Category:E-Mail
MONTHYEARML24030A0672024-01-26026 January 2024 Email EA Fonsi Notice to Kewaunee Solutions for Exemptions on Site Restoration Activities ML23268A4362023-09-21021 September 2023 Extension Date Approval for Request for Additional Information for Exemptions on Site Restoration Activities ML23134A0012023-05-0909 May 2023 NRC Email Acceptance - Kewaunee Solutions Exemption Request Regarding Decommissioning Trust Funds for Site Restoration Activities (Docket No. 50-305) ML23129A0672023-05-0505 May 2023 NRC Email Acceptance - Kewaunee Solutions Exemption Request for Low-Level Radioactive Waste Transport Change from 20 to 45 Days Acknowledgement ML23100A0032023-04-0404 April 2023 Solutions - Acknowledgement Email Regarding Exemption Regarding Decommissioning Trust Funds for Site Restoration Activities (Docket No 50-305) ML23094A1442023-03-31031 March 2023 Solutions - Acknowledgement Email Regarding Exemption for Low-Level Radioactive Waste Transport within 20 Days (Docket No. 50-305) ML22108A1762022-04-14014 April 2022 E-mail: Proposed Order Conditions for In-Direct Transfer of Licenses Held by Energysolutions, LLC (Zion, TMI Unit-2, La Crosse Boiling Water Reactor, Kewaunee, Energysolutions Radioactive Materials License, and Energysolutions Export Licens ML22053A2992022-02-18018 February 2022 Email - Additional Time for Request for Additional Information Response Regarding Kewaunee Solutions Decommissioning Quality Assurance Program; NRC Response Included; (EPID L-2021-LLO-0002 and L-2021-DP3-0000) ML22027A3642022-01-26026 January 2022 KPS: CY2022 Inspection Plan, Docket No. 05000305, License No. DPR-43 ML22007A3182022-01-0707 January 2022 E-mail from C. Adams, State of Wisconsin, to K. Sturzebecher, NRC, Notification and Request Kewaunee Power Station License Transfer (L-2021-LLO-002) ML21348A0522021-12-0303 December 2021 E-mail to P. Schmidt, State of Wisconsin, from K. Sturzebecher, NRC - Notification and Request Kewaunee Power Station License Transfer ML21096A1332021-04-0606 April 2021 E-mail for Approval of Proprietary Withholding for Dominion Energy Exemptions for the Magnastor Storage Cask ML20015A3002020-01-14014 January 2020 KPS: CY2020 Master Inspection Plan ML19130A2082019-05-0808 May 2019 Email - NRC Email to FEMA Dated May 8, 2019: NRC Response to Comment on FEMA Review of Proposed Changes to DBNPS Emergency Plan for Permanently Defueled Condition ML19072A0652019-03-0606 March 2019 Conversation Record with T. Szymanski/Dominion Energy Response to 10 CFR 72.30(c)(3) in Triennial Update for Kewaunee ML19070A2642019-03-0505 March 2019 Email Conversation with T. Szymanski/Dominion Energy Decommissioning Funding Plan (Dfp): Kewaunee ML18351A2742018-12-17017 December 2018 KPS: CY2019 Master Inspection Plan ML17354A9382017-12-20020 December 2017 CY2018 Master Inspection Plan ML17156A0032017-06-0202 June 2017 NRR E-mail Capture - Acceptance for Review of Revision 24 to the Dominion Nuclear Facility Quality Assurance Program Description (QAPD) Topical Report (CAC Nos. MF9732-MF9739) ML17040A0222016-10-18018 October 2016 Wisconsin State Notification (LAR259-L53082) ML16287A7142016-10-13013 October 2016 E-mail - Request for Additional Information: Dominion Energy Kewaunee, Dominion Nuclear Connecticut and Virginia Electric Power Company Nuclear Facility Quality Assurance Program Description Topical Report ML16041A2732016-02-10010 February 2016 Final RAIs Regarding LAR 259 ML16054A2382015-10-14014 October 2015 E-44108 Attachment 8 E-mail from Stewart J. Yuen (Kewaunee Power Station) to Don Shaw (Areva) for Kewaunee Power Station ML15090A4872015-03-26026 March 2015 OEDO-15-00251 - Michael Mulligan, Citizen Ltr 2.206 - Emergency Ultrasonic Inspection Test or Best Available Flaw Detection Technology for USA Reactor Plants Similar to the Thousands of Cracks Discovered in Belgium Nuclear Power Plants ML15071A2752015-03-12012 March 2015 NRR E-mail Capture - Request for Additional Information on Kewaunee 50.54(p) Changes to Physical Security Plan - TAC MF5779 ML15057A2192015-02-25025 February 2015 NRR E-mail Capture - Acceptance Review: Dominion Fleet-Request for Approval of Cyber Security Plan (CSP) Revised Implementation Schedule ML14258A7432014-09-0505 September 2014 NRR E-mail Capture - FW: Comparison of Crystal River'S Exemption Secy Paper with Kewaunee'S ML14251A0972014-08-22022 August 2014 NRR E-mail Capture - Draft RAI to Kewaunee Power Station on Control Room Staffing Issue ML14164A0742014-06-0202 June 2014 NRR E-mail Capture - Draft Request for Additional Information Concerning Dek'S Request for Exemption from Conducting Annual Force-on-Force Exercises at Kewaunee Power Station ML14132A2062014-04-27027 April 2014 NRR E-mail Capture - Kewaunee Amendment Request for Emergency Plan Changes MF3411 - Draft RAIs ML14155A0402014-04-0707 April 2014 NRR E-mail Capture - Summarry of Kewaunee Mitigation Strategy Phone Call Last Week ML14134A5872014-04-0707 April 2014 NRR E-mail Capture - Minor Editorial/Typographical Changes to License Condition TAC MF1771) ML14097A5112014-04-0101 April 2014 NRR E-mail Capture - Draft RAI Related to Kewaunee Proposed Deletion of License Condition on Mitigation Strategy ML14069A3832014-03-0606 March 2014 NRR E-mail Capture - Draft RAI on Kewaunee Permanently Defueled Technical Specifications ML13312A2422013-11-0707 November 2013 NRR E-mail Capture - MF1952-RAII-SRXB-Cunana-002-2011-11-08, Request for Additional Information ML13297A0482013-10-23023 October 2013 NRR E-mail Capture - MF2567 - Kewaunee Eplan RAI #1 and Comparable Wording from Other Eplans ML13295A5672013-10-22022 October 2013 NRR E-mail Capture - MF2567 Kewaunee Exemption Nlar 102 (50.47 and 10 CFR Appendix E) Includes Kewaunee EP Briefing - 19 June 2013 Handout ML13275A0772013-10-0101 October 2013 NRR E-mail Capture - MF2743-RAII-AHPB-Keefe-001-2013-10-01 Request for Additional Information ML13275A0722013-10-0101 October 2013 NRR E-mail Capture - FW: MF1771-MF1952 RAI 9-27-2013.docx ML13275A0622013-09-27027 September 2013 NRR E-mail Capture - FW: MF2370 - Review of Training Plan for Certified Fuel Handler (CFH) Training - (Corrected) Request for Additional Information (RAI) ML13246A0032013-08-30030 August 2013 NRR E-mail Capture - Record of Docketing of Certifications Pertaining to Decommissioning of Kewaunee Power Station (KPS) ML13218B3722013-08-0606 August 2013 NRR E-mail Capture - MF1952 KPS Permanently Defueled License and TS - Request for Additional Information - MF1952-RAII-SCVB-Heida-001-2013-08-06 ML13186A0212013-07-0303 July 2013 NRR E-mail Capture - MF1771 - Correction to Stated Date Due for Request for Information Dated 6/26/2013 (ML13178A011) ML13178A0112013-06-26026 June 2013 NRR E-mail Capture - MF1771 (and Part of MF1952) - KPS - Record of Clarification Call and Associated Request for Additional Information (RAI) Deletion of License Condition 2.C.(15) ML13151A2452013-05-29029 May 2013 NRR E-mail Capture - Kewaunee Correspondence - Dispositioning Flawed Document, Summary of Facility Changes, Tests and Experiments and Summary of Commitment Changes ML13149A0412013-05-28028 May 2013 NRR E-mail Capture - MF1771 - Kewaunee LAR 255 Deletion of Licensing Condition 2.C.(15) - LIC-109 Acceptance Review Results ML13144A1002013-05-23023 May 2013 NRR E-mail Capture - Record of Docketing of Outgoing NRC Correspondence Serial No. 13-293: Certification of Permanent Removal of Fuel -- Confirming Successful EIE Docketing ML13134A5272013-05-14014 May 2013 NRR E-mail Capture - ML13133A086 = MF1438 - KPS - Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 50.75(h)(1)(iv) - Acceptance Review Results ML13133A0862013-05-10010 May 2013 NRR E-mail Capture - FW: MF1438 KPS - Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 50.75(h)(1)(iv) - Acceptance Review Results ML13128A3612013-05-0707 May 2013 NRR E-mail Capture - MD7112 - Record of Permanent Cessation of Operations 10CFR50.4(b)(8), 10CFR50.82, and the Scheduling of Certain Future Decommissioning Events 2024-01-26
[Table view] Category:Inspection Plan
MONTHYEARML22027A3642022-01-26026 January 2022 KPS: CY2022 Inspection Plan, Docket No. 05000305, License No. DPR-43 ML17354A9382017-12-20020 December 2017 CY2018 Master Inspection Plan ML16356A6032016-12-21021 December 2016 Master Inspection Plan Calendar Year 2017 ML15357A1902015-12-21021 December 2015 Master Inspection Plan - Calendar Year 2016 ML14353A4082014-12-18018 December 2014 Master Inspection Plan - Calendar Year 2015 IR 05000305/20120012013-03-0404 March 2013 Annual Assessment Letter for Kewaunee Power Station (Report 05000305/2012001) ML12277A1642012-09-27027 September 2012 Response to Request for Additional Information on Reactor Vessel Internals Inspection Plan Review Request ML12249A4192012-09-0404 September 2012 Mid-Cycle Assessment Letter for Kewaunee Power Station IR 05000305/20110062011-09-0101 September 2011 Mid-Cycle Letter for Kewaunee Power Station; 05000305-11-006 IR 05000305/20110012011-03-0404 March 2011 Annual Assessment Letter for Kewaunee Power Station (05000305-11-001) ML1024400582010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Kewaunee Power Station IR 05000305/20100012010-03-0303 March 2010 Kewaunee Power Station EOC Annual Assessment Letter (Report 05000305-10-001) ML0924402722009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan IR 05000305/20090012009-03-0404 March 2009 Annual Assessment Letter, Kewaunee (IR 05000305-09-001) ML0824602762008-09-0202 September 2008 Kewaunee - Mid-Cycle Performance Review and Inspection Plan ML0735403332007-12-19019 December 2007 Change to the Inspection Plan 1/1/08 - 12/31/08 ML0724304312007-08-31031 August 2007 8/31/07 Kewaunee - Mid-Cycle Performance Review and Inspection Plan ML0707103942007-03-12012 March 2007 Document Request Letter for PI&R Inspection IR 05000305/20070012007-03-0202 March 2007 EOC Annual Assessment Letter (Report 05000305-07-001) ML0705701322007-01-18018 January 2007 Inspection Plan Kewaunee IR 05000305-07-006 (DRS) ML0703102502007-01-18018 January 2007 IR 05000305-07-006, Kewaunee Power, Inspection Plan ML0624303402006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan IR 05000305/20060012006-03-0202 March 2006 (EOC) Annual Assessment Letter (Report 05000305/2006001) ML0524202512005-08-30030 August 2005 Mid-Cycle Performance Review and Inspection Plan - Kewaunee Power Station ML0506204232005-03-0202 March 2005 Annual Assessment Letter - Kewaunee, 03/02/05 ML0424505152004-08-30030 August 2004 Mid-cycle Performance Review and Inspection Plan - Kewaunee Nuclear Power Plant ML0406411582004-03-0404 March 2004 End-of-Cycle Letter IR 05000305/20040012003-08-27027 August 2003 IR 05000305-04-001 - Mid-Cycle Assessment Letter IR 05000305/20030012003-03-0404 March 2003 Annual Assessment Letter - Kewaunee (Report 05000305-03-001) ML0224002262002-08-22022 August 2002 Mid-Cycle Performance Review and Inspection Plan - Kewaunee Nuclear Power Plant (August 22, 2002) IR 05000305/20020012002-03-0404 March 2002 Annual Assessment Letter - Kewaunee Nuclear Plant (Report 50-305/02-01) 2022-01-26
[Table view] |
Text
Edwards, Rhex From: Edwards, Rhex Sent: Wednesday, December 20, 2017 12:17 PM To: William F Zipp
Subject:
KPS: CY2018 Master Inspection Plan
Dear Mr. Zipp,
In accordance with Inspection Manual Chapter (IMC) 2561, "Decommissioning Power Reactor Inspection Program," the NRC Region Ill staff developed a Master Inspection Plan (MIP) for the Kewaunee Power Station for calendar year 2018. The inspection plan is based on your current performance and your planned decommissioning activities for the site in January through December 2018. Below is a list of the periodic inspection procedures we expect to use during our inspections. The procedures used during each inspection will depend on the specific activities being conducted at the site. Additional discretionary inspection procedures may be used if decommissioning or ISFSI activities warrant. We will gladly discuss any questions you may have regarding this MIP. If you have questions, please contact me at (630) 829-9722. If you have questions related to security inspections, please contact the Plant Support Branch Chief at 630-829-9500.
Sincerely, Rhex Edwards Inspection Procedure (IP) Start Date End Date IP 36801: Organization, 10/01/2018 11/01/2018 Management, and Cost Control IP 37801: Safety Reviews, 10/01/2018 11/01/2018 Design Changes, and Modifications IP 40801: Self Assessment, 10/01/2018 11/01/2018 Audits, and CAP IP 83750: Occupational 02/01/2018 03/01/2018 Radiation Exposure IP 83801: Inspection of 10/01/2018 11/01/2018 Remedial and Final Surveys at Permanently Shutdown Reactors IP 84750: Radioactive Waste 02/01/2018 03/01/2018 Treatment, Effluent and Environmental Monitoring IP 86750: Waste Management 02/01/2018 03/01/2018 and Transportation Rhex Edwards Senior Health Physicist USNRC Region Ill 1
DNMS MCID 630-829-9722 2