|
|
Line 14: |
Line 14: |
| | document type = MEMORANDUMS-CORRESPONDENCE, STAFF REQUIREMENTS MEMORANDUMS | | | document type = MEMORANDUMS-CORRESPONDENCE, STAFF REQUIREMENTS MEMORANDUMS |
| | page count = 2 | | | page count = 2 |
| | | project = TAC:59787 |
| | | stage = Other |
| }} | | }} |
|
| |
|
Latest revision as of 04:38, 13 December 2021
Letter Sequence Other |
---|
|
Results
Other: ML20137H372, ML20137L926, ML20137Z363, ML20138B512, ML20138L407, ML20141E527, ML20141H534, ML20141H544, ML20141H549, ML20151R074, ML20154N150
|
MONTHYEARML20132E6081985-07-19019 July 1985 Supplemental Safety Evaluation Supporting Licensee CRD Mechanisms & Associated Position Instrumentation,Per 850712 Safety Evaluation & Licensee 850710 & 18 Submittals.Control Rod Program Acceptable for Plant Restart Project stage: Request ML20132F0231985-07-19019 July 1985 Forwards Safety Evaluation Re Environ Qualification of Electric Equipment Important to Safety & Authorizes Interim Operation in dry-out Mode at Max 15% of Rated Power,Based on Listed Conditions,Until Technical Review Completed Project stage: Approval ML20132F0721985-07-19019 July 1985 Safety Evaluation Documenting Deficiencies in Licensee Program for Environ Qualification of Electric Equipment Important to Safety.Licensee Response to Generic Ltr 84-24 Inadequate.However,Operation at 15% Power Authorized Project stage: Approval ML20134M0161985-08-20020 August 1985 Submits Discussion of Technical Issues Re Environ Qualification Program Raised During Meetings W/Nrc.Aging & Operability Time Program Operator Response Time,Temp Profiles & Shutdown Cooling Paths & Equipment Evaluated Project stage: Meeting IR 05000267/19850211985-08-30030 August 1985 Insp Rept 50-267/85-21 on 850721-31.No Violation or Deviation Noted.Major Areas Inspected:Operational Safety Verification Project stage: Request ML20137X1411985-09-30030 September 1985 Safety Evaluation Supporting Util 850830,0910,11 & 23 Requests for Authorization to Operate at Max 8% Power,For Up to 45 Days,To Remove Moisture from RCS Project stage: Approval ML20137X1241985-09-30030 September 1985 Forwards Safety Evaluation Based on Util 850830,0910,11 & 23 Requests for Authorization to Operate at Max 8% Power,For Up to 45 Days,To Remove Moisture from Rcs.Authorization Granted,Subj to Listed Commitments Project stage: Approval ML20138E3921985-10-11011 October 1985 Forwards Request for Addl Info on 850924 Request for Special Consideration & Schedule Extension to Equipment Qualification rule,10CFR50.49.Info Requested within 7 Days of Ltr Receipt Project stage: RAI ML20138C8111985-10-21021 October 1985 Forwards Response to 851011 Request for Addl Info Re 850924 Request for Schedule Extension for Environ Qualification Program Under 10CFR50.49 from 851130 to 860331 Project stage: Request ML20138R7331985-10-31031 October 1985 Summary of 851029 Meeting W/Util & ORNL Re Schedule Extension to Equipment Qualification Rule.List of Attendees, Agenda & Matls Presented by Util Encl Project stage: Meeting ML20209J0821985-11-0505 November 1985 Forwards Request for Addl Info Re Equipment Qualification Program & Request for Extension of Deadline for Compliance W/Equipment Qualification Rule,Per 851029 Meeting Project stage: RAI ML20136F6991985-11-19019 November 1985 Modifies Scheduled Commitment for Submittal of Final Draft Proposal of Upgraded Tech Specs for NRC Comment,Per 851008 Request.Revised Submittal Date of 851130 Approved.Revised Tabulation of Commitments Encl Project stage: Draft Other ML20136J1831985-11-21021 November 1985 Staff Requirements Memo Re Commission 851119 Meeting in Washington,Dc on Licensee Environ Qualification Exemption Request.Recommendation on Extension Request Should Be Provided by 851122 Project stage: Meeting ML20136J0151985-11-22022 November 1985 Notifies of Withdrawal of 850924 Schedule Extension Request for Environ Qualification Program.Approval of Revised Schedule Extension for Implementation of Program Beyond 851130 Under Provision of 10CFR50.49 Requested Project stage: Withdrawal ML20137H3721985-11-26026 November 1985 Memorandum & Order Granting Extension of 851130 Deadline for Environ Qualification of Electrical Equipment to 860531 & Approving Proposal to Allow Operation w/35% Reactor Power Limit During Interim.Served on 851127 Project stage: Other ML20137Z3631985-12-0505 December 1985 Staff Requirements Memo Re Affirmation/Discussion & Vote on Extension of 851130 Deadline for Environ Qualification & Revised Post 851130 Environ Qualification Extension Request Project stage: Other ML20138L4071985-12-10010 December 1985 Rev B to EE-EQ-0019, Engineering Evaluation of Liner Cooling W/Fire Water Following High Energy Line Break from 35% Power Operation at Fort St Vrain Project stage: Other ML20138B5121985-12-10010 December 1985 Forwards Evaluations to Document Completion of Confirmatory Actions Required to Support 35% Power Restriction During Environ Qualification Schedule Extension Period Project stage: Other ML20136C8221985-12-26026 December 1985 Forwards Request for Addl Info to Complete Resolution of Confirmatory Action 6 Re Insp of High Energy Piping.Concerns Include Potential for Inservice Degradation & Exam & Insp Methods Project stage: RAI ML20137L9261985-12-31031 December 1985 Heat Stress Mgt Program for Nuclear Power Industry, Interim Rept Project stage: Other ML20141E5271986-01-0303 January 1986 Forwards Summary of Position on Confirmatory Action 6 Re Insp of Critical Areas of High Energy Piping & Responses to Six Addl Info Requests.Limited Insp Plan Will Be Completed by Middle of Jan 1986.Drawings Encl Project stage: Other ML20141H5341986-01-0808 January 1986 Forwards NDE Procedures,Per DW Warembourg Project stage: Other ML20141H5441986-01-0808 January 1986 Issue 1 to NDE Procedure QCIM-38, Ultrasonic Exam of Class 1 & 2 Piping Welds Joining Similar & Dissimilar Matls Project stage: Other ML20141H5491986-01-0808 January 1986 Issue 5 to NDE Procedure QCIM-30, Radiographic Exam Procedure Project stage: Other ML20137M1091986-01-15015 January 1986 Forwards Addl Info to Support Util Intention to Use Ice Vests to Allow Personnel Access W/Elevated Bldg Temps. T Bernard Prof Opinion Documented in Encl Draft Heat Stress Mgt Program. Rept Available in Central Files Project stage: Draft Other ML20137L9001986-01-21021 January 1986 Forwards EPRI Interim Rept, Heat Stress Mgt Program for Nuclear Power Industry, to Replace Draft Transmitted by Walker ,To Support 35% Power Bldg Access.Rept Will Be Available in Mar as EPRI NP4453 Project stage: Draft Other ML20151R0741986-01-29029 January 1986 Informs That NRR Ltr to Licensee Summarizing Findings Re Environ Qualification Extension Sufficient to Authorize Limited Operation.No License Amend Required to Support Authorization Project stage: Other ML20154N1501986-03-0303 March 1986 Forwards Final Rept on Inservice Insp Program Performed on High Energy Piping.Program Inspected 35 Critical Areas of Piping Per Safety Evaluation of Confirmatory Item 6. Integrity Verified in Support of 35% Power Operation Project stage: Other 1985-12-31
[Table View] |
|
---|
Category:MEMORANDUMS-CORRESPONDENCE
MONTHYEARML20212G5351999-09-27027 September 1999 Forwards Signed Original Confirmatory Order (Effective Immediately)(Morrison Knudsen Corp,Cleveland,Oh) for Transmittal to Ofc of Fr for Publication.Without Encl ML20211A4361999-08-18018 August 1999 Notification of Significant Licensee Meeting 99-47 with Entergy Nuclear,Inc on 990831 to Discuss Results of NRC Plant Performance Review of Pilgrim Nuclear Power Station Issued on 990409 ML20212H7621999-06-22022 June 1999 Notification of 990701 Meeting with NEI & Entergy in Rockville,Md to Discuss Price-Anderson Issues Re Transfer of Pilgrim License from Beco to Entergy ML20205L0301999-04-0909 April 1999 Notification of 990413 Meeting with Boston Edison Co & Entergy Nuclear Generation Co in Rockville,Md to Discuss Sale & Transfer of Pilgrim Station from Boston Edison Co to Entergy Nuclear Generation Co ML20196J5801998-12-0707 December 1998 Notification of 981209 Meeting with Representatives of Beco & Entergy in Rockville,Md to Discuss Sale of Pilgrim Plant ML20196F5611998-12-0202 December 1998 Forwards Info Re OL Exam Administered on 981016-23 at Pilgrim Station,For Distribution Under Rids A070 ML20196F3461998-12-0202 December 1998 Forwards Info Re Operator Licensing Exam Administered on 981016-23 at Pilgrim Station,For Distribution Under Rids Code IE42 ML20154D5091998-10-0202 October 1998 Notification of Meeting W/Beco on 981008 in Rockville,Md to Discuss Core Spray Piping Integrity ML20154G5141998-10-0202 October 1998 Notification of 981008 Meeting W/Beco in Rockville,Md to Discuss Core Spray Piping Integrity.Meeting Has Been Rescheduled to 981015 ML20236W8131998-08-0404 August 1998 Forwards Regulatory Documents Comprising Regulatory History of Notice of Proposed RM Entitled Miscellaneous Changes to Licensing Requirements for Independent Storage of Spent Nuclear Fuel & HLW Which Amended 10CFR72 ML20247G2441998-04-15015 April 1998 Notification of Significant Licensee Meeting 98-34 W/Util on 980427 to Discuss Weaknesses in Licensee Alarm Assessment Program (EA 98-191) ML20203E2781998-02-19019 February 1998 Notification of Significant Licensee Meeting 98-18 W/Util in King of Prussia,Pa on 980310 Re Plant Design Basis Project Discussion ML20202D5011997-11-28028 November 1997 Forwards Table Summarizing Contractor Costs,Staff Hours & FTEs Expended in Removing Sites from Site Decommissioning Mgt Plan & Fsv & Shoreham Nuclear Power Facilities,In Response to C Paperiello 970605 Memorandum ML20199C7581997-10-31031 October 1997 Notification of Significant Licensee Meeting 97-112 W/Util on 971113 to Discuss NRC SALP ML20212D6201997-10-28028 October 1997 Notification of Licensee Meeting on 971121 W/Util in King of Prussia,Pa to Discuss Apparent Violations Identified During NRC Insp 50-293/97-05 ML20149H4801997-07-24024 July 1997 Staff Requirements Memo Re SECY-97-138, Termination of Fort St Vrain Nuclear Generating Station Ol ML20140F6151997-06-11011 June 1997 Notification of 970612 Meeting W/Util in Rockville,Md to Discuss Net Positive Suction Head for ECCS Pumps ML20141C8691997-05-0505 May 1997 Forwards Notice for Transmittal to Ofc of Fr Re Issuance of License Amend for Psc,Fort St Vrain Nuclear Generating Station Re Redesignated Approved Decommissioning Plan, & Approved Final Radiation Survey Plan ML20137Q9761997-03-31031 March 1997 Informs That as-found LOCA & Life Testing & Analysis Does Not Provide Acceptable Approach for Demonstrating Qualification at Accident Temp Higher than 340F,per 970110 TAR ML20137B4781997-03-14014 March 1997 Undated Memo Discussing Beco Reorganization ML20141A7361997-03-12012 March 1997 Rcommends That Key RES Staff Attend Subcommittee Meetings to Address Any Questions,Arise in Discussions Among Members & to Answer Any Key Questions Posed in Advance by Subcommittee Chairmen ML20136D6041997-03-0404 March 1997 Forwards Signed Original of FRN for Transmittal to Ofc of Federal Register for Publication ML20149M3291996-11-12012 November 1996 Forwards Input Re TIA on Plant Licensing Basis & Subsequent Mod Under 10CFR50.59 for Two Safety Significant Problems ML20129K2561996-11-0505 November 1996 Notification of Significant Licensee Meeting 96-109 W/Listed Attendees on 961202-03 in Philadelphia,Pa to Provide Training,Resolve Interagency Exercise Scheduling Conflicts & Discuss Current Issues in Emergency Preparedness ML20134G2511996-11-0505 November 1996 Forwards Notice of Forthcoming Meeting W/Psc on Decommissioning & License Termination of Fsv ML20134F8951996-11-0505 November 1996 Notification of 961203 Meeting W/Public Service Co of Co in Rockville,Md to Discuss Decommissioning & License Termination of Fort St Vrain ML20129D8331996-09-19019 September 1996 Notification of 961003 Predecisional Enforcement Conference 96-98 W/Util to Discuss Containment Penetration Protection. Meeting Closed to Public ML20236X0011996-09-12012 September 1996 Provides follow-up to Meeting Re Use of Natural or Depleted U in Storage Casks/Use of Neutron Absorbing Matls,In Order to Improve Basis & Shed Light on Direct Final Possibility ML20134J7301996-07-26026 July 1996 Forwards Resolution of Spent Fuel Storage Pool Action Plan Issues Re Response to Two Postulated Event Sequences Involving SFP ML20137H1331995-12-29029 December 1995 Responds to Request of 951108 for Investigative Assistance in Interviewing R Sawyer & K Zarht Re Alleged Discrimination & Wrongful Termination of Contractor Radiation Protection Technicians at Fort St Vrain,Oi Case A4-95-064 ML20137H2951995-11-21021 November 1995 Forwards Copies of Transcripts of R Sawyer & K Zarht Re Alleged Discrimination & Wrongful Termination of Contractor Radiation Protection Technicians Case A4-95-064.W/o Encls ML20136B2301995-11-17017 November 1995 Forwards Repy to NOV ML20136B1711995-08-31031 August 1995 Agrees W/Office of Enforcement Regional Approach ML20136B1831995-08-31031 August 1995 Discusses Proposed Meeting Re OI 4-95-015 ML20136B2121995-08-30030 August 1995 Confirms 950911 for OI Meeting Re OI 4-95-015 ML20136B1901995-08-30030 August 1995 Ack Receipt of Mail ML20137H2651995-08-25025 August 1995 Forwards Copy of OI Rept Where Investigation Did Substantiate That Seg Technician Deliberately Failed to Perform Response Checks in Accordance W/Procedures.W/O Encl ML20136B1661995-08-17017 August 1995 Forwards OI Rept of Investigation Re Alleged Falsification of Records.W/O Encl ML20136B2191995-08-0707 August 1995 Informs That Enforcement Action Will Be Required Re OI 4-95-015 Concerning Failure to Perform Response Checks ML20136B1581995-06-20020 June 1995 Requests That General Counsel Anlayze Rept & Determine Whether Sufficient Evidence Exists to Take EA Re Falsification of Records ML20137H2551995-06-0303 June 1995 Forwards Copy of OI Rept,Reviewing Licensee Investigation Rept & Confirmed Licensee Conclusions That Radiation Survey Records & Radiation Work Permits Falsified.W/O Encl ML20136B1471995-05-26026 May 1995 Forwards OI Rept of Investigation Re Alleged Falsification of Radiation Survey Records ML20137K0111995-04-20020 April 1995 Discusses Verbal DOJ Declination of Prosecution Re Public Svc Co of Colorado,For Plant ML20137K0611995-04-12012 April 1995 Documents Events Surrounding Discovery of Barrels Being Shipped from Plant to Richland Disposal Facility W/Different Radiation Exposure Readings than Were Listed on Shipping Manifest ML20137K0781995-04-12012 April 1995 Documents Events Surrounding Segs Placement of Problematic Radiation Protection Technician on Administrative Leave NUREG-1299, Forwards Continuation of Curtiss Papers to Be Filed Under Commission Correspondence in Pdr.Advanced Copy Sent to Pdr. List of Documents Included in Four Boxes Encl1994-06-29029 June 1994 Forwards Continuation of Curtiss Papers to Be Filed Under Commission Correspondence in Pdr.Advanced Copy Sent to Pdr. List of Documents Included in Four Boxes Encl ML20137J8251994-04-14014 April 1994 Discusses Chronology of Events Since Preliminary Notification of Event or Unusual Occurrence Case 4-94-010 ML20137S2081994-03-28028 March 1994 Discusses 940325 Telcon from Listed Licensee & Contractor Personnel Re Rept of Falsified Survey Records ML20059G9501994-01-19019 January 1994 Staff Requirements Memo Re SECY-93-352,Proposed Export of Fort St Vrain Unirradiated HEU Fuel Assemblies to France for Recovery & Down-Blending to LEU XSNM-2748, & SECY-93-333, Final Amend to 10CFR55 on Renewal of Licenses.. IR 05000293/19930291993-11-23023 November 1993 Notification of Significant Licensee Meeting 93-156 W/Util on 931202 Re Three Recently Reported Design Issues in Insp Rept 50-293/93-29 1999-09-27
[Table view] Category:STAFF REQUIREMENTS MEMORANDUMS
MONTHYEARML20149H4801997-07-24024 July 1997 Staff Requirements Memo Re SECY-97-138, Termination of Fort St Vrain Nuclear Generating Station Ol ML20059G9501994-01-19019 January 1994 Staff Requirements Memo Re SECY-93-352,Proposed Export of Fort St Vrain Unirradiated HEU Fuel Assemblies to France for Recovery & Down-Blending to LEU XSNM-2748, & SECY-93-333, Final Amend to 10CFR55 on Renewal of Licenses.. ML20246D8841989-06-19019 June 1989 Staff Requirements Memo Re 890601 Briefing on Operating Reactors & Fuel Facilities in Rockville,Md.Commission Expressed Disappointment in Long Term Operating Performance of Turkey Point Nuclear Power Plant ML20195C5421988-10-26026 October 1988 Staff Requirements Memo Re 881014 Discussion/Possible Vote in Rockville,Md Re Plant Restart.No Vote Taken at Meeting to Enable Commission to Fully Consider Info Presented ML20153B1141988-06-29029 June 1988 Staff Requirements Memo Re Commission 880621 Briefing on TVA Reorganization & Status of Plants ML20196K2861988-06-24024 June 1988 Staff Requirements Memo Re Boston Edison Co 880609 Briefing in Rockville,Md on Status of Plant.Zech Cautioned Licensee That Transition from Shutdown Activities to Operational Performance Requires Close Attention by Mgt & Personnel ML20147H6231988-03-0404 March 1988 Staff Requirements Memo Re Briefing on Status of Near Term Operating Licenses on 880224.Staff Committed to Provide Commission W/Util Projected Response Date to Questions on Potential Upgrading of Containment Bldg ML20236Y1501987-12-0707 December 1987 Staff Requirements Memo Re 871125 Affirmation/Discussion & Vote.Commission Approved Order Directing Aslab to Issue Decision by 880131 Re Installation of high-density Spent Fuel Racks & Order Vacating Stay for Low Power Operations ML20216D5701987-06-24024 June 1987 Staff Requirements Memo Re 870617 Discussion/Possible Vote on Authorization to Exceed 35% Power Level.Commission Voted to Authorize Operation Above 35% But Not to Exceed 82% of Rated Power ML20215L3101987-05-0707 May 1987 Staff Requirements Memo Re Commission 870430 Affirmation/ Discussion & Vote in Washington,Dc on SECY-87-68A Concerning Order to Rescind 861020 Order Directing Licensee to Show Why OL Should Not Be Modified.Order Signed on 870501 ML20207R2301987-03-11011 March 1987 Staff Requirements Memo on 870226 Briefing on Status of & Possible Vote in Washington,Dc Re Restricted Power Levels for Facility.Commission Decided Not to Vote on Restart of Plant ML20213H1031986-11-17017 November 1986 Staff Requirements Memo Re Commission 861107 Affirmation/ Discussion & Vote in Washington,Dc on SECY-86-325A,approving Order Authorizing Issuance of Full Power License to Perry 1 & SECY-86-292/292A,approving Order Against Matls Disclosure ML20215L5341986-10-23023 October 1986 Staff Requirements Memo Re Commission Briefing in Washington,Dc on Status of Facility ML20206L5601986-08-0808 August 1986 Staff Requirements Memo Re 860731 Affirmation/Discussion & Vote in Washington,Dc Re SECY-86-203,SECY-86-221,SECY-86-168 & SECY-86-184 ML20207Q7071986-08-0707 August 1986 Staff Requirements Memo Requesting Provision of point-by- Point Response of Generic Safety Concerns Outlined in ASLB .Response to 860609 & 0710 Requests Re Adequacy of Alert Sys During Stormy Winter Nights Also Requested ML20210J6121986-03-27027 March 1986 Staff Requirements Memo on 860320 Affirmation/Discussion & Vote in Washington,Dc Re SECY-84-4, Final Rule to Modify GDC 4 of App A,10CFR50, SECY-86-44, Review of ALAB-819, SECY-86-54,SECY-86-64 & SECY-86-80 ML20154G8601986-03-0303 March 1986 Staff Requirements Memo Re 860219 Briefing in Washington,Dc on Status of Isap for Operating Nuclear Power Plants. Commissioner Asselstine Requested Staff to Identify Fees Collected from Plants Involved in Isap Pilot Program ML20154A3421986-02-25025 February 1986 Staff Requirements Memo Re 860213 Affirmation/Discussion & Vote in Washington,Dc.Order Denying Suffolk County 860122 Motion Re Shoreham Emergency Exercise Approved.Order Denying Met Ed Employee 860114 Motion Also Approved ML20137R6991986-02-0707 February 1986 Staff Requirements Memo Re 860129 Affirmation/Discussion & Vote in Washington,Dc Concerning SECY-86-25 on Shoreham Cancellation of Emergency exercise,SECY-86-27 on Waterford & ALAB-812 & SECY-85-386 on Sixty Minutes Broadcast ML20141E2171986-01-0202 January 1986 Staff Requirements Memo Re 851218 Affirmation/Discussion & Vote in Washington,Dc Re SECY-85-241A & SECY-85-39 (ALAB-818).Board Established by Order to Preside Over Hearing on RCS Leak Rate Data Falsifications at TMI-2 ML20138N5501985-12-19019 December 1985 Staff Requirements Memo Re 851212 Affirmation/Discussion & Vote in Washington,Dc Re SECY-85-367A on Proposed Transaction for Refinancing Interest in Palo Verde 1 & Fee Refund for Black Fox ML20137Z3631985-12-0505 December 1985 Staff Requirements Memo Re Affirmation/Discussion & Vote on Extension of 851130 Deadline for Environ Qualification & Revised Post 851130 Environ Qualification Extension Request ML20137P5401985-11-25025 November 1985 Staff Requirements Memo Re 851119 Affirmation/Discussion & Vote in Washington,Dc on Order Extending 851130 Deadline for Environ Qualification at Listed Plants ML20136J1831985-11-21021 November 1985 Staff Requirements Memo Re Commission 851119 Meeting in Washington,Dc on Licensee Environ Qualification Exemption Request.Recommendation on Extension Request Should Be Provided by 851122 ML20137D3791985-11-21021 November 1985 Staff Requirements Memo Re 851114 Affirmation/Discussion & Vote in Washington,Dc.Orders Granting & Denying Extension of 851130 Equipment Qualification Deadline for Nine Mile Point & Brunswick,Respectively,Approved ML20140H5691985-09-0707 September 1985 Staff Requirements Memo Re 850903 Briefing in Washington,Dc on near-term Ols.Acrs Requested to Provide Updated Position on Prior to Anticipated Low Power or Full Power OL Decision, If ACRS View Differs from 811215 Rept ML20210R7231985-06-28028 June 1985 Partially Withheld Staff Requirements Memo Approving Draft Ltr to Congressman Markey & Memo Encl in SECY-85-93 Re Ofc of Inspector & Auditor Rept on Region II Handling of Falsification of Operator Qualifications.W/O Encls ML20128G7621985-06-28028 June 1985 Staff Requirements Memo Re 850620 Affirmation/Discussion & Vote in Washington,Dc.Edo & RES Should Forward Fr Notice Re Approved Final Rule on Pressurized Thermal Shock for Signature & Publication ML20133K5231985-04-0101 April 1985 Staff Requirements Memo Re Commission 850315 Briefing in Washington,Dc Concerning Continuance for NRC Investigation of TMI-2 Operators at Facility.Investigation Should Continue.Action on COMNP-85-14 & COMJP-85-1 Complete ML20126D9981984-05-18018 May 1984 Staff Requirements Memo Re 840516 Meeting on Continuation of Review of Proposed Shoreham Order.General Agreement Reached on Proposed Order as Modified at Meeting ML20126E0621984-05-16016 May 1984 Staff Requirements Memo Re 840511 Continuation of Discussion or Oral Presentations & Proposed Order Re OL Proceeding.Portions Deleted ML20133M2931979-06-0404 June 1979 Staff Requirements Memo Re 790530 Briefing in Washington, DC on Pipe Stress Issue at Beaver Valley.Subsequent Briefings on Seismic Reanalysis Matters Scheduled for Near Future.No Requirements as Result of Meeting 1997-07-24
[Table view] |
Text
l me IN RESPONSE, PLEASE y* / 1 -
- UNITED STATES REFER TO: M851126B
,,k @._
3
~,,-
)
. NUCLEAR REGULATORY COMMISSION .
WASHINGTON, D.C. 20656
.g '
~ e y/ December 5,-1985 e s,. _
"OFFCE OF THE MCRETARY 9
MEMORANDUM FOR: ~ William J.- Dircks, Executive Director
- for Operations. j Herzel H.E. Plaine, General Counsel FROM:: 0i S uel J. Chilk, Secretary
SUBJECT:
STAFF REQUIREMENTS - AFFIRMATION / DISCUSSION <
AND VOTE, 4:00 P.M., TUESDAY, NOVEMBER 26, :
1985, COMMISSIONERS' CONFERENCE ROOM,HD.C.
OFFICE (OPEN TO PUBLIC ATTENDANCE)
I '. SECY-85-370 - Environmental Qualification (EQ) Extension of the November 30, 1985 Deadline for the' Fort St. Vrain Nuclear Generating Station The Commission, by a 5-0 vote, approved an order extending the
-deadline for environmental qualification at the Fort St. Vrain Nuclear-Generating Station from November. 30,.1985 to May 31, 1986. The' Commission'also authorized the Director of NRR to authorize operation of. Fort St. Vrain at up to 35 percent of full power through May 31,.1986fcontingent on a finding that the confirmatory submittals from the licensee are acceptable.
(Subsequently, on November.26, 1985 the Secretary signed the ;
Order.)
II. SECY-85-338A - Revised Environmental Qualification ' (EQ) -
Extension Request Post-November 30, 1985 for the Pilgrim Nuclear Lower Station- ,
The Commission, by a 3-2 vote-(with Chairman Palladino and Commissioners Bernthal and Asselstine agreeing), approved' '
issuing an' order d enying . a request from' Boston Edison Company to
~
extend the EQLdeadline from. November.30, 1985 to February 8, l 1986.- Commissioners Roberts and'Zech would have granted the :
extension to allow documentation of' test results 3o be-completed. Commissioner Zech would also have granted an .!'
extension to allow completion of testing on one piece of equipment.
8512110283 851205
. PDR 10CFR
. PT9.7 PDR
.c
y h ^ (Subsequently, on November 27, 1985-the Secretary. signed the Order.).
cc: Chairman Palladino
' Commissioner Roberts Commissioner Asselstine Commissioner Bernthal Commissioner Zech
- Commission Staf f Offices PDR - Advance DCS - 016 Phillips
.