Letter Sequence Meeting |
|---|
|
Administration
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
Results
Other: ML20076E880, ML20079M106, ML20080E109, ML20100G880, ML20100G888, ML20100H212, ML20112G667, ML20127J807, ML20135B301, ML20135D754, ML20137H372, ML20137S741, ML20141P181, ML20154K144, ML20197C598, ML20197G513, ML20205C845, ML20206B459, ML20207K470, ML20211P495, ML20215E408, ML20215G100, ML20235G758
|
MONTHYEARML20076E8801983-05-17017 May 1983 Responds to NRC 830413 Order Re Environ Qualification of safety-related Electrical Equipment,Per 10CFR50.49.Environ Qualification Records Audit Will Be Completed by 831231 Project stage: Other ML20080E1091983-08-15015 August 1983 Provides Followup to Util Re Environ Qualification of safety-related Electrical Equipment. Justification for Continued Operation W/Components Not Fully Qualified Provided Project stage: Other ML20079M1061984-01-0909 January 1984 Advises NRC Re Status of Three Commitments Made in Util Concerning Environ Qualification of safety-related Electrical Equipment.Valve Actuators Tested & Successfully Passed HELB Tests Project stage: Other ML20100G8881984-09-11011 September 1984 Four-Minute Isolation of Postulated Steam Line Breaks at Fort St Vrain Nuclear Generating Station Project stage: Other ML20112G6671984-12-27027 December 1984 Informs of Efforts to Environmentally Qualify Certain post-accident Monitoring Equipment Per 10CFR50.49.Equipment Identified in Reg Guide 1.97 & Existing in Harsh Environ Will Be Qualified by 850331 Project stage: Other ML20108A2121985-02-0404 February 1985 Informs of Receipt of Generic Ltr 84-24 on 850121 & Request for Addl Info on Environ Qualification of Electrical Equipment on 850128.Responses to Both Ltrs Will Be Provided by 850328 Project stage: Request ML20100H2121985-03-25025 March 1985 Forwards Response to NRC 841227 Order Re Certification of Compliance w/10CFR50.49 (Generic Ltr 84-24).Util Previously Submitted Ltrs Re Environ Qualification of safety-related Equipment in Response to IE Bulletin 79-01B Project stage: Other ML20100G8801985-03-28028 March 1985 Forwards Addl Info Re Environ Qualification Program. Response to NRC 850128 Concerns & Summary of Completion Schedule for Outstanding Items Encl Project stage: Other ML20237L1731985-03-29029 March 1985 Notification of 850403 Meeting W/Util in Bethesda,Md to Discuss Equipment Qualification Project stage: Meeting ML20127J8071985-06-11011 June 1985 Maintains Util Position of Full Compliance w/10CFR50.49 in Response to Eh Johnson 850611 Inquiry Re Environ Qualifications of Electrical Equipment Important to Safety. Responses to Each Concern Presented in Encl Project stage: Other ML20237L1551985-06-25025 June 1985 Submits Daily Highlight.Notifies of 850702 Meeting W/Util in Bethesda,Md to Discuss State of Compliance of Plant W/ Equipment Qualification Rule 10CFR50.49 Project stage: Meeting ML20244D4841985-07-10010 July 1985 Provides Feedback on Current NRR Conclusions Re Facility Compliance W/Equipment Qualification Rule & Operator Action Needed to Terminate Design Basis Events.Summary of 850702 Meeting W/Util in Bethesda,Md Encl Project stage: Meeting ML20132B9171985-07-11011 July 1985 Discusses Resolution of Technical Issues of Aging & Operability Times Per 850702 Meeting Re Environ Qualification Program.Hold on Reactor Power to 15% Proposed as Initial Limitation Project stage: Meeting ML20132F0721985-07-19019 July 1985 Safety Evaluation Documenting Deficiencies in Licensee Program for Environ Qualification of Electric Equipment Important to Safety.Licensee Response to Generic Ltr 84-24 Inadequate.However,Operation at 15% Power Authorized Project stage: Approval ML20132E6081985-07-19019 July 1985 Supplemental Safety Evaluation Supporting Licensee CRD Mechanisms & Associated Position Instrumentation,Per 850712 Safety Evaluation & Licensee 850710 & 18 Submittals.Control Rod Program Acceptable for Plant Restart Project stage: Request ML20132F0231985-07-19019 July 1985 Forwards Safety Evaluation Re Environ Qualification of Electric Equipment Important to Safety & Authorizes Interim Operation in dry-out Mode at Max 15% of Rated Power,Based on Listed Conditions,Until Technical Review Completed Project stage: Approval ML20134M0161985-08-20020 August 1985 Submits Discussion of Technical Issues Re Environ Qualification Program Raised During Meetings W/Nrc.Aging & Operability Time Program Operator Response Time,Temp Profiles & Shutdown Cooling Paths & Equipment Evaluated Project stage: Meeting IR 05000267/19850211985-08-30030 August 1985 Insp Rept 50-267/85-21 on 850721-31.No Violation or Deviation Noted.Major Areas Inspected:Operational Safety Verification Project stage: Request ML20135B3011985-08-30030 August 1985 Forwards Justification to Operate Facility at Reduced Power Level.Requests That NRC Provide Concurrence for Facility to Be Operated at 8% Power Level for Period of Time Not to Exceed 45 Days.Operation Does Not Pose Undue Safety Risk Project stage: Other ML20135D7541985-08-30030 August 1985 Advises That Rev of Emergency Procedures Committed to in Deferred to Coincide W/Final Environ Qualification Program Documentation.Procedure Revs at This Time Will Cause More Confusion than Clarity for Operators Project stage: Other ML20205C8451985-09-10010 September 1985 Forwards Info Supporting 850830 Request to Operate at 8% Power to Facilitate Core Dryout for 45 Days,Per 850826,0903 & 04 Telcons.Moisture Removal Needed to Maintain Conditions Prescribed in FSAR & Tech Specs Project stage: Other ML20205C4811985-09-11011 September 1985 Provides Commitment That Operating Procedures & Operator Training Described in Providing Addl Info in Support of Request to Operate at Up to 8% Power Will Be Complete Prior to Withdrawal of Control Rods Project stage: Withdrawal ML20137S7411985-09-23023 September 1985 Forwards Addl Calculations,Clarifying Util Re Predicted Fuel/Pcrv Liner Temps Resulting from Design Basis Event from 8% Power & Subsequent Reactor Cooling Utilizing Liner Cooling Sys.Calculations Confirm Original Position Project stage: Other ML20137X1411985-09-30030 September 1985 Safety Evaluation Supporting Util 850830,0910,11 & 23 Requests for Authorization to Operate at Max 8% Power,For Up to 45 Days,To Remove Moisture from RCS Project stage: Approval ML20137X1241985-09-30030 September 1985 Forwards Safety Evaluation Based on Util 850830,0910,11 & 23 Requests for Authorization to Operate at Max 8% Power,For Up to 45 Days,To Remove Moisture from Rcs.Authorization Granted,Subj to Listed Commitments Project stage: Approval ML20138E3921985-10-11011 October 1985 Forwards Request for Addl Info on 850924 Request for Special Consideration & Schedule Extension to Equipment Qualification rule,10CFR50.49.Info Requested within 7 Days of Ltr Receipt Project stage: RAI ML20138C8111985-10-21021 October 1985 Forwards Response to 851011 Request for Addl Info Re 850924 Request for Schedule Extension for Environ Qualification Program Under 10CFR50.49 from 851130 to 860331 Project stage: Request ML20138R7331985-10-31031 October 1985 Summary of 851029 Meeting W/Util & ORNL Re Schedule Extension to Equipment Qualification Rule.List of Attendees, Agenda & Matls Presented by Util Encl Project stage: Meeting ML20209J0821985-11-0505 November 1985 Forwards Request for Addl Info Re Equipment Qualification Program & Request for Extension of Deadline for Compliance W/Equipment Qualification Rule,Per 851029 Meeting Project stage: RAI ML20136F6991985-11-19019 November 1985 Modifies Scheduled Commitment for Submittal of Final Draft Proposal of Upgraded Tech Specs for NRC Comment,Per 851008 Request.Revised Submittal Date of 851130 Approved.Revised Tabulation of Commitments Encl Project stage: Draft Other ML20136J1831985-11-21021 November 1985 Staff Requirements Memo Re Commission 851119 Meeting in Washington,Dc on Licensee Environ Qualification Exemption Request.Recommendation on Extension Request Should Be Provided by 851122 Project stage: Meeting ML20136J0151985-11-22022 November 1985 Notifies of Withdrawal of 850924 Schedule Extension Request for Environ Qualification Program.Approval of Revised Schedule Extension for Implementation of Program Beyond 851130 Under Provision of 10CFR50.49 Requested Project stage: Withdrawal ML20137H3721985-11-26026 November 1985 Memorandum & Order Granting Extension of 851130 Deadline for Environ Qualification of Electrical Equipment to 860531 & Approving Proposal to Allow Operation w/35% Reactor Power Limit During Interim.Served on 851127 Project stage: Other ML20137Z3631985-12-0505 December 1985 Staff Requirements Memo Re Affirmation/Discussion & Vote on Extension of 851130 Deadline for Environ Qualification & Revised Post 851130 Environ Qualification Extension Request Project stage: Other ML20138B5121985-12-10010 December 1985 Forwards Evaluations to Document Completion of Confirmatory Actions Required to Support 35% Power Restriction During Environ Qualification Schedule Extension Period Project stage: Other ML20138L4071985-12-10010 December 1985 Rev B to EE-EQ-0019, Engineering Evaluation of Liner Cooling W/Fire Water Following High Energy Line Break from 35% Power Operation at Fort St Vrain Project stage: Other ML20137S1171985-12-23023 December 1985 Evaluation of Confirmatory Action Items to Support 35% Power Operation at Fort St Vrain, Technical Evaluation Rept Project stage: Other ML20136C8221985-12-26026 December 1985 Forwards Request for Addl Info to Complete Resolution of Confirmatory Action 6 Re Insp of High Energy Piping.Concerns Include Potential for Inservice Degradation & Exam & Insp Methods Project stage: RAI ML20151N7211985-12-27027 December 1985 Forwards Response to 851105 Request for Addl Info Needed to Determine If Environ Qualification Program Complies W/ Requirements of 10CFR50.49.Sys Description & Temp Profiles Used in Environ Qualification Program Also Encl Project stage: Request ML20137L9261985-12-31031 December 1985 Heat Stress Mgt Program for Nuclear Power Industry, Interim Rept Project stage: Other ML20141E5271986-01-0303 January 1986 Forwards Summary of Position on Confirmatory Action 6 Re Insp of Critical Areas of High Energy Piping & Responses to Six Addl Info Requests.Limited Insp Plan Will Be Completed by Middle of Jan 1986.Drawings Encl Project stage: Other ML20141H5441986-01-0808 January 1986 Issue 1 to NDE Procedure QCIM-38, Ultrasonic Exam of Class 1 & 2 Piping Welds Joining Similar & Dissimilar Matls Project stage: Other ML20141H5491986-01-0808 January 1986 Issue 5 to NDE Procedure QCIM-30, Radiographic Exam Procedure Project stage: Other ML20141H5341986-01-0808 January 1986 Forwards NDE Procedures,Per DW Warembourg Project stage: Other ML20137M1091986-01-15015 January 1986 Forwards Addl Info to Support Util Intention to Use Ice Vests to Allow Personnel Access W/Elevated Bldg Temps. T Bernard Prof Opinion Documented in Encl Draft Heat Stress Mgt Program. Rept Available in Central Files Project stage: Draft Other ML20137L9001986-01-21021 January 1986 Forwards EPRI Interim Rept, Heat Stress Mgt Program for Nuclear Power Industry, to Replace Draft Transmitted by Walker ,To Support 35% Power Bldg Access.Rept Will Be Available in Mar as EPRI NP4453 Project stage: Draft Other ML20151R0741986-01-29029 January 1986 Informs That NRR Ltr to Licensee Summarizing Findings Re Environ Qualification Extension Sufficient to Authorize Limited Operation.No License Amend Required to Support Authorization Project stage: Other ML20141P1811986-01-29029 January 1986 Rev 00 to Justification/Analysis:Environ Qualification of Square D Pressure & Temp Switches Project stage: Other ML20137R9991986-02-0707 February 1986 Authorizes Interim Operation at 35% of Full Power,Per 851210,860103,08 & 15 Confirmatory Analyses.Forwards Supporting SER & Current Listing of Commitments Project stage: Other ML20141M8081986-02-14014 February 1986 Advises That DBAs Re Permanent Loss of Forced Circulation & Rapid Depressurization of Reactor Vessel Must Be Addressed in Equipment Qualification Program.Util Cooperation W/Program Mods Confirmed During 851029 Meeting Project stage: Meeting 1985-03-25
[Table View] |
Text
_ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ - _
h PublicService
. uo....
Company of Colorado 2420 W. 26th Avenue, Suite 1000 Denver, Colorado 80211 August 20, 1985 Fort St. Vrain Unit No. 1 P-85293 Mr. W. D. Martin b$b0
'l Regional Administrator r
N lear Regulatory Commission ALG26885 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011
~
Docket No. 50-267
SUBJECT:
Fort St. Vrain Environmental Qualification Program
Dear Mr. Martin:
The NRC and PSC have had several meetings and a considerable exchange of information concerning the Fort St.
Vrain Environmental Qualification (EQ) program beginning in late March of this year to the present time. As a result of this exchange of information, we are aggressively pursuing several activities related to our environmental qualification program. Given the technical issues that
- t. ave recently been raised, PSC is working in the following areas with the objective of resolving these technical issues as soon as possible:
1.
Aging and Operability Time Program 2.
Four Minute Versus Ten Minute Operator Response Time 3.
Temperature Profiles 4.
Complete Review ofSafeShutdownCoolingPath(s) including the Liner Cooling System 5.
Complete Field Walkdown of EQ Safe Shutdown Cooling Equipment 6.
Complete Review, Evaluation, and Update of All Environmental f
Qualification Files I
P a n es - c 66 4 snu 7
>w yy
-2 This has developed into a massive work effort with all tasks being conducted in parallel. Completion of task evaluations in one area are necessarily highly dependent upon the results of the other areas.
Given all these activities, PSC is identifying what appear to be concerns in some of the areas being evaluated.
PSC has not progressed far enough in all areas to permit a complete evaluation, but PSC feels it is important to keep the NRC abreast of our findings, activities and progress.
Aging and Operability As we previously committed to you, we are continuing with the aging and operability studies. Due to limited information available on materials for Fort St. Vrain's unique temperature profiles, we have identified some areas of concern. On this basis, we have expanded our efforts in order to establish the necessary materials data base to bring these studies to a conclusion.
Our aging studies are identifying potential concerns with some equipment items.
The potential concerns are being re-evaluated on the basis of all program information.
Corrective action is under consideration and will be scheduled and prioritized by late August or early September.
Although we have experienced some setbacks due to lack of industry data bank information, we are still proceeding on a path to complete the basic aging studies by the end of August. We would plan to get with the NRC as soon thereafter as we can complete our review and evaluation of this work.
Four Minute vs Ten Minute Operator Response We are continuing our work on a steam leak detection system.
Based onNRC'scommentsatourrecentsitemeeting(July 30,1985),we are evaluating an automatic steam leak detection / isolation system. We are proceeding with the design work of this system with the full intent of installing the system on an expedited schedule should the system prove to be feasible as well as acceptable to the NRC. We are also re-evaluating the previous steam leak scenarios that were presented to the NRC in our letter dated March 28,1985(P-85112) in order to identify all automatic actions that will take place to mitigate the consequences of a high energy line break and to better define operator action required as a result of these automatic actions (full credit was not taken in our previous scenarios for control system and plant protective system actions and automatic valve closures that would result in terminating many of the leak paths).
Preliminary results indicate that 7 of the 10 steam line break scenarios would result in automatic isolation and in the remaining 3 cases only one operator action is required to terminate the leak, Completion of this study will permit better interim operator training in response to some concerns raised by the NRC at the July 30, 1985 site meeting. This study should be complete by the end of August.
Temperature Profiles l
We believe our temperature profiles are somewhat conservative and we are proceeding to re-evaluate these profiles on two different bases.
First, we are utilizing the codes that were used originally for generating the profiles. Some refinements to the code have been made to account for other external effects. The objective of this effort is to define profile conservatism as well as provide additional information needed as input for the steam leak detection system design, aging, operability time analysis and system access studies.
Information from this effort should be available to us by the end of j
August 1985. Preliminary scoping studies in this area indicate that the harsh environment could result in equipment access problems.
As a second effort we are developing temperature profiles utilizing a completely different model and code. The primary objective of this second effort is to detennine conservatism (if any) in the existing i
1 temperature profiles as well as obtain additional information concerning the steam leak and the resulting harsh environments. The output from this additional effort will also be utilized for design input to the steam leak detection / isolation system. We are actively pursuing this effort in order to complete the input to the model by the end of August. This schedule will permit a preliminary scoping run of the temperature profiles by mid-September.
l Review Safe Shutdown Cooling Path (s)
We have initiated a complete review of the Safe Shutdown Cooling Path (s) which will include a review of the various assumptions that i
have been made in the past.
Preliminary results of this review have
];
identified some apparent qualification concerns with the similarity i
arguments utilized to qualify equipment, assumptions concerning equipment locations and harsh environments, and possible discrepancies in the safe shutdown cooling equipment list.
In addition, we have identified four (4) valves that have a potential to be submerged.
These valves are presently being evaluated.
Corrective action will be implemented as soon as possible.
The results of this review will be evaluated in conjunction with all l
of the other activities and studies, and corrective action will be l
implemented as soon as possible.
j i
1 l
f I
I I
Field Walkdown As a part of our overall effort of addressing the various technical issues we have initiated a complete field walkdown of our safe shutdown cooling equipment. This work is still in progress and final evaluations have not been made, however, we feel it is important to apprise you of the typical problem areas being identified. We have identified taped splices, (typical of pigtail connection required for motor and solenoid valve terminations) which are acceptable per Fort St. Vrain standards, but are questionable in terms of meeting qualification requirements.
We are evaluating the replacement of taped splices and will be starting a replacement program as soon as possible.
We have also identified some junction boxes that have interior rust or oil contamination. We are proceeding imediately to evaluate the effects of this contamination and are implementing a field maintenance effort to correct maintenance type items.
We have identified some discrepancies in installed equipment model numbers versus test reports.
These discrepancies will require evaluation against the original test reports, similarity arguments, etc. to determine final resolution or corrective action.
We will also be evaluating the installed equipment configuration against the test report data.
We expect completion of the field walkdown effort in early September.
In the interim, we will "be evaluating the results of the field walkdown efforts and developing an agressive but controlled program for corrective maintenance and modifications where necessary.
Review / Update Environmental Qualification Files In preparation for incorporating the aging and operability time results into our program, as well as documenting any other changes or requirements that may result from the above listed activities, we have initiated a review to develop additional information and analyses for completion of our environmental files. A project group has been established to ensure timely completion of these files comensurate with the completion of the various other studies and evaluations outlined herein.
5-Other Activities Other activities include a drawing review and complete circuit analyses including breaker / fuse coordination.
In addition, we are reverifying equipment failure modes. We have completed the fuse and breaker coordination review referenced in our fiarch 28, 1985 letter (P-85112) and have identified some valve circuits (2 breakers requiring set point changes, I circuit requiring rewire, 3 breakers requiring changeout and 5 valve breaker sections requiring additional fuse installation) within MCC's which do not meet our criteria.
Design work to correct these areas is underway.
It is anticipated that deficiencies can be corrected by mid-October.
NRC Generic letter 85-15_
We are in receipt of the August 6, 1985 Generic Letter, and we are evaluating the various aspects of the letter.
While we are proceeding on a very aggressive basis to resolve any and all technical issues associated with our EQ program, it is obvious that we have had only a very short time to provide technical issue resolution for unique situations based on relatively recent guidance and feedback from the NRC.
It appears that based on various issues before us, the installation of the steam leak detection / isolation system will be critical to final resolution of the EQ issues. While we are aggressively pursuing the design and installation of this system as well as pursuing resolution to all other technical issues, we will in all probability be filing on or before September 30, 1985 for an extension beyond November 30, 1985.
Interim Operation In the interim, we are proceeding on the basis that the 15% power release approved by the NRC SER dated July 19, 1985, is still the controlling operational requirement on the bases that steam conditions and resulting pipe stresses at 15% power represent an acceptable operating condition We are presently in a shutdown mode due to moisture levels in the primary coolant, but we intend to gu to power operation not to exceed 15% as moisture conditions may permit.
We will keep you informed of our progress in the various areas outlined above. Again, we are making every effort possible to resolve any and all issues as they arise.
If you have any questions please contact Mr. M. H. Holmes at (303) 571-8409.
Very truly yours, d2fr. YYn J,w y D. W. Warembourg, Manag6r Nuclear Engineering Division DWW:pa