ML093520079: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(One intermediate revision by the same user not shown)
Line 3: Line 3:
| issue date = 12/14/2009
| issue date = 12/14/2009
| title = License Renewal Application 10 CFR Part 54.21(b) Annual Update
| title = License Renewal Application 10 CFR Part 54.21(b) Annual Update
| author name = Franke J A
| author name = Franke J
| author affiliation = Progress Energy Florida, Inc
| author affiliation = Progress Energy Florida, Inc
| addressee name =  
| addressee name =  
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:tProgress Energy Crystal River Nuclear Plant Docket No. 50-302 Operating License No. DPR-72 Ref: 10 CFR 54 December 14, 2009 3F1209-06 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
{{#Wiki_filter:tProgress Energy Crystal River Nuclear Plant Docket No. 50-302 Operating License No. DPR-72                                                           Ref: 10 CFR 54 December 14, 2009 3F1209-06 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001


==Subject:==
==Subject:==
Crystal River Unit 3 -License Renewal Application 10 CFR Part 54.21(b) Annual Update (TAC NO. ME0274)
Crystal River Unit 3 - License Renewal Application 10 CFR Part 54.21(b) Annual Update (TAC NO. ME0274)


==References:==
==References:==
(1)      CR-3 to NRC letter, dated December 16, 2008, "Crystal River Unit 3 -
Application for Renewal of Operating License" (2)    NRC to CR-3 letter, dated December 1, 2009, "Request for Additional Information for the Review of the Crystal River Unit 3, Nuclear Generating Plant, License Renewal Application (TAC NO. ME0274)"


(1) CR-3 to NRC letter, dated December 16, 2008, "Crystal River Unit 3 -Application for Renewal of Operating License" (2) NRC to CR-3 letter, dated December 1, 2009, "Request for Additional Information for the Review of the Crystal River Unit 3, Nuclear Generating Plant, License Renewal Application (TAC NO. ME0274)"
==Dear Sir:==


==Dear Sir:==
On December 16, 2008, Florida Power Corporation (FPC), doing business as Progress Energy Florida, Inc. (PEF), requested renewal of the operating license for Crystal River Unit 3 (CR-3) to extend the term of its operating license an additional 20 years beyond the current expiration date (Reference 1).
On December 16, 2008, Florida Power Corporation (FPC), doing business as Progress Energy Florida, Inc. (PEF), requested renewal of the operating license for Crystal River Unit 3 (CR-3) to extend the term of its operating license an additional 20 years beyond the current expiration date (Reference 1).Annually, during the NRC staff review of the License Renewal Application (LRA), and at least three months before the completion of the review, PEF is required by 10 CFR 54.21(b) to amend the LRA by identifying any change to the CR-3 Current Licensing Basis (CLB) that materially affects the contents of the LRA.PEF has completed a review of CLB changes that have occurred since the CR-3 LRA was submitted and has identified no changes to the CLB that materially affect the contents of the LRA, including the FSAR supplement.
Annually, during the NRC staff review of the License Renewal Application (LRA), and at least three months before the completion of the review, PEF is required by 10 CFR 54.21(b) to amend the LRA by identifying any change to the CR-3 Current Licensing Basis (CLB) that materially affects the contents of the LRA.
Note that pending changes were identified associated with Extended Power Uprate (EPU), Steam Generator Replacement (SGR), and related activities that are being implemented during the current refueling outage and the next refueling outage. Therefore, these changes are not yet incorporated into the CLB as of this update period. CLB changes associated with EPU/SGR andrelated activities will be the subject of responses to the NRC's December 1, 2009, request for additional information for the CR-3 License Renewal Application review (Reference 2). Impacts to the CR-3 LRA associated with these changes will be conveyed to the NRC within the response to that letter.This letter does not contain any new or revised regulatory commitments.
PEF has completed a review of CLB changes that have occurred since the CR-3 LRA was submitted and has identified no changes to the CLB that materially affect the contents of the LRA, including the FSAR supplement. Note that pending changes were identified associated with Extended Power Uprate (EPU), Steam Generator Replacement (SGR), and related activities that are being implemented during the current refueling outage and the next refueling outage. Therefore, these changes are not yet incorporated into the CLB as of this update period. CLB changes associated with EPU/SGR andrelated activities will be the subject of responses to the NRC's December 1, 2009, request for additional information for the CR-3 License Renewal Application review (Reference 2). Impacts to the CR-3 LRA associated with these changes will be conveyed to the NRC within the response to that letter.
This letter does not contain any new or revised regulatory commitments.
If you have any questions regarding this submittal, please contact Mr. Mike Heath, Supervisor, License Renewal, at (910) 457-3487, e-mail at mike.heath@pgnmail.com.
If you have any questions regarding this submittal, please contact Mr. Mike Heath, Supervisor, License Renewal, at (910) 457-3487, e-mail at mike.heath@pgnmail.com.
cerel o~n A. Franke Vice President Crystal River Unit 3 JAF/dwh xc: NRC CR-3 Project Manager NRC License Renewal Project Manager NRC Regional Administrator, Region II Senior Resident Inspector Progress Energy Florida, Inc. Lt Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL 34428 U. S. Nuclear Regulatory Commission Page 2 of 2 3F1209-06 STATE OF FLORIDA COUNTY OF CITRUS Jon A. Franke states that he is the Vice President, Crystal River Nuclear Plant for Florida Power Corporation, doing business as Progress Energy Florida, Inc.; that he is authorized on the part of said company to sign and file with the Nuclear Regulatory Commission the information attached hereto; and that all such statements made and matters set forth therein are true and correct to the best of his knowledge, information d belief.<'K Jon A. Franke Vice President Crystal River Nuclear Plant The foregoing document was acknowledged before me this IL day of J &#xa2; , 2009, by Jon A. Franke.Signature of Notary Public State of Florida MW, CAROYNE ORMtN j'Notay Pubk Sbc Cmuon# DD 524380 (Print, type, or stamp Commissioned Name of Notary Public)Personally  
cerel o~n A. Franke Vice President Crystal River Unit 3 JAF/dwh xc:       NRC CR-3 Project Manager NRC License Renewal Project Manager NRC Regional Administrator, Region II Senior Resident Inspector Progress Energy Florida, Inc.                                                                           Lt Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL 34428
.Produced Known / ' -OR- Identification}}
 
U. S. Nuclear Regulatory Commission                                                         Page 2 of 2 3F1209-06 STATE OF FLORIDA COUNTY OF CITRUS Jon A. Franke states that he is the Vice President, Crystal River Nuclear Plant for Florida Power Corporation, doing business as Progress Energy Florida, Inc.; that he is authorized on the part of said company to sign and file with the Nuclear Regulatory Commission the information attached hereto; and that all such statements made and matters set forth therein are true and correct to the best of his knowledge, information       d belief.
                                                                    <'K Jon A. Franke Vice President Crystal River Nuclear Plant The foregoing   document     was   acknowledged       before   me this     IL     day   of J       &#xa2;             , 2009, by Jon A. Franke.
Signature of Notary Public State of Florida MW, CAROYNE ORMtN j'Notay         Pubk Sbc Cmuon#DD 524380 (Print, type, or stamp Commissioned Name of Notary Public)
Personally             . Produced Known         /     ' -OR-   Identification}}

Latest revision as of 23:26, 13 November 2019

License Renewal Application 10 CFR Part 54.21(b) Annual Update
ML093520079
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 12/14/2009
From: Franke J
Progress Energy Florida
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
3F1209-06, TAC ME0274
Download: ML093520079 (2)


Text

tProgress Energy Crystal River Nuclear Plant Docket No. 50-302 Operating License No. DPR-72 Ref: 10 CFR 54 December 14, 2009 3F1209-06 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

Crystal River Unit 3 - License Renewal Application 10 CFR Part 54.21(b) Annual Update (TAC NO. ME0274)

References:

(1) CR-3 to NRC letter, dated December 16, 2008, "Crystal River Unit 3 -

Application for Renewal of Operating License" (2) NRC to CR-3 letter, dated December 1, 2009, "Request for Additional Information for the Review of the Crystal River Unit 3, Nuclear Generating Plant, License Renewal Application (TAC NO. ME0274)"

Dear Sir:

On December 16, 2008, Florida Power Corporation (FPC), doing business as Progress Energy Florida, Inc. (PEF), requested renewal of the operating license for Crystal River Unit 3 (CR-3) to extend the term of its operating license an additional 20 years beyond the current expiration date (Reference 1).

Annually, during the NRC staff review of the License Renewal Application (LRA), and at least three months before the completion of the review, PEF is required by 10 CFR 54.21(b) to amend the LRA by identifying any change to the CR-3 Current Licensing Basis (CLB) that materially affects the contents of the LRA.

PEF has completed a review of CLB changes that have occurred since the CR-3 LRA was submitted and has identified no changes to the CLB that materially affect the contents of the LRA, including the FSAR supplement. Note that pending changes were identified associated with Extended Power Uprate (EPU), Steam Generator Replacement (SGR), and related activities that are being implemented during the current refueling outage and the next refueling outage. Therefore, these changes are not yet incorporated into the CLB as of this update period. CLB changes associated with EPU/SGR andrelated activities will be the subject of responses to the NRC's December 1, 2009, request for additional information for the CR-3 License Renewal Application review (Reference 2). Impacts to the CR-3 LRA associated with these changes will be conveyed to the NRC within the response to that letter.

This letter does not contain any new or revised regulatory commitments.

If you have any questions regarding this submittal, please contact Mr. Mike Heath, Supervisor, License Renewal, at (910) 457-3487, e-mail at mike.heath@pgnmail.com.

cerel o~n A. Franke Vice President Crystal River Unit 3 JAF/dwh xc: NRC CR-3 Project Manager NRC License Renewal Project Manager NRC Regional Administrator, Region II Senior Resident Inspector Progress Energy Florida, Inc. Lt Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL 34428

U. S. Nuclear Regulatory Commission Page 2 of 2 3F1209-06 STATE OF FLORIDA COUNTY OF CITRUS Jon A. Franke states that he is the Vice President, Crystal River Nuclear Plant for Florida Power Corporation, doing business as Progress Energy Florida, Inc.; that he is authorized on the part of said company to sign and file with the Nuclear Regulatory Commission the information attached hereto; and that all such statements made and matters set forth therein are true and correct to the best of his knowledge, information d belief.

<'K Jon A. Franke Vice President Crystal River Nuclear Plant The foregoing document was acknowledged before me this IL day of J ¢ , 2009, by Jon A. Franke.

Signature of Notary Public State of Florida MW, CAROYNE ORMtN j'Notay Pubk Sbc Cmuon#DD 524380 (Print, type, or stamp Commissioned Name of Notary Public)

Personally . Produced Known / ' -OR- Identification