| | title = (D91660) Request for Additional Information (RAI) Draft Questions Corporate Security Plans Submitted 7/30/2012 | | | title = NRR E-mail Capture - (D91660) Request for Additional Information (RAI) Draft Questions Corporate Security Plans Submitted 7/30/2012 |
| | author name = Feintuch K | | | author name = Feintuch K |
| | author affiliation = NRC/NRR/DORL | | | author affiliation = NRC/NRR/DORL |
Line 21: |
Line 21: |
|
| |
|
| ==Subject:== | | ==Subject:== |
| (D91660) Request for Additional Information (RAI) draft questions Re: corporate security plans submitted 7/30/2012 Attachments: MExxxx Ke and Fleet Sec Plan Draft RAI Questions.pdf By letter dated July 30, 2012 (Agencywide Documents Access and Management System Accession No. | | (D91660) Request for Additional Information (RAI) draft questions Re: corporate security plans submitted 7/30/2012 Attachments: MExxxx Ke and Fleet Sec Plan Draft RAI Questions.pdf By letter dated July 30, 2012 (Agencywide Documents Access and Management System Accession No. ML12214A581), Dominion Generation, submitted Dominions Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 15 for the Kewaunee Power Station. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure. |
| ML12214A581), Dominion Generation, submitted Dominions Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 15 for the Kewaunee Power Station. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure. | |
| The Reactor Security Licensing Branch (RSLB) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations, Section 50.54(p)(2). The RSLB staff has determined that additional information is necessary to complete its review. | | The Reactor Security Licensing Branch (RSLB) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations, Section 50.54(p)(2). The RSLB staff has determined that additional information is necessary to complete its review. |
| The Request for Additional Information (RAI) items are attached. The attachment is identical to that sent to you informally in an email message dated October 4, 2012. | | The Request for Additional Information (RAI) items are attached. The attachment is identical to that sent to you informally in an email message dated October 4, 2012. |
Letter Sequence Draft RAI |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
|
MONTHYEARRA-12-082, Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, (Revision 12)2012-07-13013 July 2012 Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, (Revision 12) Project stage: Request NOC-AE-12002878, Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan Revision 142012-07-17017 July 2012 Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan Revision 14 Project stage: Request ML12214A2642012-07-25025 July 2012 PVNGS Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program, Revision 14 Project stage: Request CP-201200875, Report of Changes to the Physical Security Plan (Revision 7)2012-07-26026 July 2012 Report of Changes to the Physical Security Plan (Revision 7) Project stage: Request ML12214A5812012-07-30030 July 2012 Associated ISFSIs - Submittal of Security Plan, Training & Qualification Plan, Safeguards Contingency Plan & ISFSI Security Program Project stage: Request RBG-47269, Submittal of Revision 10 to the Security Plan, T&Q Plan and Safeguards Contingency Plan2012-08-0202 August 2012 Submittal of Revision 10 to the Security Plan, T&Q Plan and Safeguards Contingency Plan Project stage: Request L-2012-305, Revision 15 to the Physical Security Plan, Cover Letter2012-08-0303 August 2012 Revision 15 to the Physical Security Plan, Cover Letter Project stage: Request ULNRC-05889, Union Electric Co. Facility Operating License NPF-030 Physical Security Plan, Revision 102012-08-0303 August 2012 Union Electric Co. Facility Operating License NPF-030 Physical Security Plan, Revision 10 Project stage: Request ML12219A2282012-08-0303 August 2012 Revision to the Sequoyah Nuclear Plant Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan and Independent Spent Fuel Storage Installation Security Program, Revision 9 Project stage: Request ML12221A3362012-08-0808 August 2012 Draft RAI on Revision to Security Plan Project stage: Draft RAI ML12229A2872012-08-13013 August 2012 Security Plan, Revision 9 to the Training and Qualification Plan, and Safeguards Contingency Plan Project stage: Request ML12237A0772012-08-23023 August 2012 Draft Request for Information Email - Related to Physical Security Plant (Psp), Training and Qualification Plan (T&Qp), and Safeguards Contingency Plan (Scp), Revision 14 (TAC D91660) Project stage: Draft RAI ML12229A4332012-09-0606 September 2012 Request for Additional Information Regarding Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 12 (TAC No. D91660) Project stage: RAI ML12251A0472012-09-11011 September 2012 Request for Additional Information, Review of Physical Security Plan (Psp), Training and Qualification Plan (T&Qp), and Safeguards Contingency Plan (Scp), Revision 14 (TAC D91660) Project stage: RAI ML12255A0742012-09-18018 September 2012 Request for Additional Information, Changes to Callaway Physical Security Plan (TAC No. D91660) Project stage: RAI ML12286A3362012-10-0404 October 2012 (ANO) Units 1 and 2, Revision 14 of the ANO Security Plan Project stage: Request ML12284A0182012-10-0505 October 2012 NRR E-mail Capture - (D91660) Request for Additional Information (RAI) Draft Questions Corporate Security Plans Submitted 7/30/2012 Project stage: Draft RAI ULNRC-05921, Response to Request for Additional Information Regarding Changes to Security Plan (TAC No. D91660)2012-10-18018 October 2012 Response to Request for Additional Information Regarding Changes to Security Plan (TAC No. D91660) Project stage: Response to RAI ML12296A0102012-10-19019 October 2012 NRR E-mail Capture - D91660 - Dominion Physical Security Plan - Request for Additional Information - This Message Is Publically Available and non-sensitive Project stage: RAI ML12296A9302012-10-23023 October 2012 Enclosudraft Request for Additional Information Project stage: RAI ML12305A0432012-10-29029 October 2012 Email Security-Related Request for Additional Information, Review of Revision 10 of the Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan (TAC D91660) Project stage: RAI ML12305A0192012-10-30030 October 2012 NRR E-mail Capture - FW: D91660 - NextEra Energy Duane Arnold Physical Security Plan - RAI - This Message Is Publically Available and non-sensitive Project stage: RAI ML12306A5462012-11-0101 November 2012 E-mail, Request for Additional Information - Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 7 for the CPNPP (TAC No. D91660) Project stage: RAI ML12292A3222012-11-0101 November 2012 Request for Additional Information Regarding Revision 9 to Security Plant, Training & Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installa Project stage: RAI ML12297A3602012-11-0101 November 2012 Request for Additional Information, Review of Revision 14 of the Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan Project stage: RAI ML12300A0372012-11-0505 November 2012 Request for Additional Information Regarding Physical Security Plan, Training and Qualifications Plan, Safeguards Contingency Plan and Independent Spent Fuel Storage Installation Security Program Project stage: RAI ML12300A3222012-11-0505 November 2012 Redacted Letter Only, Request for Additional Information Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan (TAC D91660) Project stage: RAI ML12307A3692012-11-0707 November 2012 Request for Additional Information Regarding Revision 18 to the Physical Security Plan (TAC No. D91660) Project stage: RAI ML12310A0292012-11-16016 November 2012 Request for Additional Information Related to Physical Security Plan, Revision 16 Project stage: RAI ML12314A3562012-11-20020 November 2012 Request for Additional Information, Round 2, Changes to Callaway Physical Security Plan (TAC No. D91660) Project stage: RAI ML12335A0112012-11-28028 November 2012 Response to Request for Additional Information Regarding Review of Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 14 Project stage: Response to RAI ML12347A3022012-12-12012 December 2012 Email, Request for Additional Information on Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 15, (TAC No. D91660) Project stage: RAI ML12341A1592012-12-18018 December 2012 Request for Additional Information Regarding Physical Security Plan, Training Qualifications Plan, and Safeguards Contingency Security Program Revision 15 Project stage: RAI ML13002A0352012-12-19019 December 2012 Response to Request for Additional Information Regarding Revision 9 to the Wolf Creek Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan Project stage: Response to RAI ML12356A2182012-12-21021 December 2012 Email, Request for Additional Information Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 14 (TAC No. D91660) Project stage: RAI ML13010A5522013-01-16016 January 2013 Request for Additional Information Regarding Revision 18 to the Physical Security Plan Project stage: RAI ML13010A5512013-01-16016 January 2013 Request for Additional Information Regarding Revision 18 to the Physical Security Plan (TAC No. D91660) Project stage: RAI ML13023A4072013-01-23023 January 2013 Request for Additional Information Email, Review of Physical Security Plan (Psp), Training and Qualification Plan (T&Qp), and Safeguards Contingency Plan (Scp), Revision 7 Project stage: RAI ULNRC-05954, Response to Request for Additional Information Changes to Physical Security Plan (TAC No. D91660)2013-01-28028 January 2013 Response to Request for Additional Information Changes to Physical Security Plan (TAC No. D91660) Project stage: Response to RAI ML13029A7132013-01-29029 January 2013 Email, Request for Additional Information, Revision 13 to Physical Security, Safeguards Contingency, and Training and Qualification Plan (TAC No. D91660) Project stage: RAI ML13077A3372013-03-18018 March 2013 Email, Request for Additional Information, Physical Security Plan (Psp), Training and Qualification Plan (T&Qp), and Safeguards Contingency Plan (Scp), Revision 14 (TAC D91660) Project stage: RAI ML13120A0832013-03-22022 March 2013 Request for Additional Information Email Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 20 (TAC No. D91660) Project stage: RAI ML13120A0842013-03-22022 March 2013 Request for Additional Information Email Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 20 (TAC No. D91660) Project stage: RAI ML13165A3442013-06-12012 June 2013 Revision 15 of the ANO Security Plan Project stage: Request ML13165A0842013-06-13013 June 2013 Request for Additional Information Email Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 21 (TAC No. D91660) Project stage: RAI ML13116A3702013-07-12012 July 2013 (Redacted) Review of Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 10 (TAC No. D91660) Project stage: Approval ML13116A0942013-07-12012 July 2013 (Redacted) Review of Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 9 (TAC No. D91660) Project stage: Approval ML13116A3912013-07-12012 July 2013 (Redacted) Review of Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 17 (TAC No. D91660) Project stage: Approval ML13120A2322013-07-18018 July 2013 (Redacted) Review of Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, Revisions 14 and 15 (TAC D91660) Project stage: Approval ML13275A3102013-11-25025 November 2013 Cover Memo from Robert Caldwell to Robert Pascarelli, RAI for V C Summer Revision 10 Security Plan Review Project stage: RAI 2012-07-26
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24030A0672024-01-26026 January 2024 Email EA Fonsi Notice to Kewaunee Solutions for Exemptions on Site Restoration Activities ML23268A4362023-09-21021 September 2023 Extension Date Approval for Request for Additional Information for Exemptions on Site Restoration Activities ML23134A0012023-05-0909 May 2023 NRC Email Acceptance - Kewaunee Solutions Exemption Request Regarding Decommissioning Trust Funds for Site Restoration Activities (Docket No. 50-305) ML23129A0672023-05-0505 May 2023 NRC Email Acceptance - Kewaunee Solutions Exemption Request for Low-Level Radioactive Waste Transport Change from 20 to 45 Days Acknowledgement ML23100A0032023-04-0404 April 2023 Solutions - Acknowledgement Email Regarding Exemption Regarding Decommissioning Trust Funds for Site Restoration Activities (Docket No 50-305) ML23094A1442023-03-31031 March 2023 Solutions - Acknowledgement Email Regarding Exemption for Low-Level Radioactive Waste Transport within 20 Days (Docket No. 50-305) ML22108A1762022-04-14014 April 2022 E-mail: Proposed Order Conditions for In-Direct Transfer of Licenses Held by Energysolutions, LLC (Zion, TMI Unit-2, La Crosse Boiling Water Reactor, Kewaunee, Energysolutions Radioactive Materials License, and Energysolutions Export Licens ML22053A2992022-02-18018 February 2022 Email - Additional Time for Request for Additional Information Response Regarding Kewaunee Solutions Decommissioning Quality Assurance Program; NRC Response Included; (EPID L-2021-LLO-0002 and L-2021-DP3-0000) ML22027A3642022-01-26026 January 2022 KPS: CY2022 Inspection Plan, Docket No. 05000305, License No. DPR-43 ML22007A3182022-01-0707 January 2022 E-mail from C. Adams, State of Wisconsin, to K. Sturzebecher, NRC, Notification and Request Kewaunee Power Station License Transfer (L-2021-LLO-002) ML21348A0522021-12-0303 December 2021 E-mail to P. Schmidt, State of Wisconsin, from K. Sturzebecher, NRC - Notification and Request Kewaunee Power Station License Transfer ML21096A1332021-04-0606 April 2021 E-mail for Approval of Proprietary Withholding for Dominion Energy Exemptions for the Magnastor Storage Cask ML20015A3002020-01-14014 January 2020 KPS: CY2020 Master Inspection Plan ML19130A2082019-05-0808 May 2019 Email - NRC Email to FEMA Dated May 8, 2019: NRC Response to Comment on FEMA Review of Proposed Changes to DBNPS Emergency Plan for Permanently Defueled Condition ML19072A0652019-03-0606 March 2019 Conversation Record with T. Szymanski/Dominion Energy Response to 10 CFR 72.30(c)(3) in Triennial Update for Kewaunee ML19070A2642019-03-0505 March 2019 Email Conversation with T. Szymanski/Dominion Energy Decommissioning Funding Plan (Dfp): Kewaunee ML18351A2742018-12-17017 December 2018 KPS: CY2019 Master Inspection Plan ML17354A9382017-12-20020 December 2017 CY2018 Master Inspection Plan ML17156A0032017-06-0202 June 2017 NRR E-mail Capture - Acceptance for Review of Revision 24 to the Dominion Nuclear Facility Quality Assurance Program Description (QAPD) Topical Report (CAC Nos. MF9732-MF9739) ML17040A0222016-10-18018 October 2016 Wisconsin State Notification (LAR259-L53082) ML16287A7142016-10-13013 October 2016 E-mail - Request for Additional Information: Dominion Energy Kewaunee, Dominion Nuclear Connecticut and Virginia Electric Power Company Nuclear Facility Quality Assurance Program Description Topical Report ML16041A2732016-02-10010 February 2016 Final RAIs Regarding LAR 259 ML16054A2382015-10-14014 October 2015 E-44108 Attachment 8 E-mail from Stewart J. Yuen (Kewaunee Power Station) to Don Shaw (Areva) for Kewaunee Power Station ML15090A4872015-03-26026 March 2015 OEDO-15-00251 - Michael Mulligan, Citizen Ltr 2.206 - Emergency Ultrasonic Inspection Test or Best Available Flaw Detection Technology for USA Reactor Plants Similar to the Thousands of Cracks Discovered in Belgium Nuclear Power Plants ML15071A2752015-03-12012 March 2015 NRR E-mail Capture - Request for Additional Information on Kewaunee 50.54(p) Changes to Physical Security Plan - TAC MF5779 ML15057A2192015-02-25025 February 2015 NRR E-mail Capture - Acceptance Review: Dominion Fleet-Request for Approval of Cyber Security Plan (CSP) Revised Implementation Schedule ML14258A7432014-09-0505 September 2014 NRR E-mail Capture - FW: Comparison of Crystal River'S Exemption Secy Paper with Kewaunee'S ML14251A0972014-08-22022 August 2014 NRR E-mail Capture - Draft RAI to Kewaunee Power Station on Control Room Staffing Issue ML14164A0742014-06-0202 June 2014 NRR E-mail Capture - Draft Request for Additional Information Concerning Dek'S Request for Exemption from Conducting Annual Force-on-Force Exercises at Kewaunee Power Station ML14132A2062014-04-27027 April 2014 NRR E-mail Capture - Kewaunee Amendment Request for Emergency Plan Changes MF3411 - Draft RAIs ML14134A5872014-04-0707 April 2014 NRR E-mail Capture - Minor Editorial/Typographical Changes to License Condition TAC MF1771) ML14155A0402014-04-0707 April 2014 NRR E-mail Capture - Summarry of Kewaunee Mitigation Strategy Phone Call Last Week ML14097A5112014-04-0101 April 2014 NRR E-mail Capture - Draft RAI Related to Kewaunee Proposed Deletion of License Condition on Mitigation Strategy ML14069A3832014-03-0606 March 2014 NRR E-mail Capture - Draft RAI on Kewaunee Permanently Defueled Technical Specifications ML13312A2422013-11-0707 November 2013 NRR E-mail Capture - MF1952-RAII-SRXB-Cunana-002-2011-11-08, Request for Additional Information ML13297A0482013-10-23023 October 2013 NRR E-mail Capture - MF2567 - Kewaunee Eplan RAI #1 and Comparable Wording from Other Eplans ML13295A5672013-10-22022 October 2013 NRR E-mail Capture - MF2567 Kewaunee Exemption Nlar 102 (50.47 and 10 CFR Appendix E) Includes Kewaunee EP Briefing - 19 June 2013 Handout ML13275A0722013-10-0101 October 2013 NRR E-mail Capture - FW: MF1771-MF1952 RAI 9-27-2013.docx ML13275A0772013-10-0101 October 2013 NRR E-mail Capture - MF2743-RAII-AHPB-Keefe-001-2013-10-01 Request for Additional Information ML13275A0622013-09-27027 September 2013 NRR E-mail Capture - FW: MF2370 - Review of Training Plan for Certified Fuel Handler (CFH) Training - (Corrected) Request for Additional Information (RAI) ML13246A0032013-08-30030 August 2013 NRR E-mail Capture - Record of Docketing of Certifications Pertaining to Decommissioning of Kewaunee Power Station (KPS) ML13218B3722013-08-0606 August 2013 NRR E-mail Capture - MF1952 KPS Permanently Defueled License and TS - Request for Additional Information - MF1952-RAII-SCVB-Heida-001-2013-08-06 ML13186A0212013-07-0303 July 2013 NRR E-mail Capture - MF1771 - Correction to Stated Date Due for Request for Information Dated 6/26/2013 (ML13178A011) ML13178A0112013-06-26026 June 2013 NRR E-mail Capture - MF1771 (and Part of MF1952) - KPS - Record of Clarification Call and Associated Request for Additional Information (RAI) Deletion of License Condition 2.C.(15) ML13151A2452013-05-29029 May 2013 NRR E-mail Capture - Kewaunee Correspondence - Dispositioning Flawed Document, Summary of Facility Changes, Tests and Experiments and Summary of Commitment Changes ML13149A0412013-05-28028 May 2013 NRR E-mail Capture - MF1771 - Kewaunee LAR 255 Deletion of Licensing Condition 2.C.(15) - LIC-109 Acceptance Review Results ML13144A1002013-05-23023 May 2013 NRR E-mail Capture - Record of Docketing of Outgoing NRC Correspondence Serial No. 13-293: Certification of Permanent Removal of Fuel -- Confirming Successful EIE Docketing ML13134A5272013-05-14014 May 2013 NRR E-mail Capture - ML13133A086 = MF1438 - KPS - Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 50.75(h)(1)(iv) - Acceptance Review Results ML13133A0862013-05-10010 May 2013 NRR E-mail Capture - FW: MF1438 KPS - Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 50.75(h)(1)(iv) - Acceptance Review Results ML13128A3612013-05-0707 May 2013 NRR E-mail Capture - MD7112 - Record of Permanent Cessation of Operations 10CFR50.4(b)(8), 10CFR50.82, and the Scheduling of Certain Future Decommissioning Events 2024-01-26
[Table view] |
Text
NRR-PMDAPEm Resource From: Feintuch, Karl Sent: Friday, October 05, 2012 2:07 PM To: 'margaret.earle@dom.com' Cc: Sreenivas, V; Kim, James; Cotton, Karen; Costa, Richard
Subject:
(D91660) Request for Additional Information (RAI) draft questions Re: corporate security plans submitted 7/30/2012 Attachments: MExxxx Ke and Fleet Sec Plan Draft RAI Questions.pdf By letter dated July 30, 2012 (Agencywide Documents Access and Management System Accession No. ML12214A581), Dominion Generation, submitted Dominions Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 15 for the Kewaunee Power Station. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure.
The Reactor Security Licensing Branch (RSLB) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations, Section 50.54(p)(2). The RSLB staff has determined that additional information is necessary to complete its review.
The Request for Additional Information (RAI) items are attached. The attachment is identical to that sent to you informally in an email message dated October 4, 2012.
A clarification conference call to discuss these questions is scheduled on October 10, 2012, at 1:30 PM ET.
You have received RAI questions for other Dominion fleet plants. At the meeting a collective response schedule will be discussed appropriate to the corporate structure of your security plans. V. Sreenivas will be conducting the conference call on October 10, 2012.
Karl Feintuch 301-414-3079 USNRC PM for Kewaunee Power Station PM, Dominion Fleet 1
Hearing Identifier: NRR_PMDA Email Number: 500 Mail Envelope Properties (Karl.Feintuch@nrc.gov20121005140600)
Subject:
(D91660) Request for Additional Information (RAI) draft questions Re: corporate security plans submitted 7/30/2012 Sent Date: 10/5/2012 2:06:51 PM Received Date: 10/5/2012 2:06:00 PM From: Feintuch, Karl Created By: Karl.Feintuch@nrc.gov Recipients:
"Sreenivas, V" <V.Sreenivas@nrc.gov>
Tracking Status: None "Kim, James" <James.Kim@nrc.gov>
Tracking Status: None "Cotton, Karen" <Karen.Cotton@nrc.gov>
Tracking Status: None "Costa, Richard" <Richard.Costa@nrc.gov>
Tracking Status: None
"'margaret.earle@dom.com'" <margaret.earle@dom.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 1352 10/5/2012 2:06:00 PM MExxxx Ke and Fleet Sec Plan Draft RAI Questions.pdf 65068 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
NSIR REVIEW - TAC D91660 10 CFR 50.54(p)(2) CHANGES TO SECURITY PLAN DOMINION ENERGY KEWAUNEE, INC KEWAUNEE POWER STATION DOCKET NO. 50-305 LICENSE NO. DPR-43 By letter dated July 30, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12214A581), Dominion Generation, submitted Dominions Physical Security Plan (PSP), Training and Qualification Plan (T&QP), and Safeguards Contingency Plan (SCP), Revision 15 for the Kewaunee Power Station. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure. The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(p)(2). The NRC staff has determined that the additional information requested below is needed to complete its review.
- 1. Section 15.1 of the PSP describes illumination at the site. Describe the type of alternative technology being implemented at the protected area perimeter to augment illumination. Describe how the alternative technology provides the capability to perform protected area perimeter assessment in no-light or low-light conditions and specifically during the loss of normal power. Describe how the alternative technology is integrated within the protected area perimeter intrusion detection and assessment systems to meet the requirements of 10 CFR 73.55(e)(7)(i)(C), 73.55(i)(2), and 73.55(i)(3)(vii). See Security Frequently Asked Question (SFAQ) 10-15. Additionally, appropriate changes should be made during the next revision of the sites PSP to ensure the language clearly describes the type(s) of technology used to augment illumination for the assessment of the PA perimeter in no-light or low light conditions and during the loss of normal power, and how the technology meets the requirements of 10 CFR 73.55(e)(7)(i)(C), 73.55(i)(2),
and 73.55(i)(3)(vii).
Regulatory Basis:
Consistent with 10 CFR 73.55(c)(3), the licensee shall establish, maintain, and implement a Physical Security Plan which describes how the performance objective and requirements set forth in this section will be implemented.
Consistent with10 CFR 73.55(e)(7)(i)(C), isolation zones shall be monitored with assessment equipment designed to satisfy the requirements of Section 73.55(i) and provide real-time and play- back/recorded video images of the detected activities before and after each alarm annunciation.
Enclosure
Consistent with 10 CFR 73.55(i)(2), intrusion detection equipment must annunciate and video assessment equipment shall display concurrently, in at least two continuously staffed onsite alarm stations, at least one of which must be protected in accordance with the requirements of the central alarm station within this section.
Consistent with 10 CFR 73.55(i)(3)(vii), the licensees intrusion detection and assessment systems must be designed to ensure intrusion detection and assessment equipment at the protected area perimeter remains operable from an uninterruptible power supply in the event of the loss of normal power.
Consistent with 10 CFR 73.55(i)(6)(iii), the licensee shall describe in the security plans how the lighting requirements of this section are met and, if used, the type(s) and application of low-light technology.
- 2. Section 15.1 of the PSP describes illumination for all the Dominion sites. The last paragraph of Section 15.1 describes a loss of power scenario that seems to apply to all sites. In Section 7 of the SCP, on page C-28, the description for loss of power scenario is described differently for Kewaunee than in Section 15.1 of the PSP.
These descriptions seem to be contradictory. Clarify how Kewaunee Power Station meets the illumination requirements of 10 CFR 73.55(i)(6) in a loss of power scenario. Additionally, appropriate changes should be made during the next revision of the sites PSP and SCP to ensure the language is consistent and clearly describes the effect of a loss of power on illumination at Kewaunee Power Station.
Regulatory Basis:
Consistent with 10 CFR 73.55(c)(3), the licensee shall establish, maintain, and implement a Physical Security Plan which describes how the performance objective and requirements set forth in this section will be implemented.
Consistent with 10 CFR 73.55(i)(6)(i), the licensee shall ensure that all areas of the facility are provided with illumination necessary to satisfy the design requirements of Section 73.55(b) and implement the protective strategy.
Consistent with 10 CFR 73.55(i)(6)(ii), the licensee shall provide a minimum of 0.2 foot-candles, measured horizontally at ground level, in the isolation zones and appropriate exterior areas within the protected area. Alternatively, the licensee may augment the facility illumination system by means of low-light technology to meet the requirements of this section or otherwise implement the protective strategy.
Consistent with 10 CFR 73.55(i)(6)(iii), the licensee shall describe in the security plans how the lighting requirements of this section are met and, if used, the type(s) and application of low-light technology.