Staff Requirements Memo on 870226 Briefing on Status of & Possible Vote in Washington,Dc Re Restricted Power Levels for Facility.Commission Decided Not to Vote on Restart of Plant
ML20207R230
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 03/11/1987
From: Chilk S
NRC OFFICE OF THE SECRETARY (SECY)
To: Parler W, Stello V
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO), NRC OFFICE OF THE GENERAL COUNSEL (OGC)
References
REF-10CFR9.7 M870226A, NUDOCS 8703160454
Download: ML20207R230 (2)


Text

IN RESPONSE, PLEASE e'

S 0

\\W s

o UNITED STATES f

NUCLEAR REGULATORY COMMISSION

/j_,d n

I E

WASHIN GTON, D.C. 20555 e

$'+,*****#'#

$2.-G7 March 11, 1987

/

OFFICE OF THE SECRETARY MEMORANDUM FOR:

Victor Stello, Jr.

Executive Director for Operations William C. Parler, General Counsel (D

Samuel J. Chil,'$

FROM:

Fecretary

SUBJECT:

STAFF REQUIREMENTS - BRIEFING ON STATUS OF AND POSSIBLE VOTE ON RESTRICTED POWER LEVELS FOR FORT ST._VPATM: 10:00 A.M.,

THURSDAY, FEBRUARY 26, 1987, COMMISSIONERS' CONFERENCE ROOM, D.C. OFFICE (OPEN TO PUBLIC ATTENDANCE)

The Commission was briefed by the licensee and the staff on the readiness of Fort St. Vrain to restart at restricted power levels.

The following licensee representatives addressed the Commission:

Richard Walker, CEO Robert Williams, Jr.

Vice President for Nuclear Operations C.

Fuller, Station Manager P. Tomlinson, Manager Quality Assurance Division D. Warembourg, Manager Nuclear Engineering Division L. Brey, Manager Licensing and Fuels Division M. Neihoff, Manager Nuclear Design By a vote of 5-0, the Commission decided not to vote that day on restart of Fort St. Vrain.

8703160454 070311 PDR 10CFR PT9.7 PDR

(

i e The Commission requested OGC to investigate and report to the Commission if the U.S. Attorney's indictment of individuals previously employed by the licensee uncovers information relevant to the restart decision of Fort St. Vrain.

(Subsequently, by memorandum dated February 27, 1987 (Parler to Commission), OGC informed the Commission of its investigation.)

The Commission requested the staff to reaffirm its recommen-dation for restricted restart of Fort St. Vrain, and to review and provide its evaluation of the licensee's modification of the plant management team, given the resignation of Mr. Gahm.

Commissioner Asselstine requested a staff evaluation of the licensee's balance of personnel between new employees and employees with knowledge and experience of the plant.

(EDO)

(SECY Suspense:

when ready)

The Commission also requested to be informed, prior to the staff authorizing plant operation beyond 35 percent of rated power, of the licensee's readiness for continued power ascension.

cc:

Chairman Zech Commissioner Roberts Commissioner Asselstine Commissioner Bernthal Commissioner Carr Commission Staff Offices PDF - Advance DCS - 016 Phillips

.