Letter Sequence Approval |
---|
|
Results
Other: ML20137H372, ML20137L926, ML20137Z363, ML20138B512, ML20138L407, ML20141E527, ML20141H534, ML20141H544, ML20141H549, ML20151R074, ML20154N150
|
MONTHYEARML20132E6081985-07-19019 July 1985 Supplemental Safety Evaluation Supporting Licensee CRD Mechanisms & Associated Position Instrumentation,Per 850712 Safety Evaluation & Licensee 850710 & 18 Submittals.Control Rod Program Acceptable for Plant Restart Project stage: Request ML20132F0231985-07-19019 July 1985 Forwards Safety Evaluation Re Environ Qualification of Electric Equipment Important to Safety & Authorizes Interim Operation in dry-out Mode at Max 15% of Rated Power,Based on Listed Conditions,Until Technical Review Completed Project stage: Approval ML20132F0721985-07-19019 July 1985 Safety Evaluation Documenting Deficiencies in Licensee Program for Environ Qualification of Electric Equipment Important to Safety.Licensee Response to Generic Ltr 84-24 Inadequate.However,Operation at 15% Power Authorized Project stage: Approval ML20134M0161985-08-20020 August 1985 Submits Discussion of Technical Issues Re Environ Qualification Program Raised During Meetings W/Nrc.Aging & Operability Time Program Operator Response Time,Temp Profiles & Shutdown Cooling Paths & Equipment Evaluated Project stage: Meeting IR 05000267/19850211985-08-30030 August 1985 Insp Rept 50-267/85-21 on 850721-31.No Violation or Deviation Noted.Major Areas Inspected:Operational Safety Verification Project stage: Request ML20137X1411985-09-30030 September 1985 Safety Evaluation Supporting Util 850830,0910,11 & 23 Requests for Authorization to Operate at Max 8% Power,For Up to 45 Days,To Remove Moisture from RCS Project stage: Approval ML20137X1241985-09-30030 September 1985 Forwards Safety Evaluation Based on Util 850830,0910,11 & 23 Requests for Authorization to Operate at Max 8% Power,For Up to 45 Days,To Remove Moisture from Rcs.Authorization Granted,Subj to Listed Commitments Project stage: Approval ML20138E3921985-10-11011 October 1985 Forwards Request for Addl Info on 850924 Request for Special Consideration & Schedule Extension to Equipment Qualification rule,10CFR50.49.Info Requested within 7 Days of Ltr Receipt Project stage: RAI ML20138C8111985-10-21021 October 1985 Forwards Response to 851011 Request for Addl Info Re 850924 Request for Schedule Extension for Environ Qualification Program Under 10CFR50.49 from 851130 to 860331 Project stage: Request ML20138R7331985-10-31031 October 1985 Summary of 851029 Meeting W/Util & ORNL Re Schedule Extension to Equipment Qualification Rule.List of Attendees, Agenda & Matls Presented by Util Encl Project stage: Meeting ML20209J0821985-11-0505 November 1985 Forwards Request for Addl Info Re Equipment Qualification Program & Request for Extension of Deadline for Compliance W/Equipment Qualification Rule,Per 851029 Meeting Project stage: RAI ML20136F6991985-11-19019 November 1985 Modifies Scheduled Commitment for Submittal of Final Draft Proposal of Upgraded Tech Specs for NRC Comment,Per 851008 Request.Revised Submittal Date of 851130 Approved.Revised Tabulation of Commitments Encl Project stage: Draft Other ML20136J1831985-11-21021 November 1985 Staff Requirements Memo Re Commission 851119 Meeting in Washington,Dc on Licensee Environ Qualification Exemption Request.Recommendation on Extension Request Should Be Provided by 851122 Project stage: Meeting ML20136J0151985-11-22022 November 1985 Notifies of Withdrawal of 850924 Schedule Extension Request for Environ Qualification Program.Approval of Revised Schedule Extension for Implementation of Program Beyond 851130 Under Provision of 10CFR50.49 Requested Project stage: Withdrawal ML20137H3721985-11-26026 November 1985 Memorandum & Order Granting Extension of 851130 Deadline for Environ Qualification of Electrical Equipment to 860531 & Approving Proposal to Allow Operation w/35% Reactor Power Limit During Interim.Served on 851127 Project stage: Other ML20137Z3631985-12-0505 December 1985 Staff Requirements Memo Re Affirmation/Discussion & Vote on Extension of 851130 Deadline for Environ Qualification & Revised Post 851130 Environ Qualification Extension Request Project stage: Other ML20138L4071985-12-10010 December 1985 Rev B to EE-EQ-0019, Engineering Evaluation of Liner Cooling W/Fire Water Following High Energy Line Break from 35% Power Operation at Fort St Vrain Project stage: Other ML20138B5121985-12-10010 December 1985 Forwards Evaluations to Document Completion of Confirmatory Actions Required to Support 35% Power Restriction During Environ Qualification Schedule Extension Period Project stage: Other ML20136C8221985-12-26026 December 1985 Forwards Request for Addl Info to Complete Resolution of Confirmatory Action 6 Re Insp of High Energy Piping.Concerns Include Potential for Inservice Degradation & Exam & Insp Methods Project stage: RAI ML20137L9261985-12-31031 December 1985 Heat Stress Mgt Program for Nuclear Power Industry, Interim Rept Project stage: Other ML20141E5271986-01-0303 January 1986 Forwards Summary of Position on Confirmatory Action 6 Re Insp of Critical Areas of High Energy Piping & Responses to Six Addl Info Requests.Limited Insp Plan Will Be Completed by Middle of Jan 1986.Drawings Encl Project stage: Other ML20141H5341986-01-0808 January 1986 Forwards NDE Procedures,Per DW Warembourg Project stage: Other ML20141H5441986-01-0808 January 1986 Issue 1 to NDE Procedure QCIM-38, Ultrasonic Exam of Class 1 & 2 Piping Welds Joining Similar & Dissimilar Matls Project stage: Other ML20141H5491986-01-0808 January 1986 Issue 5 to NDE Procedure QCIM-30, Radiographic Exam Procedure Project stage: Other ML20137M1091986-01-15015 January 1986 Forwards Addl Info to Support Util Intention to Use Ice Vests to Allow Personnel Access W/Elevated Bldg Temps. T Bernard Prof Opinion Documented in Encl Draft Heat Stress Mgt Program. Rept Available in Central Files Project stage: Draft Other ML20137L9001986-01-21021 January 1986 Forwards EPRI Interim Rept, Heat Stress Mgt Program for Nuclear Power Industry, to Replace Draft Transmitted by Walker ,To Support 35% Power Bldg Access.Rept Will Be Available in Mar as EPRI NP4453 Project stage: Draft Other ML20151R0741986-01-29029 January 1986 Informs That NRR Ltr to Licensee Summarizing Findings Re Environ Qualification Extension Sufficient to Authorize Limited Operation.No License Amend Required to Support Authorization Project stage: Other ML20154N1501986-03-0303 March 1986 Forwards Final Rept on Inservice Insp Program Performed on High Energy Piping.Program Inspected 35 Critical Areas of Piping Per Safety Evaluation of Confirmatory Item 6. Integrity Verified in Support of 35% Power Operation Project stage: Other 1985-12-31
[Table View] |
Safety Evaluation Supporting Util 850830,0910,11 & 23 Requests for Authorization to Operate at Max 8% Power,For Up to 45 Days,To Remove Moisture from RCSML20137X141 |
Person / Time |
---|
Site: |
Fort Saint Vrain ![Xcel Energy icon.png](/w/images/6/6c/Xcel_Energy_icon.png) |
---|
Issue date: |
09/30/1985 |
---|
From: |
NRC |
---|
To: |
|
---|
Shared Package |
---|
ML20137X130 |
List: |
---|
References |
---|
GL-85-15, TAC-59787, NUDOCS 8510040463 |
Download: ML20137X141 (5) |
|
|
---|
Category:SAFETY EVALUATION REPORT--LICENSING & RELATED ISSUES
MONTHYEARML20141K9961997-05-0505 May 1997 Safety Evaluation Supporting Amend 89 to License DPR-34 ML20128D7191992-12-0101 December 1992 Safety Evaluation Approving Exemption from Requirement of 10CFR50.54(q) to Change to Biennial Emergency Plan Exercise Rather than Annual Following Completion of Next Scheduled Exercise at Plant ML20246J3261989-08-30030 August 1989 Safety Evaluation Supporting Amend 72 to License DPR-34 ML20245J3781989-08-14014 August 1989 Safety Evaluation Supporting Amend 71 to License DPR-34 ML20245J4511989-08-0808 August 1989 Safety Evaluation Responding to Issues Re Tech Spec Upgrade & Plant Defueling.Stated Tech Spec Sections Should Be Upgraded ML20246J3131989-07-0707 July 1989 Safety Evaluation Concluding That Operators Role in Mitigating High Energy Line Break at Facility Acceptable ML20247R2261989-05-26026 May 1989 Final Safety Evaluation Re LER 87-20 Concerning Interactions Between Steamline Rupture Detection/Isolation Sys,Plant Protective Sys & Control Sys at Facility ML20245C5031989-04-18018 April 1989 Safety Evaluation Supporting Amend 70 to License DPR-34 ML20248D6501989-03-31031 March 1989 Safety Evaluation Supporting Amend 69 to License DPR-34 ML20236A1401989-02-27027 February 1989 Safety Evaluation Supporting Amend 68 to License DPR-34 ML20235T4511989-02-24024 February 1989 Safety Evaluation Re Facility Core Support Flow Vent Sys. Continued Operation of Facility W/Current Core Support Flow Sys Configuration Acceptable ML20235J3421989-02-16016 February 1989 Safety Evaluation Supporting Util Action in Response to Generic Ltr 83-28,item 2.1 (Part 2) Confirming Establishment of Interface W/Either NSSS Vendor or Vendors of Each Component in Reactor Trip Sys ML20235J3841989-02-13013 February 1989 Safety Evaluation Concluding That Continued Operation of Facility Not Affected by Steam Generator Tube Failures Experienced by Advanced gas-cooled Reactors ML20195D3911988-10-27027 October 1988 Safety Evaluation Supporting Corrective Actions of LER 86-017 ML20205G0021988-10-24024 October 1988 Safety Evaluation Supporting Amend 65 to License DPR-34 ML20154J8021988-09-15015 September 1988 Safety Evaluation Supporting Amend 64 to License DPR-34 ML20154J4621988-09-15015 September 1988 Safety Evaluation Supporting Amend 63 to License DPR-34 ML20207F0571988-08-10010 August 1988 Safety Evaluation Supporting Util 870206 Submittal Re Safe Shutdowns During Postulated Accident Conditions ML20207F0431988-08-0505 August 1988 Safety Evaluation Supporting Amend 61 to License DPR-34 ML20207F2411988-08-0505 August 1988 Safety Evaluation Supporting Amend 62 to License DPR-34 ML20151M1601988-07-21021 July 1988 Safety Evaluating Supporting Requirements for Redundancy in Responding to Rapid Depressurization Accident ML20151A9961988-06-20020 June 1988 Safety Evaluation Supporting Amend 60 to License DPR-34 ML20195K0651988-06-15015 June 1988 SER Concurring W/Util Proposed Corrective Actions in Engineering Rept Entitled, Rept of Helium Circulator S/N 2101 Damage & Inlet Piping S/N 2001 Repair & Mod Activities ML20195F9661988-06-15015 June 1988 Safety Evaluation Re Destructive Exam Rept for Fuel Test Assembly-2.Fuel Represented by Fuel Test Assembly-2 Predicted to Be Safe for Operation in Facility for 1,800 EFPDs ML20154F8891988-05-10010 May 1988 Safety Evaluation Re Proposed Safe Shutdown Sys & Exemption Requests Concerning 10CFR50,App R.Licensee Request for Exemptions in Listed Areas Should Be Granted.Concept for Providing post-fire Shutdown Acceptable ML20148S6031988-04-0707 April 1988 Safety Evaluation Supporting Amend 59 to License DPR-34 ML20151B6651988-04-0101 April 1988 Supplemental Safety Evaluation Supporting Util Compliance w/10CFR50.App R Re Safe Shutdown DHR Capacity ML20150C4541988-03-10010 March 1988 Safety Evaluation Concluding That Seismic Analysis Methods for Bldg 10 & Walkover Structure Conservative.Gaps Provided Adequate to Accommodate Relative Motions Which Occur Between Subj Structures & Walkover Structure & Turbine Bldg ML20147C8181988-02-25025 February 1988 Safety Evaluation Supporting Changes to Interim Tech Specs 3/4.1.7, Reactivity Change W/Temp NUREG-1220, Safety Evaluation Accepting Plant Special Senior Licensed Fuel Handler Initial & Requalification Operator Training Program,Per NUREG-1220, Training Review Criteria & Procedures1988-01-13013 January 1988 Safety Evaluation Accepting Plant Special Senior Licensed Fuel Handler Initial & Requalification Operator Training Program,Per NUREG-1220, Training Review Criteria & Procedures ML20237D7631987-12-18018 December 1987 Safety Evaluation Updating 861118 Fire Protection Sys Safety Evaluation.Util Alternate Fire Protection Configuration Acceptable ML20149E1621987-12-18018 December 1987 Marked-up Safety Evaluation Re Proposed Safe Shutdown Sys & Exemption Requests Concerning 10CFR50,App R ML20236U6961987-11-23023 November 1987 Safety Evaluation Supporting Amend 57 to License DPR-34. Addendum to Review of Proposed Tech Spec Change:Core Inlet Valves/Min Helium Flow & Max Core Region Temp Rise,Limiting Condition for Operation..., Technical Evaluation Rept Encl ML20236U5761987-11-20020 November 1987 Safety Evaluation Re Helium Circulator S/N C-2101 Damage. Util Corrective Action Program Initiated ML20236R3001987-11-13013 November 1987 Safety Evaluation Supporting Util Responses to Generic Ltr 83-28,Item 2.2.1 Re Equipment Classification Programs for All safety-related Components ML20238C7621987-09-0202 September 1987 Safety Evaluation Concurring W/Util 870702 & 27 Ltrs & 870818 Telcon Re Elimination or Reduction of Maint Requirements on Certain Fire Seals ML20235N6491987-07-13013 July 1987 Safety Evaluation Supporting Amend 56 to License DPR-34 ML20235F5281987-07-0202 July 1987 Safety Evaluation Re Safe Shutdown of Steam Generator Matls. Under Severe Transient Conditions,Fuel Temp Can Be Maintained Under Accepted Temp Limits & Plant Can Be Safely Shutdown ML20235F5151987-07-0202 July 1987 Safety Evaluation Re Safe Emergency Shutdown of Reactor Sys. Operation at 82% Acceptable ML20235F5441987-07-0202 July 1987 Safety Evaluation Re Effect of Firewater Cooldown on Steam Generator Structural Integrity.All Tests Acceptable ML20235E5281987-06-29029 June 1987 Safety Evaluation Supporting Amend 55 to License DPR-34 ML20216G9511987-06-24024 June 1987 Revised Safety Evaluation Re Steam Line Rupture Detection & Isolation Sys (Slrdis).Slrdis Meets Requirements of 10CFR50, App A,Gdc 20 & GDC 4 ML20216G9911987-06-24024 June 1987 Supplemental Safety Evaluation Supporting Application for Amend to License DPR-34 Re Tech Specs for Steam Line Rupture Detection & Isolation Sys ML20215J5401987-06-22022 June 1987 Draft Safety Evaluation Re Safe Emergency Shutdowns.Facility Operation at 82% Power Acceptable ML20216J1921987-06-17017 June 1987 Safety Evaluation Re Mods to Reduce Moisture Ingress Into Reactor Vessel.Periodic Insps & Preventive Maint Should Be Performed on Pertinent Components.Operational Performance Should Be Continuously Upgraded ML20214M4681987-05-20020 May 1987 Safety Evaluation Supporting Amend 54 to License DPR-34 ML20215J8271987-05-0505 May 1987 Safety Evaluation Supporting Amend 53 to License DPR-34 ML20209D7561987-04-22022 April 1987 Safety Evaluation Supporting Util 870211 Submittal Re Performance Enhancement Program,Finding 4-10 ML20206J9331987-04-0606 April 1987 Safety Evaluation Supporting Amend 52 to License DPR-34 ML20205S1141987-03-31031 March 1987 Safety Evaluation Accepting Util 831104 Response to Generic Ltr 83-28,Item 4.5.2, Reactor Trip Sys Reliability On-Line Testing. Facility Designed to Permit on-line Functional Testing,Including Testing of Reactor Trip Contactors 1997-05-05
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20196G6731997-07-0101 July 1997 Informs Commission That Decommissioning Process Has Been Completed at PSC of Colorado Fsvngs,Unit 1 Located in Town of Platteville in Weld County,Co ML20141K9961997-05-0505 May 1997 Safety Evaluation Supporting Amend 89 to License DPR-34 ML20140E1121997-04-10010 April 1997 Confirmatory Survey of Group Effluent Discharge Pathway Areas for Fsv Nuclear Station,Platteville,Co ML20134D1661997-01-30030 January 1997 Rev 1,Vol 6 to Final Survey Rept,Final Survey of Group E (Book 2A of 2) ML20137S6111996-12-31031 December 1996 Annual Rept Pursuant to Section 13 or 15(d) of Securities Exchange Act 1934, for Fy Ended Dec 1996 ML20134G6401996-10-29029 October 1996 Rev 0,Volume 6,Books 1 & 2 of 2 to Final Survey of Group E ML20134G6171996-10-29029 October 1996 Rev 2,Volume 1,Books 1 & 2 of 2 to Final Survey Description & Results ML20134G7271996-10-29029 October 1996 Rev 0,Volume 11,Book 1 of 1 to Final Survey of Group J ML20134G6861996-10-29029 October 1996 Rev 0,Volume 8,Books 1 & 2 of 2 to, Final Survey of Group G ML20134G6321996-10-26026 October 1996 Rev 1,Volume 5,Books 2 & 3 of 3 to Final Survey of Group D ML20133D7831996-10-22022 October 1996 Preliminary Rept - Orise Support of NRC License Insp at Fsv on 960930-1003 ML20116A4661996-07-19019 July 1996 Fsv Final Survey Exposure Rate Measurements ML20112J6861996-05-31031 May 1996 June 1996 Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments for Fsv Decommissioning.Rept Covers Period of 960216-0531 ML20112C1531996-05-17017 May 1996 Fsv Final Survey Exposure Rate Measurements ML20101G5521996-03-21021 March 1996 Confirmatory Survey Activities for Fsv Nuclear Station PSC Platteville,Co, Final Rept ML20097E3201996-01-31031 January 1996 Nonproprietary Fort St Vrain Technical Basis Documents for Piping Survey Instrumentation ML20095K4131995-12-26026 December 1995 Rev 3 to Decommissioning Plan ML20095H7211995-12-20020 December 1995 Revs to Fort St Vrain Decommissioning Fire Protection Plan Update ML20095K9751995-12-15015 December 1995 Fort St Vrain Project Update Presentation to NRC, on 951207 & 15 ML20096C1671995-12-13013 December 1995 Rev 4 to Decommissioning Fire Protection Plan ML20094M1651995-11-30030 November 1995 Nonproprietary Fsv Technical Basis Documents for Piping Survey Implementation ML20092F3461995-09-14014 September 1995 Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments for Fsv Decommissioning, Covering Period of 950516-0815.W/ ML20137H3531994-12-31031 December 1994 Partially Withheld, Rept of Independent Counsel Investigation Concerning Issues at Fort St Vrain Nuclear Generating Station Decommissioning Project, App D,Comments by Mkf & Westinghouse Team & Responses ML20137S2331994-12-31031 December 1994 Rept of Independent Counsel Investigation Concerning Issues at Fort St Vrain Nuclear Generating Station Decommissioning Project, Dec 1994 ML20029C6031993-12-31031 December 1993 1993 Annual Rept Public Svc Co of Colorado. W/940405 Ltr ML20058Q3791993-12-21021 December 1993 Rev 1 to Decommissioning Plan for Fort St Vrain Nuclear Generating Station ML20045B3641993-06-30030 June 1993 June 1993 Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments for Fsv Decommissioning. ML20045A4291993-06-0303 June 1993 LER 93-003-00:on 930505,new Source of Natural Gas Introduced within 0.5 Miles of ISFSI & Reactor Bldg W/O Prior NRC Approval.Caused by Field Routing of Natural Gas Pipe.Well Isolated by Well operator.W/930603 Ltr ML20077D1631993-05-10010 May 1993 Enforcement Conference, in Arlington,Tx ML20125C7161992-12-0707 December 1992 Part 21 Rept Re Possibility for Malfunction of Declutching Mechanisms in SMB/SB-000 & SMB/SB/SBD-00 Actuators. Malfunction Only Occurs During Seismic Event.Balanced Levers May Be Purchased from Vendor.List of Affected Utils Encl ML20128D7191992-12-0101 December 1992 Safety Evaluation Approving Exemption from Requirement of 10CFR50.54(q) to Change to Biennial Emergency Plan Exercise Rather than Annual Following Completion of Next Scheduled Exercise at Plant ML20127P5861992-11-23023 November 1992 Followup to 921005 Part 21 Rept Re Potential Defect in SB/SBD-1 Housing Cover Screws.Procedure Re Replacement of SBD-1 Spring Cover Bolts Encl.All Fasteners Should Be Loosened & Removed.List of Affected Utils Encl ML20127F5691992-11-0303 November 1992 Informs Commission of Intent to Issue Order Approving Plant Decommissioning Plan & Corresponding Amend to License DPR-34 ML20101E5761992-05-31031 May 1992 Monthly Defueling Operations Rept for May 1992 for Fort St Vrain ML20096E8221992-04-30030 April 1992 Monthly Operating Rept for Apr 1992 for Fort St Vrain.W/ ML20095E9601992-04-17017 April 1992 Rev to Fort St Vrain Proposed Decommissioning Plan ML20100R7431992-03-31031 March 1992 Monthly Operating Rept for Mar 1992 for Fort St Vrain.W/ ML20090L0621992-02-29029 February 1992 Monthly Operating Rept for Feb 1992 for Fort St Vrain Unit 1 ML20092D0081992-01-31031 January 1992 Monthly Operating Rept for Jan 1992 for Fort St Vrain Nuclear Generating Station ML20102B2241992-01-22022 January 1992 Fort St Vrain Station Annual Rept of Changes,Tests & Experiments Not Requiring Prior Commission Approval Per 10CFR50.59, for Period 910123-920122 ML20094N6701991-12-31031 December 1991 Public Svc Co Annual Financial Rept for 1991 ML20091J6251991-12-31031 December 1991 Monthly Operating Rept for Dec 1991 for Fort St Vrain.W/ ML20094D6711991-11-30030 November 1991 Monthly Operating Rept for Nov 1991 for Fort St Vrain Unit 1 ML20090M1871991-11-20020 November 1991 FOSAVEX-91 Scenario for 1991 Plant Exercise of Defueling Emergency Response Plan ML20086D6891991-11-15015 November 1991 Proposed Decommissioning Plan for Fort St Vrain Nuclear Generating Station ML20085N1451991-11-0505 November 1991 Revised Ro:Operability Date of 910830 for Electric Motor Driven Fire Water Pump P-4501 Not Met.Pump Not Actually Declared Operable Until 911025.Caused by Unforseen Matl & Testing Problems.Equivalent Pump Available ML20086C5451991-10-31031 October 1991 Monthly Operating Rept for Oct 1991 for Fort St Vrain.W/ ML20085H6611991-10-10010 October 1991 Assessment of Mgt Modes for Graphite from Reactor Decommissioning ML20091D7671991-10-0101 October 1991 Rev B to Engineering Evaluation of Prestressed Concrete Reactor Vessel & Core Support Floor Structures for Proposed Sys 46 Temp Change ML20085D9861991-09-30030 September 1991 Monthly Operating Rept for Sept 1991 for Fort St Vrain.W/ 1997-07-01
[Table view] |
Text
. .
SAFETY EVALUATION CONCERNING LIMITED LOW POWER OPERATION OF FORT ST. VRAIN DOCKET NO. 50-267
1.0 INTRODUCTION AND BACKGROUND
By Confirmatory Action Letter dated July 19, 1985, the staff authorized the restart of Fort St. Vrain (FSV) and its operation up to 15 percent of Rated Thermal Power. This allowed the licensee to operate the reactor to remove moisture, but limited operation until certain equipment qualification issues were resolved. Specifically, the licensee had to complete aging and equipment operability time studies required for equipment qualification under 10 CFR 50.49.
By letter dated August 20, 1985, the licensee reported to the staff on the progress of his equipment qualification program. New problems discovered by the licensee includad:
- Equipment items subject to submergence Unqualified taped electrical splices
- Contaminated or rusted electrical junction boxes
- Discrepancies in equipment model numbers in comparison to test.
reports
- Additional equipment potentially exposed to a harsh environment In discussions between the licensee ar,j the staff, the licensee agreed not to operate the reactor until this situation could be reviewed and approved by the staff.
By letter dated August 30, 1985, the licensee requested authorization from the staff to operate FSV at low power for a limited period to continue moisture removal. Specifically, the licensee requested NRC approval to operate at power levels not to exceed 8 percent (of full power) for a period not to exceed 45 days or extend beyond November 30, 1985. The licensee supplemented this request with additional information by letters dated September 10, 11 and 23, 1*
2.0 EVALUATION 2.1 Desinability of Continued Moisture hemoval.
The licensee has committed to and initiated multiple efforts to minimize moisture ingress into the FSV reactor. The licensee considers it prudent to continue to reduce the level of moisture in the reactor vessel.
8510040463 850930 PDR ADOCK 05000267 P PDR
The staff has reviewed the question of moisture ingress into the FSV reactor in its October 1984 Assessment Report (Reference 1). The staff has concluded in this report that reducing moisture ingress would improve the reliability of overall plant operations and potentially improve the performance of the control rod drive mechanisms. The staff required the licensee to implement modifications to reduce the frequency and severity of further moisture ingress events.
Hence, the staff concludes that further lowering of the reactor moisture level is consistent with the staff's previous findings on moisture ingress, and therefore should be continued.
2.2 Qualification Status Of Equipment For Decay Heat Removal The licensee has stated that a number of equipment r"lalification problems at FSV remain unresolved. The licensee is working to resolve these issues as rapidly as possible. The staff has found that pending resolution of these issues, equipment necessary to maintain forced Helium circulation cooling can not be considered qualified. Therefore, no credit can be taken for automatic operation of this equipment.
The licensee has stated, however, that operation at low power for a 45 day period before November 30, 1985, would rely only on manual operation of the liner cooling system for decay heat. removal following a high energy (steam) line break accident; and that operation of this equipment in the manual mode is not vulnerable to an accident environment.
The liner cooling system has two redundant loops and is in continuous operation during reactor operation. The normal supply for liner cooling water is the Reactor Plant Cooling Water System (System 46) pumps.
These pumps are located on Level 8 in the Reactor Building and east of the 4A wall. Therefore, with the relatively low Reactor Building temperature profiles at 8 percent power, it is expected that these pumps would not be affected during the steam line rupture. The remainder of System 46 is also expected to survive the accident due to the relatively low temperature-profile.
However, even if all electrical items in System 46 fail, fire water can be manually valved into the liner cooling system. This would be a once ,
through system with the water being supplied by the fire water pumps located outside of the building. In this case, no qualification is required of any electrical items. Portions of the liner cooling system exposed to a harsh environment can be manually operated.
The licensee has committed to have in effect, prior to restart, emergency procedures which reflect the dependence on the liner cooling system as the decay heat removal path. Operators would verify operation of the liner cooling system following a high energy line break accident. This verification would be by direct local observation of equipment operation and valve lineup. Operation would be periodically reverified. In the event.that the operators conclude that the liner cooling system is not
performing its design function, they would restore its operation through manual actions. The licensee is not taking credit for any automatic equipment operation in assuring operation of the liner cooling system.
Instead, the licensee is relying entirely on appropriate manual actions.
Reliance on manual operation for the liner cooling system is acceptable because the accident analysis indicates that there is adequate time (over 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />) in which to gain access to the necessary components and take action to assure that liner cooling is restored. This time limitation is. based on maintaining the reactor vessel concrete below 400 F, the level at which the concrete could be expected to lose a significant fraction of its compressive strength. The licensee has stated that failure of other equipment does not affect the independent operation of the liner cooling system and that even in the event of equipment failures ample time margin is available to enable operators to perform the manual operations necessary to realign the system or to effect any necessary repairs.
In summary, the licensee has shown that the liner cooling system can be used to remove decay heat, and has committed to implement, prior to.
restart, emergency procedures to assure that:
- 1) The operator will not be misled by failure of equipment, and,
- 2) required equipment is verified to be available and operable.
~
2.3 Accident Consequences The licensee has stated that plant operation at 8 percent power level greatly reduces the requirements for decay heat removal. At this power level, the.
average core temperature would be 640 F. Decay heat calculations would yield a maximum temperature of 1337 F 100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> after reactor shutdown, without any liner cooling. With one loop of liner cooling, fuel temperatures would reach 1281*F about 100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> after reactor shutdown. These temperatures are well below the 2400 F ful temperature reached in normal operation, and the 2900 F fuel temperature at which fission product release begins to occur. Under these conditions, there would be no significant fuel failure or fission product activity released. Operation of the liner cooling system would be assured by the licensee's procedures following a reactor shutdown.
The staff performed independent calculations concerning decay heat removal for Fort St. Vrain when operated at the 8 percent level. The staff's calculations find that the maximum fuel temperature reached is about 1350*F after 3 days, with only the liner cooling system in operation (Reference 2). The staff calculated peak temperature with the liner cooling system in operation is higher than the temperature calculated by the licensee assuming no liner cooling because of different assumptions about coolant flows and core temperatures in low power operation. The staff's calculations are more conservative because the minimum allowable flow and higher core temperatures were assumed as initial conditions. It should also be noted that both the core heatup and the cooldown produced by the liner cooling system take place very gradually. Hence, temporary interruptions of the liner cooling system operation do not greatly affect fuel temperatures.
~~
4_
The staff concludes that the liner cooling system provides adequate decay heat removal for FSV at the 8 percent power level and that operation in this mode has no unacceptable accident consequences.
2.4 Return To Power Operation The licensee has stated that the need to remove moisture from the FSV reactor will potentially delay eventual return to power operation. FSV technical specifications (Sections LCO 4.2.10 and 4.2.11) limit the allowable moisture levels in reactor primary coolant. The licensee states it must continue moisture removal operation or delay the ret"rn of FSV to power operation.
Eventual startup of the plant will aise require the licensee to resolve problems with equipment qualification. hence, if the reactor moisture level is reduced now, and maintained in that condition, reactor power operation can begin promptly when the other problems are resolved.
Additionally, maintaining the reactor at low moisture levels during this period minimizes the potential for the moisture to adversely affect the exposed reactor systems, thus delaying the plant's return to power operation.
The staff concludes that return to power operation of FSV is in the public interest and that lower power operation to allow moisture removal should be permitted.
3.0 CONCLUSION
The staff finds the continued low power operation of FSV to remove moisture is desirable. This is part of the licensee's overall effort to reduce the undesirable effects of moisture ingress on the reactor. The staff also finds that limited operation to remove moisture now would potentially allow Fort St. Vrain to return to power operation at an earlier date after current equipment qualification problems are resolved. In low power operation, the staff finds that decay heat can be safely removed by the liner cooling system. The licensee has committed to put in place prior to restart appropriate procedures and training to assure that the liner cooling system can be placed in operation manually and to assure that its operation will not be affected by unresolved problems with equipment qualification. The NRC will verify acceptable implementation of these procedures by inspection prior to restart. Thus, the staff concludes that Fort St. Vrain can be safely operated for a period not to exceed 45 days and at a power level not to exceed 8 percent of full power. However, operation at low power levels is only acceptable for a period of 45 days before November 30, 1985. After this period, plant operation must be in accordance with Commission policy as stated in GL 85-15.
Date: September 27, 1985 Principal Contributors:
K. Heitner, DL T. King, DL A. Masciantonio, DE
7-
References:
- 1. Preliminary Report Related to the Restart and Continued Operation of Fort St. Vrain Nuclear Generating Station, October 1984.
- 2. Letter to T. L. King, NRC, from S. J. Ball, ORNL, on ORECA Analysis of FSV 8% Power Severe Accident Sequences dated September 9, 1985 m
O t
9
---_--.__---___..__.s