Letter Sequence Withdrawal |
---|
|
Results
Other: ML20137H372, ML20137L926, ML20137Z363, ML20138B512, ML20138L407, ML20141E527, ML20141H534, ML20141H544, ML20141H549, ML20151R074, ML20154N150
|
MONTHYEARML20132E6081985-07-19019 July 1985 Supplemental Safety Evaluation Supporting Licensee CRD Mechanisms & Associated Position Instrumentation,Per 850712 Safety Evaluation & Licensee 850710 & 18 Submittals.Control Rod Program Acceptable for Plant Restart Project stage: Request ML20132F0231985-07-19019 July 1985 Forwards Safety Evaluation Re Environ Qualification of Electric Equipment Important to Safety & Authorizes Interim Operation in dry-out Mode at Max 15% of Rated Power,Based on Listed Conditions,Until Technical Review Completed Project stage: Approval ML20132F0721985-07-19019 July 1985 Safety Evaluation Documenting Deficiencies in Licensee Program for Environ Qualification of Electric Equipment Important to Safety.Licensee Response to Generic Ltr 84-24 Inadequate.However,Operation at 15% Power Authorized Project stage: Approval ML20134M0161985-08-20020 August 1985 Submits Discussion of Technical Issues Re Environ Qualification Program Raised During Meetings W/Nrc.Aging & Operability Time Program Operator Response Time,Temp Profiles & Shutdown Cooling Paths & Equipment Evaluated Project stage: Meeting IR 05000267/19850211985-08-30030 August 1985 Insp Rept 50-267/85-21 on 850721-31.No Violation or Deviation Noted.Major Areas Inspected:Operational Safety Verification Project stage: Request ML20137X1411985-09-30030 September 1985 Safety Evaluation Supporting Util 850830,0910,11 & 23 Requests for Authorization to Operate at Max 8% Power,For Up to 45 Days,To Remove Moisture from RCS Project stage: Approval ML20137X1241985-09-30030 September 1985 Forwards Safety Evaluation Based on Util 850830,0910,11 & 23 Requests for Authorization to Operate at Max 8% Power,For Up to 45 Days,To Remove Moisture from Rcs.Authorization Granted,Subj to Listed Commitments Project stage: Approval ML20138E3921985-10-11011 October 1985 Forwards Request for Addl Info on 850924 Request for Special Consideration & Schedule Extension to Equipment Qualification rule,10CFR50.49.Info Requested within 7 Days of Ltr Receipt Project stage: RAI ML20138C8111985-10-21021 October 1985 Forwards Response to 851011 Request for Addl Info Re 850924 Request for Schedule Extension for Environ Qualification Program Under 10CFR50.49 from 851130 to 860331 Project stage: Request ML20138R7331985-10-31031 October 1985 Summary of 851029 Meeting W/Util & ORNL Re Schedule Extension to Equipment Qualification Rule.List of Attendees, Agenda & Matls Presented by Util Encl Project stage: Meeting ML20209J0821985-11-0505 November 1985 Forwards Request for Addl Info Re Equipment Qualification Program & Request for Extension of Deadline for Compliance W/Equipment Qualification Rule,Per 851029 Meeting Project stage: RAI ML20136F6991985-11-19019 November 1985 Modifies Scheduled Commitment for Submittal of Final Draft Proposal of Upgraded Tech Specs for NRC Comment,Per 851008 Request.Revised Submittal Date of 851130 Approved.Revised Tabulation of Commitments Encl Project stage: Draft Other ML20136J1831985-11-21021 November 1985 Staff Requirements Memo Re Commission 851119 Meeting in Washington,Dc on Licensee Environ Qualification Exemption Request.Recommendation on Extension Request Should Be Provided by 851122 Project stage: Meeting ML20136J0151985-11-22022 November 1985 Notifies of Withdrawal of 850924 Schedule Extension Request for Environ Qualification Program.Approval of Revised Schedule Extension for Implementation of Program Beyond 851130 Under Provision of 10CFR50.49 Requested Project stage: Withdrawal ML20137H3721985-11-26026 November 1985 Memorandum & Order Granting Extension of 851130 Deadline for Environ Qualification of Electrical Equipment to 860531 & Approving Proposal to Allow Operation w/35% Reactor Power Limit During Interim.Served on 851127 Project stage: Other ML20137Z3631985-12-0505 December 1985 Staff Requirements Memo Re Affirmation/Discussion & Vote on Extension of 851130 Deadline for Environ Qualification & Revised Post 851130 Environ Qualification Extension Request Project stage: Other ML20138L4071985-12-10010 December 1985 Rev B to EE-EQ-0019, Engineering Evaluation of Liner Cooling W/Fire Water Following High Energy Line Break from 35% Power Operation at Fort St Vrain Project stage: Other ML20138B5121985-12-10010 December 1985 Forwards Evaluations to Document Completion of Confirmatory Actions Required to Support 35% Power Restriction During Environ Qualification Schedule Extension Period Project stage: Other ML20136C8221985-12-26026 December 1985 Forwards Request for Addl Info to Complete Resolution of Confirmatory Action 6 Re Insp of High Energy Piping.Concerns Include Potential for Inservice Degradation & Exam & Insp Methods Project stage: RAI ML20137L9261985-12-31031 December 1985 Heat Stress Mgt Program for Nuclear Power Industry, Interim Rept Project stage: Other ML20141E5271986-01-0303 January 1986 Forwards Summary of Position on Confirmatory Action 6 Re Insp of Critical Areas of High Energy Piping & Responses to Six Addl Info Requests.Limited Insp Plan Will Be Completed by Middle of Jan 1986.Drawings Encl Project stage: Other ML20141H5341986-01-0808 January 1986 Forwards NDE Procedures,Per DW Warembourg Project stage: Other ML20141H5441986-01-0808 January 1986 Issue 1 to NDE Procedure QCIM-38, Ultrasonic Exam of Class 1 & 2 Piping Welds Joining Similar & Dissimilar Matls Project stage: Other ML20141H5491986-01-0808 January 1986 Issue 5 to NDE Procedure QCIM-30, Radiographic Exam Procedure Project stage: Other ML20137M1091986-01-15015 January 1986 Forwards Addl Info to Support Util Intention to Use Ice Vests to Allow Personnel Access W/Elevated Bldg Temps. T Bernard Prof Opinion Documented in Encl Draft Heat Stress Mgt Program. Rept Available in Central Files Project stage: Draft Other ML20137L9001986-01-21021 January 1986 Forwards EPRI Interim Rept, Heat Stress Mgt Program for Nuclear Power Industry, to Replace Draft Transmitted by Walker ,To Support 35% Power Bldg Access.Rept Will Be Available in Mar as EPRI NP4453 Project stage: Draft Other ML20151R0741986-01-29029 January 1986 Informs That NRR Ltr to Licensee Summarizing Findings Re Environ Qualification Extension Sufficient to Authorize Limited Operation.No License Amend Required to Support Authorization Project stage: Other ML20154N1501986-03-0303 March 1986 Forwards Final Rept on Inservice Insp Program Performed on High Energy Piping.Program Inspected 35 Critical Areas of Piping Per Safety Evaluation of Confirmatory Item 6. Integrity Verified in Support of 35% Power Operation Project stage: Other 1985-12-31
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20205G8771999-03-26026 March 1999 Forwards Copy of Cover Page from Fort St-Vrain Welding Manual,Which Had Been Listed as Encl on Page 4 of 990325 Reply to EA 98-081.Cover Page Had Been Inadvertently Left Out with Original Reply ML20197H8811998-12-0101 December 1998 Forwards Proposed Change to Fsv ISFSI Physical Protection Plan in Which Commitment Is Made to Provide Feature to Security Posture for Facility ML20236R9191998-07-20020 July 1998 Ltr Contract:Mod 4 to Task Order 27, Task Area No 4 of Basic Contract - Fort St Vrain Insp Under Contract NRC-02-95-003 ML20199H8141997-11-21021 November 1997 Responds to Requesting Clarification as to Whether Increase in Tritium & Iron-55 Contamination Limits That Were Approved for Plant Apply to All Licensees ML20198K1931997-10-10010 October 1997 Provides Supplemental Info in Support of Util Proposed Rev to Physical Security Plan for Plant Plant Isfsi.Plan Withheld,Per 10CFR2.790(d) & 10CFR73.21 ML20198H5601997-09-16016 September 1997 Final Response to FOIA Request for Documents.Documents Listed in App a Being Released in Entirety ML20141F3521997-05-14014 May 1997 Forwards Proposed Issue 4 of Physical Security Plan for Fort St Vrain ISFSI for Review & Approval.Encl Withheld,Per 10CFR2.790(d) ML20141C8611997-05-0909 May 1997 Informs of Approval of Fsv Final Survey Rept & Effluent Pathway Survey Plan & Supporting Analysis ML20141K9881997-05-0505 May 1997 Forwards Amend 89 to License DPR-34 & Supporting Safety Evaluation.Amend Designates All Elements of Approved Decommissioning Plan as License Termination Plan ML20138G2701997-04-28028 April 1997 Provides Response to NRC Comments Re Proposed Sampling & Survey Plan for Fsv Effluent Pathway.Response Documents Fsv Liquid Effluent Discharge Pathway Areas Are Acceptable for Release for Unrestricted Use IAW Draft NUREG/CR-5849 ML20148D4651997-04-24024 April 1997 Forwards Revised Interim Ltr Rept Which Describes Procedures & Results of Confirmatory Survey of Group E Effluent Discharge Pathway Areas at Fsv Station NUREG/CR-5849, Requests That Licensee Provide Evidence That Average Contamination Levels in Group E Effluent Discharge Pathway Areas Meet Averaging Criteria in Draft NUREG/CR-58491997-04-23023 April 1997 Requests That Licensee Provide Evidence That Average Contamination Levels in Group E Effluent Discharge Pathway Areas Meet Averaging Criteria in Draft NUREG/CR-5849 ML20138B0511997-04-22022 April 1997 Forwards Copy of Proposed Amend to Fsv NPDES Permit, Wastewater Discharge Permit CO-0001121 Requested to Support Repowering Activities,Iaw Section 3.2.d of Fsv Non-Radiological Ts,App B to License DPR-34 ML20140E1061997-04-10010 April 1997 Forwards Confirmatory Survey of Group Effluent Discharge Pathway Areas for Fsv Nuclear Station,Platteville,Co ML20137S4481997-04-0808 April 1997 Informs That Decommissioning Activities at Fsv Are Complete & NRC Issued Exemption from Requirements of 10CFR50.54(w) in .Property Damage Insurance Policy Is Maintaned to Protect Fsv balance-of-plant Assets ML20137S0821997-04-0707 April 1997 Forwards Insp Rept 50-267/97-01 on 970310-11.No Violations Noted ML20137S1691997-04-0707 April 1997 Fifth Partial Response to FOIA Request for Documents. Forwards Documents Listed in App K ML20137S5421997-04-0707 April 1997 Forwards Final Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments Affecting Decommissioning of Fort St Vrain Nuclear Station ML20148D5951997-04-0404 April 1997 Forwards Confirmatory Survey for Fsv Nuclear Station, Psc,Platteville,Co, Final Rept ML20137R6921997-04-0404 April 1997 Informs of Approval for Request for Addl 45 Days to Remedy Deficiencies Identified in NRC Re Financial Assurance Mechanism for Fsv Decommissioning Costs ML20137J8051997-03-31031 March 1997 Third Partial Response to FOIA Request for Documents.Records in App F Encl & Will Be Available in Pdr.App G & H Records Withheld in Part (Ref FOIA Exemptions 5 & 7) ML20148D5811997-03-26026 March 1997 Forwards Confirmatory Survey Plan for Group E Effluent Discharge Pathway Areas at Fsv Nuclear Station, Covered in Final Survey Rept,Vol 6 ML20137G7361997-03-25025 March 1997 Requests Addl Time for Util to Respond to NRC Comments in Re Financial Assurance Mechanism for Fort St Vrain Decommissioning Costs ML20137G9521997-03-24024 March 1997 Forwards Quarterly 10CFR50.59 Rept for Period 961201-970228 Re Changes,Tests & Experiments for Fort St Vrain Decommissioning ML20137H1131997-03-24024 March 1997 Second Partial Response to FOIA Request for Documents. Forwards Documents Listed in App D.Documents Also Available in Pdr.Documents Listed in App E Withheld in Part (Ref FOIA Exemption 6) ML20137C0181997-03-18018 March 1997 Documents That No Personnel Has Received Radiation Exposure at Fsv in 1997 or at Any Time Subsequent to ML20137C0061997-03-18018 March 1997 Documents That There Have Been No Activities Involving Release of Radioactive Matls from Fsv Nuclear Station That Potentially Could Have Affected Environ,Subsequent to Previous Radiological Envion Operating Rept ML20136G1201997-03-11011 March 1997 Forwards Annual Radioactive Effluent Release Rept for Jan- Dec 1996 & Jan-Mar 1997. All Effluent Releases Completed as of 960703.Repts on Activities After 960703 Reflect Disposal of Solid Waste ML20136B1331997-02-28028 February 1997 First Partial Response to FOIA Request for Documents. Documents Listed in App a Already Available in Pdr.Forwards App B Documents.App C Documents Being Withheld in Entirety (Ref FOIA Exemption 5) ML20135D7891997-02-27027 February 1997 Forwards Responses to Comments Re Fort St Vrain Final Survey Rept ML20135D9531997-02-27027 February 1997 Forwards Copy of Amend to Util Npdes,Wastewater Discharge Permit CO-0001121,which Clarifies That Monitoring of Farm Pond Outlet Required When Industrial Wastewater Being Discharged Through Upstream Goosequill Ditch ML20135A8711997-02-14014 February 1997 Requests That Encl Deficiencies Identified in Financial Assurance Mechanism for Fort St Vrain Decommissioning Cost Be Addressed within 45 Days ML20134D1551997-01-31031 January 1997 Forwards Util Responses to NRC Comments Provided in NRC Ltr Re Sampling & Survey Plan Used for Final Radiological Survey of Liquid Effluent Pathway at Ft St Vrain ML20134C8481997-01-30030 January 1997 Forwards Draft Confirmatory Survey Rept for Fsv Nuclear Station,Psc,Platteville,Co Providing Info on Essap Activities on 960930-1003 ML20133L4961997-01-0707 January 1997 Forwards Comments That Need to Be Resolved Before Final Approval of Util Submittal Entitled, Proposed Sampling & Survey Plan for Effluent Pathway,Ft St Vrain Final Survey Program ML20133E0481997-01-0202 January 1997 Forwards Comments to Fsv Nuclear Station, Decommissioning Project Final Survey Rept (Volumes 4-11), for Consideration ML20132G0421996-12-23023 December 1996 Forwards Insp Rept 50-267/96-05 on 961203-05.No Violations Noted ML20132F2841996-12-19019 December 1996 Forwards Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments Affecting Decommissioning of Plant,Covering Period of 960901-1130 ML20133A8591996-12-16016 December 1996 Forwards Original & Copy Transcripts of Public Hearing,Held on 961203 in Platteville,Co Re Decommissioning & License Termination of Util Ft Saint Vrain Nuclear Generating Station ML20133N0011996-12-0404 December 1996 Recommends That NRC Require License to Modify Submission of Unexecuted Draft Trust Agreement Remaining Decommissioning Costs for Ft St Vrain Nuclear Generating Station in Listed Ways ML20135B3861996-11-25025 November 1996 Informs That NRC Reviewed Util 961114 Submittal (P-96096) Entitled, Fort St Vrain Final Emergency Response Plan, & Meets Requirements of 10CFR50.54(q) ML20135A5861996-11-25025 November 1996 Submits Suppl Info Re Annual Environ Rept for 1995 Operation of Fsv ISFSI ML20135A6361996-11-20020 November 1996 Submits Copy of Describing Discharge Practices for Groundwater Seeping Into Fsv'S Reactor Building Sump ML20134L4721996-11-14014 November 1996 Notifies NRC That Util Adopted Fsv ISFSI Emergency Response Plan to Direct Emergency Response for Radiological Accidents Occuring at Site,Until 10CFR50 License Is Terminated ML20134F4351996-10-30030 October 1996 Forwards Sections 1,2,6 & 8 from Survey Packages F0015, F0039 & F0126 & Sections 1,2 & 6 from Survey Package F0115 to Support on-site NRC Insp ML20134G5991996-10-30030 October 1996 Forwards Volumes 1-12 to Final Survey Rept for Groups A,B,C Rev 1,D Rev 1,E,F Rev 1 & G-J for NRC Approval in Support of Forthcoming Request for Termination of Fsv 10CFR50 License ML20133D7691996-10-22022 October 1996 Forwards Preliminary Rept Re Orise Support of NRC License Insp at Fsv on 960930-1003 ML20136B1411996-10-15015 October 1996 FOIA Request for Documents Re NOV Addressed to Scientific Ecology Group Re NRC Insp Rept 50-267/94-03 & OI Investigation Repts 4-94-010 & 4-95-015 ML20128M6181996-10-0404 October 1996 Forwards Ltr from PSC to Co Dept of Public Health & Environ Describing Monitoring Practices at Plant ML20128G8041996-10-0101 October 1996 Forwards Fsv Decommissioning Fire Protection Plan Update 1999-03-26
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20205G8771999-03-26026 March 1999 Forwards Copy of Cover Page from Fort St-Vrain Welding Manual,Which Had Been Listed as Encl on Page 4 of 990325 Reply to EA 98-081.Cover Page Had Been Inadvertently Left Out with Original Reply ML20197H8811998-12-0101 December 1998 Forwards Proposed Change to Fsv ISFSI Physical Protection Plan in Which Commitment Is Made to Provide Feature to Security Posture for Facility ML20198K1931997-10-10010 October 1997 Provides Supplemental Info in Support of Util Proposed Rev to Physical Security Plan for Plant Plant Isfsi.Plan Withheld,Per 10CFR2.790(d) & 10CFR73.21 ML20141F3521997-05-14014 May 1997 Forwards Proposed Issue 4 of Physical Security Plan for Fort St Vrain ISFSI for Review & Approval.Encl Withheld,Per 10CFR2.790(d) ML20138G2701997-04-28028 April 1997 Provides Response to NRC Comments Re Proposed Sampling & Survey Plan for Fsv Effluent Pathway.Response Documents Fsv Liquid Effluent Discharge Pathway Areas Are Acceptable for Release for Unrestricted Use IAW Draft NUREG/CR-5849 ML20148D4651997-04-24024 April 1997 Forwards Revised Interim Ltr Rept Which Describes Procedures & Results of Confirmatory Survey of Group E Effluent Discharge Pathway Areas at Fsv Station ML20138B0511997-04-22022 April 1997 Forwards Copy of Proposed Amend to Fsv NPDES Permit, Wastewater Discharge Permit CO-0001121 Requested to Support Repowering Activities,Iaw Section 3.2.d of Fsv Non-Radiological Ts,App B to License DPR-34 ML20140E1061997-04-10010 April 1997 Forwards Confirmatory Survey of Group Effluent Discharge Pathway Areas for Fsv Nuclear Station,Platteville,Co ML20137S4481997-04-0808 April 1997 Informs That Decommissioning Activities at Fsv Are Complete & NRC Issued Exemption from Requirements of 10CFR50.54(w) in .Property Damage Insurance Policy Is Maintaned to Protect Fsv balance-of-plant Assets ML20137S5421997-04-0707 April 1997 Forwards Final Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments Affecting Decommissioning of Fort St Vrain Nuclear Station ML20148D5951997-04-0404 April 1997 Forwards Confirmatory Survey for Fsv Nuclear Station, Psc,Platteville,Co, Final Rept ML20148D5811997-03-26026 March 1997 Forwards Confirmatory Survey Plan for Group E Effluent Discharge Pathway Areas at Fsv Nuclear Station, Covered in Final Survey Rept,Vol 6 ML20137G7361997-03-25025 March 1997 Requests Addl Time for Util to Respond to NRC Comments in Re Financial Assurance Mechanism for Fort St Vrain Decommissioning Costs ML20137G9521997-03-24024 March 1997 Forwards Quarterly 10CFR50.59 Rept for Period 961201-970228 Re Changes,Tests & Experiments for Fort St Vrain Decommissioning ML20137C0061997-03-18018 March 1997 Documents That There Have Been No Activities Involving Release of Radioactive Matls from Fsv Nuclear Station That Potentially Could Have Affected Environ,Subsequent to Previous Radiological Envion Operating Rept ML20137C0181997-03-18018 March 1997 Documents That No Personnel Has Received Radiation Exposure at Fsv in 1997 or at Any Time Subsequent to ML20136G1201997-03-11011 March 1997 Forwards Annual Radioactive Effluent Release Rept for Jan- Dec 1996 & Jan-Mar 1997. All Effluent Releases Completed as of 960703.Repts on Activities After 960703 Reflect Disposal of Solid Waste ML20135D7891997-02-27027 February 1997 Forwards Responses to Comments Re Fort St Vrain Final Survey Rept ML20135D9531997-02-27027 February 1997 Forwards Copy of Amend to Util Npdes,Wastewater Discharge Permit CO-0001121,which Clarifies That Monitoring of Farm Pond Outlet Required When Industrial Wastewater Being Discharged Through Upstream Goosequill Ditch ML20134D1551997-01-31031 January 1997 Forwards Util Responses to NRC Comments Provided in NRC Ltr Re Sampling & Survey Plan Used for Final Radiological Survey of Liquid Effluent Pathway at Ft St Vrain ML20134C8481997-01-30030 January 1997 Forwards Draft Confirmatory Survey Rept for Fsv Nuclear Station,Psc,Platteville,Co Providing Info on Essap Activities on 960930-1003 ML20133E0481997-01-0202 January 1997 Forwards Comments to Fsv Nuclear Station, Decommissioning Project Final Survey Rept (Volumes 4-11), for Consideration ML20132F2841996-12-19019 December 1996 Forwards Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments Affecting Decommissioning of Plant,Covering Period of 960901-1130 ML20133A8591996-12-16016 December 1996 Forwards Original & Copy Transcripts of Public Hearing,Held on 961203 in Platteville,Co Re Decommissioning & License Termination of Util Ft Saint Vrain Nuclear Generating Station ML20133N0011996-12-0404 December 1996 Recommends That NRC Require License to Modify Submission of Unexecuted Draft Trust Agreement Remaining Decommissioning Costs for Ft St Vrain Nuclear Generating Station in Listed Ways ML20135A5861996-11-25025 November 1996 Submits Suppl Info Re Annual Environ Rept for 1995 Operation of Fsv ISFSI ML20135A6361996-11-20020 November 1996 Submits Copy of Describing Discharge Practices for Groundwater Seeping Into Fsv'S Reactor Building Sump ML20134L4721996-11-14014 November 1996 Notifies NRC That Util Adopted Fsv ISFSI Emergency Response Plan to Direct Emergency Response for Radiological Accidents Occuring at Site,Until 10CFR50 License Is Terminated ML20134F4351996-10-30030 October 1996 Forwards Sections 1,2,6 & 8 from Survey Packages F0015, F0039 & F0126 & Sections 1,2 & 6 from Survey Package F0115 to Support on-site NRC Insp ML20134G5991996-10-30030 October 1996 Forwards Volumes 1-12 to Final Survey Rept for Groups A,B,C Rev 1,D Rev 1,E,F Rev 1 & G-J for NRC Approval in Support of Forthcoming Request for Termination of Fsv 10CFR50 License ML20133D7691996-10-22022 October 1996 Forwards Preliminary Rept Re Orise Support of NRC License Insp at Fsv on 960930-1003 ML20136B1411996-10-15015 October 1996 FOIA Request for Documents Re NOV Addressed to Scientific Ecology Group Re NRC Insp Rept 50-267/94-03 & OI Investigation Repts 4-94-010 & 4-95-015 ML20128M6181996-10-0404 October 1996 Forwards Ltr from PSC to Co Dept of Public Health & Environ Describing Monitoring Practices at Plant ML20128G8041996-10-0101 October 1996 Forwards Fsv Decommissioning Fire Protection Plan Update ML20128G0481996-09-30030 September 1996 Submits Rev to Psco Definitions of Contents of Documentation Packages Re Fsv Final Survey Project ML20129C0421996-09-20020 September 1996 Forwards Quarterly Submittal of 10CFR50.59 Rept of Changes, Tests & Experiments for Facility Decommissioning,Covering Period of 960601-0831 ML20133D7601996-09-16016 September 1996 Forwards Confirmatory Survey Plan for Fsv Nuclear Station Decommissioning Project,First Final Survey Rept Submittal- Vols 1-5.NRC Comments Incorporated.Spending Plan Attached ML20117P0711996-09-13013 September 1996 Describes Util Plans to Remove Bldg 28 from Plant Facility ML20129A4431996-09-11011 September 1996 Describes Util Plans for Demonstrating That Liquid Effluent Pathway & Surrounding Open Land Areas Satisfy 10 Mrem/Yr Criteria Provided in Plant Final Survey Plan ML20117K5291996-09-0404 September 1996 Provides Notification That Util Will Be Revising Financial Assurance Mechanism That Will Be Used to Cover Remaining Costs of Decommissioning Plant ML20117C7281996-08-22022 August 1996 Discusses Impact of Final Decommissioning Rule & Requests NRC Concurrence That Requirements to Submit & Obtain Approval of License Termination Plan Have Been Satisfied ML20116P3431996-08-16016 August 1996 Describes Actions to Remove Structures & Equipment Items from Fort St Vrain Facility for NRC Info.Requests That NRC Advise Util of Wishes to Perform Confirmatory Survey of Any Parts of New Fuel Storage Building Before 960903 ML20133D7551996-08-14014 August 1996 Provides Environ Survey & Site Assessment Program'S (Essap) Comments Re Review of Fsv Nuclear Station Decommissioning Project Final Survey Rept ML20116M0771996-08-14014 August 1996 Provides Suppl Response to Re Insp Rept 50-267/96-01 in Jan 1996 Re NRC Concerns About Fsv Final Survey Program.Specifically,Bias in Instrumentation Response Overestimating Amount of Contamination Present ML20116M1841996-08-13013 August 1996 Forwards Util Responses to NRC Comments in Re Use of in-situ Gamma Spectroscopy to Measure Exposure Rates During Plant Final Survey.Approval to Use in-situ Gamma Spectroscopic instrument,Microspec-2,requested ML20116K0061996-08-0909 August 1996 Submits Fort St Vrain Nuclear Station Decommissioning Project Final Survey Rept ML20116M1241996-08-0808 August 1996 Responds to NRC Bulletin 96-004, Chemical,Galvanic,Or Other Reactions in Spent Fuel Storage & Transportation. Informs That Modular Vault Dry Storage Sys Is Not Susceptible to Problems Addressed in Bulletin ML20116F3611996-08-0202 August 1996 Submits Revised Documentation for Fort St Vrain Final Survey Program ML20116F8141996-08-0202 August 1996 Informs of Util Intent to Modify Fort St Vrain Control Room,Which Will Make Certain Final Survey Locations Unavailable for Further Review.Final Survey Efforts Are Complete ML20116A4511996-07-19019 July 1996 Requests NRC Approval of Proposed Method to Fsv Final Survey Plan to Determine Exposure Rates in Prestressed Concrete Reactor Vessel 1999-03-26
[Table view] Category:UTILITY TO NRC
MONTHYEARML20059H9471990-09-14014 September 1990 Forwards Rev to Proposed Physical Security Plan,Per .Encl Withheld (Ref 10CFR73.21) ML20064A6841990-09-14014 September 1990 Notifies That Ms Frazier License OP-5608-1 Terminated Effective 900906,per 10CFR50.74 ML20059K2091990-09-14014 September 1990 Requests That Dj Trumblee Reactor Operator License Be Terminated,Effective 900912 ML20059L5831990-09-14014 September 1990 Forwards Application for Amend to License DPR-34,changing Tech Spec Design Features Section to Remove CRD & Orifice Assemblies from Core Regions Defueled in Support of Plant Closure Activities ML20059D3231990-08-15015 August 1990 Forwards fitness-for-duty Performance Data Rept for Plant ML20058N5661990-08-0808 August 1990 Requests Exemption from 10CFR50.54(w)(1) Requirements for Min Property Insurance Coverage ML20058L8031990-08-0303 August 1990 Forwards GA-C18103, Fort St Vrain Cycle 3 Core Performance, Per Request for Addl Info Re Proposed Amend to Tech Spec Which Would Allow Util to Complete Defueling of Facility ML20058M1931990-07-31031 July 1990 Advises of Termination of Kj Einig Reactor Operator License, Effective 900727 ML20056A1791990-07-30030 July 1990 Responds to NRC Re Violations Noted in Insp Rept 50-267/90-07.Corrective Actions:Electrical & Mechanical Craft Personnel Assigned to Planning & Scheduling Organization ML20055H8091990-07-23023 July 1990 Forwards Addl Info in Support of 900622 SAR for Isfsi. Proprietary SAR Withheld (Ref 10CFR2.790) ML20056A1711990-07-20020 July 1990 Discusses Decommissioning Funding for Plant.Util Revised Decommissioning Financial Plan,Based on Safstor,Currently in Effect & Funds Will Be Accumulated Per Plan Provisions ML20055H6571990-07-20020 July 1990 Responds to NRC Bulletin 90-001, Loss of Fill Oil in Transmitters Mfg by Rosemount. No Rosemount Model 1153 or 1154 Transmitters Presently in Use at Plant ML20058P6891990-07-20020 July 1990 Forwards Security Plan for Proposed ISFSI for NRC Review,Per 900622 & 0412 Ltrs.Plan Withheld (Ref 10CFR73.21) ML20055G8601990-07-20020 July 1990 Responds to NRC Re Violations Noted in Insp Rept 50-267/90-07.Corrective Actions:Site Mgt Recognized Applicability of 10CFR50.72(b)(2)(vi) Re Previous Day Notification & Immediately Notified NRC ML20055H2811990-07-20020 July 1990 Forwards Rev 4 to Updated Fire Protection Plan ML20055G7061990-07-20020 July 1990 Forwards Application for Amend to License DPR-34,revising Tech Spec 6.1 to Remove Equipment to Support Plant Closure ML20059D1361990-07-13013 July 1990 Applies for Exemption from Payment of Annual Fees for FY90, Per 10CFR171 ML20055E0401990-07-0303 July 1990 Forwards Issue 3 to FPOR-18, Fire Protection Operability Requirements, as Result of Rev 3 to Facility Fire Protection Plan ML20055E0331990-07-0202 July 1990 Informs of Plans to Remove B Helium Circulator from Plant Prestressed Concrete Reactor Vessel in Mannner Similar to Previous Circulator Maint Outages.Requests Timely Ack of NRC Concurrence W/Undertaking ML20055E9171990-06-29029 June 1990 Resubmits Semiannual Radioactive Effluent Release Rept Jul-Dec 1989, as Result of Omitted Tables ML20044A8281990-06-29029 June 1990 Notifies of Termination of Wj Ashmore,License SOP-43244 & Requests That Reactor Operator License Be Terminated Effective 900620,per 10CFR50.74 ML20055D3931990-06-29029 June 1990 Forwards Response to Generic Ltr 90-04,requesting Info on Status of Generic Safety Issues.W/O Encl ML20055D1591990-06-22022 June 1990 Forwards Proposed Change to Updated Fsar,App B Re Use of Controls Other than Change Notice Sys to Implement Mods Such as Cutting & Capping of Piping,In Order to Obtain Positive Equipment Isolation ML20043J0581990-06-15015 June 1990 Forwards Proposed Issue 5 to Fort St Vrain Nuclear Generating Station Defueling Emergency Response Plan, Deleting Offsite Emergency Response Capabilities,Per Util 890816 Defueling SAR & NUREG-0654 ML20043D3291990-05-25025 May 1990 Forwards Response to NRC 900330 Ltr Re Violations Noted in Insp Rept 50-267/90-04.Encl Withheld (Ref 10CFR73.21) ML20055D2051990-05-25025 May 1990 Responds to Violations Noted in Insp Rept 50-267/90-06. Corrective Actions:Extensive Training on Radiological Emergency Response Plan Implementing Procedures Will Be Provided to Operating Crews Beginning in May 1990 ML20043C8981990-05-25025 May 1990 Responds to NRC 900427 Ltr Re Violations Noted in Insp Rept 50-267/90-05.Corrective Actions:Mgt Will Continue to Stress Requirement for Procedural Compliance on Ongoing Basis ML20043B3691990-05-22022 May 1990 Describes Util Current Plans for Removal of Certain Plant Equipment Items.Components to Be Removed Have No Required Nor Useful Function During Planned or Postulated Remaining Defueling or Shutdown Conditions ML20043A9491990-05-11011 May 1990 Forwards Issue 59 to AOP-K-1, Environ Disturbances - Earthquake. ML20042F9771990-05-0404 May 1990 Forwards Assessment of Possible Sources of Water in Plant Core,Means of Detecting Water in Pcrv & Effects of Water Ingress on Reactivity,For Info ML20042F9011990-05-0101 May 1990 Forwards Conceptual Plan & Cost Estimates for Early Dismantlement of Fort St Vrain Pcrv, Per NRC 900315 Request ML20042E8911990-04-27027 April 1990 Requests 30-day Extension to 900529 to Submit Response to Violations Noted in Insp Rept 50-267/90-04 ML20042F3111990-04-26026 April 1990 Forwards Application to Amend License DPR-34,providing Tech Spec Changes Needed to Complete Defueling ML20012D4711990-03-19019 March 1990 Requests Approval of Encl Exemption Request Allowing Util to Accumulate Decommissioning Funds Beyond Termination of Operations ML20012B7541990-03-0707 March 1990 Informs of Electronic Transfer of Fees on 900307 for Invoice IO547 ML20011F4691990-02-22022 February 1990 Responds to NRC 900116 Ltr Re Violations Noted in Insp Rept 50-267/89-23.Violation Re Fire Doors 13 & 9 Between 480-volt Ac Switchgear Room & Bldg 10 Propped Open on 891129 Disputed.Improved Communications Underway ML20006E7821990-02-15015 February 1990 Forwards Responses to 891004 Questions Re Decommissioning Financial Plan ML20011E8941990-02-0707 February 1990 Responds to 890719 NRC Bulletin 89-002 Re safety-related Anchor/Darling Model S350W Swing Check Valves.Licensee Reviewed Plant Data Base & Design Documents & Concludes That No Anchor/Darling Model S350W Valves Installed at Plant ML20011E7861990-02-0707 February 1990 Forwards Overview of Evaluation on Compliance W/Environ Qualification Regulation (10CFR50.49) During Defueling of Facility.During Defueling,Pcrv Will Be Maintained at Nearly Atmospheric Pressures & Rapid Depressurization Not Possible ML20011E5031990-02-0606 February 1990 Notifies of Termination of Ma Rhoton Employment W/Util, Effective 900206 ML20006D6621990-02-0606 February 1990 Responds to Generic Ltr 89-13, Svc Water Sys Problems Affecting Safety-Related Equipment. Currently Established Preventive Maint & Tech Spec Surveillance Activities on HXs Remaining in Svc Will Continue ML20006B2091990-01-26026 January 1990 Forwards Fire Operability Requirements 3 & 14,Issues 3 & 4, Respectively,To Fire Protection Program Plan,Section FP.6.1. Changes Cover Halon Sys & Basis & Records Ctr Halon Sys ML20006B7791990-01-25025 January 1990 Forwards Application for Amend to License DPR-34,changing Section 7.1 of Tech Specs.Specifically,Senior Vice President,Nuclear Operations Revised to Vice President, Nuclear Operations & Nuclear Training Manager Revised ML20006A5001990-01-19019 January 1990 Notifies of Util Intent to Bore 10 Concrete Core Drills Into Prestressed Concrete Reactor Vessel Barrel Section at Various Elevations Found Necessary for Decommissioning Planning.Drillings Wil Begin on 900205.Assessment Encl ML20006A5041990-01-19019 January 1990 Responds to NRC 891218 Ltr Re Weaknesses Noted in Insp Rept 50-267/89-22.Corrective Actions:During Power Operations Three Licensed Reactor Operators Will Be Present in Control & Short in Emergency Public Address Sys Repaired ML20005G5001990-01-12012 January 1990 Forwards Approved Proposed Change to NPDES Permit to Use Halocide Product for Microbiological Control in Smaller Cooling Tower ML19354D8581990-01-0505 January 1990 Forwards Safety Assessment of Proposed Changes to Fire Protection Program Plan,Per P Erickson Request.Changes Cover Acceptance Criteria for Shutdown Cooling Following Fire & New Fire Protection Cooldown Trains 1 & 2 ML20005F5531990-01-0303 January 1990 Certifies That Util Has Implemented fitness-for-duty Program Meeting 10CFR26 Requirements ML20005D8921989-12-21021 December 1989 Forwards Proposed Change to Plant NPDES Permit ML19354D7441989-12-0808 December 1989 Requests Relief from Requirements of Generic Ltr 89-10 Re motor-operated Valves Since Plant Permanently Shut Down Since 890818 & Defueling Initiated on 891127 1990-09-14
[Table view] |
Text
3 s
0rubiicservice- : ": :.'
P.O. Box 840 Dene,co so20m November 22, 1985 Fort St. Vrain OSCAR R. LEE Un .1 VICE PRESIDENT Mr. Samuel J. Chilk, Secretary U.S. Nuclear Regulatory Commission 1717 H. Street N.W.
Washington, DC 20555 Docket No. 50-267
SUBJECT:
Revision of Request for Special Consideration and Schedule Extension, 10CFR50.49
REFERENCE:
PSC Letter Walker to Chilk dated September 24, 1985 (P-85334)
Gentlemen:
The Public Service Company of Colorado (PSC) withdraws the schedule extension request for the Fort St. Vrain (FSV) Environmental Qualification (EQ) ? mgram in the referenced letter, and hereby requests approval CY t revised schedule extension for implementation of the FSV Er F. #7- beyond November 30, 1985, under the provisions of paragraph c ' e,( .!FR50.49. This request contains a revised justification 'for continued operation which would restrict Fort St.
Vrain operation to 35 percent of rated power during a schedule extension period which would expire May 31, 1986. The exceptional circumstances that warrant this schedule extension to May 31, 1986 have not been revised, and are included herein for completeness.
Exceptional Circumstances
- 1) The FSV plant is a High Temperature Gas-Cooled Reactor (HTGR),
the only one of its kind in the USA. Because of this uniqueness, ,
the equipment qualification information sharing available to the i Light Water Reactor industry was in most cases not available or applicable to FSV because of the higher temperature harsh environments encountered during postulated FSV accident conditions.
g ; g7 0 t I
t 2)';The EQ ' rule '(10CFR50.49) does not recognize the unique aspects
.., and design characteristics of an HTGR, and there is essentially no; HTGR EQ guidance available within the nuclear industry. This p imposed upon PSC the' added burden of determining the applicability of bulletins, NUREGs, and regulations on the EQ issue to the HTGR. In particular, the.NRC order for modification of the- FSV license concerning EQ, issued on October 27, 1980, required.PSC to determine and apply to the FSV plant the environmental qualification requirements in the D0R guidelines or NUREG 0588 "to the extent applicable to a gas-cooled reactor".
PSC did indeed make the required determinations and submitted to the NRC their understanding of how the EQ program would apply to an HTGR, and in particular to FSV. Attachment 1 to the referenced letter provides a summary of the chronology of significant events involving the development of the FSV EQ program which clearly documents that PSC has consistently applied its .best efforts in developing the FSV EQ p ogram. Since January, 1985, the FSV Environmental Qualification Program has greatly benefitted from written NRC staff guidance in applying the required regulations to the FSV HTGR.
- 3) Although the recent NRC staff guidance has been helpful, FSV is currently still in the unique and exceptional situation of never having received from the NRC a comprehensive Technical Evaluation Report (TER) or Safety Evaluation Report (SER), including required corrective actions, in response to the proposed FSV EQ program. These NRC evaluations would be of genuine assistance as evidenced :by the meaningful and constructive interactions with the NRC staff that have taken place since January 1985. As a result of these interactions, PSC has launched into an aggressive
. evaluation / corrective action program to resolve the various FSV EQ technical issues.
- 4) Since The early 1970's a basic assumption of the FSV EQ program has been-that plant operating personnel would be able to complete l
- a number' of. manual actions to isolate a high energy line break during the first four minutes of an accident.* This position was ;
reviewed and approved as part of Supplement No. 1 to the NRC SER for the FSV operating license in June 1973, and as part of Amendment No. 18 to the plant operating license in October 1977.
! In January 1985 PSC was notified that as a matter of NRC policy, this four minute operator response time assumption may no longer be considered valid. This notification constituted a fundamental change in the previously- approved licensing basis of the FSV plant.
t' i
- D
'Since January 1985, it is PSC's understanding that, under current
.. NRC policy, operators cannot be relied upon to ir.itiate required manual actions for at least ten minutes following the onset of an accident. Because a ten minute operator response time would be technically unacceptable due -to FSV's high temperature steam conditions and the resulting FSV environmental accident conditions, PSC has recently committed to the installation of an automatic Steam Line Rupture Detection / Isolation System. While this new system will resolve a number of FSV EQ technical issues, the related FSV EQ programmatic changes will require an extended period of time to implement.
Justification for Continued Operation Prior to the exceptional circumstances that arose in early 1985, the redundant safe shutdown, forced circulation cooling water systems using firewater were considered qualified to respond to the design basis Fort St. Vrain harsh environment accident conditions. However, with the modified requirements that resulted from the recent interactions with the NRC staff, not all of this equipment can be considered fully qualified to the requirements of 10CFR50.49. PSC has determined that in the interim period until all of this equipment can be qualified, the health and safety of the public can be adequately protected by placing a 35 percent power level restriction on the operation of the Fort St. Vrain plant. The following is a summary of the safety aspects associated with operation at power levels not to exceed 35 percent of rated power.
During this proposed interim period of restricted operation, PSC would maximize reliance on non-electrical equipment and systems which can be manually actuated to mitigate the consequences of harsh environment accidents, and therefore, does not require environmental qualification. With the 35 percent power level restriction, only the PCRV liner cooling system, using firewater supplied by pumps located outside the harsh environment, would be required to provide core cooling. Due to the high heat capacity and slow thermal response of the reactor core, a period of many hours is available before manual actuation of PCRV liner cooling would be required.
, With the 35 percent restriction, no fuel particle coating failures would occur during a harsh environment accident beyond those already assumed and analyzed for nonnal full power operation in the FSV Final Safety Analysis Report (FSAR) and the bases for the FSV Technical Specifications. Relying only on the PCRV liner cooling system for core cooling, the fuel particle coatings would maintain their required integrity throughout the various postulated harsh environment accident conditions. Additionally, in the event that the PCRV could not be depressurized during a postulated accident from 35 percent of rated power, calculations have shown that peak fuel temperatures would be further reduced from the depressurized peak
. fuel temperature case, thereby providing additional margin for assuring fuel particle integrity.
The PCRV reactor coolant pressure boundary steel liner would retain its integrity following the various postulated high energy line breaks from 35 percent power, and the PCRV concrete fission product containment boundary would continue to perform its safety function.
Since there is no breach of either the reactor coolant pressure boundary or the containment boundary, there would be no release of abnormal quantities of fission products to the Reactor Building atmosphere. Offsite doses caused by a high energy line break and subsequent PCRV liner cooldown fron 35 percent power would be negligible.
For reactor operation at 35 percent of rated power, all safety features of the FSV Plant Protective System are in effect, as required by the Technical Specifications. PSC considers interim operation with these plant safety features fully in effect to be most prudent to protect against the complete spectrum of possible accident conditions.
PSC considers that operation of FS" at reactor power levels not to exceed 35 percent of rated will estatlish the necessary conditions to meet the intent of 10CFR50.49 for interim operation of FSV in that:
A. The integrity of the reactor coolant pressure boundary can be maintained.
B. The reactor can be shutdown and maintained in a shutdown condition.
C. Offsite exposures remain well below 10CFR100 guidelines.
.1 The above . justification for continued operation with a 35 percent
. power level restriction has been discussed with the NRC staff and the results of the various analyses have been presented by PSC. However, 1PSC acknowledges that formal written evaluations confirming the above justification and conclusions will have to be submitted to the NRC staff for final review prior to plant operation up to the 35 percent power restriction.. Attachment 1 to this letter lists the detailed technical evaluations which must be documented and submitted to the NRC' staff for.their final review regarding the: safety benefits of the 35 percent power restriction.
Necessity For Schedule Extension PSC has been aggressively pursuing the environmental qualification of Fort St. Vrain safe shutdown, forced circulation cooling systems and equipment since the inception of the environmental-qualification concern in.the early 1970's -(see Attachment 1 to the. referenced letter). Much of this earlier work involved actual environmental qualification testing at steam temperatures and conditions much more severe = than those required for light water reactor equipment qualification. This environmental qualification testing work -was performed throughout the 1970s and early 1980s on the Fort St. Vrain l equipment and-systems requiring qualification. This extensive EQ L testing program was required by the higher temperatures and pressures present in Fort St. Vrain steam piping systems at the onset of a high -
energy line break accident.
However, all of this EQ testing work was based on accident
. temperature profiles which assumed a four minute operator response time, which had previously been reviewed and approved by the NRC on two occasions. Upon being informed of the current NRC position in January 1985, i.e., that the NRC is no longer-convinced that Fort St.
.Vrain operators can respond to a high energy line break in less than ten . minutes, the fundamental basis of the original Fort St. Vrain environmental qualification program was disallowed. Consequently building temperature ' profiles resulting from the high temperature steam conditions at Fort St. Vrain made it impossible to requalify l the required equipment for the environment resulting from a ten minute high temperature steam leak.
PSC has now committed to the design and installation of a Steam Line Rupture Detection / Isolation System (SLRDIS). However, additional time will be required to complete the design, licensing and installation of this automatic system. The impacts and effects of this altered direction on the Fort St. Vrain EQ program are substantial:
I l
l 4
- 1. Revised Reactor Building and Turbine Building temperature profiles must be developed for the spectrum of line break sizes which will be either: (1) automatically detected and isolated by SLRDIS,(2) detected and alarmed by SLRDIS but isolated by operator action after ten plus minutes, or (3) be small leaks
-which are detected by operators making their normal rounds and !
isolated by operator action.
- 2. NRC concerns with Fort St. Vrain equipment aging and operability times must be resolved. The above mentioned temperature profiles must be developed before the aging and operability time work can be finalized. .
- 3. SLRDIS must be designed and approved by the NRC (SLRDIS will require FSV Technical Specification changes and appears to involve an unreviewed safety question). The installation of SLRDIS must then be completed and tested.
- 4. The 10CFR50.49 environmental qualification work on the new equipment being added for the SLRDIS must be completed.
- 5. The EQ program documentation and equipment qualification files must be revised to reflect the resolution of the above issues.
PSC has been actively pursuing the resolution and completion of the above work since early-1985 when NRC's concerns with the Fort St.
Vrain EQ program were identified. Attachment 2 to this letter contains additional details on the environmental qualification work currently in progress. Completion of this work will, however, require a schedule extension to May 31, 1986, which is hereby requested.
Sumary
- PSC has acted in good faith and with due diligence with regard to the EQ program for FSV. PSC is convinced that the FSV EQ program has had to confront unique and exceptional circumstances, which are deserving of a schedule extension. ,
- Fort St. Vrain can be operated up to 35 percent of rated power without compromising the integrity of fuel particle coatings or other fission product barriers with cooling provided by the liner cooling flow paths using fire water in the event of a harsh environment accident. The confirmatory evaluations of Attachment I will be provided to the NRC staff.
l i
- .PSC will continue to aggressively pursue all efforts required to assure that SLRDIS and the redundant FSV safe shutdown, forced circulation cooling systems are qualified to the requirements of 10CFR50.49 on or before May 31, 1986.
PSC would be pleased to provide additional information or respond to any questions you may have regarding this request for extension of the Fort St. Vrain EQ program schedule.
Very truly yours, 0.R. Lee, Vice President Electric Production ORL/MHH:jmt Attachments @{M '
y cc: Director, NRR, NRC Director, IE, NRC
Attachment 1
. to P-85832 CONFIRMATORY ACTIONS IN SUPPORT OF THE FORT ST. VRAIN 35 PERCENT POWER RESTRICTION DURING THE ENVIRONMENTAL QUALIFICATION SCHEDULE EXTENSION PERIOD PSC will complete and document the following actions to confirm the acceptability of a 35 percent power restriction during the Fort St.
Vrain environmental qualification schedule extension period to May 31, 1986. PSC will submit the results of these actions to the NRC staff for review and approval prior to resuming Fort St. Vrain plant operation at power levels up to the 35 percent power restriction.
- 1. Complete an evaluation which confirms that PCRV liner cooling using fire water can be utilized to prevent significant damage to any of the fission product barriers, including fuel particle coatings, in the event of a high energy line break at power levels up to the 35 percent power restriction.
- 2. Evaluate the leak tightness and structural integrity of the PCRV during the heatup which would occur following an extended loss of forced circulation cooling resulting from a high energy line break from 35 percent of rated power. Consider the cold reheat helium interspace leak, PCRV penetrations and seals, and other portions of the PCRV where leakage may be a concern. Actual PCRV leakage experience should be considered (e.g., the recent LER on the PCRV penetration cold reheat helium leak).
- 3. Provide high energy line brean temperature profiles for accidents from reactor power levels up to 35 percent demonstrating access to plant areas where operators are required to take the necessary manual actions by specified times. Identify all assumptions made regarding operator response times to the high energy line break, Credit will be taken only for qualified systems. An evaluation will be made for the need for SLRDIS for 35 percent power operation.
- 4. Provide an evaluation of the estimated time and primary coolant temperature beyond which the PCRV should not be depressurized during the remainder of a PCRV liner c,oldown following a postulated high energy line break from the 35 percent power level.
1
Attachment 1 to P-85432
, 5. Provide an estimate of the maximum reactor power level at which it would be safe to perform a pressurized PCRV liner cooldown while protecting the integrity of the PCRV liner and liner cooling system.
- 6. Submit a plan and perform inservice inspections on several critical areas of Fort St. Vrain's high energy piping to verify the integrity of this piping, prior to returning the plant to operation.
- 7. Evaluate the need for actuating the Fort St. Vrain reserve shutdown system for postulated high energy line breaks from power levels up to 35 percent. Determine the latest time by which manual actuation must be accomplished, if needed, and evaluate the feasibility of taking the required manual actions by this time.
- 8. Confirm that procedures for taking the necessary operator actions in response to a high energy line break from 35 percent power will be in place prior to resuming Fort St. Vrain plant operation. Evaluate the need for any chances to the Fort St.
Vrain Technical Specifications to accommodate Fort St. Vrain operation up to the 35 percent power level restriction, including the possible use of a pressurized PCRV liner cooldown in the event of a high energy line break.
- 9. Document the extent of PCRV damage expected during a liner cooldown from 35 percent power following, a high energy line break.
- 10. Evaluate the effect of a PCRV liner cooldown from the 35 percent power level on the previously analyzed PCRV hot spots.
- 11. Evaluate the impacts on the integrity of the PCRV liner cooling system of re-establishing liner cooling after prolonged periods of core heating without liner cooling or forced circulation cooling. Verify that the impacts of re-establishing liner cooling following a postulated high energy line break from 35 percent power with a pressurized liner cooldown would be no worse than those for the depressurized liner cooldown after 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br /> from full power previously evaluated in the Fort St. Vrain FSAR.
Compare the associated heat fluxes to the maximum acceptable heat flux to the PCRV liner cooling system assuming single loop operation.
- 12. If Fort St. Vrain operators will be required to take manual actions in environments whose temperatures exceed normal power plant operating temperatures to respond to high energy line breaks from 35 percent power, provide the NRC with information on the ability of operators to work in these higher temperature environments and the need for operators to utilize cool suits.
L
Attachment 1 to P-85432
, 13. Provide a sumary listing of which systems and their associated equipment items are considered qualified for 35 percent power operation, and a confirmation that no unqualified equipment items are needed.
- 14. Submit an engineering evaluation that describes the systems and equipment,which will be utilized to respond to a high energy line break from 35 percent power.
o
Attachment 2 to P-85432
- 1. Safe Shutdown Cooling Path Reviews and Evaluations In order to ensure full compliance with 10CFR50.49, PSC is performing an evaluation of safe shutdown cooling modes at Fort St. Vrain. The purpose of these evaluations is to independently identify all components required for safe shutdown cooling and to ensure that the electrical equipment in these modes is included in Fort St. Vrain's Environmental Qualification Program.
As described in the FSAR, two basic modes of core cooling are available at Fort St. Vrain, redundant forced circulation safe shutdown cooling systems and redundant PCRV liner cooling flow paths. Although there are various means to accomplish each of these modes of core cooling, certain systems and components have been designated as required for safe shutdown cooling.
Both Fort St. Vrain Operation's personnel and Engineering personnel are participating in the evaluation of these core cooling mode evaluations. Existing plant operating procedures are being utilized to identify systems and flow paths for these cooling modes. P&I's are being reviewed in detail to identify all electrical equipment in these systems and flow paths.
Finally, the electrical schematic diagrams are being reviewed to ensure that all electrical components are identified.
- 2. Field Walkdown Efforts A walkdown of safe shutdown equipment is being performed to verify the installed condition of the equipment and to ensure that the equipment installed is the equipment analyzed in the EQ program. Thus far this walkdown has identified a number of concerns such as contaminated junction boxes, unanalyzed taped splices, equipment model number discrepancies, and unanalyzed equipment installation configurations. All of these concerns are presently being addressed as part of the overall EQ program.
Corrective action is presently underway. Site forces are presently being supplemented to mount an aggressive field work program to accomplish corrective action as soon as possible.
l
Attacliment 2 to P-85432
, 3. Aging and Operability Time Studies PSC has been involved in an extensive effort to provide full qualification of our safe shutdown equipment, including aging and operability times. The method used for qualification is based on current industry practice, and is based on conservative ambient temperatures and High Energy Line Break (HELB) profiles. Any age sensitive material whose qualified life does not extend into the next refueling outage will be replaced before May 31, 1986.
The results of numerous preliminary aging and operability time studies have been submitted to PSC by our consultants and have been reviewed. The results of these studies are presented below in tabular form.
TABLE 1: STATUS OF AGING AND OPERABILITY TIME STUDIES TOTAL NUMBER TOTAL NUMBER OF ITEMS OF COMPONENTS l EQUIPMENT REQUIRED 156 1246 FOR SAFE SHUTDOWN EQUIPMENT REVIEWED 74 742 TO DATE EQUIPMENT FOUND TO 56 594 BE ACCEPTABLE NOTE: Several components may constitute one item; for example, if there are six valves of the same type, the valve type would be considered one item and the six individual valves would be considered six components.
The acceptability of the components identified in Table 1 are based purely on their ability to withstand a high energy line break. This number does not account for any additional field work required (e.g. field splices, cleaned junction boxes, etc.).
o Attachment 2 to P-85432
. The results are presented in preliminary form due to the preliminary nature of -the existing HELB profiles. Once the profiles are finalized, the results will be submitted to PSC in their final form. The qualification packages will be included in the FSV auditable files.
The aging and operability time studies have been impacted by the recent decision to install a steam line rupture detection / isolation system. These studies are being conducted utilizing the new preliminary steam line rupture detection / isolation system profiles.
- 4. Temperature Profiles Originally, the FSV Environmental Qualification Program was based on Reactor Building and Turbine Building temperature profiles
-that assumed a 4 minute isolation time based on operator action.
In order to resolve the 4 = minute versus 10 minute operator response time issue, PSC committed to install an automatic steam line rupture detection / isolation system. As a result the building HELB temperature profiles must be reanalyzed. Due to rapid isolation of the systems, preliminary scoping studies indicate that the new temperature profiles have a significantly reduced impact on the environmental qualification of electrical equipment. However, these profiles must be first evaluated and then submitted to NRC. The reanalysis of the temperature profiles is very critical to many of the programs and evaluations presently underway. The reanalyses, however, is time consuming.
PSC is proceeding as rapidly as possible to finalize these effects.
l i
- 3-4
~.
Attachment 2 to P-85432
, 5. Steam Line Rupture Detection / Isolation System The detection portion of the steam line rupture detection / isolation system is currently scheduled for delivery and installation by mid-December. Following installation, PSC will proceed with an extensive functional test to ensure the that system will not activate spuriously. PSC expects an in service date of May 31, 1986.
The steam line rupture detection / isolation system should resolve the 4 minute versus 10 minute operator response time issue for isolation of an HELB. This will greatly decrease the amount of energy that will be released into the reactor or turbine building, resulting in environmental qualification HELB profiles that have significantly reduced impact on the environmental qualification of electrical equipment.
- 6. Electrical Coordination Study An engineering evaluation was conducted to ensure selective fault clearing on the essential AC and DC load centers to confirm the safe operation of the plant in the event of a steam line rupture.
This review identified 2 breakers requiring setpoint changes, 1 circuit requiring rewire, 3 breakers requiring changeout and 5 valve breaker sections requiring additional fuse installation.
- 7. Auditable Files With the addition of aging and operability times, it is necessary to establish a new auditable file system for our EQ documentation. The new file system will be based on the criteria identified in IE Information Notice 85-39. Auditable files for the safe shutdown cooling equipment will be complete by May 31, 1986.
. Attachment 2 to P-85432
. 8. Other Reviews To complement the other systems reviews, the following activities are being performed.
(a) Identification of the electrical state (energized versus de-energized) of the electrical components required to achieve safe shutdown, both in normal plant operation and during the post steam line break state.
(b) Review and delineation of the function of the components required to achieve safe shutdown, both in normal plant operation and during the post steam line break state.
(c) Review of all the electrical circuitry for the components in Item (b) to assure that any subcomponent or circuitry involved is: (1) in the EQ Program; (2) that an analysis has been performed to determine that its EQ induced . failure will not compromise the components safe shutdown function; or (3) being added to the EQ program.
(d) Detennination of the anticipated cyclic operation of electricol components to include past and future operation, testing, calibration, and safe shutdown functions. This is being used as part of the aging evaluation and overall qualification review of each component.
All of the above evaluations, reviews or studies will be included as part of the overall EQ documentation by May 31, 1986.