NRR E-mail Capture - Acceptance for Review of Revision 24 to the Dominion Nuclear Facility Quality Assurance Program Description (QAPD) Topical Report (CAC Nos. MF9732-MF9739)
ML17156A003
Person / Time
Site: Millstone, Kewaunee, Surry, North Anna  Dominion icon.png
Issue date: 06/02/2017
From: Randy Hall
Plant Licensing Branch II
To: Sly C
Dominion Generation
References
MF9732, MF9733, MF9734, MF9735, MF9736, MF9737, MF9738, MF9739
Download: ML17156A003 (3)


Text

1 NRR-PMDAPEm Resource From:

Hall, Randy Sent:

Friday, June 02, 2017 11:11 AM To:

Craig.Sly@dom.com Cc:

Diane Aitken (Generation - 6); Tom.Huber@dom.com; Margaret.Earle@dom.com; Kavanagh, Kerri; Ferguson, Ashley

Subject:

Acceptance for Review of Revision 24 to the Dominion Nuclear Facility Quality Assurance Program Description (QAPD) Topical Report (CAC Nos. MF9732-MF9739)

June 2, 2017 Mr. Craig Sly Manager, Nuclear Regulatory Affairs Virginia Electric and Power Company

Dear Mr. Sly,

By letter dated April 11, 2017 (Agencywide Documents Access and Management System Accession No. ML17108A334), Dominion Energy Kewaunee, Inc., Dominion Nuclear Connecticut, Inc., and Virginia Electric and Power Company (Dominion, the licensee) submitted for the U.S. Nuclear Regulatory Commission (NRC) staffs review and approval, Revision 24 to the Nuclear Facility Quality Assurance Program Description (QAPD)

Topical Report. Dominions application states that the proposed changes are applicable only to the North Anna and Surry Power Stations, and that the revision would add an exception to ANSI/ANS 3.1 (12/79 Draft) for conducting annual training of non-licensed plant staff. Dominion has submitted the proposed revision for NRC approval in accordance with 10 CFR 50.54(a)(4), as the proposed changes would reduce commitments to the previously accepted QAPD.

The purpose of this email is to provide the results of the NRC staffs acceptance review of this quality assurance program description change request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed change in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 120 hours0.00139 days <br />0.0333 hours <br />1.984127e-4 weeks <br />4.566e-5 months <br /> to complete. The NRC staff expects to complete this review in approximately 8 months, which is January 31, 2018. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors, including requests for additional information or unanticipated addition of scope to the review.

2 If you have any questions, please contact me at (301) 415-4032.

Sincerely, Randy Hall, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation USNRC (301) 415-4032 Randy.Hall@nrc.gov

Hearing Identifier:

NRR_PMDA Email Number:

3550 Mail Envelope Properties (Randy.Hall@nrc.gov20170602111000)

Subject:

Acceptance for Review of Revision 24 to the Dominion Nuclear Facility Quality Assurance Program Description (QAPD) Topical Report (CAC Nos. MF9732-MF9739)

Sent Date:

6/2/2017 11:10:59 AM Received Date:

6/2/2017 11:10:00 AM From:

Hall, Randy Created By:

Randy.Hall@nrc.gov Recipients:

"Diane Aitken (Generation - 6)" <diane.aitken@dom.com>

Tracking Status: None "Tom.Huber@dom.com" <Tom.Huber@dom.com>

Tracking Status: None "Margaret.Earle@dom.com" <Margaret.Earle@dom.com>

Tracking Status: None "Kavanagh, Kerri" <Kerri.Kavanagh@nrc.gov>

Tracking Status: None "Ferguson, Ashley" <Ashley.Ferguson@nrc.gov>

Tracking Status: None "Craig.Sly@dom.com" <Craig.Sly@dom.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 3393 6/2/2017 11:10:00 AM Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received: