Info Meeting with a Question and Answer Session to Discuss NRC 2022 EOC Plant Performance Assessment of Ptbh, Units 1 and 2
ML23171B106
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 06/21/2023
From: Karla Stoedter
NRC/RGN-III/DORS/RPB2
To: Strope M
Point Beach
Shared Package
ML23013A321 List:
References
Download: ML23171B106 (1)


Text

Michael Strope Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516

SUBJECT:

INFORMATION MEETING WITH A QUESTION AND ANSWER SESSION TO DISCUSS NRC 2022 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2

Dear Michael Strope:

This letter is to inform you that the U.S. Nuclear Regulatory Commission (NRC) will conduct an Information Meeting with a Question and Answer Session on Monday, July 10, 2023, from 5:30 p.m. to 6:30 p.m. (CDT) at Two Rivers Fire Department, 2122 Monroe Street, Two Rivers, WI. The purpose of this meeting is for the NRC staff to meet directly with individuals to discuss regulatory and technical issues. Attendees will have an opportunity to ask questions of the NRC staff or make comments about the issues discussed throughout the meeting, however the NRC is not actively soliciting comments towards regulatory decisions at this meeting.

Specifically, members of the NRC will be available to discuss the assessment of Point Beach Nuclear Plant, Unit 1 and 2 performance. NextEra Energy is encouraged to participate in this meeting.

If you have any questions regarding this meeting, please contact me at 630-829-9731.

Sincerely, Karla Stoedter, Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket Nos. 05000266, 05000301 License Nos. DPR-24 and DPR-27 cc: Distribution via LISTSERV June 21, 2023 Signed by Stoedter, Karla on 06/21/23

Letter to Michael Strope from Karla Stoedter dated June 21, 2023.

SUBJECT:

INFORMATION MEETING WITH A QUESTION AND ANSWER SESSION TO DISCUSS NRC 2022 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 DISTRIBUTION:

Paul Zurawski RidsNrrDorlLpl3 RidsNrrPMPointBeach RidsNrrDroIrib Resource John Giessner Mohammed Shuaibi Diana Betancourt-Roldan Allan Barker R3-DORS ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML23171B106 Publicly Available Non-Publicly Available Sensitive Non-Sensitive OFFICE RIII RIII NAME RNg:gmp KStoedter DATE 06/21/2023 06/21/2023 OFFICIAL RECORD COPY