IR 05000266/2019004
ML20036E023 | |
Person / Time | |
---|---|
Site: | Point Beach |
Issue date: | 02/05/2020 |
From: | Richard Skokowski Division Reactor Projects III |
To: | Craven R Point Beach |
References | |
IR 2019004 | |
Download: ML20036E023 (27) | |
Text
ary 5, 2020
SUBJECT:
POINT BEACH NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000266/2019004 AND 05000301/2019004
Dear Mr. Craven:
On December 31, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Point Beach Nuclear Plant and discussed the results of this inspection with Mr. B. Woyak, Site Safety Assurance and Learning Director, and other members of your staff.
The results of this inspection are documented in the enclosed report.
One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Point Beach Nuclear Plant. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA by Michael Kunowski Acting for/
Richard A. Skokowski, Chief Branch 4 Division of Reactor Projects Docket Nos. 05000266 and 05000301 License Nos. DPR-24 and DPR-27
Enclosure:
As stated
Inspection Report
Docket Numbers: 05000266 and 05000301 License Numbers: DPR-24 and DPR-27 Report Numbers: 05000266/2019004 and 05000301/2019004 Enterprise Identifier: I-2019-004-0059 Licensee: NextEra Energy Point Beach, LLC Facility: Point Beach Nuclear Plant Location: Two Rivers, WI Inspection Dates: September 30, 2019 to December 31, 2019 Inspectors: K. Barclay, Resident Inspector M. Garza, Emergency Preparedness Inspector T. Hartman, Senior Resident Inspector G. O'Dwyer, Reactor Engineer G. Roach, Senior Operations Engineer L. Rodriguez, Reactor Inspector J. Seymour, Reactor Ops Engineer Approved By: Richard A. Skokowski, Chief Branch 4 Division of Reactor Projects Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Point Beach Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations Main Feedwater Isolation Valve Component Materials not Suitable for Environmental Conditions Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green None (NPP) 71111.15 Systems NCV 05000266,05000301/2019004-01 Open/Closed The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Title 10 CFR Part 50, Appendix B, Criterion III, "Design Control," when the licensee failed to assure the main feedwater isolation valve actuators and supporting subsystem components installed in the plant were suitable for the environment under which they were required to operate.
Additional Tracking Items None.
PLANT STATUS
Unit 1 began the inspection period at rated thermal power. On October 23, 2019, power was reduced to below 60 percent to support turbine stop and governor valve testing. The Unit returned to rated thermal power on October 24, 2019, and remained at or near rated thermal power for the remainder of the inspection period.
Unit 2 operated at or near rated thermal power for the entire inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.04Q - Equipment Alignment Partial Walkdown Sample (IP Section 03.01)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) G-02 emergency diesel generator on November 16, 2019
- (2) Unit 1 containment spray train A on November 21, 2019
- (3) Unit 2 motor-driven auxiliary feedwater pump on December 16, 2019
71111.04S - Equipment Alignment Complete Walkdown Sample (IP Section 03.02)
- (1) The inspectors evaluated system configurations during a complete walkdown of the Unit 2 safety injection system on November 26, 2019.
71111.05A - Fire Protection (Annual) Annual Inspection (IP Section 03.02)
- (1) The inspectors evaluated fire brigade performance on December 2, 7, and 17, 2019.
71111.05Q - Fire Protection Quarterly Inspection (IP Section 03.01)
The inspectors evaluated fire protection program implementation in the following selected areas:
- (1) Fire Zones 308 and 309 on November 1, 2019
- (2) Fire Zones 304N, 304S, and 305 on December 15, 2019
71111.06 - Flood Protection Measures Inspection Activities - Internal Flooding (IP Section 02.02a.)
The inspectors evaluated internal flooding mitigation protections in the:
- (1) emergency diesel generator building
- (2) circulating water pump house
71111.07T - Heat Sink Performance Triennial Review (IP Section 02.02)
The inspectors evaluated heat exchanger/sink performance for the following:
- (1) Emergency Diesel Generator (G-02) Heat Exchanger (HX-055B), cooled by the service water system, Section 02.02.b
- (2) Ultimate Heat Sink, Sections 02.02.d.5 and 02.02.d.7
71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance Requalification Examination Results (IP Section 03.03)
- (1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered from September 23, 2019 to October 16, 2019.
71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance Licensed Operator Requalification Program (IP Section 03.04)
- (1) Biennial Requalification Written Examinations The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on August 30, 2018.
Annual Requalification Operating Tests The inspectors evaluated the adequacy of the facility licensees annual requalification operating test.
Administration of an Annual Requalification Operating Test The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.
Requalification Examination Security The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.
Remedial Training and Re-examinations The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.
Operator License Conditions The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.
Control Room Simulator The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.
Problem Identification and Resolution The inspectors evaluated the licensees ability to identify and resolve problems associated with licensed operator performance.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)
- (1) The inspectors observed and evaluated licensed operator performance in the control room during a Unit 1 downpower to support main stop valve testing on October 23, 2019.
- (2) The inspectors observed and evaluated licensed operator performance in the control room during Unit 1 Rod operability testing on November 5, 2019.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated a licensed operator simulator scenario on November 18, 2019.
71111.12 - Maintenance Effectiveness Routine Maintenance Effectiveness Inspection (IP Section 02.01)
The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:
- (1) Unit 2 auxilary feed water valve 2AF-4000 failed to close on November 7, 2019
- (2) Bus H-02 13.8 kV breaker failed to close on March 21, 2019
- (3) G-05 gas turbine generator tripped on September 12, 2019
Quality Control (IP Section 02.02) (1 Sample)
The inspectors evaluated maintenance and quality control activities associated with the following equipment performance activities:
- (1) Maintenance activities related to the failure of Unit 2 feed water isolation system in January of 2019, and quality control issues related to the commercial grade dedication of reactor protection replacement relays, which failed in April and May of 2019.
71111.13 - Maintenance Risk Assessments and Emergent Work Control Risk Assessment and Management Sample (IP Section 03.01)
The inspectors evaluated the risk assessments for the following planned and emergent work activities:
- (1) elevated risk due to 1P-29 turbine-driven auxiliary feedwater pump maintenance and testing on October 24, 2019
- (2) elevated risk due to emergent maintenance on G-02 emergency diesel generator on November 15, 2019
- (3) elevated risk due to 1P-15B safety injection pump being out-of-service during valve testing on December 26, 2019
71111.15 - Operability Determinations and Functionality Assessments Operability Determination or Functionality Assessment (IP Section 02.02)
The inspectors evaluated the following operability determinations and functionality assessments:
- (1) evaluation of the minimum operating temperature of the main feedwater isolation valves
- (2) increased reactor coolant system leakage through a letdown control valve
- (3) slowly lowering auxiliary feedwater accumulator pressure
- (4) evaluation of the flooding implications related to identified drain valve leakage into the residual heat removal pump cubicles
- (5) degraded performance on the #3 crossover steam dump valve
71111.18 - Plant Modifications Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)
The inspectors evaluated the following temporary or permanent modifications:
- (1) white and yellow bus inverter and static switch replacement
71111.19 - Post-Maintenance Testing Post-Maintenance Test Sample (IP Section 03.01)
The inspectors evaluated the following post maintenance tests:
- (1) 0-PT-FP-003, Electric Motor-Driven Fire Pump Functional Test, after maintenance on the P-35A motor-driven fire pump on October 15, 2019
- (2) testing after auxiliary feed water relief valve replacement on October 24, 2019
- (3) testing after maintenance on 2AF-4000 turbine-driven auxiliary feedwater pump discharge valve on November 7, 2019
- (4) testing after SW-4479 actuator diagnostic maintenance on November 5, 2019
- (5) testing after G-02 emergency diesel generator strainer housing maintenance on November 15, 2019
- (6) testing after DY-0D inverter replacement on October 31, 2019, and November 1, 2019
71111.22 - Surveillance Testing The inspectors evaluated the following surveillance tests: Surveillance Tests (other) (IP Section 03.01)
- (1) Unit 1 turbine-driven auxiliary feedwater pump cold start testing on October 23, 2019
- (2) Unit 1 train A containment spray pump and valve testing on November 20, 2019
71114.04 - Emergency Action Level and Emergency Plan Changes Inspection Review (IP Section 02.01-02.03)
- (1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
- 2018-PB-044, Emergency Plan 7.0, 11/16/18
- 2018-PB-046, Emergency Plan Appendix L, 11/16/18
- 2019-PB-001, Emergency Plan Appendix A, 02/02/19
- 2019-PB-002, Emergency Plan 5.0, 02/05/19
- 2019-PB-003, Emergency Plan 2.0, 02/05/19
- 2019-PB-004, Emergency Plan 6.0, 02/05/19
- 2019-PB-010, Emergency Plan Implementing Procedure 1.2-1, 05/20/19
- 2019-PB-011, Emergency Plan Implementing Procedure 1.2, 05/20/19
- 2019-PB-012, Emergency Plan Appendix B, 05/20/19
- 2019-PB-013, On-shift Staffing, 06/03/19 This evaluation does not constitute NRC approval.
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
MS09: Residual Heat Removal Systems (IP Section 02.08) ===
- (1) Unit 1 October 1, 2018 - September 30, 2019
- (2) Unit 2 October 1, 2018 - September 30, 2019 MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)
- (1) Unit 1 October 1, 2018 - September 30, 2019
- (2) Unit 2 October 1, 2018 - September 30, 2019
71152 - Problem Identification and Resolution Semiannual Trend Review (IP Section 02.02)
- (1) The inspectors reviewed the licensees corrective action program, trend reports, major equipment problem lists, system health reports, self-assessments, and additional documents, to identify trends that might indicate the existence of a more significant safety issue.
INSPECTION RESULTS
Main Feedwater Isolation Valve Component Materials not Suitable for Environmental Conditions Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green None (NPP) 71111.15 Systems NCV 05000266,05000301/2019004-01 Open/Closed The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Title 10 CFR Part 50, Appendix B, Criterion III, "Design Control," when the licensee failed to assure the main feedwater isolation valve actuators and supporting subsystem components installed in the plant were suitable for the environment under which they were required to operate.
Description:
On January 30, 2019, the licensee received a Main Feedwater Isolation Valve (MFIV) trouble annunciator. The licensee dispatched an operator to investigate and found the Unit 1 main feedwater isolation valve (MFIV) actuator extend 3-way valve, 1CS-256B, blowing air to the atmosphere. The operator also reported that the pressure at the MFIV accumulator, 1CS-256B, was reading 200 psig and lowering. The licensee declared Unit 1 Train B MFIV, 1CS-3125, inoperable and shut the associated air valve to stop the air leak. This allowed the accumulator to restore pressure above the minimum Technical Specification requirement of 227.5 psig. The MFIVs are safety-related and required to isolate the feedwater system in the event of a main steam line break inside containment.
The licensee determined that the cause of the valve leakage was "extreme" cold temperatures. At the time, the local area temperature was 3 degrees F. The licensee determined that the o-ring seals and valve seats (elastomers) were made from a rubber compound that lost its flexibility at that low temperature. In addition, the elastomers would shrink at a much faster rate than the surrounding metal challenging their ability to seal properly. The licensee added portable heaters to the area, which raised the local area temperature. The licensee unisolated the air to the valve, verified that valve was no longer leaking, and returned the components and system to operable within the technical specifications allowed outage time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.
A follow-up by the resident inspectors questioned why the valve leaked at a temperature of 3 degrees F when they were qualified for -20 degrees F. The licensee determined that the
'Viton' elastomers included in the components was not effective at sealing in significantly cold temperatures. The licensee also found the valves they installed were only manufactured for a minimum temperature +20 degrees F, when the design called for components to be qualified down to -20 degrees F. This was due to some communication and verification errors between the licensee and vendor supplying the components. The extent of condition identified 24 valves that could directly affect the performance of the MFIVs that were installed without meeting design specifications. The licensee also identified more than 96 components that utilize an elastomer that could be adversely affected by the cold weather. The MFIVs and their associated components were installed in 2011 under Engineering Change (EC) 258382 for Unit 1 and EC 258480 for Unit 2.
Corrective Actions: The licensee added portable heaters to the area to raise local area temperatures and revised their cold weather procedure to ensure the area remains above 35 degrees F throughout the cold season. The licensee is planning on adding heat tracing to the components of concern as well as replacing the components with an appropriate material that will meet the original design criteria.
Corrective Action References: AR 2328869
Performance Assessment:
Performance Deficiency: The inspectors determined that failure to ensure systems and components were capable to perform their design function in the associated environmental conditions was a performance deficiency. Specifically, the licensee installed safety-related components with elastomers in an environment that could fall below the minimum temperature for its application, which caused the valve to leak and render the system inoperable.
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the MFIV actuator extend 3-way valve, 1CS-256B, began leaking which depressurized the safety-related accumulator below the minimum operable pressure of 227.5 psig. This rendered the associated MFIV inoperable because it can no longer be assured to close during a main steam line break event.
Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Specifically, the inspectors determined that this finding is of very low safety significance (Green) because they answered "No" to all questions in Exhibit 2.
Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.
Enforcement:
Violation: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires, in part, that measures be established for the selection and review for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems and components.
Contrary to the above, since June 7, 2011 (for Unit 2), and December 9, 2011 (for Unit 1), the licensee failed to review for suitability of application of materials essential to the safety-related functions of the MFIVs. Specifically, the licensee utilized a type of elastomers that were not appropriate for the environmental conditions (extreme cold) they could be subject to.
Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
Observation: Semiannual Trend Review 71152 During the inspection quarter, the inspectors reviewed a significant number of licensee corrective action program documents to assess the following performance attributes:
- complete, accurate, and timely documentation of the identified problem in the corrective action program;
- evaluation and timely disposition of operability and reportability issues;
- consideration of extent of condition and cause, generic implications, common cause, and previous occurrences;
- completion of corrective actions in a timely manner commensurate with the safety significance of the issue; and
- identification of negative trends associated with equipment performance that can potentially impact nuclear safety.
The inspectors reviewed the site's response to several deficiencies associated with control rods due to the increasing number and repetitive nature of the deficiencies. The inspectors identified that in 2019, the rod control and position indication systems experienced several occurrences of either blowing fuses during rod movement or experiencing erratic indication while stationary.
The inspectors noted that the failure of rod control fuses in August 2019 was identical to a failure that occurred in December 2018. In December 2018, the failure caused Unit 2 Rod F-6 to insert 20 steps into the core. Troubleshooting efforts were not able to identify any direct causes, so the licensee implemented a modification to change the fuse rating from 10 Amps to 15 Amps to account for small power spiking. In August 2019, a similar failure caused Rod F-6 to insert completely into the core. Again, troubleshooting efforts were unable to identify the cause, so the licensee implemented another modification to change the fuse rating from 15 Amps to 25 Amps. Additionally, the licensee changed the frequency of rod testing to minimize the number of times the rods needed to be moved, therefore limiting the chances for the fuses to fail. The licensee also recognized this same rod experienced a similar failure in December 2010 with no cause identified. The licensee is planning additional troubleshooting and repairs during the upcoming outage. The inspectors independently reviewed the licensees efforts and verified the rods remain capable of performing their safety-related function.
The inspectors also noted an increasing frequency of erratic control rod indications. In November 2019, Unit 2 Rod J-4 began intermittently indicating positions other than its actual 228 steps. Troubleshooting did not identify any direct causes and the licensee was unable to correct the erratic indications. The licensee declared J-4 rod position indication inoperable and continues to perform the required TS actions. In December 2019, Unit 1 Rod H-8 began experiencing the same issue. Troubleshooting did not identify a direct cause and the licensee was unable to correct the erratic indication. The licensee declared H-8 rod position indication inoperable and continues to perform the required TS actions. The licensee is planning additional troubleshooting and repairs during the upcoming outages.
The inspectors did not identify any findings or violations of more than minor significance.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On December 31, 2019, the inspectors presented the integrated inspection results to Mr. B. Woyak, Site Safety Assurance and Learning Director, and other members of the licensee staff.
- On October 4, 2019, the inspectors presented the Heat Sink Performance inspection results to Mr. R. Craven, Site Director, and other members of the licensee staff.
- On October 11, 2019, the inspectors presented the Biennial inspection of the licensed operator requalification program inspection results to Darren Peterson, Site Training Manager, and other members of the licensee staff.
- On November 14, 2019, the inspectors presented the Biennial inspection of the operator license conditions portion of the licensed operator requalification program inspection results to Mr. A. Fahrenkrug, Operations Training Supervisor, and other members of the licensee staff.
- On December 13, 2019, the inspectors presented the Emergency Preparedness Inspection Exit Meeting inspection results to Mr. D. Smith, Emergency Preparedness Manager, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
71111.04Q Corrective Action AR 2327911 G-501, Aux Diesel Generator, Start 09/13/2019
Documents AR 2329945 Procedure Step Incorrectly Marked N/A 10/01/2019
AR 2330266 Human Performance Error During DY-0D Wire Bypass Work 10/03/2019
AR 2337674 Red Lock Applied To 1AF-233B (High Side ISO To 12/7/2019
1FIT4074A)
Drawings 110E017 Sh. 3 P&ID Safety Injection System, Unit 1 48
M-207 Sheet 1A P&ID Service Water 42
M-209 Sheet 12 PI&D EM. Diesel Air Starting Sys. 23
M-217 Sheet 1 PI&D Auxiliary Feedwater System 104
M-219 Sheet 1 P&ID Fuel Oil System 51
M-219 Sheet 2 P&ID Fuel Oil System Diesel Generator Building 16
M-2217 P&ID Auxiliary Feedwater System 7
Miscellaneous CL 7A Safety Injection System Checklist Mode 1, 2, 3 Unit 1 38
Procedures 1-SOP-Y-001 Shifting 120V RPS/Safeguards Instrument Buses 8
Work Orders 40574458 2DY-04 EC 290150 Yellow Bus Inv & Static Rep. 10/04/2019
71111.04S Corrective Action AR 2337610 Blue Boric Acid Identified On 2SI-897B 12/06/2019
Documents
Resulting from
Inspection
Drawings 110E035 Sheet 1 P&ID Safety Injection System Unit 2 56
110E035 Sheet 2 P&ID Safety Injection System Unit 2 60
Procedures TLB 17 Tank Level Book 9
Safety Injection Accumulators 1(2)T-34 A/B
71111.05A Fire Plans PFP-2-TB 8 Pre-Fire Plan Unit 2 Turbine Building Elev 8 FT 1
Miscellaneous Fire Drill Package 12/06/2019
Fire Drill Package 12/02/2019
Procedures AOP-40 Response To Fire 5
NP 2.4.1 Fire Brigade Program 2
NP 4.2.32 Respiratory Protection Program 19
PC 75 Part 1 Monthly and Turnaround Maintenance For The Scott 4.5 33
Self-Contained Breathing Apparatus
Inspection Type Designation Description or Title Revision or
Procedure Date
PC 75 Part 2 Monthly Fire Brigade Equipment Inventory 20
PFP-SOG-001 Pre-Fire Plan Standard Operating Guidelines 0
71111.05Q Corrective Action 2315273 Incorrect Information Basis Provided to NRC 05/22/2019
Documents AR 2195016 OM 3.27 High Safety Significant Fire Barrier Questionable 03/30/2017
AR 2300038 Door Did Not Close Freely Due To Wind 01/31/2019
AR 2302041 OM 3.27 Not Updated Timely With New HSS Barriers 02/14/2019
AR 2302823 HSS FP SYS Components Not Conservative in OM 3.27 02/21/2019
Fire Plans PFP-0-CB Pre-Fire Plan Control Building Elev. 8 ft., 2 ft., 44 ft., and 2
ft.
Miscellaneous FPTE 2016-019 PBNP Detailed Fire Modeling Report: Fire Compartment 1
304N, Auxiliary Feedwater Pump Room North Section,
EL. 8'-0"
FPTE 2016-020 PBNP Detailed Fire Modeling Report: Fire Compartment 1
304S, Auxiliary Feedwater Pump Room South Section,
EL. 8'0"
FPTE 2016-021 PBNP Detailed Fire Modeling Report: Fire Compartment 1
305, 4160V Vital Switchgear Room, EL. 8'-0"
FPTE 2016-022 PBNP Detailed Fire Modeling Report: Fire Compartment 1
308, Diesel Room - G01, EL. 8'-0"
FPTE 2016-023 PBNP Detailed Fire Modeling Report: Fire Compartment 1
309, Diesel Generator - G02, EL. 8'-0"
71111.06 Calculations 2009-0008 Circulating Water Pump House Internal / External Flooding 0&2
2014-0007 Allowable Flood Levels 3
2014-04473 Internal Flooding Assessment of Emergency Diesel 1
Generator Building
Corrective Action 2330050 Inconsequential Error In DGB Flooding Calculation 10/02/2019
Documents
Resulting from
Inspection
Drawings E-121202 Diesel Generator Building Concrete Plan @ EL 28' - 0" 8
Procedures ARB C81 4-1 Alarm Response Book - Building Sump / Trench Level Hi 1
ARP C01 B 1-2 Alarm Response Procedure - Electric Fire Pump Running 3
NP 8.4.17 PBNP Flooding Program 32
Work Orders 40339097 02 DGB / Inspect Piping From Trenches Inside Building 01/27/2015
Inspection Type Designation Description or Title Revision or
Procedure Date
40644281 Test PAB and TB Sump Alarms 10/26/2019
71111.07T Calculations 2005-0054 Control Building GOTHIC Temperature Calculation 8
Corrective Action 02188565 Delaminating Coating and Pits Inside HX-12B 02/28/2017
Documents 02249144 HX-55B, G-02 Glycol Cooler HX, Foreign Material Found 02/12/2018
249167 Missing Piece from F-222 North Strainer Basket Might be 02/12/2018
Same as Piece Found in AR 02249144
286065 U2 A Containment Fan Cooler Tubes Need Plugging 10/16/2018
296665 South SW Header Flowmeter Calibration 01/04/2019
2304475 P-32C SW Pump Performance Outside Acceptance Criteria 03/05/2019
2304497 P-32A SW Pump OOS Due to Hi Flow on IT-07A Comp. 03/06/2019
Test Data
2307153 Inspect HX-15D Coils & Condensate Drains 03/25/2019
2310869 Rebaselining of P-32A and P-32C Improvements 04/16/2019
2314119 FS-3765 G02 EDG Fire Protection Flow Switch Failure 05/12/2019
During TS-76
2315218 Elevated Seat Leakage on SW-LW-61 Radwaste SW Return 05/22/2019
2316108 FS-3765 Will Not Clear Upon Restoration Following 05/29/2019
Maintenance
Corrective Action 02330268 2019 Heat Sink Inspection Question Regarding SW-833 10/03/2019
Documents 02330279 NRC UHS Inspector Identified Inconsistent HX-55B 10/03/2019
Resulting from Inspection Results Documentation
Inspection 02330281 2019 Heat Sink Inspection Question on FSAR Temp. 10/03/2019
Disparity
Drawings CBDM-207 ISI Classification Diagram Service Water 40
CBDM-217 ISI Classification Diagram Auxiliary Feedwater System 41
CBDM-2207 ISI Classification Diagram Service Water 33
Engineering 15413 Control Room Alternate Cooling 0
Changes
Engineering PMCR 2174658 Periodic Maintenance Change Request Evaluation to 02/07/2017
Evaluations Reduce Frequency of HX-55B Inspect and Clean From One
Year to Two Years
Miscellaneous Control 01832 HX-55A/B G-01/G-02 Glycol to Water HX specification sheet 09/12/2007
and Form U-1 Manufacturer's Data Report
Inspection Type Designation Description or Title Revision or
Procedure Date
UFSAR 2018 Point Beach Nuclear Plant Units 1 & 2 Final Safety Analysis UFSAR
Report 2018
Operability 2265466 SW-LW-62 Timing Shut Issue 07/19/2018
Evaluations
Procedures AOP-13A Circulating Water System Malfunction 25
AOP-13C Severe Weather Conditions 48
AOP-9A Service Water System Malfunction 37
ARP C02 F 3-1 Alarm Response Procedure for Emergency Diesel Generator 08/06/2014
G-02 Glycol Cooler Low Flow Alarm
Work Orders 40399570 GL 89-13 Inspect Crib/Install Buoys and Fish Deterrent 08/03/2016
40425576 HX-055B Eddy Current Testing 01/05/2017
40430951 2HX-015A1 - A8 GL 89-13 Clean Heat Exchanger as Req. 01/25/2019
40430992 GL 89-13 Inspect and Clean Pumphouse Forebay 04/18/2017
40431005 IT-275, 2SW-2880 SW Supply to TB2 (CSD) 04/21/2017
40438452 GL 89-13 Inspect Crib/Remove Buoys and Fish Deterrent 09/23/2016
40461873 Inspect and Clean G-02 EDG HX-55B 01/05/2017
40462394 HX-012B GL 89-13 Open/Inspect/Clean/Close HX 03/14/2017
40473343 IT-270, 1SW-2880 SW Supply to TB1 (CSD) 10/20/2017
40473363 FL 89-13 Inspect and Clean Pumphouse Forebay 11/08/2017
40486697 SFP and Radwaste SW VLV Leak Checks 02/25/2017
40493054 ICP 6.42 - Intake Surge Chamber Level Detection 08/11/2017
40520839 G-02 EDG Endurance And Margin Testing per TS 82 09/10/2018
40544125 IT-275, 2SW-2880SW Supply to TB2 (CSD) 11/23/2018
40549413 HX-055B GL 89-13 Open/Inspect/Clean/Close G-02 EDG 02/12/2018
HX-55B
40556859 SFP and Radwaste SW VLV Leak Checks 03/22/2018
40573714 IT-270, 1SW-2880 SW Supply to TB1 (CSD) 05/03/2019
40595167 ICP 6.42 - Intake Surge Chamber Level Detection 02/15/2019
40599350 IT-72, Service Water Valves 03/29/2019
40607973 IT-07A, P-32A Service Water Pump Test 03/20/2019
40607974 IT-07B, P-32B Service Water Pump Test 03/20/2019
40610316 2 Year IT-07C, P-32C Service Water Pump 03/20/2019
40613620 IT-07F, P-32F Service Water Pump Test 05/27/2019
Inspection Type Designation Description or Title Revision or
Procedure Date
40613631 IT-07D, P-32D Service Water Pump Test 05/27/2019
40614733 IT-72, Service Water Valves 06/10/2019
40619402 SFP and Radwaste SW VLV Leak Checks 05/29/2019
40627240 2Z-027-4 Lubricate and Maintain Screen 08/15/2019
40629182 TS-76 , Automatic Spklr/Water Spray Surv. Test 08/23/2019
40629229 TS-34, U2C Accident Fan Cooler Units Surv. Test 09/19/2019
40656371 2Z-027-1 Lubricate and Maintain Screen 08/13/2019
40665061 FS-3765 G02 EDG Fire Protection Flow Switch Failure 06/19/2019
71111.11B Corrective Action AR 2259869 Abnormal Response of 2HC-468 A Atmos. Controller 04/16/2018
Documents AR 2261478 Update ADV Controllers to Match Plant 04/25/2018
AR 2277741 HU Issues Need to be Reviewed in Aggregate 08/28/2018
AR 2315732 Missed Technical Specification Action Entry 05/25/2019
AR 2330250 NRC Change in Medical Condition Not Reported to NRC 10/03/2019
AR 53745 Inability to Null Steam Generator Atmospheric Dump 02/11/2004
Controllers
Corrective Action AR 2330832 NRC Identified Simulator Testing Parameter Not Meet 10/08/2019
Documents ANSI-3.5
Resulting from
Inspection
Engineering Cycle 38 Testing Real Time Test; 100% Steady State Drift Test; Steady State 02/03/2018
Evaluations Performance Testing; Malfunction Testing
Cycle 39 Testing Real Time Test; 100% Steady State Drift Test; Steady State 04/10/2019
Performance Testing; Malfunction Testing
Post Event Unit 1 Plant Trip - Circulating Water Malfunction 06/14/2018
Testing
SCT 6.2.2. Unit 1 48% Power Steady State Performance Test Unit 1 02/03/2018
SCT 6.2.2. Unit 1 75% Power Steady State Performance Test Unit 1 C39 09/09/2019
SCT 6.2.3 Unit 1 48% Power Steady State Performance Test Unit 1 C39 09/09/2019
SCT 6.2.3 Unit 1 28% Power Steady State Performance Test Unit 1 C38 01/20/2018
Miscellaneous 2018 EXAM 3 RO RO Written Examination 08/30/2018
2018 EXAM 3 SRO Written Examination 08/30/2018
Attendance Licensed Operator Continuous Training Attendance Records 2018-2019
Inspection Type Designation Description or Title Revision or
Procedure Date
Records
eSOMS Credit for Watch Proficiency Records 10/03/2019
Standing Watch
10/1/2017 to
9/30/2019
Reports
eSOMS Credit for Watch Proficiency Record 10/10/2019
Standing Watch
6/1/2019 to
6/30/2019 Report
License 2018 and 2019 License Reactivation Records Various 2018-2019
Reactivation
Records
Medical Records Licensed Operator Medical Records (Various) 10/08/2019
PBF-6097 Operations Watchstander Temporary Restriction Form 06/14/2019
PBN JPM Job Performance Measure 5
P000.002d.COT
PBN JPM Job Performance Measure 9
P000.012a.AOT
PBN JPM Job Performance Measure 8
P000.029.AOT
PBN JPM Job Performance Measure 0
P000.039r.AOT
PBN JPM Job Performance Measure 2
P000.052.COT
PBN JPM Job Performance Measure 1
P004.013b.COT
PBN JPM Job Performance Measure 1
P010.002.COT
PBN JPM Job Performance Measure 2
P028.002a.EMR
PBN JPM Job Performance Measure 0
P060.002b.AOT
PBN JPM Job Performance Measure 0
Inspection Type Designation Description or Title Revision or
Procedure Date
P062.006a.COT
PBN JPM Job Performance Measure 2
P064.010.COT
PBN LOC 000 Simulator Scenario Guide 4
004E
PBN LOC 000 Simulator Scenario Guide 0
054E
PBN LOC 000 Simulator Scenario Guide 0
057E
PBN LOC 000 Simulator Scenario Guide 0
064E
Performance Licensed Operator Annual Examination Performance 2018-2019
Records Records
Remediation 2018 and 2019 Remediation Packages Various 2018-2019
Records
Training Plan Long Range Training Plans 2018-2020 2018-2020
Procedures DTG 94.0 Simulator Health Management 4
DTG 94.1 Scenario-Based Testing Desktop Guide 04/25/2013
DTG 94.3 Simulator Work Requests 3
FP-T-SAT-74 NRC Operator License Application and Renewal 9
Requirements
OP-AA-100-1001 License Maintenance and Activation 6
TR-AA-220-1002 NRC Licensed Operator Exam Security 4
TR-AA-220-1004 Licensed Operator Continuing Training Annual Operating 5
and Biennial Written Exams
TR-AA-221-1000 Simulator Change Control 5
TR-AA-230-1007 Conduct of Simulator Training and Evaluation 12
Self-Assessments AR - L2A #: NRC IP 71111.11 Pre-Inspection Assessment 08/25/2019
26212
PBN 17-007 Nuclear Assurance Audit of Point Beach Training Program 08/11/2017
Work Orders SWR 02104275 EC 284214 Unit 2 PORV Pneumatic Backup (NFPA 805) 01/21/2016
SWR 02150118 EC 283634 Replace 1HC-135 Letdown Backpressure 08/16/2016
Controller
Inspection Type Designation Description or Title Revision or
Procedure Date
SWR 02181583 EC 286487 Replace 1TR-2000A, 1TR-2000B, and 1TR- 01/25/2017
2001 Recorders
SWR 02212171 SW Pump Discharge Check Valve Failure Malfunction 06/26/2017
SWR 02308612 Excessive Steam Dump Capacity 07/10/2019
SWR 02323981 Condensate Pump Mini Recirculation Flow Orifice Size 08/09/2019
SWR 02329323 Xenon Response During Rapid Load Reduction 09/26/2019
71111.11Q Corrective Action AR 2333755 U1 Turb Stop Vlv Testing Date Incorrect - NRC Identified 10/31/2019
Documents
Resulting from
Inspection
Miscellaneous PBN LOC 19F As Found 0
003E
Procedures OP 2D Unit 1 Power Operation Maneuvering - Unit 1 1
TS 5 Rod Exercise Test Unit 1 35
71111.12 Corrective Action AR 2272613 Issue Discovered with Commercial Grade Dedication 07/18/2019
Documents AR 2286089 2P-11A Pump To Motor Coupling Retorque (PWE) 10/16/2018
AR 2299832 1CS-256B Leaking Air To Atmosphere (Air To CS-3125 01/30/2019
MFIV)
AR 2303942 1AF-4006-O MOV Wiring Drawing Issues 02/28/2019
AR 2306821 H21-21 Breaker Failed To Close 03/21/2019
AR 2312211 Unusual Odor From 1C-164 RP Train B Relay Logic Cabinet 04/25/2019
AR 2312347 Relay 1RC-3A Found De-Energized During Visual 04/26/2019
Inspection
AR 2312381 Bus H-02 MR Planned Unavailability Perf Criterion 04/26/2019
Exceeded
AR 2313368 RC-4A Found Dropped Out During WR94193589 05/06/2019
AR 2313489 Early Failure of Reactor Protection Relays 05/06/2019
AR 2313558 CAT ID 9087982 Lists Incorrect Part Number 05/07/2019
AR 2314346 CPED Extent of Condition 05/14/2019
AR 2315450 IEE Paperwork Not Performed For RPS Relays 05/23/2019
AR 2320440 Replace 1RC-1A, 1RC-2A, and 1RC-4A Reactor Protection 07/09/2019
Relays
AR 2327756 G-05 Trip Post-Maintenance During PC 29 Trip 17 09/12/2019
Inspection Type Designation Description or Title Revision or
Procedure Date
AR 2334539 2AF-4000 Failed to Close 11/07/2019
AR 2338314 FME Controls Not Documented 12/13/2019
Corrective Action AR 2335957 Corrective Action Closure Notes Not Aligned 11/18/2019
Documents
Resulting from
Inspection
Drawings 499B466 Sheet Elementary Wiring Diagram Turbine Driven Auxiliary 16
867 Feedwater Pump Discharge
Engineering EE 484267 Commercial Grade Evaluation For Catalog ID 9087982 06/11/2019
Evaluations (Reactor Protection Relay)
Miscellaneous Maintenance Rule Scoping and Performance Criteria: 3&4
13.8KV System
Maintenance Rule Performance Criteria: Condensate and 06/06/2012
Feedwater System
Maintenance Rule Performance Criteria: Auxiliary Feedwater 02/24/2016
Maintenance Rule Performance Criteria - Gas Turbine 02/07/2006
Maintenance Rule (a)(1) Status Evaluation: 13.8 KV 06/12/2019
Maintenance Rule (a)(1) Action Plan: 13.8KV 10/03/2019
EVT-GT-2019- Maintenance Rule Functional Failure Evaluation For AR 09/26/2019
36351 2327756
Procedures MA-AA-101-1000 Foreign Material Exclusion Procedure 24
RMP 9374-4 Functional Testing of Contactors / Thermal Overload Relays 10
Work Orders 40574589 01 1RP - Replace Train A RT and RC Relays 04/14/2019
40575120 13 2AF-04000 / Remove Sealtite 10/10/2019
40575120 14 2AF-04000 / Reinstall Sealtite 10/18/2019
40575120 19 2AF-04000; Stroke Valve-PMT 10/19/2018
40648400 01 1CS-256B Leaking Air To Atmosphere (Air To 1CS-3125 04/13/2019
MFIV)
71111.13 Corrective Action AR 2335107 Strainer Cleaning Not Included In Risk Profile 11/11/2019
Documents
Miscellaneous Current Risk Summary Report; PBN Unit 1 and 2 10/24/2019
Current Risk Summary Report; PBN Unit 1 and 2 11/15/2019
Point Beach Station Unit 1 and 2 Daily Status Report 10/24/2019
Inspection Type Designation Description or Title Revision or
Procedure Date
Current Risk Summary Report; PBN Unit 1 and 2 12/26/2019
Phoenix Risk History 12/26/2019 -
2/27/2019
71111.15 Calculations 2014-0007 Allowable Flood Levels 3
2014-02058 Internal Flooding Effects 2
Corrective Action AR 2299832 1CS-256B Leaking Air to Atmosphere (Air to 1CS-3125 01/30/2019
Documents MFIV)
AR 2330625 Valve Leak By 10/07/2019
AR 2332670 1OS-3-DV (Xover Steam Dump Valve 3) Degraded 10/23/2019
Performance
AR 2334885 Increased RCS Unidentified Leakage due to 1CV-112A 11/09/2019
Leakby
AR 2337517 Pressure in 1T-224B Slowly Decreasing Since 10/28/19 12/04/2019
Corrective Action AR 2328869 MFIV Design Low temperature Value of -20 deg F 09/23/2019
Documents Questioned
Resulting from AR 2339135 RHR Cubicle Drain Valve Leakage 12/20/2019
Inspection
Drawings 684J971 Sheet PI&D Waste Disposal System 78
1A
Engineering 2019-0022 Evaluation of RHR Cubicle Drain Valve Backleakage 0
Evaluations
Miscellaneous Flowserve Certificate of Compliance/Conformance [for Main 03/25/2011
Feedwater Isolation Valve Components]
NPM 2002-0595 Siemens Westinghouse Engineering Study WEP-02-0135 11/08/2002
Dated 09/24/02
Work Orders 40641320 01 2WL-04100 Valve Leak Check 10/07/2019
40641321 01 1WL-04101 Valve Leak Check 09/19/2019
40641322 01 2WL-04101 Valve Leak Check 10/07/2019
71111.18 Corrective Action AR 2332170 Inverter Transfer Lockout Switch Operation Not As Expected 10/19/2019
Documents AR 2332502 New 2DY-04 Inverter Aligned To 2Y-104 Over Voltage Alarm 10/22/2019
AR 2332530 Changes in Yellow Power Instrument Readings 10/22/2019
AR 2333726 Track Updates For EC 291314 (NRC Open Phase 10/31/2019
Inspection)
Inspection Type Designation Description or Title Revision or
Procedure Date
AR 2334823 WO Directed Calibration of Wrong Relay 11/08/2019
AR 2334984 Unexpected Inverter Trouble Alarms During Tagout 11/11/2019
Engineering 290150 White and Yellow Bus Inverter and Static Switch 3
Changes Replacement
Miscellaneous Failure Modes and Effects Analysis: 12kVA Inverter 09/06/2018
Work Orders 40574458 10 2DY-04 EC 290150 Yellow Bus INV & Static Switch Rep. 10/19/2019
40574458 18 1DY-04, Wire Static Switch Control Circuit From TB-49 10/01/2019
40574458 41 2-27/Y04 and 2-27/Y104 Under Voltage Relay Calibrations 11/08/2019
71111.19 Corrective Action AR 2334362 SW-04479 Measured Packing Friction Exceeds Target 11/05/2019
Documents Value
AR 2334369 SW-04479 Active Packing Leak 11/05/2019
AR 2336432 Incorrect PMT In 1RMP 9306-1 and 2RMP 9306-1 11/21/2019
Corrective Action AR 2335692 FME Practices Observed Not In Compliance With 11/15/2019
Documents Requirements
Resulting from AR 2337901 Work Package Has Inconsistent Placekeeping - NRC 12/10/2019
Inspection Identified
AR 2339922 Procedure Step Signed Off Out of Order, NRC Identified 01/03/2020
AR 2339952 Follow Up From AR 2337901 01/03/2020
Procedures 1RMP 9306-1 Main Steam Non-Return Check Valve Inspection Without 1
Removing Cover (Unit 1)
2RMP 9306-1 Main Steam Non-Return Check Valve Inspection Without 1
Removing Cover (Unit 2)
Work Orders 40574462 12 DY-0D, OPS and EM To Energize and Test New Inverter 11/01/2019
40618352 B52-P-035A - Circuit Breaker Test 10/15/2019
40618861 SW-04479-O: MOV Actuator Diagnostics & Inspections 11/05/2019
40667301 1AF-4061/Replace Relief Valve 10/24/2019
40671070 B42-P-035A - Contactor Clean, Inspect & Test 10/15/2019
40673408 Change Oil in P-035A-M Change Oil in Electric Fire Pump 10/15/2019
Motor
40676320 0-PT-FP-003 Electric Motor-Driven Fire Pump Functional 10/15/2019
Test
40690970 2AF-4000 Failed To Close Troubleshooter 11/07/2019
40690970 03 2AF-04000 OPS PMT / RTS Testing 11/07/2019
Inspection Type Designation Description or Title Revision or
Procedure Date
40691838 01 F-222/EDG HX-55B Inlet Strainer Will Not Isolate 11/15/2019
40691838 04 HX-055B Open/Inspect G-02 EDG Coolant HX 11/15/2019
71111.22 Procedures IT 05 Train A Train A Containment Spray Pump and Valves Unit 1 7
IT 08A Cold Start of Turbine-Driven Auxiliary Feed Pump and Valve 82
Test (Quarterly) Unit 1
OP 2A Unit 1 Normal Power Operation Unit 1 12
71114.04 Corrective Action AR02271508 50.54(q) Domentation Improvement 07/10/2018
Documents AR02272045 References for the Emergency Plan 07/13/2018
AR02294041 Commitment Not Updated Following LAR 12/11/2018
AR02313560 Emergency Plan Documents not Revised to Remove the 05/07/2019
OSRPF
AR02316012 Emergency Preparedness Annual Review - 10CFR 50.54(q) 05/29/2019
Discrepencies
Miscellaneous 2018-PB-044 Emergency Plan 7.0 11/16/2018
2018-PB-046 Emergency Plan Appendix L 11/16/2018
2019-PB-001 Emergency Plan Appendix A 02/05/2019
2019-PB-002 Emergency Plan 5.0 02/05/2019
2019-PB-003 Emergency Plan 2.0 02/05/2019
2019-PB-004 Emergency Plan 6.0 02/05/2019
2019-PB-010 Emergency Plan Implementing Procedure 1.2-1 05/20/2019
2019-PB-011 Emergency Plan Implementing Procedure 1.2 05/20/2019
2019-PB-012 Emergency Plan Appendix B 05/20/2019
2019-PB-013 On-shift Staffing 06/03/2019
71151 Corrective Action AR Searches; Systems: Component Cooling Water, Service 10/01/2018 -
Documents Water 09/30/2019
AR Searches; Systems: Residual Heat Removal 10/01/2018 -
09/30/2019
Miscellaneous MSPI Derivation Reports; Residual Heat Removal, Cooling 10/01/2018 -
Water; Unavailability Index; Units 1 and 2 09/30/2019
MSPI Derivation Reports; Residual Heat Removal, Cooling 10/01/2018 -
Water; Unreliability Index; Units 1 and 2 09/30/2019
MSPI Margin Reports; Units 1 and 2 10/01/2018 -
Inspection Type Designation Description or Title Revision or
Procedure Date
09/30/2019
PBN-BFJR-18- MSPI Basis Document for PBNP 26
054
71152 Corrective Action AR 2294755 Control Rod F-06 Experienced Uncontrol motion 12/14/2018
Documents AR 2298207 IRPI F-6 at 22 Steps Deviation / Limit is 24 01/16/2019
AR 2298878 Unit 1 IRPI Deviation Greater Than 8 Steps 01/22/2019
AR 2299991 IRPI J-10 on 2C-04 Lowered by 8 Steps (PPCS Indic Stable) 01/31/2019
AR 2320920 F-8 IRPI Eratic Indication 07/14/2019
AR 2321593 F-08 RPI Drifting on 1C-04 07/18/2019
AR 2324133 Dropped F-6 Rod 08/12/2019
AR 2332919 Momentary Control Rod Deviation Alarm 10/24/2019
AR 2334233 IRPI for Unit 2 J-04 is Noisy 11/04/2019
AR 2335253 Unit 2 RPI J4 Noisy, IRPI is OOS 11/12/2019
AR 2336143 Trend AR for IRPI Issues 11/19/2019
Miscellaneous Trend Report Jun 1 - Nov 30, 2019 12/02/2019
24