{{#Wiki_filter:!sc Arizona Nuclear Power Project P.O. BOX $2034 o PHOENIX, AmZoNA 85072-20M                  1933 fgy ,b Of fQ ANPP-33899 November 1, 1985        q[gfggEg  .
Mr. John B. Martin, Director US Nuclear Regulatory Commission Region V 1450 Maria Lane, Suite 210 Walnut Creek, CA 94596
 
==Subject:==
Palo Verde Nuclear Generating Station Unit 2 Construction Status and Operational Readiness Report Docket No. STN 50-529 File: 85-056-026
 
==Reference:==
Letter dated October 10, 1985 from                        D. F. Kirsch, NRC, to E. E. Van Brunt, Jr.,          APS     
 
==Subject:==
Construction Status and Operational Readiness Report
 
==Dear Mr. Martin:==
 
The referenced letter requested that ANPP provide information in the subject
  - areas listed in Attachment 1 of the referenced letter.                  Attachments to this provide the following information:
: a. Project History
: b. Licensee and Contractor Initiated Stop Work Actions                                              ,
: c. Construction Deficiency Evaluation Reports (DER's) d.-  Construction Status
: e. Preoperational Test Status
: f. Independent Third Party Inspections
: g. Licensee and Contractor Audits Attachments b. , c. , f. and g. are not Unit Specific t
(
A SO
 
Mr. John B. Martin.
Palo Verde Nuclear Generating Station Unit 2    .
Construction Status and Operational Readiness Report
    .Page Two ANPP-33899
    -If you have any further questions regarding this information, please call Mr. W. F. Quinn of my staff.
Very truly yours,
          ,                                                              /
                                                        -  R          /\W(
E. E. Van Brunt, Jr.
Executive Vice President Project Director EEVB/WFQ/JK0/dle Attachments cc:    E. A. Licitra-
          'R. Zimmerman-A. C. Gehr M. Iey
 
7.-
i Mr.' John;B.' Martin-Palo Verde Nuclear Generating Station Unit 2
                -Construction Status and Operational Readiness Report Page Three-ANPP-33899
              - bcca    'D. B. Karner'                      'All w/a
                        'J. G. Haynes
                        -R. M. Butler W. E. Ide W. F. Quinn T.-F. Quan M. A. Jones LCTS Coordinator J. R. Bynum J. Orlowski                ,
A. J. McCabe W. G. Bingham
                        .S. Shapiro        .
C. Ferguson T. Bradish
                        .P.-Brandjes I
 
L a._    Project-History Palo Verde Nuclear Generating Station Unit No. 2 PIANT CHARACTERISTICS:
              ' Docket No.:                05000529 CP No. & Date Issued:      CPPR-142/05-25-76 CP Expiration Date:        12/31/85 Applicant:-                Arizona Public Service Company Plant Incation:            36 miles west of Phoenix, AZ ~
IE Region:                  V AE:                        Bechtel NSSS:                      Combustion Engineering Constructor:                Bechtel                                ,
Reactor Type:              PWR DER (MWE):                  1304 KEY PERSONNEL:
Corporate
 
==Contact:==
E. E. Van Brunt,    Jr.,  ANPP Executive Vice President Corporate Address:          P. O. Box 53999 Phoenix, AZ_ 85072-3999 Corporate Phone No.:        (602) 932-5300 NRC LPM:                    E. Licitra IE Resident Inspector:      R. Zimmerman/G. Hernandez FUEL LOAD DATE CHANGES AS REPORTED BY UTILITY:-
Reason for Change Report Date      New Schedule                  Reported by Utility 07-28-82        08-01-84            Impact of scheduling problems with 08-16-83        02-01-85            key equipment. Augmentation of the 03-26-84      Last Quarter          plant's emergency response system of 1985            as results of TMI lessons learned.
Complexity of the transition from construction    to  start-up  phase.
Unit 1 delays.
LOCAL PUBLIC DOCUMENT ROOM:
Phoenix Public Library 12 East McDowell Road Phoenix, AZ 85004 0323K/0016K u
 
      -b  r
            %                          /
Status as of 10/20/85 CONS 1RUCTION STATUS REPORT
                                                      . NUCLEAR POWER PIANTS Palo Verde'2
: CONSTRUCTION STATUS:
Applicant's Current Estimated Fuel Imading -Date:              11/00/85
                      ' Applicant's' Previous-Estimated Fuel Load Date:                08/01/84
                      -Applicant's-Estimated Fuel Inading Date at CP Issuance:-        .11/00/83 Applicant's Current Estimated Commercial Operation Date:        Second Quarter of 1986 Applicant's Construction Completion Estimate as-Defined in CP: (Earliest)- 02/01/83 (Latest)      12/31/85 (CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 99%
COMMENTS EEGARDING CURRENT CONSTRUCTION STATUS:
ESTIMATED ACTUAL ESTIMATED        ACTUAL      ESTIMATED START    START    COMPLETION COMPLETION % COMPLETE Mobilize and Prepare site:                            06/76' _              06/77          ~100%
                      . Place structural
                          . concrete:                      .08/77'                12/81          100%
                      -Install Reactor Pressure Vessel:                06/80                07/80          100%
                      -Install Large Bore 05/85          100%
l Process Pipe:                    09/78 Install Large Bore
                          ' Pipe Hangers, Restraints, and Snubbers:.                      10/78                05/85          100%
Install Small
:Scre Pipe:. .
04/79-      11/85  -
99.6%
Install Cable Tray:                  06/78                03/82          100%
                      -Install Exposed Mital Conduit:                  01/78      10/85                    99.9%
Install Power,-
Control, Instrumen-tation and Security Cable:                          02/81      11/85                    99.5%
Install Electrical Terminations:                    05/81      11/85                    99.1%
Conduct Reactor Cold Hydrostatic Test:                11/84                11/84          100%
Conduct Hot Functional
                          -Test:                            06/85                08/85          100%
                      . Conduct Preop and Acceptance Test
                          .Necessary'for Fuel Inad:                      03/83      11/85                    88%
iT
 
s
                        - b., -Licensee and Contractor Initiated Stop Work Actions
                                    ' Licensee Initiated Stop Work Actions
                                                                                        ~
          '- Year    Organization            Reason / Period,            Corrective Actions 1978'    Bechtel'          Radial bends did not meet    -Rework tag prepared in
                                      ~ drawing - requirements. Re-  compliance with WPP/QCI pairs started without NCR      54.0 As-built survey record
                                      .or repair instructions docu- attached to NCR. NCR mented. (12/13/78-12/15/78) issued C-Y-1078 (12/14/78) 1979    -Bechtel          ASME code acceptance cri-      Test data and results ob-teria not met for ultra-      tained for acceptance of sonic testing. (7/31/79-      double welded stainless 8/21/79)                      steel pipe.
1981    Bechtel and      Insulation being deformed      Deforming of insulation CE              to fit between Reactor        analyzed and accepted.
: Vessel and RV support col-    Gaps minimized.
uans and technical justi-fication not provided for assurance of quality and in-tegrity of system not' vio-lated. (5/5/81-5/21/81) 1981    Bechtel          Procedures / instructions or  Procedure initiated and PCN controls not developed to '    written to WPP/QCI 28.0 control the connection and charging of batteries to assure safety of personnel and equipment. (8/31/81-9/1/81)-
            ~1981    Bechtel          Five Star Grout 150 used and Authorization for use de-does not meet required        leted from 13-CM-365.
strength.    (12/14/81-4/28/82)
          . 1982    AFS Operations Control of temporary elec-        90AC-0ZZ11 identified as trical jumpers, temporary-      procedure for Startup to lifting of. terminal leads,    use: 73AC-9ZZ05 was re-temporary ' change of set-    vised to be in effect only points and use of temporary at fuel load.
modification not being per-formed in accordance with 73AC-9ZZ05 but in accordance with 90AC-0ZZ11. (4/1/82-4/2/82) 0050K/0003K 1
                    - Year            Organization                                                  Reason / Period                          Corrective' Actions 1982        .Bechtel-
:                                              Tendons            1 stored without weat- All tendons discussed in-her protection.z (5/18/82- spected, rust removed and 5/21/82)                                        -recoated. No signs of pit-
                                                                                                                                      . ting or other: deficiency.
Considered acceptable and-c~
covered with plastic for-weather protection.
                                                                                                                      ,                  Western Concrete personnel reinstructed in require-
                                                                                                                                    -    ments for storage of-tendons.
                      -    'l f j                                              ,
i 1982- =Bechtel                                              Stopped installation of                              Issue of DCP 1SN-SQ-001, 5:                                ;                ' sample supply lines to air                            Rev. 5. Existing system
            ,N*
radiation monitors as'sup-                            installed in accordance
>                                                                                Lply sample lines are not                              with current revision of-designed to requirements of design drawing. Problem ANSI N13.1 Seat B5.                                  resolved on QAF82-45.
(5/27/82-6/29/82) 1982          Bechtel-                                      Material accountability not Complete inventory taken, being maintained in Zone III controlled access material area established for this                            and tool log updated. Re-work. (6/2/82-6/2/82)                                moved section pipe spool-and inspected. Area in-spected, personnel in-L                                                                                                                                          structed.
~
                        .1982          Bechtel                                      Procedure cancelled which                            BPC will re"tew WPP-QCI
                              '                                                      governs BPC preparation for 31.0 and write PCN; review
"                                                                                    area' transfer / release. Re- Fire Barriers, Cable Tray quirement for~ inspection /                          Covers and Conduit Sealant acceptance of cable tray                              and incorporate into exist-covers and barriers dele-                            ing procedures or add to ted. Requirement for in-                              WPP/QCI 31.0 spection/ acceptance of un-scheduled commodities has e                                                                                    been deleted as was commit-
-                                                                                    ment to verify installation /
inspection documentation with-in scope of area transfer.
(7/20/82-7/22/82) 1982 .APS Startup                                            Test Director not certified Test Director will be fa-as' qualified for test MG300, miliarized with the pro-
      ~
FPN P02. (7/21/82-7/22/82) cedure and familiarization will be documented. QC to be present during test.
i t
i e e
                ._          -      .. . _ . _ . . ~. _ ...-._._ _ _ . _ _ _ - - _ _ . ~ . - _ . . . - _ _ _ . ~ _ . _ . - , .
 
  -Year  Oraanization            Reason / Period              Corrective Actions 1982  APS'Startup      Circuit breaker removed        -90GA-0ZZ28 revised and without permission and no.      Maintenance will assure clearance was requested nor that personnel are aware' issued. ~(8/4/82-8/4/82)        of station clearance re-quirements and test con-duct requirements.
1982 .BPC Startup        Failure to:- respond in a      Corrective actions agreed        ,
and APS        timely manner to OTNs; to      on by Bechtel.and APS QA.
Maintenance. implement requirements of.
                            'AD-112'with regard to M&TE usage-logs and forms; to re-spond to calibration overdue                                  "
                          . notices; to comply with ANSI:
N45.2.16, Section 3; provide an adequate response to CAR 82-036. (9/17/82-9/18/82) 1982 -Maintenance        Work Order 482 & 483 issued Procedure initiated in'ac-to set safety valves did not cordance with code and provide adequate instruc-      specifications. - Special tions to perform the work      instructions issued with as required by code, ASME      work orders.
Section XI.    (10/14/82-11/21/82) 1982- APS and            Valves SGN-HV-05 and SGN-HV- Performed required actions Bechtel        06 were stroked over a two of steam generator      re-Startup        hour period and allowed ap- covery plan, proximately 100,000 gals.
of highly contaminated H 2O into the secondary side of SG1 and at the time SG2 was                                      t unknown. Isolation valves for nitrogen purge thought to'be closed were open. (10/19/82-10/19/82) 1983  APS Startup      Cleanliness of Iow Pressure Inspection to determine and            Safety Injectica System was amount 'of damage and veri-
            -Operations    ~ indeterminate and continued fication of cleanliness.
operation without corrective Potential.causes for entry action could lead to signi- of foreign material into ficant damage to LPSI pumps. system investigated. On-(1/18/83-1/19/83)              going inspections and evaluation of system cleanliness.
y          ,,
u F
Year          Orsanization          Reason / Period            ' Corrective' Actions 1983' JAPS Startup            Startup and Maintenance Per- 90AC-0ZZO2 and 90GA-0ZZ28 Operations  sonnel were not performing    were revised and require a work activities in accord-      review of TER's prior to
                        -                      ance with approved project      rework or installation of procedures. (2/8/83-3/4/83) materials on "Q" class com-ponents to determine if an NCR should be written of if it    is  reportable. All' TER's written 1/17/83-2/11/83 to be reviewed.
                .1983            Bechtel        Typical drawings in FCR        DCP issued providing ne-71577E differ signifi-        cessary drawing clari-cantly from actual field      fication.
conditions and bolts could be installed incorrectly.
Original field conditions will become indeterminate if bolts are installed without adequate directions.
(11/21/83-4/14/84)
                ,1983. .Bechtel                Reportability evaluation in DCPs-were transmitted to question. If skewed T          Resident Engineering for joints do not affect safety reportability review. Con-why are welds being re--      dition not reportable.
paired? (11/23/83-12/20/83) 1983          Combustion      Personnel records do not      Inspectors performed demon-
: Engineering  provide documentation of-      stration of proficiency.
certification of inspectors.
1            (11/28/83-12/2/83) 1983          Innryco, Inc. Contract PV83-8215 Specifi- Program was reviewed and fication 83-95.71-06-001 did approved.
4                                  did not adequately in-plement the applicable technical and quality re-quirements which must be in-posed on Inryco as a result of the scope of work Inryco is to perform. (12/16/83-
                                                -12/30/83)
                              ^-                    -
Bechtel'Initia ed Stop Work Actions
    ^            ~
Year    Orsanization              . Reason / Period            Corrective Actions
        +
1977  ..Sh  urt el ff &-    E-7018 weld rod not stored    Drying ovens obtained Andrews        in drying ovens              from Bechtel. SDDR (6/17/77 - 6/17/77)          issued.
1978. Peabody            Penetrant materials not      Materials-tested & OK, Testing        analyzed.                    procedures revised (1/12/78 - 1/27/78)
          '1978. Construction'          Unauthorized M-6 solvent      SAR Change Notice 814 used-for cleaning.            issued to define qualifi-
                                                                      - cation parameters. WPP/QCI
                                                  ~
(2/10/78    .3/16/78) 14.0 revised.
          '1979      Construction        Youngstown pipe material      Radiograph accomplished -
is suspect - DER 79-4        no defects found.
(5/18/79 - 6/22/79) 1979    Clark              Unacceptable curing          construction NCRs issued.
Painting        operations (11/5/79 -        Supplier QA program 11/8/79)                      improvement initiated.
1980    Construction        Rockbestos Class IE cable    Supplier and Bechtel may have unqualified          controls implemented.
splices. DER 80-4              Cable qualified, any (3/5/80 - 10/24/80)          cable with repairs is approved for outside containment only.
1980    Construction      .HPSI suction pump piping      Piping arrangements were may not be acceptable to      determined acceptable.
pump supplier. DER 79-13 (3/28/80 - 11/14/80) 1980    Construction        ITT Grinnell pipe supports  ' Acceptable - based on Code were received were under-    ' Inquiry, ASME File No.
                                      -size fillet welds.              NI-77-406.
r DER 80-6 -(4/25/80 - 7/8/80)
          .1980'    construction        Certain cable pulling        Condition acceptable based stopped due to potential      on engineering analysis. i
                                        ' deficiency in Containment                                I rebar detailing. DER 80-19                              i (6/30/80'- 10/18/80) i l
l v    ,                                                  ,
Year ~              Organisation            Reason / Period                      Corrective Actions 1980: . Construction'                  Unit 3 shell ~ concrete                Condition acceptable based i
placement stopped based                on engineering analysis, on 80-SW-4 and DER 80-19.
:(6/30/80 - 10/17/80) 1980:                Construction    . Unit 2 anchor bolts for .              Design change implemented.
seal table are inadequately Condition corrected.
embedded - DER 80                                                          (7/3/80 - 10/22/80)                ..
4-                                    ,
1980                Construction    ' Defic'encies on Whiting                NCRs issued, procedures polar crane and improper              revised, training processing of Bechtel                  conducted.
documents.
(10/16/80 - 11/3/80) 1980                Construction      Concrete placement deficien- Condition acceptable based cies - SI tank. DER 80-24 on engineering analysis.
(10/17/80 - 2/2/81) 1980                M. M. Sundt/      Concrete truck mix not                NCRs issued and preventive
:                                        Tanner Co. properly monitored                    action implemented.
enroute.
(11/13/80 - 11/14/80) 1981                Reliance Truck QA program deficiencies                  Audit findings resolven.
Company      found during audit by                  Supplier QA Manager Bechtel                                replaced.
(2/17/81 - 8/11/81) 1981                Construction-    Ultrasonic by Peabody not              NCR issued. WPP/QCI 12.0 witnessed by Bechtel Level            revised to clarify require-II or III                              ment..
(2/25/81 - 3/10/81) 1981                Construction    . Construction Startup testing NCRs issued, procedures accomplished without                  issued.
formal procedural control.
(5/13/81 - 5/21/81) 1981                Construction      Bolts failed due to                    NCRs issued. Bolt testing incorrect hardness.                    program accomplished.
DER 81-14                              Refer to DER 81-14.
(6/15/81 - 7/6/81) 1981                Otis Elevator -  Welding program not                    Welding of brackets approved by Bechtel,                  affected. Bechtel walkdown (10/8/81 - 11/16/81)                  ' determined welds accept-able. Supplier will use Bechtel controlled filler material.
 
Year    Oraanizetion.          Reason / Period          Corrective Actions 1981' Marathon        : Supplier lack of control    Procedures developed and Steel        for subcontracted NDE -      implemented.
field erected tanks.
                                    . Initiated 12/10/81 -
Closed 7/21/83 upon
                            '',      completion of reverifica-tion activity.
1982. CoEsip        Supplier weld deficiencies  SDDR 3236 issued - Consip on main control panels -    weld procedure revised.
at supplier's facility.
                                    .(4/12/82.- 5/27/82) -
            '1982    construction  Grouting procedure to        condition corrected to accomplish DER 81-35        meet QA program require-disposition not approved    ments.
or controlled.
(8/17/82 - 8/20/82) 1983    Construction  Engineering procedure        Approved QC procedure for repair of crack in      issued.
spray pond does not address QC participation.
(5/17/83 - 5/20/83) 1983    Construction  Site process sheets for      Review cycle modified, installation of Unit 3      QA review accomplished.
reactor vessel internals not submitted for QA approval.
1983    Construction  QA overview of pipe support Reinspections conducted.          !
reinspection program        QA reverification program identified unacceptable    implemented to require-weld conditions not found    monthly overview of weld by QC. DER 83-74            activities.
(12/2/83 - 12/12/83) 1984    Engineering  ' Validation program of HVAC Documents were issued which duct supports by Engineering meet QA program require-and supplier does not meet ments.
QA program requirements.
(3/2/84 - 3/8/84) 1984    Construction    Items removed during        Condition corrected, authorized replacement      Procedures revised to activities were not properly clarify requirements.
identified and controlled.
(5/3/84 - 6/8/84)
I Year Organization          Reason / Period            Corrective Actions 1984 Columbia        Materials received at      Condition corrected. Items Specialty Co. jobsite were not processed met the requirements for under the Columbia Specialty their intended use.
QA program.
(11/16/84 - 12/31/84) 1985 Brand Indust. Seismic gap hardware did    Commitments establish a Services Inc. not conform to the require- program to identify and ments and procedures did    correct deficiencies.
not provide adequate acceptable criteria.
(8/30/85 - 10/22/85)
                                                            .+
                                  \ 7"
: c. Construction Deficiency Evaluation Reports (DER's) 10 CFR 50.55(e)
              't~            DER No.'                Description          Corrective Measures          Status 78-1        Fabrication of Anchor      Documentation reviewed    Closed 04/11/78 Bolts for Major NSSS      and corrected            Not reportable components 78-2        Void in concrete place-    Void repaired            closed 05/19/78 ment                                                Not reportable 78-3        Stainless Steel pipe      All pipe and pipe spools Final report spools                    from Youngstown Welding  11/17/78 and Engineering Company  Reportable have been rejected, quar-antined, and the company removed from the AVL by Pullman Power Products 78-4        Defective fillet welds    Drawing corrected        Closed 05/19/78 due to drafting error                                Not reportable on DWG's l
l I
 
5 1
DER No.'              i Description            Corrective Measures              Status 79-1      , Voided 79-2        weld: sequence of Unit      . Weld sequence verified      Final report
                    ,    #1 sad Unit #2. polar .      correct                      06/04/79
                        . cran support girders ;                                    Not reportable 79-3.      Nath errori in.calcula-      Calculation corrected        Closed 06/01/79 i  ,
tions x                  ,
Not reportable 79-4        Imagitudinal weld de-        NDE showed no defects        ' Closed facts in S/S pipe                                          Not reportable 79      Polar crane girder:          Procedures prepared and      Closed 06/01/79 welds                        Implemented                  Not reportable 79-6?      2" defective socket          Coating removed prior to closed 05/19/79
                        . weld valves                  welding                      Not reportable 79-7    . . Polar crane bracket          NDE showed satisfactory      Closed 11/30/79 welds                        results                      Not reportable 79-6        Cracked Auxiliary            Switches replaced; 100%      Closed 08/28/79 switches,                    reinspection conducted      Not reportable 79-9        Pipe spool heat treat-        All material tested          Closed 05/19/79 ment                          satisfactorily              Not reportable 79-10      Safety-related pipe sup- A complete re-inspection Final report port assemblies'in Unit      program has been initi- 03/06/80 ated with deficiencies
                                                                  ~
                        .#1                                                        Reportable being documented, training sessions updated, fillet weld gauges supplied, and increased surveillance 79-12.      Inadequate concrete          Specifications and pro- Final report strength achieved with        cedures revised, all ac- 12/30/80 pneumatically placed          cessible areas chipped      Reportable motor. repairs -              and ' reworked, and all in-accessible areas evaluated
                                      ~
and dispositioned accept-as-is in NCR C-R2040 based on Design Criteria.
u
 
s-DER No.            Description          Corrective Measures          Status 79-13      Pump suction pipe con-  A review of the various  Final report
[-                  figuration on the high pressure safety injec .
piping arrangements has  12/03/80
                                            -shown them to be accept- Not reportable tion pumps (HPSI)        able under all existing
                                            -guidelines and no further action is required n-N
      +
DER No..                  Description-          ' Corrective Measures        Status
      '80-1            Inadequate design of    Calculations-peEformed;    closed 06/27/80 Seismic'I instrument    verified satisfactory      Not reportable supports 2          .An error in~ calculations Calculatio's  e re-        Closed 06/27/80 for tubing support      performed                  Not reportable
      '80-3          -Relating to undersized'  Accepted without repair. Final report
                      -structural steel fillet                              12/24/80
                      ' welds                                                Not reportable 80-4            Class 1E, 600V, Power    Procedures revised; ap-    Final report cable                    plicable cable repaired    11/05/80 Not reportable 80-5            Class 3, piping system  All welds NDL'd. satis-    Final report -
welds                    factory                    07/09/80 Not reportable 80-6            Safety-related sway      Stop work order notice      Final report struts-                  80-SW-3 closed and          07/10/81 NCR P-A-125                Not reportable revised to use-as-is.
      '80-7            Steam Generator piping    Forms revised to slow      Final report welds                    interpass tesperature      07/03/80 Not reportable 80          Hilti drop-in anchors    FCR written to delete      Final report type type of anchor        07/03/80 bbt ' re portable 80-9            Operability failure of  A11' installed and no in- Final report vertical fire dampers    stalled fire dampers        09/15/80 found that did not meet Reportable the required tolerances were replaced. A re-design has been incorporated to elevate future problems.
80-10          Namco Controls Series    Anchor / Darling to provide Final report EA180 limit switches    replacement gaskets for 07/03/80 the subject valve limit    Reportable switches.
80-11          Defective pressure switch MDA Scientific to pro-    Final report in the chlorine          vide alternate pressure    07/03/80 detectors                switches after approval / Reportable qualification.
 
DER No.          Description          ' Corrective Measures          Status 80-12  _ Pipe spools with the
                  ~
Paper work corrected      Final report same I.D. number                                    07/03/80        '
Not reportable 80  Dowel omission during    Add dowels prior to con    Final repcrt concrete placement        crete placement which      07/08/80 the into the slab.        Reportable 80-14  Pipe strap, pipe ear      All installations veri-- Final repot full length welding      fied correct              07/10/80 Not reportable 80-15  Closure of COMSIP,        COMSIP to: furnish modi-  _ Final report Incorporated contain-    fication kit details and 07/09/80 ment gas analysis system instructions. Units to pump valve                be modified with proper field change procedures.
80  Inadequate embedment of  A design change will be    Final report anchor bolts for Units    implemented so that the 07/21/0
            #1 and #2 seal tables    seal table is adequately. Reportable anchored in the rein-forced concrete and meets all seismic Category 1 requirements.
80-17  Inadequate design of re- The' design for all three Final report inforcing steel in the    (3) units has been        07/21/80 walls of the Main Steam  changed to add the- re-    Reportable Support Structure for    quired amout of steel Unit #1                  to meet established
  ,                                    Design Criteria.
80-18  Blocked tendon sheaths    Blockages removed and      Final Report in Unit #1 and #2        reinspected                07/21/80 containment                                          Not reportable 80  Reinforcing steel shown  Analysis performed; all    Final report in the drawings may not  stresses are within        11/06/80 be accurately reflected  allowable limits            Not reportable in the actual desan in certain areas 80-20  Three (3) shipping studs Studs not neded; use-        Final report jammed in reactor vessel as-is                        07/30/80 Not reportable y            - -
j s
d.
1
                    ' DER'No.                              Description                            Corrective Measures                        Status 80-21                . Borg-Warner valves with                  Valves have been I.D.'ed Final report
* stem extensions could                    and NCR'ed. Borg-Warner 07/29/80 loosen after a few                      will supply parts and in- Reportable cycles                                    structions for rework 22                - Dowel omission from con- Item was NCR'ed.. Dis-                          .
Final report crete wall pour of Unit                  position was to drill                          09/24/80
                                                #2 Control Building                      and grout the required                          Reportable dowels into wall 80-23                  Loose bushings on corner Bechtel verified which                                          Final report and LADA sway struts                      struts were in question                        03/02/81 through Corner & LADA.                        Not reportable Bechtel will rework all identified struts using a C&L inspection and repair procedure 60-24                  Excessive shear stresses The Bechtel calculations Final report in Unit #1 & #2 con-                      are being updated to be . 03/30/81 crete slabs supporting                    consistent with the ac- Not reportable the safety injection                      tual data as submitted tanks 1B, 2A, and 2B                      by combustion engineering 25                  Improperly grouted Re-                    Voids repaired                                Final report actor Vessel Supports                                                                    10/17/80 Not reportable 80-26                  Weld deficiencies on the None required                                                  Final report main control panel                                                                      07/14/81 Not reportable
                                              - Fractured bearing cap-                    Shias added; lugs ad-                          Closed 10/20/80 80-27 sules on Unit il con-                    justed                                        Not reportable tainment polar crane wheels 80-28                  Potential failure of                      All controllers were re- Final report temperature detection                    turned to McGraw-Edison                        10/23/80 controllers used on                      for repair or replacement Reportable CTI-Nuclear Air Handling and Filtration equipment 80-29                    Potential motor shaft                    subject equipment is                          Final report breakage in Six Hydrogen being reworked per sup-                                        10/31/80
;.                                                Monitors                                  pliers recossendations                        Reportable
  - - - -        ,..w,      .-,-,,-_,.,._,en,,,._,__.,,,              ,,m,g%,,4.--,.-.-,wn.-,., , , , , , - . . , , . .  ,.ep.- %_ %.7      -,m-r.._,. ..---m,,,nw,,
 
                                                                                                                                            . -.      .. .~            . ..- . - - .
                                                                                                                                                                                      't.
4                                ,
DER No.                              Description'                                Corrective Measures                      Status                                  .
_5.                  _80-30                    ' Borg-Warner 3", 1500#,
                                                  - motor operated gate                <
Use-as-is                _
                                                                                                                                      . Final report submitted
                                                  - valve failure to close                                                              11/05/82 under operating con-                                                                Not reportable ditions i
80-31:                      . Breakers in'bettery              - Reworked in accordance                          Final report chargers supplied by                  with suppliers recom-                        11/05/80
                                                  - power conversion (EM-051) aandations
                                                          ~
Reportable 80-32                        Pipe cold' spring for--              Training session                              Closed 01/26/81                                      '
fit-up                                conducted                                    Not reportable-1 80-33                      Validity of Marathon'                  SDDR supplied and                            Closed 01/26/81 CMTR's for CF&I steel                                                                Not reportable
                      ~80-34                      Foxboro, Model 270,' dis- SCN issued to track                                        Closed 11/24/80 plays and housings re-                equipment better                              Not reportable quire repair 35                        Potential defect of                i Not used in safety-                            Closed 11/12/80 Rosemount Pressure                    related systems                                Not reportable
                                                  - transmitter on MSIV and MFIV  1 80-36;                      Isose bushings on ITT                  Bushing repaired                              Final report-Grinnel sway struts                                                                  06/19/81 Not reportable 80-37                      Concrete void in Unit                A procedure was develop- Final report
                                                    #2. Control Building Sump ed and implemented to                                      07/09/81 correct this deficiency                      Reportable                                        ,
                      .80-38                        Pipe apools pulled to                  Bechtel removed'and re- Final report
                                                  - facilitate installation              installed new pipe to de-~ 01/12/81-of pipe supports may                  sign specs and retrain                        Reportable overstress welds                '
associated personnel in erection of piping
!                      80-39                      Cable tray supports not                Dwas have been revised,                      Final report meeting dvs. requirements cable. trays inspected and 03/16/81 reworked as needed                            Reportable 80-40                      control Building race-                Drawing revised and                          closed 12/11/80
!                                                  ways and FSAR separation wiring relocated as                                        Not reportable criteria                              necessary 1
1-                                                                                                _7-i
                  --    _,...-  ..w...-,m._%...m            m em , m , , . n.-v...    ,.-~m,7- m ,_m_,m,,,.y.,      . . y - y_m ,  ,m m m      ,,,.,%,_.,-y,..._w.y-.,...
 
F=            .
    "I            DER No.              Description ~        Corrective Measures                                  1 Status 80-41  - Class 1E conductors      Install additional sup-                Final report a                  coming within six        ports or move termina-                  01/12/81 inches of non-class      tion blocks or provide a - Reportable
                              - 1E conductors on six ITE barrier satisfying Code Gould 480 volt load        requirements for center isolation relay    division between.
cabinets                  Class IE and. Non-Class 1E wiring.
                                                                                                ' Final report
                                      ~
80-42    Texas bolt material not  Code Case N-310-1
: meeting ASME Section III accepted                                01/27/82
                                                ,                                                Not reportable 80-43    Field weld repair made    Weld verified satis-                    Closed 02/06/81 on Borg-Warner valves    factory                                let reportable 80-44    Missing screws from        None required                          Closed 01/08/81 bottom of control cab-                                            Not reportable inet instruments 80-45    Additional rebar rein-    Reworked in accordance                  Final report forcement required by    with engineering dis-                  02/04/81 drawing, not included in position (Isolated Case) Reportable containment placement
                    '80-46    ASME Section XI ultra-    Indication considered                  Final report sonic pre-service ex-    acceptable. Procedures                  04/30/81 amination revealing in-    revised accordingly.                    No t reportable dications in Pullman power elbows 80-47    Deficiency in the con-    Stiffner plates added to Final report tainment fuel trans-      reduce stresses below                  03/18/81
        ,                      fer housing tube design  allowable limits. Dwg's Reportable have been revised to in-corporate this change.
w
                                                                                , v-n~ r e-e n e- mn e,, v , e .-m    e+v~n-,w-------nn.- - - - - -
 
y_          _
q        - DER No.            Description        ' Corrective Measures-        Status 81-1      Concrete void in Unit 2  Repaired lthe void        Closed 02/09/81 Auxiliary Building                                  Not reportable          ,
81-2      Indications'in radio-    8" piping apool was        Final report.
                    . graphs of piping spools  repaired                  04/20/81:                '
Not reportable 81    .GE fuse blocks may be    None required              Closed 03/12/81 loose / misaligned                                  Not reportable
_81-4      Corner and lada sway-    NCR invalidated            DER cancelled struts                                              02/18/81 81-5      Swivel bearings on RCP    None required              Final report cannot be rotated                                    06/12/81 Not reportable 81-6      Cracked turnbuckle        Assemblies returned        Final report assemblies for Control    to manufacturer            04/15/81 Room lighting            and replaced              Reportable 81-7      Auxiliary feedwater      Mismatch corrected        Closed 05/08/84          ,
pump nozzle mismatch      during *it-up              Not reportable 81-8      Weld defects on cask      Welds repaired per NCR-    Closed 04/29/81 loading Gate / Spent ~                              Not reportable Fuel Transfer Gate 81-9      Unacceptable - radiograph Grindins mark repaired    closed 06/12/81 accepted                  and weld re-radiographed ' Not reportable 81-10    Hardened washers not      Code case shall be docu- Final report
                    .used as required by-      mented                    06/04/82 ASME Code
                                    ~
Not reportable          I 4        81-11    Broken fiber on the      Replace broken wire        Final report armature of 4.16 KV                                  10/22/81 switchgear                                          Not reportable
''                  - Mating force of 125VDC  NCR dispositioned to 81-12                                                          Final report fuse blocks              perform field modifi-      11/02/82 cation (retaining clip)    Not reportable 81-13    4.16KV switchgear.        Wiring errors corrected    Final report wiring violates                                      09/18/81 separation criteria                                  Reportable
=;.                          s              3  ,              o                                              ;
1 m-+
s
    -                                >+
                                                                                                                                                        ~7 DER No.          Description                  Corrective Measures                                  Status
                >81-14L
                          ~A-354 anchor bolt fail-        All accessible bolts                            Final report
                          .ures                          . hardness tested. All                          01/28/83 failures will be re-                          Reportable placed 81  Auxiliary feedwater              SARCN to change 10                            Final report                                  ,
pump may not deliver            second requirement to                          02/16/83 faedwater flow within            20 seconds                                    Not reportable 10 seconds                                                                                                                    ,
16  -Operated GE breakers.            Bearing assemblies were                        Final report may deform                      replaced                                      07/10/81 Reportable 81-17  Pipe supports'fabri-            Applicable drawing re-                        Final report cated without weld              vised to show fillet                          06/08/82 joint preparation                weld only or increased                        Not reportable fillet weld 81-18  MCC's contain tie                Re-tighten wire bundles                        Final report
                          -material which may un-                                                          12/30/81-ravel or loosen                                                                Not reportable 81-19  ~ Possible short circuit          Repair necessary cir-                          Final report in Foxboro recorders            cuits                                          08/03/81 Not reportable 81-20  Weld. details on pipe            Hangers reworked; draw-                        Final. report support drawing con-            ings corrected                                07/30/81 trary to ASME require-                                                          Reportable ments 81  Re-energization problem -Power supplies and cir-                                Closed 07/13/81 in ESFAS relay cabinets          cuit boards returned to                        Not reportable manufacturer 81-22  Premature time out of            Replaced as required                            Final report AGASTAT relays                  during testing; appli-                        10/21/81, cable panel inspected                          Not ~ reportable 81-23  MCC's have bent or              Revised installation                          Closed 08/21/81 broken terminal blocks          instructions issued'                          Not reportable s
81-24  Void in Unit il Control          Void repaired                                  Closed 08/19/81 Building concrete                                                              Not reportable k-w___._._--
 
=
                                                ~                - t t
4                            #
u    ' DER'Noi          Description            Corrective Measures          Status-81-25  AFW pumps could not be      Storage procedures re-    Final report rotated by hand            vised                      02/18/82 Not reportable 81-26;  Blocked tubes in. Unit    Felt plugs removed        Final report
                #1 Steam Generators                                  11/18/81 Not reportable 81-27  Esbed plate failed to      None required              Closed 08/28/81 comply with weld cri-                                Not reportable teria 81-28  Elexible conduit has      conduit replaced          Closed 09/28/81 split jackets                                        Not reportable 81-29  Failure of ASTM A490      Defective bolts replaced Final report bolts                      inspection program to      11/25/81, verify tension in high    05/11/83 strength bolts            Reportable 81-30  Indication in ASME Code    Indication removed; use- Final report pipe                      as-is                      01/08/82 Not reportable 81-31  Valve operator material    Affected valves modified Final report substitution                                          10/15/81 Reportable 81-32  HPSI bearings and  .      None                      Final report sleeves discolored                                    11/25/84 Not reportable 81-33  Sleeve bearing shifted    Use-as-is                  closed 10/06/81 in upward direction                                  Not reportable 81-34  ' Fillet welds on pipe      Use-as-is                  Closed 10/09/81 supports not thick                                    Not. reportable enough 81-35  Backfill erosion under    Temporary gas, water      Final report Unit #1 and #2 Auxiliary lines removed; abandoned 05/20/82, and Control buildings      lines groupted            04/06/83 Reportable
    ,    81-36  Incorrect size fillet      Support standards revised Closed 10/05/81 weld on pipe support                                  Not reportable
  ' DER No.-          Description        Corrective Measures          Status 81-37    Foxboro displays failed  Displays modified to      Final report environmental testing    quality environmentally  01/29/82 Not reportable 81-38  . Minimum wall thickness  Calculations ~ performed Closed 10/20/81
            -violations              to verify adequacy of    Not reportable PiPe 61-39    Gas Stripper has un-    Pipe replaced; notifica- Final report documented section of    tions to effected        02/28/83 pipe and welds.          disciplines              Not reportable 81  Missing vertical dowels  Dowels installed        Closed 11/20/81 in concrete poor in.                              Not reportable Radweste building 81-41    Possible stress in Unit  Use-as-is.                Final report
              #2 containment piping-                            12/29/82 Not reportable 81-42    Unit #2 RCP bearing      Grinding performed and    Final report housing has sand holes  holes sealed            01/29/82 Not reportable 81-43    Loose nuts and couplings NCRs dispositioned to    Final report on Units il and #2      correct deficiencies. 10/21/82, Generators              Inspection  performed    03/29/83      7 on Unit #3 Steam Generator 81-44    Pressure regulating      Regulating valves        Final report valves do not meet      replaced                  07/06/82 design requirements                                Not reportable 81-45  'rnit 1 pressurizer      Screws re-torqued and    Final report m.issing lockwires      lockwire installed        04/19/82 Not reportable 81-46    Borg-Warner valve        Valves modified as        Final report installed on horizonal  required                  12/30/81 plane                                              Reportable 81-47    Volds in Unit il MSSS    Grout patch repaired      Final report support floor slab                                10/16/82 Not reportable 4
DER No.            Description          Corrective Measures          Status 81-48' . Defective cylinder head  Head replaced prior to    Final report
            +
on Unit #2 DG              start-up                  01/05/82 Reportable 81-49. MSSS water level trans-    Flexihose re-installed    Final report mitters may give er-      to prevent erroneous      01/05/82,              ,
roneous readings          output                    Reportable
      . ~
          .81-50. Non-conservatism in de-    SARCN to reflect correct ' Closed 12/23/81.
sign basis water con-      design basis              Not. reportable sumption analysis 81-51  DG Control cabinets.      Isolation and separation Final report wiring not separated      of wiring accomplished    08/23/84 per vendor documents      Reportable 81-52  LPSI and CS pumps have    . Loose pit    tack welded'  Final report loose anti-rotation pins                              05/26/82 Not reportable 81-53  Wiring separation viola- Barriers erected to meet Final report tions in Main Control    separation requirements    05/24/84 Reportable 81-54  Indication in Unit #1      Indication removed by      Final report S/G #2 outlet nossle      grinding. NCR disposi-      03/03/82 tioned. Use-as-is.        Not reportable 81-55  Water line leak under      All temporary water, air Final report
  "-                Auxiliary Building        and gas lines removed.      09/29/84 81-56  Unit il letdown Heat Ex- The weld was repaired        Final report changers had improperly                                04/05/82 welded stiffener rings                                Not reportable 81-57  Type HMA Auxiliary Re-    NCR of spositioned rework Final report lays have excess unin-      for affected leads        07/06/82 sulated leads
 
-m          -
DER No.-          Description            Corrective Measures            Status 1  82-17    Ex-core neutron monitor    New cable purchased /re ~    Final report cables haveing greater      placed which meets at-      08/26/82 length sad attenuation      tenuation requirements      ;Not reportable than design
              ,82-2      During an internal in-    -Dispositioned " Rework"      Final report spection '(of heat ex-      and since accepted by        03/22/84
                        ' changers), 4 welds were    radiographic examination Not reportable found visually unaccept-able        >
82-3      Diesel generators lube      Replacement of defective Final report oil strainer baskets re- baskets                        03/23/82 quire replacements per  .-                              Reportable 10CFR21 by Cooper Energy Services                                                            -
82-4    ' Design specification      All installed clamps cor- Final report 1
drawings for instrument    rected to comply with the 07/23/84 tubing clamps do not        Code                        Reportable show locknuts as re-quired by ASME Code 82-5      Unit #2 reactor coolant NCR dispositioned to re- Final report pump delivered with sand move the blasting sand          06/16/82
                        .in cooler chamber housing                              r  Not reportable 82-6      Unit #3 valves (11..        Qualification documenta- Final report total) shipped,and're-      tion processed. NCR is- 02/18/82 moved from receiving'      sued against the Unit #3 Not reportable area without qualifica-    equipment as required tion documentation 82-7. Five Star Special "150"    WPP/QC1 revised to review Final report grout used in contain-      manufacturer's final cer- 04/07/82 ment construction ob-      tification. Remove Five Not reportable served stratification      Star Special "150" grout from approved list 82-8      G.E. switchgear has        NCRs dispositioned to        Final report parts not certified by      replace the identified      10/25/82 subsuppliers for nuclear components correcting all Not reportable use                        equipment deliveries to g                                            the jobsite c
L
 
s a, ,                          <s                                                  ,
v-          , ,
DER No.            Description-        Corrective Measures-        Status 82-9;      Thernowells in diesel    NCRs dispositioned to    Final report
                              . generator lube oil sys-  replace thernowells      '11/04/82 tems by Cooper' Energy.                            Not reportable were not procured to
                            , Code 82-10    ' code material I.D. nos. Addenda incorporated as  Final report obliterated on 8 pipe '  applicable                04/27/82 supports in Unit #2                                Not reportable containment and MSSS due
:to galvanizing 82-11      Six nozzles in the re-    NCR dispositioned to al- Final report actor bottom head had    low tube installation    03/15/82 porosity in the weld      work to proceed          Not reportable 7                              sone, deep surface de--
facts, and nicked welding surfaces
;                    82-12    ; Instrument clamps in-    NCR dispositioned to      Final report    s
        -                  -/ stalled without calcula- review / rework all dis-  06/08/82
                      .        tions for thermal ex-    crepancies of installa-  Reportable pension'                  tion 82-13      Reinforcing bars omitted Horizontal rebars in-      Final report
          ,                    from Unit #3 fuel trans- stalled                    06/04/82
                              . fer tube inspection.
Not reportable station 82-14      Units #1 and #2 instru-  Fasteners replaced with  Final report ment installation bolting certified fasteners      07/07/82 procured to ASME III                                Reportable Code was used without issue control 82-15      ASME III Code pipe sup-  NCRs dispositioned to    Final report ports not traceable l to  check and verify each-    07/14/82
                              - QIB material        '
                                                      ,,  material drawn from      Reportable storage for installation 82-16      Condensate pots were      NCR dispositioned use-as- Closed 04/16/82 found to be noncon-      is                        Not reportable forming
                                              - + m ;- - - - -        . -- -        - - .  .,-                    - -
                                ~3
  ,.,z P
                                                                                                  }
                                            *                                      +
r t
              ' DER No.              ~ Description                  Corrective Measures            -
Status 82-17:    Bechte1' supplier docu-            The computerized SDR has Final report ment register errors may been corrected, preclud- 12/09/82 Not reportable allow' outdated CE pro-          - ing redundant logging cedures to be used for
: Unit' #1 : instrument calibration 82-18      Pump motors have metal-          - NCR dispositioned to-            Final report flush and replace the
                                                                        ~
                            -particles in lube oil                                                09/16/82 and deterioration of              - motor oil                        Not reportable
                            -internal epory coating 82-19~    Class IE MCC's burned              NCRs dishesitioned to              Final report out due to damage.during replace damaged com-                        09/14/82 testing                            ponents                          Not reportable
                '82-20'      20' section of 8" sched- NCR dispositioned use-                      Closed 05/05/82 ule-80 pipe,has numerous as-is for.the installed                      Not reportable areas below minimum wall section. The non-in-1                      thickness                          stalled section returned to manufacturer 82-21      Cable support atructure            NCR dispositioned to-              Closed 05/06/82 e                          had shop welds not in            . use-as-is since no rework Not reportable
        ,                    accordance with drawing            required 82-22      Knee--braced steel                NCR dispositioned use-as- Closed.06/03/82 framing of the MSSS in-            is since no rework re-            Not reportable correctly                          quired                                          ,
82-23    -Inspection revealed                Piping spool repaired.            Closed 05/14/82 numerous unauthorized-              Wall thickness verified          Not reportable 1 grinding on SI system.
24      Weld procedure not pre- ~ Dispositioned use-as-is                    Final report
                            -qualifted by Anetek-                                                  09/15/82      :
Straza for reactor hot                                                Not reportable leg pipeistops e                                      t 82-25      Q-Class pipe in auxiliary " Cracks" were actually.                    Closed 06/11/82 building has visible                shallow' surface, proving Not reportable 2"-4"' indications near            Ladequate wall thickness                                -
weld-
                  .82-26    L Mounting failures of              Broken brackets rewelded. Final report valve position in-                  Other similar switches            09/09/82 dicating switches                  inspected                        Not reportable f
ll                    .,
y.
l
          +                                ,
1
 
g..
DER No.              Description            Corrective Measures          Status 82-27      Fuel building gate        Returned to supplier for Closed 06/01/82 supports improperly        rework                      Not reportable welded
* 82-28    Jog' fan-blade locknuts    NCR dispositioned use-      Final report under-torqued              as-is                      07/23/82 Not reportable 82-29    Multiple linear in-        NCRs dispositioned use-    Final report dication on Main          as-is                      11/24/82 Feedwater lines                                        Not reportable 82-30'    Cleanliness control not    VGS inspected and          Final report maintained on Unit il      cleaned                    07/20/82 VGS :-                                                Not reportable 82-31    ' Wiring error in.the        Correct wiring error        Closed 06/24/82 Plant Monitoring System                                Not reportable
            ' 82-  Purge dan material in      Material' removed and      Closed 07/02/82 CH system                  check valve reassembled    Not reportable
            '82-33      Leakage. past 3" Anchor-. Set screw staked in        Final report Darling check valve        place                      08/20/82 Not reportable 82-34      Concrete void in Unit    - Repair the void            Final report
                          #1 MSSS                                                07/23/82 Not reportable 82-35      Unit #2 LPSI and CS        Field personnel in-        Final report pump hold down bolts        structed on verification 09/29/82 under-torqued-              of torque valves          Not reportable 36    .DG Control-Panel wiring    New lugs installed        Final-report
                        -not crimped                                            08/06/82 Reportable 82-37      Class'1E wiring in-        Procedures rewritten for Final report properly crimped.          maintenance program hy-    11/15/82, draulic crisp units. All- 07/18/82 future crimps to be done Reportable at a minimum of 7900 psi N
DER No.            Description            Corrective Measures        Sta tus 82-38    Containment isolation      Bolts retightened      Final report valves had actuator                                01/12/83 bolts loose                                        Not reportable 82-39    Valve limit switches      All switches inspected  Final report below flood level in      and found satisfactory  05/16/83 containment                                        Not reportable 82-40  _ Unit #1 circuit breakers Test procedures re-      Final report incorrectly set after      written; testing pro-  12/28/82 testing                    gram revised            Reportable
                              ~
82-41    Improperly crimped lugs    New connections in-    Final report in Unit #3 switchgear      stalled as applicable  11/23/82 Reportable 82-42    Unit #1 RCP nozzle weld    Stainless steel portion Final report leak                      of nozzel replaced by a 03/28/83 double piece of incenel Reportable 82-43    Improperly crimped lugs    All lugs inspected and  Final report in Unit #2                repaired as necessary  02/07/83 Reportable 82-44  Borg-Warner valve          Motor aperators re-    Final report operators not qualified    placed with qualified  11/15/82 for use in containment    operators              Reportable 82-46  ITT-Barton transmitters    Transmitters replaced  Final report do not meet requirements with Rosemount; SARCN to 03/15/84 change diversity re-    Reportable quirements 82-47    Minimum wall thickness    Inspect and repair the  Final report violations on 24" pipe    areas of corrosion      11/19/82 Reportable    -
48    Check valves siezed open Check valves redesigned; Final report by welding heat            all check valves flow  12/07/82 tested                  Reportable 82-49  Unit #1 and #2 S/G has    Replace beam attachments Final report pipe support incorrectly with applicable brackets 10/08/82 welded                                            Reportable
 
e
      +
        . DER No.-            Description          Corrective Measuree          -Status 82-50    Flexible conduit coup-    Conduits modified for      Final report lings may be damaged        proper support            03/09/84 during seismic event                                  Reportable 82-51    Pipe line failure in        Plasite repairs effected Final report Unit il essential          for applicable piping    '01/09/84
                    . cooling system                                        Reportable 52    Pipe' supports facor-      Inspections of nU' it il  Final report rectly installed-          pipe supports..            11/08/82 Not reportable 82-53    Joy' fan blade failure    ' Containment. lines plate  Final report in Unit il                ' repaired; fan blade re-    08/29/83 placed;.all fans rein-    Not reportable 4
spected
;-        82-54    MSIV's have internal        Valves reinspected and    Final report-corrosion                  refurbished                01/26/82 Reportable 82-55    DC motor feeder cables      Undersized cable re-      Final report may not provide suf- _      placed; cable sizing      02/23/83 ficient operating volt-    procedure revised          Reportable age 82-56    Condensate storage tank.~  Calculations performed    . Final repcrt scaled down without new    on tank; satisfactory as 07/21/83 seismic calculations        built                      Not reportable 82-57'  ' Auxiliary feedwater        Valves replaced with        Final report valves are carbon steel    stainless steel bodies    12/28/82 instead of stainless                                  Reportable steel 58    DG cubicles may not be      DCP' issued to anchor      Final' report
.                    . qualified seismically      cubicles acceptably        11/22/82 Reportable 82-59    DG crankcase sump coat-    Loose paint removed from Final report ing flaking off-          sump                        11/22/82 Not reportable 82-60      DG has non-conforming      Defective piston re-      Final report material certification      placed                    11/22/82 Reportable t
i
[. .
 
DER No..          Description          Corrective Measures          Status 82-61    RCP diffuser ring cap      Cap; screw material      Final report
    ,                  ' screws may-fail          changed; wedging device  01/25/84 added                    Not reportable 62    ESFASJDC power supply      Review conducted to      Final report ground detectors failed  assure consistency be-  08/03/83 testing                  tween test procedures    Not reportable and specifications 82-63  ' Calculation error in      Design analysis showed  Final report seismic calculation' of  acceptable as-built      06/27/83 RWT                      condition                Not reportable 82-64    Dissimilar metal socket  Welds replaced with cor- Final report welds                      rect material            11/29/82 Not reportable 82-65    Battery racks may not    Additional calculations  Closed 11/04/82 be seismically quali-    performed. Racks to be  Not reportable fled                      replaced as necessary -
82-66    Demineralized water      Water removed            Closed 11/10/82 1eaked into the reactor                            Not .re portable vessel 82-67    ESFAS power supplies do  Power supplies replaced  Final report
                      ' not meet -specifications                          12/16/82 L                                                                          Not reportable i
i 82-68    Cables to startup trans-' Use-as-is                Final report
.                      . formers may not carry                            09/16/83 full current                                      Not reportable 82-69    Incorrectly marked fuses Replaced fuses            Final report L                        in CEDM's-                                        03/08/83 Not reportable
              ~ 82-70    Improper grinding next    Use-as-is                Closed 11/18/82 to weld                                            Not reportable 82-71'    Loose bolt holding yoke  Re-torqued the bolt      Final report to valve body                                      01/26/83 No t reportable 82-72    Concrete void in Un it    Grouting program ini-    Final report
;.                      #2 containment wall      tiated to fill voids    06/30/83 Reportable m                                ,          ,  +
u r DER No.            Description          Corrective Measures          Status 82-73  Pipe support clampstin    Defective- clamps re-    Final report Unit #2 MSSS may have    placed; inspection con-  01/31/84 excess gap =              ducted to identify other Reportable deficiencies 82-74  Adjustable resistors      Modification effected to Final report have wrong size bolts    replace nuts and washers 12/23/82 Not reportable 82-75  Refueling water tank      Improper studs, clips    Final report suction strainers in-    replaced                  12/23/82 properly secured                                    Reportable 82-76  -Target rock valves do    Solenoid operators modi- Final report not-meet specification /  fied; replace target      07/11/84 test requirements        rock solenoids with      Reportable .
valcor 82-77  Foxboro displays failed  Qualified models supplied Final report Class 1E testing          for use                  12/23/82 Not reportable
  '82-78  Improperly crimped lugs  All lugs inspected; de-  Final report in water chiller control fective lugs replaced      01/17/83 panels                                              Reportable 82-79  Contro1~ air tubing      Tubing separated to acet Final report violates separation      requirements              01/17/83 criteria                                            Not reportable
  ~82-80    Low insulation valves    Terminal blocks replaced Final report' for' terminals blocks    with splices              08/31/84 Not reportable 81-  R-Class instruments      Honeywell instruments    Final report used in lieu of Q-Class  inspected for ' conform- . 04/12/83 in DG control cabinets    ance                      Reportable 82-82  . Mechanical snubbers do'  NCRs dispositioned to    Final report not-permit 5* nove-        rework the affected      01/19/83 ment without binding      snubbers                Reportable 82-83    DG butterfly valves did. Valves interchanged and  Closed 01/06/83 not comply with require- replaced                    Not reportable ments DER No.-        Description            Corrective Measures      Status 82-84  Class lE load centers in Space heaters inspected  Final report Unit #1 had internals      for correct voltage    04/19/83 damage by space heaters                          Not reportable 82-85  Harlo relay panels in    Incorrect relays re-    Final report Unit #1 failed testing    placed with qualified  03/07/83 relays                  Reportable
 
_.m.
      - DER No.          Description          Corrective Measures            Status 83-1    DG voltage regulating    Transformers repaired per Final report system may not perform    DCP                        - 02/16/83 4              .as specified                                          Reportable 83    Valve operators inter-    Affected operators were    Final report changed                  replaced                    05/03/84 Reportable 83-3    Foreign material in      Housing flushed and        Final report bearing housing of        cleaned                    02/28/84 Unit 1 HPSI pump                                      Not ' reportable 83'-4    Test proceddres for air  Procedures revised;.        Final report handling units do not    retests performed '        04/27/84 meet ANSI 510                                        No t reportable 83-5    Weld undercut on pipe    Use as is                    Final report.
in SI system                                          02/28/83 i                                                                      Not reportable 83-6    Undersize shock sup-      Shock suppressor replaced Final report presor in Un it 1                                    02/28/83-
                -Containment-                                          Reportable 83  ' Maxi-bolt anchors        Replaced affected bolts      Final report    i improperly installed                                  03/04/83
:                                                                        Not reportable 83-8    Hydrogen recombiner      _ Existing timers replaced Final report failed Qualification                                  02/28/83 test                                                  Reportable 83-9    Unit 1 LPSI pumps        Both LPSI trains flushed . Final report strainers                and cleaned                  09/06/83 Not reportable I
83-10    Main steam relief valves . Valves returned to manu- Final report l                exceed 5% blowdown        facturer for refurbish-      02/28/84 unit                      ment                        Not reportable 83-11    Exide batteries may      Stress or batteries          Final report leak or corrode at        relieved; permanent          06/14/83 terminals                repairs effected            Not reportable 83-12    480V MCC interlocks may'  Interlocks changed          Final report
                ' malfunction              out under GE supervision 05/03/83 Reportable e
v l
DER No.                  Description                        Corrective Measures                                    Status 83-13          Violation of Tagout          Training conducted on                                    Final report requirements                  tagging procedures                                      07/14/83 Not reportable 83-      ' Leaking capacitors            Defective relays replaced Final report in DG relays                                                                          09/27/83 Reportable 83-15          A 354 Anchor' bolt bone      Torque valve determin'-                                  Final report under installation torque ation methodology                                          09/23/83 changed; drawings                                      Reportable revised 83-16          DG govenor and voltage      . DCP issued to correct                                  Final report regulator do not reset -      deficiency                                              05/03/83 after trip                                                                            Reportable i
83-17          Fire protection switches All damaged switches                                        Final report failed to meet THI            replaced.                                              07/19/83
                            ' criteria                                                                              Reportable Additional hex nuts
    ~
83-18        .' Pipe supports do not                                                                Final report meet Seismic IX require- installed; drawing                                          04/28/83 ments                        revised                                                Not reportable 83-19          Shock. arrestors do not      Applicable shock                                        Final report function properly            arrestors replaced                                      01/03/84 Not reportable              '
83-20:        ~ Startup test personnel      All personnel properly                                  Final report qualification                trained and qualified                                .04/29/83 N'o t reportable c              83-21        -LPSI pump operated in          Training provided to                                  .
Final report 05/06/83
~
violation of procedures      operators Not reportable 83-22          Hydrogen recombiner          Circuit breakers                                        Final report circuit-breaker failed        replaced                                                10/24/83 '
to operate improperly                                                                Reportable 83-23          MSIV-bypass isolation          Solenoid valves replaced Closed valves failed to close                                                                05/10/83
                            -within 5 seconda                                                                        Not reportable
:83-24          DG lube' oil and jacket      Ne w heaters installed                                  Final report water heaters do not                                                              ' 05/18/83 maintain temperatures                                                              -Reportable
        , . ,    -      ,            ,  .-,,,-.v..  , -    , , , , , , ,        ,,,.,,,.,,_.-.e.,- ,,, - . . . _ . . . , , . ,      .,n  . - ,
 
DER No..          ; Description        Corrective Measures          Status 83-25  -Instrument l tubing'does  Use-as-is; revised        Final report not have boundary class  specifications issued    09/21/83 break                                              Not reportable.
          '83-26    BOP ESFAS modules failed Cabinets modified to      Final report testing due to over-      increase ventilation;    10/28/83
                    . heating.                  drawings revised          Not reportable 83    Need position indication Adjust switches as        Closed.
            ,        switches functioning      necessary; 0-ring        04/28/83 improperly                and terminal boards      Notreportable replaced 83-28    Snubbers installed in-    Use as is; Specification Final report' violation of reserve      change to clarify pro-    06/08/83 range requirements        cedure                    Not reportable 83-29    Hangers in SI system      Supports repaired; draw- Final report installed incorrectly    ings revised              06/06/83 Reportable 83-30    A354 bolt broke while    Torque procedures        Final report torquing on Unit 2 AFW    revised; drawings        01/30/84 pump.                    revised                  Not reportable 83-31    Temperature rise in DG    Ventilation modifications Final report-control cabinet could    made to provide forced-  08/23/83
                    -exceed design              ventilation              Reportable 83-32    Socket welds in Unit 1    Transition pieces instal- Final report S/G                      1ed;' drawings revised    02/29/84 Not reportable 83-33    GE breakers with EC-l'    Defects corrected per    Final report ~
trips may have defect    NCR dispositioned-        06/24/83 Reportable 83-34'  : Instrument racks in . Defective welds repaired Final report
;,                  ' Unit 2 have surface                                09/19/83 cracks                                              Not reportable 83-35    Inverters produced        High frequency snubber    Final report voltage spikes on DC-    capacitor reworked        01/09/84 supply bus                                          Reportable 83-36'    Excessive cycling of      Actuators refurbished      Final report j:                    hydramotor actuators      and retested; Training    12/21/83 program conducted          Not reportable i
{
 
DER N'.
o          Description            Corrective Measures        Status 83-37  Missed factory operations Defects repaired as        Final report on nuit 3 S/G              appropriate - -'          12/05/84 Reportable 83-38  Clip angles used _ for HVAC Use-as-is                Final report supports do not meet-                                10/06/83 requirements.                                        Not reportable 83-39  Re'jectable indications    Reworked pump case;        Final report on Unit 1 RCP inspected all other welds 01/03/84 Not reportable 83-40  -Unit 1 LPSI and CS putap  New lower end brackets    Final report motors leaking oil        installed; new design      02/02/84 housing                    Reportable 83-41  Flooding in Control        Circulating water intake Final report Building                    canal sealed; electrical 09/21/83-ducts sealed; all joints Reportable sealed 83-42'  Failed thernovells          Original thernovells      Final report.
in the RCS                replaced with new,    .
09/14/84-redesigned thernowells    Reportable 83-43  Improper crisp termina-    All relay cabinets by      Final report tions                      Harlo reinspected; dis-    09/27/84 crepancies will be        Reportable corrected 83-44  Wiring errors in PPS      Wiring corrected and      Final report cabinets                    retested                  08/15/83 Reportable .
83-45  Cable separations in        Wiring redone in accor-  Final report Unit 1 Control Room        dance with applicable    09/26/83 panels                      requirements; procedures Reportable revised 46  Value overtorqued during Adjusted electrical          Final report hydrostatic testing        leads and reed switch    01/09/84 Reportable 83-47'  Power supplies may damage Additional fuses in-        Final report instrument conductor        stalled                  10/17/83 penetrations                                          Reportable -
 
DER No.                Description          Corrective Measures          Status 48-    Solenoid. valves subjected Refurbished with high      Final report to excessive heat-        . temperature connectors,  10/28/83 lead wires and 0-rings    Not reportable Broken impeller blades /
        ~
83-49                                Diffuser redesigned;      Final report diffuser bolts              capscrew numbers          09/14/84 increased;-impe11ers      Not reportable backfiled; bearing sleeves replaced 83  Combined with DER 83-49 83-51  =AFh pump failed testing    Surveillance _ test path  Final report eliminated; SARCN to      09/25/84 change required flow      Reportable rates 83-52    Power supplies feed        Filter elements installed; Final report noise into 125 VDC bus      annunciators returned. 12/22/83 for re-work                Reportable
        ~83-53    . Unit.3 embed plates do -  Imbed plates and anchor    Final report not meet specification      bolts were evaluated and 10/15/84 reworked as necessary      Reportable 54    Washers found in Unit 1    Inose parts removed;      Final report S/G's                      remainder of system        01/17/84 inspected                  Not reportable 83  Thermal liner on cold      Line.rs removed.from'      Final report leg of RCP.lA missing      system                    12/30/84 Not reportable 83-56    Discrepancies with          Larger hydraulic reser-    Final report MSIV's                    ,voir; pump material        04/13/84 replaced; relief valve--  Reportable installed 83-57    Cracks in CEA shroud        4 and 12 finger guides    Final report
                                              -removed; snubters added    09/14/84 for lateral support      Reportable 83-63    HPSI_ isolation valves      Isolation valves were    Final report failed to open-            repaired                  10/9/84 Reportable
                ~
83-64    Pressure relief valves      Test rig replaced          Final report
                  -failed testing                                        05/24/84 Not reportable
_27 1
 
o DER N'.-          Description              Corrective Measures          Status 83-65    Safety relief valves        Valves reconditioned        Final report
          -              found dirty and rusted      and tested; cleanliness    01/23/84 requirements addressed      Reportable 83-66  -APW pump impeller wear      Wear ring material          Final report ring fractured.              changed; sent_to manu-    06/21/84 facturer for rework        Reportable 83-67    Ex-core detectors below      Detectors relocated above Final report
                        . flood level.                flood level                01/23/84 Reportable 83-68    Battery racks construc-      Non-conforming hardware      Final report ted.with materials not      . replaced -                ~02/09/84 meeting specifications .                                Reportable 83-69    Seismic supports on          Added additional shaft      Final report Posi-Seal valves'incor-      supports to' raise          07/11/84 rectly installed              frequency,' validating      Reportable seismic analysis 83-70'  Wiring in ERF Cabinets      ' Wiring rerouted; metal      Final report not in conformance with      barriers installed; color 02/28/84 specification                coding of wiring            Reportable 83-71    Shock arrestors may have Snubbers replaced as            Final report required                    04/24/84 generic defect Reportable 83-72    Undersize welds.in            Specification revised;      Final report Unit 1 Auxiliary Building Training for QC                03/14/84 inspectors                  Not reportable 83-73    Unqualified power sup-        Power supplies replaced    Final report plies installed 1E            with IE instruments        11/15/84 instrument cabinets                                      Reportable 83-74    Undersize welds in U  n it 1 Inspections conducted on Final report Auxiliary Building            all units pipe supports    09/21/84 for weld size              Not reportable 83-75    Improperly torqued            Bolts retorqued            Final report bolts on panel filler                                . 07/24/84 assemblies                                                Not reportable 83-76    Improper AFW pump logic      Logic diagram revised;      Final report modifications on exist-    05/07/84 ing logic                  Reportable l
l DER No.-          Description'          Corrective-Measures            Status 83-77    Unit 2 concrete pour      Honeycombed areas            Final report contains honeycombs      repaired                    07/13/84 Not reportable-83-78    No user tests or docu-    Samples'tated for hard-      Final report mentation for. Rock Bolt  ness, and elongation;        08/02/84 Expansion Anchor          analysis performed to        Not reportable accept as is 83-79 ~ TAC interference spikes                                  Final report on DC. bus
                                          ._  Specificatios
                                          'Micarta          revise'd; ,. 03/09/84 boards-installed Not reportable 83  MFIV close in 20 seconds; closing speed control        Final report Specification requires  . valve fully open;          38/23/84 5 seconds                  package to 3500f at          Not reportable n    70*F 83-81    Schedule 160.SS pipe      Replace the ' piping        Final report from Gulfalloy contains                                08/29/84 a manufacturing defect                                  Not reportable 82    Improper bend radius in  cables rejected and re-      Final report DG control cabinets      placed ~ to meet bend .      08/10/84 radius requirements          Reportable 83-83    Incorrect away strut      Strut replaced              Final report
              -supporting Class QlA                                    08/23/84 piping was installed                                  Reportable Missing bolts for MCC (6) Installations made to 8344                                                            Final report in Unit #1                conform to revised          05/15/84 '
drawings                    Not reportable 83-85  ' Perimeter microwave      Safeguards information      Final report detection system has a                                '01/20/84 manufacturing defect                                  Not reportable 83-86    Seismic analysis of the  Add stiffener plates to      Final report shutdown HX did not      base plate                  01/26/84 address baseplate thick-                              Reportable
                -ness adequately 83    Remote operated manual    Deficient SI valves        Final report HPSI valves                corrected                  03/13/84 Not reportable 83-88    QA lack of' procedures &  Appropriate procedures        Final report programs for testing    reviewed and revised        04/13/84 and startup E
DER No.-              Description                                Corrective Measures                                                    Status
            '84      L Methodology used to                      Procedures revised to                                                      Final report track required ratesting provide a; documented-                                                                      04/09/84 activities                                program to track re-                                                      Not reportable
                                                                  - quirements for out-standing .preoperational retest after work is performed on a previously tested structure system or component
            .84-2 Rust, scale, and pitting NCRs were dispositioned                                                                    -Final report in the clevis and arm                    use-as-is                                                                  07/13/84 of several SI and CH                                                                                                Not reportable valves 84-3        Feedwater isolation                      Inspect and rework PWIVs Final report valves; lower 4-way                      and MSIVs to remove un-                                                    05/25/84 valve found stuck during acceptable pipe sealant                                                                    Reportable testing                                  and replace with Inctite
<                                                                    No. 277 prior to fuel load 84      External security wiring Contains proprietary                                                                        Closed 01/27/84 not in conformance with                  security information per Not reportable specification                            10CFR 2.790 84-5        De)ris found in reactor                  NCR dispositioned to                                                        Closed 02/10/84-internal during move-                    clean area and return                                                      Not reportable ment of the CEA Shroud                    tools to proper storage Assembly from the UGS 84-6        Possible deficiencies                    Modules returned to                                                        Final report I'^                        in' absolute and de-~                    vendor for repair                                                        -12/12/84
,,                          viation alarm modules                                                                                                Reportable b              84-7_        Failure to provide cor-                  NCRs initiated to re-                                                      Final report rective action as                        instate rework on valves 07/13/84 stated in DER 80-21                      requiring modifications                                                    Reportable
:84-6          ITT/Barton Model 763                    Transmitters will be re- Final report Transmitters do not                      placed or refurbished                                                      07/24/84 meet specifications                                                                                                  Reportable                            ,
I 84-9        Relating to CAD welding                  Code Case Approved                                                        Final report E                            for cathodic protection                  procedues revised                                                          10/15/84
                          . ground connection                                                                                                  Not Reportable F
      -        +~~,--e , , , _ ,  -.....m..-------._,--  - _,,. -.,, .. . , - - - , . . ~ . . . - - . ~ . . - , - - _ , - - - , - , _ _ ~ -
 
f DER No.                            DescriptioE                Corrective Measures                                                      Status
                        ~
84-10                ' Abnormal number of          100% inspection revealed . Final report                                                        ,.
single element RTDs        no probles'with-the RTDs 08/01/84 open-circuited                                                                                  Not reportable 84-12'                Zone III violations ofi    'The entire Unit 1 RCS                                                Final report RCP 1A and S/G #1          returned to Class B                                                  09/10/84
,                                                                            cleanliness, and the                                                Not reportable demonstration test completed 84-13                . Relating to HVAC            Deficiencies evaluated                                                Final report and resolved per acceptance criteria'                                                                            -12/12/84 NCRs. Drawings revised                                              Reportable 84-14                  Some studs and nuts in-    DCN issued to allow the                                              Closed 03/13/84 g                                                stalled on SI & RC.sys-    use of SA-194, GR 8M                                                  Not reportable
;-                                              tems which do not meet. material in the boric                                                                            '
ASME requirements for      acid related systems, boric acid service.        as applicable
!                        84-15.                Relating to welds'          Inspection criteria                                                  Final report attaching pipe restraint clarified; design docu-                                                  11/15/84 3
supports less than de-      ments revised                                                        Not Reportable
: l.                                                sign-calculated dimen-aion in Unit-2
                          ~84-16                  ESFAS. relay cabinets      Added stiffener plates                                                Final report =
08/02/84
*~
baseplates                  to cabinets.and up-dated installation DWG's Reportable 84-17'                The core shroud envelope Measurements of core                                                    Closed 04/23/84 ghroud panels accomplish- Not reportable
                                                                              ..I as' required I                          84-18                  Wiring error on LPSI        Wiring errors on control . Final report pump  "B" CS-3 switch      switch corrected                                                      09/10/84 Not reportable 84-19                  Improperly' installed      Nonconforming flanges re- Final report blind flanges              moved and replaced to                                                07/30/84 meet Piping Material                                                  Not reportable J
Classifications 84-20                  Displacement of a con-      Use-as-is                                                              Final report necting'line in the SI                                                                            10/15/84 system                                                        ,
Not Reportable 21                  Rosemount transmitters      Hardware replaced,                                                    Final report not torqued to specified sample walkdown                                                          11/05/84
          ~
valve                        conducted                                                            Reportable I
4
 
DER No.-          Description            Corrective Measures        Status 84-22  . Unit #1 CEA shroud sup-  Contaminated area cleaned Final report port contaminated with    and checked for.cor-      08/01/84 oil                        rosion. Oil. retention    Reportable bars are being added to the Polar Cranes to con-tain oil in gear case 84-23    Auxiliary feedwater        No future reflow cire. Final report pump'"B" discharge valve testing will be done. Re- 07/12/84 to concensate storage      circ. valves V018 and    Reportable tank                      V027    will be replaced by spectacle flanges!
l    '84-24    L*.mitorque valve opera-    Bolts retorqued,'in-      Final report 3'
tors loose on valve        struction manuals revised 10/23/84 bodies                                                Reportable
      '84-25    Containment supply          Piano wires on safety-    Final report registers would not        related registers to be    11/27/84 cycle                      replaced                  Reportable 84-26    Improperly tested or      Interlocks will be        Final report adjusted interlock          manually tested unless    09/21/84 properly tested          Reportable personnel are performing
                                          .the function 84-27    Improperly handled in-    Reinspection performed    Final report strumentation from          of instruments. Training 12/12/84 Waldinger Corp.            performed. Documents      Reportable Revised 84-28    Diesel generator fuel      Use-as-is and repair      Final report lines                      for modifications        2/15/85 Not reportable i      84-29    Build up of material on    Clean, recoat with        Final report Unit #2 diesel generator plasite lining              09/25/84 HX                                                    Reportable 84-30  -Improper documentation      Review of all code-      Final report of diesel generator        related documentation    09/18/84 components                  concluded correct and    Not reportable on file, use-as-is 84-32                                Superceded by DER 84-34 1
L DER No.                  Description                                Corrective Measures                        Status 84-33        Incorrectly installed                          Weld added                                Final report hanger support assembly                                                                  09/21/84 Not reportable 84-34        ' Critical friction type'                        Connectors retightened;                  Final report high. strength con-                            drawings revised                        10/26/84 nectors                                                                                  Reportable 184-35          Setpoint potentiometers                        Potentiometers replaced                  Final report in the PPS drif t out-                                                                    09/18/84 side of tolerance                                                                        Not reportable 84-36        SI valve stalls just off Valves removed and                                              Final report closing seat when open-                        repaced                                  11/28/84
                            -ing or closing                                                                            Reportable
                                                                                              ~
84-37        Unauthorized /unq~ualified Sealant qualified for                                          Final report duct sealant                                    use; retraining conducted 11/02/84 Reportable 84-38        Laproperly welded flange Rework / repair by adding                                        Final report in Unit #2                                      filler material                        .09/18/84
                                                                                                                    ' Reportable 84-39        LPSI and containment                            Use-as-is, but do not                    Final report spray _ pumps have ex-                          run pump in -the 2500                    09/26/84 perienced abnormal                              to 3500 flow range during Not reportable rumbling noises                                shutdown cooling mode of operation
            ~84-40          Unit #2 auxiliary.                              Parts cleaned. Proper                    Final report feedwater pump has                              flushing and chemical                    12/14/84 corrosion                                      control                                  Not reportable 84-41        Adequacy of Cardinal                            Documents revised,                        Final report Industrial Products                            training audits and                      12/13/84 program for supplier                            integrated audit                          Not reportable qualification                                  performed 84-42        Unqualified torque                              None                                      Final report i                            switches installed on                                                                    10/30/84 safety related valves                                                                      o reportable N't i              84-43        HPSI 3" gate valve                              Valve stem cleaned                        Closed 07/18/84 failure to open                                and lubricated                          _ Not reportable 84-44          Fatique failures of                            Maintenance inspection                    Final report the charging pumps                            program initiated                        11/28/84 Not reportable
                                                                                    , .. _        , . _      . _ _  . ~ . _ _ _ _ _ _ _ . . . - _ _ _ .            _ .        _ . _ _ _ . _                _.    . _ _ _    _
 
DER No.          Description            Corrective Measures          Status 84-45  ' Relating to spot welding Testing to be performed; Final' report on skid mounting indica- retrofit to be completed 10/19/84 tion and control                                      Not reportable 84-46  Refueling water tank        DCPs prepared to perform Final report penetration sleeves;      required grouting work      09/24/84 connection would be                                    Reportable
          -overstressed during a seismic event 84-47  Hacksaw blade in the      Weld on line SI 130        , closed 07/24/84 Unit #3 SI system          was completed                Not reportable 84-48  Improper material for      Pipe plugs replaced with Final report
          . pipe plugs on MSIV        proper material            10/18/84 Reportable
                                            ~
84-49  Auxiliary feedwater        Mini-flow individually      Final report system experience          adjusted for 'each pump    09/26/84 hydraulic resonance          to reduce the vibration    Reportable to acceptable limits 84  Main steam isolation      -Precharge pressure /          Final report valves do not close as      temperature curve          10/25/84 required                  revised'                    Reportable 84-51  . Failure of turbine-driven Changes initiated to re- Final report auxiliary feedwater pump flect the feedwater de- 09/26/84 to quick start from        livery time change from    Reportable ambient conditions          20 to 30 seconds 84-!2    Relating to the atmos-      DCPs initiated to in-      Final report pheric dump valve; a        crease the thickness of. '09/26/84
          . review of the seismic    = the resistor base flange Not. reportable-analysis report deter-      to two inches mined that the base flange of the resistor is overstressed during an SSE and will break    ,
53    Nuts on bolts found-        NCR's evaluated, Pro-      Final report loose on PC and CH          cedures revised,            12/18/84.
valves                      training performed          Not reportable 84-54    Containment sump isola-    Reworked valves            Final report tion valve                                              12/12/84 Reportable
        ;me
(-      ,
DER No.                  Description-                            Corrective Measures              Status W          84-55        Non "Q" material in-                      Modules replaced; pro-            Final report 11/15/84 installed in Q1E fustru- cedures revised
: mentation cabinets                                                          Reportable 84-56        Fire dampers were ' found                  Damper Reworked                  Final Report to close inconsistently                                                      12/08/84 I.
                                                                ,                                        Reportable 84-57        Evaluation relating to                  .SARCN to change time              Closed 09/19/84 radioactive waste drain- from 10 seconds to'                                Not reportable-system                                    40 seconds
        -    184-58        Auxiliary feedwater sys- Valves cleaned and/or                              Final report tem solenoid' valve failed replaced                                        11/12/84 to open in-response.to                                                      Not reportable AFAS signal 84-59        MCC cables damaged by                      cables replaced; edge            Final report fire stops                                protectors installed              10/09/84 ~
Reportable 4
84-60        Improper lubricant used- Valves flushed and                                Final report in.Limitorque valve                      re-lubricated                    11/12/84 operators                                                                  Reportable 61        Auxiliary pressurizer                    Redundant valve in-              Final report
      ~
spray system-loop valve-                  atalled-                        10/17/84 potential to stop open                                                      Not reportable
                                                                                                        ~
84-62        Load sequencer did not                    Rework Control                  Final report function properly during Circuits                                          12/08/84 safeguards - tes ting                                                      Not reportable 84-63        SIT vent valve would                      Valves cleaned and/or            Final report not close during testing' replaced'                                        11/12/84 Not reportable
              '84-64        Snubbers will not cycle                    Rework snubbers, monitor- Final report ing program                      12/12/84 Reportable r
Inst. leads removed from Leads in the CSB                                  Final report 65
-                            UGS have shown splitting removed                                            11/12/84 of outer sheath                                                            Not reportable 84-66        Downconer feedwater iso- Actuators redesigned;                              Final report f                                                                        closure time revised            10/03/84 lation valves Reportable 84-67          Steam generator system                    Valves cleaned and/or            Final report i                              valve solenoid operations replaced                                          11/12/84 at low voltage                                                              Not reportable l-
?
m -. . . _ . . _ . . _ _ _ _      __ _ ..-. . _ -. _ - .,.. _ . _ _ ~ , _ . _ _ . ,..                  ,
 
L
                                                                  +
DER No.          Description            Corrective Measures              Status
        -8'4-68  ESC  "A" would not re-        New temperature switches Final report sequence due to temp.        installed                    11/15/84-switch trip after LOP                                      Reportable 84-69  Reactor protection system Barrier material removed Final report shunt trip contacts          and relays retested          11/09/84 Not reportable 84-70  Diesel engine  "A" in Unit': Lubricate control            closed 09/28/84
                  #1 tripped.off because        mechanism                  'Not reportable-of engine overspeed 84-71'  A spurious load shed of      None required                Closed 09/17/84 the 4160 V SWGR SO4                                        Not reportable Feeder Breaker 84-72  During pre-op test SI        Rework operators            Final report valve torqued out near                                    12/12/84 the closed seat                                          Reportable 84-73  . Test cards for excore        Test cards replaced,        Final report system have an incorrect rework discriminator              11/05/84 value for "R26"              cards                        Reportable Inspection and repair
    ~
84-74  Inverters failed pre-op                                    Final report testing                      as necessary, Procedure      12/14/84 revision                    Not reportable 84-75. DG essential exhaust fan Start signal time                Closed fails to start within 5: changed                          09/27/84 seconds in' Mode 1 or 4                                    Not reportable operation 84-76    Stator temperatures          HVAC modified                Final report
;-                could be exceeded                                        12/12/84 Not reportable 84-77  Rosemount transmitters        Transmitters replaced        Final report manufactured after            or refurbished              11/02/84 January 10, 1984 may not                                  Reportable
: j.                have hermetic seal 84-78  .Valcor valves experience Dropping register in-            Final report coil failures                stalled to reduce  voltage 11/16/84
'                                                                            Reportable 84-79    Broken terminal lug on      Damaged lug replaced        Closed DG could cause abnormal                                  10/04/84 temp. rise                                                Not reportable u
x
    . DER No.-          Description          Corrective Measures          Status c    J84-80    -DG."A"_ tripped off on    Hydraulic govenor ad-    Closed overspeed'when load was-justed                  10/03/84 removed                                            Not reportable 84-81    65%-90% hesitation of. Operators reworked      Final report the'odpen position when                            12/12/84 3 of 4 valves are in                              Reportable closed position 84-82    Improper mate between    Use-as-is                Final report seat and disc of SI                                11/09/84 check valve                                        Not reportable 84-83    HPSIL"A" injection lines Orifices installed        Final report experiencing cavitation  downstream              11/28/84 Not reportable 84-84_    Discrepancy between      ESFAS response time      Final report CESSAR Section 5.1.4 and changed                  10/26/84 CESSAR Chapter 15, deal-                          Not reportable ing with valve closure time 84-85    -Containment purge _ valve FSAR revised            Final report closing time on Contain-                          10/26/84 ment Isolation Activa-                            Not reports.ble Signal assumed in CESSAR 15-4-8 Amend 6 or later was not assumed in Palo Verde FSAR e
84-86    Pipe flanges corroded    Cleaned flanges and      Closed in DG system              bolts                    10/19/84 Not reportalle 84-87    Pre-operational test      None                    Closed procedure discrepancy                              10/24/84 on HPSI system                                    Not reportable 84-88    Grout missing on down-    Place grout              linal report comer feedwater lines                              11/30/84 Reportable-84-89    Transmitters mounted      Reworked transmitters    Final report
                -upside down                                        12/06/84 Not reportable 84-90    Rx. Vessel shin pina      Shim Pins Staked        Final Report improperly staked                                12/06/84 Not reportable
          .a..      ,,
DER No.                        Description                        Corrective Measures                                    Str.,tus '
91'            Miscellantous pipe                  . Inspection Performed                                      Final report found in U-2 RCP                                                                                12/06/84 Not reportable 84-92          : Inadequate pressure                    None                                                      Closed 4                              for fire protection                                                                            11/07/84 in the MSSS                                                                                      Not reportable -
84-93            No support rails for                  Bracing installed                                        Final report Control Roon Panel B05                                                                          12/08/84
                                                                                                                                -Reportable 84-94              overstress on CEDM                    Use-as-is                                                Closed l                              lifting lugs                                                                                    11/12/84 Not reportable 84            Spray chemical addition              Pump inspected;                                          Closed                  '
pump run for 6.5 hours :              Use-as-is'                                                11/12/84 3-                            with suction and dis-charge valve closed 84-96              Excessive closure time              -Actuators replaced                                        Final report for containment purge                                                                          12/07/84 valves                                                                                          Reportable 84-97              Sway strut bracket                    Use-as-is                                                closed                  e welded incorrectly                                                                              11/14/84 Not reportable
-            84-98              GE Relays not        .
Contacts adjusted                                        Final report properly ~ set at factory                                                                      12/14/84 Reportable 84-99              Regen Heat Exchanger                  Bracket restored                                        Final r.      :t improperly mounted                                                                              12/14/84 Reportable c'            84-100 - Compression Terminal                            Inspection and tightening Final report screws at terminal                    as necessary - specs                                    12/14/84 blocks are loose-                      revised                                                  Reportable 84-101            Containment Purge Valve                Inspection and rework                                    Final report failed to open                        as necessary                                            12/14/84 Reportable'
,            84-102            Improperly secured A/D                Inspection and rework                                    Final report
:-                              check valve                            as necessary                                            10/14/84 Reportable i.
:                                                                                                          l s
DER No.            Description              Corrective Measures                  Sta tus -
84-103  D/G Building Roof          Restraints installed                  Final report Hatch not locked                                                10/14/84 Reportable 84-104-- SIT Vent' valves          Seat ring modified                    Closed 12/26/84 leaking past seat                                                Not reportable 84-105  Vertical uplift not        Documents revised                    Closed 12/26/84 considered in pipe                                              Not reportable support design-84-106  Spurious load shed        Sequencer module                      Final report on B0P EFAS                replaced                              02/27/85..
Not reportable
 
    ' DER No.        Description          Corrective Measures          Status 85-01  Aux. FW taper pin        Coupling / Pedestal      Final report stresses excessive      reworked, document        06/06/85 ravision                  Reportable i
85-02  Brown,Boveri - High      Additional testing        Final report Leakage in SCR's        incorporated              02/26/85 Not reportable 85-03  containment shell min  . Document review and      Final report GAP violated            revision as necessary    06/14/85 training                Not reportable 85-04  Ruskin fire' dampers      Dampers reworked        Final report deficient                                          04/05/85 Feportable 85-05  Fire proofing on non-    Repair / rework performed Final report segregated buses          evaluation performed    06/20/85 Reportable 85-06  Diesel generator trip    None required            Closed 03/05/85 during testing                                    Not reportable 85-07  CE inetrument rack        Bolting replaced        Final report bolting deficiencies      Document review          09/09/85 Not reportable 85-08  AlW AFAS logic circuit    Calibration performed    Final report hysteresis                                        05/30/85 Not reportable 85-09  Substitution of welded    Evaluation performed    Closed 03/15/85 connections for bolted                            Not reportable connections 85-10  Leaking welds on spray    Monitoring program      closed 03/25/85 pond (MIC)                developed - reexamination N o t reportable performed chemical control incorporated 85-11  CST Transfer Pump        Documents revised        Closed 03/26/85 insufficiently sized                              Not reportable 85-12  Cracks in Aux. Building  Specification revised-  Final report brought to personnel    06/14/85 attention                Not reportable
 
I t
DER ~No.            Description          ~ Corrective Measures        Status 85-13    Stress calculations for    Calculations revised      Final report SI linss inconsistent      documents revised        ~04/09/85 Not reportable 85-14    Low pressure lube oil      Circuit reworked          Final report failure during testing                              06/14/85 of diesel generator                                ~ Reportable 85-15    Piping min wall,          None required            Final report thickness violation                                  07/15/85 Not reportable 85-16    -AHU Spoke Cracked          Replaced AHU hubs        Final report New hubs for all units    08/13/85 reportable 85-17    Essential AHU Seismic      Seismic report amended    Closed 05/07/85 i~
                    . analysis                  review / revised documents Not reportable-85-18    Brown Boveri K-Line        Procedure revision for    Closed 05/15/85 Circuit breakers          inspection during        Not reportable deficient                  maintenance 4
85-19    ' Iodine removal system    SCAP's reworked          Final report excess flow rate                                    07/25/85 Not reportable 85-20  Cracked rocker arm        Rocker are replaced      Final report on diesel generator-      maintenance program      09/30/85 incorporated              Reportable 85-21  Anchor Darling air check None required              Closed 05/31/85 valve failure to seat                                Not reportable i                      properly 85-22  Control relay visual      Relays inspected / cleaned Final report indicat. ors breaking off as necessary - procedure 07/05/85 into relay                revised                    Reportable 85-23    Diesel generator start    Replace valves            Final report failure due to Mechanical                          09/09/85 l                    valve failure                                        Not reportable 85-24  ' Fractured bolting on      Bolting replaced -        Final report i                  _' diesel turbocharger      Torque increased          C9/13/85 Reportable e
1 t
h
                . DER No.                          Description                                      Corrective Measures                                                - Status 85-25      Aux FW pump trip on                                            Control circuit modifi-                                    Final report A'AS-2 signal cold                                              cations monitoring                                        10/15/85 conditions                                                  - program through periodic Reportable testing 85-26      Inadequate design of                                            Circuit modifications                                      Final report.
containment purge system document revisions                                                                                09/11/85 1                                  ducting                                                                                                                    Not reportable
                    .85-27    - Slippage of shock                                                Torque increased -                                          Final report suppression pipe clamps                                        documents revised                                          09/18/85 s                    Reportable
                    .85-28        CE instrument rack                                              Under evaluation                                            Open Conduit bend radius violations 4                                                                                                                ,
85-29      Evaluation of beam -                                            Calculation revised-                                        Closed 08/26/85 support designs                                                further instructions                                      Not reportable provided 85-30      CAD drawings do not                                            Drawings revised -                                          Closed 08/26/85 reflect as built                                                document revisions.                                        Not reportable condition                                                      Attention to detail emphasized 85-31      Q class pipes / pipe                                            Documents revised                                          Closed 05/28/85-supports hung on                                                drawings revised                                            Not reportable non-Q beams 85-32      Min seismic separation                                          Under evaluation                                            Open between buildings violated 85-33      ANI withdrawal of                                              None required                                            . Closed 09/25/85' acceptance of Bisco                                                                                                        Not reportable cable / pipe fire stops i
85-34      Override feature on D/G                                        Under evaluation                                            Open prevents pickup of emergency loads i
  +
s--      -
oy..            ,w.- -- %y-r-_.,  -.e.w.=,,---*+m,,,._,.n.-  -.y, - , , g%--  , ,,wwm,g,    .ey---ee. *-+e+'e -e    t==t-''----rvf+9        ~r--'F-    -e=    ww-r- t * * - ' * **
 
y ,.                        t.-  ,  s $
e t f
                                                    ~
: d. - Construction Status A11~ safety. related and important to safety systems and areas will be accepted by operations' to ensure drawings are up-to-date and system coaletion prior to fuel load. The status as of October 21, 1985, is as follows:
                                                                          ' SUBSYSTEMS TOTAL SUBSYSTEMS                  ACCEPTED      WALKED DOWN 230                          189            220 TOTAL AREAS                . ACCEPTED      WALKED DOWN 67                          41              67 CONSTRUCTION STATUS The following -safety-related and important to safety systems have . outstanding
              ' work that is required for fuel load.
              ' The remaining work is relat'ively minor in nature. It is          tracked by the site tracking aystems and will be prior to issuance of an 0.L.
AF      Auxiliary Feedwater AS      Auxiliary Steam      .-
CC      Chemical Production CD-    . Condensate
                  .CE        Stator Cooling CH      Chemical and Volume Control CL      Containment Imak Test CP      Containment Purge CT      Condensate Transfer and Storage DF      Diesel Fuel Oil and Transfer DG      Diesel Generator Systems DW-    Demineralized Water EC      Essential Chilled Water ED      Feedwater Hester Extraction Steam and Drains ES      Safety Equipment Status System EW      Essential Cooling Water FH      Fuel Handling FP      Fire Protection GH      Generator hyudrogen and'CO2 GR      Gaseous Radweste HA      HVAC - Auxiliary Building HC      HVAC - Containment-HD      HVAC - Diesel Generator Building HF      HVAC - Fuel Building HJ      HVAC - Control Building HP      Containment Hydrogen Control HR      HVAC - Radweste Building f
t'
 
                                                                            }
i IA ,  Instrument and Service' Air LR    Liquid Radwaste MA'    Main Generation MB    Excitation' and Voltage' Regulation MT    Main Turbine NA    13.8-KV Power_
NB    4.16-KV Power NC    Nuclear Cooling Water
    ;NQ      Uninterruptible AC Power.
LOW      Oily Waste and Nonradioactive Waste PB . 4.16-KV Power PC      Fuel Pool Cooling and Cleanup PE. Standby Generation PG      480-V Power, Switchgear PH    480-V Power, MCC PK    125-V DC Power PN    . Instrument AC Power QB  ~ Essential Lighting.
QC      Yard, Roadway, and Fence Lighting QD      Emergency Lighting                                          ,
QF      IS-Plant Communications QK      Fire Detection and Alarm QM      Special Process Trace Heating RC      Reactor Coolant RD      Radioactive Waste Drains RE      Nonnuclear Process Sampling RI      In-Core Reactor Instrumentation RJ      Plant Computer RK    Plant Annunciator RM      Main Control Board SA    Engineered Safety Features Actuation SB    Reactor Protection SC    Secondary Chemical Control SD    Area Radiation Monitoring SE    Ex-Core Neutron Monitoring SF    Reactor Control SG    Main Steam SI    Safety Injection and Ehutdown Cooling SM    Seismic Instrumentatin SP    Essential Spray Ponds-SQ    Radiation Monitoring
* SR    Solid Radwaste SS    Nuclear Sampling System Sanitary Drainage and Treatment
: l. ST SV    Loose Parts and Vibration Monitoring WC      Chilled Water ZA    Auxiliary Building ZC      Co'ntainment Building ZF      hiel Building
      -ZG      Diesel Generator Building ZJ. Control' Building ZM    MSSS Building ZR      Radwaste Building ZT      Turbine Buiding and Pedestal                                  1
 
      .w
: }
r
: e. -Preoperational Test Status
                  - Preoperational Testing ~ - ~~ Preoperational testing required -for ' fuel load will be completed' on :all ; safety related or important to safety systems
                  - prior to fuel load. The status as of October 21, 1985 is as follows:
TOTAL TESTS                                  TEST COMPLETE                              TEST RESULTS APPROVED 182'                                        168                                                118 ,
l The~ remaining 14 tests that are not complete are listed below.
TESTS ON HOLD PROCEDURE #~                                      DESCRIPTION                                    % COMPLETE
                          . 91PE-2CP01-                  Containment Purge System                                                      89 91PE-2HP01                  : Hydrogen Purge System                                                        89 93PE-2QD02                  Modular A.C. Emergency Lighting                                                0 TESTS IN PROGRESS 91PE-2HJ02                  Control Room Pressurization                                                  70 Test
                          -'91PE-2SR02-                  Solid Radwaste System                                                          5 92PE-2SB19                  QSPDS Preoperational Test-                                                    95 TESTS TO BE PERFORMED AFTER INITIAL FUEL LOAD (To Be Performed Per FSAR 14.2.5 Phase'I Tests)
The. Following Tests Have Not Been Performed-91PE-2LR02                  Liquid Radwaste Evaporator Test 92PE-2QF06                  In Plant Communihations (Safety Frequency Radio Frequency) 92PE-2SB20 ^                DNBR Calculator to PMS Data ' Link                                                                                    .
                          ~92PE-2SQ01-                  Radiation Monitoring Preop 4      .
4 92PE-2SQO2                  ' Post-Accident' Radiation Monitor 92PE-2SQO3                  Digital Radiation Monitoring System
                          ~92PE-2SQ04                  Safety Related Radiation Monitoring i .-                        91PE-2SS02                  Gas Analyzer Test i
r
                            ,                                                    _1_                                                                                          ,
e,,-,        s, w+s-    .c rr,  ww-r-~e-w-    w    , ,,ew---w---w,--o-w-,e-r,-----~w      ee,--en  ~~m-wv,-,--    -v-*~*g  ,--r-~ve w, e
 
The following Preoperational tests have been performed and have        some incomplete portions.
93PE-2PE01  Diesel Generator Electrical Test
      - 92PE-2SB08  CEA Position Isolation Assembly (CPIA) Channel D 92PE-2SB07  CEA Position Isolation Assembly (CPIA) Channel A 91PE-2CH04  CVCS Charging Test 91PE-2SP01  Essential Spray Pond System
      ' 91PE-2SC01  Secondary Chemistry Blowdown Flashtank 93PE-2PK01  Class IE 125 VDC Power System 93PE-2PB01  4.16kV Class IE Preoperational Procedure 91PE-2CH07  RMW, BAM, VCI Preoperational Test 91HF-2ED01  Main Steam Traps and Drain Valves HFT 91PE-2SG04  Steam Generator Isolations
      - 92PE-2SB15  Core Operating Limit Supervisory System Test 92PE-2QK01  Fire Detection and Alarm System 93PE-2PK02  125VDC Class IE Station Battery Service Test 93PE-2MA01  Main Generator 91PE-2SG03  Atmosperic Dump Valve Test 92PE-2SE04  Excore Nuclear Instrumentation Safety Channel B 92PE-2SA01  BOP Engineered Safety Features Actuation System Panel Test 92HF-2SB18  RTD Response Time Test
                                                                                                                                      )
L___                                                                                  j
 
            /                                                      f i
: f. Independent Third Party Inspections 1980 - Training Program'- RQS Corp.
i 1982 - Overall review of Chemical Control Program - Tom M. Laronge Inc.                                                            l
                      - Training Program (Follow-Up 1980 Review) - RQS Corp.
                      - Pre-INPO Audit - United Engineers
                                                        ~
                      -_Radwaste Program - Bechtel National
                      - Beergency Plan Audit'- HMM and Associates
                      - Quality Assurance Program Evaluation - Torrey Pines *
                      - Operations Evaluation - INPO 1983.- Training Audit - Seville Training System
                      - Security Audit - Newsack Inc.
                      - Personnel / Manpower needs evaluation - Sargent & Lundy 1984 - AIARA Study - Hydra Nuclear
                      - Fire Protection Audit - INPELL 1984 P
                      - NTOL Evaluation and Corporate Assistance Visit INPO 1985 - Western Regional Joint. Utility QA Audit
* Torrey Pines Technology _ conducted an extensive independent quality assurance audit at PVNGS in the area of organization,' management, quality
                                                                            ~
assurance, design and' construction ~ activities in 1982. -The QA program at p                    PVNGS was found to be effective and successful.
I f
f I
i
  ?
j_
 
F.''  - .~  -
: g. -Licensee and Contractor Audits
                                                                                                                                                ~
                                                            . Summary of Bechtel Quality Assurance Audits 1973 1974 1975 1976 1977'1978 1979 1980 1981'1982 1983 1984 1985 Total
            - QA Audit of                                                                                                                                                80  53  49 -724
            - Construction                                                          33' 111                  90        70          67            76        95 i-        .
Findings                                                          30~        65 145 121 117-                                  85        83          54  53  63 816 QA Audit of:                                                                                                                                              30  21  21 212 Subcontractors                                                                                13        21          38            34        34 Findings                                                                                  36        53          54            37.      19          11  33  36 279 QA Audit of                                                                                                                        33        31          15  24- 29 609 H.O. Engr.                              23 117          74          48          64          55        56          40 Findings                            11'    76        58          57          75          40        73          26            16          5        17  15  16 444 QA Audit of                                                                                                                        76        62          39  59  83 558
_ Vendors                                                                              7        69        62          61 Hold On Shipment                                                                        0        12        16          33            12          6          6  7  10 102 Note 1: Bechtel does not utilize observations
            ~ Note 2: -Stop work Notices issued by Bechtel are summarized in Section B Note 3: Construction Audits for 1976 and 1977 include subcontracts
                                                                                                                , ~ . _ - - _ - - _ . . . . - . . .            - - . _ _ _ _ . . _ _ _ . ~ . - . - _ _ _ . . _ - - - _ _ . . _ _ . . _ - - _ - _ _ _ _ _ _ . _ . . _ . _
 
Summary of APS Quality Assurance Audits 1974 1975 1976 1977 1978 1979 1980 1981 1982 1983 1984 1985 Total APS - Construction Audits              0    0    1    2    2  2      2-    2    2    1  3    0  17 Findings            0    0    0    9    8  1      6    0    6    0  0    0  30 Observations        0    0    5  16  10  11      5    2    0    0  6    0  55 APS - Nuclear Services (includes *)
Audits              5    2    4    4    3  4      5    5    8    8 10  11  69 Findings            23    3  11  13  12  8    12    10  10  10  12  10 134 Observations        26    1    9    23 13  17      7    7  21  16  21  13 174
(*) - Nuclear Services                          Licensing Nuclear Engineering                      Emergency Planning Nuclear Projects Records Management      Project Services Nuclear Operations Support              Esployee Relations Nuclear Fuels Management APS - Quality Assurance Audits              0    0    1  2    2  6      7    7    6    6  8    6  51 Findings            0    0    0  9    8  6    18    10  13    7 14    3  88 Observations        0    0    5  16  10  28    12    6  30  22  11 ,  4 144 APS - Operations (includes *)
Audits              0    0    0  0    0  0      0    1  13    12 35  '32  93 Findings            0    0    0  0    0  0      0    1  42    53 40    57 193 Observations        0    0    0  0    0  0      0    6  23    11 42    45 127
-(*) - Operations                              Nuclear Prcduction Administrative Services                  Plant Services Security                                Technical Support Operations Engineering                    Outage 11anagement Radiation Protection                    Mainterance APS - Startup 0  0  0      0    1  13    12 20      9  55 Audits                0    0    0 4 100 Findings            0  0    0  0    0  0      0    1  42    33 20 0    0    0  0      0    6  23    11 31    4  75 Observations        0    0 1974 1975 1976 1977 1978 1979 1980 -1981 1982 1983 1984 1985 To tal APS'- System Protection (Relay Settings)
Audits                                      0    0    0~  0    0    0    0    1    1    1    0    0    3 Findings                                    0    0    0    0    0    0    0    0    0    0  -0    0    0 Observations                                0    0    0    0    0    0    0    1-  1    0    0    0    2 Bechtel'- Construction 1 Audits                                      0~  1  16  31  29  47  26    20  23  32    3    6 234 Findings                                  'O    3    7  60'  54  43'  63    46  58  98    8    5 445 Observations                                0    0    5  11  12  23    0    17  41  38    4    4- 155 Bechtel - Downey/Norwalk Audits                                      3    2. 4    3    4    4-  5. 5    3    4    2    1  40 Findings                                  7    0    7    2  11    8    2    1    0    4    3    3  48 Observations                                5    0    2  23  16    8  10    15    1    3    5    0  88 Bechtel - Engineering
            ' Audits                                    0-  1    0    0    0    0    0    0    1    1    4    1    8 Findings                                  0    0    0    0    0    0    0    0    1    5    4    1  11 Observations                                0    3    0    0    0    0    0    0    0    7  10-  1  21 Bechtel - Quality Assurance 0    0    0    0    6    1. 3    1  13 Audits-                                    0    2    0    0 Findings                                  0_  0    0    0    0    0    0    0  14    1    8    3  26 0    0    0    0    0    0    0  11    0    6    3    20 Observations                              0 Bechtel - Startup Audits                                      0  0    0    0    0    0    0    0    1    0    0    0    1 Findings                                  0    0    0    0    0    0    0    0    7    0    0    0    7
;              Observations                              0    0    0    0    0    0    0    0    3    0    0    0'    3 Bechtel - Supplier Quality 1'
1    1    1    0    0    0    0    0    2    0    0    5 Audits                                      0 4
Findings                                    0  2    0    0    0    0    0    0    0    2    0    0 0    0    0    0    0    0    0    0    1    0    0    1 Observations                                0 l
 
{J 1974 1975 1976 1977 1978 1979 1980 1981 1982 1983 1984 1985 Total Combustion Engineering - Avery*
Audits                                          0    0  0    2  2    1  1        1          1      0  0  0        8 Findings                                        0    0  0    4 20    7    7        6          4      0  0  0      48 Observations                                    0    0  0    1  5    0  0        0          0      0  0  0        6 Combustion Engineering - Chattanooga
* Audits                                          2    0  1    1  1    1    1        0          0      0  0  0        8 Findings                                        1    0  0    0  1    6  1        0          0      0  0  0      10 Observations                                    2    0  0    2  5    4    0        0          0      0  0  0      17 Combustion Engineering - Hematite
* Audits                                          0-    0  0    0  0    0    0        0          1      -0  0  0        1 Findings                                        0    0- 0    0  0    0  0        0          0      0  0  0        0 Observations                                    0    0  0-  0  0    0    0        0          0      0  0  0        0 Combustion Engineering - Nuclear Products Manufacturing Audits                                          0    0  0    0  0    0    0        0          1      2  1  l'      5 Findings                                        0    0  0    0  0    0    0        0          3      0  7  3      13 Observations                                    0    0  0    0  0    0    0        0          0      0  4  1        5 Combustion Engineering - PVNGS Site Audits                                          0    0  0    0  0    0    0        1          0      0  1  0        2 4
Findings                                        0    'O  O    O  O  .0    0        4          0      0  3  0        7 Observations                                    0    0  0    0  0    0    0        2          0      0  3  0        5 Combustion Engineering - Windsor
          . Audits                                          1    3  2    2  2    1    1        1          0      0  1  1      15 Findings-                                        2    5  5    4 20    8    6        3'.        0      0  3  2      58 Observations                                    .1    0  5    1  5    0    0        0.          O'      O  7  2      21
* Audits conducted by Combustion Engineering 1
 
Subcontractor Audits 1974 1975 1976 1977 1978 1979 1980 1981 1982 1983 1984 1985 Total Audits              2    1    2  4    4    3    2    2  2  8      l' 0  31 Findings            3    1    2  3. 12    17    13    3-  4  29      3  0  90 Corrective Action Reports Summary "1974 1975 1976 1977 1978 1979-1980 1981 1982 1983 1984 1985 CARS                0    0    #    #    #    #    # #21 178 330 461 396 Audit' Findings          11  J    30  129 -111    98 101    77 143 205 108 125 Total              11    5    30  129 111      98 101    98 321 535 569 521*
      #lfor.1976-1981, nineteen (19) Quality Assurance Deficiency Reports (QADRs) were issued.
* Through 10/21/85 Note 1: Stop Work Notices are summarized in Section B.
l
                                  ,          ~5-
 
Attachment to g.
The Bechtel and . APS Audit programs are supplemented by a surveillance /
monitoring program to evaluate a sample of quality-related activities on a
  ' daily basis 'for compliance to specifications,      procedures,  and drawing requirements. A summary of these activities is given below.
Bechtel Conducted 1979  1980    1981    1982    1983    1984    1985    Total Number construction  1018  1170    753      692    766      794    759    5952 Subcontractor 264    216    198      141    370-    303    218    1710 APS Conducted 1982    1983    1984    1985    Total Number                                    976    2248    3048    3074    9346
_.}}

Latest revision as of 16:52, 29 December 2020

Forwards Info Re Const Status & Operational Readiness Rept,Including Project History,Const Status,Independent third-party Insps & Licensee & Contractor Audits,Per 851010 Request
ML20205G848
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 11/01/1985
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-33899, NUDOCS 8511130362
Download: ML20205G848 (66)


Text

!sc Arizona Nuclear Power Project P.O. BOX $2034 o PHOENIX, AmZoNA 85072-20M 1933 fgy ,b Of fQ ANPP-33899 November 1, 1985 q[gfggEg .

Mr. John B. Martin, Director US Nuclear Regulatory Commission Region V 1450 Maria Lane, Suite 210 Walnut Creek, CA 94596

Subject:

Palo Verde Nuclear Generating Station Unit 2 Construction Status and Operational Readiness Report Docket No. STN 50-529 File: 85-056-026

Reference:

Letter dated October 10, 1985 from D. F. Kirsch, NRC, to E. E. Van Brunt, Jr., APS

Subject:

Construction Status and Operational Readiness Report

Dear Mr. Martin:

The referenced letter requested that ANPP provide information in the subject

- areas listed in Attachment 1 of the referenced letter. Attachments to this provide the following information:

a. Project History
b. Licensee and Contractor Initiated Stop Work Actions ,
c. Construction Deficiency Evaluation Reports (DER's) d.- Construction Status
e. Preoperational Test Status
f. Independent Third Party Inspections
g. Licensee and Contractor Audits Attachments b. , c. , f. and g. are not Unit Specific t

(

A SO

Mr. John B. Martin.

Palo Verde Nuclear Generating Station Unit 2 .

Construction Status and Operational Readiness Report

.Page Two ANPP-33899

-If you have any further questions regarding this information, please call Mr. W. F. Quinn of my staff.

Very truly yours,

, /

- R /\W(

E. E. Van Brunt, Jr.

Executive Vice President Project Director EEVB/WFQ/JK0/dle Attachments cc: E. A. Licitra-

'R. Zimmerman-A. C. Gehr M. Iey

7.-

i Mr.' John;B.' Martin-Palo Verde Nuclear Generating Station Unit 2

-Construction Status and Operational Readiness Report Page Three-ANPP-33899

- bcca 'D. B. Karner' 'All w/a

'J. G. Haynes

-R. M. Butler W. E. Ide W. F. Quinn T.-F. Quan M. A. Jones LCTS Coordinator J. R. Bynum J. Orlowski ,

A. J. McCabe W. G. Bingham

.S. Shapiro .

C. Ferguson T. Bradish

.P.-Brandjes I

L a._ Project-History Palo Verde Nuclear Generating Station Unit No. 2 PIANT CHARACTERISTICS:

' Docket No.: 05000529 CP No. & Date Issued: CPPR-142/05-25-76 CP Expiration Date: 12/31/85 Applicant:- Arizona Public Service Company Plant Incation: 36 miles west of Phoenix, AZ ~

IE Region: V AE: Bechtel NSSS: Combustion Engineering Constructor: Bechtel ,

Reactor Type: PWR DER (MWE): 1304 KEY PERSONNEL:

Corporate

Contact:

E. E. Van Brunt, Jr., ANPP Executive Vice President Corporate Address: P. O. Box 53999 Phoenix, AZ_ 85072-3999 Corporate Phone No.: (602) 932-5300 NRC LPM: E. Licitra IE Resident Inspector: R. Zimmerman/G. Hernandez FUEL LOAD DATE CHANGES AS REPORTED BY UTILITY:-

Reason for Change Report Date New Schedule Reported by Utility 07-28-82 08-01-84 Impact of scheduling problems with 08-16-83 02-01-85 key equipment. Augmentation of the 03-26-84 Last Quarter plant's emergency response system of 1985 as results of TMI lessons learned.

Complexity of the transition from construction to start-up phase.

Unit 1 delays.

LOCAL PUBLIC DOCUMENT ROOM:

Phoenix Public Library 12 East McDowell Road Phoenix, AZ 85004 0323K/0016K u

-b r

% /

Status as of 10/20/85 CONS 1RUCTION STATUS REPORT

. NUCLEAR POWER PIANTS Palo Verde'2

CONSTRUCTION STATUS:

Applicant's Current Estimated Fuel Imading -Date: 11/00/85

' Applicant's' Previous-Estimated Fuel Load Date: 08/01/84

-Applicant's-Estimated Fuel Inading Date at CP Issuance:- .11/00/83 Applicant's Current Estimated Commercial Operation Date: Second Quarter of 1986 Applicant's Construction Completion Estimate as-Defined in CP: (Earliest)- 02/01/83 (Latest) 12/31/85 (CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 99%

COMMENTS EEGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COMPLETE Mobilize and Prepare site: 06/76' _ 06/77 ~100%

. Place structural

. concrete: .08/77' 12/81 100%

-Install Reactor Pressure Vessel: 06/80 07/80 100%

-Install Large Bore 05/85 100%

l Process Pipe: 09/78 Install Large Bore

' Pipe Hangers, Restraints, and Snubbers:. 10/78 05/85 100%

Install Small

Scre Pipe:. .

04/79- 11/85 -

99.6%

Install Cable Tray: 06/78 03/82 100%

-Install Exposed Mital Conduit: 01/78 10/85 99.9%

Install Power,-

Control, Instrumen-tation and Security Cable: 02/81 11/85 99.5%

Install Electrical Terminations: 05/81 11/85 99.1%

Conduct Reactor Cold Hydrostatic Test: 11/84 11/84 100%

Conduct Hot Functional

-Test: 06/85 08/85 100%

. Conduct Preop and Acceptance Test

.Necessary'for Fuel Inad: 03/83 11/85 88%

iT

s

- b., -Licensee and Contractor Initiated Stop Work Actions

' Licensee Initiated Stop Work Actions

~

'- Year Organization Reason / Period, Corrective Actions 1978' Bechtel' Radial bends did not meet -Rework tag prepared in

~ drawing - requirements. Re- compliance with WPP/QCI pairs started without NCR 54.0 As-built survey record

.or repair instructions docu- attached to NCR. NCR mented. (12/13/78-12/15/78) issued C-Y-1078 (12/14/78) 1979 -Bechtel ASME code acceptance cri- Test data and results ob-teria not met for ultra- tained for acceptance of sonic testing. (7/31/79- double welded stainless 8/21/79) steel pipe.

1981 Bechtel and Insulation being deformed Deforming of insulation CE to fit between Reactor analyzed and accepted.

Vessel and RV support col- Gaps minimized.

uans and technical justi-fication not provided for assurance of quality and in-tegrity of system not' vio-lated. (5/5/81-5/21/81) 1981 Bechtel Procedures / instructions or Procedure initiated and PCN controls not developed to ' written to WPP/QCI 28.0 control the connection and charging of batteries to assure safety of personnel and equipment. (8/31/81-9/1/81)-

~1981 Bechtel Five Star Grout 150 used and Authorization for use de-does not meet required leted from 13-CM-365.

strength. (12/14/81-4/28/82)

. 1982 AFS Operations Control of temporary elec- 90AC-0ZZ11 identified as trical jumpers, temporary- procedure for Startup to lifting of. terminal leads, use: 73AC-9ZZ05 was re-temporary ' change of set- vised to be in effect only points and use of temporary at fuel load.

modification not being per-formed in accordance with 73AC-9ZZ05 but in accordance with 90AC-0ZZ11. (4/1/82-4/2/82) 0050K/0003K 1

- Year Organization Reason / Period Corrective' Actions 1982 .Bechtel-

Tendons 1 stored without weat- All tendons discussed in-her protection.z (5/18/82- spected, rust removed and 5/21/82) -recoated. No signs of pit-

. ting or other: deficiency.

Considered acceptable and-c~

covered with plastic for-weather protection.

, Western Concrete personnel reinstructed in require-

- ments for storage of-tendons.

- 'l f j ,

i 1982- =Bechtel Stopped installation of Issue of DCP 1SN-SQ-001, 5:  ; ' sample supply lines to air Rev. 5. Existing system

,N*

radiation monitors as'sup- installed in accordance

> Lply sample lines are not with current revision of-designed to requirements of design drawing. Problem ANSI N13.1 Seat B5. resolved on QAF82-45.

(5/27/82-6/29/82) 1982 Bechtel- Material accountability not Complete inventory taken, being maintained in Zone III controlled access material area established for this and tool log updated. Re-work. (6/2/82-6/2/82) moved section pipe spool-and inspected. Area in-spected, personnel in-L structed.

~

.1982 Bechtel Procedure cancelled which BPC will re"tew WPP-QCI

' governs BPC preparation for 31.0 and write PCN; review

" area' transfer / release. Re- Fire Barriers, Cable Tray quirement for~ inspection / Covers and Conduit Sealant acceptance of cable tray and incorporate into exist-covers and barriers dele- ing procedures or add to ted. Requirement for in- WPP/QCI 31.0 spection/ acceptance of un-scheduled commodities has e been deleted as was commit-

- ment to verify installation /

inspection documentation with-in scope of area transfer.

(7/20/82-7/22/82) 1982 .APS Startup Test Director not certified Test Director will be fa-as' qualified for test MG300, miliarized with the pro-

~

FPN P02. (7/21/82-7/22/82) cedure and familiarization will be documented. QC to be present during test.

i t

i e e

._ - .. . _ . _ . . ~. _ ...-._._ _ _ . _ _ _ - - _ _ . ~ . - _ . . . - _ _ _ . ~ _ . _ . - , .

-Year Oraanization Reason / Period Corrective Actions 1982 APS'Startup Circuit breaker removed -90GA-0ZZ28 revised and without permission and no. Maintenance will assure clearance was requested nor that personnel are aware' issued. ~(8/4/82-8/4/82) of station clearance re-quirements and test con-duct requirements.

1982 .BPC Startup Failure to:- respond in a Corrective actions agreed ,

and APS timely manner to OTNs; to on by Bechtel.and APS QA.

Maintenance. implement requirements of.

'AD-112'with regard to M&TE usage-logs and forms; to re-spond to calibration overdue "

. notices; to comply with ANSI:

N45.2.16, Section 3; provide an adequate response to CAR 82-036. (9/17/82-9/18/82) 1982 -Maintenance Work Order 482 & 483 issued Procedure initiated in'ac-to set safety valves did not cordance with code and provide adequate instruc- specifications. - Special tions to perform the work instructions issued with as required by code, ASME work orders.

Section XI. (10/14/82-11/21/82) 1982- APS and Valves SGN-HV-05 and SGN-HV- Performed required actions Bechtel 06 were stroked over a two of steam generator re-Startup hour period and allowed ap- covery plan, proximately 100,000 gals.

of highly contaminated H 2O into the secondary side of SG1 and at the time SG2 was t unknown. Isolation valves for nitrogen purge thought to'be closed were open. (10/19/82-10/19/82) 1983 APS Startup Cleanliness of Iow Pressure Inspection to determine and Safety Injectica System was amount 'of damage and veri-

-Operations ~ indeterminate and continued fication of cleanliness.

operation without corrective Potential.causes for entry action could lead to signi- of foreign material into ficant damage to LPSI pumps. system investigated. On-(1/18/83-1/19/83) going inspections and evaluation of system cleanliness.

y ,,

u F

Year Orsanization Reason / Period ' Corrective' Actions 1983' JAPS Startup Startup and Maintenance Per- 90AC-0ZZO2 and 90GA-0ZZ28 Operations sonnel were not performing were revised and require a work activities in accord- review of TER's prior to

- ance with approved project rework or installation of procedures. (2/8/83-3/4/83) materials on "Q" class com-ponents to determine if an NCR should be written of if it is reportable. All' TER's written 1/17/83-2/11/83 to be reviewed.

.1983 Bechtel Typical drawings in FCR DCP issued providing ne-71577E differ signifi- cessary drawing clari-cantly from actual field fication.

conditions and bolts could be installed incorrectly.

Original field conditions will become indeterminate if bolts are installed without adequate directions.

(11/21/83-4/14/84)

,1983. .Bechtel Reportability evaluation in DCPs-were transmitted to question. If skewed T Resident Engineering for joints do not affect safety reportability review. Con-why are welds being re-- dition not reportable.

paired? (11/23/83-12/20/83) 1983 Combustion Personnel records do not Inspectors performed demon-

Engineering provide documentation of- stration of proficiency.

certification of inspectors.

1 (11/28/83-12/2/83) 1983 Innryco, Inc. Contract PV83-8215 Specifi- Program was reviewed and fication 83-95.71-06-001 did approved.

4 did not adequately in-plement the applicable technical and quality re-quirements which must be in-posed on Inryco as a result of the scope of work Inryco is to perform. (12/16/83-

-12/30/83)

^- -

Bechtel'Initia ed Stop Work Actions

^ ~

Year Orsanization . Reason / Period Corrective Actions

+

1977 ..Sh urt el ff &- E-7018 weld rod not stored Drying ovens obtained Andrews in drying ovens from Bechtel. SDDR (6/17/77 - 6/17/77) issued.

1978. Peabody Penetrant materials not Materials-tested & OK, Testing analyzed. procedures revised (1/12/78 - 1/27/78)

'1978. Construction' Unauthorized M-6 solvent SAR Change Notice 814 used-for cleaning. issued to define qualifi-

- cation parameters. WPP/QCI

~

(2/10/78 .3/16/78) 14.0 revised.

'1979 Construction Youngstown pipe material Radiograph accomplished -

is suspect - DER 79-4 no defects found.

(5/18/79 - 6/22/79) 1979 Clark Unacceptable curing construction NCRs issued.

Painting operations (11/5/79 - Supplier QA program 11/8/79) improvement initiated.

1980 Construction Rockbestos Class IE cable Supplier and Bechtel may have unqualified controls implemented.

splices. DER 80-4 Cable qualified, any (3/5/80 - 10/24/80) cable with repairs is approved for outside containment only.

1980 Construction .HPSI suction pump piping Piping arrangements were may not be acceptable to determined acceptable.

pump supplier. DER 79-13 (3/28/80 - 11/14/80) 1980 Construction ITT Grinnell pipe supports ' Acceptable - based on Code were received were under- ' Inquiry, ASME File No.

-size fillet welds. NI-77-406.

r DER 80-6 -(4/25/80 - 7/8/80)

.1980' construction Certain cable pulling Condition acceptable based stopped due to potential on engineering analysis. i

' deficiency in Containment I rebar detailing. DER 80-19 i (6/30/80'- 10/18/80) i l

l v , ,

Year ~ Organisation Reason / Period Corrective Actions 1980: . Construction' Unit 3 shell ~ concrete Condition acceptable based i

placement stopped based on engineering analysis, on 80-SW-4 and DER 80-19.

(6/30/80 - 10/17/80) 1980: Construction . Unit 2 anchor bolts for . Design change implemented.

seal table are inadequately Condition corrected.

embedded - DER 80 (7/3/80 - 10/22/80) ..

4- ,

1980 Construction ' Defic'encies on Whiting NCRs issued, procedures polar crane and improper revised, training processing of Bechtel conducted.

documents.

(10/16/80 - 11/3/80) 1980 Construction Concrete placement deficien- Condition acceptable based cies - SI tank. DER 80-24 on engineering analysis.

(10/17/80 - 2/2/81) 1980 M. M. Sundt/ Concrete truck mix not NCRs issued and preventive

Tanner Co. properly monitored action implemented.

enroute.

(11/13/80 - 11/14/80) 1981 Reliance Truck QA program deficiencies Audit findings resolven.

Company found during audit by Supplier QA Manager Bechtel replaced.

(2/17/81 - 8/11/81) 1981 Construction- Ultrasonic by Peabody not NCR issued. WPP/QCI 12.0 witnessed by Bechtel Level revised to clarify require-II or III ment..

(2/25/81 - 3/10/81) 1981 Construction . Construction Startup testing NCRs issued, procedures accomplished without issued.

formal procedural control.

(5/13/81 - 5/21/81) 1981 Construction Bolts failed due to NCRs issued. Bolt testing incorrect hardness. program accomplished.

DER 81-14 Refer to DER 81-14.

(6/15/81 - 7/6/81) 1981 Otis Elevator - Welding program not Welding of brackets approved by Bechtel, affected. Bechtel walkdown (10/8/81 - 11/16/81) ' determined welds accept-able. Supplier will use Bechtel controlled filler material.

Year Oraanizetion. Reason / Period Corrective Actions 1981' Marathon  : Supplier lack of control Procedures developed and Steel for subcontracted NDE - implemented.

field erected tanks.

. Initiated 12/10/81 -

Closed 7/21/83 upon

, completion of reverifica-tion activity.

1982. CoEsip Supplier weld deficiencies SDDR 3236 issued - Consip on main control panels - weld procedure revised.

at supplier's facility.

.(4/12/82.- 5/27/82) -

'1982 construction Grouting procedure to condition corrected to accomplish DER 81-35 meet QA program require-disposition not approved ments.

or controlled.

(8/17/82 - 8/20/82) 1983 Construction Engineering procedure Approved QC procedure for repair of crack in issued.

spray pond does not address QC participation.

(5/17/83 - 5/20/83) 1983 Construction Site process sheets for Review cycle modified, installation of Unit 3 QA review accomplished.

reactor vessel internals not submitted for QA approval.

1983 Construction QA overview of pipe support Reinspections conducted.  !

reinspection program QA reverification program identified unacceptable implemented to require-weld conditions not found monthly overview of weld by QC. DER 83-74 activities.

(12/2/83 - 12/12/83) 1984 Engineering ' Validation program of HVAC Documents were issued which duct supports by Engineering meet QA program require-and supplier does not meet ments.

QA program requirements.

(3/2/84 - 3/8/84) 1984 Construction Items removed during Condition corrected, authorized replacement Procedures revised to activities were not properly clarify requirements.

identified and controlled.

(5/3/84 - 6/8/84)

I Year Organization Reason / Period Corrective Actions 1984 Columbia Materials received at Condition corrected. Items Specialty Co. jobsite were not processed met the requirements for under the Columbia Specialty their intended use.

QA program.

(11/16/84 - 12/31/84) 1985 Brand Indust. Seismic gap hardware did Commitments establish a Services Inc. not conform to the require- program to identify and ments and procedures did correct deficiencies.

not provide adequate acceptable criteria.

(8/30/85 - 10/22/85)

.+

\ 7"

c. Construction Deficiency Evaluation Reports (DER's) 10 CFR 50.55(e)

't~ DER No.' Description Corrective Measures Status 78-1 Fabrication of Anchor Documentation reviewed Closed 04/11/78 Bolts for Major NSSS and corrected Not reportable components 78-2 Void in concrete place- Void repaired closed 05/19/78 ment Not reportable 78-3 Stainless Steel pipe All pipe and pipe spools Final report spools from Youngstown Welding 11/17/78 and Engineering Company Reportable have been rejected, quar-antined, and the company removed from the AVL by Pullman Power Products 78-4 Defective fillet welds Drawing corrected Closed 05/19/78 due to drafting error Not reportable on DWG's l

l I

5 1

DER No.' i Description Corrective Measures Status 79-1 , Voided 79-2 weld: sequence of Unit . Weld sequence verified Final report

, #1 sad Unit #2. polar . correct 06/04/79

. cran support girders ; Not reportable 79-3. Nath errori in.calcula- Calculation corrected Closed 06/01/79 i ,

tions x ,

Not reportable 79-4 Imagitudinal weld de- NDE showed no defects ' Closed facts in S/S pipe Not reportable 79 Polar crane girder: Procedures prepared and Closed 06/01/79 welds Implemented Not reportable 79-6? 2" defective socket Coating removed prior to closed 05/19/79

. weld valves welding Not reportable 79-7 . . Polar crane bracket NDE showed satisfactory Closed 11/30/79 welds results Not reportable 79-6 Cracked Auxiliary Switches replaced; 100% Closed 08/28/79 switches, reinspection conducted Not reportable 79-9 Pipe spool heat treat- All material tested Closed 05/19/79 ment satisfactorily Not reportable 79-10 Safety-related pipe sup- A complete re-inspection Final report port assemblies'in Unit program has been initi- 03/06/80 ated with deficiencies

~

.#1 Reportable being documented, training sessions updated, fillet weld gauges supplied, and increased surveillance 79-12. Inadequate concrete Specifications and pro- Final report strength achieved with cedures revised, all ac- 12/30/80 pneumatically placed cessible areas chipped Reportable motor. repairs - and ' reworked, and all in-accessible areas evaluated

~

and dispositioned accept-as-is in NCR C-R2040 based on Design Criteria.

u

s-DER No. Description Corrective Measures Status 79-13 Pump suction pipe con- A review of the various Final report

[- figuration on the high pressure safety injec .

piping arrangements has 12/03/80

-shown them to be accept- Not reportable tion pumps (HPSI) able under all existing

-guidelines and no further action is required n-N

+

DER No.. Description- ' Corrective Measures Status

'80-1 Inadequate design of Calculations-peEformed; closed 06/27/80 Seismic'I instrument verified satisfactory Not reportable supports 2 .An error in~ calculations Calculatio's e re- Closed 06/27/80 for tubing support performed Not reportable

'80-3 -Relating to undersized' Accepted without repair. Final report

-structural steel fillet 12/24/80

' welds Not reportable 80-4 Class 1E, 600V, Power Procedures revised; ap- Final report cable plicable cable repaired 11/05/80 Not reportable 80-5 Class 3, piping system All welds NDL'd. satis- Final report -

welds factory 07/09/80 Not reportable 80-6 Safety-related sway Stop work order notice Final report struts- 80-SW-3 closed and 07/10/81 NCR P-A-125 Not reportable revised to use-as-is.

'80-7 Steam Generator piping Forms revised to slow Final report welds interpass tesperature 07/03/80 Not reportable 80 Hilti drop-in anchors FCR written to delete Final report type type of anchor 07/03/80 bbt ' re portable 80-9 Operability failure of A11' installed and no in- Final report vertical fire dampers stalled fire dampers 09/15/80 found that did not meet Reportable the required tolerances were replaced. A re-design has been incorporated to elevate future problems.

80-10 Namco Controls Series Anchor / Darling to provide Final report EA180 limit switches replacement gaskets for 07/03/80 the subject valve limit Reportable switches.

80-11 Defective pressure switch MDA Scientific to pro- Final report in the chlorine vide alternate pressure 07/03/80 detectors switches after approval / Reportable qualification.

DER No. Description ' Corrective Measures Status 80-12 _ Pipe spools with the

~

Paper work corrected Final report same I.D. number 07/03/80 '

Not reportable 80 Dowel omission during Add dowels prior to con Final repcrt concrete placement crete placement which 07/08/80 the into the slab. Reportable 80-14 Pipe strap, pipe ear All installations veri-- Final repot full length welding fied correct 07/10/80 Not reportable 80-15 Closure of COMSIP, COMSIP to: furnish modi- _ Final report Incorporated contain- fication kit details and 07/09/80 ment gas analysis system instructions. Units to pump valve be modified with proper field change procedures.

80 Inadequate embedment of A design change will be Final report anchor bolts for Units implemented so that the 07/21/0

  1. 1 and #2 seal tables seal table is adequately. Reportable anchored in the rein-forced concrete and meets all seismic Category 1 requirements.

80-17 Inadequate design of re- The' design for all three Final report inforcing steel in the (3) units has been 07/21/80 walls of the Main Steam changed to add the- re- Reportable Support Structure for quired amout of steel Unit #1 to meet established

, Design Criteria.

80-18 Blocked tendon sheaths Blockages removed and Final Report in Unit #1 and #2 reinspected 07/21/80 containment Not reportable 80 Reinforcing steel shown Analysis performed; all Final report in the drawings may not stresses are within 11/06/80 be accurately reflected allowable limits Not reportable in the actual desan in certain areas 80-20 Three (3) shipping studs Studs not neded; use- Final report jammed in reactor vessel as-is 07/30/80 Not reportable y - -

j s

d.

1

' DER'No. Description Corrective Measures Status 80-21 . Borg-Warner valves with Valves have been I.D.'ed Final report

  • stem extensions could and NCR'ed. Borg-Warner 07/29/80 loosen after a few will supply parts and in- Reportable cycles structions for rework 22 - Dowel omission from con- Item was NCR'ed.. Dis- .

Final report crete wall pour of Unit position was to drill 09/24/80

  1. 2 Control Building and grout the required Reportable dowels into wall 80-23 Loose bushings on corner Bechtel verified which Final report and LADA sway struts struts were in question 03/02/81 through Corner & LADA. Not reportable Bechtel will rework all identified struts using a C&L inspection and repair procedure 60-24 Excessive shear stresses The Bechtel calculations Final report in Unit #1 & #2 con- are being updated to be . 03/30/81 crete slabs supporting consistent with the ac- Not reportable the safety injection tual data as submitted tanks 1B, 2A, and 2B by combustion engineering 25 Improperly grouted Re- Voids repaired Final report actor Vessel Supports 10/17/80 Not reportable 80-26 Weld deficiencies on the None required Final report main control panel 07/14/81 Not reportable

- Fractured bearing cap- Shias added; lugs ad- Closed 10/20/80 80-27 sules on Unit il con- justed Not reportable tainment polar crane wheels 80-28 Potential failure of All controllers were re- Final report temperature detection turned to McGraw-Edison 10/23/80 controllers used on for repair or replacement Reportable CTI-Nuclear Air Handling and Filtration equipment 80-29 Potential motor shaft subject equipment is Final report breakage in Six Hydrogen being reworked per sup- 10/31/80

. Monitors pliers recossendations Reportable

- - - - ,..w, .-,-,,-_,.,._,en,,,._,__.,,, ,,m,g%,,4.--,.-.-,wn.-,., , , , , , - . . , , . . ,.ep.- %_ %.7 -,m-r.._,. ..---m,,,nw,,

. -. .. .~ . ..- . - - .

't.

4 ,

DER No. Description' Corrective Measures Status .

_5. _80-30 ' Borg-Warner 3", 1500#,

- motor operated gate <

Use-as-is _

. Final report submitted

- valve failure to close 11/05/82 under operating con- Not reportable ditions i

80-31: . Breakers in'bettery - Reworked in accordance Final report chargers supplied by with suppliers recom- 11/05/80

- power conversion (EM-051) aandations

~

Reportable 80-32 Pipe cold' spring for-- Training session Closed 01/26/81 '

fit-up conducted Not reportable-1 80-33 Validity of Marathon' SDDR supplied and Closed 01/26/81 CMTR's for CF&I steel Not reportable

~80-34 Foxboro, Model 270,' dis- SCN issued to track Closed 11/24/80 plays and housings re- equipment better Not reportable quire repair 35 Potential defect of i Not used in safety- Closed 11/12/80 Rosemount Pressure related systems Not reportable

- transmitter on MSIV and MFIV 1 80-36; Isose bushings on ITT Bushing repaired Final report-Grinnel sway struts 06/19/81 Not reportable 80-37 Concrete void in Unit A procedure was develop- Final report

  1. 2. Control Building Sump ed and implemented to 07/09/81 correct this deficiency Reportable ,

.80-38 Pipe apools pulled to Bechtel removed'and re- Final report

- facilitate installation installed new pipe to de-~ 01/12/81-of pipe supports may sign specs and retrain Reportable overstress welds '

associated personnel in erection of piping

! 80-39 Cable tray supports not Dwas have been revised, Final report meeting dvs. requirements cable. trays inspected and 03/16/81 reworked as needed Reportable 80-40 control Building race- Drawing revised and closed 12/11/80

! ways and FSAR separation wiring relocated as Not reportable criteria necessary 1

1- _7-i

-- _,...- ..w...-,m._%...m m em , m , , . n.-v... ,.-~m,7- m ,_m_,m,,,.y., . . y - y_m , ,m m m ,,,.,%,_.,-y,..._w.y-.,...

F= .

"I DER No. Description ~ Corrective Measures 1 Status 80-41 - Class 1E conductors Install additional sup- Final report a coming within six ports or move termina- 01/12/81 inches of non-class tion blocks or provide a - Reportable

- 1E conductors on six ITE barrier satisfying Code Gould 480 volt load requirements for center isolation relay division between.

cabinets Class IE and. Non-Class 1E wiring.

' Final report

~

80-42 Texas bolt material not Code Case N-310-1

meeting ASME Section III accepted 01/27/82

, Not reportable 80-43 Field weld repair made Weld verified satis- Closed 02/06/81 on Borg-Warner valves factory let reportable 80-44 Missing screws from None required Closed 01/08/81 bottom of control cab- Not reportable inet instruments 80-45 Additional rebar rein- Reworked in accordance Final report forcement required by with engineering dis- 02/04/81 drawing, not included in position (Isolated Case) Reportable containment placement

'80-46 ASME Section XI ultra- Indication considered Final report sonic pre-service ex- acceptable. Procedures 04/30/81 amination revealing in- revised accordingly. No t reportable dications in Pullman power elbows 80-47 Deficiency in the con- Stiffner plates added to Final report tainment fuel trans- reduce stresses below 03/18/81

, fer housing tube design allowable limits. Dwg's Reportable have been revised to in-corporate this change.

w

, v-n~ r e-e n e- mn e,, v , e .-m e+v~n-,w-------nn.- - - - - -

y_ _

q - DER No. Description ' Corrective Measures- Status 81-1 Concrete void in Unit 2 Repaired lthe void Closed 02/09/81 Auxiliary Building Not reportable ,

81-2 Indications'in radio- 8" piping apool was Final report.

. graphs of piping spools repaired 04/20/81: '

Not reportable 81 .GE fuse blocks may be None required Closed 03/12/81 loose / misaligned Not reportable

_81-4 Corner and lada sway- NCR invalidated DER cancelled struts 02/18/81 81-5 Swivel bearings on RCP None required Final report cannot be rotated 06/12/81 Not reportable 81-6 Cracked turnbuckle Assemblies returned Final report assemblies for Control to manufacturer 04/15/81 Room lighting and replaced Reportable 81-7 Auxiliary feedwater Mismatch corrected Closed 05/08/84 ,

pump nozzle mismatch during *it-up Not reportable 81-8 Weld defects on cask Welds repaired per NCR- Closed 04/29/81 loading Gate / Spent ~ Not reportable Fuel Transfer Gate 81-9 Unacceptable - radiograph Grindins mark repaired closed 06/12/81 accepted and weld re-radiographed ' Not reportable 81-10 Hardened washers not Code case shall be docu- Final report

.used as required by- mented 06/04/82 ASME Code

~

Not reportable I 4 81-11 Broken fiber on the Replace broken wire Final report armature of 4.16 KV 10/22/81 switchgear Not reportable

- Mating force of 125VDC NCR dispositioned to 81-12 Final report fuse blocks perform field modifi- 11/02/82 cation (retaining clip) Not reportable 81-13 4.16KV switchgear. Wiring errors corrected Final report wiring violates 09/18/81 separation criteria Reportable

=;. s 3 , o  ;

1 m-+

s

- >+

~7 DER No. Description Corrective Measures Status

>81-14L

~A-354 anchor bolt fail- All accessible bolts Final report

.ures . hardness tested. All 01/28/83 failures will be re- Reportable placed 81 Auxiliary feedwater SARCN to change 10 Final report ,

pump may not deliver second requirement to 02/16/83 faedwater flow within 20 seconds Not reportable 10 seconds ,

16 -Operated GE breakers. Bearing assemblies were Final report may deform replaced 07/10/81 Reportable 81-17 Pipe supports'fabri- Applicable drawing re- Final report cated without weld vised to show fillet 06/08/82 joint preparation weld only or increased Not reportable fillet weld 81-18 MCC's contain tie Re-tighten wire bundles Final report

-material which may un- 12/30/81-ravel or loosen Not reportable 81-19 ~ Possible short circuit Repair necessary cir- Final report in Foxboro recorders cuits 08/03/81 Not reportable 81-20 Weld. details on pipe Hangers reworked; draw- Final. report support drawing con- ings corrected 07/30/81 trary to ASME require- Reportable ments 81 Re-energization problem -Power supplies and cir- Closed 07/13/81 in ESFAS relay cabinets cuit boards returned to Not reportable manufacturer 81-22 Premature time out of Replaced as required Final report AGASTAT relays during testing; appli- 10/21/81, cable panel inspected Not ~ reportable 81-23 MCC's have bent or Revised installation Closed 08/21/81 broken terminal blocks instructions issued' Not reportable s

81-24 Void in Unit il Control Void repaired Closed 08/19/81 Building concrete Not reportable k-w___._._--

=

~ - t t

4 #

u ' DER'Noi Description Corrective Measures Status-81-25 AFW pumps could not be Storage procedures re- Final report rotated by hand vised 02/18/82 Not reportable 81-26; Blocked tubes in. Unit Felt plugs removed Final report

  1. 1 Steam Generators 11/18/81 Not reportable 81-27 Esbed plate failed to None required Closed 08/28/81 comply with weld cri- Not reportable teria 81-28 Elexible conduit has conduit replaced Closed 09/28/81 split jackets Not reportable 81-29 Failure of ASTM A490 Defective bolts replaced Final report bolts inspection program to 11/25/81, verify tension in high 05/11/83 strength bolts Reportable 81-30 Indication in ASME Code Indication removed; use- Final report pipe as-is 01/08/82 Not reportable 81-31 Valve operator material Affected valves modified Final report substitution 10/15/81 Reportable 81-32 HPSI bearings and . None Final report sleeves discolored 11/25/84 Not reportable 81-33 Sleeve bearing shifted Use-as-is closed 10/06/81 in upward direction Not reportable 81-34 ' Fillet welds on pipe Use-as-is Closed 10/09/81 supports not thick Not. reportable enough 81-35 Backfill erosion under Temporary gas, water Final report Unit #1 and #2 Auxiliary lines removed; abandoned 05/20/82, and Control buildings lines groupted 04/06/83 Reportable

, 81-36 Incorrect size fillet Support standards revised Closed 10/05/81 weld on pipe support Not reportable

' DER No.- Description Corrective Measures Status 81-37 Foxboro displays failed Displays modified to Final report environmental testing quality environmentally 01/29/82 Not reportable 81-38 . Minimum wall thickness Calculations ~ performed Closed 10/20/81

-violations to verify adequacy of Not reportable PiPe 61-39 Gas Stripper has un- Pipe replaced; notifica- Final report documented section of tions to effected 02/28/83 pipe and welds. disciplines Not reportable 81 Missing vertical dowels Dowels installed Closed 11/20/81 in concrete poor in. Not reportable Radweste building 81-41 Possible stress in Unit Use-as-is. Final report

  1. 2 containment piping- 12/29/82 Not reportable 81-42 Unit #2 RCP bearing Grinding performed and Final report housing has sand holes holes sealed 01/29/82 Not reportable 81-43 Loose nuts and couplings NCRs dispositioned to Final report on Units il and #2 correct deficiencies. 10/21/82, Generators Inspection performed 03/29/83 7 on Unit #3 Steam Generator 81-44 Pressure regulating Regulating valves Final report valves do not meet replaced 07/06/82 design requirements Not reportable 81-45 'rnit 1 pressurizer Screws re-torqued and Final report m.issing lockwires lockwire installed 04/19/82 Not reportable 81-46 Borg-Warner valve Valves modified as Final report installed on horizonal required 12/30/81 plane Reportable 81-47 Volds in Unit il MSSS Grout patch repaired Final report support floor slab 10/16/82 Not reportable 4

DER No. Description Corrective Measures Status 81-48' . Defective cylinder head Head replaced prior to Final report

+

on Unit #2 DG start-up 01/05/82 Reportable 81-49. MSSS water level trans- Flexihose re-installed Final report mitters may give er- to prevent erroneous 01/05/82, ,

roneous readings output Reportable

. ~

.81-50. Non-conservatism in de- SARCN to reflect correct ' Closed 12/23/81.

sign basis water con- design basis Not. reportable sumption analysis 81-51 DG Control cabinets. Isolation and separation Final report wiring not separated of wiring accomplished 08/23/84 per vendor documents Reportable 81-52 LPSI and CS pumps have . Loose pit tack welded' Final report loose anti-rotation pins 05/26/82 Not reportable 81-53 Wiring separation viola- Barriers erected to meet Final report tions in Main Control separation requirements 05/24/84 Reportable 81-54 Indication in Unit #1 Indication removed by Final report S/G #2 outlet nossle grinding. NCR disposi- 03/03/82 tioned. Use-as-is. Not reportable 81-55 Water line leak under All temporary water, air Final report

"- Auxiliary Building and gas lines removed. 09/29/84 81-56 Unit il letdown Heat Ex- The weld was repaired Final report changers had improperly 04/05/82 welded stiffener rings Not reportable 81-57 Type HMA Auxiliary Re- NCR of spositioned rework Final report lays have excess unin- for affected leads 07/06/82 sulated leads

-m -

DER No.- Description Corrective Measures Status 1 82-17 Ex-core neutron monitor New cable purchased /re ~ Final report cables haveing greater placed which meets at- 08/26/82 length sad attenuation tenuation requirements ;Not reportable than design

,82-2 During an internal in- -Dispositioned " Rework" Final report spection '(of heat ex- and since accepted by 03/22/84

' changers), 4 welds were radiographic examination Not reportable found visually unaccept-able >

82-3 Diesel generators lube Replacement of defective Final report oil strainer baskets re- baskets 03/23/82 quire replacements per .- Reportable 10CFR21 by Cooper Energy Services -

82-4 ' Design specification All installed clamps cor- Final report 1

drawings for instrument rected to comply with the 07/23/84 tubing clamps do not Code Reportable show locknuts as re-quired by ASME Code 82-5 Unit #2 reactor coolant NCR dispositioned to re- Final report pump delivered with sand move the blasting sand 06/16/82

.in cooler chamber housing r Not reportable 82-6 Unit #3 valves (11.. Qualification documenta- Final report total) shipped,and're- tion processed. NCR is- 02/18/82 moved from receiving' sued against the Unit #3 Not reportable area without qualifica- equipment as required tion documentation 82-7. Five Star Special "150" WPP/QC1 revised to review Final report grout used in contain- manufacturer's final cer- 04/07/82 ment construction ob- tification. Remove Five Not reportable served stratification Star Special "150" grout from approved list 82-8 G.E. switchgear has NCRs dispositioned to Final report parts not certified by replace the identified 10/25/82 subsuppliers for nuclear components correcting all Not reportable use equipment deliveries to g the jobsite c

L

s a, , <s ,

v- , ,

DER No. Description- Corrective Measures- Status 82-9; Thernowells in diesel NCRs dispositioned to Final report

. generator lube oil sys- replace thernowells '11/04/82 tems by Cooper' Energy. Not reportable were not procured to

, Code 82-10 ' code material I.D. nos. Addenda incorporated as Final report obliterated on 8 pipe ' applicable 04/27/82 supports in Unit #2 Not reportable containment and MSSS due

to galvanizing 82-11 Six nozzles in the re- NCR dispositioned to al- Final report actor bottom head had low tube installation 03/15/82 porosity in the weld work to proceed Not reportable 7 sone, deep surface de--

facts, and nicked welding surfaces

82-12  ; Instrument clamps in- NCR dispositioned to Final report s

- -/ stalled without calcula- review / rework all dis- 06/08/82

. tions for thermal ex- crepancies of installa- Reportable pension' tion 82-13 Reinforcing bars omitted Horizontal rebars in- Final report

, from Unit #3 fuel trans- stalled 06/04/82

. fer tube inspection.

Not reportable station 82-14 Units #1 and #2 instru- Fasteners replaced with Final report ment installation bolting certified fasteners 07/07/82 procured to ASME III Reportable Code was used without issue control 82-15 ASME III Code pipe sup- NCRs dispositioned to Final report ports not traceable l to check and verify each- 07/14/82

- QIB material '

,, material drawn from Reportable storage for installation 82-16 Condensate pots were NCR dispositioned use-as- Closed 04/16/82 found to be noncon- is Not reportable forming

- + m ;- - - - - . -- - - - . .,- - -

~3

,.,z P

}

  • +

r t

' DER No. ~ Description Corrective Measures -

Status 82-17: Bechte1' supplier docu- The computerized SDR has Final report ment register errors may been corrected, preclud- 12/09/82 Not reportable allow' outdated CE pro- - ing redundant logging cedures to be used for

Unit' #1 : instrument calibration 82-18 Pump motors have metal- - NCR dispositioned to- Final report flush and replace the

~

-particles in lube oil 09/16/82 and deterioration of - motor oil Not reportable

-internal epory coating 82-19~ Class IE MCC's burned NCRs dishesitioned to Final report out due to damage.during replace damaged com- 09/14/82 testing ponents Not reportable

'82-20' 20' section of 8" sched- NCR dispositioned use- Closed 05/05/82 ule-80 pipe,has numerous as-is for.the installed Not reportable areas below minimum wall section. The non-in-1 thickness stalled section returned to manufacturer 82-21 Cable support atructure NCR dispositioned to- Closed 05/06/82 e had shop welds not in . use-as-is since no rework Not reportable

, accordance with drawing required 82-22 Knee--braced steel NCR dispositioned use-as- Closed.06/03/82 framing of the MSSS in- is since no rework re- Not reportable correctly quired ,

82-23 -Inspection revealed Piping spool repaired. Closed 05/14/82 numerous unauthorized- Wall thickness verified Not reportable 1 grinding on SI system.

24 Weld procedure not pre- ~ Dispositioned use-as-is Final report

-qualifted by Anetek- 09/15/82  :

Straza for reactor hot Not reportable leg pipeistops e t 82-25 Q-Class pipe in auxiliary " Cracks" were actually. Closed 06/11/82 building has visible shallow' surface, proving Not reportable 2"-4"' indications near Ladequate wall thickness -

weld-

.82-26 L Mounting failures of Broken brackets rewelded. Final report valve position in- Other similar switches 09/09/82 dicating switches inspected Not reportable f

ll .,

y.

l

+ ,

1

g..

DER No. Description Corrective Measures Status 82-27 Fuel building gate Returned to supplier for Closed 06/01/82 supports improperly rework Not reportable welded

  • 82-28 Jog' fan-blade locknuts NCR dispositioned use- Final report under-torqued as-is 07/23/82 Not reportable 82-29 Multiple linear in- NCRs dispositioned use- Final report dication on Main as-is 11/24/82 Feedwater lines Not reportable 82-30' Cleanliness control not VGS inspected and Final report maintained on Unit il cleaned 07/20/82 VGS :- Not reportable 82-31 ' Wiring error in.the Correct wiring error Closed 06/24/82 Plant Monitoring System Not reportable

' 82- Purge dan material in Material' removed and Closed 07/02/82 CH system check valve reassembled Not reportable

'82-33 Leakage. past 3" Anchor-. Set screw staked in Final report Darling check valve place 08/20/82 Not reportable 82-34 Concrete void in Unit - Repair the void Final report

  1. 1 MSSS 07/23/82 Not reportable 82-35 Unit #2 LPSI and CS Field personnel in- Final report pump hold down bolts structed on verification 09/29/82 under-torqued- of torque valves Not reportable 36 .DG Control-Panel wiring New lugs installed Final-report

-not crimped 08/06/82 Reportable 82-37 Class'1E wiring in- Procedures rewritten for Final report properly crimped. maintenance program hy- 11/15/82, draulic crisp units. All- 07/18/82 future crimps to be done Reportable at a minimum of 7900 psi N

DER No. Description Corrective Measures Sta tus 82-38 Containment isolation Bolts retightened Final report valves had actuator 01/12/83 bolts loose Not reportable 82-39 Valve limit switches All switches inspected Final report below flood level in and found satisfactory 05/16/83 containment Not reportable 82-40 _ Unit #1 circuit breakers Test procedures re- Final report incorrectly set after written; testing pro- 12/28/82 testing gram revised Reportable

~

82-41 Improperly crimped lugs New connections in- Final report in Unit #3 switchgear stalled as applicable 11/23/82 Reportable 82-42 Unit #1 RCP nozzle weld Stainless steel portion Final report leak of nozzel replaced by a 03/28/83 double piece of incenel Reportable 82-43 Improperly crimped lugs All lugs inspected and Final report in Unit #2 repaired as necessary 02/07/83 Reportable 82-44 Borg-Warner valve Motor aperators re- Final report operators not qualified placed with qualified 11/15/82 for use in containment operators Reportable 82-46 ITT-Barton transmitters Transmitters replaced Final report do not meet requirements with Rosemount; SARCN to 03/15/84 change diversity re- Reportable quirements 82-47 Minimum wall thickness Inspect and repair the Final report violations on 24" pipe areas of corrosion 11/19/82 Reportable -

48 Check valves siezed open Check valves redesigned; Final report by welding heat all check valves flow 12/07/82 tested Reportable 82-49 Unit #1 and #2 S/G has Replace beam attachments Final report pipe support incorrectly with applicable brackets 10/08/82 welded Reportable

e

+

. DER No.- Description Corrective Measuree -Status 82-50 Flexible conduit coup- Conduits modified for Final report lings may be damaged proper support 03/09/84 during seismic event Reportable 82-51 Pipe line failure in Plasite repairs effected Final report Unit il essential for applicable piping '01/09/84

. cooling system Reportable 52 Pipe' supports facor- Inspections of nU' it il Final report rectly installed- pipe supports.. 11/08/82 Not reportable 82-53 Joy' fan blade failure ' Containment. lines plate Final report in Unit il ' repaired; fan blade re- 08/29/83 placed;.all fans rein- Not reportable 4

spected

- 82-54 MSIV's have internal Valves reinspected and Final report-corrosion refurbished 01/26/82 Reportable 82-55 DC motor feeder cables Undersized cable re- Final report may not provide suf- _ placed; cable sizing 02/23/83 ficient operating volt- procedure revised Reportable age 82-56 Condensate storage tank.~ Calculations performed . Final repcrt scaled down without new on tank; satisfactory as 07/21/83 seismic calculations built Not reportable 82-57' ' Auxiliary feedwater Valves replaced with Final report valves are carbon steel stainless steel bodies 12/28/82 instead of stainless Reportable steel 58 DG cubicles may not be DCP' issued to anchor Final' report

. . qualified seismically cubicles acceptably 11/22/82 Reportable 82-59 DG crankcase sump coat- Loose paint removed from Final report ing flaking off- sump 11/22/82 Not reportable 82-60 DG has non-conforming Defective piston re- Final report material certification placed 11/22/82 Reportable t

i

[. .

DER No.. Description Corrective Measures Status 82-61 RCP diffuser ring cap Cap; screw material Final report

, ' screws may-fail changed; wedging device 01/25/84 added Not reportable 62 ESFASJDC power supply Review conducted to Final report ground detectors failed assure consistency be- 08/03/83 testing tween test procedures Not reportable and specifications 82-63 ' Calculation error in Design analysis showed Final report seismic calculation' of acceptable as-built 06/27/83 RWT condition Not reportable 82-64 Dissimilar metal socket Welds replaced with cor- Final report welds rect material 11/29/82 Not reportable 82-65 Battery racks may not Additional calculations Closed 11/04/82 be seismically quali- performed. Racks to be Not reportable fled replaced as necessary -

82-66 Demineralized water Water removed Closed 11/10/82 1eaked into the reactor Not .re portable vessel 82-67 ESFAS power supplies do Power supplies replaced Final report

' not meet -specifications 12/16/82 L Not reportable i

i 82-68 Cables to startup trans-' Use-as-is Final report

. . formers may not carry 09/16/83 full current Not reportable 82-69 Incorrectly marked fuses Replaced fuses Final report L in CEDM's- 03/08/83 Not reportable

~ 82-70 Improper grinding next Use-as-is Closed 11/18/82 to weld Not reportable 82-71' Loose bolt holding yoke Re-torqued the bolt Final report to valve body 01/26/83 No t reportable 82-72 Concrete void in Un it Grouting program ini- Final report

. #2 containment wall tiated to fill voids 06/30/83 Reportable m , , +

u r DER No. Description Corrective Measures Status 82-73 Pipe support clampstin Defective- clamps re- Final report Unit #2 MSSS may have placed; inspection con- 01/31/84 excess gap = ducted to identify other Reportable deficiencies 82-74 Adjustable resistors Modification effected to Final report have wrong size bolts replace nuts and washers 12/23/82 Not reportable 82-75 Refueling water tank Improper studs, clips Final report suction strainers in- replaced 12/23/82 properly secured Reportable 82-76 -Target rock valves do Solenoid operators modi- Final report not-meet specification / fied; replace target 07/11/84 test requirements rock solenoids with Reportable .

valcor 82-77 Foxboro displays failed Qualified models supplied Final report Class 1E testing for use 12/23/82 Not reportable

'82-78 Improperly crimped lugs All lugs inspected; de- Final report in water chiller control fective lugs replaced 01/17/83 panels Reportable 82-79 Contro1~ air tubing Tubing separated to acet Final report violates separation requirements 01/17/83 criteria Not reportable

~82-80 Low insulation valves Terminal blocks replaced Final report' for' terminals blocks with splices 08/31/84 Not reportable 81- R-Class instruments Honeywell instruments Final report used in lieu of Q-Class inspected for ' conform- . 04/12/83 in DG control cabinets ance Reportable 82-82 . Mechanical snubbers do' NCRs dispositioned to Final report not-permit 5* nove- rework the affected 01/19/83 ment without binding snubbers Reportable 82-83 DG butterfly valves did. Valves interchanged and Closed 01/06/83 not comply with require- replaced Not reportable ments DER No.- Description Corrective Measures Status 82-84 Class lE load centers in Space heaters inspected Final report Unit #1 had internals for correct voltage 04/19/83 damage by space heaters Not reportable 82-85 Harlo relay panels in Incorrect relays re- Final report Unit #1 failed testing placed with qualified 03/07/83 relays Reportable

_.m.

- DER No. Description Corrective Measures Status 83-1 DG voltage regulating Transformers repaired per Final report system may not perform DCP - 02/16/83 4 .as specified Reportable 83 Valve operators inter- Affected operators were Final report changed replaced 05/03/84 Reportable 83-3 Foreign material in Housing flushed and Final report bearing housing of cleaned 02/28/84 Unit 1 HPSI pump Not ' reportable 83'-4 Test proceddres for air Procedures revised;. Final report handling units do not retests performed ' 04/27/84 meet ANSI 510 No t reportable 83-5 Weld undercut on pipe Use as is Final report.

in SI system 02/28/83 i Not reportable 83-6 Undersize shock sup- Shock suppressor replaced Final report presor in Un it 1 02/28/83-

-Containment- Reportable 83 ' Maxi-bolt anchors Replaced affected bolts Final report i improperly installed 03/04/83

Not reportable 83-8 Hydrogen recombiner _ Existing timers replaced Final report failed Qualification 02/28/83 test Reportable 83-9 Unit 1 LPSI pumps Both LPSI trains flushed . Final report strainers and cleaned 09/06/83 Not reportable I

83-10 Main steam relief valves . Valves returned to manu- Final report l exceed 5% blowdown facturer for refurbish- 02/28/84 unit ment Not reportable 83-11 Exide batteries may Stress or batteries Final report leak or corrode at relieved; permanent 06/14/83 terminals repairs effected Not reportable 83-12 480V MCC interlocks may' Interlocks changed Final report

' malfunction out under GE supervision 05/03/83 Reportable e

v l

DER No. Description Corrective Measures Status 83-13 Violation of Tagout Training conducted on Final report requirements tagging procedures 07/14/83 Not reportable 83- ' Leaking capacitors Defective relays replaced Final report in DG relays 09/27/83 Reportable 83-15 A 354 Anchor' bolt bone Torque valve determin'- Final report under installation torque ation methodology 09/23/83 changed; drawings Reportable revised 83-16 DG govenor and voltage . DCP issued to correct Final report regulator do not reset - deficiency 05/03/83 after trip Reportable i

83-17 Fire protection switches All damaged switches Final report failed to meet THI replaced. 07/19/83

' criteria Reportable Additional hex nuts

~

83-18 .' Pipe supports do not Final report meet Seismic IX require- installed; drawing 04/28/83 ments revised Not reportable 83-19 Shock. arrestors do not Applicable shock Final report function properly arrestors replaced 01/03/84 Not reportable '

83-20: ~ Startup test personnel All personnel properly Final report qualification trained and qualified .04/29/83 N'o t reportable c 83-21 -LPSI pump operated in Training provided to .

Final report 05/06/83

~

violation of procedures operators Not reportable 83-22 Hydrogen recombiner Circuit breakers Final report circuit-breaker failed replaced 10/24/83 '

to operate improperly Reportable 83-23 MSIV-bypass isolation Solenoid valves replaced Closed valves failed to close 05/10/83

-within 5 seconda Not reportable

83-24 DG lube' oil and jacket Ne w heaters installed Final report water heaters do not ' 05/18/83 maintain temperatures -Reportable

, . , - , , .-,,,-.v.. , - , , , , , , , ,,,.,,,.,,_.-.e.,- ,,, - . . . _ . . . , , . , .,n . - ,

DER No..  ; Description Corrective Measures Status 83-25 -Instrument l tubing'does Use-as-is; revised Final report not have boundary class specifications issued 09/21/83 break Not reportable.

'83-26 BOP ESFAS modules failed Cabinets modified to Final report testing due to over- increase ventilation; 10/28/83

. heating. drawings revised Not reportable 83 Need position indication Adjust switches as Closed.

, switches functioning necessary; 0-ring 04/28/83 improperly and terminal boards Notreportable replaced 83-28 Snubbers installed in- Use as is; Specification Final report' violation of reserve change to clarify pro- 06/08/83 range requirements cedure Not reportable 83-29 Hangers in SI system Supports repaired; draw- Final report installed incorrectly ings revised 06/06/83 Reportable 83-30 A354 bolt broke while Torque procedures Final report torquing on Unit 2 AFW revised; drawings 01/30/84 pump. revised Not reportable 83-31 Temperature rise in DG Ventilation modifications Final report-control cabinet could made to provide forced- 08/23/83

-exceed design ventilation Reportable 83-32 Socket welds in Unit 1 Transition pieces instal- Final report S/G 1ed;' drawings revised 02/29/84 Not reportable 83-33 GE breakers with EC-l' Defects corrected per Final report ~

trips may have defect NCR dispositioned- 06/24/83 Reportable 83-34'  : Instrument racks in . Defective welds repaired Final report

, ' Unit 2 have surface 09/19/83 cracks Not reportable 83-35 Inverters produced High frequency snubber Final report voltage spikes on DC- capacitor reworked 01/09/84 supply bus Reportable 83-36' Excessive cycling of Actuators refurbished Final report j
hydramotor actuators and retested; Training 12/21/83 program conducted Not reportable i

{

DER N'.

o Description Corrective Measures Status 83-37 Missed factory operations Defects repaired as Final report on nuit 3 S/G appropriate - -' 12/05/84 Reportable 83-38 Clip angles used _ for HVAC Use-as-is Final report supports do not meet- 10/06/83 requirements. Not reportable 83-39 Re'jectable indications Reworked pump case; Final report on Unit 1 RCP inspected all other welds 01/03/84 Not reportable 83-40 -Unit 1 LPSI and CS putap New lower end brackets Final report motors leaking oil installed; new design 02/02/84 housing Reportable 83-41 Flooding in Control Circulating water intake Final report Building canal sealed; electrical 09/21/83-ducts sealed; all joints Reportable sealed 83-42' Failed thernovells Original thernovells Final report.

in the RCS replaced with new, .

09/14/84-redesigned thernowells Reportable 83-43 Improper crisp termina- All relay cabinets by Final report tions Harlo reinspected; dis- 09/27/84 crepancies will be Reportable corrected 83-44 Wiring errors in PPS Wiring corrected and Final report cabinets retested 08/15/83 Reportable .

83-45 Cable separations in Wiring redone in accor- Final report Unit 1 Control Room dance with applicable 09/26/83 panels requirements; procedures Reportable revised 46 Value overtorqued during Adjusted electrical Final report hydrostatic testing leads and reed switch 01/09/84 Reportable 83-47' Power supplies may damage Additional fuses in- Final report instrument conductor stalled 10/17/83 penetrations Reportable -

DER No. Description Corrective Measures Status 48- Solenoid. valves subjected Refurbished with high Final report to excessive heat- . temperature connectors, 10/28/83 lead wires and 0-rings Not reportable Broken impeller blades /

~

83-49 Diffuser redesigned; Final report diffuser bolts capscrew numbers 09/14/84 increased;-impe11ers Not reportable backfiled; bearing sleeves replaced 83 Combined with DER 83-49 83-51 =AFh pump failed testing Surveillance _ test path Final report eliminated; SARCN to 09/25/84 change required flow Reportable rates 83-52 Power supplies feed Filter elements installed; Final report noise into 125 VDC bus annunciators returned. 12/22/83 for re-work Reportable

~83-53 . Unit.3 embed plates do - Imbed plates and anchor Final report not meet specification bolts were evaluated and 10/15/84 reworked as necessary Reportable 54 Washers found in Unit 1 Inose parts removed; Final report S/G's remainder of system 01/17/84 inspected Not reportable 83 Thermal liner on cold Line.rs removed.from' Final report leg of RCP.lA missing system 12/30/84 Not reportable 83-56 Discrepancies with Larger hydraulic reser- Final report MSIV's ,voir; pump material 04/13/84 replaced; relief valve-- Reportable installed 83-57 Cracks in CEA shroud 4 and 12 finger guides Final report

-removed; snubters added 09/14/84 for lateral support Reportable 83-63 HPSI_ isolation valves Isolation valves were Final report failed to open- repaired 10/9/84 Reportable

~

83-64 Pressure relief valves Test rig replaced Final report

-failed testing 05/24/84 Not reportable

_27 1

o DER N'.- Description Corrective Measures Status 83-65 Safety relief valves Valves reconditioned Final report

- found dirty and rusted and tested; cleanliness 01/23/84 requirements addressed Reportable 83-66 -APW pump impeller wear Wear ring material Final report ring fractured. changed; sent_to manu- 06/21/84 facturer for rework Reportable 83-67 Ex-core detectors below Detectors relocated above Final report

. flood level. flood level 01/23/84 Reportable 83-68 Battery racks construc- Non-conforming hardware Final report ted.with materials not . replaced - ~02/09/84 meeting specifications . Reportable 83-69 Seismic supports on Added additional shaft Final report Posi-Seal valves'incor- supports to' raise 07/11/84 rectly installed frequency,' validating Reportable seismic analysis 83-70' Wiring in ERF Cabinets ' Wiring rerouted; metal Final report not in conformance with barriers installed; color 02/28/84 specification coding of wiring Reportable 83-71 Shock arrestors may have Snubbers replaced as Final report required 04/24/84 generic defect Reportable 83-72 Undersize welds.in Specification revised; Final report Unit 1 Auxiliary Building Training for QC 03/14/84 inspectors Not reportable 83-73 Unqualified power sup- Power supplies replaced Final report plies installed 1E with IE instruments 11/15/84 instrument cabinets Reportable 83-74 Undersize welds in U n it 1 Inspections conducted on Final report Auxiliary Building all units pipe supports 09/21/84 for weld size Not reportable 83-75 Improperly torqued Bolts retorqued Final report bolts on panel filler . 07/24/84 assemblies Not reportable 83-76 Improper AFW pump logic Logic diagram revised; Final report modifications on exist- 05/07/84 ing logic Reportable l

l DER No.- Description' Corrective-Measures Status 83-77 Unit 2 concrete pour Honeycombed areas Final report contains honeycombs repaired 07/13/84 Not reportable-83-78 No user tests or docu- Samples'tated for hard- Final report mentation for. Rock Bolt ness, and elongation; 08/02/84 Expansion Anchor analysis performed to Not reportable accept as is 83-79 ~ TAC interference spikes Final report on DC. bus

._ Specificatios

'Micarta revise'd; ,. 03/09/84 boards-installed Not reportable 83 MFIV close in 20 seconds; closing speed control Final report Specification requires . valve fully open; 38/23/84 5 seconds package to 3500f at Not reportable n 70*F 83-81 Schedule 160.SS pipe Replace the ' piping Final report from Gulfalloy contains 08/29/84 a manufacturing defect Not reportable 82 Improper bend radius in cables rejected and re- Final report DG control cabinets placed ~ to meet bend . 08/10/84 radius requirements Reportable 83-83 Incorrect away strut Strut replaced Final report

-supporting Class QlA 08/23/84 piping was installed Reportable Missing bolts for MCC (6) Installations made to 8344 Final report in Unit #1 conform to revised 05/15/84 '

drawings Not reportable 83-85 ' Perimeter microwave Safeguards information Final report detection system has a '01/20/84 manufacturing defect Not reportable 83-86 Seismic analysis of the Add stiffener plates to Final report shutdown HX did not base plate 01/26/84 address baseplate thick- Reportable

-ness adequately 83 Remote operated manual Deficient SI valves Final report HPSI valves corrected 03/13/84 Not reportable 83-88 QA lack of' procedures & Appropriate procedures Final report programs for testing reviewed and revised 04/13/84 and startup E

DER No.- Description Corrective Measures Status

'84 L Methodology used to Procedures revised to Final report track required ratesting provide a; documented- 04/09/84 activities program to track re- Not reportable

- quirements for out-standing .preoperational retest after work is performed on a previously tested structure system or component

.84-2 Rust, scale, and pitting NCRs were dispositioned -Final report in the clevis and arm use-as-is 07/13/84 of several SI and CH Not reportable valves 84-3 Feedwater isolation Inspect and rework PWIVs Final report valves; lower 4-way and MSIVs to remove un- 05/25/84 valve found stuck during acceptable pipe sealant Reportable testing and replace with Inctite

< No. 277 prior to fuel load 84 External security wiring Contains proprietary Closed 01/27/84 not in conformance with security information per Not reportable specification 10CFR 2.790 84-5 De)ris found in reactor NCR dispositioned to Closed 02/10/84-internal during move- clean area and return Not reportable ment of the CEA Shroud tools to proper storage Assembly from the UGS 84-6 Possible deficiencies Modules returned to Final report I'^ in' absolute and de-~ vendor for repair -12/12/84

,, viation alarm modules Reportable b 84-7_ Failure to provide cor- NCRs initiated to re- Final report rective action as instate rework on valves 07/13/84 stated in DER 80-21 requiring modifications Reportable

84-6 ITT/Barton Model 763 Transmitters will be re- Final report Transmitters do not placed or refurbished 07/24/84 meet specifications Reportable ,

I 84-9 Relating to CAD welding Code Case Approved Final report E for cathodic protection procedues revised 10/15/84

. ground connection Not Reportable F

- +~~,--e , , , _ , -.....m..-------._,-- - _,,. -.,, .. . , - - - , . . ~ . . . - - . ~ . . - , - - _ , - - - , - , _ _ ~ -

f DER No. DescriptioE Corrective Measures Status

~

84-10 ' Abnormal number of 100% inspection revealed . Final report ,.

single element RTDs no probles'with-the RTDs 08/01/84 open-circuited Not reportable 84-12' Zone III violations ofi 'The entire Unit 1 RCS Final report RCP 1A and S/G #1 returned to Class B 09/10/84

, cleanliness, and the Not reportable demonstration test completed 84-13 . Relating to HVAC Deficiencies evaluated Final report and resolved per acceptance criteria' -12/12/84 NCRs. Drawings revised Reportable 84-14 Some studs and nuts in- DCN issued to allow the Closed 03/13/84 g stalled on SI & RC.sys- use of SA-194, GR 8M Not reportable

- tems which do not meet. material in the boric '

ASME requirements for acid related systems, boric acid service. as applicable

! 84-15. Relating to welds' Inspection criteria Final report attaching pipe restraint clarified; design docu- 11/15/84 3

supports less than de- ments revised Not Reportable

l. sign-calculated dimen-aion in Unit-2

~84-16 ESFAS. relay cabinets Added stiffener plates Final report =

08/02/84

  • ~

baseplates to cabinets.and up-dated installation DWG's Reportable 84-17' The core shroud envelope Measurements of core Closed 04/23/84 ghroud panels accomplish- Not reportable

..I as' required I 84-18 Wiring error on LPSI Wiring errors on control . Final report pump "B" CS-3 switch switch corrected 09/10/84 Not reportable 84-19 Improperly' installed Nonconforming flanges re- Final report blind flanges moved and replaced to 07/30/84 meet Piping Material Not reportable J

Classifications 84-20 Displacement of a con- Use-as-is Final report necting'line in the SI 10/15/84 system ,

Not Reportable 21 Rosemount transmitters Hardware replaced, Final report not torqued to specified sample walkdown 11/05/84

~

valve conducted Reportable I

4

DER No.- Description Corrective Measures Status 84-22 . Unit #1 CEA shroud sup- Contaminated area cleaned Final report port contaminated with and checked for.cor- 08/01/84 oil rosion. Oil. retention Reportable bars are being added to the Polar Cranes to con-tain oil in gear case 84-23 Auxiliary feedwater No future reflow cire. Final report pump'"B" discharge valve testing will be done. Re- 07/12/84 to concensate storage circ. valves V018 and Reportable tank V027 will be replaced by spectacle flanges!

l '84-24 L*.mitorque valve opera- Bolts retorqued,'in- Final report 3'

tors loose on valve struction manuals revised 10/23/84 bodies Reportable

'84-25 Containment supply Piano wires on safety- Final report registers would not related registers to be 11/27/84 cycle replaced Reportable 84-26 Improperly tested or Interlocks will be Final report adjusted interlock manually tested unless 09/21/84 properly tested Reportable personnel are performing

.the function 84-27 Improperly handled in- Reinspection performed Final report strumentation from of instruments. Training 12/12/84 Waldinger Corp. performed. Documents Reportable Revised 84-28 Diesel generator fuel Use-as-is and repair Final report lines for modifications 2/15/85 Not reportable i 84-29 Build up of material on Clean, recoat with Final report Unit #2 diesel generator plasite lining 09/25/84 HX Reportable 84-30 -Improper documentation Review of all code- Final report of diesel generator related documentation 09/18/84 components concluded correct and Not reportable on file, use-as-is 84-32 Superceded by DER 84-34 1

L DER No. Description Corrective Measures Status 84-33 Incorrectly installed Weld added Final report hanger support assembly 09/21/84 Not reportable 84-34 ' Critical friction type' Connectors retightened; Final report high. strength con- drawings revised 10/26/84 nectors Reportable 184-35 Setpoint potentiometers Potentiometers replaced Final report in the PPS drif t out- 09/18/84 side of tolerance Not reportable 84-36 SI valve stalls just off Valves removed and Final report closing seat when open- repaced 11/28/84

-ing or closing Reportable

~

84-37 Unauthorized /unq~ualified Sealant qualified for Final report duct sealant use; retraining conducted 11/02/84 Reportable 84-38 Laproperly welded flange Rework / repair by adding Final report in Unit #2 filler material .09/18/84

' Reportable 84-39 LPSI and containment Use-as-is, but do not Final report spray _ pumps have ex- run pump in -the 2500 09/26/84 perienced abnormal to 3500 flow range during Not reportable rumbling noises shutdown cooling mode of operation

~84-40 Unit #2 auxiliary. Parts cleaned. Proper Final report feedwater pump has flushing and chemical 12/14/84 corrosion control Not reportable 84-41 Adequacy of Cardinal Documents revised, Final report Industrial Products training audits and 12/13/84 program for supplier integrated audit Not reportable qualification performed 84-42 Unqualified torque None Final report i switches installed on 10/30/84 safety related valves o reportable N't i 84-43 HPSI 3" gate valve Valve stem cleaned Closed 07/18/84 failure to open and lubricated _ Not reportable 84-44 Fatique failures of Maintenance inspection Final report the charging pumps program initiated 11/28/84 Not reportable

, .. _ , . _ . _ _ . ~ . _ _ _ _ _ _ _ . . . - _ _ _ . _ . _ . _ _ _ . _ _. . _ _ _ _

DER No. Description Corrective Measures Status 84-45 ' Relating to spot welding Testing to be performed; Final' report on skid mounting indica- retrofit to be completed 10/19/84 tion and control Not reportable 84-46 Refueling water tank DCPs prepared to perform Final report penetration sleeves; required grouting work 09/24/84 connection would be Reportable

-overstressed during a seismic event 84-47 Hacksaw blade in the Weld on line SI 130 , closed 07/24/84 Unit #3 SI system was completed Not reportable 84-48 Improper material for Pipe plugs replaced with Final report

. pipe plugs on MSIV proper material 10/18/84 Reportable

~

84-49 Auxiliary feedwater Mini-flow individually Final report system experience adjusted for 'each pump 09/26/84 hydraulic resonance to reduce the vibration Reportable to acceptable limits 84 Main steam isolation -Precharge pressure / Final report valves do not close as temperature curve 10/25/84 required revised' Reportable 84-51 . Failure of turbine-driven Changes initiated to re- Final report auxiliary feedwater pump flect the feedwater de- 09/26/84 to quick start from livery time change from Reportable ambient conditions 20 to 30 seconds 84-!2 Relating to the atmos- DCPs initiated to in- Final report pheric dump valve; a crease the thickness of. '09/26/84

. review of the seismic = the resistor base flange Not. reportable-analysis report deter- to two inches mined that the base flange of the resistor is overstressed during an SSE and will break ,

53 Nuts on bolts found- NCR's evaluated, Pro- Final report loose on PC and CH cedures revised, 12/18/84.

valves training performed Not reportable 84-54 Containment sump isola- Reworked valves Final report tion valve 12/12/84 Reportable

me

(- ,

DER No. Description- Corrective Measures Status W 84-55 Non "Q" material in- Modules replaced; pro- Final report 11/15/84 installed in Q1E fustru- cedures revised

mentation cabinets Reportable 84-56 Fire dampers were ' found Damper Reworked Final Report to close inconsistently 12/08/84 I.

, Reportable 84-57 Evaluation relating to .SARCN to change time Closed 09/19/84 radioactive waste drain- from 10 seconds to' Not reportable-system 40 seconds

- 184-58 Auxiliary feedwater sys- Valves cleaned and/or Final report tem solenoid' valve failed replaced 11/12/84 to open in-response.to Not reportable AFAS signal 84-59 MCC cables damaged by cables replaced; edge Final report fire stops protectors installed 10/09/84 ~

Reportable 4

84-60 Improper lubricant used- Valves flushed and Final report in.Limitorque valve re-lubricated 11/12/84 operators Reportable 61 Auxiliary pressurizer Redundant valve in- Final report

~

spray system-loop valve- atalled- 10/17/84 potential to stop open Not reportable

~

84-62 Load sequencer did not Rework Control Final report function properly during Circuits 12/08/84 safeguards - tes ting Not reportable 84-63 SIT vent valve would Valves cleaned and/or Final report not close during testing' replaced' 11/12/84 Not reportable

'84-64 Snubbers will not cycle Rework snubbers, monitor- Final report ing program 12/12/84 Reportable r

Inst. leads removed from Leads in the CSB Final report 65

- UGS have shown splitting removed 11/12/84 of outer sheath Not reportable 84-66 Downconer feedwater iso- Actuators redesigned; Final report f closure time revised 10/03/84 lation valves Reportable 84-67 Steam generator system Valves cleaned and/or Final report i valve solenoid operations replaced 11/12/84 at low voltage Not reportable l-

?

m -. . . _ . . _ . . _ _ _ _ __ _ ..-. . _ -. _ - .,.. _ . _ _ ~ , _ . _ _ . ,.. ,

L

+

DER No. Description Corrective Measures Status

-8'4-68 ESC "A" would not re- New temperature switches Final report sequence due to temp. installed 11/15/84-switch trip after LOP Reportable 84-69 Reactor protection system Barrier material removed Final report shunt trip contacts and relays retested 11/09/84 Not reportable 84-70 Diesel engine "A" in Unit': Lubricate control closed 09/28/84

  1. 1 tripped.off because mechanism 'Not reportable-of engine overspeed 84-71' A spurious load shed of None required Closed 09/17/84 the 4160 V SWGR SO4 Not reportable Feeder Breaker 84-72 During pre-op test SI Rework operators Final report valve torqued out near 12/12/84 the closed seat Reportable 84-73 . Test cards for excore Test cards replaced, Final report system have an incorrect rework discriminator 11/05/84 value for "R26" cards Reportable Inspection and repair

~

84-74 Inverters failed pre-op Final report testing as necessary, Procedure 12/14/84 revision Not reportable 84-75. DG essential exhaust fan Start signal time Closed fails to start within 5: changed 09/27/84 seconds in' Mode 1 or 4 Not reportable operation 84-76 Stator temperatures HVAC modified Final report

- could be exceeded 12/12/84 Not reportable 84-77 Rosemount transmitters Transmitters replaced Final report manufactured after or refurbished 11/02/84 January 10, 1984 may not Reportable
j. have hermetic seal 84-78 .Valcor valves experience Dropping register in- Final report coil failures stalled to reduce voltage 11/16/84

' Reportable 84-79 Broken terminal lug on Damaged lug replaced Closed DG could cause abnormal 10/04/84 temp. rise Not reportable u

x

. DER No.- Description Corrective Measures Status c J84-80 -DG."A"_ tripped off on Hydraulic govenor ad- Closed overspeed'when load was-justed 10/03/84 removed Not reportable 84-81 65%-90% hesitation of. Operators reworked Final report the'odpen position when 12/12/84 3 of 4 valves are in Reportable closed position 84-82 Improper mate between Use-as-is Final report seat and disc of SI 11/09/84 check valve Not reportable 84-83 HPSIL"A" injection lines Orifices installed Final report experiencing cavitation downstream 11/28/84 Not reportable 84-84_ Discrepancy between ESFAS response time Final report CESSAR Section 5.1.4 and changed 10/26/84 CESSAR Chapter 15, deal- Not reportable ing with valve closure time 84-85 -Containment purge _ valve FSAR revised Final report closing time on Contain- 10/26/84 ment Isolation Activa- Not reports.ble Signal assumed in CESSAR 15-4-8 Amend 6 or later was not assumed in Palo Verde FSAR e

84-86 Pipe flanges corroded Cleaned flanges and Closed in DG system bolts 10/19/84 Not reportalle 84-87 Pre-operational test None Closed procedure discrepancy 10/24/84 on HPSI system Not reportable 84-88 Grout missing on down- Place grout linal report comer feedwater lines 11/30/84 Reportable-84-89 Transmitters mounted Reworked transmitters Final report

-upside down 12/06/84 Not reportable 84-90 Rx. Vessel shin pina Shim Pins Staked Final Report improperly staked 12/06/84 Not reportable

.a.. ,,

DER No. Description Corrective Measures Str.,tus '

91' Miscellantous pipe . Inspection Performed Final report found in U-2 RCP 12/06/84 Not reportable 84-92  : Inadequate pressure None Closed 4 for fire protection 11/07/84 in the MSSS Not reportable -

84-93 No support rails for Bracing installed Final report Control Roon Panel B05 12/08/84

-Reportable 84-94 overstress on CEDM Use-as-is Closed l lifting lugs 11/12/84 Not reportable 84 Spray chemical addition Pump inspected; Closed '

pump run for 6.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> : Use-as-is' 11/12/84 3- with suction and dis-charge valve closed 84-96 Excessive closure time -Actuators replaced Final report for containment purge 12/07/84 valves Reportable 84-97 Sway strut bracket Use-as-is closed e welded incorrectly 11/14/84 Not reportable

- 84-98 GE Relays not .

Contacts adjusted Final report properly ~ set at factory 12/14/84 Reportable 84-99 Regen Heat Exchanger Bracket restored Final r. :t improperly mounted 12/14/84 Reportable c'84-100 - Compression Terminal Inspection and tightening Final report screws at terminal as necessary - specs 12/14/84 blocks are loose- revised Reportable 84-101 Containment Purge Valve Inspection and rework Final report failed to open as necessary 12/14/84 Reportable'

,84-102 Improperly secured A/D Inspection and rework Final report

- check valve as necessary 10/14/84 Reportable i.
l s

DER No. Description Corrective Measures Sta tus- 84-103 D/G Building Roof Restraints installed Final report Hatch not locked 10/14/84 Reportable 84-104-- SIT Vent' valves Seat ring modified Closed 12/26/84 leaking past seat Not reportable 84-105 Vertical uplift not Documents revised Closed 12/26/84 considered in pipe Not reportable support design-84-106 Spurious load shed Sequencer module Final report on B0P EFAS replaced 02/27/85..

Not reportable

' DER No. Description Corrective Measures Status 85-01 Aux. FW taper pin Coupling / Pedestal Final report stresses excessive reworked, document 06/06/85 ravision Reportable i

85-02 Brown,Boveri - High Additional testing Final report Leakage in SCR's incorporated 02/26/85 Not reportable 85-03 containment shell min . Document review and Final report GAP violated revision as necessary 06/14/85 training Not reportable 85-04 Ruskin fire' dampers Dampers reworked Final report deficient 04/05/85 Feportable 85-05 Fire proofing on non- Repair / rework performed Final report segregated buses evaluation performed 06/20/85 Reportable 85-06 Diesel generator trip None required Closed 03/05/85 during testing Not reportable 85-07 CE inetrument rack Bolting replaced Final report bolting deficiencies Document review 09/09/85 Not reportable 85-08 AlW AFAS logic circuit Calibration performed Final report hysteresis 05/30/85 Not reportable 85-09 Substitution of welded Evaluation performed Closed 03/15/85 connections for bolted Not reportable connections 85-10 Leaking welds on spray Monitoring program closed 03/25/85 pond (MIC) developed - reexamination N o t reportable performed chemical control incorporated 85-11 CST Transfer Pump Documents revised Closed 03/26/85 insufficiently sized Not reportable 85-12 Cracks in Aux. Building Specification revised- Final report brought to personnel 06/14/85 attention Not reportable

I t

DER ~No. Description ~ Corrective Measures Status 85-13 Stress calculations for Calculations revised Final report SI linss inconsistent documents revised ~04/09/85 Not reportable 85-14 Low pressure lube oil Circuit reworked Final report failure during testing 06/14/85 of diesel generator ~ Reportable 85-15 Piping min wall, None required Final report thickness violation 07/15/85 Not reportable 85-16 -AHU Spoke Cracked Replaced AHU hubs Final report New hubs for all units 08/13/85 reportable 85-17 Essential AHU Seismic Seismic report amended Closed 05/07/85 i~

. analysis review / revised documents Not reportable-85-18 Brown Boveri K-Line Procedure revision for Closed 05/15/85 Circuit breakers inspection during Not reportable deficient maintenance 4

85-19 ' Iodine removal system SCAP's reworked Final report excess flow rate 07/25/85 Not reportable 85-20 Cracked rocker arm Rocker are replaced Final report on diesel generator- maintenance program 09/30/85 incorporated Reportable 85-21 Anchor Darling air check None required Closed 05/31/85 valve failure to seat Not reportable i properly 85-22 Control relay visual Relays inspected / cleaned Final report indicat. ors breaking off as necessary - procedure 07/05/85 into relay revised Reportable 85-23 Diesel generator start Replace valves Final report failure due to Mechanical 09/09/85 l valve failure Not reportable 85-24 ' Fractured bolting on Bolting replaced - Final report i _' diesel turbocharger Torque increased C9/13/85 Reportable e

1 t

h

. DER No. Description Corrective Measures - Status 85-25 Aux FW pump trip on Control circuit modifi- Final report A'AS-2 signal cold cations monitoring 10/15/85 conditions - program through periodic Reportable testing 85-26 Inadequate design of Circuit modifications Final report.

containment purge system document revisions 09/11/85 1 ducting Not reportable

.85-27 - Slippage of shock Torque increased - Final report suppression pipe clamps documents revised 09/18/85 s Reportable

.85-28 CE instrument rack Under evaluation Open Conduit bend radius violations 4 ,

85-29 Evaluation of beam - Calculation revised- Closed 08/26/85 support designs further instructions Not reportable provided 85-30 CAD drawings do not Drawings revised - Closed 08/26/85 reflect as built document revisions. Not reportable condition Attention to detail emphasized 85-31 Q class pipes / pipe Documents revised Closed 05/28/85-supports hung on drawings revised Not reportable non-Q beams 85-32 Min seismic separation Under evaluation Open between buildings violated 85-33 ANI withdrawal of None required . Closed 09/25/85' acceptance of Bisco Not reportable cable / pipe fire stops i

85-34 Override feature on D/G Under evaluation Open prevents pickup of emergency loads i

+

s-- -

oy.. ,w.- -- %y-r-_., -.e.w.=,,---*+m,,,._,.n.- -.y, - , , g%-- , ,,wwm,g, .ey---ee. *-+e+'e -e t==t-----rvf+9 ~r--'F- -e= ww-r- t * * - ' * **

y ,. t.- , s $

e t f

~

d. - Construction Status A11~ safety. related and important to safety systems and areas will be accepted by operations' to ensure drawings are up-to-date and system coaletion prior to fuel load. The status as of October 21, 1985, is as follows:

' SUBSYSTEMS TOTAL SUBSYSTEMS ACCEPTED WALKED DOWN 230 189 220 TOTAL AREAS . ACCEPTED WALKED DOWN 67 41 67 CONSTRUCTION STATUS The following -safety-related and important to safety systems have . outstanding

' work that is required for fuel load.

' The remaining work is relat'ively minor in nature. It is tracked by the site tracking aystems and will be prior to issuance of an 0.L.

AF Auxiliary Feedwater AS Auxiliary Steam .-

CC Chemical Production CD- . Condensate

.CE Stator Cooling CH Chemical and Volume Control CL Containment Imak Test CP Containment Purge CT Condensate Transfer and Storage DF Diesel Fuel Oil and Transfer DG Diesel Generator Systems DW- Demineralized Water EC Essential Chilled Water ED Feedwater Hester Extraction Steam and Drains ES Safety Equipment Status System EW Essential Cooling Water FH Fuel Handling FP Fire Protection GH Generator hyudrogen and'CO2 GR Gaseous Radweste HA HVAC - Auxiliary Building HC HVAC - Containment-HD HVAC - Diesel Generator Building HF HVAC - Fuel Building HJ HVAC - Control Building HP Containment Hydrogen Control HR HVAC - Radweste Building f

t'

}

i IA , Instrument and Service' Air LR Liquid Radwaste MA' Main Generation MB Excitation' and Voltage' Regulation MT Main Turbine NA 13.8-KV Power_

NB 4.16-KV Power NC Nuclear Cooling Water

NQ Uninterruptible AC Power.

LOW Oily Waste and Nonradioactive Waste PB . 4.16-KV Power PC Fuel Pool Cooling and Cleanup PE. Standby Generation PG 480-V Power, Switchgear PH 480-V Power, MCC PK 125-V DC Power PN . Instrument AC Power QB ~ Essential Lighting.

QC Yard, Roadway, and Fence Lighting QD Emergency Lighting ,

QF IS-Plant Communications QK Fire Detection and Alarm QM Special Process Trace Heating RC Reactor Coolant RD Radioactive Waste Drains RE Nonnuclear Process Sampling RI In-Core Reactor Instrumentation RJ Plant Computer RK Plant Annunciator RM Main Control Board SA Engineered Safety Features Actuation SB Reactor Protection SC Secondary Chemical Control SD Area Radiation Monitoring SE Ex-Core Neutron Monitoring SF Reactor Control SG Main Steam SI Safety Injection and Ehutdown Cooling SM Seismic Instrumentatin SP Essential Spray Ponds-SQ Radiation Monitoring

  • SR Solid Radwaste SS Nuclear Sampling System Sanitary Drainage and Treatment
l. ST SV Loose Parts and Vibration Monitoring WC Chilled Water ZA Auxiliary Building ZC Co'ntainment Building ZF hiel Building

-ZG Diesel Generator Building ZJ. Control' Building ZM MSSS Building ZR Radwaste Building ZT Turbine Buiding and Pedestal 1

.w

}

r

e. -Preoperational Test Status

- Preoperational Testing ~ - ~~ Preoperational testing required -for ' fuel load will be completed' on :all ; safety related or important to safety systems

- prior to fuel load. The status as of October 21, 1985 is as follows:

TOTAL TESTS TEST COMPLETE TEST RESULTS APPROVED 182' 168 118 ,

l The~ remaining 14 tests that are not complete are listed below.

TESTS ON HOLD PROCEDURE #~ DESCRIPTION  % COMPLETE

. 91PE-2CP01- Containment Purge System 89 91PE-2HP01  : Hydrogen Purge System 89 93PE-2QD02 Modular A.C. Emergency Lighting 0 TESTS IN PROGRESS 91PE-2HJ02 Control Room Pressurization 70 Test

-'91PE-2SR02- Solid Radwaste System 5 92PE-2SB19 QSPDS Preoperational Test- 95 TESTS TO BE PERFORMED AFTER INITIAL FUEL LOAD (To Be Performed Per FSAR 14.2.5 Phase'I Tests)

The. Following Tests Have Not Been Performed-91PE-2LR02 Liquid Radwaste Evaporator Test 92PE-2QF06 In Plant Communihations (Safety Frequency Radio Frequency) 92PE-2SB20 ^ DNBR Calculator to PMS Data ' Link .

~92PE-2SQ01- Radiation Monitoring Preop 4 .

4 92PE-2SQO2 ' Post-Accident' Radiation Monitor 92PE-2SQO3 Digital Radiation Monitoring System

~92PE-2SQ04 Safety Related Radiation Monitoring i .- 91PE-2SS02 Gas Analyzer Test i

r

, _1_ ,

e,,-, s, w+s- .c rr, ww-r-~e-w- w , ,,ew---w---w,--o-w-,e-r,-----~w ee,--en ~~m-wv,-,-- -v-*~*g ,--r-~ve w, e

The following Preoperational tests have been performed and have some incomplete portions.

93PE-2PE01 Diesel Generator Electrical Test

- 92PE-2SB08 CEA Position Isolation Assembly (CPIA) Channel D 92PE-2SB07 CEA Position Isolation Assembly (CPIA) Channel A 91PE-2CH04 CVCS Charging Test 91PE-2SP01 Essential Spray Pond System

' 91PE-2SC01 Secondary Chemistry Blowdown Flashtank 93PE-2PK01 Class IE 125 VDC Power System 93PE-2PB01 4.16kV Class IE Preoperational Procedure 91PE-2CH07 RMW, BAM, VCI Preoperational Test 91HF-2ED01 Main Steam Traps and Drain Valves HFT 91PE-2SG04 Steam Generator Isolations

- 92PE-2SB15 Core Operating Limit Supervisory System Test 92PE-2QK01 Fire Detection and Alarm System 93PE-2PK02 125VDC Class IE Station Battery Service Test 93PE-2MA01 Main Generator 91PE-2SG03 Atmosperic Dump Valve Test 92PE-2SE04 Excore Nuclear Instrumentation Safety Channel B 92PE-2SA01 BOP Engineered Safety Features Actuation System Panel Test 92HF-2SB18 RTD Response Time Test

)

L___ j

/ f i

f. Independent Third Party Inspections 1980 - Training Program'- RQS Corp.

i 1982 - Overall review of Chemical Control Program - Tom M. Laronge Inc. l

- Training Program (Follow-Up 1980 Review) - RQS Corp.

- Pre-INPO Audit - United Engineers

~

-_Radwaste Program - Bechtel National

- Beergency Plan Audit'- HMM and Associates

- Quality Assurance Program Evaluation - Torrey Pines *

- Operations Evaluation - INPO 1983.- Training Audit - Seville Training System

- Security Audit - Newsack Inc.

- Personnel / Manpower needs evaluation - Sargent & Lundy 1984 - AIARA Study - Hydra Nuclear

- Fire Protection Audit - INPELL 1984 P

- NTOL Evaluation and Corporate Assistance Visit INPO 1985 - Western Regional Joint. Utility QA Audit

  • Torrey Pines Technology _ conducted an extensive independent quality assurance audit at PVNGS in the area of organization,' management, quality

~

assurance, design and' construction ~ activities in 1982. -The QA program at p PVNGS was found to be effective and successful.

I f

f I

i

?

j_

F. - .~ -

g. -Licensee and Contractor Audits

~

. Summary of Bechtel Quality Assurance Audits 1973 1974 1975 1976 1977'1978 1979 1980 1981'1982 1983 1984 1985 Total

- QA Audit of 80 53 49 -724

- Construction 33' 111 90 70 67 76 95 i- .

Findings 30~ 65 145 121 117- 85 83 54 53 63 816 QA Audit of: 30 21 21 212 Subcontractors 13 21 38 34 34 Findings 36 53 54 37. 19 11 33 36 279 QA Audit of 33 31 15 24- 29 609 H.O. Engr. 23 117 74 48 64 55 56 40 Findings 11' 76 58 57 75 40 73 26 16 5 17 15 16 444 QA Audit of 76 62 39 59 83 558

_ Vendors 7 69 62 61 Hold On Shipment 0 12 16 33 12 6 6 7 10 102 Note 1: Bechtel does not utilize observations

~ Note 2: -Stop work Notices issued by Bechtel are summarized in Section B Note 3: Construction Audits for 1976 and 1977 include subcontracts

, ~ . _ - - _ - - _ . . . . - . . . - - . _ _ _ _ . . _ _ _ . ~ . - . - _ _ _ . . _ - - - _ _ . . _ _ . . _ - - _ - _ _ _ _ _ _ . _ . . _ . _

Summary of APS Quality Assurance Audits 1974 1975 1976 1977 1978 1979 1980 1981 1982 1983 1984 1985 Total APS - Construction Audits 0 0 1 2 2 2 2- 2 2 1 3 0 17 Findings 0 0 0 9 8 1 6 0 6 0 0 0 30 Observations 0 0 5 16 10 11 5 2 0 0 6 0 55 APS - Nuclear Services (includes *)

Audits 5 2 4 4 3 4 5 5 8 8 10 11 69 Findings 23 3 11 13 12 8 12 10 10 10 12 10 134 Observations 26 1 9 23 13 17 7 7 21 16 21 13 174

(*) - Nuclear Services Licensing Nuclear Engineering Emergency Planning Nuclear Projects Records Management Project Services Nuclear Operations Support Esployee Relations Nuclear Fuels Management APS - Quality Assurance Audits 0 0 1 2 2 6 7 7 6 6 8 6 51 Findings 0 0 0 9 8 6 18 10 13 7 14 3 88 Observations 0 0 5 16 10 28 12 6 30 22 11 , 4 144 APS - Operations (includes *)

Audits 0 0 0 0 0 0 0 1 13 12 35 '32 93 Findings 0 0 0 0 0 0 0 1 42 53 40 57 193 Observations 0 0 0 0 0 0 0 6 23 11 42 45 127

-(*) - Operations Nuclear Prcduction Administrative Services Plant Services Security Technical Support Operations Engineering Outage 11anagement Radiation Protection Mainterance APS - Startup 0 0 0 0 1 13 12 20 9 55 Audits 0 0 0 4 100 Findings 0 0 0 0 0 0 0 1 42 33 20 0 0 0 0 0 6 23 11 31 4 75 Observations 0 0 1974 1975 1976 1977 1978 1979 1980 -1981 1982 1983 1984 1985 To tal APS'- System Protection (Relay Settings)

Audits 0 0 0~ 0 0 0 0 1 1 1 0 0 3 Findings 0 0 0 0 0 0 0 0 0 0 -0 0 0 Observations 0 0 0 0 0 0 0 1- 1 0 0 0 2 Bechtel'- Construction 1 Audits 0~ 1 16 31 29 47 26 20 23 32 3 6 234 Findings 'O 3 7 60' 54 43' 63 46 58 98 8 5 445 Observations 0 0 5 11 12 23 0 17 41 38 4 4- 155 Bechtel - Downey/Norwalk Audits 3 2. 4 3 4 4- 5. 5 3 4 2 1 40 Findings 7 0 7 2 11 8 2 1 0 4 3 3 48 Observations 5 0 2 23 16 8 10 15 1 3 5 0 88 Bechtel - Engineering

' Audits 0- 1 0 0 0 0 0 0 1 1 4 1 8 Findings 0 0 0 0 0 0 0 0 1 5 4 1 11 Observations 0 3 0 0 0 0 0 0 0 7 10- 1 21 Bechtel - Quality Assurance 0 0 0 0 6 1. 3 1 13 Audits- 0 2 0 0 Findings 0_ 0 0 0 0 0 0 0 14 1 8 3 26 0 0 0 0 0 0 0 11 0 6 3 20 Observations 0 Bechtel - Startup Audits 0 0 0 0 0 0 0 0 1 0 0 0 1 Findings 0 0 0 0 0 0 0 0 7 0 0 0 7

Observations 0 0 0 0 0 0 0 0 3 0 0 0' 3 Bechtel - Supplier Quality 1'

1 1 1 0 0 0 0 0 2 0 0 5 Audits 0 4

Findings 0 2 0 0 0 0 0 0 0 2 0 0 0 0 0 0 0 0 0 0 1 0 0 1 Observations 0 l

{J 1974 1975 1976 1977 1978 1979 1980 1981 1982 1983 1984 1985 Total Combustion Engineering - Avery*

Audits 0 0 0 2 2 1 1 1 1 0 0 0 8 Findings 0 0 0 4 20 7 7 6 4 0 0 0 48 Observations 0 0 0 1 5 0 0 0 0 0 0 0 6 Combustion Engineering - Chattanooga

  • Audits 2 0 1 1 1 1 1 0 0 0 0 0 8 Findings 1 0 0 0 1 6 1 0 0 0 0 0 10 Observations 2 0 0 2 5 4 0 0 0 0 0 0 17 Combustion Engineering - Hematite
  • Audits 0- 0 0 0 0 0 0 0 1 -0 0 0 1 Findings 0 0- 0 0 0 0 0 0 0 0 0 0 0 Observations 0 0 0- 0 0 0 0 0 0 0 0 0 0 Combustion Engineering - Nuclear Products Manufacturing Audits 0 0 0 0 0 0 0 0 1 2 1 l' 5 Findings 0 0 0 0 0 0 0 0 3 0 7 3 13 Observations 0 0 0 0 0 0 0 0 0 0 4 1 5 Combustion Engineering - PVNGS Site Audits 0 0 0 0 0 0 0 1 0 0 1 0 2 4

Findings 0 'O O O O .0 0 4 0 0 3 0 7 Observations 0 0 0 0 0 0 0 2 0 0 3 0 5 Combustion Engineering - Windsor

. Audits 1 3 2 2 2 1 1 1 0 0 1 1 15 Findings- 2 5 5 4 20 8 6 3'. 0 0 3 2 58 Observations .1 0 5 1 5 0 0 0. O' O 7 2 21

  • Audits conducted by Combustion Engineering 1

Subcontractor Audits 1974 1975 1976 1977 1978 1979 1980 1981 1982 1983 1984 1985 Total Audits 2 1 2 4 4 3 2 2 2 8 l' 0 31 Findings 3 1 2 3. 12 17 13 3- 4 29 3 0 90 Corrective Action Reports Summary "1974 1975 1976 1977 1978 1979-1980 1981 1982 1983 1984 1985 CARS 0 0 # # # # # #21 178 330 461 396 Audit' Findings 11 J 30 129 -111 98 101 77 143 205 108 125 Total 11 5 30 129 111 98 101 98 321 535 569 521*

  1. lfor.1976-1981, nineteen (19) Quality Assurance Deficiency Reports (QADRs) were issued.
  • Through 10/21/85 Note 1: Stop Work Notices are summarized in Section B.

l

, ~5-

Attachment to g.

The Bechtel and . APS Audit programs are supplemented by a surveillance /

monitoring program to evaluate a sample of quality-related activities on a

' daily basis 'for compliance to specifications, procedures, and drawing requirements. A summary of these activities is given below.

Bechtel Conducted 1979 1980 1981 1982 1983 1984 1985 Total Number construction 1018 1170 753 692 766 794 759 5952 Subcontractor 264 216 198 141 370- 303 218 1710 APS Conducted 1982 1983 1984 1985 Total Number 976 2248 3048 3074 9346