential risk contribution due to large early release frequency  
IMC 0609 Appendix H, Containment Integrity Significance Determination Process was
(LERF). Point Beach is a 2-loop Westinghouse Pressurized Water Reactor (PWR) with  
used to determine the potential risk contribution due to large early release frequency
a large dry containment. Sequences important to LERF include steam generator tube  
(LERF). Point Beach is a 2-loop Westinghouse Pressurized Water Reactor (PWR) with
rupture events and inter-system loss-of-coolant-accident (LOCA) events. These were not the dominant core damage sequences for this finding.  
a large dry containment. Sequences important to LERF include steam generator tube
rupture events and inter-system loss-of-coolant-accident (LOCA) events. These were
Therefore, based on the detailed risk evaluation, the SRAs determined that the finding  
not the dominant core damage sequences for this finding.
was of very low safety significance (Green).  
Therefore, based on the detailed risk evaluation, the SRAs determined that the finding
 
was of very low safety significance (Green).
Enforcement: Title 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures,
Enforcement: Title 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," requires, in part, that "activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions,  
and Drawings," requires, in part, that activities affecting quality shall be prescribed by
procedures, or drawings.Contrary to this requirement, from January 19, 1996 until  
documented instructions, procedures, or drawings, of a type appropriate to the
November 25, 2013, the licensee failed to ensure that activities affecting quality were prescribed by documented procedures of a type appropriate to the circumstances to address external flooding as described in the FSAR. Specifically, PC 80 Part 7, "Lake  
circumstances and shall be accomplished in accordance with these instructions,
Water Level Determination" directed advanced installation of concrete barriers to protect  
procedures, or drawings. Contrary to this requirement, from January 19, 1996 until
against deep wave action from the lake, which introduced significant unrecognized  
November 25, 2013, the licensee failed to ensure that activities affecting quality were
blockages in the natural drainage path credited in the FSAR to protect against the  
prescribed by documented procedures of a type appropriate to the circumstances to
probable maximum precipitation and Turbine Building internal flooding event. Corrective actions for this issue included changing the procedure and FSAR to include actions to provide an additional flood relief path through the CWPH building and reliance on  
address external flooding as described in the FSAR. Specifically, PC 80 Part 7, Lake
internal flood relief dampers for the affected flooding events. Because the violation was
Water Level Determination directed advanced installation of concrete barriers to protect
24  of very low safety significance and was entered into the licensee's corrective action program (CR 01932698), this violation is being treated as an NCV, consistent with
against deep wave action from the lake, which introduced significant unrecognized
 
blockages in the natural drainage path credited in the FSAR to protect against the
Section 2.3.2 of the NRC Enforcement Policy.  (NCV 05000266/2014007-02; 05000301/2014007-02; Failure to Maintain External Flooding Procedure to Address
probable maximum precipitation and Turbine Building internal flooding event. Corrective
actions for this issue included changing the procedure and FSAR to include actions to
provide an additional flood relief path through the CWPH building and reliance on
internal flood relief dampers for the affected flooding events. Because the violation was
                                          23


All Possible CLB Floods)  
    of very low safety significance and was entered into the licensees corrective action
    program (CR 01932698), this violation is being treated as an NCV, consistent with
    Section 2.3.2 of the NRC Enforcement Policy. (NCV 05000266/2014007-02;
    05000301/2014007-02; Failure to Maintain External Flooding Procedure to Address
    All Possible CLB Floods)
(3) Failure to Perform a Required 10 CFR 50.59 Evaluation
    Introduction: The inspectors identified a finding of very low safety significance and
    associated Severity Level IV, non-citied violation, of 10 CFR 50.59(d)(1), Changes,
    tests and experiments, when, on November 25, 2013, the licensee failed to perform an
    evaluation against the criteria in 10 CFR 50.59(c)(2) for a change to procedure
    PC 80 Part 7 to include actions to maintain functionality of drainage paths during
    probable maximum precipitation and turbine building flooding events. Specifically,
    PC 80 Part 7, Lake Water Level Determination was changed to include actions to open
    the CWPH rollup doors to provide an additional drainage path while wave barriers were
    in place, without evaluating the viability of reliance on additional flood features not
    credited for external flooding in the CLB.
    Description: When developing the procedural actions to address the deficiency
    associated with the new wave barriers, the licensee failed to recognize that these
    actions were outside the CLB. Specifically, procedure PC 80 Part 7 was revised on
    November 25, 2013 to include direction to ENSURE Maintenance has raised the North
    and South CWPH Roll-up doors approximately two feet to provide flooding relief. These
    actions were directed to be performed in advance of the installation of the wave run-up
    barriers, to ensure that while the barriers were installed, an additional flow path would be
    created because the credited flow paths for the PMP external and turbine building
    internal flooding events would be blocked during this time.
    Final Safety Analysis Report Section 2.5 Hydrology regarding for the maximum
    precipitation flood event states, in part, that the topography of the site results in
    adequate natural drainage to remove this amount of water and limit ponding depth to
    prevent adversely affecting safety related equipment. Contrary to these statements, the
    newly created actions which were developed to compensate for the nonfunctional
    natural drainage paths during wave barrier installation required use of additional features
    not credited for external flooding events. Specifically, the actions included opening the
    CWPH roll-up doors and routing flood waters through the CWPH and relying on internal
    flood relief dampers to open and drain the water. The inspectors noted that the
    10 CFR 50.59 screening documentation for Revision 6 of PC 80 Part 7, the revision
    which added CWPH door actions to the procedure, did not include any discussion of the
    actions to open the CWPH doors to provide a flood water flow path. The inspectors
    observed that due to the licensees position that this action was in accordance with the
    CLB, licensee personnel failed to screen or evaluate these actions under the
    requirements of 10 CFR 50.59.
    The inspectors noted that as a result of the failure to evaluate these actions under
    10 CFR 50.59, the licensee failed to properly consider several factors associated with
    the newly created drainage path that should have been evaluated. Some of these
    factors included flood water flow rates through the open doors, the impact of debris and
    slush from the outdoors being carried into the CWPH room and clogging the flood relief
    dampers, the potential for substitution of unintended manual actions in place of passively
                                              24


(3) Failure to Perform a Required 10 CFR 50.59 Evaluation
credited actions in the CLB, the impact of the cold temperatures on the equipment in the
Introduction: The inspectors identified a finding of very low safety significance and associated Severity Level IV, non-citied violation, of 10 CFR 50.59(d)(1), "Changes,
rooms during the potentially extended periods of time during which the doors could be
tests and experiments," when, on November 25, 2013, the licensee failed to perform an evaluation against the criteria in 10 CFR 50.59(c)(2) for a change to procedure  PC 80 Part 7 to include actions to maintain functionality of drainage paths during
open, and security impacts.
probable maximum precipitation and turbine building flooding events. Specifically,
Analysis: The inspectors determined that the licensees failure to fully evaluate the
PC 80 Part 7, "Lake Water Level Determination" was changed to include actions to open
viability of newly created flooding drainage paths as required by 10 CFR 50.59(d)(1) was
the CWPH rollup doors to provide an additional drainage path while wave barriers were
a performance deficiency, because it was the result of the failure to meet the
in place, without evaluating the viability of reliance on additional flood features not credited for external flooding in the CLB.
requirements of 10 CFR 50.59; the cause was reasonably within the licensees ability to
foresee and correct; and it should have been prevented. The inspectors determined that
Description:  When developing the procedural actions to address the deficiency associated with the new wave barriers, the licensee failed to recognize that these
this finding has a cross-cutting aspect in the area of problem identification and
actions were outside the CLB. Specifically, procedure PC 80 Part 7 was revised on November 25, 2013 to include direction to "ENSURE Maintenance has raised the North and South CWPH Roll-up doors approximately two feet to provide flooding relief."  These
resolution, because the licensee failed to thoroughly evaluate issues to ensure that
actions were directed to be performed in advance of the installation of the wave run-up
resolutions address causes and extent of conditions commensurate with their safety
barriers, to ensure that while the barriers were installed, an additional flow path would be
significance (P.2). Specifically, the licensee failed to fully evaluate a deficiency found in
created because the credited flow paths for the PMP external and turbine building
PC 80 Part 7 associated with wave barriers blocking natural drainage paths, to ensure
internal flooding events would be blocked during this time.  
that the corrective actions adequately addressed the problem.
Final Safety Analysis Report Section 2.5 "Hydrology" regarding for the maximum
The performance deficiency was screened in accordance with the guidance of
precipitation flood event states, in part, that "the topography of the site results in  
lMC 0612, Appendix B, and determined to be more than minor because the finding was
adequate natural drainage to remove this amount of water and limit ponding depth to
associated with the Mitigating Systems Cornerstone attributes of Protection Against
prevent adversely affecting safety related equipment."  Contrary to these statements, the newly created actions which were developed to compensate for the nonfunctional natural drainage paths during wave barrier installation required use of additional features
External Factors (Flood Hazard) and Design Control, and adversely affected the
not credited for external flooding events. Specifically, the actions included opening the  
cornerstone objective to ensure the availability, reliability, and capability of systems that
CWPH roll-up doors and routing flood waters through the CWPH and relying on internal
respond to initiating events to prevent undesirable consequences (i.e. core damage).
flood relief dampers to open and drain the water.  The inspectors noted that the
Specifically, the licensee did not fully demonstrate that the availability, reliability, and
10 CFR 50.59 screening documentation for Revision 6 of PC 80 Part 7, the revision which added CWPH door actions to the procedure, did not include any discussion of the actions to open the CWPH doors to provide a flood water flow path.  The inspectors
capability of mitigating systems would be maintained during flooding events due to the
observed that due to the licensee's position that this action was in accordance with the  
sites failure to evaluate the viability of alternate flood drainage paths through the CWPH.
CLB, licensee personnel failed to screen or evaluate these actions under the  
The inspectors evaluated the finding using IMC 0609, Attachment 0609.04, Tables 2
and 3, and Appendix A. Based on a review of Appendix A, Exhibit 2, Item 4.B, the
inspectors determined that this issue screened as having very low safety significance
(Green).
Because this issue involved the failure to perform a written evaluation pursuant to
10 CFR 50.59, Changes, Tests, and Experiments, it, by definition, impacted the
regulatory process. As a result, the traditional enforcement process was determined to
be applicable. In determining the severity level of the traditional enforcement aspect of
the issue, the inspectors identified that Subsection d.2 of Section 6.1, Reactor
Operations, of the NRC Enforcement Policy lists a 10 CFR 50.59 violation that results in
conditions evaluated by the SDP as having very low safety significance as an example
of a Severity Level IV violation. Because the associated finding was determined to be of
very low safety significance, this issue was determined to represent a Severity Level IV
violation under the traditional enforcement process.
Enforcement: Title 10 CFR 50.59(d)(1) requires, in part, that the licensee shall maintain
records of changes in the facility, of changes in procedures, and of tests and
experiments made pursuant to paragraph (c) of this section. These records must
include a written evaluation which provides the bases for the determination that the
change, test, or experiment does not require a license amendment pursuant to
paragraph (c)(2) of this section. Title 10 CFR 50.59(c)(2) lists several examples and
states, in part, that a licensee shall obtain a license amendment pursuant to
10 CFR 50.90 prior to implementing a proposed change, test, or experiment if the
change, test, or experiment would meet the description of any of the listed examples.
                                            25


requirements of 10 CFR 50.59.
    Contrary to the above, on November 25, 2013, the licensee failed to perform an
The inspectors noted that as a result of the failure to evaluate these actions under 
    evaluation against the criteria in 10 CFR 50.59(c)(2) for a change to procedure
10 CFR 50.59, the licensee failed to properly consider several factors associated with
    PC 80 Part 7 to include actions to maintain functionality of drainage paths during
the newly created drainage path that should have been evaluated.  Some of these
    probable maximum precipitation and turbine building flooding events. Specifically,
factors included flood water flow rates through the open doors, the impact of debris and slush from the outdoors being carried into the CWPH room and clogging the flood relief dampers, the potential for substitution of unintended manual actions in place of passively 
    PC 80 Part 7, Lake Water Level Determination was changed to include actions to open
25  credited actions in the CLB, the impact of the cold temperatures on the equipment in the rooms during the potentially extended periods of time during which the doors could be
    the CWPH rollup doors to provide an additional drainage path while wave barriers were
open, and security impacts.
    in place, without evaluating the viability of reliance on additional flood features not
Analysis:  The inspectors determined that the licensee's failure to fully evaluate the viability of newly created flooding drainage paths as required by 10 CFR 50.59(d)(1) was
    credited for external flooding in the CLB. Corrective actions for this issue included
a performance deficiency, because it was the result of the failure to meet the
    actions to update the FSAR to describe the new flood paths, performing a 10 CFR 50.59
requirements of 10 CFR 50.59; the cause was reasonably within the licensee's ability to
    screening and 10 CFR 50.59 evaluation for the new drainage path which had put the site
foresee and correct; and it should have been prevented.  The inspectors determined that this finding has a cross-cutting aspect in the area of problem identification and resolution, because the licensee failed to thoroughly evaluate issues to ensure that
    outside of the CLB, revising a related functionality assessment, controlling external
resolutions address causes and extent of conditions commensurate with their safety
    flooding areas to ensure they are clear of debris, and creating a procedure to install
significance (P.2).  Specifically, the licensee failed to fully evaluate a deficiency found in PC 80 Part 7 associated with wave barriers blocking natural drainage paths, to ensure that the corrective actions adequately addressed the problem.
    curtains on the CWPH rollup doors during periods when they were required to be open.
    Because this violation was of very low safety significance and because the issue was
The performance deficiency was screened in accordance with the guidance of 
    entered into the licensees corrective action program (CR 01946330), this violation is
lMC 0612, Appendix B, and determined to be more than minor because the finding was
    being treated as a Severity Level IV NCV, consistent with Section 2.3.2 of the NRCs
associated with the Mitigating Systems Cornerstone attributes of Protection Against External Factors (Flood Hazard) and Design Control, and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that
    Enforcement Policy. (NCV 05000266/2014007-03; 05000301/2014007-03; Failure to
respond to initiating events to prevent undesirable consequences (i.e. core damage). 
    Perform a Required 10 CFR 50.59 Evaluation)
Specifically, the licensee did not fully demonstrate that the availability, reliability, and
    The associated finding for this issue was evaluated separately from the traditional
capability of mitigating systems would be maintained during flooding events due to the
    enforcement violation; and therefore, the finding is being assigned a separate Tracking
site's failure to evaluate the viability of alternate flood drainage paths through the CWPH.  The inspectors evaluated the finding using IMC 0609, Attachment 0609.04, Tables 2  and 3, and Appendix A.  Based on a review of Appendix A, Exhibit 2, Item 4.B, the
    Number. (FIN 05000266/2014007-04; 05000301/2014007-04; Failure to Perform a
inspectors determined that this issue screened as having very low safety significance (Green).
    Required 10 CFR 50.59 Evaluation)
Because this issue involved the failure to perform a written evaluation pursuant to  10 CFR 50.59, "Changes, Tests, and Experiments," it, by definition, impacted the
(4) Failure to Establish EFR Attributes to Assess the Effectiveness of Corrective Actions
regulatory process. As a result, the traditional enforcement process was determined to
    Introduction: The inspectors identified a finding of very low safety significance (Green)
be applicable.  In determining the severity level of the traditional enforcement aspect of
    and associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion V,
the issue, the inspectors identified that Subsection d.2 of Section 6.1, "Reactor
    Instructions, Procedures, and Drawings, for the failure to ensure the effectiveness
Operations," of the NRC Enforcement Policy lists a 10 CFR 50.59 violation that results in conditions evaluated by the SDP as having very low safety significance as an example of a Severity Level IV violation.  Because the associated finding was determined to be of
    review attributes for a significant condition adverse to quality would ensure the corrective
very low safety significance, this issue was determined to represent a Severity Level IV violation under the traditional enforcement process.
    actions would eliminate or reduce the recurrence rate.
Enforcement:  Title 10 CFR 50.59(d)(1) requires, in part, that "the licensee shall maintain records of changes in the facility, of changes in procedures, and of tests and
    Description: The licensee performed a common cause analysis (CCA) of the two White
experiments made pursuant to paragraph (c) of this section.  These records must include a written evaluation which provides the bases for the determination that the change, test, or experiment does not require a license amendment pursuant to
    findings documented in NRC Inspection Reports 05000266/2012-009 and 2013-012.
paragraph (c)(2) of this section."  Title 10 CFR 50.59(c)(2) lists several examples and
    The CCA was documented in CR 01896156. Each of the two white findings had a root
states, in part, that a licensee shall obtain a license amendment pursuant to 
    cause analysis (RCA) performed and the CCA determined whether common causes
10 CFR 50.90 prior to implementing a proposed change, test, or experiment if the
    from the RCAs existed. The licensee identified two CCAs. CCA 1 was Leadership has
change, test, or experiment would meet the description of any of the listed examples. 
    not consistently driven the organization to identify risk significant conditions and evaluate
26  Contrary to the above, on November 25, 2013, the licensee failed to perform an evaluation against the criteria in 10 CFR 50.59(c)(2) for a change to procedure
    those conditions to ensure timely resolution. CCA 2 was Several examples of technical
PC 80 Part 7 to include actions to maintain functionality of drainage paths during probable maximum precipitation and turbine building flooding events. Specifically, PC 80 Part 7, "Lake Water Level Determination" was changed to include actions to open  
    procedure quality issues have led to workers applying knowledge based decision making
the CWPH rollup doors to provide an additional drainage path while wave barriers were  
    during activities resulting in additional risk to the station.
in place, without evaluating the viability of reliance on additional flood features not  
    The CCA and the RCAs were performed in accordance with licensee procedure
credited for external flooding in the CLB. Corrective actions for this issue included  
    PI-AA-100-1005 and as required by this procedure the licensee also established an EFR
actions to update the FSAR to describe the new flood paths, performing a 10 CFR 50.59 screening and 10 CFR 50.59 evaluation for the new drainage path which had put the site outside of the CLB, revising a related functionality assessment, controlling external  
    plan. The purpose of the EFR was to outline the attributes needed to assess the
flooding areas to ensure they are clear of debris, and creating a procedure to install curtains on the CWPH rollup doors during periods when they were required to be open. Because this violation was of very low safety significance and because the issue was entered into the licensee's corrective action program (CR 01946330), this violation is  
    effectiveness of the corrective actions to prevent recurrence (CAPRs). The EFRs were
being treated as a Severity Level IV NCV, consistent with Section 2.3.2 of the NRC's
    not limited to just CAPRs but could also apply to corrective actions when necessary.
Enforcement Policy. (NCV 05000266/2014007-03; 05000301/2014007-03; Failure to Perform a Required 10 CFR 50.59 Evaluation)
                                                26
The associated finding for this issue was evaluated separately from the traditional enforcement violation; and therefore, the finding is being assigned a separate Tracking  


Number. (FIN 05000266/2014007-04; 05000301/2014007-04; Failure to Perform a  
The inspectors reviewed the EFRs established by the licensee for the two CCAs
Required 10 CFR 50.59 Evaluation)
identified in CR 01896156. The EFRs were to be performed six months following CAPR
(4) Failure to Establish EFR Attributes to Assess the Effectiveness of Corrective Actions
implementation. The inspectors noted that of the five success criteria established by the
 
licensee three of them relied entirely upon NRC feedback. Common Cause Analysis 1,
Introduction: The inspectors identified a finding of very low safety significance (Green) and associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," for the failure to ensure the effectiveness
criteria 1, required positive NRC Resident Inspector feedback regarding issue resolution
review attributes for a significant condition adverse to quality would ensure the corrective
and timeliness. Common Cause Analysis 1, criteria 2, required zero findings with a
actions would eliminate or reduce the recurrence rate.  
crosscutting aspect of H.1(a) [Decision Making - Systematic Process], and CCA 2,
criteria 1, required zero findings with a H.2(b) crosscutting aspect [training]. Discussions
with licensee personnel and a review of the CCA determined that use of H.2(b) was a
typographical error and that H.2(c) [Procedure Quality] was intended to be used.
The inspectors challenged the licensee regarding the use of NRC inspector findings as
one of the few measures of how effective their corrective actions had been implemented.
The inspectors were concerned with the use of performance measures that were not
under the licensees control, were informal, and had a zero tolerance.
The main focus of the inspectors concerns was that the licensee had originally failed to
identify the weakness and violations noted above and had not recognized the need to
correct them until the NRC observations. The inspector noted that this approach was
not proactive and that waiting to see if the NRC found any new items in the next six
months would neither demonstrate the problems had been corrected nor identify that
they had not been corrected. The inspectors concluded that the EFRs were not
effective.
Analysis: The inspectors determined that the licensees failure to establish EFR criteria
that would have identified whether the CAPRs had effectively resolved the conditions
was a performance deficiency warranting further review.
The inspectors determined that this finding was more than minor in accordance with
IMC 0612, Appendix B, because it was affected the Mitigating Systems Cornerstone
objective to ensure availability, reliability, and capability of systems that respond to
initiating events to prevent undesirable consequences.
The inspectors evaluated the finding using IMC 0609, Appendix A. The inspectors
determined the finding was of very low safety significance (Green) because the finding
was not a deficiency affecting the design or qualification of a mitigating structure, system
or component and did not result in a loss of operability or functionality. In addition, the
finding did not represent a loss of system or function, did not represent an actual loss of
function of a least a single train for longer than its technical specification allowed outage
time, and did not represent an actual loss of function of one or more nontechnical
specification trains of equipment designated as high safety-significance.
The finding had a cross cutting aspect in the area of problem identification and
resolution, specifically resolution, because licensee personnel failed to ensure the
corrective actions to prevent recurrence had effective attributes. (P.2)
Enforcement: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures,
and Drawings, requires, in part, that activities affecting quality be prescribed by
procedures of a type appropriate to the circumstances and shall be accomplished in
accordance with these procedures. Licensee procedure PI-AA-100-1005, Revision 8,
                                            27


Description:  The licensee performed a common cause analysis (CCA) of the two White
      Root Cause Analysis, had been written and established in accordance with
findings documented in NRC Inspection Reports 05000266/2012-009 and 2013-012.
      10 CFR Part 50, Appendix B, Criterion V.
The CCA was documented in CR 01896156Each of the two white findings had a root
      Step 4.11.2.B, of PI-AA-100-1005, required, in part, The effectiveness review plan
cause analysis (RCA) performed and the CCA determined whether common causes  
      outlines attributes to verify, responsibility and due dates. The attributes of effectiveness
from the RCAs existed. The licensee identified two CCAs. CCA 1 was "Leadership has
      are the critical elements from those improvements that will guarantee success.
not consistently driven the organization to identify risk significant conditions and evaluate those conditions to ensure timely resolution."  CCA 2 was "Several examples of technical procedure quality issues have led to workers applying knowledge based decision making
      Contrary to the above, on February 7, 2014, the NRC inspectors identified that some of
during activities resulting in additional risk to the station."
      the EFR attributes for CCA 1 and CCA 2, of CR 01896156 would not have assessed the
      critical elements of the CAPRs and thus the verification that the corrective actions were
      effective would not have been performed as required by PI-AA-100-1005.
      This violation is being treated as an NCV, consistent with Section 2.3.2 of the
      Enforcement Policy, because it was of very low safety significance (Green) and was
      entered into the CAP as CR 01938326. (NCV 05000266/2014007-05;
      05000301/2014007-05, Failure to Establish EFR Attributes to Assess the
      Effectiveness of Corrective Actions).
02.04 Independent Assessment of Extent of Condition and Extent of Cause
      As directed by IP 95002, the inspectors independently assessed the validity of the
      licensees conclusions regarding the extent of condition and extent of cause of the
      issues. The objective of this requirement was to independently sample performance, as
      necessary, within the key attributes of the cornerstones that were related to the subject
      issues and to provide assurance that the licensees evaluations regarding the extent of
      condition and extent of cause were sufficiently comprehensive. The extent of condition
      review differs from the extent of cause review in that the extent of condition review
      focuses on the actual condition and its existence in other places. The extent of cause
      review should focus more on the actual root causes (RC) of the condition and on the
      degree that these RCs have resulted in additional weaknesses.
  .1  Extent of Condition
  a. Inspection Scope
      The inspectors conducted an independent extent of condition review of the (1) White
      NOV for the Turbine Driven Auxiliary Feedwater Pump (TDAFWP) issue; (2) the White
      Flooding issue; and (3) and the Common Cause Evaluation of both issues. The
      inspectors review focused on the conditions identified in the primary root causes
      associated with the above issues.
      The inspectors interviewed station personnel, and reviewed program and process
      documentation, maintenance procedures, and corrective action documents. In addition,
      the inspectors conducted field walk downs of safety related equipment that involved
      possible alignment requirements such as pumps and motor-operated valves (MOVs).
      The inspectors looked for installation conditions that may challenge alignment of rotating
      equipment, as was the case with the TDAFWP. The inspectors also performed walk
      downs of plant areas that could be impacted by the wave run-up design basis flooding
      event. Walk down activities included evaluation of the locations where the wave run-up
      barriers would be constructed, and assessment of the physical flood barriers and sand
      bags that would be utilized to respond to a wave run-up event.
                                                  28


b. Assessment
The CCA and the RCAs were performed in accordance with licensee procedure  PI-AA-100-1005 and as required by this procedure the licensee also established an EFR plan. The purpose of the EFR was to outline the attributes needed to assess the
  The inspectors assessed the licensees extent of condition evaluation through their own
effectiveness of the corrective actions to prevent recurrence (CAPRs). The EFRs were
  independent extent of condition review. However, this assessment was only possible
not limited to just CAPRs but could also apply to corrective actions when necessary.  
  due to changes the licensee made to the initial extent of condition evaluation.
    
  Additionally, significant actions still remained to be defined by the licensee to determine
27  The inspectors reviewed the EFRs established by the licensee for the two CCAs identified in CR 01896156. The EFRs were to be performed six months following CAPR
  with high confidence their corrective actions would be effective.
implementation. The inspectors noted that of the five success criteria established by the licensee three of them relied entirely upon NRC feedback. Common Cause Analysis 1, criteria 1, required positive NRC Resident Inspector feedback regarding issue resolution
  TDAFWP White Finding
and timeliness. Common Cause Analysis 1, criteria 2, required zero findings with a  
  The licensee defined the condition in RCE 10768931, TDAFWP Coupling Degradation
crosscutting aspect of H.1(a) [Decision Making - Systematic Process], and CCA 2,  
  During IT 08 Run, as the 1 P-29 TDAFWP coupling degraded due to misalignment. The
criteria 1, required zero findings with a H.2(b) crosscutting aspect [training].  Discussions
   setup condition was the misalignment exceeded the coupling vendor's specification. The
with licensee personnel and a review of the CCA determined that use of H.2(b) was a
  same-same condition would be any other identical couplings on the 1P-29 TDAFWP,
typographical error and that H.2(c) [Procedure Quality] was intended to be used.  
  which there are none, and the coupling on the 2P-29 TDAFWP being misaligned. The
The inspectors challenged the licensee regarding the use of NRC inspector findings as one of the few measures of how effective their corrective actions had been implemented.
  same-similar condition would be other pumps with the same model coupling and have
The inspectors were concerned with the use of performance measures that were not under the licensee's control, were informal, and had a zero tolerance. The main focus of the inspectors' concerns was that the licensee had originally failed to identify the weakness and violations noted above and had not recognized the need to
  alignment problems. No other pumps at Point Beach used the Thomas 54 Size 262
  flexible disc coupling. The similar-similar condition would be other pumps that use
  Thomas flexible disc couplings and have alignment problems which identified seven
  other sets of pumps, the only safety related pumps being the containment spray pumps.
  The licensees CCA 1896156; Degraded Cornerstone - Mitigating Systems, Two
  White Findings, conducted an in-depth review of the AFW degraded coupling root
  cause analysis report and identified that the extent of condition performed under
  RCE 01768931 only considered what other equipment used Thomas Flexible disc
  couplings to ensure alignment criteria was specified in alignment procedures. The CCA
  concluded a more appropriate extent of condition would have considered all rotating
  equipment that has alignment criteria specified.
  As a result, the CCA initiated actions 26 through 29 to have the system engineers for all
  mitigating system pumps, review and revise assembly procedures to incorporate
  TDAFWP pump lessons learned. However, CCA action 15 was to expand the extent of
  condition assessment to include all rotating equipment that has alignment criteria
  specified. This action was not yet defined or started and therefore its scope or
  effectiveness could not be assessed.
  The inspectors independent extent of condition review considered all safety related
  rotating equipment where alignment may be needed to ensure expected operation and
  reliability. Therefore, the inspectors selected a sample of pumps and MOVs. The
  inspectors verified installation procedures for the pumps included in the action items
  mentioned above were changed appropriately.
  The inspectors performed a walk down of one set of Emergency Core Cooling Pumps
  and a variety of plant configurations of MOVs with system engineers and maintenance
  personnel. The inspectors did not identify any conditions that would challenge alignment
  of these components during installation. The inspectors found that alignment of MOVs
  was not required by vendor or licensee procedures as the MOVs should be inherently
  aligned through the valve yoke. If alignment issues were to result from installation, they
  were expected to be discovered through the as-left MOV testing. A small number of
  MOVs had attached supports. Condition Report 01938749 was initiated to evaluate the
                                              29


correct them until the NRC observations.  The inspector noted that this approach was
need to do MOV testing after installation of supports on MOVs to ensure installation of
 
the supports did not affect valve performance.
not proactive and that waiting to see if the NRC found any new items in the next six months would neither demonstrate the problems had been corrected nor identify that they had not been corrected.  The inspectors concluded that the EFRs were not
The inspectors reviewed a sample of the CAP and found the following condition reports
 
that contained concerns with equipment alignment. Condition Report 01216019
effective.
discussed cracking of a valve yoke in 1999 due to actions taken to alleviate a yoke
Analysis:  The inspectors determined that the licensee's failure to establish EFR criteria that would have identified whether the CAPRs had effectively resolved the conditions was a performance deficiency warranting further review.
alignment issue. Condition Report 01660763 discussed a large amount of pipe strain
 
when installing pump 2P-73B in 2011 (similar to the issue with the TDAFWP). Condition
Report 01202954 discussed alignment issues with 2P-11B where the base has to be cut.
The inspectors determined that this finding was more than minor in accordance with 
Condition Report 01879455 discussed alignment issues due to bearing housing fit-up.
IMC 0612, Appendix B, because it was affected the Mitigating Systems Cornerstone objective to ensure availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences.
Condition Report 01808901 discussed an alignment issue with the Emergency Diesel
 
Generator, G-01, circulation oil pump due to excessive pipe strain.
As discussed above, the licensees expanded extent of condition evaluation, CCA action
The inspectors evaluated the finding using IMC 0609, Appendix A.  The inspectors
item 15, to include all rotating equipment that requires alignment had not been further
determined the finding was of very low safety significance (Green) because the finding
defined, but based on the inspectors review of previous CAP issues and walk downs, the
was not a deficiency affecting the design or qualification of a mitigating structure, system or component and did not result in a loss of operability or functionality.  In addition, the finding did not represent a loss of system or function, did not represent an actual loss of
scope should include pumps, valves, fans, and diesels as a minimum. The evaluation
function of a least a single train for longer than its technical specification allowed outage
may conclude the condition does not exist in these components or that existing
time, and did not represent an actual loss of function of one or more nontechnical
processes adequately address alignment of the components.
specification trains of equipment designated as high safety-significance.
The inspectors concluded the extent of condition was initially too narrowly defined, which
The finding had a cross cutting aspect in the area of problem identification and
would not have been acceptable, but was subsequently expanded in the CCE. Based
resolution, specifically resolution, because licensee personnel failed to ensure the
on the walk downs, which did not identify challenges to alignment during installation, the
corrective actions to prevent recurrence had effective attributes.  (P.2)
actions taken to revise the installation procedures for the mitigating system pumps and
 
expanded action to evaluate additional rotating equipment, the inspectors assessed this
aspect of IP 95002 was met for the TDAFWP White finding.
Enforcement:  Title 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," requires, in part, that activities affecting quality be prescribed by procedures of a type appropriate to the circumstances and shall be accomplished in
accordance with these procedures.  Licensee procedure PI-AA-100-1005, Revision 8, 
28  "Root Cause Analysis," had been written and established in accordance with  10 CFR Part 50, Appendix B, Criterion V. Step 4.11.2.B, of PI-AA-100-1005, required, in part, "The effectiveness review plan outlines attributes to verify, responsibility and due dates.  The attributes of effectiveness are the critical elements from those improvements that will guarantee success." Contrary to the above, on February 7, 2014, the NRC inspectors identified that some of the EFR attributes for CCA 1 and CCA 2, of CR 01896156 would not have assessed the critical elements of the CAPRs and thus the verification that the corrective actions were
effective would not have been performed as required by PI-AA-100-1005. This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy, because it was of very low safety significance (Green) and was entered into the CAP as CR 01938326.  (NCV 05000266/2014007-05; 05000301/2014007-05, Failure to Establish EFR Attributes to Assess the Effectiveness of Corrective Actions).
02.04 Independent Assessment of Extent of Condition and Extent of Cause
  As directed by IP 95002, the inspectors independently assessed the validity of the
licensee's conclusions regarding the extent of condition and extent of cause of the issues.  The objective of this requirement was to independently sample performance, as necessary, within the key attributes of the cornerstones that were related to the subject
issues and to provide assurance that the licensee's evaluations regarding the extent of
condition and extent of cause were sufficiently comprehensive.  The extent of condition
 
review differs from the extent of cause revi
ew in that the extent of condition review focuses on the actual condition and its existence in other places.  The extent of cause review should focus more on the actual root causes (RC) of the condition and on the degree that these RCs have resulted in additional weaknesses. .1 Extent of Condition
a. Inspection Scope
The inspectors conducted an independent extent of condition review of the (1) White NOV for the Turbine Driven Auxiliary Feedwater Pump (TDAFWP) issue; (2) the White
Flooding issue; and (3) and the Common Cause Evaluation of both issues.  The
inspectors' review focused on the conditions identified in the primary root causes
associated with the above issues. The inspectors interviewed station personnel, and reviewed program and process documentation, maintenance procedures, and corrective action documents.  In addition,
the inspectors conducted field walk downs of safety related equipment that involved
possible alignment requirements such as pumps and motor-operated valves (MOVs). 
The inspectors looked for installation conditions that may challenge alignment of rotating equipment, as was the case with the TDAFWP.
  The inspectors also performed walk downs of plant areas that could be impacted by the wave run-up design basis flooding
event.  Walk down activities included evaluation of the locations where the wave run-up
barriers would be constructed, and assessment of the physical flood barriers and sand
bags that would be utilized to respond to a wave run-up event. 
29  b. Assessment
 
The inspectors assessed the licensee's extent of condition evaluation through their own independent extent of condition review.  However, this assessment was only possible due to changes the licensee made to the initial extent of condition evaluation.  Additionally, significant actions still remained to be defined by the licensee to determine
with high confidence their corrective actions would be effective.
 
TDAFWP White Finding
  The licensee defined the "condition" in RCE 10768931, TDAFWP Coupling Degradation
 
During IT 08 Run, as the 1 P-29 TDAFWP coupling degraded due to misalignment.  The
setup condition was the misalignment exceeded the coupling vendor's specification.  The
"same-same" condition would be any other identical couplings on the 1P-29 TDAFWP, which there are none, and the coupling on the 2P-29 TDAFWP being misaligned.  The "same-similar" condition would be other pumps with the same model coupling and have alignment problems.  No other pumps at Point Beach used the Thomas 54 Size 262
flexible disc coupling.  The "similar-similar" condition would be other pumps that use Thomas flexible disc couplings and have alignment problems which identified seven other sets of pumps, the only safety related pumps being the containment spray pumps.
The licensee's CCA 1896156; Degraded Cornerstone - Mitigating Systems, Two  White Findings, conducted an in-depth review of the AFW degraded coupling root 
cause analysis report and identified that the extent of condition performed under 
RCE 01768931 only considered what other equipment used Thomas Flexible disc couplings to ensure alignment criteria was specified in alignment procedures.  The CCA concluded a more appropriate extent of condition would have considered all rotating
equipment that has alignment criteria specified.
 
As a result, the CCA initiated actions 26 through 29 to have the system engineers for all mitigating system pumps, review and revise assembly procedures to incorporate TDAFWP pump lessons learned.  However, CCA action 15 was to expand the extent of
condition assessment to include all rotating
equipment that has alignment criteria specified.  This action was not yet defined or started and therefore its scope or
effectiveness could not be assessed.
 
The inspector's independent extent of condition review considered all safety related rotating equipment where alignment may be needed to ensure expected operation and
reliability.  Therefore, the inspectors selected a sample of pumps and MOVs.  The
inspectors verified installation procedures for the pumps included in the action items
 
mentioned above were changed appropriately.
The inspectors performed a walk down of one set of Emergency Core Cooling Pumps
and a variety of plant configurations of MOVs with system engineers and maintenance
personnel.  The inspectors did not identify any conditions that would challenge alignment of these components during installation.  The inspectors found that alignment of MOV's
was not required by vendor or licensee procedures as the MOVs should be inherently aligned through the valve yoke.  If alignment issues were to result from installation, they
were expected to be discovered through the as-left MOV testing.  A small number of MOVs had attached supports.  Condition Report 01938749 was initiated to evaluate the 
30  need to do MOV testing after installation of supports on MOVs to ensure installation of the supports did not affect valve performance.  
 
The inspectors reviewed a sample of the CAP and found the following condition reports that contained concerns with equipment alignment. Condition Report 01216019  
discussed cracking of a valve yoke in 1999 due to actions taken to alleviate a yoke  
 
alignment issue. Condition Report 01660763 discussed a large amount of pipe strain  
when installing pump 2P-73B in 2011 (similar to the issue with the TDAFWP). Condition Report 01202954 discussed alignment issues with 2P-11B where the base has to be cut. Condition Report 01879455 discussed alignment issues due to bearing housing fit-up. Condition Report 01808901 discussed an alignment issue with the Emergency Diesel  
Generator, G-01, circulation oil pump due to excessive pipe strain.  
 
As discussed above, the licensee's expanded extent of condition evaluation, CCA action item 15, to include "all rotating equipment that requires alignment" had not been further defined, but based on the inspectors review of previous CAP issues and walk downs, the  
scope should include pumps, valves, fans, and diesels as a minimum. The evaluation  
may conclude the condition does not exist in these components or that existing  
processes adequately address alignment of the components.  
The inspectors concluded the extent of condition was initially too narrowly defined, which  
would not have been acceptable, but was subsequently expanded in the CCE. Based  
on the walk downs, which did not identify challenges to alignment during installation, the  
actions taken to revise the installation procedures for the mitigating system pumps and  
expanded action to evaluate additional rotating equipment, the inspectors assessed this aspect of IP 95002 was met for the TDAFWP White finding.  
White Flooding Finding
 
The licensee described the condition for the White flooding finding as procedure  "PC 80 Part 7, did not prescribe adequate barriers to implement external flooding wave run-up protection features-."  The licensee's extent of condition addressed other
external flood protection measures as well as additional external hazard protection
measures and commitments.  The inspectors performed an independent extent of
condition by performing plant walk downs, interviewing personnel, reviewing corrective
action programs generated for site identified external flooding issues, and assessing selected plant procedures. During walk downs of the plant areas where flood barriers would be built, the inspectors questioned plant personnel regarding possible bypass mechanisms around the flood
protection features.  Specifically, the inspectors questioned whether storm drains outside
the CWPH that communicated directly with the lakeshore could present a wave barrier bypass hazard.  Licensee personnel stated they had only briefly considered these drains but had rejected them as a possible bypass path without performing an analysis or any
follow-up.  Following a request from the NRC inspectors for information regarding these
drain lines and the potential wave barrier bypass paths, the licensee performed an
engineering calculation to review the impacts.  The calculation determined that the drain
paths did not in fact represent a significant threat to having high lake water bypass the flood protection features.  The inspectors determined that the calculation was neither simple nor straightforward and should have been performed as part of the licensee's
extent of condition. 
31  During a review of the licensee's corrective action program the inspectors observed that licensee personnel had identified that the installation of the more robust flood protection barriers would introduce an unintended consequence of blocking the natural flow path of rain water and snow melt.  The licensee had identified this unintended consequence while performing Fukushima external threat calculations and not due to the extent of
condition review for the White flooding finding.  This issue represented a flaw in the
licensees' initial corrective action which was first put in place in March 2013 as an
immediate action to restore compliance.  Inspectors noted that this issue should have
been identified prior to installation and represented another missed opportunity to
identify for their extent of condition.
  Instead, the inspectors noted that this left the site in a position where they were still in discovery when the IP 95002 inspection team arrived
onsite. Inspectors also noted a corrective action document generated several months after completion of the RCE, and approximately one week prior to the inspection team's arrival onsite, regarding conflicting AOP procedures.  Specifically, the inspectors noted a
CR that stated the High Winds AOP was in conflict with the External Flooding AOP, in
that the former required CWPH roll up doors to be open and the latter required them to
be closed.  The inspectors observed that invoking both procedures at the same time
could easily be required depending on weather conditions.  The inspectors noted that this was another example of late discovery, which represented an additional missed opportunity for the licensee to have identified the issue during their RCE extent of
condition. The inspectors' review of external flooding procedures to ensure that the procedure was adequately corrected to ensure protection of equipment during a design basis flood
yielded several deficiencies.  These deficiencies are described in more detail in the findings section of the report.  Specifically, during the inspectors' review of PC 80 Part 7 and PBF-2124 the inspectors identified a number of issues resulting in the determination
that both procedures were flawed and would not have accomplished their intended
function. PC 80 Part 7 procedural deficiencies included error traps where steps can be performed out of sequence (i.e. barriers installed before CWPH doors open); failure to include CWPH doors in robust tag-out process to ensure their 'open' position was controlled;
and direction to install barriers at +0.5 ft. plant elevation, which was not early enough in
accordance with the licensee's timeline calculation.  PBF-2124 procedural inadequacies
included a note that allowed them to rely on last month's data for lake level if the current
month's data was not readily available, direction to install barriers at the incorrect threshold of +0.5 ft. plant elevation, and direction to install jersey barriers rather than the more robust barriers associated with the licensee's RCE corrective actions (reference to
the jersey barriers referred to the previous flooding strategy).  The inspectors identified that the same +0.5 ft. installation threshold error was made in the licensee's external
flooding abnormal procedure, AOP 13C. The licensee's extent of condition did not
extend to non-external event design basis items because as stated in the RCE "-separate and rigorous processes already in
place to ensure site documentation is up to date and accurate-for instance, AOPs are
reviewed (and validated) on a regular basis to ensure quality and accuracy of the
procedure."  Yet during the inspectors' review it was observed that procedure technical
quality was determined by the licensee to be a root cause for the TDAFWP White finding.  The inspectors also noted that it would have been appropriate for the licensee to more thoroughly evaluate the modification 10 CFR 50.59 process during their extent 
32  of condition review, due to the integral role that the inadequate 10 CFR 50.59 review played in the original performance deficiency.  This may have also been appropriate in
light of the licensee's failure to properly utilize the 10 CFR 50.59 process during development of the modification to correct the performance deficiency, as discussed in the findings section of this report. The team concluded that the requirements of IP 95002 for the extent of condition were not met for the flooding White finding. c. Findings
No findings were identified. .2  Extent of Cause
a. Inspection Scope
  TDAFWP The inspectors conducted an independent extent of cause reviewed based on the root and contributing causes identified by the licensee in RCE 10768931, TDAFWP Coupling
Degradation During IT 08 Run.  Licensee personnel identified the Root Cause as the
TDAFWP exhaust steam piping was not installed properly during original construction to eliminate stresses on the turbine per vendor recommendations resulting in cold piping
spring and coupling misalignment.  Contributing Cause 2 (CC2) was determined to be that as-found alignment data was classified as information-only, resulting in no
evaluation of out-of-tolerance conditions and the procedures lacked acceptance criteria. 
Contributing Cause 3 (CC3) was determined to be that the TDAFWP and turbine were
not aligned during original construction using vendor recommended dowels allowing subsequent movement of equipment. The inspectors determined that the root cause was narrowly focused and not a good candidate to perform an independent extent of cause.  In fact, most aspects of the root
cause were included in the extent of condition discussed above.  Instead the inspectors
selected CC2 and CC3 to perform the independent extent of cause.
The inspectors reviewed the licensee's extent of cause evaluations to assess whether
they were of sufficient breadth and depth to accurately capture the extent of the causes. 
The inspectors' independent extent of cause evaluation involved in-plant walk downs
and observation of work activities, interviews with station management and staff, reviews
of program implementing procedures, reviews of program monitoring and station improvement efforts, and comprehensive searches of the corrective action program.
White Flooding Finding
White Flooding Finding
 
The licensee described the condition for the White flooding finding as procedure
The inspectors performed an independent extent of cause based on the root and contributing causes in the licensee's RCE.  The inspectors focused their review on the licensee's two identified root causes, as well as the two contributing causes identified in
PC 80 Part 7, did not prescribe adequate barriers to implement external flooding wave
the RCE.  The root causes identified by the licensee included inadequate identification
run-up protection features. The licensees extent of condition addressed other
and understanding of the external flooding CLB (RC1), and inappropriate prioritization of
external flood protection measures as well as additional external hazard protection
flood protection deficiencies in the corrective action program based on
measures and commitments. The inspectors performed an independent extent of
conditional/immediate station risk perceptions (RC2). The contributing causes the licensee identified included a lack of clear supporting detail in station documents for 
condition by performing plant walk downs, interviewing personnel, reviewing corrective
33  external events combined with a lack of use and understanding of license basis (CC1), and a lack of formality and rigor regarding the station's follow-up and resolution of NRC
action programs generated for site identified external flooding issues, and assessing
concerns (CC2).  
selected plant procedures.
The inspectors reviewed the licensee's extent of cause evaluations to assess whether
During walk downs of the plant areas where flood barriers would be built, the inspectors
they were of sufficient breadth and depth to accurately capture the extent of the causes.
questioned plant personnel regarding possible bypass mechanisms around the flood
The inspectors interviewed licensee m
protection features. Specifically, the inspectors questioned whether storm drains outside
anagement and personnel, reviewed program and process documentation, performed plant walk downs, reviewed licensee program
the CWPH that communicated directly with the lakeshore could present a wave barrier
monitoring and improvement efforts, and
bypass hazard. Licensee personnel stated they had only briefly considered these drains
reviewed corrective action documents.
but had rejected them as a possible bypass path without performing an analysis or any
b. Assessment
follow-up. Following a request from the NRC inspectors for information regarding these
  TDAFWP  The inspectors determined that the extent of cause evaluations conducted by the licensee for the TDAFW issues were narrowly focused.  The extent of each cause
drain lines and the potential wave barrier bypass paths, the licensee performed an
evaluations conducted by the inspectors broadly considered other programs and  
engineering calculation to review the impacts. The calculation determined that the drain
components that may be affected by simila
paths did not in fact represent a significant threat to having high lake water bypass the
r causes.  The limited sampled performed by the inspectors did not identify significant issues to concluded the cause would be applicable in those areas.  Therefore, based on the actions taken so far, and with the additional actions entered into the licensee's corrective action program, overall, the inspectors concluded that Extent of Cause objectives of the 95002 inspection procedure
flood protection features. The inspectors determined that the calculation was neither
were met for the TDAFWP finding.  The inspectors noted a number of licensee actions
simple nor straightforward and should have been performed as part of the licensees
are yet to be defined or completed as discussed below. Specific results of the
extent of condition.
inspectors' review of the causes and program areas are discussed below.
                                          30
CC2:  RMP 9044-1 Identified As-Found Alignment Data as Information Only Resulting In No Evaluation of Out-of-Tolerance Conditions and Lacked Acceptance Criteria
 
The inspectors determined that the vibration monitoring and In-service Test (IST) procedures require reviews by appropriate departments, including operations and engineering. The procedures do not discuss information only data.  Personnel involved
with these programs stated all data taken was reviewed by engineering.  The review of
the corrective action program only identified the following issues.
 
Condition Report 019118667 described a condition found during review of the 1P-11A coupling setting. It was identified that the as found coupling gap was recorded as 0.046 inch.  The procedural requirement in RMP 9006-2A, required the gap to be 0.125 inches
per the OEM installation requirements for the Falk Model 1080T20 coupling.  A review of
the last performed pump work on 1P-11A in 2010 under WO 392829, which included
procedure RMP 9006-2A, recorded the coupling back of hub to back of hub dimension as 7.035 inches and did not record the actual gap, as the coupling was not removed.  The as found coupling back of hub to back of hub dimension under the current work was  
7.034 inches with a gap of 0.046.  Based on this information and that the coupling hubs
have not been replaced, the as found coupling appears to have been set incorrectly
since the coupling was last removed in 2007 under WO 188114.  
 
34  Another CR 01895229 stated that during the previous TDAFW Pump 95001, the NRC identified that routine maintenance procedures lack acceptance criteria.


During this review, some instances were found where as-found alignment data is now being evaluated.  The inspectors did not identify instances where vibration or IST data
During a review of the licensees corrective action program the inspectors observed that
 
licensee personnel had identified that the installation of the more robust flood protection
was not evaluated.
barriers would introduce an unintended consequence of blocking the natural flow path of
 
rain water and snow melt. The licensee had identified this unintended consequence
while performing Fukushima external threat calculations and not due to the extent of
The licensee's extent of cause evaluation for CC2 considered as-found Thomas Series
condition review for the White flooding finding. This issue represented a flaw in the
54 Size 262 coupling alignment data that was being treated as information-only.  It found this cause only applied to procedure RMP 9044-1 because the P-29 turbine-pump combination is the only equipment that utilizes the Thomas Series 54 Size 262 coupling. 
licensees initial corrective action which was first put in place in March 2013 as an
The licensee determined RMP 9044-1 needed to be revised to include acceptance
immediate action to restore compliance. Inspectors noted that this issue should have
criteria for the critical parameters of the Thomas Series 54 Size 262 coupling that could
been identified prior to installation and represented another missed opportunity to
affect operability, and included formal evaluation by engineering if any of these criteria are exceeded.  No other corrective actions were required.
identify for their extent of condition. Instead, the inspectors noted that this left the site in
a position where they were still in discovery when the IP 95002 inspection team arrived
The licensee evaluation also included other Thomas flexible disc pack coupling alignment data and determined as-found data that is not evaluated applied to
onsite.
procedures or work orders associated with the following equipment:
Inspectors also noted a corrective action document generated several months after
* P-028 Main Feedwater Pumps (Series 51 Size 450)
completion of the RCE, and approximately one week prior to the inspection teams
* P-007 Monitor Tank Pumps (Series DBZ-A Size 101)
arrival onsite, regarding conflicting AOP procedures. Specifically, the inspectors noted a
* P-014 Containment Spray Pumps (Series DBZ-A Size 101)
CR that stated the High Winds AOP was in conflict with the External Flooding AOP, in
* P-099 SGFP Seal Water Injection Pumps (Series DBZ-C Size 126)
that the former required CWPH roll up doors to be open and the latter required them to
* P-004 Boric Acid Transfer Pumps (Series DBZ-C Size 126)
be closed. The inspectors observed that invoking both procedures at the same time
* W-001 Containment Accident Recirculation Fans (375SN)
could easily be required depending on weather conditions. The inspectors noted that
* W-004 Containment Reactor Cavity Cooling Fans (Series AMR)
this was another example of late discovery, which represented an additional missed
The licensee action was to review the procedures or work orders for the above
opportunity for the licensee to have identified the issue during their RCE extent of
equipment and revise them as necessary to include acceptance criteria for the critical
condition.
 
The inspectors review of external flooding procedures to ensure that the procedure was
parameters.
adequately corrected to ensure protection of equipment during a design basis flood
 
yielded several deficiencies. These deficiencies are described in more detail in the
findings section of the report. Specifically, during the inspectors review of PC 80 Part 7
The inspectors found the licensee extent of condition to be narrowly focused on either the specific Thomas Series 54 Size 262 coupling or other Thomas flexible disc pack couplings and did not consider other alignment procedures or procedures and programs
and PBF-2124 the inspectors identified a number of issues resulting in the determination
where as-found or information-only date may be taken and not evaluated. However, the
that both procedures were flawed and would not have accomplished their intended
inspectors only found a few instances in the CAP where this weakness existed and
function.
therefore could not conclude the cause identified extended into other equipment and programs and therefore concluded this aspect requirements of IP 95002 was adequately met for CC2.
PC 80 Part 7 procedural deficiencies included error traps where steps can be performed
 
out of sequence (i.e. barriers installed before CWPH doors open); failure to include
CWPH doors in robust tag-out process to ensure their open position was controlled;
CC3:  1 P-29 Pump and Turbine Were Not Aligned During Original Installation Using Vendor Recommended Dowels Allowing Subsequent Movement of Equipment
and direction to install barriers at +0.5 ft. plant elevation, which was not early enough in
  Through review of a sample of vendor manuals, the inspectors did not identify any vendor guidance concerning alignment that should have been incorporated into licensee
accordance with the licensees timeline calculation. PBF-2124 procedural inadequacies
procedures.  However, there were some issues identified in the corrective action  
included a note that allowed them to rely on last months data for lake level if the current
program that the inspectors considered representative of CC3.
months data was not readily available, direction to install barriers at the incorrect
 
threshold of +0.5 ft. plant elevation, and direction to install jersey barriers rather than the
 
more robust barriers associated with the licensees RCE corrective actions (reference to
35  For instance, CR 01920659, dated November 14, 2013, found that the 1P-029 as-found alignment checks were outside the acceptance criteria of RMP 9044-1, Auxiliary
the jersey barriers referred to the previous flooding strategy). The inspectors identified
Feedwater Pump Terry Turbine Overhaul.  The acceptance criteria for horizontal alignment (offset) is -0.002 to 0.002 and, the as-found results were -0.0037 for horizontal alignment.  The as-found vertical alignment was satisfactory.  The 1P-029-T was
that the same +0.5 ft. installation threshold error was made in the licensees external
realigned per RMP 9044-1 as part of the contingency work plan.  Although the 2P-029
flooding abnormal procedure, AOP 13C.
was doweled in accordance with vendor manual instructions, there was no mention of
The licensees extent of condition did not extend to non-external event design basis
doweling in this procedure.
items because as stated in the RCE separate and rigorous processes already in
 
place to ensure site documentation is up to date and accuratefor instance, AOPs are
Condition Report 01217509 dated June 8, 2000, states the post maintenance test  (PMT) for WO 9925677 indicated a probable alignment problem with P-132.  Work 
reviewed (and validated) on a regular basis to ensure quality and accuracy of the
Order 9927144 was created to perform a "hot" alignment on P-132.  The term "hot"
procedure. Yet during the inspectors review it was observed that procedure technical
alignment is more commonly referred to in vendor manuals as a "final" alignment.  The
quality was determined by the licensee to be a root cause for the TDAFWP White
vendor manual for all Goulds 3196 pumps calls for an initial alignment to be performed when a pump is installed or reinstalled.  The manual then calls for a final alignment to be performed "after the unit has been run under actual operating conditions for a sufficient
finding. The inspectors also noted that it would have been appropriate for the licensee
length of time to bring the unit up to operating temperature."  The manual goes on to say
to more thoroughly evaluate the modification 10 CFR 50.59 process during their extent
that the final alignment should be checked after approximately one week of operation.  The manual also states that "the final alignment procedure......must be followed".  Based on the inspector's review, final alignments described in the Goulds pumps' manual are not performed at Point Beach Nuclear Plant.  These final alignments should be
                                            31
performed as they are specifically called for by the pump manufacturer.  Pump
misalignment could cause premature failure of critical pump parts such as bearings and  
seals.
Another CR 01195885, dated April 17, 2001, stated that oil analysis shows evidence of bearing wear for a safety injection pump motor. During alignment, the motor shaft was
apparently not at the mechanical center as recommended by the manufacturer.  It was
mis-positioned such that contact was made at the inboard bearing thrust face with the
coupling compressed.
The inspectors also identified current observations by oversight organizations that are
indicative of conflicts with vendor manual instructions.  Point Beach Daily Quality
Summary, dated October 16, 2012, discussed an observed activity for AF-00109, 
P-38A Auxiliary Feed Pump Discharge Check Valve Inspection.  It noted that the work
instructions were minimal and lacked warnings to avoid cocking the bonnet during disassembly and reassembly that were stated in the vendor technical manual (VTM). 
The scope in the WO instructions was written from the lift check valve's vendor technical manual and is different from what is listed in the Engineering technical basis. This
observation also indicates possible alignment issues with this check valve that supports the need to consider valves during evaluation of the extent of cause for CC2.
Another observation, Point Beach Daily Quality Summary for 2P-29 TDAFW Pump
Assembly, dated November 19, 2012, noted that CR 01824455, Functional Criteria Not
Met, was initiated by Maintenance for the failure of the inboard bearing clearance to
meet the functional criteria.  The System Engineer provided additional information to  CR 01824455 on November 17, 2012 stating that the functional criteria from preceding  Step 5.23.17 should have replaced the current criteria.  The system engineer initiated PCR 01825115 to put the correct criteria into the procedure.  In light of the alignment 
36  issues with this pump, the inspectors were concerned the licensee process did not account for the latest vendor guidance to be entered into the applicable procedures.  
After completion of the independent extent of cause for CC3, the inspectors reviewed the licensee's extent of cause for CC3.  The licensee justified not doing an extent of
cause on CC3 base on it being unique to the TDAFWPs.  Justification was based on the  
following:
"Since the piping misalignment issue has been resolved on 2P-29 and it is not experiencing the governor valve chugging problem, no extent of cause is required for this maintenance activity.  The Terry turbine and pump are
unique in design compared to other driven pumps or components.  Most
 
pumps and other pieces of equipment are driven with an electric motor.  In
the normal configuration, the pump is considered the fixed point due to being hard piped with suction and discharge pipe and is doweled once set.  The motor is moved as needed to obtain the required alignment tolerances
and is not doweled.  Moving the motor to obtain proper alignment is being
restrained by hold down bolts. Slight movement of the motor to
accomplish proper alignment is permitted since only the connection to the motor is the flexible power source conduit. For the AFW turbine and the pump, both are hard piped, which is a significant challenge during
alignment.  In addition, both the turbine and pump are to be doweled per
their respective vendor manuals, which is unique compared to other
rotating pieces of equipment.  This condition of no dowels has existed
since startup and is considered an original which included procedure RMP 9006-2A construction deficiency of which the cause will not be determined.  Therefore no extent of cause is justified for this."
 
With a relatively small sample the inspectors found issues that had been identified
previously by the licensee that indicated CC3 may extend to other equipment with vendor manual information.  Therefore, the inspectors concluded the licensee's extent of cause evaluation for CC3 was narrowly focused and may not capture other vendor
guidance into licensee procedures. Condition Report 1939217 was initiated for this
observation.  The recommended corrective action was to review a sample of vendor
recommendations contained in VTMs for safety related equipment to determine whether
there are broader issues associated with implementation of vendor recommendations.
While the inspectors determined the licensee's extent of cause evaluation was narrowly
focused, other than the doweling guidance, no instances were identified where vendor
guidance was not appropriately incorporated into licensee procedures.  Based on this
and the licensee action referenced above, the inspectors concluded the 95002 procedure requirements were satisfied.
White Flooding Finding
 
The inspectors determined that the extent of cause evaluations conducted by the
licensee for the External Flooding deficiencies were narrowly focused. Each of the inspectors' independent extent of cause evaluations broadly considered other programs, procedures, functional areas that may be affected by similar causes.  The limited sample
performed by the inspectors identified a few notable issues which are documented in
37  detail in the findings section of this report and the section below. Based on the actions taken so far, the inspectors concluded that Extent of Cause objectives of the 95002
inspection procedure were not met for the Flooding finding.  Areas of concern will be reviewed as part of a future inspection.  Specific results of the inspectors' review of the causes are discussed below.
 
RC1:  Inadequate Identification and Understanding of the External Flooding CLB
 
The inspectors reviewed the licensee's extent of cause evaluation for the first root cause identified, RC1.  Specifically, RC1 was identified as "less than adequate identification and understanding of the external flood protection design and licensing basis resulted in
loss of high lake level protection measures in 1996 when AOP 13B was cancelled."
Inspectors reviewed corrective action pr
ograms from the preceding 2-year period, external events program controls, and general procedures in the areas of High winds, Tornados, High Energy Line Breaks, Internal Flooding, and External Flooding, and walked down related plant areas to independently assess whether the licensee had
appropriately identified deficiencies in understanding and identification of the design and
license basis.  
 
No significant issues were identified.  However, inspectors noted examples described in the findings section of the report, where the licensee had failed to fully recognize impacts
of the wave run up barriers during the probable maximum precipitation (PMP) and
turbine building flooding event until the 95002 inspection team arrived onsite. The
inspectors noted that given the topography of the site and associated drainage
characteristics, this issue should have been more readily identified as part of the extent of condition and extent of cause evaluations.  
In addition, as noted in the findings section of this report, the licensee failed to recognize
that the conflict with the barriers resulted in a failure to comply with the CLB and the
need to open the CWPH roll-up doors constituted a compensatory action that needed to be reviewed in accordance with 10 CFR 50.59.  The inspectors noted that this issue was served as an example where licensee personnel still demonstrated a lack of understanding of the CLB, which served as evidence that the extent of cause for this
root cause have not been fully probed and deficiencies corrected.  
 
RC2:  Inappropriate Prioritization of Flood Protection Deficiencies in the Corrective Action Program Based on Conditional/Immediate Station Risk Perceptions
 
The inspectors reviewed the licensee's extent of cause evaluation for the second root
cause identified, RC2. Specifically, RC2 was identified as "the degraded function of high
lake level protection measures for wave run-up identified in the corrective action program were inappropriately prioritized based on conditional/immediate station risk perceptions rather than compliance with license commitments resulting in untimely
resolution of the issues."
 
During review of RC2, inspectors interviewed plant personnel to evaluate general
understanding of the flooding deficiencies, recognition of associated risks, and effectiveness of site communication campai
gns.  As previously noted, inspectors observed that broader issues with risk recognition may still exist, based on discussion
with site personnel. 
38  The inspectors assessed the extent of cause relative to the licensee's failure to characterize the wave barrier as nonfunctional and thus failed to properly prioritize 
fixing the deficient strategy due to the lack of risk recognition. The inspectors noted that of the 11 functionality assessments (FA) that the licensee sampled as part of their extent of cause, and including an additional FA, excluded from the licensee's sample because
the NRC had already found it deficient, half were found to be deficient in their
conclusions or logic.  The inspectors observed that no action was taken to correct these
deficiencies, as the CR written on the results of the review was closed to no action.  In
addition, no action was taken to learn from the results of the review, or probe these results more deeply due to reliance on some procedural changes being made to the FA process.
The inspectors noted that the site's focus on the perception that these deficient FA
conclusions were non-consequential had parallels to the White flooding finding root cause.  Specifically, the licensee had drawn the wrong FA conclusion, but plant personnel had determined that it did not matter as long as the correct action was
ultimately taken.  The inspectors observed that in the case of the original White Flooding
finding, site personnel had not properly addressed the deficiency even though there was
a belief that the correct action had been taken. The inspectors noted that the licensee would have been driven to correct the deficiency more promptly if the FA conclusion had been correctly classified as non-functional. This highlights the importance of drawing the
correct functionality conclusion.  The inspectors concluded that to ensure correction of
the deficiencies associated with these FAs, and as an extension, the root cause that
drove them to perform the functionality assessment sample, it may have been
appropriate to enact more robust corrective actions to arrest the trend.
The inspectors learned during the functionality assessment review, as documented in
CR 01924763, "FA errors & less than adequate corrective action program threshold," an
individual had discovered deficiencies in the conclusions of several FAs, and chose not
to write a CR because they felt that initiation of a new CR would constitute low value work.  The inspectors noted that this example served as a data point of an individual that may still be focused on what they believe is or is not significant, without looking at the  
bigger picture, and failing to write a CR to ensure that risks could be evaluated. 
Inadequate corrective action program threshold and risk recognition were common to the
flooding root cause and common cause evaluations. The inspectors questioned whether
this might be an indication that the workforce has not been fully reached by licensee communications focused on fixing licensee personnel's lack of risk recognition, and instilling them with the objective to prove that something is safe.  
 
The inspectors noted that in response to the CR 01924763, "less than adequate
corrective action program threshold" this CR was closed to no action, with a note that stated that coaching was provided.  Inspectors noted that without any review of the behavior documented in the CR, it would be difficult for the licensee to determine
whether this behavior was a single isolated incident, or more of a wide spread problem.
Inspectors noted that it may have been appropriate for the licensee to take action to
make this determination so that more robust corrective actions than coaching could be
 
taken, if necessary.
 
39  The inspectors also noted that because the extent of cause was not extended from the FA process to a similar process, the Operability Determination process, the licensee
missed an opportunity to implement robust corrective actions to address deficiencies in the operability determination process.  The inspectors noted that within the previous  2 years, there had been approximately five NRC findings associated with inadequate
operability determinations.  The licensee noted that they had adopted a new operability
determination process procedure in August of 2013, and had taken actions as a result of
an April 2013 Condition Evaluation to perform one-time trainings for Operations and
Engineering to improve operability determination process knowledge.  The inspectors noted that Condition Evaluations serve as lower level evaluations that do not generally probe deeply into issues, and may not reveal all aspects of a complex issue.  Inspectors also noted that actions to perform one-time trainings may not be robust enough to
ensure sustainable improvement.  The inspectors concluded that given the critically important function that operability evaluations serve, it may have been appropriate to enact more robust corrective actions to ensure improvement in this area.
CC1:  Lack of Clear Supporting Detail in Station Documents for External Events Combined with a Lack of Use and Understanding of License Basis
  The inspectors reviewed the licensee's extent of cause evaluation for the first contributing cause identified, CC1.  Specifically, CC1 was identified as "deficiency in having clear supporting detail in station documents for external events combined with a lack of use and understanding of license basis resulted in the FSAR requirements
 
remaining unmet."
 
Inspectors reviewed corrective action pr
ograms from the preceding 2-year period, external events program controls, and general procedures in the areas of High winds,
Tornados, High Energy Line Breaks, Internal Flooding, and External Flooding, and
walked down related plant areas to independently assess whether the licensee had
appropriately identified deficiencies in clear supporting detail in station documents associated with the license basis.
No significant issues were identified.  However, inspectors identified several deficiencies
with the licensee's failure to ensure clear supporting detail existed in station documents
associated with internal flooding.  Specifically, inspectors noted that although during a
design basis turbine building flooding event, the site was crediting tripping the circulating water pumps to mitigate the flood with a short specified amount of time, i.e. 34 minutes or less, the site failed to evaluate and control this action under the time critical operator
action procedure. In addition, inspectors noted that the site had chosen to credit failure
of the turbine building roll up door during the same internal flooding event.  Inspectors
identified that the site had failed to upgrade this door to an augmented quality classification, despite the fact that they had taken action to credit the door in the design basis to perform the safety related function of flood relief.
 
The inspectors also noted that reliance on the failure of the turbine building door for the
internal turbine building flooding event was not clearly articulated in changes the  
licensee made to the FSAR, in that the TDAFW pump rooms noted that the door was credited for flood relief, but the EDGs did not contain the same statement despite a similar reliance on the same door.  These issues were entered into the licensee's
corrective action program.  The inspectors determined that these issues could be related 
40  to CC1, in that station documents did not clearly define and control features that were credited to mitigate internal flooding scenarios.
 
CC2:  Lack of Formality and Rigor Regarding the Station's Follow-Up and Resolution of
NRC Concerns
 
The inspectors reviewed the licensee's extent of cause evaluation for the second
contributing cause identified, CC2.  Specifically, CC2 was identified as "station's rigor for follow up on NRC concerns lacks formality and as a result the CR written for the  1Q2012 URI was not validated for accuracy, nor contained the necessary action, thus contributing to the untimely resolution of potentially degraded flood protection
 
measures."
 
During review of CC2, inspectors identified that the licensee's extent of cause was
narrow, and should have focused more broadly.  Specifically, the licensee's evaluations focused only on improvements and deficiencies associated with the tracking and resolution of NRC concerns. The inspectors questioned whether the site should have
looked across the organizations at similar processes and interactions with other external stakeholders.  Specifically, the inspectors noted that tracking and resolution of nuclear oversight, corporate nuclear review boards, management review board, and independent site evaluations may have similarities to the NRC issue tracking and
resolution processes.  The inspectors noted that the site missed an opportunity to  
identify improvements in these processes.  The inspectors did not identify any instances
where the site had not appropriately tracked or resolved issues associated with these groups, but inspectors also recognized that deficiencies in these areas may not be readily identifiable due to the nature of these interactions.  
The inspectors concluded the 95002 procedure requirements for the flooding White
finding were not satisfied.


    of condition review, due to the integral role that the inadequate 10 CFR 50.59 review
    played in the original performance deficiency. This may have also been appropriate in
    light of the licensees failure to properly utilize the 10 CFR 50.59 process during
    development of the modification to correct the performance deficiency, as discussed in
    the findings section of this report.
    The team concluded that the requirements of IP 95002 for the extent of condition were
    not met for the flooding White finding.
  c. Findings
  c. Findings
No findings were identified 02.05 Safety Culture Consideration
    No findings were identified.
.2  Extent of Cause
  a. Inspection Scope
  a. Inspection Scope
As part of the current 95002 inspection, the inspectors independently confirmed that a
    TDAFWP
number of safety culture components that contributed to the risk significant issues that were the subject of this inspection were identified in the licensee's RCEs. The licensee's
    The inspectors conducted an independent extent of cause reviewed based on the root
root cause evaluations included a discussion of the applicable safety culture components described in Regulatory Issue Summary 2006-013, "Information on the  
    and contributing causes identified by the licensee in RCE 10768931, TDAFWP Coupling
Changes Made to the Reactor Oversight Process to More Fully Address Safety Culture," (ADAMS Accession No. ML061880341) as they applied to the violations and findings.
    Degradation During IT 08 Run. Licensee personnel identified the Root Cause as the
The licensee determined that weaknesses in decision making (conservative
    TDAFWP exhaust steam piping was not installed properly during original construction to
assumptions and systematic process), resources (procedures/work instructions), work practices (oversight), work control (planning), and the corrective action process  (low threshold and evaluations) were the most prevalent safety culture attributes.  The
    eliminate stresses on the turbine per vendor recommendations resulting in cold piping
licensee also included the results of a 2013 station nuclear safety culture self-
    spring and coupling misalignment. Contributing Cause 2 (CC2) was determined to be
assessment and employees concern program site "pulsing" surveys.  For each of the
    that as-found alignment data was classified as information-only, resulting in no
41  identified prevalent and contributing safety culture components, the inspectors confirmed that the licensee established corrective actions to address the issues. Assessment
    evaluation of out-of-tolerance conditions and the procedures lacked acceptance criteria.
 
    Contributing Cause 3 (CC3) was determined to be that the TDAFWP and turbine were
The inspection team independently confirmed a sample of other safety culture components which contributed to the issue(s) that were also identified in the root cause analysis. These additional safety culture components included weaknesses in the CAP
    not aligned during original construction using vendor recommended dowels allowing
and resources.  For each of the identified prevalent and contributing safety culture
    subsequent movement of equipment.
components, the inspection team confirmed that the licensee established appropriate
    The inspectors determined that the root cause was narrowly focused and not a good
corrective actions to address the issues. Some corrective actions are complete, but pending corrective actions and effectiveness of those actions has not been confirmed to a point where the NRC has confidence that the licensee's actions are sufficient to
    candidate to perform an independent extent of cause. In fact, most aspects of the root
address and correct the causes and issues.  During the course of interviews with
    cause were included in the extent of condition discussed above. Instead the inspectors
licensee personnel, the inspection team asked interviewees questions related to safety
    selected CC2 and CC3 to perform the independent extent of cause.
conscience work environment (SCWE) to determine if the licensee's staff were reluctant
    The inspectors reviewed the licensees extent of cause evaluations to assess whether
to raise safety concerns or if fear of retaliation existed for raising safety concerns.  The inspection team did not identify concerns related to SCWE.
    they were of sufficient breadth and depth to accurately capture the extent of the causes.
    The inspectors independent extent of cause evaluation involved in-plant walk downs
The inspection team confirmed that the licensee's root cause, extent of condition, and
    and observation of work activities, interviews with station management and staff, reviews
    of program implementing procedures, reviews of program monitoring and station
    improvement efforts, and comprehensive searches of the corrective action program.
    White Flooding Finding
    The inspectors performed an independent extent of cause based on the root and
    contributing causes in the licensees RCE. The inspectors focused their review on the
    licensees two identified root causes, as well as the two contributing causes identified in
    the RCE. The root causes identified by the licensee included inadequate identification
    and understanding of the external flooding CLB (RC1), and inappropriate prioritization of
    flood protection deficiencies in the corrective action program based on
    conditional/immediate station risk perceptions (RC2). The contributing causes the
    licensee identified included a lack of clear supporting detail in station documents for
                                                32


extent of cause evaluations appropriately considered the safety culture components as described in IMC 0305, Operating Reactor Assessment Program.  
  external events combined with a lack of use and understanding of license basis (CC1),
The inspectors observed that the previously cited example of a failure to initiate a CR, as
  and a lack of formality and rigor regarding the stations follow-up and resolution of NRC
described in CR 01924763, "FA errors & less than adequate CAP threshold," was an
  concerns (CC2).
important data point from a safety culture and CR initiation standpoint. This CR
  The inspectors reviewed the licensees extent of cause evaluations to assess whether
documented an individual's failure to write a CR to document deficiencies in the
  they were of sufficient breadth and depth to accurately capture the extent of the causes.
conclusions of several functionality assessments.  The inspectors noted that while the issue itself was just one data point, the licensee's failure to act to determine the extent to which those behaviors were prevalent onsite was an additional data point in the area of  
  The inspectors interviewed licensee management and personnel, reviewed program and
safety culture. The inspectors noted that the licensee had instead closed the CR to no
  process documentation, performed plant walk downs, reviewed licensee program
action, and noted that coaching had been provided. The inspectors determined that  
  monitoring and improvement efforts, and reviewed corrective action documents.
investigative actions may have been appropriate to assist in the licensee's assessment of whether their RCE corrective actions to improve CR initiation and risk recognition had adequately reached the working level staff. This may have especially been appropriate
b. Assessment
given the fact that similar inappropriate CAP threshold issues played a role in the  
  TDAFWP
common cause for the greater than green findings being evaluated during the 95002
  The inspectors determined that the extent of cause evaluations conducted by the
inspection.
  licensee for the TDAFW issues were narrowly focused. The extent of each cause
  evaluations conducted by the inspectors broadly considered other programs and
  components that may be affected by similar causes. The limited sampled performed by
  the inspectors did not identify significant issues to concluded the cause would be
  applicable in those areas. Therefore, based on the actions taken so far, and with the
  additional actions entered into the licensees corrective action program, overall, the
  inspectors concluded that Extent of Cause objectives of the 95002 inspection procedure
  were met for the TDAFWP finding. The inspectors noted a number of licensee actions
  are yet to be defined or completed as discussed below. Specific results of the
  inspectors review of the causes and program areas are discussed below.
  CC2: RMP 9044-1 Identified As-Found Alignment Data as Information Only Resulting In
  No Evaluation of Out-of-Tolerance Conditions and Lacked Acceptance Criteria
  The inspectors determined that the vibration monitoring and In-service Test (IST)
  procedures require reviews by appropriate departments, including operations and
  engineering. The procedures do not discuss information only data. Personnel involved
  with these programs stated all data taken was reviewed by engineering. The review of
  the corrective action program only identified the following issues.
  Condition Report 019118667 described a condition found during review of the 1P-11A
  coupling setting. It was identified that the as found coupling gap was recorded as 0.046
  inch. The procedural requirement in RMP 9006-2A, required the gap to be 0.125 inches
  per the OEM installation requirements for the Falk Model 1080T20 coupling. A review of
  the last performed pump work on 1P-11A in 2010 under WO 392829, which included
  procedure RMP 9006-2A, recorded the coupling back of hub to back of hub dimension
  as 7.035 inches and did not record the actual gap, as the coupling was not removed.
  The as found coupling back of hub to back of hub dimension under the current work was
  7.034 inches with a gap of 0.046. Based on this information and that the coupling hubs
  have not been replaced, the as found coupling appears to have been set incorrectly
  since the coupling was last removed in 2007 under WO 188114.
                                            33


Inspectors noted that the O.2a safety culture component may not have been adequately considered during the licensee's safety culture evaluation. Specifically, O.2a is focused on ensuring that appropriate training and knowledge transfer was in place to ensure
Another CR 01895229 stated that during the previous TDAFW Pump 95001, the NRC
technical competency of staff. The inspectors noted that the licensee marked this
identified that routine maintenance procedures lack acceptance criteria.
aspect as not applicable. The inspectors observed that this safety culture aspect may have played a role in the licensee's root cause associated with licensee staff's failure to understand the CLB.  Mainly, the inspectors noted that training and knowledge transfer
During this review, some instances were found where as-found alignment data is now
could have increased licensee personnel's understanding of the CLB. The inspectors
being evaluated. The inspectors did not identify instances where vibration or IST data
observed that at the least, this training and knowledge transfer could have prompted the
was not evaluated.
identification of vague requirements in the design basis or licensee staff's lack of full understanding of the CLB.  The inspectors noted that this could have driven resolution of questions on requirements. 
The licensees extent of cause evaluation for CC2 considered as-found Thomas Series
42  The inspectors noted that subject matter experts at the site who were charged with ownership and knowledge of the external flooding program and other functional areas,
54 Size 262 coupling alignment data that was being treated as information-only. It found
did not have any qualification cards or required subject matter trainings to ensure their competency. This remained unchanged after the finding.  The inspectors noted that corrective actions to provide general external events training and to develop a formal
this cause only applied to procedure RMP 9044-1 because the P-29 turbine-pump
external events program may have appropriately addressed concerns about subject matter experts training adequacy, as the procedure consolidated requirements into
combination is the only equipment that utilizes the Thomas Series 54 Size 262 coupling.
controlling program procedures.  However, the inspectors concluded that more
The licensee determined RMP 9044-1 needed to be revised to include acceptance
specialized training could have increased defense in depth in the training and knowledge
criteria for the critical parameters of the Thomas Series 54 Size 262 coupling that could
transfer areas. The inspectors concluded the 95002 procedure requirements were satisfied for the TDAFWP finding but not for the White flooding finding. b. Findings
affect operability, and included formal evaluation by engineering if any of these criteria
No findings were identified 02.06 Evaluation of IMC 0305 Criteria for Treatment of Old Design Issues
are exceeded. No other corrective actions were required.
  The licensee did not request credit for self-identification of an old design issue.  Consequently, the subject risk significant issues were not evaluated against the  IMC 0305 criteria for treatment of an old design issue. 4OA5 Other Activities
The licensee evaluation also included other Thomas flexible disc pack coupling
  The inspectors utilized other inspection procedures as part of the assessment of the licensee's performance.  The following inspection samples were completed as part of
alignment data and determined as-found data that is not evaluated applied to
this inspection.
procedures or work orders associated with the following equipment:
* 71111.01 - External Flooding - 1 sample
*      P-028 Main Feedwater Pumps (Series 51 Size 450)
* 71111.06 - Internal Flooding - 1 sample
*     P-007 Monitor Tank Pumps (Series DBZ-A Size 101)
* 71111.15 - Operability Evaluations - 1 sample
*     P-014 Containment Spray Pumps (Series DBZ-A Size 101)
* 71152 - Problem Identification and Reporting - Annual Follow-Up  of Selected Samples - 1 sample 4OA6  Management Meeting
*     P-099 SGFP Seal Water Injection Pumps (Series DBZ-C Size 126)
Exit Meeting Summary
*     P-004 Boric Acid Transfer Pumps (Series DBZ-C Size 126)
On March 6, 2014 , the inspectors presented the inspection results to Mr. E. McCartney, Site Vice President, and other members of the licensee staff. The licensee acknowledged the issues presented.  The inspectors confirmed that none of the potential report input discussed was considered proprietary. ATTACHMENT:  SUPPLEMENTAL INFORMATION
*      W-001 Containment Accident Recirculation Fans (375SN)
1  Attachment
*      W-004 Containment Reactor Cavity Cooling Fans (Series AMR)
SUPPLEMENTAL INFORMATION KEY POINTS OF CONTACT
The licensee action was to review the procedures or work orders for the above
Licensee E. McCartney, Site Vice President
equipment and revise them as necessary to include acceptance criteria for the critical
R. Wright, Plant General Manager
parameters.
R. Weber, Operations Director
The inspectors found the licensee extent of condition to be narrowly focused on either
M. Millen, Licensing Manager
the specific Thomas Series 54 Size 262 coupling or other Thomas flexible disc pack
K. Longston, Acting EP Manager
couplings and did not consider other alignment procedures or procedures and programs
J. Atkins, Systems Engineering Manager B. Beltz, Assistant Operations Manager
where as-found or information-only date may be taken and not evaluated. However, the
F. Hennessy, Performance Improvement Manager
inspectors only found a few instances in the CAP where this weakness existed and
J. Pruitt, Site Quality Manager
therefore could not conclude the cause identified extended into other equipment and
R. Welty, Radiation Protection Manager R. Harrsch, Engineering Director D. Lauterbur, Training Manger
programs and therefore concluded this aspect requirements of IP 95002 was adequately
P. Wild, Design Engineering Manager
met for CC2.
L. Christensen, Licensing Project Manager
CC3: 1 P-29 Pump and Turbine Were Not Aligned During Original Installation Using
B. Scherwinski, Engineering Analyst II T. Schneider, Licensing F. Huber, Projects Manager
Vendor Recommended Dowels Allowing Subsequent Movement of Equipment
Through review of a sample of vendor manuals, the inspectors did not identify any
vendor guidance concerning alignment that should have been incorporated into licensee
procedures. However, there were some issues identified in the corrective action
program that the inspectors considered representative of CC3.
                                          34


S. Cassidy, Communications Manager
For instance, CR 01920659, dated November 14, 2013, found that the 1P-029 as-found
C. Trezise, Director Special Projects
alignment checks were outside the acceptance criteria of RMP 9044-1, Auxiliary
M. Ley, Civil/Mechanical Engineering Supervisor
Feedwater Pump Terry Turbine Overhaul. The acceptance criteria for horizontal
T. Lesniak, Mechanical Maintenance Department Head M. Maertens, Business Operations Manager R. Clark, Licensing
alignment (offset) is -0.002 to 0.002 and, the as-found results were -0.0037 for horizontal
S. Ruesch, Employee Concerns Program Manager
alignment. The as-found vertical alignment was satisfactory. The 1P-029-T was
realigned per RMP 9044-1 as part of the contingency work plan. Although the 2P-029
was doweled in accordance with vendor manual instructions, there was no mention of
doweling in this procedure.
Condition Report 01217509 dated June 8, 2000, states the post maintenance test
(PMT) for WO 9925677 indicated a probable alignment problem with P-132. Work
Order 9927144 was created to perform a "hot" alignment on P-132. The term "hot"
alignment is more commonly referred to in vendor manuals as a "final" alignment. The
vendor manual for all Goulds 3196 pumps calls for an initial alignment to be performed
when a pump is installed or reinstalled. The manual then calls for a final alignment to be
performed "after the unit has been run under actual operating conditions for a sufficient
length of time to bring the unit up to operating temperature." The manual goes on to say
that the final alignment should be checked after approximately one week of operation.
The manual also states that "the final alignment procedure......must be followed". Based
on the inspectors review, final alignments described in the Goulds pumps' manual are
not performed at Point Beach Nuclear Plant. These final alignments should be
performed as they are specifically called for by the pump manufacturer. Pump
misalignment could cause premature failure of critical pump parts such as bearings and
seals.
Another CR 01195885, dated April 17, 2001, stated that oil analysis shows evidence of
bearing wear for a safety injection pump motor. During alignment, the motor shaft was
apparently not at the mechanical center as recommended by the manufacturer. It was
mis-positioned such that contact was made at the inboard bearing thrust face with the
coupling compressed.
The inspectors also identified current observations by oversight organizations that are
indicative of conflicts with vendor manual instructions. Point Beach Daily Quality
Summary, dated October 16, 2012, discussed an observed activity for AF-00109,
P-38A Auxiliary Feed Pump Discharge Check Valve Inspection. It noted that the work
instructions were minimal and lacked warnings to avoid cocking the bonnet during
disassembly and reassembly that were stated in the vendor technical manual (VTM).
The scope in the WO instructions was written from the lift check valves vendor technical
manual and is different from what is listed in the Engineering technical basis. This
observation also indicates possible alignment issues with this check valve that supports
the need to consider valves during evaluation of the extent of cause for CC2.
Another observation, Point Beach Daily Quality Summary for 2P-29 TDAFW Pump
Assembly, dated November 19, 2012, noted that CR 01824455, Functional Criteria Not
Met, was initiated by Maintenance for the failure of the inboard bearing clearance to
meet the functional criteria. The System Engineer provided additional information to
CR 01824455 on November 17, 2012 stating that the functional criteria from preceding
Step 5.23.17 should have replaced the current criteria. The system engineer initiated
PCR 01825115 to put the correct criteria into the procedure. In light of the alignment
                                          35


J. Petro, Licensing Director
issues with this pump, the inspectors were concerned the licensee process did not
A. Gustafson, Training K. Locke, Licensing
account for the latest vendor guidance to be entered into the applicable procedures.
Nuclear Regulatory Commission
After completion of the independent extent of cause for CC3, the inspectors reviewed
A. Boland, Director, Division of Reactor Projects J. Cameron, Chief, Branch 4, Division of Reactor Projects
the licensees extent of cause for CC3. The licensee justified not doing an extent of
K. Barclay, Acting Senior Resident Inspector Point Beach
cause on CC3 base on it being unique to the TDAFWPs. Justification was based on the
R. Elliott, Acting Resident Inspector Point Beach
following:
      Since the piping misalignment issue has been resolved on 2P-29 and it is
      not experiencing the governor valve chugging problem, no extent of cause
      is required for this maintenance activity. The Terry turbine and pump are
      unique in design compared to other driven pumps or components. Most
      pumps and other pieces of equipment are driven with an electric motor. In
      the normal configuration, the pump is considered the fixed point due to
      being hard piped with suction and discharge pipe and is doweled once set.
      The motor is moved as needed to obtain the required alignment tolerances
      and is not doweled. Moving the motor to obtain proper alignment is being
      restrained by hold down bolts. Slight movement of the motor to
      accomplish proper alignment is permitted since only the connection to the
      motor is the flexible power source conduit. For the AFW turbine and the
      pump, both are hard piped, which is a significant challenge during
      alignment. In addition, both the turbine and pump are to be doweled per
      their respective vendor manuals, which is unique compared to other
      rotating pieces of equipment. This condition of no dowels has existed
      since startup and is considered an original which included procedure RMP
      9006-2A construction deficiency of which the cause will not be determined.
      Therefore no extent of cause is justified for this.
With a relatively small sample the inspectors found issues that had been identified
previously by the licensee that indicated CC3 may extend to other equipment with
vendor manual information. Therefore, the inspectors concluded the licensees extent of
cause evaluation for CC3 was narrowly focused and may not capture other vendor
guidance into licensee procedures. Condition Report 1939217 was initiated for this
observation. The recommended corrective action was to review a sample of vendor
recommendations contained in VTMs for safety related equipment to determine whether
there are broader issues associated with implementation of vendor recommendations.
While the inspectors determined the licensees extent of cause evaluation was narrowly
focused, other than the doweling guidance, no instances were identified where vendor
guidance was not appropriately incorporated into licensee procedures. Based on this
and the licensee action referenced above, the inspectors concluded the 95002
procedure requirements were satisfied.
White Flooding Finding
The inspectors determined that the extent of cause evaluations conducted by the
licensee for the External Flooding deficiencies were narrowly focused. Each of the
inspectors independent extent of cause evaluations broadly considered other programs,
procedures, functional areas that may be affected by similar causes. The limited sample
performed by the inspectors identified a few notable issues which are documented in
                                          36


 
detail in the findings section of this report and the section below. Based on the actions
  2 LIST OF ITEMS OPENED, CLOSED AND DISCUSSED
taken so far, the inspectors concluded that Extent of Cause objectives of the 95002
Opened  05000266/2014007-01
inspection procedure were not met for the Flooding finding. Areas of concern will be
05000301/2014007-01 NCV Failure to Take Corrective Actions to Address External Flooding Procedure Deficiencies
reviewed as part of a future inspection. Specific results of the inspectors review of the
05000266/2014007-02
causes are discussed below.
RC1: Inadequate Identification and Understanding of the External Flooding CLB
The inspectors reviewed the licensees extent of cause evaluation for the first root cause
identified, RC1. Specifically, RC1 was identified as less than adequate identification
and understanding of the external flood protection design and licensing basis resulted in
loss of high lake level protection measures in 1996 when AOP 13B was cancelled.
Inspectors reviewed corrective action programs from the preceding 2-year period,
external events program controls, and general procedures in the areas of High winds,
Tornados, High Energy Line Breaks, Internal Flooding, and External Flooding, and
walked down related plant areas to independently assess whether the licensee had
appropriately identified deficiencies in understanding and identification of the design and
license basis.
No significant issues were identified. However, inspectors noted examples described in
the findings section of the report, where the licensee had failed to fully recognize impacts
of the wave run up barriers during the probable maximum precipitation (PMP) and
turbine building flooding event until the 95002 inspection team arrived onsite. The
inspectors noted that given the topography of the site and associated drainage
characteristics, this issue should have been more readily identified as part of the extent
of condition and extent of cause evaluations.
In addition, as noted in the findings section of this report, the licensee failed to recognize
that the conflict with the barriers resulted in a failure to comply with the CLB and the
need to open the CWPH roll-up doors constituted a compensatory action that needed to
be reviewed in accordance with 10 CFR 50.59. The inspectors noted that this issue was
served as an example where licensee personnel still demonstrated a lack of
understanding of the CLB, which served as evidence that the extent of cause for this
root cause have not been fully probed and deficiencies corrected.
RC2: Inappropriate Prioritization of Flood Protection Deficiencies in the Corrective
Action Program Based on Conditional/Immediate Station Risk Perceptions
The inspectors reviewed the licensees extent of cause evaluation for the second root
cause identified, RC2. Specifically, RC2 was identified as the degraded function of high
lake level protection measures for wave run-up identified in the corrective action
program were inappropriately prioritized based on conditional/immediate station risk
perceptions rather than compliance with license commitments resulting in untimely
resolution of the issues.
During review of RC2, inspectors interviewed plant personnel to evaluate general
understanding of the flooding deficiencies, recognition of associated risks, and
effectiveness of site communication campaigns. As previously noted, inspectors
observed that broader issues with risk recognition may still exist, based on discussion
with site personnel.
                                          37


05000301/2014007-02 NCV Failure to Maintain External Flooding Procedure to Address All Possible CLB Floods
The inspectors assessed the extent of cause relative to the licensees failure to
05000266/2014007-03
characterize the wave barrier as nonfunctional and thus failed to properly prioritize
fixing the deficient strategy due to the lack of risk recognition. The inspectors noted that
of the 11 functionality assessments (FA) that the licensee sampled as part of their extent
of cause, and including an additional FA, excluded from the licensees sample because
the NRC had already found it deficient, half were found to be deficient in their
conclusions or logic. The inspectors observed that no action was taken to correct these
deficiencies, as the CR written on the results of the review was closed to no action. In
addition, no action was taken to learn from the results of the review, or probe these
results more deeply due to reliance on some procedural changes being made to the FA
process.
The inspectors noted that the sites focus on the perception that these deficient FA
conclusions were non-consequential had parallels to the White flooding finding root
cause. Specifically, the licensee had drawn the wrong FA conclusion, but plant
personnel had determined that it did not matter as long as the correct action was
ultimately taken. The inspectors observed that in the case of the original White Flooding
finding, site personnel had not properly addressed the deficiency even though there was
a belief that the correct action had been taken. The inspectors noted that the licensee
would have been driven to correct the deficiency more promptly if the FA conclusion had
been correctly classified as non-functional. This highlights the importance of drawing the
correct functionality conclusion. The inspectors concluded that to ensure correction of
the deficiencies associated with these FAs, and as an extension, the root cause that
drove them to perform the functionality assessment sample, it may have been
appropriate to enact more robust corrective actions to arrest the trend.
The inspectors learned during the functionality assessment review, as documented in
CR 01924763, FA errors & less than adequate corrective action program threshold, an
individual had discovered deficiencies in the conclusions of several FAs, and chose not
to write a CR because they felt that initiation of a new CR would constitute low value
work. The inspectors noted that this example served as a data point of an individual that
may still be focused on what they believe is or is not significant, without looking at the
bigger picture, and failing to write a CR to ensure that risks could be evaluated.
Inadequate corrective action program threshold and risk recognition were common to the
flooding root cause and common cause evaluations. The inspectors questioned whether
this might be an indication that the workforce has not been fully reached by licensee
communications focused on fixing licensee personnels lack of risk recognition, and
instilling them with the objective to prove that something is safe.
The inspectors noted that in response to the CR 01924763, less than adequate
corrective action program threshold this CR was closed to no action, with a note that
stated that coaching was provided. Inspectors noted that without any review of the
behavior documented in the CR, it would be difficult for the licensee to determine
whether this behavior was a single isolated incident, or more of a wide spread problem.
Inspectors noted that it may have been appropriate for the licensee to take action to
make this determination so that more robust corrective actions than coaching could be
taken, if necessary.
                                          38


05000301/2014007-03 NOV Failure to Perform a Required 10 CFR Part 50.59
The inspectors also noted that because the extent of cause was not extended from the
Evaluation
FA process to a similar process, the Operability Determination process, the licensee
05000266/2014007-04
missed an opportunity to implement robust corrective actions to address deficiencies in
the operability determination process. The inspectors noted that within the previous
2 years, there had been approximately five NRC findings associated with inadequate
operability determinations. The licensee noted that they had adopted a new operability
determination process procedure in August of 2013, and had taken actions as a result of
an April 2013 Condition Evaluation to perform one-time trainings for Operations and
Engineering to improve operability determination process knowledge. The inspectors
noted that Condition Evaluations serve as lower level evaluations that do not generally
probe deeply into issues, and may not reveal all aspects of a complex issue. Inspectors
also noted that actions to perform one-time trainings may not be robust enough to
ensure sustainable improvement. The inspectors concluded that given the critically
important function that operability evaluations serve, it may have been appropriate to
enact more robust corrective actions to ensure improvement in this area.
CC1: Lack of Clear Supporting Detail in Station Documents for External Events
Combined with a Lack of Use and Understanding of License Basis
The inspectors reviewed the licensees extent of cause evaluation for the first
contributing cause identified, CC1. Specifically, CC1 was identified as deficiency in
having clear supporting detail in station documents for external events combined with a
lack of use and understanding of license basis resulted in the FSAR requirements
remaining unmet.
Inspectors reviewed corrective action programs from the preceding 2-year period,
external events program controls, and general procedures in the areas of High winds,
Tornados, High Energy Line Breaks, Internal Flooding, and External Flooding, and
walked down related plant areas to independently assess whether the licensee had
appropriately identified deficiencies in clear supporting detail in station documents
associated with the license basis.
No significant issues were identified. However, inspectors identified several deficiencies
with the licensees failure to ensure clear supporting detail existed in station documents
associated with internal flooding. Specifically, inspectors noted that although during a
design basis turbine building flooding event, the site was crediting tripping the circulating
water pumps to mitigate the flood with a short specified amount of time, i.e. 34 minutes
or less, the site failed to evaluate and control this action under the time critical operator
action procedure. In addition, inspectors noted that the site had chosen to credit failure
of the turbine building roll up door during the same internal flooding event. Inspectors
identified that the site had failed to upgrade this door to an augmented quality
classification, despite the fact that they had taken action to credit the door in the design
basis to perform the safety related function of flood relief.
The inspectors also noted that reliance on the failure of the turbine building door for the
internal turbine building flooding event was not clearly articulated in changes the
licensee made to the FSAR, in that the TDAFW pump rooms noted that the door was
credited for flood relief, but the EDGs did not contain the same statement despite a
similar reliance on the same door. These issues were entered into the licensees
corrective action program. The inspectors determined that these issues could be related
                                          39


05000301/2014007-04 FIN Failure to Perform a Required 10 CFR Part 50.59
      to CC1, in that station documents did not clearly define and control features that were
Evaluation
      credited to mitigate internal flooding scenarios.
05000266/2014007-05
      CC2: Lack of Formality and Rigor Regarding the Stations Follow-Up and Resolution of
      NRC Concerns
      The inspectors reviewed the licensees extent of cause evaluation for the second
      contributing cause identified, CC2. Specifically, CC2 was identified as stations rigor for
      follow up on NRC concerns lacks formality and as a result the CR written for the
      1Q2012 URI was not validated for accuracy, nor contained the necessary action, thus
      contributing to the untimely resolution of potentially degraded flood protection
      measures.
      During review of CC2, inspectors identified that the licensees extent of cause was
      narrow, and should have focused more broadly. Specifically, the licensees evaluations
      focused only on improvements and deficiencies associated with the tracking and
      resolution of NRC concerns. The inspectors questioned whether the site should have
      looked across the organizations at similar processes and interactions with other external
      stakeholders. Specifically, the inspectors noted that tracking and resolution of nuclear
      oversight, corporate nuclear review boards, management review board, and
      independent site evaluations may have similarities to the NRC issue tracking and
      resolution processes. The inspectors noted that the site missed an opportunity to
      identify improvements in these processes. The inspectors did not identify any instances
      where the site had not appropriately tracked or resolved issues associated with these
      groups, but inspectors also recognized that deficiencies in these areas may not be
      readily identifiable due to the nature of these interactions.
      The inspectors concluded the 95002 procedure requirements for the flooding White
      finding were not satisfied.
  c.  Findings
      No findings were identified
02.05 Safety Culture Consideration
  a. Inspection Scope
      As part of the current 95002 inspection, the inspectors independently confirmed that a
      number of safety culture components that contributed to the risk significant issues that
      were the subject of this inspection were identified in the licensees RCEs. The licensees
      root cause evaluations included a discussion of the applicable safety culture
      components described in Regulatory Issue Summary 2006-013, Information on the
      Changes Made to the Reactor Oversight Process to More Fully Address Safety Culture,
      (ADAMS Accession No. ML061880341) as they applied to the violations and findings.
      The licensee determined that weaknesses in decision making (conservative
      assumptions and systematic process), resources (procedures/work instructions), work
      practices (oversight), work control (planning), and the corrective action process
      (low threshold and evaluations) were the most prevalent safety culture attributes. The
      licensee also included the results of a 2013 station nuclear safety culture self-
      assessment and employees concern program site pulsing surveys. For each of the
                                                40


05000301/2014007-05 NCV Failure to Establish EFR Attributes to Assess the  
identified prevalent and contributing safety culture components, the inspectors confirmed
Effectiveness of Corrective Actions
that the licensee established corrective actions to address the issues.
Assessment
Closed  05000266/2014007-01
The inspection team independently confirmed a sample of other safety culture
05000301/2014007-01 NCV Failure to Take Corrective Actions to Address External Flooding Procedure Deficiencies
components which contributed to the issue(s) that were also identified in the root cause
05000266/2014007-02
analysis. These additional safety culture components included weaknesses in the CAP
05000301/2014007-02 NCV Failure to Maintain External Flooding Procedure to Address All Possible CLB Floods
and resources. For each of the identified prevalent and contributing safety culture
05000266/2014007-03
components, the inspection team confirmed that the licensee established appropriate
corrective actions to address the issues. Some corrective actions are complete, but
pending corrective actions and effectiveness of those actions has not been confirmed to
a point where the NRC has confidence that the licensees actions are sufficient to
address and correct the causes and issues. During the course of interviews with
licensee personnel, the inspection team asked interviewees questions related to safety
conscience work environment (SCWE) to determine if the licensees staff were reluctant
to raise safety concerns or if fear of retaliation existed for raising safety concerns. The
inspection team did not identify concerns related to SCWE.
The inspection team confirmed that the licensees root cause, extent of condition, and
extent of cause evaluations appropriately considered the safety culture components as
described in IMC 0305, Operating Reactor Assessment Program.
The inspectors observed that the previously cited example of a failure to initiate a CR, as
described in CR 01924763, FA errors & less than adequate CAP threshold, was an
important data point from a safety culture and CR initiation standpoint. This CR
documented an individuals failure to write a CR to document deficiencies in the
conclusions of several functionality assessments. The inspectors noted that while the
issue itself was just one data point, the licensees failure to act to determine the extent to
which those behaviors were prevalent onsite was an additional data point in the area of
safety culture. The inspectors noted that the licensee had instead closed the CR to no
action, and noted that coaching had been provided. The inspectors determined that
investigative actions may have been appropriate to assist in the licensees assessment
of whether their RCE corrective actions to improve CR initiation and risk recognition had
adequately reached the working level staff. This may have especially been appropriate
given the fact that similar inappropriate CAP threshold issues played a role in the
common cause for the greater than green findings being evaluated during the 95002
inspection.
Inspectors noted that the O.2a safety culture component may not have been adequately
considered during the licensees safety culture evaluation. Specifically, O.2a is focused
on ensuring that appropriate training and knowledge transfer was in place to ensure
technical competency of staff. The inspectors noted that the licensee marked this
aspect as not applicable. The inspectors observed that this safety culture aspect may
have played a role in the licensees root cause associated with licensee staffs failure to
understand the CLB. Mainly, the inspectors noted that training and knowledge transfer
could have increased licensee personnels understanding of the CLB. The inspectors
observed that at the least, this training and knowledge transfer could have prompted the
identification of vague requirements in the design basis or licensee staffs lack of full
understanding of the CLB. The inspectors noted that this could have driven resolution of
questions on requirements.
                                          41


05000301/2014007-03 NOV Failure to Perform a Required 10 CFR Part 50.59
      The inspectors noted that subject matter experts at the site who were charged with
Evaluation  
      ownership and knowledge of the external flooding program and other functional areas,
05000266/2014007-04
      did not have any qualification cards or required subject matter trainings to ensure their
      competency. This remained unchanged after the finding. The inspectors noted that
      corrective actions to provide general external events training and to develop a formal
      external events program may have appropriately addressed concerns about subject
      matter experts training adequacy, as the procedure consolidated requirements into
      controlling program procedures. However, the inspectors concluded that more
      specialized training could have increased defense in depth in the training and knowledge
      transfer areas.
      The inspectors concluded the 95002 procedure requirements were satisfied for the
      TDAFWP finding but not for the White flooding finding.
  b. Findings
      No findings were identified
02.06 Evaluation of IMC 0305 Criteria for Treatment of Old Design Issues
      The licensee did not request credit for self-identification of an old design issue.
      Consequently, the subject risk significant issues were not evaluated against the
      IMC 0305 criteria for treatment of an old design issue.
4OA5 Other Activities
      The inspectors utilized other inspection procedures as part of the assessment of the
      licensees performance. The following inspection samples were completed as part of
      this inspection.
      *      71111.01 - External Flooding - 1 sample
      *      71111.06 - Internal Flooding - 1 sample
      *      71111.15 - Operability Evaluations - 1 sample
      *      71152 - Problem Identification and Reporting - Annual Follow-Up
              of Selected Samples - 1 sample
4OA6 Management Meeting
      Exit Meeting Summary
      On March 6, 2014, the inspectors presented the inspection results to
      Mr. E. McCartney, Site Vice President, and other members of the licensee staff. The
      licensee acknowledged the issues presented. The inspectors confirmed that none of the
      potential report input discussed was considered proprietary.
ATTACHMENT: SUPPLEMENTAL INFORMATION
                                              42


05000301/2014007-04 FIN Failure to Perform a Required 10 CFR Part 50.59
                                SUPPLEMENTAL INFORMATION
Evaluation
                                  KEY POINTS OF CONTACT
05000266/2014007-05
Licensee
E. McCartney, Site Vice President
R. Wright, Plant General Manager
R. Weber, Operations Director
M. Millen, Licensing Manager
K. Longston, Acting EP Manager
J. Atkins, Systems Engineering Manager
B. Beltz, Assistant Operations Manager
F. Hennessy, Performance Improvement Manager
J. Pruitt, Site Quality Manager
R. Welty, Radiation Protection Manager
R. Harrsch, Engineering Director
D. Lauterbur, Training Manger
P. Wild, Design Engineering Manager
L. Christensen, Licensing Project Manager
B. Scherwinski, Engineering Analyst II
T. Schneider, Licensing
F. Huber, Projects Manager
S. Cassidy, Communications Manager
C. Trezise, Director Special Projects
M. Ley, Civil/Mechanical Engineering Supervisor
T. Lesniak, Mechanical Maintenance Department Head
M. Maertens, Business Operations Manager
R. Clark, Licensing
S. Ruesch, Employee Concerns Program Manager
J. Petro, Licensing Director
A. Gustafson, Training
K. Locke, Licensing
Nuclear Regulatory Commission
A. Boland, Director, Division of Reactor Projects
J. Cameron, Chief, Branch 4, Division of Reactor Projects
K. Barclay, Acting Senior Resident Inspector Point Beach
R. Elliott, Acting Resident Inspector Point Beach
                                              1          Attachment


05000301/2014007-05 NCV Failure to Establish EFR Attributes to Assess the  
                LIST OF ITEMS OPENED, CLOSED AND DISCUSSED
Effectiveness of Corrective Actions  
Opened
    
05000266/2014007-01    NCV  Failure to Take Corrective Actions to Address External
   3  LIST OF DOCUMENTS REVIEWED
05000301/2014007-01          Flooding Procedure Deficiencies
The following is a partial list of documents reviewed during the inspection. Inclusion on this list
05000266/2014007-02    NCV  Failure to Maintain External Flooding Procedure to
does not imply that the NRC inspectors reviewed the documents in their entirety, but rather that selected sections or portions of the documents were evaluated as part of the overall inspection effort. Inclusion of a document on this list does not imply NRC acceptance of the document or
05000301/2014007-02          Address All Possible CLB Floods
any part of it, unless this is stated in the body of the inspection report.
05000266/2014007-03    NOV  Failure to Perform a Required 10 CFR Part 50.59
05000301/2014007-03          Evaluation
05000266/2014007-04    FIN  Failure to Perform a Required 10 CFR Part 50.59
05000301/2014007-04          Evaluation
05000266/2014007-05   NCV   Failure to Establish EFR Attributes to Assess the
05000301/2014007-05          Effectiveness of Corrective Actions
Closed
05000266/2014007-01    NCV   Failure to Take Corrective Actions to Address External
05000301/2014007-01          Flooding Procedure Deficiencies
05000266/2014007-02    NCV   Failure to Maintain External Flooding Procedure to
05000301/2014007-02          Address All Possible CLB Floods
05000266/2014007-03    NOV  Failure to Perform a Required 10 CFR Part 50.59
05000301/2014007-03          Evaluation
05000266/2014007-04    FIN  Failure to Perform a Required 10 CFR Part 50.59
05000301/2014007-04          Evaluation
05000266/2014007-05    NCV  Failure to Establish EFR Attributes to Assess the
05000301/2014007-05          Effectiveness of Corrective Actions
                                      2


                                  LIST OF DOCUMENTS REVIEWED
The following is a partial list of documents reviewed during the inspection. Inclusion on this list
does not imply that the NRC inspectors reviewed the documents in their entirety, but rather that
selected sections or portions of the documents were evaluated as part of the overall inspection
effort. Inclusion of a document on this list does not imply NRC acceptance of the document or
any part of it, unless this is stated in the body of the inspection report.
Corrective Action Documents
Corrective Action Documents
  CR 01195739, CCW Pump Vibration  
CR 01195739, CCW Pump Vibration
CR 01195885, Oil Analysis Shows Evidence of Bearing Wear on Safety Injection Pump Motor  
CR 01195885, Oil Analysis Shows Evidence of Bearing Wear on Safety Injection Pump Motor
CR 01196175, G-02 Exhibited High Axial Impact-Type Acceleration  
CR 01196175, G-02 Exhibited High Axial Impact-Type Acceleration
CR 01200210, RMP For Reactor Coolant Pump Uncoupling Questioned CR 01200598, Refueling Water Storage Tank Throttle Valve Difficult To Operate  
CR 01200210, RMP For Reactor Coolant Pump Uncoupling Questioned
CR 01202954, 2P-11B Alignment Problems  
CR 01200598, Refueling Water Storage Tank Throttle Valve Difficult To Operate
CR 01208186, G-01 EDG Bearing Vibration  
CR 01202954, 2P-11B Alignment Problems
CR 01208318, RCS Piping Stress  
CR 01208186, G-01 EDG Bearing Vibration
CR 01212030, Service Water Pump Gland Follower Improperly Aligned CR 01215799, Inadequacies Identified In SI Pump Routine Maintenance Procedure CR 01216019, Potential for Cracking In MSB Lift Yoke  
CR 01208318, RCS Piping Stress
CR 01217509, P-132 BDE Distillate Pump Alignment  
CR 01212030, Service Water Pump Gland Follower Improperly Aligned
CR 01390003, License Renewal Exam of STP-00014 has Minor Indication  
CR 01215799, Inadequacies Identified In SI Pump Routine Maintenance Procedure
CR 01610365, P-032C SW Pump Shaft Vibration Trending High  
CR 01216019, Potential for Cracking In MSB Lift Yoke
CR 01633548, NOS Identified IER1 11-1, Flood Barrier Door Inspection CR 01639502, Jacking Bolt Broken For Motor Alignment CR 01655812, 2P-10B Bearing Housing Bracket Jack Bolt Holding Alignment  
CR 01217509, P-132 BDE Distillate Pump Alignment
CR 01660763, P-73A/B Suction And Discharge Pump Piping Misalignment  
CR 01390003, License Renewal Exam of STP-00014 has Minor Indication
CR 01678709, NRC Issues Position on Missile Protection For G-01/02 Exhaust  
CR 01610365, P-032C SW Pump Shaft Vibration Trending High
CR 01691196, Operability Determination Issues Across Fleet CR 01723755, Safe Shutdown Fire Dampers No Inspected CR 01726015, FSAR Questions Regarding Cross Over Steam Dump Testing  
CR 01633548, NOS Identified IER1 11-1, Flood Barrier Door Inspection
CR 01639502, Jacking Bolt Broken For Motor Alignment
CR 01655812, 2P-10B Bearing Housing Bracket Jack Bolt Holding Alignment
CR 01660763, P-73A/B Suction And Discharge Pump Piping Misalignment
CR 01678709, NRC Issues Position on Missile Protection For G-01/02 Exhaust
CR 01691196, Operability Determination Issues Across Fleet
CR 01723755, Safe Shutdown Fire Dampers No Inspected
CR 01726015, FSAR Questions Regarding Cross Over Steam Dump Testing
CR 01727221, Plant Safe Shutdown Equipment Exposed To Tornados
CR 01736062, High Energy Line Break Door Issues
CR 01748940, Tornado Hazard
CR 01757131, Potential Violation RSPS Degraded Function
CR 01760171, G-01 and G-02 EDGs Declared Inoperable
CR 01762122, Design Basis Docs On Tornado Missiles
CR 01768931, 1P-29 Turbine Driven Auxiliary Feedwater Pump Degraded Coupling
CR 01771762, Green Finding - Weld Design Deficiency in the EDG Missile Protection Barriers
CR 01779635, Green Finding - Failure to Incorporate WOG ERG, Revision 2 into the EOPs
CR 01780474, G05 Control System Does Not Control Well
CR 01799222, 1P-28B, MFW Pump, High Vibration As-Found Alignment Data
CR 01801696, Quarterly DQS of a Licensing Topic
CR 01804588, Inadequate Scoping of Non-Safety Related System into Maintenance Rule
CR 01805402, Procedure PC 80 Part 7 Lake Water Level Determination Issues
CR 01806402, Procedure PC 80 Part 7 Lake Water Determination Issues
CR 01806545, Inconsistent Application of IPEEE Information in CLB
CR 01807841, Sand Bags Erroneously Eliminated From PB Flood Contingencies
CR 01807866, WR - Obtain Hot and Cold Pump And Motor Growth Readings
CR 01808661, Failure to Implement Risk Management Actions During Emergent Work Activities
                                                3


CR 01727221, Plant Safe Shutdown Equipment Exposed To Tornados
CR 01808901, Coupling Misalignment On 0P-217A G-01 Circulation Oil Pump
CR 01809095, Deficiencies In PC 80 Part 7, Lake Level Determination
CR 01816327, Missing Appendix R Calculations
CR 01824582, PC 80 Part 7 CA 01809095 Due July 31, 2013
CR 01826212, Generator to Engine Coupling Is Degraded
CR 01826753, Coupling on Turbine Has Minor Damage
CR 01833683, Green Finding - Failure to Update the Fire Emergency Plan
CR 01845168, CMP for EN-AA-203-1001 Revision 10 (OD/FA) Implementation
CR 01847140, G-05 Functionality During Severe Weather
CR 01849522, G01/G02 Missile Shield Impact on External Flooding
CR 01850776, 2P-028A High Vibration At Drive End Bearing
CR 01851639, Green Finding - Failure to Submit LER Within 60 Days
CR 01853775, Basis for Flood Barriers Not Referenced In FSAR
CR 01853779, Current Licensing Basis for External Flooding Not Changed
CR 01855615, Resident NRC Inspector Roof Inspection Questions
CR 01856318, FSAR Not Updated for External Flooding Features
CR 01856322, Failure to Establish Adequate Procedures to Respond to PMP Event
CR 01856327, Failure to Maintain Features to Address Max Wave Run Up
CR 01860140, Prior to Starting Work Problems Found With TDAFWP Work Package
CR 01861967, Recent Issues Related to Operability/Functionality, April 1, 2013
CR 01863557, FSAR Errors Identified in Self-Assessment
CR 01863560, High Energy Line Break Door Issue Trending
CR 01875052, Electrical Short Circuit Protection Issues
CR 01875056, Electrical Short Circuit Protection Issues
CR 01877254, G-05 Excessive Hunting at Peak Load
CR 01879455, 2P-011B Pump OB Bearing Doweling Issue
CR 01878130, 2013 CAP FSA - CR Initiation Sensitivity
CR 01880011, Calculation 2005-0053, Revision 1 Presents Appendix R Issues
CR 01883633, Flooding Root Cause Evaluation; Revision 3
CR 01886923, Determine If An Issue Was a Missed Opportunity - Flooding
CR 01889400, Condition Evaluation Did Not Evaluate Scope Identified in Parent CR 01763937
CR 01889518, Final Effectiveness Review  Prompt Operability Determinations and
  Functionality Assessments
CR 01892543, Interim Actions Were Not Fully Effective (EFR 1889518)
CR 01894831, 95001 Inspection AR Screened as CAQ
CR 01894925, NRC 95001 RCE 01768931 Enhancement
CR 01895229, Routine Maintenance Procedures Lack a Specific Standard for Alignment Data
CR 01896156, Degraded Cornerstone - Mitigating Systems Two White Findings
CR 01900061, Functionality Assessment CA1806402-01 Conclusion Questioned
CR 01901996, ACE for Green Finding for Probable Maximum Precipitation Event Controls
CR 01902111, Validate That AOP-13C Will Meet Station Blackout Requirements
CR 01907036, 95002 VSGR Door Gaps Documentation Potential Deficiency
CR 01907864, 95002 Preps: Difference in Annual Snowfall Levels in FSAR
CR 01912749, Subsoil Drainage System is Blocked
CR 01914914, 2-P11A Pump Alignment Challenges
CR 01917384, Unable To Obtain Acceptable Alignment On G-03 Lube Oil Circulation Pump
CR 01918667, 1P-11A As-found Coupling Gap Below RMP Requirements
CR 01919077, Adverse Trend - Engineering CAP Backlog
CR 01920608, Adverse Trend - Engineering CAP Backlog
CR 01920659, 1P-029 As-found Alignment Checks Were Outside the Acceptance Criteria of
  RMP 9044-1
                                          4


CR 01736062, High Energy Line Break Door Issues
CR 01920783, During Performance of WO# 40241255 Checking Alignment on the Terry turbine
 
CR 01921089, Recent Decline In Operations Performance
CR 01748940, Tornado Hazard
CR 01922342, Increase In Initiation Rate of Anonymous and NSC ARs
CR 01757131, Potential Violation RSPS Degraded Function CR 01760171, G-01 and G-02 EDG's Declared Inoperable CR 01762122, Design Basis Docs On Tornado Missiles
CR 01924763, FA Errors & Less Than Adequate CAP Threshold
CR 01768931, 1P-29 Turbine Driven Auxiliary Feedwater Pump Degraded Coupling
CR 01927436, 2P-11B Loose Hold Down Bolts And As-Found Alignment
CR 01771762, Green Finding - Weld Design Deficiency in the EDG Missile Protection Barriers
CR 01932698, 95002 Wave Run-Up Protection May Conflict With Other Floods
CR 01779635, Green Finding - Failure to Incorporate WOG ERG, Revision 2 into the EOPs CR 01780474, G05 Control System Does Not Control Well CR 01799222, 1P-28B, MFW Pump, High Vibration As-Found Alignment Data
CR 01936250, Employee Behavior Not Aligning With Expectations
CR 01801696, Quarterly DQS of a Licensing Topic
CR 01936497, Conflict Between AOP-13C High Winds And PC 80 Part 7 Barrier
CR 01804588, Inadequate Scoping of Non-Safety Related System into Maintenance Rule
CR 01937027, 95002 Revise NP 7.5.2 and Form PBF-9178 to Address Flooding
CR 01805402, Procedure PC 80 Part 7 Lake Water Level Determination Issues
CR 01937424, PBSA-ENG-15-01 External Events Program Quick Hit Assessment
CR 01806402, Procedure PC 80 Part 7 Lake Water Determination Issues CR 01806545, Inconsistent Application of IPEEE Information in CLB
CR 01938711, NRC 95002 Inspection - RCE 1883633 EOCA for CC2
CR 01807841, Sand Bags Erroneously Elimi
nated From PB Flood Contingencies CR 01807866, WR - Obtain Hot and Cold Pump And Motor Growth Readings
CR 01808661, Failure to Implement Risk Management Actions During Emergent Work Activities 
  4  CR 01808901, Coupling Misalignment On 0P-217A G-01 Circulation Oil Pump CR 01809095, Deficiencies In PC 80 Part 7, Lake Level Determination
CR 01816327, Missing Appendix R Calculations
CR 01824582, PC 80 Part 7 CA 01809095 Due July 31, 2013 CR 01826212, Generator to Engine Coupling Is Degraded
CR 01826753, Coupling on Turbine Has Minor Damage
CR 01833683, Green Finding - Failure to Update the Fire Emergency Plan
CR 01845168, CMP for EN-AA-203-1001 Revision 10 (OD/FA) Implementation
 
CR 01847140, G-05 Functionality During Severe Weather CR 01849522, G01/G02 Missile Shield Impact on External Flooding CR 01850776, 2P-028A High Vibration At Drive End Bearing
 
CR 01851639, Green Finding - Failure to Submit LER Within 60 Days
CR 01853775, Basis for Flood Barriers Not Referenced In FSAR
CR 01853779, Current Licensing Basis for External Flooding Not Changed
CR 01855615, Resident NRC Inspector Roof Inspection Questions CR 01856318, FSAR Not Updated for External Flooding Features
CR 01856322, Failure to Establish Adequate Procedures to Respond to PMP Event
CR 01856327, Failure to Maintain Features to Address Max Wave Run Up
CR 01860140, Prior to Starting Work Problems Found With TDAFWP Work Package CR 01861967, Recent Issues Related to Operability/Functionality, April 1, 2013 CR 01863557, FSAR Errors Identified in Self-Assessment
CR 01863560, High Energy Line Break Door Issue Trending
CR 01875052, Electrical Short Circuit Protection Issues
CR 01875056, Electrical Short Circuit Protection Issues
CR 01877254, G-05 Excessive "Hunting" at Peak Load CR 01879455, 2P-011B Pump OB Bearing Doweling Issue CR 01878130, 2013 CAP FSA - CR Initiation Sensitivity
CR 01880011, Calculation 2005-0053, Revision 1 Presents Appendix R Issues
CR 01883633, Flooding Root Cause Evaluation; Revision 3
CR 01886923, Determine If An Issue Was a Missed Opportunity - Flooding CR 01889400, Condition Evaluation Did Not Evaluate Scope Identified in Parent CR 01763937 CR 01889518, Final Effectiveness Review - Prompt Operability Determinations and
Functionality Assessments
CR 01892543, Interim Actions Were Not Fully Effective (EFR 1889518)
CR 01894831, 95001 Inspection AR Screened as CAQ
CR 01894925, NRC 95001 RCE 01768931 Enhancement CR 01895229, Routine Maintenance Procedures Lack a Specific Standard for Alignment Data CR 01896156, Degraded Cornerstone - Mitigating Systems Two White Findings
CR 01900061, Functionality Assessment CA1806402-01 Conclusion Questioned
CR 01901996, ACE for Green Finding for Probable Maximum Precipitation Event Controls
CR 01902111, Validate That AOP-13C Will Meet Station Blackout Requirements CR 01907036, 95002 VSGR Door Gaps Documentation Potential Deficiency CR 01907864, 95002 Preps:  Difference in Annual Snowfall Levels in FSAR
CR 01912749, Subsoil Drainage System is Blocked
 
CR 01914914, 2-P11A Pump Alignment Challenges
CR 01917384, Unable To Obtain Acceptable Alignment On G-03 Lube Oil Circulation Pump
CR 01918667, 1P-11A As-found Coupling Gap Below RMP Requirements
CR 01919077, Adverse Trend - Engineering CAP Backlog
CR 01920608, Adverse Trend - Engineering CAP Backlog
CR 01920659, 1P-029 As-found Alignment Checks Were Outside the Acceptance Criteria of
RMP 9044-1 
  5  CR 01920783, During Performance of WO# 40241255 Checking Alignment on the Terry turbine CR 01921089, Recent Decline In Operations Performance  
CR 01922342, Increase In Initiation Rate of Anonymous and NSC ARs CR 01924763, FA Errors & Less Than Adequate CAP Threshold CR 01927436, 2P-11B Loose Hold Down Bolts And As-Found Alignment  
CR 01932698, 95002 Wave Run-Up Protection May Conflict With Other Floods  
CR 01936250, Employee Behavior Not Aligning With Expectations  
CR 01936497, Conflict Between AOP-13C High Winds And PC 80 Part 7 Barrier  
CR 01937027, 95002 Revise NP 7.5.2 and Form PBF-9178 to Address Flooding CR 01937424, PBSA-ENG-15-01 External Events
Program Quick Hit Assessment CR 01938711, NRC 95002 Inspection - RCE 1883633 EOCA for CC2  
 
NRC Identified CRs
NRC Identified CRs
  CR 01938106, Incomplete Disposition of AR 01860140 On Unit 1 TDAFWP CR 01938122, During NRC Walk Down Black Putty and Dry Boric Acid Was Noted on the Base  
CR 01938106, Incomplete Disposition of AR 01860140 On Unit 1 TDAFWP
Plate of the Unit 2 Train B Containment Spray Pump  
CR 01938122, During NRC Walk Down Black Putty and Dry Boric Acid Was Noted on the Base
CR 01938271, Snow Was on the Barrier Installation Pads As Well As A Power Cable  
  Plate of the Unit 2 Train B Containment Spray Pump
CR 01938314, Visible Dimple Noted Near Jacking Bolt CR 01938317, During Walk Down Dried Boric Acid Noted on The Unit 2 Train B RHR  Pump Seal  
CR 01938271, Snow Was on the Barrier Installation Pads As Well As A Power Cable
CR 01938326, Final Effectiveness Reviews for Common Cause 1 and 2 Were Inappropriately  
CR 01938314, Visible Dimple Noted Near Jacking Bolt
Reliant Upon NRC Input  
CR 01938317, During Walk Down Dried Boric Acid Noted on The Unit 2 Train B RHR
CR 01938384, Alignment Issue With Valve 2RH-823B Reach Rod  
   Pump Seal
CR 01938501, Maximum Precipitation and Wave Run Up Not Assessed Simultaneously CR 01938670, Root Cause Reports Were Not Aligned with the 95002 Procedure CR 01938711, Scope for the Extent of Cause of Contributing Cause 2 From the Flooding RCE  
CR 01938326, Final Effectiveness Reviews for Common Cause 1 and 2 Were Inappropriately
Is Limited to NRC Concerns Only  
  Reliant Upon NRC Input
CR 01938749, Attachment of Spring Cans to the MOVs After All As Left Testing Completed  
CR 01938384, Alignment Issue With Valve 2RH-823B Reach Rod
CR 01938706, Formal Aggregate Review of all Flooding Related CRs CR 01938825, Potential Storm Drain Bypass of Wave Run Up Barriers Not Assessed CR 01938861, Risk Analysis Sections in Root and Common Causes Narrowly Focused  
CR 01938501, Maximum Precipitation and Wave Run Up Not Assessed Simultaneously
CR 01939011, Expand FSAR Section on Probable Maximum Precipitation Event  
CR 01938670, Root Cause Reports Were Not Aligned with the 95002 Procedure
CR 01939095, VTM Dowling Recommendation Not Incorporated Into Procedures  
CR 01938711, Scope for the Extent of Cause of Contributing Cause 2 From the Flooding RCE
CR 01939217, TDAFWP Root Cause Did Not Implement a Vendor Recommendation  
  Is Limited to NRC Concerns Only
CR 01939345, No Corrective Actions Initiated for Flooding Barriers During Cold Weather CR 01939362, Functionality Assessments Found Issues But No Corrective Actions Taken CR 01939389, Needed Enhancement to FSAR Appendix A.7, Internal Flooding  
CR 01938749, Attachment of Spring Cans to the MOVs After All As Left Testing Completed
CR 01939838, Remove Door 349 When Wave Run Up Barriers Are Installed  
CR 01938706, Formal Aggregate Review of all Flooding Related CRs
CR 01940082, Procedure PC 80 Part 7, Revision 6 50.59 Screen Error  
CR 01938825, Potential Storm Drain Bypass of Wave Run Up Barriers Not Assessed
CR 01940118, Procedure PC 80 Part 7, Revision 4 50.59 Screen Error CR 01940511, Errors Identified in Surveillance PBF-2124  
CR 01938861, Risk Analysis Sections in Root and Common Causes Narrowly Focused
CR 01940562, Poor CAP Product Quality  
CR 01939011, Expand FSAR Section on Probable Maximum Precipitation Event
CR 01940606, Errors Identified in Procedure PC 80, Part 7  
CR 01939095, VTM Dowling Recommendation Not Incorporated Into Procedures
 
CR 01939217, TDAFWP Root Cause Did Not Implement a Vendor Recommendation
CR 01940621, FSAR Revision Required  
CR 01939345, No Corrective Actions Initiated for Flooding Barriers During Cold Weather
CR 01940739, Unintentional Change to PC 80 Part 7 Identified  
CR 01939362, Functionality Assessments Found Issues But No Corrective Actions Taken
CR 01941022, Additional Errors Found in PBF-2124 CR 01941085, Potential Licensing Basis Questions Identified  
CR 01939389, Needed Enhancement to FSAR Appendix A.7, Internal Flooding
CR 01941262, Quality Level of Flood Related Doors in Error  
CR 01939838, Remove Door 349 When Wave Run Up Barriers Are Installed
CR 01941902, Readiness for Inspection Letter Sent the Same Day as it Was Identified That the  
CR 01940082, Procedure PC 80 Part 7, Revision 6 50.59 Screen Error
Site was Not Ready for the Inspection
CR 01940118, Procedure PC 80 Part 7, Revision 4 50.59 Screen Error
  6  CR 01942059, Another Error Found In PBF-2124 CR 01942315, Several Drawing Errors Identified
CR 01940511, Errors Identified in Surveillance PBF-2124
 
CR 01940562, Poor CAP Product Quality
CR 01942317, Error Identified On ARB C01 B1-1
CR 01940606, Errors Identified in Procedure PC 80, Part 7
CR 01942343, Error Identified In AOP-13C CR 01943803, Use of Wrong NRC Cross Cutting Code in Effectiveness Review Criteria
CR 01940621, FSAR Revision Required
CR 01946330, Severity Level IV Violation for 50.59 - Use of Roll-Up Doors
CR 01940739, Unintentional Change to PC 80 Part 7 Identified
 
CR 01941022, Additional Errors Found in PBF-2124
CR 01941085, Potential Licensing Basis Questions Identified
Drawings  M-1, Equipment Location Plan Containment Operating Floor Unit 1, Revision 19 M-3, Water Intake Facility General Arrangement Plan B-B, Revision, November 17, 1967
CR 01941262, Quality Level of Flood Related Doors in Error
M-4, Water Intake Facility General Arrangement Plan C-C and D-D, November 17, 1967
CR 01941902, Readiness for Inspection Letter Sent the Same Day as it Was Identified That the
M-15, Water Intake Facility Piping Section F-F, November 4, 1969
  Site was Not Ready for the Inspection
M-16, Circulating Water Pump House Piping, Revision 13 M-2007, Equipment Location Plan Ground Floor North, Revision 22 M-2009, Equipment Location Plan Sections H-H and K-K, Revision 9
                                            5
M-2010, Equipment Location Miscellaneous Section, Revision 5  
 
C-1, Site Plan, Revision 19
6704-E-121001, Plant Key Plan, Drawing, Index and Specification Numbers, Revision 4 6704-E-121102, Diesel Generator Building Floor and Roof Plan, Revision 5 6704-E-151001, Diesel Generator Building Yard Area Grading Plan, Revision 3
M-165, Turbine Building Floor & Equipment Drainage Area No 3 - Plan at EL. 8.0, Revision 6


CR 01942059, Another Error Found In PBF-2124
CR 01942315, Several Drawing Errors Identified
CR 01942317, Error Identified On ARB C01 B1-1
CR 01942343, Error Identified In AOP-13C
CR 01943803, Use of Wrong NRC Cross Cutting Code in Effectiveness Review Criteria
CR 01946330, Severity Level IV Violation for 50.59 - Use of Roll-Up Doors
Drawings
M-1, Equipment Location Plan Containment Operating Floor Unit 1, Revision 19
M-3, Water Intake Facility General Arrangement Plan B-B, Revision, November 17, 1967
M-4, Water Intake Facility General Arrangement Plan C-C and D-D, November 17, 1967
M-15, Water Intake Facility Piping Section F-F, November 4, 1969
M-16, Circulating Water Pump House Piping, Revision 13
M-2007, Equipment Location Plan Ground Floor North, Revision 22
M-2009, Equipment Location Plan Sections H-H and K-K, Revision 9
M-2010, Equipment Location Miscellaneous Section, Revision 5
C-1, Site Plan, Revision 19
6704-E-121001, Plant Key Plan, Drawing, Index and Specification Numbers, Revision 4
6704-E-121102, Diesel Generator Building Floor and Roof Plan, Revision 5
6704-E-151001, Diesel Generator Building Yard Area Grading Plan, Revision 3
M-165, Turbine Building Floor & Equipment Drainage Area No 3 - Plan at EL. 8.0, Revision 6
Licensee Procedures
Licensee Procedures
  AD-AA-103, Nuclear Safety Culture Program, Revision 5 EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 7  
AD-AA-103, Nuclear Safety Culture Program, Revision 5
EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 11  
EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 7
EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 12  
EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 11
EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 15 RMP 9044-1, Auxiliary Feedwater Pump Terry Turbine Overhaul, Revision 35 RMP 9376-1, Limitorque MOV Removal, Installation, SWAP, and Testing for Gate and
EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 12
Globe Valves  
EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 15
RMP 9376-2, Limitorque MOV Static/DP Testing for Gate and Globe Valves  
RMP 9044-1, Auxiliary Feedwater Pump Terry Turbine Overhaul, Revision 35
RMP 9376-3, Limitorque MOV Removal, Installation, and Adjustment for Butterfly Valves  
RMP 9376-1, Limitorque MOV Removal, Installation, SWAP, and Testing for Gate and
RMP 9376-4, Limitorque Motor Operator Model SMB-000 Disassembly, Inspection Repair,   and Re-Assembly RMP 9376-5, Limitorque Motor Operator Model SMB-0 Through SMB-4 Disassembly,  
  Globe Valves
Inspection, Repair, and Re-Assembly  
RMP 9376-2, Limitorque MOV Static/DP Testing for Gate and Globe Valves
RMP 9376-6, Limitorque Motor Operator Model SMB-00 Disassembly, Inspection, Repair, and  
RMP 9376-3, Limitorque MOV Removal, Installation, and Adjustment for Butterfly Valves
Re-Assembly RMP 9008-1, RHR Pump Removal and Installation RMP 9005-2, SI Pump Overhaul  
RMP 9376-4, Limitorque Motor Operator Model SMB-000 Disassembly, Inspection Repair,
Vendor Manual 0501, Pacific Pumps, Inc.  
  and Re-Assembly
AOP-13C; Abnormal Operating Procedure-Severe Weather Conditions, Revision 32  
RMP 9376-5, Limitorque Motor Operator Model SMB-0 Through SMB-4 Disassembly,
NP 7.5.2; PBNP Owner Controlled Area Temporary Structure Limitations, Revision 12  
Inspection, Repair, and Re-Assembly
NA-AA-200, Employees Concern Program Process Description, Revision 5  
RMP 9376-6, Limitorque Motor Operator Model SMB-00 Disassembly, Inspection, Repair, and
PI-AA-01, Corrective Action Program and Condition Reporting, Revision 3 PI-AA-204, Condition Identification and Screening Process, Revision 22  
  Re-Assembly
PI-AA-205, Condition Evaluation and Corrective Action, Revision 23  
RMP 9008-1, RHR Pump Removal and Installation
PI-AA-100-1005, Root Cause Analysis, Revision 8
RMP 9005-2, SI Pump Overhaul
  7  PI-AA-100-1006, Common Cause Evaluation, Revision 6 PI-AA-100-1007, Apparent Cause Analysis, Revision 7
Vendor Manual 0501, Pacific Pumps, Inc.
PI-AA-100-1008, Condition Evaluation, Revision 5 PI-AA-101-1001, Quick Hit Assessments, Revision 5 MA-AA-203-1001, Work Order Planning, Revision 1
AOP-13C; Abnormal Operating ProcedureSevere Weather Conditions, Revision 32
PDM 1.0, Vibration Monitoring Program
NP 7.5.2; PBNP Owner Controlled Area Temporary Structure Limitations, Revision 12
Procedure IT 02, High Head Safety Injection Pumps and Valves Train B, Unit 2
NA-AA-200, Employees Concern Program Process Description, Revision 5
Procedure IT 03, Low Head Safety Injection Pumps and Valves Train A, Unit 1
PI-AA-01, Corrective Action Program and Condition Reporting, Revision 3
Procedure IT 06, Containment Spray Pump and Valves Procedure IT 12, 1P-11B, Component Cooling Water Pumps and Valves Unit 1 Procedure IT-07D, Service Water Pump (Quarterly) Surveillance
PI-AA-204, Condition Identification and Screening Process, Revision 22
PC 80 Part 7, Lake Water Level Determination, Revision 3
PI-AA-205, Condition Evaluation and Corrective Action, Revision 23
PC 80 Part 7, Lake Water Level Determination, Revision 4
PI-AA-100-1005, Root Cause Analysis, Revision 8
PC 80 Part 7, Lake Water Level Determination, Revision 5 PC 80 Part 7, Lake Water Level Determination, Revision 6 PC 80 Part 7, Lake Water Level Determination, Revision 7
                                            6
PC 80 Part 7, Lake Water Level Determination, Revision 8
PC 80 Part 7, Lake Water Level Determination, Revision 9
PC 80 Part 7, Lake Water Level Determination, Revision 10 CL 11A G-02, G-02 Diesel Generator Checklist, Revision 29 NP 7.2.29; External Events Program, Revision 0


PI-AA-100-1006, Common Cause Evaluation, Revision 6
PI-AA-100-1007, Apparent Cause Analysis, Revision 7
PI-AA-100-1008, Condition Evaluation, Revision 5
PI-AA-101-1001, Quick Hit Assessments, Revision 5
MA-AA-203-1001, Work Order Planning, Revision 1
PDM 1.0, Vibration Monitoring Program
Procedure IT 02, High Head Safety Injection Pumps and Valves Train B, Unit 2
Procedure IT 03, Low Head Safety Injection Pumps and Valves Train A, Unit 1
Procedure IT 06, Containment Spray Pump and Valves
Procedure IT 12, 1P-11B, Component Cooling Water Pumps and Valves Unit 1
Procedure IT-07D, Service Water Pump (Quarterly) Surveillance
PC 80 Part 7, Lake Water Level Determination, Revision 3
PC 80 Part 7, Lake Water Level Determination, Revision 4
PC 80 Part 7, Lake Water Level Determination, Revision 5
PC 80 Part 7, Lake Water Level Determination, Revision 6
PC 80 Part 7, Lake Water Level Determination, Revision 7
PC 80 Part 7, Lake Water Level Determination, Revision 8
PC 80 Part 7, Lake Water Level Determination, Revision 9
PC 80 Part 7, Lake Water Level Determination, Revision 10
CL 11A G-02, G-02 Diesel Generator Checklist, Revision 29
NP 7.2.29; External Events Program, Revision 0
Root Cause Reports
Root Cause Reports
 
RCE 01757131, Potential Violation Due to a Degraded Emergency Planning Risk Significant
RCE 01757131, Potential Violation Due to a Degraded Emergency Planning Risk Significant Planning Standard Function, Revision 4 RCE 01768931, Unit 1 Turbine Driven Auxiliary Feedwater Pump 1P-29 Coupling Degraded  
  Planning Standard Function, Revision 4
During IT-08A Run, Revision 5  
RCE 01768931, Unit 1 Turbine Driven Auxiliary Feedwater Pump 1P-29 Coupling Degraded
RCE 01883633, Potential Greater Than Green Finding Flooding, Revision 3  
  During IT-08A Run, Revision 5
RCE 01896156, Degraded Cornerstone - Mitigating Systems Two White Findings, Revision 1  
RCE 01883633, Potential Greater Than Green Finding Flooding, Revision 3
Calculations
RCE 01896156, Degraded Cornerstone - Mitigating Systems Two White Findings, Revision 1
 
Calculations
FPL-076-CALC-017, Maximum Precipitation Analysis for Past Reportability, Revision 0  
FPL-076-CALC-017, Maximum Precipitation Analysis for Past Reportability, Revision 0
CALC 2008-0024, AFWP Room Flood Basis Calculation-January 23, 2014, Revision 1  
CALC 2008-0024, AFWP Room Flood Basis CalculationJanuary 23, 2014, Revision 1
CALC 2009-0008, Circulating Water Pump House Internal Flooding, Revision 1 FPL-076-CALC-016, Flow Depth Sensitivity to Openings with Wave Barriers-February 6, 2014, Revision 0  
CALC 2009-0008, Circulating Water Pump House Internal Flooding, Revision 1
 
FPL-076-CALC-016, Flow Depth Sensitivity to Openings with Wave BarriersFebruary 6, 2014,
FPL-076-CALC-003, Point Beach DELFT3D Surge and Wave Model, Revision 0  
  Revision 0
EC 279455, Time Available to Respond to Threat From Rising Water, June 24, 2013  
FPL-076-CALC-003, Point Beach DELFT3D Surge and Wave Model, Revision 0
 
EC 279455, Time Available to Respond to Threat From Rising Water, June 24, 2013
FPL-076-CALC-014, PBNP Precipitation and Snow Intensity Determination and Roof Drainage Evaluation - December 18, 2013, Revision 0 FPL-076-CALC-015, Maximum Precipitation Flood Effects - January 7, 2014, Revision 0  
FPL-076-CALC-014, PBNP Precipitation and Snow Intensity Determination and Roof Drainage
CALC 2014-0002, Effects on Safety Equipment of Bypassing the Installed Wave Run-Up Barriers Through The Storm Drains - February 11, 2014, Revision 0  
  Evaluation - December 18, 2013, Revision 0
 
FPL-076-CALC-015, Maximum Precipitation Flood Effects - January 7, 2014, Revision 0
CALC 2014-0002, Effects on Safety Equipment of Bypassing the Installed Wave Run-Up
  Barriers Through The Storm Drains - February 11, 2014, Revision 0
Miscellaneous Documents
Miscellaneous Documents
  List of Technical Procedure Revisions for 2013  
List of Technical Procedure Revisions for 2013
Presentation for Outage Review Board Team Meeting, February 4, 2014  
Presentation for Outage Review Board Team Meeting, February 4, 2014
Corrective Action Review Board Package for February 4, 2014
Corrective Action Review Board Package for February 4, 2014
  8  PBSA-PBNP-13-013, Quick Hit Assessment Report for the 95002 Mock Inspection for  Degraded Cornerstone, October 29, 2013
                                            7
PBSA-ENG-07-13, 2008 Component Design Basis Inspection Preparations, March 10-20, 2008 PBSA-ENG-10-20, Focused Self-Assessment of Flooding Program, September 20-23, 2010 PBSA-ENG-11-01, Component Design Basis Inspection Preparations, January 17-27, 2011
PBSA-ENG-06-02, SA Preparation for Design Basis Inspection Based on 71111.21, 
January 16 - February 2, 2006
PBSA-ENG-12-20, Quick Hit Assessment Report-Flooding Program, April 15 - May 24, 2013
PBSA-PBNP-13-02, CR 01908740, Quick Hit Assessment Report Station Nuclear Safety  Culture, September 23 through October 4, 2013 PBSA-PBNP-12-02, Quick Hit Assessment Report Station Nuclear Safety Culture 
September 17 through 20, 2012
MOR 2013-23, Missed Opportunity Review-Potential Greater Than Green Finding-Flooding,
July 9, 2013 NOS Daily Quality Summary Related to Flooding MOR-Gas Accumulation Management  Program, April 24, 2013


CEI Independent Evaluation, Point Beach Root Cause Evaluation for NRC White Performance  
PBSA-PBNP-13-013, Quick Hit Assessment Report for the 95002 Mock Inspection for
Indicator-Flooding, September 20, 2013  
  Degraded Cornerstone, October 29, 2013
EC 280223, Review of Flooding Vulnerability Report for Possible CLB Encroachment, October 22, 2013 NEE 05-PR-003, Flooding Vulnerability Report, Revision 0  
PBSA-ENG-07-13, 2008 Component Design Basis Inspection Preparations, March 10-20, 2008
EN-AA-203-1001 Operations Training-Operability Determinations/Functionality Assessment  
PBSA-ENG-10-20, Focused Self-Assessment of Flooding Program, September 20-23, 2010
Training Materials, August 28, 2013  
PBSA-ENG-11-01, Component Design Basis Inspection Preparations, January 17-27, 2011
EN-AA-203-1001 Engineering Lesson Plan-Operability Determinations/Functionality  
PBSA-ENG-06-02, SA Preparation for Design Basis Inspection Based on 71111.21,
Assessments, July 3, 2013 SCR 2013-0213, 50.59 Screening Form FSAR Sect 2.5 PMP Flood-January 28, 2014, Revision 1  
  January 16 - February 2, 2006
Monthly Weather Review-The Prediction of Surges in the Southern Basin of Lake Michigan;  
PBSA-ENG-12-20, Quick Hit Assessment ReportFlooding Program, April 15 - May 24, 2013
May 1965  
PBSA-PBNP-13-02, CR 01908740, Quick Hit Assessment Report Station Nuclear Safety
NPC98-00509, Harza Preliminary Hydrologic and Hydraulic Studies for Nuclear Power Plant Site Selection, March 18, 1966 NOS Observations, October 30, 2008, November 20, 2009, August 16, 2010, April 23, 2011,  
  Culture, September 23 through October 4, 2013
November 19, 2011  
PBSA-PBNP-12-02, Quick Hit Assessment Report Station Nuclear Safety Culture
Point Beach Daily Quality Summary - 1P-29 Turbine Driven Auxiliary Feedwater Pump,  January 27, 2012  
  September 17 through 20, 2012
Point Beach Daily Quality Summary - Initial Auxiliary Feedwater Pump and Terry Turbine Alignment, June 22, 2012 Point Beach Daily Quality Summary - Terry Turbine Oil Change and Sampling, July 02, 2012 PBN 12-010, Nuclear Oversight Report: Maintenance-Corrective and Preventative,
MOR 2013-23, Missed Opportunity ReviewPotential Greater Than Green FindingFlooding,
July 12, 2012  
  July 9, 2013
Point Beach Daily Quality Summary - 1/2 P-38 AFW Pump October 16, 2012 PBN-12-014, Nuclear Oversight Report: System Engineering, November 19, 2012 Point Beach Daily Quality Summary - 2P-29 TDAFW Pump Assembly, November 19, 2012  
NOS Daily Quality Summary Related to Flooding MORGas Accumulation Management
PBN-13-003 Nuclear Oversight Report: Engineering Design, March 8, 2013  
  Program, April 24, 2013
Point Beach Daily Quality Summary - Fire Protection Walkdown P-53 Motor Driven Auxiliary Feed Pump Rooms, October 2, 2013  
CEI Independent Evaluation, Point Beach Root Cause Evaluation for NRC White Performance
MOR 2013-09 Missed Opportunity Review, 1-29-T, Auxiliary Feed Water Pump Turbine Coupling Failure, CR 1846183, February 7, 2014 WO 383111-01, STP-00014; Inspect for License Renewal per LR-TR-519, May 17, 2010  
  IndicatorFlooding, September 20, 2013
WO 40188994-09, Simulate PC 50 Part 7 Draft with New Barriers (PMT), November 21, 2013  
EC 280223, Review of Flooding Vulnerability Report for Possible CLB Encroachment,
WO 40188994-04, Verify Ability to Place and Secure Jersey Barriers (PMT), July 10, 2013
  October 22, 2013
  9  Fleet Daily Quality Summary Report-Fukushima, November 22, 2011 Point Beach Daily Quality Summary Report-Flooding Related, April 4, 2012
NEE 05-PR-003, Flooding Vulnerability Report, Revision 0
Point Beach Nuclear Oversight Report-Fire Protection and Flood Doors, October 7, 2010 Point Beach Nuclear Oversight Report-ISFSI Environmental Impacts Audit, July 14, 2011 Point Beach Nuclear Oversight Report-Review of OE Related to Flooding and Actions Taken,
EN-AA-203-1001 Operations TrainingOperability Determinations/Functionality Assessment
March 8, 2013
  Training Materials, August 28, 2013
Point Beach Nuclear Oversight Report-Review of Commitments-Flooding Walk Downs,
EN-AA-203-1001 Engineering Lesson PlanOperability Determinations/Functionality
March 30, 2013
  Assessments, July 3, 2013
Fleet Daily Quality Summary Report-Flooding Underground Cables, January 21, 2008 WO 40220319-01, PC 80 Part 7 Install CWPH Concrete Block Barriers, February 4, 2014 Pictures of Wave Barriers Constructed, November 26, 2013 
SCR 2013-0213, 50.59 Screening Form FSAR Sect 2.5 PMP FloodJanuary 28, 2014,
  10  LIST OF ACRONYMS USED ADAMS Agencywide Document Access Management System AFW Auxiliary Feedwater AR Action Request CAPR Corrective Action to Prevent Recurrence
  Revision 1
CC Contributing Cause
Monthly Weather ReviewThe Prediction of Surges in the Southern Basin of Lake Michigan;
CCA Common Cause Analysis
  May 1965
CCDP Conditional Core Damage Probability
NPC98-00509, Harza Preliminary Hydrologic and Hydraulic Studies for Nuclear Power Plant
CDF Core Damage Frequency CFR Code of Federal Regulations CLB Current License Basis
  Site Selection, March 18, 1966
CR Condition Report
NOS Observations, October 30, 2008, November 20, 2009, August 16, 2010, April 23, 2011,
CW Circulating Water
  November 19, 2011
CWPH Circulating Water Pump House CY Calendar Year  DRP Division of Reactor Projects
Point Beach Daily Quality Summary - 1P-29 Turbine Driven Auxiliary Feedwater Pump,
EFR Effectiveness Review
   January 27, 2012
EJ Expansion Joint
Point Beach Daily Quality Summary - Initial Auxiliary Feedwater Pump and Terry Turbine
EP Emergency Preparedness EPRI Electric Power Research Institute FA Functionality Assessment
  Alignment, June 22, 2012
FP Fire Protection
Point Beach Daily Quality Summary - Terry Turbine Oil Change and Sampling, July 02, 2012
FSAR Final Safety Analysis Report
PBN 12-010, Nuclear Oversight Report: Maintenance-Corrective and Preventative,
gpm Gallons per Minute
  July 12, 2012
HCLPF High Consequence of Low Probability of Failure HEP Human Error Probability IMC Inspection Manual Chapter
Point Beach Daily Quality Summary - 1/2 P-38 AFW Pump October 16, 2012
INPO Institute of Nuclear Power Operations 
PBN-12-014, Nuclear Oversight Report: System Engineering, November 19, 2012
IP Inspection Procedure
Point Beach Daily Quality Summary - 2P-29 TDAFW Pump Assembly, November 19, 2012
IPEEE Individual Plant Examination External Events IR Inspection Report IST In-service Test
PBN-13-003 Nuclear Oversight Report: Engineering Design, March 8, 2013
KSA Knowledge Skills and Abilities
Point Beach Daily Quality Summary - Fire Protection Walkdown P-53 Motor Driven Auxiliary
LERF Large Early Release Frequency
  Feed Pump Rooms, October 2, 2013
LOCA Loss of Coolant Accident
MOR 2013-09 Missed Opportunity Review, 1-29-T, Auxiliary Feed Water Pump Turbine
LOOP Loss of Off-Site Power MOV Motor Operated Valve N/A Not Applicable
  Coupling Failure, CR 1846183, February 7, 2014
NCV Non-Cited Violation
WO 383111-01, STP-00014; Inspect for License Renewal per LR-TR-519, May 17, 2010
NOV Notice of Violation
WO 40188994-09, Simulate PC 50 Part 7 Draft with New Barriers (PMT), November 21, 2013
NRC U.S. Nuclear Regulatory Commission OEM Original Equipment Manufacturer OSHA Occupational Safety Health and Safety
WO 40188994-04, Verify Ability to Place and Secure Jersey Barriers (PMT), July 10, 2013
PARS Publicly Available Records
                                            8
PC Procedure Call-Up
PMP Probable Maximum Precipitation
PMT Post Maintenance Test PRA Probabilistic Risk Assessment PWR Pressurized Water Reactor
RASP Risk Assessment Standardization Project 
  11  RC Root Cause RCE Root Cause Evaluation
ROP Reactor Oversight Process SCWE Safety Conscience Work Environment SDP Significance Determination Process
SME Subject Matter Expert
SPAR Standardized Plant Analysis Risk
SQAC Significant Condition Adverse to Quality
SRA Senior Reactor Analyst SW Service Water TDAFWP Turbine Driven Auxiliary Feedwater Pump
TB Turbine Building
TS Technical Specification
URI Unresolved Item VTM Vendor Technical Manual Yr Year
WO Work Order
 
  E. McCartney -3-
previous terminology will be converted to the latest revision in accordance with the  cross-reference in IMC 0310.  The revised cross-cutting aspects will be evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC-0305 starting with the CY 2014 mid-cycle assessment review.


Fleet Daily Quality Summary ReportFukushima, November 22, 2011
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and  
Point Beach Daily Quality Summary ReportFlooding Related, April 4, 2012
its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management
Point Beach Nuclear Oversight ReportFire Protection and Flood Doors, October 7, 2010
System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Point Beach Nuclear Oversight ReportISFSI Environmental Impacts Audit, July 14, 2011
Point Beach Nuclear Oversight ReportReview of OE Related to Flooding and Actions Taken,
  March 8, 2013
Point Beach Nuclear Oversight ReportReview of CommitmentsFlooding Walk Downs,
  March 30, 2013
Fleet Daily Quality Summary ReportFlooding Underground Cables, January 21, 2008
WO 40220319-01, PC 80 Part 7 Install CWPH Concrete Block Barriers, February 4, 2014
Pictures of Wave Barriers Constructed, November 26, 2013
                                          9


  Sincerely, /RA/ Anne T. Boland, Director
                          LIST OF ACRONYMS USED
Division of Reactor Projects
ADAMS Agencywide Document Access Management System
  Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27
AFW  Auxiliary Feedwater
AR    Action Request
CAPR Corrective Action to Prevent Recurrence
CC    Contributing Cause
CCA  Common Cause Analysis
CCDP Conditional Core Damage Probability
CDF  Core Damage Frequency
CFR  Code of Federal Regulations
CLB  Current License Basis
CR    Condition Report
CW    Circulating Water
CWPH Circulating Water Pump House
CY    Calendar Year
DRP  Division of Reactor Projects
EFR  Effectiveness Review
EJ    Expansion Joint
EP    Emergency Preparedness
EPRI  Electric Power Research Institute
FA    Functionality Assessment
FP    Fire Protection
FSAR Final Safety Analysis Report
gpm  Gallons per Minute
HCLPF High Consequence of Low Probability of Failure
HEP  Human Error Probability
IMC  Inspection Manual Chapter
INPO  Institute of Nuclear Power Operations
IP    Inspection Procedure
IPEEE Individual Plant Examination External Events
IR    Inspection Report
IST  In-service Test
KSA  Knowledge Skills and Abilities
LERF  Large Early Release Frequency
LOCA  Loss of Coolant Accident
LOOP  Loss of Off-Site Power
MOV  Motor Operated Valve
N/A  Not Applicable
NCV  Non-Cited Violation
NOV  Notice of Violation
NRC  U.S. Nuclear Regulatory Commission
OEM  Original Equipment Manufacturer
OSHA  Occupational Safety Health and Safety
PARS  Publicly Available Records
PC    Procedure Call-Up
PMP  Probable Maximum Precipitation
PMT  Post Maintenance Test
PRA  Probabilistic Risk Assessment
PWR  Pressurized Water Reactor
RASP  Risk Assessment Standardization Project
                                  10


Enclosure: IR 05000266/2014007; 05000301/2014007  w/Attachment:  Supplemental Information cc w/encl:  Distribution via ListServTM  Distribution
RC    Root Cause
: See next page
RCE    Root Cause Evaluation
    
ROP    Reactor Oversight Process
SCWE   Safety Conscience Work Environment
SDP    Significance Determination Process
SME   Subject Matter Expert
    
SPAR  Standardized Plant Analysis Risk
SQAC  Significant Condition Adverse to Quality
DOCUMENT NAME:  PB 2014 007  Publicly Available  Non-Publicly Available 
SRA   Senior Reactor Analyst
Sensitive  Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
SW    Service Water
  OFFICE  RIII   RIII  RIII 
TDAFWP Turbine Driven Auxiliary Feedwater Pump
RIII  NAME  BBartlett:mt/rj
TB     Turbine Building
JCameron BBartlett for
TS    Technical Specification
     DATE  04/27/14  04/27/14 
URI    Unresolved Item
  OFFICIAL RECORD COPY 
VTM    Vendor Technical Manual
  Letter to Eric McCartney from Ann Boland dated March 28, 2014
Yr    Year
WO    Work Order
SUBJECT:  POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2  NRC 95002 SUPPLEMENTAL INSPECTION REPORT 05000266/2014007; 05000301/2014007
                                  11
DISTRIBUTION
: Ernesto Quinones


RidsNrrDorlLpl3-1 Resource RidsNrrPMPointBeach
E. McCartney                                                              -3-
RidsNrrDirsIrib Resource
previous terminology will be converted to the latest revision in accordance with the
Cynthia Pederson
cross-reference in IMC 0310. The revised cross-cutting aspects will be evaluated for
cross-cutting themes and potential substantive cross-cutting issues in accordance with
IMC-0305 starting with the CY 2014 mid-cycle assessment review.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and
its enclosure, and your response (if any) will be available electronically for public inspection in
the NRC Public Document Room or from the Publicly Available Records System (PARS)
component of NRC's Agencywide Documents Access and Management System (ADAMS),
accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public
Electronic Reading Room).
                                                                          Sincerely,
                                                                          /RA/
                                                                          Anne T. Boland, Director
                                                                          Division of Reactor Projects
Docket Nos. 50-266; 50-301
License Nos. DPR-24; DPR-27
Enclosure:
IR 05000266/2014007; 05000301/2014007
  w/Attachment: Supplemental Information
cc w/encl: Distribution via ListServTM
Distribution:
See next page
DOCUMENT NAME: PB 2014 007
    Publicly Available                          Non-Publicly Available                              Sensitive                  Non-Sensitive
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
  OFFICE              RIII                                RIII                            RIII                              RIII
NAME                BBartlett:mt/rj                    JCameron
                                                        BBartlett for
DATE                04/27/14                            04/27/14
                                                          OFFICIAL RECORD COPY


Darrell Roberts  
Letter to Eric McCartney from Ann Boland dated March 28, 2014
Steven Orth  
SUBJECT: POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2
Allan Barker  
            NRC 95002 SUPPLEMENTAL INSPECTION REPORT
Carole Ariano  
            05000266/2014007; 05000301/2014007
Linda Linn  
DISTRIBUTION:
DRPIII  
Ernesto Quinones
DRSIII Patricia Buckley ROPassessment.Resource@nrc.gov
RidsNrrDorlLpl3-1 Resource
RidsNrrPMPointBeach
RidsNrrDirsIrib Resource
Cynthia Pederson
Darrell Roberts
Steven Orth
Allan Barker
Carole Ariano
Linda Linn
DRPIII
DRSIII
Patricia Buckley
ROPassessment.Resource@nrc.gov
}}
}}

Latest revision as of 07:18, 4 November 2019

IR 05000266-14-007, 05000301-14-007; 02/03/2014 - 03/06/2014; Point Beach Nuclear Plant, Units 1 and 2; Supplemental Inspection -Inspection Procedure (IP) 95002, Supplemental Inspection for One Degraded Cornerstone..
ML14087A366
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 03/28/2014
From: Boland A
Division Reactor Projects III
To: Mccartney E
Point Beach
References
EA-12-009, EA-13-125 IR-14-007
Download: ML14087A366 (58)


See also: IR 05000266/2014007

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, IL 60532-4352

March 28, 2014

EA-12-009

EA-13-125

Mr. Eric McCartney

Site Vice President

NextEra Energy Point Beach, LLC

6610 Nuclear Road

Two Rivers, WI 54241

SUBJECT: POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2

NRC 95002 SUPPLEMENTAL INSPECTION REPORT

05000266/2014007; 05000301/2014007

Dear Mr. McCartney:

On March 6, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed a follow-up

supplemental inspection pursuant to Inspection Procedure 95002, Supplemental Inspection for

One Degraded Cornerstone or any Three White Inputs in a Strategic Performance Area, at

your Point Beach Nuclear Plant, Units 1 and 2. The enclosed report documents the results of

this inspection, which were discussed at the exit on March 6, 2014, with you and other members

of your staff.

In accordance with the NRC Reactor Oversight Process (ROP), this follow-up supplemental

inspection was performed to assess the White inspection finding for the failure of the Unit 1

Turbine Driven Auxiliary Feedwater Pump (TDAFWP) and the White inspection finding for

external wave run-up flooding. These two White findings both in the Mitigating Systems

Cornerstone placed Point Beach Unit 1 in a degraded cornerstone as of the first quarter of

2013. In addition to these two White findings we requested that you also include in your

assessment the White finding in the Emergency Preparedness (EP) Cornerstone that had been

issued on July 24, 2012. A 95001, Supplemental Inspection for One or Two Inputs in a

Strategic Performance Area, had previously been performed for the White EP finding and the

White TDAFWP finding.

The NRC staff was informed on October 29, 2013, of your readiness, as of that date for us to

conduct this supplemental inspection.

The objectives of this supplemental inspection were to: (1) provide assurance that the root

causes and the contributing causes for the risk significant issues were understood;

(2) independently assess and provide assurance that the extent of condition and extent of cause

of the individual and collective issues were identified; (3) determine if safety culture components

caused or significantly contributed to the individual or collective issues; and (4) provide

assurance that the corrective actions were or will be sufficient to address and preclude

repetition of the root and contributing causes.

E. McCartney -2-

The inspection consisted of an examination of activities conducted under your license as they

related to safety, compliance with the Commissions rules and regulations, and the conditions of

your operating license. The inspectors reviewed selected procedures and records, observed

activities, and interviewed personnel.

Based on the results of the inspection, the NRC determined that Point Beach had performed an

acceptable evaluation of the White EP finding and the White TDAFWP finding but had not

performed an acceptable evaluation of the White flooding finding and had not performed an

acceptable evaluation of the collective White inputs. Taken collectively the issues associated

with the White flooding finding represented a significant weakness, as discussed in Inspection

Procedure (IP) 95002, and your actions to date have not provided the assurance level required

to meet the inspection objectives. The inspection determined that your staff failed to adequately

evaluate the root causes, contributing causes, extent-of-condition, or extent-of-cause of the

safety-significant finding, and take or plan adequate corrective actions to address the root

causes, contributing causes, extent-of-condition, or extent-of-cause and to prevent recurrence

of the safety-significant finding. The White finding associated with Notice of Violation (NOV)05000266/2013002-10 and 05000301/2013002-10 will be held open. Specific items are

discussed in additional detail in each section of the attached inspection report.

When informed of your readiness, a future inspection will be conducted to verify the corrective

actions that your staff has put in place to address and preclude a repetition of the White flooding

finding.

Based on the results of this inspection, three NRC-identified findings of very low safety

significance (Green) that involved violations of NRC requirements were identified. The NRC

identified an additional Green finding that was associated with a Severity Level IV violation of

NRC requirements evaluated through the traditional enforcement process. However, because

of their very low safety significance, and because these issues were entered into your corrective

action program, the NRC is treating these violations as non-cited violations (NCVs) in

accordance with Section 2.3.2 of the NRC Enforcement Policy.

If you contest the subject or severity of these NCVs, you should provide a response within

30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear

Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a

copy to the Regional Administrator, U.S. Nuclear Regulatory Commission - Region III,

2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement,

U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector

Office at the Point Beach Nuclear Plant. In addition, if you disagree with the cross-cutting

aspect assigned to any finding in this report, you should provide a response within 30 days of

the date of this inspection report, with the basis for your disagreement, to the Regional

Administrator, Region III, and the NRC Resident Inspector at the Point Beach Nuclear Plant.

As a result of the Safety Culture Common Language Initiative, the terminology and coding of

cross-cutting aspects were revised beginning in calendar year (CY) 2014. New cross-cutting

aspects identified in CY 2014 will be coded under the latest revision to Inspection Manual

Chapter (IMC) 0310. Cross-cutting aspects identified in the last six months of 2013 using the

E. McCartney -3-

previous terminology will be converted to the latest revision in accordance with the

cross-reference in IMC 0310. The revised cross-cutting aspects will be evaluated for

cross-cutting themes and potential substantive cross-cutting issues in accordance with

IMC-0305 starting with the CY 2014 mid-cycle assessment review.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and

its enclosure, and your response (if any) will be available electronically for public inspection in

the NRC Public Document Room or from the Publicly Available Records System (PARS)

component of NRC's Agencywide Documents Access and Management System (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

Anne T. Boland, Director

Division of Reactor Projects

Docket Nos. 50-266; 50-301

License Nos. DPR-24; DPR-27

Enclosure:

IR 05000266/2014007; 05000301/2014007

w/Attachment: Supplemental Information

cc w/encl: Distribution via ListServTM

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket Nos: 05000266; 05000301

License Nos: DPR-24; DPR-27

Report No: 05000266/2014007; 05000301/2014007

Licensee: NextEra Energy Point Beach, LLC

Facility: Point Beach Nuclear Plant, Units 1 and 2

Location: Two Rivers, WI

Dates: February 3, 2014, through March 6, 2014

Inspectors: B. Bartlett, Project Engineer

J. Beavers, Emergency Preparedness Inspector

R. Elliott, Acting Resident Inspector, Point Beach

J. Jandovitz, Project Engineer

K. Miller, Resident Inspector, Watts Bar

P. Voss, Resident Inspector, Monticello

Approved by: J. Cameron, Chief

Branch 4

Division of Reactor Projects

Enclosure

SUMMARY OF FINDINGS

Inspection Report (IR) 05000266/2014007, 05000301/2014007; 02/03/2014 - 03/06/2014;

Point Beach Nuclear Plant, Units 1 and 2; Supplemental Inspection - Inspection Procedure

(IP) 95002, Supplemental Inspection for One Degraded Cornerstone or any Three White Inputs

in a Strategic Performance Area.

This inspection was conducted by three regional inspectors and three resident inspectors. The

inspectors identified three NRC-identified findings of very low safety significance (Green) that

involved violations of NRC requirements. The NRC identified an additional Green finding that

was associated with a Severity Level IV violation of NRC requirements evaluated through the

traditional enforcement process. The significance of most findings is indicated by their color

(Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, Significance

Determination Process (SDP). Assigned cross-cutting aspects were determined using

IMC 0310, Components Within the Cross-Cutting Areas. Findings for which the SDP does not

apply may be Green or be assigned a severity level after NRC management review. The NRCs

program for overseeing the safe operation of commercial nuclear power reactors is described in

NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.

Cornerstone: Mitigating Systems

The NRC staff performed this follow-up supplemental inspection in accordance with

Inspection Procedure 95002, Inspection for One Degraded Cornerstone or Any Three

White Inputs in a Strategic Performance Area, to continue to assess the licensees

evaluation of two White inspection findings that affected the Mitigating Systems Cornerstone.

The inspection team determined that the licensee performed an adequate evaluation of some of

the issues, but failed to perform an adequate evaluation of some issues. The inspection team

determined that the root cause evaluation for the Turbine Driven Auxiliary Feedwater Pump

(TDAFWP) appropriately evaluated the root and contributing causes, adequately addressed the

extent of condition and cause, assessed safety culture, and established corrective actions for

the risk significant performance issues. However, the inspection team determined that for the

flooding White finding that the licensee failed to appropriately evaluate the root and contributing

causes, failed to adequately address the extent of condition and cause, failed to adequately

assess safety culture, and failed to establish adequate corrective actions. In addition to

assessing the licensees evaluations, the inspection team independently performed an extent of

condition and extent of cause review of the two findings and a review of the site safety culture

as it related to the root cause evaluations. The team concluded that the licensees root cause

evaluations and corrective actions, both completed and planned, were sufficient to address the

causes and prevent recurrence for the TDAFWP White finding but had significant weaknesses

resulting in failure for the flooding White finding. The licensees implementation of corrective

actions for the TDAFWP will be reviewed during future inspections.

2

A. NRC-Identified and Self-Revealed Findings

  • Green. The inspectors identified a finding of very low safety significance and associated

non-citied violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Actions, in

that from March 13, 2013 until February 14, 2014, the licensee failed to assure that for a

significant condition adverse to quality (SQAC), the cause of the condition was

determined and corrective actions were taken to preclude repetition. Specifically, the

licensees corrective actions failed to preclude repetition of an SQAC where Procedure

PC 80 Part 7, Lake Water Level Determination, as implemented, would not protect

safety-related equipment in the turbine building or Circulating Water Pump House

(CWPH). After the licensee had taken corrective actions to improve the wave barrier

procedure in response to an NRC-identified NOV, PC 80 Part 7 and other flood

protection implementing procedures specified inadequate timelines to ensure wave

run-up flood barriers would be installed prior to the lake level at which wave run-up could

impact the site. Corrective actions for this issue included changing the affected

procedures to install the wave barriers at a lower lake level, changing the lake level

determination surveillance from monthly to weekly, and reducing the allowed installation

time for the barriers from 3 weeks to 1 week.

The performance deficiency was screened against the Reactor Oversight Process per

the guidance of lMC 0612, Appendix B, and determined to be more than minor because

the finding was associated with the Mitigating Systems Cornerstone attributes of

Protection Against External Factors (Flood Hazard) and Procedure Quality, and

adversely affected the cornerstone objective to ensure the availability, reliability, and

capability of systems that respond to initiating events to prevent undesirable

consequences (i.e. core damage). Specifically, the licensees failure to correct

procedural deficiencies associated with flood barrier construction timelines, could

challenge the timely installation of the barriers, which could impact the ability of

mitigating systems to respond during an external flooding event. The inspectors

evaluated the finding using IMC 0609, Attachment 0609.04, Tables 2 and 3, and

Appendix A. Based on a review of Appendix A, Exhibit 2, Item 4.B, the inspectors

determined that this issue screened as having very low safety significance (Green).

This finding has a cross-cutting aspect in the area of problem identification and

resolution, because the licensee failed to thoroughly evaluate issues to ensure that

resolutions address causes and extent of conditions commensurate with their safety

significance. (P.2)

  • Green. The inspectors identified a finding of very low safety significance and associated

non-citied violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions,

Procedures, and Drawings, in that from January 19, 1996 until November 25, 2013, the

licensee failed to ensure that activities affecting quality were prescribed by documented

procedures of a type appropriate to the circumstances to address external flooding as

described in the Final Safety Analysis Report (FSAR). Specifically, PC 80 Part 7, Lake

Water Level Determination directed advanced installation of concrete barriers to protect

against deep wave action from the lake, which introduced significant unrecognized

blockages in the natural drainage path credited in the FSAR to protect against the

probable maximum precipitation and Turbine Building internal flooding events.

Corrective actions for this issue included changing the procedure and FSAR to include

actions to provide an additional flood relief path through the CWPH building and reliance

on internal flood relief dampers for the affected flooding events.

3

The performance deficiency was screened against the Reactor Oversight Process per

the guidance of lMC 0612, Appendix B, and determined to be more than minor because

the finding was associated with the Mitigating Systems Cornerstone attributes of

Protection Against External Factors (Flood Hazard) and Procedure Quality, and

adversely affected the cornerstone objective to ensure the availability, reliability, and

capability of systems that respond to initiating events to prevent undesirable

consequences (i.e. core damage). Specifically, the licensees failure to procedurally

control external flooding design features to ensure they would not adversely affect the

strategy for other flooding events, could negatively impact mitigating systems ability to

respond during external and internal flooding events. The inspectors evaluated the

finding using IMC 0609, Attachment 0609.04, Tables 2 and 3, and Appendix A, and

determined a detailed risk evaluation was required. Following a detailed risk evaluation,

Region III SRAs determined that the finding had very low safety significance (Green).

This finding has a cross-cutting aspect in the area of problem identification and

resolution, because the licensee failed to take effective corrective actions to address

issues in a timely manner commensurate with their safety significance. (P.3)

  • Severity Level IV: The inspectors identified a finding of very low safety significance and

associated Severity Level IV, non-citied violation of 10 CFR 50.59(d)(1), Changes, tests

and experiments, when, on November 25, 2013, the licensee failed to perform an

evaluation against the criteria in 10 CFR 50.59(c)(2) for a change to procedure

PC 80 Part 7 to include actions to maintain functionality of drainage paths during

probable maximum precipitation and turbine building flooding events. Specifically,

PC 80 Part 7, Lake Water Level Determination was changed to include actions to open

the CWPH rollup doors to provide an additional drainage path while wave barriers were

in place, without fully evaluating the viability of reliance on additional flood features not

credited for external flooding in the Current License Basis (CLB). Corrective actions for

this issue included to updating the FSAR to describe the new flood paths, performing a

10 CFR 50.59 screening and 10 CFR 50.59 evaluation for the new drainage path which

had put the site outside of the CLB, revising a related functionality assessment,

controlling external flooding areas to ensure they are clear of debris, and creating a

procedure to install curtains on the CWPH rollup doors during periods when they were

required to be open.

The inspectors determined that the licensees failure to fully evaluate the viability of

newly created flooding drainage paths as required by 10 CFR 50.59(d)(1) was a

performance deficiency. The inspectors evaluated the performance deficiency using

traditional enforcement in conjunction with the SDP because the performance deficiency

had the potential to impact the regulatory process. The performance deficiency was

screened per the guidance of lMC 0612, Appendix B, and determined to be more than

minor because the finding was associated with the Mitigating Systems Cornerstone

attributes of Protection Against External Factors (Flood Hazard) and Design Control, and

adversely affected the cornerstone objective to ensure the availability, reliability, and

capability of systems that respond to initiating events to prevent undesirable

consequences (i.e. core damage). Specifically, the licensee did not fully demonstrate

that the availability, reliability, and capability of mitigating systems would be maintained

during flooding events due to the sites failure to evaluate the viability of alternate flood

drainage paths through the CWPH. The inspectors evaluated the finding using

IMC 0609, Attachment 0609.04, Tables 2 and 3, and Appendix A. Based on a review of

Appendix A, Exhibit 2, Item 4.B, the inspectors determined that this issue screened as

4

having very low safety significance (Green). Additionally, in accordance with

Section 6.1.d.2 of the NRC Enforcement Policy, this violation is categorized as a

Severity Level IV because the resulting conditions were evaluated as having very low

safety significance (Green) by the SDP. This finding has a cross-cutting aspect in the

area of problem identification and resolution, because the licensee failed to thoroughly

evaluate issues to ensure that resolutions address causes and extent of conditions

commensurate with their safety significance. (P.2)

  • Green. The inspectors identified a finding of very low safety significance (Green) and

associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions,

Procedures, and Drawings, for the failure to ensure the effectiveness review attributes

for a significant condition adverse to quality would ensure the corrective actions would

eliminate or reduce the recurrence rate.

The inspectors determined that the licensees failure to establish effectiveness review

criteria that would have identified whether the corrective action to prevent recurrence

(CAPRs) had effectively resolved the conditions was a performance deficiency

warranting further review. The inspectors determined that this finding was more than

minor in accordance with IMC 0612, Appendix B, because it was affected the Mitigating

Systems Cornerstone objective to ensure availability, reliability, and capability of

systems that respond to initiating events to prevent undesirable consequences. If left

uncorrected, would the performance deficiency have the potential to lead to a more

significant safety concern? The inspectors evaluated the finding using IMC 0609,

Appendix A. The inspectors determined the finding was of very low safety significance

(Green) because the finding was not a deficiency affecting the design or qualification of

a mitigating structure, system or component and did not result in a loss of operability or

functionality. In addition, the finding did not represent a loss of system or function, did

not represent an actual loss of function of a least a single train for longer than its

technical specification allowed outage time, and did not represent an actual loss of

function of one or more nontechnical specification trains of equipment designated as

high safety-significance.

The finding had a cross cutting aspect in the area of problem identification and

resolution, specifically resolution, because licensee personnel failed to ensure the

corrective actions to prevent recurrence had effective attributes. (P.2)

5

REPORT DETAILS

4. OTHER ACTIVITIES

Cornerstone: Mitigating Systems

4OA4 Supplemental Inspection (95002)

a. Inspection Scope

The NRC staff performed this follow-up supplemental inspection in accordance with

inspection procedure (IP) 95002, Inspection for One Degraded Cornerstone or Any

Three White Inputs in a Strategic Performance Area, to assess the White inspection

finding for the failure of the Unit 1 Turbine Driven Auxiliary Feedwater Pump (TDAFWP)

and the White inspection finding for external wave run-up flooding. In addition to these

two White findings the licensee was requested to also include in their assessment the

White finding in the Emergency Preparedness (EP) Cornerstone that had been issued

on July 24, 2012. A 95001, Supplemental Inspection for One or Two Inputs in a

Strategic Performance Area, had previously been performed for the White EP finding

and the White TDAFWP finding.

The objectives of the supplemental inspection included:

  • To provide assurance that the root and contributing causes for the White findings

are understood.

  • To determine if the licensees corrective actions for risk-significant performance

issues are sufficient to address the root and contributing causes and prevent

recurrence.

  • To independently assess the extent of condition and the extent of cause for

individual and collective risk-significant performance issues.

  • To assess the safety culture as a possible contributor.

The inspectors reviewed the Root Cause Evaluations (RCE), in addition to other

assessments, evaluations, and corrective action program documentation completed in

support of and, as a result of, the RCEs. The inspectors reviewed corrective actions that

were taken or planned to address the identified causes. The inspectors interviewed

selected station, corporate, and contractor personnel, and held discussions with these

individuals to verify that the root and contributing causes and the contribution of safety

culture components were understood and that corrective actions taken or planned were

appropriate to address the causes and preclude repetition.

For clarity, documentation of each inspection requirement contains subsections for each

of the two White mitigating systems findings. The White EP finding was assessed by the

inspection team only as it related to commonalities to the other White findings and this is

not individually discussed in this report.

Documents reviewed during this inspection are listed in the Attachment.

6

Inspection Results

The four attributes of IP 95002 were reviewed for each of the three White findings plus

the common cause analysis performed by the licensee. Thus there were a total of 16

attributes that were reviewed. The inspectors concluded that for the White EP finding

and the White TDAFWP finding that the licensee understood the root and contributing

causes. In addition, the inspectors performed the independent extent of condition and

extent of causes and assessed the licensees corrective actions for these two White

findings and concluded that the licensees actions were sufficient. Finally, the inspectors

determined that the safety culture aspects for these two White findings were adequate

although there were safety culture components that contributed to the common cause

analysis conclusions and that corrective actions had been taken to address these

conclusions. Thus of the total of 16 attributes, eight were closed. The inspectors

determined that the root causes, extent of condition, extent of cause, corrective actions

and safety culture aspects for the White flooding finding and the common cause analysis

(CCA) were not sufficient and remain open.

.02 Evaluation of the Inspection Requirements

02.01 Problem Identification

a. Determine that the Evaluation Documented Who Identified the Issue (i.e., Licensee-

Identified, Self-Revealing, or NRC-Identified) and Under What Conditions the Issue was

Identified

The inspectors determined that neither of the RCEs for the two White findings nor the

CCA specifically addressed who identified the issues. The RCE for the TDAFWP White

finding had enough information to infer that the finding was self-revealed but the RCE for

the flooding White finding contained only a minimal inference that a NRC finding had

been issued. The CCA had remarks similar to the flooding RCE that stated that NRC

had issued White findings but again the inspectors had to infer how the findings were

identified. There were no statements in any licensee documentation or as a result of

interviews with licensee management indicating the licensee disagreed with the findings.

The licensee clearly stated the conditions under which the issues were identified. The

inspectors considered the failure to clearly state who identified the issue to be a

weakness for the TDAFWP White finding but not significant enough to leave this item

open. For the TDAFWP White finding, this aspect of IP 95002 is closed. The inspectors

concluded that the licensee failed to clearly document who identified the issue for the

White flooding finding and the CCA and this aspect of IP 95002 was not met.

b. Determine that the Evaluation Documented How Long the Issues Existed and Prior

Opportunities for Identification

The licensees evaluation for the TDAFWP White finding documented that pump to

turbine alignment issues had existed for many years and that each time the pump was

determined to be out of alignment it had been restored to within allowable limits. The

inspectors determined that the licensees evaluation was adequate with respect to

identifying how long the issue existed and prior opportunities for identification.

7

The licensees evaluation for the flooding White finding documented that the change to

the methodology of protecting the site from external lake flooding had been done in

January of 1996. The licensees evaluation also documented some prior missed

opportunities to identify; however, the evaluation failed to address other significant prior

opportunities. As discussed further in various sections of the report, the inspectors

observed that licensee personnel implemented corrective actions that significantly

impacted other license basis events but failed to recognize these impacts. Thus, there

were additional opportunities to identify which were not listed or discussed in the

licensees RCE. The inspectors determined that the licensees evaluation was not

adequate with respect to identifying how long the issue existed and prior opportunities

for identification. This aspect of IP 95002 remains open for the flooding White finding.

c. Determine that the Evaluation Documented the Plant Specific Risk Consequences, As

Applicable, and Compliance Concerns with the Issues Both Individually and Collectively

The risk evaluation performed by the licensee in discussions with the NRC Senior

Reactor Analyst (SRA) prior to issuance of the TDAFWP White finding was not the one

utilized by the licensee for the subsequent RCE. The licensees RCE, stated, in part, In

order to quickly evaluate the safety significance of this issue, the Safety Monitor program

was used by the probabilistic risk assessment (PRA) group. The NRC team did not

understand the need to quickly perform a risk assessment since one had previously

been performed and discussed with an NRC SRA. Nevertheless, the licensee chose to

perform one, but selected a program that did not align with standard NRC significance

determination techniques. The licensees Safety Monitor program is used to monitor on

line risk in a moment to moment manner and use of the program to calculate the risk

consequence for the TDAFWP failure was neither accurate nor appropriate. The team

discussed the licensees risk significance with the NRC SRA who performed the original

assessment and the SRA verified that the licensee had understood and agreed with the

original NRC conclusions. The purpose of this reassessment and write-up was not

understood either by the SRA nor the team. The inspectors also determined that the

licensee had issued a Licensee Event Report for the failure of the TDAFWP and

appropriately entered the failure in the Maintenance Rule database and the Performance

Indicators. Based upon the licensees previous demonstrated knowledge and

understanding of the risk significance of this item, the inspectors concluded that the risk

and compliance portion was weak, but that this fundamental aspect of IP95002 had

been met.

The risk evaluation performed by the licensee for the flooding White finding enforcement

conference was not accepted by the NRC although portions of the licensees

assessment was recognized as acceptable and used to ensure the NRC position was

accurate. Nevertheless, the licensee chose to repeat the previously determined

unsatisfactory risk assessment in the flooding White RCE. In the NRC Final Significance

Determination of a White Finding, dated August 9, 2013, Enclosure 2 provided an

analysis of the licensee risk information. In this analysis the NRC disagreed with the

licensees risk assessment in a number of significant ways, yet these disagreements

appeared to not be factored into the licensees subsequent risk assessment documented

in the associated RCE. The inspectors review of the flooding RCE determined that the

licensee did not address possible compliance concerns or reportability.

8

During interviews, individuals directly involved in responding to the finding cited internal

supplemental calculations, and stated that they believed there would not have been any

consequences to the plant as a result of the finding. Interviewees stated that the

findings risk significance came only from significant conservatisms used in the individual

plant examination external events (IPEEE) evaluation, and not from potential plant

consequences. Interviews with individuals not directly involved in addressing the

flooding finding revealed that working level plant personnel were familiar with the

flooding finding, but their awareness was focused more on the regulatory impacts, with

minimal awareness of potential equipment impacts.

The inspectors concluded that the licensee failed to adequately address the plant

specific risk consequences or compliance concerns related to the flooding White finding

and this aspect of IP 95002 was not met.

d. Findings

No findings were identified.

02.02 Root Cause

a. Determine that the Problem was Evaluated Using a Systematic Methodology to Identify

the Root and Contributing Causes

The inspectors reviewed the licensees RCEs, CCA, and other documents related to the

White findings. The licensee identified a total of four root causes and seven contributing

causes using a systematic methodology. In addition, the licensees CCA identified two

common causes and two contributing causes. The licensee utilized support-refute

matrix, change analysis, barrier analysis, a cause and effects diagram, an event and

causal factor chart, and a why staircase during the two root cause assessments and

the CCA. The inspectors determined that the RCE and CCA were conducted to a level

of detail commensurate with the significance of the issues. The licensees evaluations

included details of each item along with supporting data and other information.

The licensees use of systematic methodology to identify the root and contributing

causes was determined to be adequate for the TDAFWP White finding. Due to the

significant weaknesses identified in the licensees corrective actions, extent of condition,

extent of cause, and root cause, the team concluded that this aspect for the flooding

White finding was negatively impacted. This aspect of IP 95002 will remain open for the

flooding White finding.

b. Determine that the Root Cause Evaluation was Conducted to a Level of Detail

Commensurate with the Significance of the Problem

The licensee utilized the systematic methodologies for the CCA discussed above and

determined that the primary root causes were:

  • Less than adequate understanding of the design and licensing basis;
  • Corrective Action Program items with incorrect priorities;
  • Original construction stress riser introduced to the TDAFWP;

9

  • A lack of or inadequate leadership; and
  • Poor technical procedure quality.

The inspectors noted that while the licensee had poor procedure quality as a root cause

for the TDAFWP issue, the knowledge, skills, and abilities (KSA) of the workers was not

considered as a possible root cause. For example, the TDAFWP alignment procedure

did not require the taking of as-found data nor did the procedure require that if the data

was taken that it be reviewed by engineering personnel. Yet, a qualified maintenance

mechanic would have experience with the need to take such data and would know to

pass it along to their supervisor. The inspectors performed a search of the licensees

CAP database to see if a trend of issues with a cause of KSA existed and did not identify

any trends. The licensees RCEs should have discussed this aspect in sufficient detail

so as to demonstrate that this was not a root cause.

Despite the weakness noted above, the inspectors determined that the RCE for the

TDAFWP White finding was conducted to a level of detail commensurate with the

significance of the issues.

For the flooding White finding and the CCA root cause the inspectors observed that

problems with the quality of condition report evaluations and with Functionality

Assessments (FA) were identified but not included as either a root cause or a

contributing cause. The inspectors also noted that an assessment of the licensees CCA

performed prior to the team arriving on site (Quick Hit PBSA-PBNP-13-03) had a similar

observation and a recommendation to clearly articulate this theme. The inspectors

determined that neither a root cause nor a contributing cause was assigned to either

corrective action program quality or CR evaluations. One CAPR was assigned to

improve the quality of FAs. This is discussed in more detail in Section 02.04, below.

While corrective action program evaluation quality was a part of the issues identified, the

failure of the licensee to either include it as a root cause or to justify why it was not a root

cause was a significant weakness.

The inspectors determined that this aspect of the IP 95002 criteria was not met for the

flooding White finding and the CCA.

c. Determine that the Root Cause Evaluation Included a Consideration of Prior

Occurrences of the Problem and Knowledge of Prior Operating Experience

The inspectors determined that the licensees evaluation included a consideration of

prior occurrences of the issues and industry operating experience. The RCE for the

TDAFWP determined that a prior opportunity was missed in early 2011 during the Unit 2

refueling outage when pipe stresses were identified on the opposite unit TDAFWP. The

licensee determined that even though the pipe stresses were identified and corrected

that a CR was not issued and thus the opportunity to apply this information to the next

Unit 1 refueling outage and TDAFWP maintenance activity was missed.

The inspectors concluded that the root cause evaluation included a review of prior and

precursor problems and properly evaluated internal and industry operating experience.

This aspect of the IP 95002 criteria was met for the TDAFWP finding.

10

The RCE for the White flooding finding determined that prior opportunities were missed

to properly correct the deficiency. This included opportunities in 2004, when condition

reports were generated questioning the adequacy of the wave run-up barriers, given the

1996 procedure change. This also included opportunities in 2012 where a functionality

assessment inappropriately contained conclusions regarding the functionality of the

wave barriers on perceived risk. The inspectors noted that these opportunities were

factored into the determination of one of the root causes. The inspectors also noted the

RCE discussion on industry OE and noted several instances where the causes of

industry deficiencies were similar to the causal factors identified for the White flooding

issue

As discussed later in this inspection report unintended consequences were introduced

during the corrective actions to the White flooding finding. The failure to recognize these

consequences represented additional occurrences of the problem. The inspectors

determined that this aspect of the IP 95002 criteria was not met for the flooding White

finding and the CCA.

d. Determine that the Root Cause Evaluation Addresses the Extent of Condition and the

Extent of Cause of the Problem

The licensees RCE included an evaluation of the extent of condition and extent of cause

of the issues. The inspectors determined that the RCE for the TDAFWP issue was

adequate with comments. These comments are discussed in section 02.04 of this

report. The inspectors also noted that during an assessment of the licensees RCE that

was performed prior to the team arriving on site (Quick Hit PBSA-PBNP-13-03) that

deficiencies with the TDAFWP had been identified. For example, the extent of condition

prior to the Quick Hit was limited to rotating couplings of the same make and model as

that which had failed on the Unit 1 TDAFWP. Following a recommendation of the Quick

Hit team, the licensee had expanded the extent of condition to include other make and

model couplings as well as all rotating connections. Based on a review of the RCE and

CCA and discussions with licensee management and staff personnel, the inspectors

concluded that the evaluations for the TDAFWP White finding adequately addressed the

extent of condition and the extent of cause. This aspect of the IP 95002 was not for the

TDAFWP finding.

The inspectors determined that the RCE for the flooding White finding also included an

evaluation of the extent of condition and extent of cause but based on the NRC findings

documented in Section 02.04 of this report the inspectors concluded that this item was

not acceptable. For example, the RCE did not consider possible bypass paths around

the external flooding barrier. During field walk downs, the inspectors identified two

different drain pipes in the concrete near the CWPH which directly communicated with

the lake shore and should have been evaluated as possible bypass paths. The

inspectors concluded that the evaluations for the flooding White finding did not satisfy

this aspect of the IP 95002 criteria.

e. Findings

No findings were identified.

11

02.03 Corrective Actions

a. Determine that Appropriate Corrective Actions are Specified for Each Root and

Contributing Cause or that the Licensee has an Adequate Evaluation for Why No

Corrective Actions are Necessary

The inspectors assessed the corrective actions for the RCEs and the CCA. The

inspectors verified that all root causes had associated CAPRs and that all contributing

causes had associated corrective actions. The inspectors then performed a more

detailed assessment of selected CAPRs and corrective actions. The detailed

assessment included a sample of corrective action program documents, field walk

downs, interviews with selected licensee individuals, and reviews of the design and

licensing basis.

The inspectors concluded that the corrective actions for the TDAFWP finding were

vague and needed additional clarification. As previously noted, the scope of the root

cause was narrowly focused but this had previously been identified by an internal

licensee review. As a result, the scope of the corrective actions had been expanded to

include other rotating equipment connections. Additional corrective actions were

reviewed by the inspectors with no further substantive observations. The inspectors

concluded that the CAPRs and corrective actions for the TDAFWP met the requirements

of IP 95002.

During the reviews of the corrective action program documents, the inspectors noted

that the licensee questioned whether the installation of the flood protection barriers had

introduced unintended consequences. Specifically, the corrective action to install a

more robust wave barrier in lieu of sandbagging efforts failed to restore compliance with

the CLB. While the improved wave barriers provided necessary protection against wave

action, they introduced unrecognized hazards during the probable maximum

precipitation and turbine building internal flooding events. These barriers blocked

natural drainage paths credited for flood relief and rendered these paths nonfunctional

as a result of wave barrier installation. The inspectors noted that this issue was not

recognized by the licensee until November 2013 for one of the flooding events, and

January 2014 for the other event, and thus, the licensees interim corrective actions for

the flooding finding were deficient between March and November 2013 due to procedure

call-up PC 80 Part 7, which remained inadequate during this time. As a result, the

licensee was required to add compensatory actions during wave barrier installation to

provide additional flow paths by opening the CWPH roll-up doors.

When developing the compensatory action to address the deficiency associated with the

new wave barriers, the licensee failed to recognize that the new compensatory

measures required actions outside of the CLB. Specifically, Section 2.5 Hydrology in

the FSAR for the Maximum precipitation flood states, in part, that the topography of

the site results in adequate natural drainage to remove this amount of water and limit

ponding depth to prevent adversely affecting safety related equipment. The

nonfunctional drainage paths following wave barrier installation resulted in the licensee

having to identify an alternate path for flood water drainage flow. As a compensatory

action, the licensee chose to open the CWPH roll-up doors, route flood waters through

the CWPH, and relying on internal flood relief dampers to open and drain the water. The

licensee viewed those compensatory actions as still with its CLB. As a result, the

12

inspectors determined that the licensee failed to properly screen the actions as

compensatory measures under the requirements of 10 CFR 50.59.

The inspectors noted that as a result of the failure to evaluate these actions under

10 CFR 50.59, the licensee did not properly consider several factors associated with the

compensatory actions that should have been evaluated. Some of these factors included

flood water flow rates through the open doors, the impact of debris and slush from

outside being carried into the CWPH and clogging the flood relief dampers, the impact of

the cold temperatures on the equipment in the rooms during the potentially extended

periods of time during which the doors could be open, and security impacts.

In addition, the inspectors noted the licensee failed to recognize that procedure

PC 80 Part 7, failed to account for the time necessary to ensure that the barriers would

be constructed before the lake reached conditions where deep wave action could impact

the site. Specifically, the licensees calculation specified that 8.2 weeks would be

available after Procedure PC 80 Part 7, initiated actions to install the wave barriers

based on lake level.

The inspectors reviewed EC 279455, Time Available to Respond to Threat From Rising

Water, and the licensees lake level determination monthly surveillance, PBF-2124,

PPCS Forebay and Pump Bay Level Alarm Setpoints, and identified several

deficiencies. These deficiencies included non-conservative assumptions when using the

maximum monthly rate of lake level rise, non-conservative assumptions for the lake level

at which the site could be impacted by the waves, a non-conservative allowance to rely

on the previous months data if no lake level data was immediately available, and an

error in an assumption that wave barriers would be installed earlier than PC 80 Part 7,

actually required. When the licensee corrected these inputs, the inspectors noted that

the time available for action was significantly reduced to less than three weeks.

The inspectors observed that PC 80 Part 7, granted three weeks allowance for activities

to be scheduled and performed to install the wave barriers. The inspectors concluded

that the deficiencies in the licensees timelines left them vulnerable in that actions may

not have been initiated soon enough to protect the site from the wave run-up design

basis event. The inspectors determined that this aspect of IP 95002 was not met for the

flooding White finding.

b. Determine that the Corrective Actions Have Been Prioritized with Consideration of Risk-

Significance and Regulatory Compliance

The inspectors assessed the licensees timeliness of corrective actions for the RCEs and

CCA associated with the risk significant issues. The inspectors noted that there were no

formal tracking mechanisms or documentation for several of the corrective actions that

had been previously taken prior to the completion of the RCEs and CCA. Formalized

tracking measures would assure the actions are satisfactorily completed and allow for

documentation of the basis for closure.

The inspectors concluded that an appropriate schedule had been established for

implementing and completing the corrective actions for the TDAFWP White finding. This

aspect for the flooding White finding will remain open pending the inspectors review of

the additional corrective actions the licensee will need to perform.

13

c. Determine that a Schedule has been Established for Implementing and Completing the

Corrective Actions

As discussed in Section 02.03.b, above, the inspectors determined that the licensee had

established an appropriate schedule for implementing the corrective actions for the

TDAFWP White finding. The aspect for the flooding White finding will remain open

pending the inspectors review of the additional corrective actions that the licensee will

need to perform.

d. Determine that Quantitative or Qualitative Measures of Success Have Been Developed

for Determining the Effectiveness of the Corrective Actions to Prevent Recurrence

The inspectors review of the effectiveness review (EFR) plan identified a number of

weaknesses. The inspectors determined that these weaknesses rose to the level of a

finding and that the weaknesses were broad and deep enough to conclude that this

section did not meet the requirements of IP 95002. As the TDAFWP finding occurred

first and there had been additional time the EFR had already been substantially

performed for this issue. The interim assessments, combined with the general quality of

the RCE led the inspectors to conclude that this section is complete for the TDAFWP

finding but remains open for the flooding White finding and the CCA.

e. Determine that the Corrective Actions Planned or Taken Adequately Address a Notice of

Violation that was the Basis for the Supplemental Inspection, if Applicable

For the TDAFWP White finding, the licensee did not respond to the initial NOV because

the corrective actions taken and planned to be taken to correct the violation, and the

date when full compliance was achieved was already addressed on the docket in NRC

Inspection Report 05000266/2012009. As part of the 95002 inspection, the team

members performed a sampling of the immediate corrective actions and determined the

full compliance had been restored. The team considered that the IP 95002 requirements

were met for the TDAFWP White finding.

For the flooding White finding, the licensee did not respond to the initial NOV because

the corrective actions taken and planned to be taken to correct the violation, and the

date when full compliance was achieved was already addressed on the docket in

NRC Inspection Report 05000266/2013002 and 05000301/2013002 and in the

licensees submittals dated July 10, 15, and 29, 2013. As part of the 95002 inspection,

the team members performed a sampling of the immediate corrective actions and

determined the full compliance had been restored. However, as stated above, the

inspectors noted that the corrective actions resulted in unintended consequences. In

addition, as noted previously, the inspectors identified a deficiency where insufficient

corrective action was taken to correct PC 80 Part 7, in order to preclude repetition of the

original significant condition adverse to quality. Thus the team concluded that the

requirements of IP 95002 were not met for the flooding White finding.

f. Findings

(1) Failure to Take Corrective Actions to Address External Flooding Procedure Deficiencies

Introduction: The inspectors identified a finding of very low safety significance and an

associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective

14

Actions, in that from March 13, 2013 until February 14, 2014, the licensee failed to

assure that for a significant condition adverse to quality (SCAQ), the cause of the

condition was determined and corrective actions were taken to preclude repetition.

Specifically, the licensees corrective actions failed to preclude repetition of an SCAQ

where Procedure PC 80 Part 7, Lake Water Level Determination, as implemented,

would not protect safety-related equipment in the turbine building or CWPH. After the

licensee had taken corrective actions to improve the wave barrier procedure in response

to an NRC-identified NOV, PC 80 Part 7, and other flood protection implementing

procedures specified inadequate timelines to ensure wave run-up flood barriers would

be installed prior to the lake level at which wave run-up could impact the site.

Description: The inspectors reviewed procedures associated with flooding as part of

their independent extent of condition and extent of cause, and review of corrective

actions to prevent recurrence. The inspectors noted the licensee failed to recognize that

procedure, PC 80 Part 7, did not grant adequate timelines to ensure that the barriers

would be constructed before the lake reached conditions where deep wave action could

impact the site. Specifically, the licensees calculation specified that 8.2 weeks would be

available after Procedure PC 80 Part 7, initiated actions to install the wave barriers

based on lake level. The inspectors observed that based on these timelines,

PC 80 Part 7 granted three weeks allowance for activities to be scheduled and

performed to install the wave barriers. Specifically, PC 80 Part 7, stated, in part,

IF corrected mean level is greater than or equal to +0.5 ft., THEN PERFORM the

following: NOTIFY maintenance to generate on demand PM (PMRQ 00059608-02) to

INSTALL barriers and sandbags as required to be completed within three weeks.

The inspectors reviewed EC 279455, Time Available to Respond to Threat From Rising

Water, and the licensees lake level determination monthly surveillance, PBF-2124,

PPCS Forebay and Pump Bay Level Alarm Setpoints, and found several deficiencies.

These deficiencies included non-conservative assumptions when using the maximum

monthly rate of lake level rise, non-conservative assumptions for the lake level at which

the site could be impacted by the waves, non-conservative allowances to rely on the

previous months data if no lake level data was immediately available, and an error in an

assumption that wave barriers would be installed earlier than PC 80 Part 7 actually

dictated. Inspectors noted that the procedure had no barriers to prevent the previous

months data from being used during multiple subsequent months. When the licensee

corrected these inputs, the inspectors noted that the time available to fully implement the

provisions of PC 80 Part 7 significantly reduced to less than the three weeks called for in

the procedure.

The inspectors concluded that these deficiencies in the licensees timelines left them

vulnerable in that actions may not be initiated soon enough to protect the site from the

wave run-up design basis event. The inspectors noted that these deficiencies

represented a failure of the licensees corrective action to preclude repetition of an

SQAC where Procedure PC 80 Part 7, Lake Water Level Determination, as

implemented, would not protect safety-related equipment in the turbine building or

CWPH.

In addition, to the PC 80 Part 7 issues associated with the timelines for barrier

installation, the inspectors found additional procedural deficiencies that should have

been identified and corrected as part of the corrective actions taken to address the

flooding NOV. PC 80 Part 7 procedural deficiencies included error traps where steps

15

could be performed out of sequence (i.e. barriers installed before CWPH doors open),

and a failure to include CWPH doors in robust tag-out process to ensure their open

position was controlled. PBF-2124 procedural inadequacies included direction to install

jersey barriers rather than the more robust barriers associated with the licensees RCE

corrective actions. Inspectors noted that this reference to the jersey barriers referred to

the previous wave run-up flooding response strategy. The inspectors identified that the

same +0.5ft. installation threshold error was made in PBF-2124, as well as the licensees

external flooding abnormal procedure, AOP 13C.

Licensee procedure PI-AA-204, Condition Identification and Screening Process,

Section 2.45 defines a Significant Condition Adverse to Quality (SCAQ) as, Failures,

malfunctions, deficiencies, deviations, defective items, abnormal occurrences, non-

conformances, or out-of control processes that significantly threatens or has

compromised nuclear safety or radiological safety, as well as any significant reportable

industrial safety or environmental (e.g., OSHA, State, etc.) issues. SCAQ issues require

corrective actions to prevent recurrence. Condition Report 01883633 identified the

White flooding finding and associated performance deficiency as an SQAC.

The inspectors also noted that the licensee completed an interim action to improve the

wave barrier and associated procedure on March 13, 2013, and a final corrective action

CAPR 01883633-22 on November 30, 2013 to implement a plant modification to

strengthen the physical external flood protection measures associated with a high lake

level wave run-up and associated procedure guidance and design documentation. The

inspectors observed that this action was credited in the licensees RCE as an action to

prevent recurrence of the original SQAC. As a result, the inspectors determined that the

licensee failed to take corrective actions to preclude repetition of an SCAQ where

Procedure PC 80 Part 7, as implemented, would not protect safety-related equipment in

the turbine building or CWPH.

Analysis: The inspectors determined that the licensees failure to take corrective actions

to address the inadequate flooding procedure was a performance deficiency, because it

was the result of the failure to meet the requirements of 10 CFR Part 50, Appendix B,

Criterion XVI; the cause was reasonably within the licensees ability to foresee and

correct; and it should have been prevented. The inspectors determined that the finding

had a cross-cutting aspect in the area of problem identification and resolution, because

the licensee failed to thoroughly evaluate issues to ensure that resolutions address

causes and extents of condition commensurate with their safety significance (P.2).

Specifically, the licensee failed to fully evaluate issues with the flooding procedure to

ensure the corrective actions they took would assure that robust protection from wave

run-up would be installed prior to reaching a lake level where deep wave action could

present a threat to the site.

The inspectors screened the performance deficiency in accordance with IMC 0612,

Power Reactor Inspection Reports, Appendix B, and determined that the issue was

more than minor because the finding was associated with the Mitigating Systems

Cornerstone attributes of Protection Against External Factors (Flood Hazard) and

Procedure Quality, and adversely affected the cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events to

prevent undesirable consequences (i.e. core damage). Specifically, the licensees

failure to procedurally control external flooding design features, to ensure they would not

adversely affect the strategy for other flooding events, could negatively impact mitigating

16

systems ability to respond during an external flooding event. The inspectors evaluated

the finding using IMC 0609, Attachment 0609.04, Tables 2 and 3, and Appendix A.

Based on a review of Appendix A, Exhibit 2, Item 4.B, the inspectors determined that this

issue screened as having Very low safety significance (Green).

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Actions,"

requires, in part, that Measures shall be established to assure that conditions adverse

to quality, such as failures, malfunctions, deficiencies, deviations, defective material and

equipment, and non-conformances are promptly identified and corrected. In the case of

significant conditions adverse to quality, the measures shall assure that the cause of the

condition is determined and corrective action taken to preclude repetition. Contrary to

this requirement, from March 13, 2013 until February 14, 2014, the licensee failed to

assure that for a significant condition adverse to quality, the cause of the condition was

determined and corrective actions were taken to preclude repetition. Specifically, the

licensees corrective actions failed to preclude repetition of an SCAQ where Procedure

PC 80 Part 7, Lake Water Level Determination, as implemented, would not protect

safety-related equipment in the turbine building or CWPH. After the licensee had taken

corrective actions to improve the wave barrier procedure in response to an NRC-

identified NOV, PC 80 Part 7 and other flood protection implementing procedures

specified inadequate timelines to ensure wave run-up flood barriers would be installed

prior to the lake level at which wave run-up could impact the site. Specifically, the

licensee completed an interim action to improve the wave barrier and associated

procedure on March 13, 2013, and a final corrective action CAPR 01883633-22 on

November 30, 2013, to implement a plant modification to strengthen the physical

external flood protection measures associated with a high lake level wave run-up and

associated procedure guidance and design documentation. These actions failed to

preclude repetition of the original SCAQ. Corrective actions for this issue included

changing the affected procedures to install the wave barriers at a lower lake level,

changing the lake level determination surveillance from monthly to weekly, and reducing

the allowed installation time for the barriers from 3 weeks to 1 week. Because the

violation was of very low safety significance and was entered into the licensees

corrective action program (CR 01940739), this violation is being treated as an NCV,

consistent with Section 2.3.2 of the NRC Enforcement Policy.

(NCV 05000266/2014007-01; 05000301/2014007-01; Failure to Take Corrective

Actions to Address External Flooding Procedure Deficiencies)

(2) Failure to Maintain External Flooding Procedure to Address All Possible CLB Floods

Introduction: The inspectors identified a finding of very low safety significance and

associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions,

Procedures, and Drawings, in that from January 19, 1996 until November 25, 2013, the

licensee failed to ensure that activities affecting quality were prescribed by documented

procedures of a type appropriate to the circumstances to address external flooding as

described in the Final Safety Analysis Report (FSAR). Specifically, PC 80 Part 7, Lake

Water Level Determination directed advanced installation of concrete barriers to protect

against deep wave action from the lake, which introduced significant unrecognized

blockages in the natural drainage path credited in the FSAR to protect against the

probable maximum precipitation and Turbine Building internal flooding events.

17

Description: The inspectors reviewed the licensees procedures and corrective action

documents and noted an important deficiency associated with procedure PC 80 Part 7.

Specifically, CR 01932698, 95002 Wave run-up protection may conflict with other

floods, was generated a few days prior to the 95002 inspection teams arrival onsite.

This condition report described the concern that while wave barriers were installed near

the CWPH, the probable maximum precipitation and turbine building flooding events

could result in several feet of water at the CWPH and turbine building rollup doors due to

the wave barriers blocking natural site drainage paths. The inspectors noted that this

deficiency traced back to the original inappropriate action cited in the White Flooding

finding, where in 1996, the licensee inappropriately deleted an AOP directing use of

sandbags at plant doorways and substituted a wave barrier installation strategy without

recognizing the adverse impacts of the change.

The inspectors noted that the immediate corrective actions for the Flooding Apparent

Violation that were taken in March 2013 to improve the wave barrier described in

PC 80 Part 7, failed to address all deficiencies that were created when sand bagging

actions were changed to wave barrier installation in 1996. While the improved wave

barriers provided necessary protection against wave action, they failed to address

unrecognized hazards during the probable maximum precipitation and turbine building

internal flooding events. These barriers blocked natural drainage paths credited for flood

relief and rendered these paths nonfunctional as a result of wave barrier installation.

The Inspectors determined that procedure PC 80 Part 7 was inadequate until actions

were taken to modify it to provide additional flow paths for flood relief. The inspectors

noted that this issue was not recognized by the licensee until November 2013 for the

turbine building flooding event, and late January 2014 for the PMP event.

The inspectors concluded that the licensee did not adequately address the flooding

finding barrier deficiencies described in the original white flooding finding. This was

evident in the licensees interim corrective actions taken in March 2013, when the

licensee failed to restore full compliance, and did not recognize the need for providing an

additional drainage path. However, the inspectors noted that the licensee had not

implemented final corrective actions for wave barrier modification and flooding procedure

changes until November 2013, at which point steps were added to PC 80 Part 7 that

created a compensatory drainage path. As a result, the inspectors concluded that the

issue was most appropriately characterized as a failure to ensure that activities affecting

quality were prescribed by documented procedures of a type appropriate to the

circumstances to address external flooding in accordance with 10 CFR 50 Appendix B,

Criterion V. The inspectors also noted that this issue should have been readily identified

as a direct outcome of reviewing the NRC-identified finding, and it was not the result of a

thorough RCE which resulted in hidden issues surfacing.

Analysis: The inspectors determined that the licensees failure to maintain an external

flooding procedure appropriate to the circumstances to ensure the site was not

adversely impacted during CLB flooding events was a performance deficiency, because

it was the result of the failure to meet the requirements of 10 CFR Part 50, Appendix B,

Criterion V; the cause was reasonably within the licensees ability to foresee and correct;

and it should have been prevented. The inspectors determined that the finding has a

cross-cutting aspect in the area of problem identification and resolution, because the

licensee failed to take effective corrective actions to address issues in a timely manner

commensurate with their safety significance (P.3). Specifically, licensee personnel failed

to take appropriate interim corrective actions in March of 2013 when correcting a SCAQ

18

in that the interim action plan posed additional hazards to the site during design basis

floods.

The inspectors screened the performance deficiency in accordance with IMC 0612,

Power Reactor Inspection Reports, Appendix B, and determined that the issue was

more than minor because the finding was associated with the Mitigating Systems

Cornerstone attributes of Protection Against External Factors (Flood Hazard) and

Procedure Quality, and adversely affected the cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events to

prevent undesirable consequences (i.e. core damage). Specifically, the licensees

failure to procedurally control external flooding design features to ensure they would not

adversely affect the strategy for other flooding events, could negatively impact mitigating

systems ability to respond during external and internal flooding events.

The inspectors evaluated the finding in accordance with IMC 0609, Significance

Determination Process, Attachment 0609.04, Initial Characterization of Findings. The

inspectors determined that the finding affected the Mitigating Systems Cornerstone and

evaluated the finding using Appendix A, The Significance Determination Process for

Findings At-Power, Exhibit 2, for the Mitigating Systems Cornerstone. In the Mitigating

Systems Cornerstone, the inspectors answered "Yes" to the screening question Does

the finding represent a loss of system and/or function? because an assumed turbine

building (TB) internal flooding event in a condition with the jersey barriers installed due to

high lake water level could ultimately result in the loss of emergency diesel generators

and other safety-related equipment. Therefore, the finding required a detailed risk

evaluation.

The probability of the jersey barriers being installed was evaluated based on the fact that

the jersey barriers have not been installed during the 18 years (since 1996) that the

jersey barriers were available for installation if high lake water level was encountered.

Using a statistical Bayesian update with a Jeffreys non-informative prior, the probability

that the jersey barriers could have been installed was determined to be 2.63E-2.

The risk evaluation was performed by Region III Senior Reactor Analysts (SRAs). The

increase in core damage frequency (CDF) was calculated assuming scenarios

involving internal turbine building flooding events. The exposure time assumed was one

year which is the maximum allowed by the significance determination process.

For the evaluation of the risk significance, the SRAs considered TB flooding events with

three plant systems that have basically an unlimited system volume if the flooding event

is not terminated. These systems are the fire protection (FP) system, the circulating

water (CW) system, and the service water (SW) system.

To evaluate this finding, the Senior Reactor Analysts (SRAs) determined the frequency

of a pipe break (or expansion joint failure) using Electric Power Research Institute

(EPRI) Report 302000079, Pipe Rupture Frequencies for Internal Flooding Probabilistic

Risk Assessments, Revision 3. The pipe breaks of interest were determined to be

those between approximately 20,000 gpm and 36,000 gpm. The lower value of

20,000 gpm is based on the drainage capacity at the eight foot level (which is the ground

floor elevation in the TB) provided by a combination of gaps in the metal siding of the

circulating water pump house (CWPH) walkway and the storm drains still available even

with the jersey barriers installed. Pipe breaks of less than 20,000 gpm would not result

19

in water accumulation on the lowest level of the TB and thus would not imperil risk

significant equipment. The upper value of 36,000 gpm is based on calculation

2008-0024, Auxiliary Feedwater Pump Room Flood, which determined that for a

36,000 gpm TB flood rate, the TB rollup door(s) would fail at a level of 18 inches and

allow a flow of up to 36,000 gpm while maintaining the TB flood level at less than

18 inches. For the risk evaluation, a maximum TB flood rate of 36,000 gpm was thus

used to represent the delta risk associated with the finding, since this is the maximum

drainage flow through the failed TB rollup door(s). Any TB flood rate greater than

36,000 gpm would cause the TB water level to exceed 18 inches if the break flow was

not immediately terminated regardless of whether the jersey barriers were installed or

not. It was conservatively assumed that exceeding 18 inches level in the TB would

result in a core damage event (i.e., a conditional core damage probability (CCDP) of 1.0)

due to the loss of risk significant plant equipment.

Fire Protection System

The FP system was screened because of the relatively low maximum flood rates that

can occur with a break in the FP system. The capacity of the two fire water pumps

together is approximately 6,800 gpm, which is well below the drainage capacity of

approximately 20,000 gpm at the eight foot level.

Circulating Water System

The SRAs evaluated the delta risk associated with a break in the Circulating Water (CW)

system with the jersey barriers installed. Two different failure causes were available on

the CW system which could result in a break of greater than 20,000 gpm: (1) a CW

system expansion joint (EJ) failure, or (2) a CW system piping break. Each of these

failures was evaluated separately.

Circulating Water System Expansion Joints

In the EPRI report, the failure rate of an EJ per year was given for flood rates greater

than 10,000 gpm. This value was conservatively used to represent the failure rate of an

EJ for a flood greater than 20,000 gpm (i.e., a flood rate that would exceed the drainage

capacity at the eight foot level). There are eight EJs on the CW system in the TB. From

the EPRI report, the frequency of a major flood with from a CW system EJ with a flood

rate of greater than 10,000 gpm is 6.08E-6/yr/EJ. With eight EJs per Unit, the frequency

of an EJ failure is 4.86E-5/yr.

Without the jersey barriers installed, the flood water would drain out toward the CWPH

and down towards the lake with an essentially open path (i.e., essentially an unlimited

drainage rate outside the TB). With the jersey barriers installed, the drainage capacity

would be approximately 20,000 gpm at the eight foot level provided by a combination of

gaps in the metal siding of the CWPH walkway and the storm drains near the CWPH.

The drainage capacity provided by the gaps in the metal siding of the CWPH walkway

would increase as the height of the water level outside the Turbine Building increased

and would represent the majority of the drainage flow above the eight foot level. Using

the TB floor volume, the outside volume up to the jersey barriers, and the drainage rate

outside the TB (as a function of height), the licensee estimated that there was

approximately 31 minutes available to secure the CW pumps to terminate the break flow

20

before exceeding a level of 18 inches in the TB. A CW system flooding event would

require the operators to enter AOP-13A, Circulating Water System Malfunction.

Securing the CW pumps on a CW system flood event is Step 1 of the AOP. The SRAs

used the SPAR-H method (per NUREG/CR-6883) to calculate a human error probability

(HEP) for the failure of the operators to terminate a CW flood event. Using SPAR-H an

HEP for the failure of the operators to secure the CW pumps before exceeding 18 inches

level in the TB was calculated to be 0.2. This calculation assumed high stress for both

diagnosis and action and poor ergonomics for diagnosis (since a local operator would be

required to identify the flood location).

Using an HEP value of 0.2 for the probability that the operators would secure the CW

pumps before exceeding 18 inches in the TB, and the probability of 2.63E-2 that the

jersey barriers would be installed, the result was a delta core damage frequency (CDF)

of 2.56E-7/yr for an event involving a CW expansion joint failure in the turbine building.

Circulating Water System Pipe Breaks

To evaluate the CDF for CW system piping breaks, the length of large diameter CW

piping in the TB (obtained from the Point Beach PRA 7.1, Internal Flooding Notebook)

was used. For the CW piping random failure event, the frequency of a major flooding

event was conservatively estimated to be 7.95E-7/yr/ft, from the EPRI report. This is the

failure rate based on a flood rate of greater than 2000 gpm and was conservatively used

to represent the failure rate of a flood greater than 20,000 gpm. Based on this piping

failure rate per unit length and the lengths of CW piping obtained from the Point Beach

PRA 7.1, Internal Flooding Notebook, the frequency of a major flood event in the TB due

to a random CW pipe failure was evaluated to be 2.39E-5/yr. Using an HEP of 0.2

(as described above) for the failure of the operators to secure the CW pumps before

exceeding 18 inches level in the TB, and the probability of 2.63E-2 that the jersey

barriers would be installed, the result was a CDF of 1.25E-7/yr. for an event involving a

random CW system piping failure in the turbine building.

Service Water System Pipe Breaks

To evaluate the CDF for SW system piping breaks, the length of large diameter

(greater than 4 inches) SW piping in the TB was obtained from the Point Beach

PRA 7.1, Internal Flooding Notebook. From the EPRI report, a failure rate of

3.57E-7/yr/ft. was obtained for SW piping with a diameter between 4 and 10 inches,

and a failure rate of 6.44E-8/yr/ft. was obtained for SW piping with a diameter greater

than 10 inches. The length of SW piping in the TB with a diameter between 4 and

10 inches, and the length of SW piping in the TB with a diameter of greater than

10 inches was obtained from the Point Beach PRA 7.1, Internal Flooding Notebook.

The piping failure rate for a major flood event in the EPRI report is based on a flood rate

of greater than 2000 gpm. This failure rate was conservatively used to represent the

failure rate of a flood greater than 20,000 gpm. Based on these piping failure rates per

unit length and the lengths of SW piping obtained from the Point Beach PRA 7.1,

Internal Flooding Notebook, the frequency of a flood event in the TB due to a random

SW pipe failure was evaluated to be 4.40E-4/yr.

21

The pipe breaks of interest for the SW system were determined to be those between

approximately 20,000 gpm and 27,000 gpm. The lower value of 20,000 gpm is based as

stated before on the drainage capacity at the eight foot level. The upper value of 27,000

gpm is based on the flow rate for three SW pumps at run-out flow per the Point Beach

PRA 7.1, Internal Flooding Notebook. Based on a maximum SW break of 27,000 gpm,

the maximum TB flood level would be approximately 14 inches. This level would

correspond to the steady-state level at which the drainage capacity outside provided by

the gaps in the metal siding of the CWPH walkway and the storm drains near the CWPH

would equal the assumed 27,000 gpm flood rate.

The Point Beach Standardized Plant Analysis Risk (SPAR) model version 8.22 and

Systems Analysis Programs for Hands on Integrated Reliability Evaluations version

8.0.9.0 software was used to obtain a delta Conditional Core Damage Probability

(CCDP) for the event. A loss of service water (LOSW) initiating event was assumed.

Using the licensees evaluation of equipment that is lost as a function of level, all

equipment in the TB that would be submerged at or below 17 inches was assumed to fail

to bound failure of equipment at 14 inches. The 1P53 Auxiliary Feedwater Pump was

also assumed to fail as a surrogate to represent the loss of the power supply for the

Unit 2 motor-driven AFW pump 2P53 during a Unit 2 flooding event because the SPAR

model replicates Unit 1. The result was a CCDP of 1.68E-2.

Based on the probability of 2.63E-2 that the jersey barriers would be installed, and the

CCDP of 1.68E-2 for an event if the jersey barriers were installed, the result was a

CDF of 1.94E-7/yr. for an event involving a random SW system piping failure in the

turbine building.

Total CDF for Internal Events

The total CDF for internal events caused by random failures of piping and CW

expansion joints is the sum of the individual delta risk values or 5.76E-7/yr.

External Event Risk Contribution

Since the resultant internal event CDF is greater than 1.0E-7/yr., an evaluation of

external event contributions was obtained. Due to the nature of the performance

deficiency, no fire-induced floods were credible. However, a seismic-induced flooding

event was considered. Using guidance from NRCs Risk Assessment Standardization

Project (RASP) handbook, only the Bin 2 seismic events were assumed to represent a

CDF. Bin 2 was defined in the RASP handbook as seismic events with intensities

greater than 0.3g, but less than 0.5g. Earthquakes of lesser severity are unlikely to

result in large pipe failures and earthquakes of a larger magnitude could result in major

structural damage throughout the plant, which would not be representative of a

differential risk. The initiating event frequency of an earthquake in Bin 2 for

Point Beach was estimated to be 1.3E-5/yr. using Table 4A 1 of Section 4 of the RASP

handbook.

To estimate the seismic capacity of the CW piping and the CW EJs, an evaluation of the

seismic capacity for a similar Westinghouse plant was referenced. For this plant, it

stated that the CW piping and the CW EJs had high seismic capacity, and a flooding

assessment due to seismic concerns was screened from the assessment.

22

For the SW piping in the TB, making the conservative assumption that the high

confidence of low probability of failure (HCLPF) capacity for the SW piping is 0.3g, a

failure probability of 3.9E-2 was obtained for the SW system. It was conservatively

assumed that every SW system piping failure resulted in the maximum flooding rate of

27,000 gpm. Similar to the earlier evaluation of random SW piping failure due to internal

events, the licensees evaluation of equipment that is lost as a function of level was

used. All equipment in the TB with a flood level of less than or equal to 17 inches was

assumed to fail. The 1P53 Auxiliary Feedwater Pump was also assumed to fail as

discussed earlier. A dual unit loss of offsite power (LOOP) initiating event was assumed

to occur as a result of the seismic event, and it was conservatively assumed that the

operators would fail to recover off-site power for at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Also, the SW pumps

were assumed to fail-to-run. The result was a CCDP of 0.37. The CDF for a seismic

event was estimated to be 1.84E-7/yr.

Total CDF For This Issue

The total CDF associated with the finding was obtained as the sum of the CDF for the

internal events random failures of piping and CW expansion joints, and the CDF for a

seismic event or 7.6E-7/yr. The dominant sequence was associated with a random

CW system expansion joint failure in the TB that results in flooding that renders risk

significant equipment unavailable.

Large Early Release Frequency Risk Contribution

Since the total estimated change in core damage frequency was greater than 1.0E-7/yr.,

IMC 0609 Appendix H, Containment Integrity Significance Determination Process was

used to determine the potential risk contribution due to large early release frequency

(LERF). Point Beach is a 2-loop Westinghouse Pressurized Water Reactor (PWR) with

a large dry containment. Sequences important to LERF include steam generator tube

rupture events and inter-system loss-of-coolant-accident (LOCA) events. These were

not the dominant core damage sequences for this finding.

Therefore, based on the detailed risk evaluation, the SRAs determined that the finding

was of very low safety significance (Green).

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures,

and Drawings," requires, in part, that activities affecting quality shall be prescribed by

documented instructions, procedures, or drawings, of a type appropriate to the

circumstances and shall be accomplished in accordance with these instructions,

procedures, or drawings. Contrary to this requirement, from January 19, 1996 until

November 25, 2013, the licensee failed to ensure that activities affecting quality were

prescribed by documented procedures of a type appropriate to the circumstances to

address external flooding as described in the FSAR. Specifically, PC 80 Part 7, Lake

Water Level Determination directed advanced installation of concrete barriers to protect

against deep wave action from the lake, which introduced significant unrecognized

blockages in the natural drainage path credited in the FSAR to protect against the

probable maximum precipitation and Turbine Building internal flooding event. Corrective

actions for this issue included changing the procedure and FSAR to include actions to

provide an additional flood relief path through the CWPH building and reliance on

internal flood relief dampers for the affected flooding events. Because the violation was

23

of very low safety significance and was entered into the licensees corrective action

program (CR 01932698), this violation is being treated as an NCV, consistent with

Section 2.3.2 of the NRC Enforcement Policy. (NCV 05000266/2014007-02;

05000301/2014007-02; Failure to Maintain External Flooding Procedure to Address

All Possible CLB Floods)

(3) Failure to Perform a Required 10 CFR 50.59 Evaluation

Introduction: The inspectors identified a finding of very low safety significance and

associated Severity Level IV, non-citied violation, of 10 CFR 50.59(d)(1), Changes,

tests and experiments, when, on November 25, 2013, the licensee failed to perform an

evaluation against the criteria in 10 CFR 50.59(c)(2) for a change to procedure

PC 80 Part 7 to include actions to maintain functionality of drainage paths during

probable maximum precipitation and turbine building flooding events. Specifically,

PC 80 Part 7, Lake Water Level Determination was changed to include actions to open

the CWPH rollup doors to provide an additional drainage path while wave barriers were

in place, without evaluating the viability of reliance on additional flood features not

credited for external flooding in the CLB.

Description: When developing the procedural actions to address the deficiency

associated with the new wave barriers, the licensee failed to recognize that these

actions were outside the CLB. Specifically, procedure PC 80 Part 7 was revised on

November 25, 2013 to include direction to ENSURE Maintenance has raised the North

and South CWPH Roll-up doors approximately two feet to provide flooding relief. These

actions were directed to be performed in advance of the installation of the wave run-up

barriers, to ensure that while the barriers were installed, an additional flow path would be

created because the credited flow paths for the PMP external and turbine building

internal flooding events would be blocked during this time.

Final Safety Analysis Report Section 2.5 Hydrology regarding for the maximum

precipitation flood event states, in part, that the topography of the site results in

adequate natural drainage to remove this amount of water and limit ponding depth to

prevent adversely affecting safety related equipment. Contrary to these statements, the

newly created actions which were developed to compensate for the nonfunctional

natural drainage paths during wave barrier installation required use of additional features

not credited for external flooding events. Specifically, the actions included opening the

CWPH roll-up doors and routing flood waters through the CWPH and relying on internal

flood relief dampers to open and drain the water. The inspectors noted that the

10 CFR 50.59 screening documentation for Revision 6 of PC 80 Part 7, the revision

which added CWPH door actions to the procedure, did not include any discussion of the

actions to open the CWPH doors to provide a flood water flow path. The inspectors

observed that due to the licensees position that this action was in accordance with the

CLB, licensee personnel failed to screen or evaluate these actions under the

requirements of 10 CFR 50.59.

The inspectors noted that as a result of the failure to evaluate these actions under

10 CFR 50.59, the licensee failed to properly consider several factors associated with

the newly created drainage path that should have been evaluated. Some of these

factors included flood water flow rates through the open doors, the impact of debris and

slush from the outdoors being carried into the CWPH room and clogging the flood relief

dampers, the potential for substitution of unintended manual actions in place of passively

24

credited actions in the CLB, the impact of the cold temperatures on the equipment in the

rooms during the potentially extended periods of time during which the doors could be

open, and security impacts.

Analysis: The inspectors determined that the licensees failure to fully evaluate the

viability of newly created flooding drainage paths as required by 10 CFR 50.59(d)(1) was

a performance deficiency, because it was the result of the failure to meet the

requirements of 10 CFR 50.59; the cause was reasonably within the licensees ability to

foresee and correct; and it should have been prevented. The inspectors determined that

this finding has a cross-cutting aspect in the area of problem identification and

resolution, because the licensee failed to thoroughly evaluate issues to ensure that

resolutions address causes and extent of conditions commensurate with their safety

significance (P.2). Specifically, the licensee failed to fully evaluate a deficiency found in

PC 80 Part 7 associated with wave barriers blocking natural drainage paths, to ensure

that the corrective actions adequately addressed the problem.

The performance deficiency was screened in accordance with the guidance of

lMC 0612, Appendix B, and determined to be more than minor because the finding was

associated with the Mitigating Systems Cornerstone attributes of Protection Against

External Factors (Flood Hazard) and Design Control, and adversely affected the

cornerstone objective to ensure the availability, reliability, and capability of systems that

respond to initiating events to prevent undesirable consequences (i.e. core damage).

Specifically, the licensee did not fully demonstrate that the availability, reliability, and

capability of mitigating systems would be maintained during flooding events due to the

sites failure to evaluate the viability of alternate flood drainage paths through the CWPH.

The inspectors evaluated the finding using IMC 0609, Attachment 0609.04, Tables 2

and 3, and Appendix A. Based on a review of Appendix A, Exhibit 2, Item 4.B, the

inspectors determined that this issue screened as having very low safety significance

(Green).

Because this issue involved the failure to perform a written evaluation pursuant to

10 CFR 50.59, Changes, Tests, and Experiments, it, by definition, impacted the

regulatory process. As a result, the traditional enforcement process was determined to

be applicable. In determining the severity level of the traditional enforcement aspect of

the issue, the inspectors identified that Subsection d.2 of Section 6.1, Reactor

Operations, of the NRC Enforcement Policy lists a 10 CFR 50.59 violation that results in

conditions evaluated by the SDP as having very low safety significance as an example

of a Severity Level IV violation. Because the associated finding was determined to be of

very low safety significance, this issue was determined to represent a Severity Level IV

violation under the traditional enforcement process.

Enforcement: Title 10 CFR 50.59(d)(1) requires, in part, that the licensee shall maintain

records of changes in the facility, of changes in procedures, and of tests and

experiments made pursuant to paragraph (c) of this section. These records must

include a written evaluation which provides the bases for the determination that the

change, test, or experiment does not require a license amendment pursuant to

paragraph (c)(2) of this section. Title 10 CFR 50.59(c)(2) lists several examples and

states, in part, that a licensee shall obtain a license amendment pursuant to

10 CFR 50.90 prior to implementing a proposed change, test, or experiment if the

change, test, or experiment would meet the description of any of the listed examples.

25

Contrary to the above, on November 25, 2013, the licensee failed to perform an

evaluation against the criteria in 10 CFR 50.59(c)(2) for a change to procedure

PC 80 Part 7 to include actions to maintain functionality of drainage paths during

probable maximum precipitation and turbine building flooding events. Specifically,

PC 80 Part 7, Lake Water Level Determination was changed to include actions to open

the CWPH rollup doors to provide an additional drainage path while wave barriers were

in place, without evaluating the viability of reliance on additional flood features not

credited for external flooding in the CLB. Corrective actions for this issue included

actions to update the FSAR to describe the new flood paths, performing a 10 CFR 50.59

screening and 10 CFR 50.59 evaluation for the new drainage path which had put the site

outside of the CLB, revising a related functionality assessment, controlling external

flooding areas to ensure they are clear of debris, and creating a procedure to install

curtains on the CWPH rollup doors during periods when they were required to be open.

Because this violation was of very low safety significance and because the issue was

entered into the licensees corrective action program (CR 01946330), this violation is

being treated as a Severity Level IV NCV, consistent with Section 2.3.2 of the NRCs

Enforcement Policy. (NCV 05000266/2014007-03; 05000301/2014007-03; Failure to

Perform a Required 10 CFR 50.59 Evaluation)

The associated finding for this issue was evaluated separately from the traditional

enforcement violation; and therefore, the finding is being assigned a separate Tracking

Number. (FIN 05000266/2014007-04; 05000301/2014007-04; Failure to Perform a

Required 10 CFR 50.59 Evaluation)

(4) Failure to Establish EFR Attributes to Assess the Effectiveness of Corrective Actions

Introduction: The inspectors identified a finding of very low safety significance (Green)

and associated non-citied violation of 10 CFR Part 50, Appendix B, Criterion V,

Instructions, Procedures, and Drawings, for the failure to ensure the effectiveness

review attributes for a significant condition adverse to quality would ensure the corrective

actions would eliminate or reduce the recurrence rate.

Description: The licensee performed a common cause analysis (CCA) of the two White

findings documented in NRC Inspection Reports 05000266/2012-009 and 2013-012.

The CCA was documented in CR 01896156. Each of the two white findings had a root

cause analysis (RCA) performed and the CCA determined whether common causes

from the RCAs existed. The licensee identified two CCAs. CCA 1 was Leadership has

not consistently driven the organization to identify risk significant conditions and evaluate

those conditions to ensure timely resolution. CCA 2 was Several examples of technical

procedure quality issues have led to workers applying knowledge based decision making

during activities resulting in additional risk to the station.

The CCA and the RCAs were performed in accordance with licensee procedure

PI-AA-100-1005 and as required by this procedure the licensee also established an EFR

plan. The purpose of the EFR was to outline the attributes needed to assess the

effectiveness of the corrective actions to prevent recurrence (CAPRs). The EFRs were

not limited to just CAPRs but could also apply to corrective actions when necessary.

26

The inspectors reviewed the EFRs established by the licensee for the two CCAs

identified in CR 01896156. The EFRs were to be performed six months following CAPR

implementation. The inspectors noted that of the five success criteria established by the

licensee three of them relied entirely upon NRC feedback. Common Cause Analysis 1,

criteria 1, required positive NRC Resident Inspector feedback regarding issue resolution

and timeliness. Common Cause Analysis 1, criteria 2, required zero findings with a

crosscutting aspect of H.1(a) [Decision Making - Systematic Process], and CCA 2,

criteria 1, required zero findings with a H.2(b) crosscutting aspect [training]. Discussions

with licensee personnel and a review of the CCA determined that use of H.2(b) was a

typographical error and that H.2(c) [Procedure Quality] was intended to be used.

The inspectors challenged the licensee regarding the use of NRC inspector findings as

one of the few measures of how effective their corrective actions had been implemented.

The inspectors were concerned with the use of performance measures that were not

under the licensees control, were informal, and had a zero tolerance.

The main focus of the inspectors concerns was that the licensee had originally failed to

identify the weakness and violations noted above and had not recognized the need to

correct them until the NRC observations. The inspector noted that this approach was

not proactive and that waiting to see if the NRC found any new items in the next six

months would neither demonstrate the problems had been corrected nor identify that

they had not been corrected. The inspectors concluded that the EFRs were not

effective.

Analysis: The inspectors determined that the licensees failure to establish EFR criteria

that would have identified whether the CAPRs had effectively resolved the conditions

was a performance deficiency warranting further review.

The inspectors determined that this finding was more than minor in accordance with

IMC 0612, Appendix B, because it was affected the Mitigating Systems Cornerstone

objective to ensure availability, reliability, and capability of systems that respond to

initiating events to prevent undesirable consequences.

The inspectors evaluated the finding using IMC 0609, Appendix A. The inspectors

determined the finding was of very low safety significance (Green) because the finding

was not a deficiency affecting the design or qualification of a mitigating structure, system

or component and did not result in a loss of operability or functionality. In addition, the

finding did not represent a loss of system or function, did not represent an actual loss of

function of a least a single train for longer than its technical specification allowed outage

time, and did not represent an actual loss of function of one or more nontechnical

specification trains of equipment designated as high safety-significance.

The finding had a cross cutting aspect in the area of problem identification and

resolution, specifically resolution, because licensee personnel failed to ensure the

corrective actions to prevent recurrence had effective attributes. (P.2)

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures,

and Drawings, requires, in part, that activities affecting quality be prescribed by

procedures of a type appropriate to the circumstances and shall be accomplished in

accordance with these procedures. Licensee procedure PI-AA-100-1005, Revision 8,

27

Root Cause Analysis, had been written and established in accordance with

10 CFR Part 50, Appendix B, Criterion V.

Step 4.11.2.B, of PI-AA-100-1005, required, in part, The effectiveness review plan

outlines attributes to verify, responsibility and due dates. The attributes of effectiveness

are the critical elements from those improvements that will guarantee success.

Contrary to the above, on February 7, 2014, the NRC inspectors identified that some of

the EFR attributes for CCA 1 and CCA 2, of CR 01896156 would not have assessed the

critical elements of the CAPRs and thus the verification that the corrective actions were

effective would not have been performed as required by PI-AA-100-1005.

This violation is being treated as an NCV, consistent with Section 2.3.2 of the

Enforcement Policy, because it was of very low safety significance (Green) and was

entered into the CAP as CR 01938326. (NCV 05000266/2014007-05;

05000301/2014007-05, Failure to Establish EFR Attributes to Assess the

Effectiveness of Corrective Actions).

02.04 Independent Assessment of Extent of Condition and Extent of Cause

As directed by IP 95002, the inspectors independently assessed the validity of the

licensees conclusions regarding the extent of condition and extent of cause of the

issues. The objective of this requirement was to independently sample performance, as

necessary, within the key attributes of the cornerstones that were related to the subject

issues and to provide assurance that the licensees evaluations regarding the extent of

condition and extent of cause were sufficiently comprehensive. The extent of condition

review differs from the extent of cause review in that the extent of condition review

focuses on the actual condition and its existence in other places. The extent of cause

review should focus more on the actual root causes (RC) of the condition and on the

degree that these RCs have resulted in additional weaknesses.

.1 Extent of Condition

a. Inspection Scope

The inspectors conducted an independent extent of condition review of the (1) White

NOV for the Turbine Driven Auxiliary Feedwater Pump (TDAFWP) issue; (2) the White

Flooding issue; and (3) and the Common Cause Evaluation of both issues. The

inspectors review focused on the conditions identified in the primary root causes

associated with the above issues.

The inspectors interviewed station personnel, and reviewed program and process

documentation, maintenance procedures, and corrective action documents. In addition,

the inspectors conducted field walk downs of safety related equipment that involved

possible alignment requirements such as pumps and motor-operated valves (MOVs).

The inspectors looked for installation conditions that may challenge alignment of rotating

equipment, as was the case with the TDAFWP. The inspectors also performed walk

downs of plant areas that could be impacted by the wave run-up design basis flooding

event. Walk down activities included evaluation of the locations where the wave run-up

barriers would be constructed, and assessment of the physical flood barriers and sand

bags that would be utilized to respond to a wave run-up event.

28

b. Assessment

The inspectors assessed the licensees extent of condition evaluation through their own

independent extent of condition review. However, this assessment was only possible

due to changes the licensee made to the initial extent of condition evaluation.

Additionally, significant actions still remained to be defined by the licensee to determine

with high confidence their corrective actions would be effective.

TDAFWP White Finding

The licensee defined the condition in RCE 10768931, TDAFWP Coupling Degradation

During IT 08 Run, as the 1 P-29 TDAFWP coupling degraded due to misalignment. The

setup condition was the misalignment exceeded the coupling vendor's specification. The

same-same condition would be any other identical couplings on the 1P-29 TDAFWP,

which there are none, and the coupling on the 2P-29 TDAFWP being misaligned. The

same-similar condition would be other pumps with the same model coupling and have

alignment problems. No other pumps at Point Beach used the Thomas 54 Size 262

flexible disc coupling. The similar-similar condition would be other pumps that use

Thomas flexible disc couplings and have alignment problems which identified seven

other sets of pumps, the only safety related pumps being the containment spray pumps.

The licensees CCA 1896156; Degraded Cornerstone - Mitigating Systems, Two

White Findings, conducted an in-depth review of the AFW degraded coupling root

cause analysis report and identified that the extent of condition performed under

RCE 01768931 only considered what other equipment used Thomas Flexible disc

couplings to ensure alignment criteria was specified in alignment procedures. The CCA

concluded a more appropriate extent of condition would have considered all rotating

equipment that has alignment criteria specified.

As a result, the CCA initiated actions 26 through 29 to have the system engineers for all

mitigating system pumps, review and revise assembly procedures to incorporate

TDAFWP pump lessons learned. However, CCA action 15 was to expand the extent of

condition assessment to include all rotating equipment that has alignment criteria

specified. This action was not yet defined or started and therefore its scope or

effectiveness could not be assessed.

The inspectors independent extent of condition review considered all safety related

rotating equipment where alignment may be needed to ensure expected operation and

reliability. Therefore, the inspectors selected a sample of pumps and MOVs. The

inspectors verified installation procedures for the pumps included in the action items

mentioned above were changed appropriately.

The inspectors performed a walk down of one set of Emergency Core Cooling Pumps

and a variety of plant configurations of MOVs with system engineers and maintenance

personnel. The inspectors did not identify any conditions that would challenge alignment

of these components during installation. The inspectors found that alignment of MOVs

was not required by vendor or licensee procedures as the MOVs should be inherently

aligned through the valve yoke. If alignment issues were to result from installation, they

were expected to be discovered through the as-left MOV testing. A small number of

MOVs had attached supports. Condition Report 01938749 was initiated to evaluate the

29

need to do MOV testing after installation of supports on MOVs to ensure installation of

the supports did not affect valve performance.

The inspectors reviewed a sample of the CAP and found the following condition reports

that contained concerns with equipment alignment. Condition Report 01216019

discussed cracking of a valve yoke in 1999 due to actions taken to alleviate a yoke

alignment issue. Condition Report 01660763 discussed a large amount of pipe strain

when installing pump 2P-73B in 2011 (similar to the issue with the TDAFWP). Condition

Report 01202954 discussed alignment issues with 2P-11B where the base has to be cut.

Condition Report 01879455 discussed alignment issues due to bearing housing fit-up.

Condition Report 01808901 discussed an alignment issue with the Emergency Diesel

Generator, G-01, circulation oil pump due to excessive pipe strain.

As discussed above, the licensees expanded extent of condition evaluation, CCA action

item 15, to include all rotating equipment that requires alignment had not been further

defined, but based on the inspectors review of previous CAP issues and walk downs, the

scope should include pumps, valves, fans, and diesels as a minimum. The evaluation

may conclude the condition does not exist in these components or that existing

processes adequately address alignment of the components.

The inspectors concluded the extent of condition was initially too narrowly defined, which

would not have been acceptable, but was subsequently expanded in the CCE. Based

on the walk downs, which did not identify challenges to alignment during installation, the

actions taken to revise the installation procedures for the mitigating system pumps and

expanded action to evaluate additional rotating equipment, the inspectors assessed this

aspect of IP 95002 was met for the TDAFWP White finding.

White Flooding Finding

The licensee described the condition for the White flooding finding as procedure

PC 80 Part 7, did not prescribe adequate barriers to implement external flooding wave

run-up protection features. The licensees extent of condition addressed other

external flood protection measures as well as additional external hazard protection

measures and commitments. The inspectors performed an independent extent of

condition by performing plant walk downs, interviewing personnel, reviewing corrective

action programs generated for site identified external flooding issues, and assessing

selected plant procedures.

During walk downs of the plant areas where flood barriers would be built, the inspectors

questioned plant personnel regarding possible bypass mechanisms around the flood

protection features. Specifically, the inspectors questioned whether storm drains outside

the CWPH that communicated directly with the lakeshore could present a wave barrier

bypass hazard. Licensee personnel stated they had only briefly considered these drains

but had rejected them as a possible bypass path without performing an analysis or any

follow-up. Following a request from the NRC inspectors for information regarding these

drain lines and the potential wave barrier bypass paths, the licensee performed an

engineering calculation to review the impacts. The calculation determined that the drain

paths did not in fact represent a significant threat to having high lake water bypass the

flood protection features. The inspectors determined that the calculation was neither

simple nor straightforward and should have been performed as part of the licensees

extent of condition.

30

During a review of the licensees corrective action program the inspectors observed that

licensee personnel had identified that the installation of the more robust flood protection

barriers would introduce an unintended consequence of blocking the natural flow path of

rain water and snow melt. The licensee had identified this unintended consequence

while performing Fukushima external threat calculations and not due to the extent of

condition review for the White flooding finding. This issue represented a flaw in the

licensees initial corrective action which was first put in place in March 2013 as an

immediate action to restore compliance. Inspectors noted that this issue should have

been identified prior to installation and represented another missed opportunity to

identify for their extent of condition. Instead, the inspectors noted that this left the site in

a position where they were still in discovery when the IP 95002 inspection team arrived

onsite.

Inspectors also noted a corrective action document generated several months after

completion of the RCE, and approximately one week prior to the inspection teams

arrival onsite, regarding conflicting AOP procedures. Specifically, the inspectors noted a

CR that stated the High Winds AOP was in conflict with the External Flooding AOP, in

that the former required CWPH roll up doors to be open and the latter required them to

be closed. The inspectors observed that invoking both procedures at the same time

could easily be required depending on weather conditions. The inspectors noted that

this was another example of late discovery, which represented an additional missed

opportunity for the licensee to have identified the issue during their RCE extent of

condition.

The inspectors review of external flooding procedures to ensure that the procedure was

adequately corrected to ensure protection of equipment during a design basis flood

yielded several deficiencies. These deficiencies are described in more detail in the

findings section of the report. Specifically, during the inspectors review of PC 80 Part 7

and PBF-2124 the inspectors identified a number of issues resulting in the determination

that both procedures were flawed and would not have accomplished their intended

function.

PC 80 Part 7 procedural deficiencies included error traps where steps can be performed

out of sequence (i.e. barriers installed before CWPH doors open); failure to include

CWPH doors in robust tag-out process to ensure their open position was controlled;

and direction to install barriers at +0.5 ft. plant elevation, which was not early enough in

accordance with the licensees timeline calculation. PBF-2124 procedural inadequacies

included a note that allowed them to rely on last months data for lake level if the current

months data was not readily available, direction to install barriers at the incorrect

threshold of +0.5 ft. plant elevation, and direction to install jersey barriers rather than the

more robust barriers associated with the licensees RCE corrective actions (reference to

the jersey barriers referred to the previous flooding strategy). The inspectors identified

that the same +0.5 ft. installation threshold error was made in the licensees external

flooding abnormal procedure, AOP 13C.

The licensees extent of condition did not extend to non-external event design basis

items because as stated in the RCE separate and rigorous processes already in

place to ensure site documentation is up to date and accuratefor instance, AOPs are

reviewed (and validated) on a regular basis to ensure quality and accuracy of the

procedure. Yet during the inspectors review it was observed that procedure technical

quality was determined by the licensee to be a root cause for the TDAFWP White

finding. The inspectors also noted that it would have been appropriate for the licensee

to more thoroughly evaluate the modification 10 CFR 50.59 process during their extent

31

of condition review, due to the integral role that the inadequate 10 CFR 50.59 review

played in the original performance deficiency. This may have also been appropriate in

light of the licensees failure to properly utilize the 10 CFR 50.59 process during

development of the modification to correct the performance deficiency, as discussed in

the findings section of this report.

The team concluded that the requirements of IP 95002 for the extent of condition were

not met for the flooding White finding.

c. Findings

No findings were identified.

.2 Extent of Cause

a. Inspection Scope

TDAFWP

The inspectors conducted an independent extent of cause reviewed based on the root

and contributing causes identified by the licensee in RCE 10768931, TDAFWP Coupling

Degradation During IT 08 Run. Licensee personnel identified the Root Cause as the

TDAFWP exhaust steam piping was not installed properly during original construction to

eliminate stresses on the turbine per vendor recommendations resulting in cold piping

spring and coupling misalignment. Contributing Cause 2 (CC2) was determined to be

that as-found alignment data was classified as information-only, resulting in no

evaluation of out-of-tolerance conditions and the procedures lacked acceptance criteria.

Contributing Cause 3 (CC3) was determined to be that the TDAFWP and turbine were

not aligned during original construction using vendor recommended dowels allowing

subsequent movement of equipment.

The inspectors determined that the root cause was narrowly focused and not a good

candidate to perform an independent extent of cause. In fact, most aspects of the root

cause were included in the extent of condition discussed above. Instead the inspectors

selected CC2 and CC3 to perform the independent extent of cause.

The inspectors reviewed the licensees extent of cause evaluations to assess whether

they were of sufficient breadth and depth to accurately capture the extent of the causes.

The inspectors independent extent of cause evaluation involved in-plant walk downs

and observation of work activities, interviews with station management and staff, reviews

of program implementing procedures, reviews of program monitoring and station

improvement efforts, and comprehensive searches of the corrective action program.

White Flooding Finding

The inspectors performed an independent extent of cause based on the root and

contributing causes in the licensees RCE. The inspectors focused their review on the

licensees two identified root causes, as well as the two contributing causes identified in

the RCE. The root causes identified by the licensee included inadequate identification

and understanding of the external flooding CLB (RC1), and inappropriate prioritization of

flood protection deficiencies in the corrective action program based on

conditional/immediate station risk perceptions (RC2). The contributing causes the

licensee identified included a lack of clear supporting detail in station documents for

32

external events combined with a lack of use and understanding of license basis (CC1),

and a lack of formality and rigor regarding the stations follow-up and resolution of NRC

concerns (CC2).

The inspectors reviewed the licensees extent of cause evaluations to assess whether

they were of sufficient breadth and depth to accurately capture the extent of the causes.

The inspectors interviewed licensee management and personnel, reviewed program and

process documentation, performed plant walk downs, reviewed licensee program

monitoring and improvement efforts, and reviewed corrective action documents.

b. Assessment

TDAFWP

The inspectors determined that the extent of cause evaluations conducted by the

licensee for the TDAFW issues were narrowly focused. The extent of each cause

evaluations conducted by the inspectors broadly considered other programs and

components that may be affected by similar causes. The limited sampled performed by

the inspectors did not identify significant issues to concluded the cause would be

applicable in those areas. Therefore, based on the actions taken so far, and with the

additional actions entered into the licensees corrective action program, overall, the

inspectors concluded that Extent of Cause objectives of the 95002 inspection procedure

were met for the TDAFWP finding. The inspectors noted a number of licensee actions

are yet to be defined or completed as discussed below. Specific results of the

inspectors review of the causes and program areas are discussed below.

CC2: RMP 9044-1 Identified As-Found Alignment Data as Information Only Resulting In

No Evaluation of Out-of-Tolerance Conditions and Lacked Acceptance Criteria

The inspectors determined that the vibration monitoring and In-service Test (IST)

procedures require reviews by appropriate departments, including operations and

engineering. The procedures do not discuss information only data. Personnel involved

with these programs stated all data taken was reviewed by engineering. The review of

the corrective action program only identified the following issues.

Condition Report 019118667 described a condition found during review of the 1P-11A

coupling setting. It was identified that the as found coupling gap was recorded as 0.046

inch. The procedural requirement in RMP 9006-2A, required the gap to be 0.125 inches

per the OEM installation requirements for the Falk Model 1080T20 coupling. A review of

the last performed pump work on 1P-11A in 2010 under WO 392829, which included

procedure RMP 9006-2A, recorded the coupling back of hub to back of hub dimension

as 7.035 inches and did not record the actual gap, as the coupling was not removed.

The as found coupling back of hub to back of hub dimension under the current work was

7.034 inches with a gap of 0.046. Based on this information and that the coupling hubs

have not been replaced, the as found coupling appears to have been set incorrectly

since the coupling was last removed in 2007 under WO 188114.

33

Another CR 01895229 stated that during the previous TDAFW Pump 95001, the NRC

identified that routine maintenance procedures lack acceptance criteria.

During this review, some instances were found where as-found alignment data is now

being evaluated. The inspectors did not identify instances where vibration or IST data

was not evaluated.

The licensees extent of cause evaluation for CC2 considered as-found Thomas Series

54 Size 262 coupling alignment data that was being treated as information-only. It found

this cause only applied to procedure RMP 9044-1 because the P-29 turbine-pump

combination is the only equipment that utilizes the Thomas Series 54 Size 262 coupling.

The licensee determined RMP 9044-1 needed to be revised to include acceptance

criteria for the critical parameters of the Thomas Series 54 Size 262 coupling that could

affect operability, and included formal evaluation by engineering if any of these criteria

are exceeded. No other corrective actions were required.

The licensee evaluation also included other Thomas flexible disc pack coupling

alignment data and determined as-found data that is not evaluated applied to

procedures or work orders associated with the following equipment:

  • P-028 Main Feedwater Pumps (Series 51 Size 450)
  • P-007 Monitor Tank Pumps (Series DBZ-A Size 101)
  • P-099 SGFP Seal Water Injection Pumps (Series DBZ-C Size 126)
  • P-004 Boric Acid Transfer Pumps (Series DBZ-C Size 126)
  • W-001 Containment Accident Recirculation Fans (375SN)
  • W-004 Containment Reactor Cavity Cooling Fans (Series AMR)

The licensee action was to review the procedures or work orders for the above

equipment and revise them as necessary to include acceptance criteria for the critical

parameters.

The inspectors found the licensee extent of condition to be narrowly focused on either

the specific Thomas Series 54 Size 262 coupling or other Thomas flexible disc pack

couplings and did not consider other alignment procedures or procedures and programs

where as-found or information-only date may be taken and not evaluated. However, the

inspectors only found a few instances in the CAP where this weakness existed and

therefore could not conclude the cause identified extended into other equipment and

programs and therefore concluded this aspect requirements of IP 95002 was adequately

met for CC2.

CC3: 1 P-29 Pump and Turbine Were Not Aligned During Original Installation Using

Vendor Recommended Dowels Allowing Subsequent Movement of Equipment

Through review of a sample of vendor manuals, the inspectors did not identify any

vendor guidance concerning alignment that should have been incorporated into licensee

procedures. However, there were some issues identified in the corrective action

program that the inspectors considered representative of CC3.

34

For instance, CR 01920659, dated November 14, 2013, found that the 1P-029 as-found

alignment checks were outside the acceptance criteria of RMP 9044-1, Auxiliary

Feedwater Pump Terry Turbine Overhaul. The acceptance criteria for horizontal

alignment (offset) is -0.002 to 0.002 and, the as-found results were -0.0037 for horizontal

alignment. The as-found vertical alignment was satisfactory. The 1P-029-T was

realigned per RMP 9044-1 as part of the contingency work plan. Although the 2P-029

was doweled in accordance with vendor manual instructions, there was no mention of

doweling in this procedure.

Condition Report 01217509 dated June 8, 2000, states the post maintenance test

(PMT) for WO 9925677 indicated a probable alignment problem with P-132. Work

Order 9927144 was created to perform a "hot" alignment on P-132. The term "hot"

alignment is more commonly referred to in vendor manuals as a "final" alignment. The

vendor manual for all Goulds 3196 pumps calls for an initial alignment to be performed

when a pump is installed or reinstalled. The manual then calls for a final alignment to be

performed "after the unit has been run under actual operating conditions for a sufficient

length of time to bring the unit up to operating temperature." The manual goes on to say

that the final alignment should be checked after approximately one week of operation.

The manual also states that "the final alignment procedure......must be followed". Based

on the inspectors review, final alignments described in the Goulds pumps' manual are

not performed at Point Beach Nuclear Plant. These final alignments should be

performed as they are specifically called for by the pump manufacturer. Pump

misalignment could cause premature failure of critical pump parts such as bearings and

seals.

Another CR 01195885, dated April 17, 2001, stated that oil analysis shows evidence of

bearing wear for a safety injection pump motor. During alignment, the motor shaft was

apparently not at the mechanical center as recommended by the manufacturer. It was

mis-positioned such that contact was made at the inboard bearing thrust face with the

coupling compressed.

The inspectors also identified current observations by oversight organizations that are

indicative of conflicts with vendor manual instructions. Point Beach Daily Quality

Summary, dated October 16, 2012, discussed an observed activity for AF-00109,

P-38A Auxiliary Feed Pump Discharge Check Valve Inspection. It noted that the work

instructions were minimal and lacked warnings to avoid cocking the bonnet during

disassembly and reassembly that were stated in the vendor technical manual (VTM).

The scope in the WO instructions was written from the lift check valves vendor technical

manual and is different from what is listed in the Engineering technical basis. This

observation also indicates possible alignment issues with this check valve that supports

the need to consider valves during evaluation of the extent of cause for CC2.

Another observation, Point Beach Daily Quality Summary for 2P-29 TDAFW Pump

Assembly, dated November 19, 2012, noted that CR 01824455, Functional Criteria Not

Met, was initiated by Maintenance for the failure of the inboard bearing clearance to

meet the functional criteria. The System Engineer provided additional information to

CR 01824455 on November 17, 2012 stating that the functional criteria from preceding

Step 5.23.17 should have replaced the current criteria. The system engineer initiated

PCR 01825115 to put the correct criteria into the procedure. In light of the alignment

35

issues with this pump, the inspectors were concerned the licensee process did not

account for the latest vendor guidance to be entered into the applicable procedures.

After completion of the independent extent of cause for CC3, the inspectors reviewed

the licensees extent of cause for CC3. The licensee justified not doing an extent of

cause on CC3 base on it being unique to the TDAFWPs. Justification was based on the

following:

Since the piping misalignment issue has been resolved on 2P-29 and it is

not experiencing the governor valve chugging problem, no extent of cause

is required for this maintenance activity. The Terry turbine and pump are

unique in design compared to other driven pumps or components. Most

pumps and other pieces of equipment are driven with an electric motor. In

the normal configuration, the pump is considered the fixed point due to

being hard piped with suction and discharge pipe and is doweled once set.

The motor is moved as needed to obtain the required alignment tolerances

and is not doweled. Moving the motor to obtain proper alignment is being

restrained by hold down bolts. Slight movement of the motor to

accomplish proper alignment is permitted since only the connection to the

motor is the flexible power source conduit. For the AFW turbine and the

pump, both are hard piped, which is a significant challenge during

alignment. In addition, both the turbine and pump are to be doweled per

their respective vendor manuals, which is unique compared to other

rotating pieces of equipment. This condition of no dowels has existed

since startup and is considered an original which included procedure RMP

9006-2A construction deficiency of which the cause will not be determined.

Therefore no extent of cause is justified for this.

With a relatively small sample the inspectors found issues that had been identified

previously by the licensee that indicated CC3 may extend to other equipment with

vendor manual information. Therefore, the inspectors concluded the licensees extent of

cause evaluation for CC3 was narrowly focused and may not capture other vendor

guidance into licensee procedures. Condition Report 1939217 was initiated for this

observation. The recommended corrective action was to review a sample of vendor

recommendations contained in VTMs for safety related equipment to determine whether

there are broader issues associated with implementation of vendor recommendations.

While the inspectors determined the licensees extent of cause evaluation was narrowly

focused, other than the doweling guidance, no instances were identified where vendor

guidance was not appropriately incorporated into licensee procedures. Based on this

and the licensee action referenced above, the inspectors concluded the 95002

procedure requirements were satisfied.

White Flooding Finding

The inspectors determined that the extent of cause evaluations conducted by the

licensee for the External Flooding deficiencies were narrowly focused. Each of the

inspectors independent extent of cause evaluations broadly considered other programs,

procedures, functional areas that may be affected by similar causes. The limited sample

performed by the inspectors identified a few notable issues which are documented in

36

detail in the findings section of this report and the section below. Based on the actions

taken so far, the inspectors concluded that Extent of Cause objectives of the 95002

inspection procedure were not met for the Flooding finding. Areas of concern will be

reviewed as part of a future inspection. Specific results of the inspectors review of the

causes are discussed below.

RC1: Inadequate Identification and Understanding of the External Flooding CLB

The inspectors reviewed the licensees extent of cause evaluation for the first root cause

identified, RC1. Specifically, RC1 was identified as less than adequate identification

and understanding of the external flood protection design and licensing basis resulted in

loss of high lake level protection measures in 1996 when AOP 13B was cancelled.

Inspectors reviewed corrective action programs from the preceding 2-year period,

external events program controls, and general procedures in the areas of High winds,

Tornados, High Energy Line Breaks, Internal Flooding, and External Flooding, and

walked down related plant areas to independently assess whether the licensee had

appropriately identified deficiencies in understanding and identification of the design and

license basis.

No significant issues were identified. However, inspectors noted examples described in

the findings section of the report, where the licensee had failed to fully recognize impacts

of the wave run up barriers during the probable maximum precipitation (PMP) and

turbine building flooding event until the 95002 inspection team arrived onsite. The

inspectors noted that given the topography of the site and associated drainage

characteristics, this issue should have been more readily identified as part of the extent

of condition and extent of cause evaluations.

In addition, as noted in the findings section of this report, the licensee failed to recognize

that the conflict with the barriers resulted in a failure to comply with the CLB and the

need to open the CWPH roll-up doors constituted a compensatory action that needed to

be reviewed in accordance with 10 CFR 50.59. The inspectors noted that this issue was

served as an example where licensee personnel still demonstrated a lack of

understanding of the CLB, which served as evidence that the extent of cause for this

root cause have not been fully probed and deficiencies corrected.

RC2: Inappropriate Prioritization of Flood Protection Deficiencies in the Corrective

Action Program Based on Conditional/Immediate Station Risk Perceptions

The inspectors reviewed the licensees extent of cause evaluation for the second root

cause identified, RC2. Specifically, RC2 was identified as the degraded function of high

lake level protection measures for wave run-up identified in the corrective action

program were inappropriately prioritized based on conditional/immediate station risk

perceptions rather than compliance with license commitments resulting in untimely

resolution of the issues.

During review of RC2, inspectors interviewed plant personnel to evaluate general

understanding of the flooding deficiencies, recognition of associated risks, and

effectiveness of site communication campaigns. As previously noted, inspectors

observed that broader issues with risk recognition may still exist, based on discussion

with site personnel.

37

The inspectors assessed the extent of cause relative to the licensees failure to

characterize the wave barrier as nonfunctional and thus failed to properly prioritize

fixing the deficient strategy due to the lack of risk recognition. The inspectors noted that

of the 11 functionality assessments (FA) that the licensee sampled as part of their extent

of cause, and including an additional FA, excluded from the licensees sample because

the NRC had already found it deficient, half were found to be deficient in their

conclusions or logic. The inspectors observed that no action was taken to correct these

deficiencies, as the CR written on the results of the review was closed to no action. In

addition, no action was taken to learn from the results of the review, or probe these

results more deeply due to reliance on some procedural changes being made to the FA

process.

The inspectors noted that the sites focus on the perception that these deficient FA

conclusions were non-consequential had parallels to the White flooding finding root

cause. Specifically, the licensee had drawn the wrong FA conclusion, but plant

personnel had determined that it did not matter as long as the correct action was

ultimately taken. The inspectors observed that in the case of the original White Flooding

finding, site personnel had not properly addressed the deficiency even though there was

a belief that the correct action had been taken. The inspectors noted that the licensee

would have been driven to correct the deficiency more promptly if the FA conclusion had

been correctly classified as non-functional. This highlights the importance of drawing the

correct functionality conclusion. The inspectors concluded that to ensure correction of

the deficiencies associated with these FAs, and as an extension, the root cause that

drove them to perform the functionality assessment sample, it may have been

appropriate to enact more robust corrective actions to arrest the trend.

The inspectors learned during the functionality assessment review, as documented in

CR 01924763, FA errors & less than adequate corrective action program threshold, an

individual had discovered deficiencies in the conclusions of several FAs, and chose not

to write a CR because they felt that initiation of a new CR would constitute low value

work. The inspectors noted that this example served as a data point of an individual that

may still be focused on what they believe is or is not significant, without looking at the

bigger picture, and failing to write a CR to ensure that risks could be evaluated.

Inadequate corrective action program threshold and risk recognition were common to the

flooding root cause and common cause evaluations. The inspectors questioned whether

this might be an indication that the workforce has not been fully reached by licensee

communications focused on fixing licensee personnels lack of risk recognition, and

instilling them with the objective to prove that something is safe.

The inspectors noted that in response to the CR 01924763, less than adequate

corrective action program threshold this CR was closed to no action, with a note that

stated that coaching was provided. Inspectors noted that without any review of the

behavior documented in the CR, it would be difficult for the licensee to determine

whether this behavior was a single isolated incident, or more of a wide spread problem.

Inspectors noted that it may have been appropriate for the licensee to take action to

make this determination so that more robust corrective actions than coaching could be

taken, if necessary.

38

The inspectors also noted that because the extent of cause was not extended from the

FA process to a similar process, the Operability Determination process, the licensee

missed an opportunity to implement robust corrective actions to address deficiencies in

the operability determination process. The inspectors noted that within the previous

2 years, there had been approximately five NRC findings associated with inadequate

operability determinations. The licensee noted that they had adopted a new operability

determination process procedure in August of 2013, and had taken actions as a result of

an April 2013 Condition Evaluation to perform one-time trainings for Operations and

Engineering to improve operability determination process knowledge. The inspectors

noted that Condition Evaluations serve as lower level evaluations that do not generally

probe deeply into issues, and may not reveal all aspects of a complex issue. Inspectors

also noted that actions to perform one-time trainings may not be robust enough to

ensure sustainable improvement. The inspectors concluded that given the critically

important function that operability evaluations serve, it may have been appropriate to

enact more robust corrective actions to ensure improvement in this area.

CC1: Lack of Clear Supporting Detail in Station Documents for External Events

Combined with a Lack of Use and Understanding of License Basis

The inspectors reviewed the licensees extent of cause evaluation for the first

contributing cause identified, CC1. Specifically, CC1 was identified as deficiency in

having clear supporting detail in station documents for external events combined with a

lack of use and understanding of license basis resulted in the FSAR requirements

remaining unmet.

Inspectors reviewed corrective action programs from the preceding 2-year period,

external events program controls, and general procedures in the areas of High winds,

Tornados, High Energy Line Breaks, Internal Flooding, and External Flooding, and

walked down related plant areas to independently assess whether the licensee had

appropriately identified deficiencies in clear supporting detail in station documents

associated with the license basis.

No significant issues were identified. However, inspectors identified several deficiencies

with the licensees failure to ensure clear supporting detail existed in station documents

associated with internal flooding. Specifically, inspectors noted that although during a

design basis turbine building flooding event, the site was crediting tripping the circulating

water pumps to mitigate the flood with a short specified amount of time, i.e. 34 minutes

or less, the site failed to evaluate and control this action under the time critical operator

action procedure. In addition, inspectors noted that the site had chosen to credit failure

of the turbine building roll up door during the same internal flooding event. Inspectors

identified that the site had failed to upgrade this door to an augmented quality

classification, despite the fact that they had taken action to credit the door in the design

basis to perform the safety related function of flood relief.

The inspectors also noted that reliance on the failure of the turbine building door for the

internal turbine building flooding event was not clearly articulated in changes the

licensee made to the FSAR, in that the TDAFW pump rooms noted that the door was

credited for flood relief, but the EDGs did not contain the same statement despite a

similar reliance on the same door. These issues were entered into the licensees

corrective action program. The inspectors determined that these issues could be related

39

to CC1, in that station documents did not clearly define and control features that were

credited to mitigate internal flooding scenarios.

CC2: Lack of Formality and Rigor Regarding the Stations Follow-Up and Resolution of

NRC Concerns

The inspectors reviewed the licensees extent of cause evaluation for the second

contributing cause identified, CC2. Specifically, CC2 was identified as stations rigor for

follow up on NRC concerns lacks formality and as a result the CR written for the

1Q2012 URI was not validated for accuracy, nor contained the necessary action, thus

contributing to the untimely resolution of potentially degraded flood protection

measures.

During review of CC2, inspectors identified that the licensees extent of cause was

narrow, and should have focused more broadly. Specifically, the licensees evaluations

focused only on improvements and deficiencies associated with the tracking and

resolution of NRC concerns. The inspectors questioned whether the site should have

looked across the organizations at similar processes and interactions with other external

stakeholders. Specifically, the inspectors noted that tracking and resolution of nuclear

oversight, corporate nuclear review boards, management review board, and

independent site evaluations may have similarities to the NRC issue tracking and

resolution processes. The inspectors noted that the site missed an opportunity to

identify improvements in these processes. The inspectors did not identify any instances

where the site had not appropriately tracked or resolved issues associated with these

groups, but inspectors also recognized that deficiencies in these areas may not be

readily identifiable due to the nature of these interactions.

The inspectors concluded the 95002 procedure requirements for the flooding White

finding were not satisfied.

c. Findings

No findings were identified

02.05 Safety Culture Consideration

a. Inspection Scope

As part of the current 95002 inspection, the inspectors independently confirmed that a

number of safety culture components that contributed to the risk significant issues that

were the subject of this inspection were identified in the licensees RCEs. The licensees

root cause evaluations included a discussion of the applicable safety culture

components described in Regulatory Issue Summary 2006-013, Information on the

Changes Made to the Reactor Oversight Process to More Fully Address Safety Culture,

(ADAMS Accession No. ML061880341) as they applied to the violations and findings.

The licensee determined that weaknesses in decision making (conservative

assumptions and systematic process), resources (procedures/work instructions), work

practices (oversight), work control (planning), and the corrective action process

(low threshold and evaluations) were the most prevalent safety culture attributes. The

licensee also included the results of a 2013 station nuclear safety culture self-

assessment and employees concern program site pulsing surveys. For each of the

40

identified prevalent and contributing safety culture components, the inspectors confirmed

that the licensee established corrective actions to address the issues.

Assessment

The inspection team independently confirmed a sample of other safety culture

components which contributed to the issue(s) that were also identified in the root cause

analysis. These additional safety culture components included weaknesses in the CAP

and resources. For each of the identified prevalent and contributing safety culture

components, the inspection team confirmed that the licensee established appropriate

corrective actions to address the issues. Some corrective actions are complete, but

pending corrective actions and effectiveness of those actions has not been confirmed to

a point where the NRC has confidence that the licensees actions are sufficient to

address and correct the causes and issues. During the course of interviews with

licensee personnel, the inspection team asked interviewees questions related to safety

conscience work environment (SCWE) to determine if the licensees staff were reluctant

to raise safety concerns or if fear of retaliation existed for raising safety concerns. The

inspection team did not identify concerns related to SCWE.

The inspection team confirmed that the licensees root cause, extent of condition, and

extent of cause evaluations appropriately considered the safety culture components as

described in IMC 0305, Operating Reactor Assessment Program.

The inspectors observed that the previously cited example of a failure to initiate a CR, as

described in CR 01924763, FA errors & less than adequate CAP threshold, was an

important data point from a safety culture and CR initiation standpoint. This CR

documented an individuals failure to write a CR to document deficiencies in the

conclusions of several functionality assessments. The inspectors noted that while the

issue itself was just one data point, the licensees failure to act to determine the extent to

which those behaviors were prevalent onsite was an additional data point in the area of

safety culture. The inspectors noted that the licensee had instead closed the CR to no

action, and noted that coaching had been provided. The inspectors determined that

investigative actions may have been appropriate to assist in the licensees assessment

of whether their RCE corrective actions to improve CR initiation and risk recognition had

adequately reached the working level staff. This may have especially been appropriate

given the fact that similar inappropriate CAP threshold issues played a role in the

common cause for the greater than green findings being evaluated during the 95002

inspection.

Inspectors noted that the O.2a safety culture component may not have been adequately

considered during the licensees safety culture evaluation. Specifically, O.2a is focused

on ensuring that appropriate training and knowledge transfer was in place to ensure

technical competency of staff. The inspectors noted that the licensee marked this

aspect as not applicable. The inspectors observed that this safety culture aspect may

have played a role in the licensees root cause associated with licensee staffs failure to

understand the CLB. Mainly, the inspectors noted that training and knowledge transfer

could have increased licensee personnels understanding of the CLB. The inspectors

observed that at the least, this training and knowledge transfer could have prompted the

identification of vague requirements in the design basis or licensee staffs lack of full

understanding of the CLB. The inspectors noted that this could have driven resolution of

questions on requirements.

41

The inspectors noted that subject matter experts at the site who were charged with

ownership and knowledge of the external flooding program and other functional areas,

did not have any qualification cards or required subject matter trainings to ensure their

competency. This remained unchanged after the finding. The inspectors noted that

corrective actions to provide general external events training and to develop a formal

external events program may have appropriately addressed concerns about subject

matter experts training adequacy, as the procedure consolidated requirements into

controlling program procedures. However, the inspectors concluded that more

specialized training could have increased defense in depth in the training and knowledge

transfer areas.

The inspectors concluded the 95002 procedure requirements were satisfied for the

TDAFWP finding but not for the White flooding finding.

b. Findings

No findings were identified

02.06 Evaluation of IMC 0305 Criteria for Treatment of Old Design Issues

The licensee did not request credit for self-identification of an old design issue.

Consequently, the subject risk significant issues were not evaluated against the

IMC 0305 criteria for treatment of an old design issue.

4OA5 Other Activities

The inspectors utilized other inspection procedures as part of the assessment of the

licensees performance. The following inspection samples were completed as part of

this inspection.

  • 71111.15 - Operability Evaluations - 1 sample
  • 71152 - Problem Identification and Reporting - Annual Follow-Up

of Selected Samples - 1 sample

4OA6 Management Meeting

Exit Meeting Summary

On March 6, 2014, the inspectors presented the inspection results to

Mr. E. McCartney, Site Vice President, and other members of the licensee staff. The

licensee acknowledged the issues presented. The inspectors confirmed that none of the

potential report input discussed was considered proprietary.

ATTACHMENT: SUPPLEMENTAL INFORMATION

42

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

E. McCartney, Site Vice President

R. Wright, Plant General Manager

R. Weber, Operations Director

M. Millen, Licensing Manager

K. Longston, Acting EP Manager

J. Atkins, Systems Engineering Manager

B. Beltz, Assistant Operations Manager

F. Hennessy, Performance Improvement Manager

J. Pruitt, Site Quality Manager

R. Welty, Radiation Protection Manager

R. Harrsch, Engineering Director

D. Lauterbur, Training Manger

P. Wild, Design Engineering Manager

L. Christensen, Licensing Project Manager

B. Scherwinski, Engineering Analyst II

T. Schneider, Licensing

F. Huber, Projects Manager

S. Cassidy, Communications Manager

C. Trezise, Director Special Projects

M. Ley, Civil/Mechanical Engineering Supervisor

T. Lesniak, Mechanical Maintenance Department Head

M. Maertens, Business Operations Manager

R. Clark, Licensing

S. Ruesch, Employee Concerns Program Manager

J. Petro, Licensing Director

A. Gustafson, Training

K. Locke, Licensing

Nuclear Regulatory Commission

A. Boland, Director, Division of Reactor Projects

J. Cameron, Chief, Branch 4, Division of Reactor Projects

K. Barclay, Acting Senior Resident Inspector Point Beach

R. Elliott, Acting Resident Inspector Point Beach

1 Attachment

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED

Opened

05000266/2014007-01 NCV Failure to Take Corrective Actions to Address External

05000301/2014007-01 Flooding Procedure Deficiencies05000266/2014007-02 NCV Failure to Maintain External Flooding Procedure to

05000301/2014007-02 Address All Possible CLB Floods05000266/2014007-03 NOV Failure to Perform a Required 10 CFR Part 50.59

05000301/2014007-03 Evaluation

05000266/2014007-04 FIN Failure to Perform a Required 10 CFR Part 50.59

05000301/2014007-04 Evaluation

05000266/2014007-05 NCV Failure to Establish EFR Attributes to Assess the

05000301/2014007-05 Effectiveness of Corrective Actions

Closed

05000266/2014007-01 NCV Failure to Take Corrective Actions to Address External

05000301/2014007-01 Flooding Procedure Deficiencies05000266/2014007-02 NCV Failure to Maintain External Flooding Procedure to

05000301/2014007-02 Address All Possible CLB Floods05000266/2014007-03 NOV Failure to Perform a Required 10 CFR Part 50.59

05000301/2014007-03 Evaluation

05000266/2014007-04 FIN Failure to Perform a Required 10 CFR Part 50.59

05000301/2014007-04 Evaluation

05000266/2014007-05 NCV Failure to Establish EFR Attributes to Assess the

05000301/2014007-05 Effectiveness of Corrective Actions

2

LIST OF DOCUMENTS REVIEWED

The following is a partial list of documents reviewed during the inspection. Inclusion on this list

does not imply that the NRC inspectors reviewed the documents in their entirety, but rather that

selected sections or portions of the documents were evaluated as part of the overall inspection

effort. Inclusion of a document on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

Corrective Action Documents

CR 01195739, CCW Pump Vibration

CR 01195885, Oil Analysis Shows Evidence of Bearing Wear on Safety Injection Pump Motor

CR 01196175, G-02 Exhibited High Axial Impact-Type Acceleration

CR 01200210, RMP For Reactor Coolant Pump Uncoupling Questioned

CR 01200598, Refueling Water Storage Tank Throttle Valve Difficult To Operate

CR 01202954, 2P-11B Alignment Problems

CR 01208186, G-01 EDG Bearing Vibration

CR 01208318, RCS Piping Stress

CR 01212030, Service Water Pump Gland Follower Improperly Aligned

CR 01215799, Inadequacies Identified In SI Pump Routine Maintenance Procedure

CR 01216019, Potential for Cracking In MSB Lift Yoke

CR 01217509, P-132 BDE Distillate Pump Alignment

CR 01390003, License Renewal Exam of STP-00014 has Minor Indication

CR 01610365, P-032C SW Pump Shaft Vibration Trending High

CR 01633548, NOS Identified IER1 11-1, Flood Barrier Door Inspection

CR 01639502, Jacking Bolt Broken For Motor Alignment

CR 01655812, 2P-10B Bearing Housing Bracket Jack Bolt Holding Alignment

CR 01660763, P-73A/B Suction And Discharge Pump Piping Misalignment

CR 01678709, NRC Issues Position on Missile Protection For G-01/02 Exhaust

CR 01691196, Operability Determination Issues Across Fleet

CR 01723755, Safe Shutdown Fire Dampers No Inspected

CR 01726015, FSAR Questions Regarding Cross Over Steam Dump Testing

CR 01727221, Plant Safe Shutdown Equipment Exposed To Tornados

CR 01736062, High Energy Line Break Door Issues

CR 01748940, Tornado Hazard

CR 01757131, Potential Violation RSPS Degraded Function

CR 01760171, G-01 and G-02 EDGs Declared Inoperable

CR 01762122, Design Basis Docs On Tornado Missiles

CR 01768931, 1P-29 Turbine Driven Auxiliary Feedwater Pump Degraded Coupling

CR 01771762, Green Finding - Weld Design Deficiency in the EDG Missile Protection Barriers

CR 01779635, Green Finding - Failure to Incorporate WOG ERG, Revision 2 into the EOPs

CR 01780474, G05 Control System Does Not Control Well

CR 01799222, 1P-28B, MFW Pump, High Vibration As-Found Alignment Data

CR 01801696, Quarterly DQS of a Licensing Topic

CR 01804588, Inadequate Scoping of Non-Safety Related System into Maintenance Rule

CR 01805402, Procedure PC 80 Part 7 Lake Water Level Determination Issues

CR 01806402, Procedure PC 80 Part 7 Lake Water Determination Issues

CR 01806545, Inconsistent Application of IPEEE Information in CLB

CR 01807841, Sand Bags Erroneously Eliminated From PB Flood Contingencies

CR 01807866, WR - Obtain Hot and Cold Pump And Motor Growth Readings

CR 01808661, Failure to Implement Risk Management Actions During Emergent Work Activities

3

CR 01808901, Coupling Misalignment On 0P-217A G-01 Circulation Oil Pump

CR 01809095, Deficiencies In PC 80 Part 7, Lake Level Determination

CR 01816327, Missing Appendix R Calculations

CR 01824582, PC 80 Part 7 CA 01809095 Due July 31, 2013

CR 01826212, Generator to Engine Coupling Is Degraded

CR 01826753, Coupling on Turbine Has Minor Damage

CR 01833683, Green Finding - Failure to Update the Fire Emergency Plan

CR 01845168, CMP for EN-AA-203-1001 Revision 10 (OD/FA) Implementation

CR 01847140, G-05 Functionality During Severe Weather

CR 01849522, G01/G02 Missile Shield Impact on External Flooding

CR 01850776, 2P-028A High Vibration At Drive End Bearing

CR 01851639, Green Finding - Failure to Submit LER Within 60 Days

CR 01853775, Basis for Flood Barriers Not Referenced In FSAR

CR 01853779, Current Licensing Basis for External Flooding Not Changed

CR 01855615, Resident NRC Inspector Roof Inspection Questions

CR 01856318, FSAR Not Updated for External Flooding Features

CR 01856322, Failure to Establish Adequate Procedures to Respond to PMP Event

CR 01856327, Failure to Maintain Features to Address Max Wave Run Up

CR 01860140, Prior to Starting Work Problems Found With TDAFWP Work Package

CR 01861967, Recent Issues Related to Operability/Functionality, April 1, 2013

CR 01863557, FSAR Errors Identified in Self-Assessment

CR 01863560, High Energy Line Break Door Issue Trending

CR 01875052, Electrical Short Circuit Protection Issues

CR 01875056, Electrical Short Circuit Protection Issues

CR 01877254, G-05 Excessive Hunting at Peak Load

CR 01879455, 2P-011B Pump OB Bearing Doweling Issue

CR 01878130, 2013 CAP FSA - CR Initiation Sensitivity

CR 01880011, Calculation 2005-0053, Revision 1 Presents Appendix R Issues

CR 01883633, Flooding Root Cause Evaluation; Revision 3

CR 01886923, Determine If An Issue Was a Missed Opportunity - Flooding

CR 01889400, Condition Evaluation Did Not Evaluate Scope Identified in Parent CR 01763937

CR 01889518, Final Effectiveness Review Prompt Operability Determinations and

Functionality Assessments

CR 01892543, Interim Actions Were Not Fully Effective (EFR 1889518)

CR 01894831, 95001 Inspection AR Screened as CAQ

CR 01894925, NRC 95001 RCE 01768931 Enhancement

CR 01895229, Routine Maintenance Procedures Lack a Specific Standard for Alignment Data

CR 01896156, Degraded Cornerstone - Mitigating Systems Two White Findings

CR 01900061, Functionality Assessment CA1806402-01 Conclusion Questioned

CR 01901996, ACE for Green Finding for Probable Maximum Precipitation Event Controls

CR 01902111, Validate That AOP-13C Will Meet Station Blackout Requirements

CR 01907036, 95002 VSGR Door Gaps Documentation Potential Deficiency

CR 01907864, 95002 Preps: Difference in Annual Snowfall Levels in FSAR

CR 01912749, Subsoil Drainage System is Blocked

CR 01914914, 2-P11A Pump Alignment Challenges

CR 01917384, Unable To Obtain Acceptable Alignment On G-03 Lube Oil Circulation Pump

CR 01918667, 1P-11A As-found Coupling Gap Below RMP Requirements

CR 01919077, Adverse Trend - Engineering CAP Backlog

CR 01920608, Adverse Trend - Engineering CAP Backlog

CR 01920659, 1P-029 As-found Alignment Checks Were Outside the Acceptance Criteria of

RMP 9044-1

4

CR 01920783, During Performance of WO# 40241255 Checking Alignment on the Terry turbine

CR 01921089, Recent Decline In Operations Performance

CR 01922342, Increase In Initiation Rate of Anonymous and NSC ARs

CR 01924763, FA Errors & Less Than Adequate CAP Threshold

CR 01927436, 2P-11B Loose Hold Down Bolts And As-Found Alignment

CR 01932698, 95002 Wave Run-Up Protection May Conflict With Other Floods

CR 01936250, Employee Behavior Not Aligning With Expectations

CR 01936497, Conflict Between AOP-13C High Winds And PC 80 Part 7 Barrier

CR 01937027, 95002 Revise NP 7.5.2 and Form PBF-9178 to Address Flooding

CR 01937424, PBSA-ENG-15-01 External Events Program Quick Hit Assessment

CR 01938711, NRC 95002 Inspection - RCE 1883633 EOCA for CC2

NRC Identified CRs

CR 01938106, Incomplete Disposition of AR 01860140 On Unit 1 TDAFWP

CR 01938122, During NRC Walk Down Black Putty and Dry Boric Acid Was Noted on the Base

Plate of the Unit 2 Train B Containment Spray Pump

CR 01938271, Snow Was on the Barrier Installation Pads As Well As A Power Cable

CR 01938314, Visible Dimple Noted Near Jacking Bolt

CR 01938317, During Walk Down Dried Boric Acid Noted on The Unit 2 Train B RHR

Pump Seal

CR 01938326, Final Effectiveness Reviews for Common Cause 1 and 2 Were Inappropriately

Reliant Upon NRC Input

CR 01938384, Alignment Issue With Valve 2RH-823B Reach Rod

CR 01938501, Maximum Precipitation and Wave Run Up Not Assessed Simultaneously

CR 01938670, Root Cause Reports Were Not Aligned with the 95002 Procedure

CR 01938711, Scope for the Extent of Cause of Contributing Cause 2 From the Flooding RCE

Is Limited to NRC Concerns Only

CR 01938749, Attachment of Spring Cans to the MOVs After All As Left Testing Completed

CR 01938706, Formal Aggregate Review of all Flooding Related CRs

CR 01938825, Potential Storm Drain Bypass of Wave Run Up Barriers Not Assessed

CR 01938861, Risk Analysis Sections in Root and Common Causes Narrowly Focused

CR 01939011, Expand FSAR Section on Probable Maximum Precipitation Event

CR 01939095, VTM Dowling Recommendation Not Incorporated Into Procedures

CR 01939217, TDAFWP Root Cause Did Not Implement a Vendor Recommendation

CR 01939345, No Corrective Actions Initiated for Flooding Barriers During Cold Weather

CR 01939362, Functionality Assessments Found Issues But No Corrective Actions Taken

CR 01939389, Needed Enhancement to FSAR Appendix A.7, Internal Flooding

CR 01939838, Remove Door 349 When Wave Run Up Barriers Are Installed

CR 01940082, Procedure PC 80 Part 7, Revision 6 50.59 Screen Error

CR 01940118, Procedure PC 80 Part 7, Revision 4 50.59 Screen Error

CR 01940511, Errors Identified in Surveillance PBF-2124

CR 01940562, Poor CAP Product Quality

CR 01940606, Errors Identified in Procedure PC 80, Part 7

CR 01940621, FSAR Revision Required

CR 01940739, Unintentional Change to PC 80 Part 7 Identified

CR 01941022, Additional Errors Found in PBF-2124

CR 01941085, Potential Licensing Basis Questions Identified

CR 01941262, Quality Level of Flood Related Doors in Error

CR 01941902, Readiness for Inspection Letter Sent the Same Day as it Was Identified That the

Site was Not Ready for the Inspection

5

CR 01942059, Another Error Found In PBF-2124

CR 01942315, Several Drawing Errors Identified

CR 01942317, Error Identified On ARB C01 B1-1

CR 01942343, Error Identified In AOP-13C

CR 01943803, Use of Wrong NRC Cross Cutting Code in Effectiveness Review Criteria

CR 01946330, Severity Level IV Violation for 50.59 - Use of Roll-Up Doors

Drawings

M-1, Equipment Location Plan Containment Operating Floor Unit 1, Revision 19

M-3, Water Intake Facility General Arrangement Plan B-B, Revision, November 17, 1967

M-4, Water Intake Facility General Arrangement Plan C-C and D-D, November 17, 1967

M-15, Water Intake Facility Piping Section F-F, November 4, 1969

M-16, Circulating Water Pump House Piping, Revision 13

M-2007, Equipment Location Plan Ground Floor North, Revision 22

M-2009, Equipment Location Plan Sections H-H and K-K, Revision 9

M-2010, Equipment Location Miscellaneous Section, Revision 5

C-1, Site Plan, Revision 19

6704-E-121001, Plant Key Plan, Drawing, Index and Specification Numbers, Revision 4

6704-E-121102, Diesel Generator Building Floor and Roof Plan, Revision 5

6704-E-151001, Diesel Generator Building Yard Area Grading Plan, Revision 3

M-165, Turbine Building Floor & Equipment Drainage Area No 3 - Plan at EL. 8.0, Revision 6

Licensee Procedures

AD-AA-103, Nuclear Safety Culture Program, Revision 5

EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 7

EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 11

EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 12

EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 15

RMP 9044-1, Auxiliary Feedwater Pump Terry Turbine Overhaul, Revision 35

RMP 9376-1, Limitorque MOV Removal, Installation, SWAP, and Testing for Gate and

Globe Valves

RMP 9376-2, Limitorque MOV Static/DP Testing for Gate and Globe Valves

RMP 9376-3, Limitorque MOV Removal, Installation, and Adjustment for Butterfly Valves

RMP 9376-4, Limitorque Motor Operator Model SMB-000 Disassembly, Inspection Repair,

and Re-Assembly

RMP 9376-5, Limitorque Motor Operator Model SMB-0 Through SMB-4 Disassembly,

Inspection, Repair, and Re-Assembly

RMP 9376-6, Limitorque Motor Operator Model SMB-00 Disassembly, Inspection, Repair, and

Re-Assembly

RMP 9008-1, RHR Pump Removal and Installation

RMP 9005-2, SI Pump Overhaul

Vendor Manual 0501, Pacific Pumps, Inc.

AOP-13C; Abnormal Operating ProcedureSevere Weather Conditions, Revision 32

NP 7.5.2; PBNP Owner Controlled Area Temporary Structure Limitations, Revision 12

NA-AA-200, Employees Concern Program Process Description, Revision 5

PI-AA-01, Corrective Action Program and Condition Reporting, Revision 3

PI-AA-204, Condition Identification and Screening Process, Revision 22

PI-AA-205, Condition Evaluation and Corrective Action, Revision 23

PI-AA-100-1005, Root Cause Analysis, Revision 8

6

PI-AA-100-1006, Common Cause Evaluation, Revision 6

PI-AA-100-1007, Apparent Cause Analysis, Revision 7

PI-AA-100-1008, Condition Evaluation, Revision 5

PI-AA-101-1001, Quick Hit Assessments, Revision 5

MA-AA-203-1001, Work Order Planning, Revision 1

PDM 1.0, Vibration Monitoring Program

Procedure IT 02, High Head Safety Injection Pumps and Valves Train B, Unit 2

Procedure IT 03, Low Head Safety Injection Pumps and Valves Train A, Unit 1

Procedure IT 06, Containment Spray Pump and Valves

Procedure IT 12, 1P-11B, Component Cooling Water Pumps and Valves Unit 1

Procedure IT-07D, Service Water Pump (Quarterly) Surveillance

PC 80 Part 7, Lake Water Level Determination, Revision 3

PC 80 Part 7, Lake Water Level Determination, Revision 4

PC 80 Part 7, Lake Water Level Determination, Revision 5

PC 80 Part 7, Lake Water Level Determination, Revision 6

PC 80 Part 7, Lake Water Level Determination, Revision 7

PC 80 Part 7, Lake Water Level Determination, Revision 8

PC 80 Part 7, Lake Water Level Determination, Revision 9

PC 80 Part 7, Lake Water Level Determination, Revision 10

CL 11A G-02, G-02 Diesel Generator Checklist, Revision 29

NP 7.2.29; External Events Program, Revision 0

Root Cause Reports

RCE 01757131, Potential Violation Due to a Degraded Emergency Planning Risk Significant

Planning Standard Function, Revision 4

RCE 01768931, Unit 1 Turbine Driven Auxiliary Feedwater Pump 1P-29 Coupling Degraded

During IT-08A Run, Revision 5

RCE 01883633, Potential Greater Than Green Finding Flooding, Revision 3

RCE 01896156, Degraded Cornerstone - Mitigating Systems Two White Findings, Revision 1

Calculations

FPL-076-CALC-017, Maximum Precipitation Analysis for Past Reportability, Revision 0

CALC 2008-0024, AFWP Room Flood Basis CalculationJanuary 23, 2014, Revision 1

CALC 2009-0008, Circulating Water Pump House Internal Flooding, Revision 1

FPL-076-CALC-016, Flow Depth Sensitivity to Openings with Wave BarriersFebruary 6, 2014,

Revision 0

FPL-076-CALC-003, Point Beach DELFT3D Surge and Wave Model, Revision 0

EC 279455, Time Available to Respond to Threat From Rising Water, June 24, 2013

FPL-076-CALC-014, PBNP Precipitation and Snow Intensity Determination and Roof Drainage

Evaluation - December 18, 2013, Revision 0

FPL-076-CALC-015, Maximum Precipitation Flood Effects - January 7, 2014, Revision 0

CALC 2014-0002, Effects on Safety Equipment of Bypassing the Installed Wave Run-Up

Barriers Through The Storm Drains - February 11, 2014, Revision 0

Miscellaneous Documents

List of Technical Procedure Revisions for 2013

Presentation for Outage Review Board Team Meeting, February 4, 2014

Corrective Action Review Board Package for February 4, 2014

7

PBSA-PBNP-13-013, Quick Hit Assessment Report for the 95002 Mock Inspection for

Degraded Cornerstone, October 29, 2013

PBSA-ENG-07-13, 2008 Component Design Basis Inspection Preparations, March 10-20, 2008

PBSA-ENG-10-20, Focused Self-Assessment of Flooding Program, September 20-23, 2010

PBSA-ENG-11-01, Component Design Basis Inspection Preparations, January 17-27, 2011

PBSA-ENG-06-02, SA Preparation for Design Basis Inspection Based on 71111.21,

January 16 - February 2, 2006

PBSA-ENG-12-20, Quick Hit Assessment ReportFlooding Program, April 15 - May 24, 2013

PBSA-PBNP-13-02, CR 01908740, Quick Hit Assessment Report Station Nuclear Safety

Culture, September 23 through October 4, 2013

PBSA-PBNP-12-02, Quick Hit Assessment Report Station Nuclear Safety Culture

September 17 through 20, 2012

MOR 2013-23, Missed Opportunity ReviewPotential Greater Than Green FindingFlooding,

July 9, 2013

NOS Daily Quality Summary Related to Flooding MORGas Accumulation Management

Program, April 24, 2013

CEI Independent Evaluation, Point Beach Root Cause Evaluation for NRC White Performance

IndicatorFlooding, September 20, 2013

EC 280223, Review of Flooding Vulnerability Report for Possible CLB Encroachment,

October 22, 2013

NEE 05-PR-003, Flooding Vulnerability Report, Revision 0

EN-AA-203-1001 Operations TrainingOperability Determinations/Functionality Assessment

Training Materials, August 28, 2013

EN-AA-203-1001 Engineering Lesson PlanOperability Determinations/Functionality

Assessments, July 3, 2013

SCR 2013-0213, 50.59 Screening Form FSAR Sect 2.5 PMP FloodJanuary 28, 2014,

Revision 1

Monthly Weather ReviewThe Prediction of Surges in the Southern Basin of Lake Michigan;

May 1965

NPC98-00509, Harza Preliminary Hydrologic and Hydraulic Studies for Nuclear Power Plant

Site Selection, March 18, 1966

NOS Observations, October 30, 2008, November 20, 2009, August 16, 2010, April 23, 2011,

November 19, 2011

Point Beach Daily Quality Summary - 1P-29 Turbine Driven Auxiliary Feedwater Pump,

January 27, 2012

Point Beach Daily Quality Summary - Initial Auxiliary Feedwater Pump and Terry Turbine

Alignment, June 22, 2012

Point Beach Daily Quality Summary - Terry Turbine Oil Change and Sampling, July 02, 2012

PBN 12-010, Nuclear Oversight Report: Maintenance-Corrective and Preventative,

July 12, 2012

Point Beach Daily Quality Summary - 1/2 P-38 AFW Pump October 16, 2012

PBN-12-014, Nuclear Oversight Report: System Engineering, November 19, 2012

Point Beach Daily Quality Summary - 2P-29 TDAFW Pump Assembly, November 19, 2012

PBN-13-003 Nuclear Oversight Report: Engineering Design, March 8, 2013

Point Beach Daily Quality Summary - Fire Protection Walkdown P-53 Motor Driven Auxiliary

Feed Pump Rooms, October 2, 2013

MOR 2013-09 Missed Opportunity Review, 1-29-T, Auxiliary Feed Water Pump Turbine

Coupling Failure, CR 1846183, February 7, 2014

WO 383111-01, STP-00014; Inspect for License Renewal per LR-TR-519, May 17, 2010

WO 40188994-09, Simulate PC 50 Part 7 Draft with New Barriers (PMT), November 21, 2013

WO 40188994-04, Verify Ability to Place and Secure Jersey Barriers (PMT), July 10, 2013

8

Fleet Daily Quality Summary ReportFukushima, November 22, 2011

Point Beach Daily Quality Summary ReportFlooding Related, April 4, 2012

Point Beach Nuclear Oversight ReportFire Protection and Flood Doors, October 7, 2010

Point Beach Nuclear Oversight ReportISFSI Environmental Impacts Audit, July 14, 2011

Point Beach Nuclear Oversight ReportReview of OE Related to Flooding and Actions Taken,

March 8, 2013

Point Beach Nuclear Oversight ReportReview of CommitmentsFlooding Walk Downs,

March 30, 2013

Fleet Daily Quality Summary ReportFlooding Underground Cables, January 21, 2008

WO 40220319-01, PC 80 Part 7 Install CWPH Concrete Block Barriers, February 4, 2014

Pictures of Wave Barriers Constructed, November 26, 2013

9

LIST OF ACRONYMS USED

ADAMS Agencywide Document Access Management System

AFW Auxiliary Feedwater

AR Action Request

CAPR Corrective Action to Prevent Recurrence

CC Contributing Cause

CCA Common Cause Analysis

CCDP Conditional Core Damage Probability

CDF Core Damage Frequency

CFR Code of Federal Regulations

CLB Current License Basis

CR Condition Report

CW Circulating Water

CWPH Circulating Water Pump House

CY Calendar Year

DRP Division of Reactor Projects

EFR Effectiveness Review

EJ Expansion Joint

EP Emergency Preparedness

EPRI Electric Power Research Institute

FA Functionality Assessment

FP Fire Protection

FSAR Final Safety Analysis Report

gpm Gallons per Minute

HCLPF High Consequence of Low Probability of Failure

HEP Human Error Probability

IMC Inspection Manual Chapter

INPO Institute of Nuclear Power Operations

IP Inspection Procedure

IPEEE Individual Plant Examination External Events

IR Inspection Report

IST In-service Test

KSA Knowledge Skills and Abilities

LERF Large Early Release Frequency

LOCA Loss of Coolant Accident

LOOP Loss of Off-Site Power

MOV Motor Operated Valve

N/A Not Applicable

NCV Non-Cited Violation

NOV Notice of Violation

NRC U.S. Nuclear Regulatory Commission

OEM Original Equipment Manufacturer

OSHA Occupational Safety Health and Safety

PARS Publicly Available Records

PC Procedure Call-Up

PMP Probable Maximum Precipitation

PMT Post Maintenance Test

PRA Probabilistic Risk Assessment

PWR Pressurized Water Reactor

RASP Risk Assessment Standardization Project

10

RC Root Cause

RCE Root Cause Evaluation

ROP Reactor Oversight Process

SCWE Safety Conscience Work Environment

SDP Significance Determination Process

SME Subject Matter Expert

SPAR Standardized Plant Analysis Risk

SQAC Significant Condition Adverse to Quality

SRA Senior Reactor Analyst

SW Service Water

TDAFWP Turbine Driven Auxiliary Feedwater Pump

TB Turbine Building

TS Technical Specification

URI Unresolved Item

VTM Vendor Technical Manual

Yr Year

WO Work Order 11

E. McCartney -3-

previous terminology will be converted to the latest revision in accordance with the

cross-reference in IMC 0310. The revised cross-cutting aspects will be evaluated for

cross-cutting themes and potential substantive cross-cutting issues in accordance with

IMC-0305 starting with the CY 2014 mid-cycle assessment review.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and

its enclosure, and your response (if any) will be available electronically for public inspection in

the NRC Public Document Room or from the Publicly Available Records System (PARS)

component of NRC's Agencywide Documents Access and Management System (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

Anne T. Boland, Director

Division of Reactor Projects

Docket Nos. 50-266; 50-301

License Nos. DPR-24; DPR-27

Enclosure:

IR 05000266/2014007; 05000301/2014007

w/Attachment: Supplemental Information

cc w/encl: Distribution via ListServTM

Distribution:

See next page

DOCUMENT NAME: PB 2014 007

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII RIII RIII RIII

NAME BBartlett:mt/rj JCameron

BBartlett for

DATE 04/27/14 04/27/14

OFFICIAL RECORD COPY

Letter to Eric McCartney from Ann Boland dated March 28, 2014

SUBJECT: POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2

NRC 95002 SUPPLEMENTAL INSPECTION REPORT

05000266/2014007; 05000301/2014007

DISTRIBUTION:

Ernesto Quinones

RidsNrrDorlLpl3-1 Resource

RidsNrrPMPointBeach

RidsNrrDirsIrib Resource

Cynthia Pederson

Darrell Roberts

Steven Orth

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

Patricia Buckley

ROPassessment.Resource@nrc.gov