IR 05000397/2018007: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:/ | {{#Wiki_filter:==SUBJECT:== | ||
COLUMBIA GENERATING STATION - NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION REPORT (NRC INSPECTION REPORT 05000397/2018007) | |||
==Dear Mr. Sawatzke:== | |||
On April 26, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the Columbia Generating Station and discussed the results of this inspection with Mr. Alex Javorik, Vice President of Engineering, and other members of your staff. The results of this inspection are documented in the enclosed report. | |||
The NRC inspectors did not identify any finding or violation of more than minor significance. | |||
/ | This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding. | ||
Sincerely, | |||
/RA/ | |||
James F. Drake, Acting Chief Engineering Branch 2 Division of Reactor Safety Docket: 50-397 License: NPF-21 Enclosure: | |||
Inspection Report 05000397/2018007 | |||
/RA/ /RA-E/ /RA/ /RA/ /RA/ /RA/ 05/03/18 05/04/18 05/07/18 05/03/18 05/09/18 05/09/18 | U.S. NUCLEAR REGULATORY COMMISSION | ||
==Inspection Report== | |||
Docket Number: 05000397 License Number: NPF-21 Report Number: 05000397/2018007 Enterprise Identifier: I-2018-007-0002 Licensee: Energy Northwest Facility: Columbia Generating Station Location: Richland, Washington Inspection Dates: April 9, 2018, to April 26, 2018 Inspectors: J. Mateychick, Senior Reactor Inspector (Team Lead) | |||
B. Correll, Reactor Inspector S. Makor, Reactor Inspector G. Pick, Senior Reactor Inspector Approved By: J. Drake, Chief Engineering Branch 2 Division of Reactor Safety Enclosure | |||
=SUMMARY= | |||
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees performance by conducting a Triennial Fire Protection Baseline Inspection at Columbia Generating Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC and self-revealed findings, violations, and additional items are summarized in the table below. | |||
List of Findings and Violations The NRC inspectors did not identify any finding or violation of more than minor significance. | |||
=INSPECTION SCOPES= | |||
Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. | |||
Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. | |||
==REACTOR SAFETY== | |||
71111.05T - Fire Protection (Triennial) | |||
The inspectors evaluated the design, operational status, and material condition of the licensees fire protection program, including assumptions made in plant and area specific fire protection analyses, by verifying that the licensees program includes: | |||
: (1) Adequate controls for combustibles and ignition sources inside the plant; | |||
: (2) Adequate fire detection and suppression capability; | |||
: (3) Passive fire protection features in good material condition; | |||
: (4) Adequate compensatory measures for out-of-service, degraded or inoperable fire protection equipment, systems, or features; | |||
: (5) Adequate protection to ensure the post-fire capability to safely shutdown the plant, including implementation of NRC/industry fire-induced circuit failure analysis guidance; | |||
: (6) Feasible and reliable manual actions when appropriate to achieve safe shutdown; and | |||
: (7) Adequate review and documentation of fire protection program changes. | |||
Fire Protection Inspection Requirements (Four Samples) | |||
The inspectors evaluated fire protection program implementation in the following selected areas: | |||
Fire Area Description R-1D Reactor Building Northwest 471 Elevation RC-3 Cable Chase RC-4 Division 1 Electrical Equipment Room RC-14 Division 1 Switchgear Room The inspectors reviewed and evaluated the following fire protection inspection requirements: | |||
: (1) Fire brigade drill performance | |||
: (2) Protection of safe shutdown capabilities | |||
: (3) Passive fire protection | |||
: (4) Active fire protection | |||
: (5) Protection from damage from fire suppression activities | |||
: (6) Alternative shutdown capability | |||
: (7) Circuit analysis | |||
: (8) Communications | |||
: (9) Emergency lighting (Fixed and Portable 8 hour units) | |||
: (10) Cold shutdown repairs | |||
: (11) Compensatory measures a. Compensatory measures for degraded fire protection components b. Compensatory measures for components necessary to achieve safe and stable conditions | |||
: (12) Review and documentation of fire protection plan changes | |||
: (13) Control of transient combustibles and ignition sources | |||
: (14) Sample of fire protection corrective action documents B.5.b Inspection Activities (One Sample) | |||
The inspectors evaluated feasibility of the B.5.b mitigating strategies by determining the following: | |||
* Procedures are being maintained and adequate | |||
* Equipment is properly staged and is being maintained and tested | |||
* Station personnel are knowledgeable and can implement the procedures The inspectors evaluated feasibility of the following B.5.b Mitigating Strategies: | |||
ABN-TSG-008 Initiation of Drywell or Wetwell Spray Through the Residual Heat Removal System ABN-TSG-010 Spent Fuel Pool Makeup Through the Residual Heat Removal System Via Fire Water or Condensate Transfer | |||
==INSPECTION RESULTS== | |||
The NRC inspectors did not identify any finding or violation of more than minor significance. | |||
==EXIT MEETINGS AND DEBRIEFS== | |||
The inspectors verified no proprietary information was retained or documented in this report. | |||
On April 26, 2018, the inspectors presented the fire protection inspection results to Mr. A. Javorik, Vice President of Engineering, and other members of the licensee staff. | |||
=DOCUMENTS REVIEWED= | |||
Cable Routing Data Components | |||
Residual Heat Removal System, Standby Service Water System | |||
(RHR-P-2B, RHR-V-6B, RHR-FCV-64B, RHR-V-4B, SW-P-1B, RHR-V-3B, SW-V-12B) | |||
Calculations Title Revision or | |||
Number Date | |||
FP-02-07-02 Hydraulic Analysis of Fire Water Supply System 2 | |||
FPF 2.11 Emergency Lighting Monthly Inspections and 2 | |||
Appendix R Lamp Positioning | |||
ME-02-02-23 Post-Fire Safe Shutdown Flooding Analysis - 1 | |||
Radwaste Building | |||
MSE-EJJ-10-01 Expert Panel Identification and Review of Multiple April 23, 2010 | |||
Spurious Operation Scenarios | |||
NE-02-85-19 Post-Fire Safe Shutdown Analysis 12 | |||
NE-02-94-35 System Impact on Post-Fire Safe Shutdown 6 | |||
TM-2160 B.5.b Implementation 5 | |||
Action Requests (AR-) | |||
378859* 379297* 379315* 378806* 378968* 379317* 379319* 378940* | |||
378989 379316* 379320* 335821 374802 377838 378937* 340250 | |||
377836 378917* 379403* 379349* 378917* | |||
*Issued as a result of inspection activities. | |||
Drawings Title Revision | |||
Number | |||
2-217A-28 Cable Chase - Zone 2 System 66 (Preaction) 10 | |||
2-217A-29 Cable Chase - Zone 2 System 66 (Preaction) 5 | |||
2-217A-30 Cable Chase - Zone 2 System 66 (Preaction) 7 | |||
2-217A-31 Cable Chase - Zone 2 System 66 (Preaction) 6 | |||
A529 Reactor Building Stair No. A5 6 | |||
A530 Reactor Building Stair No. A6 6 | |||
Drawings Title Revision | |||
Number | |||
C 896 FP-TK-110 Water Storage Tank Plan Sections and 3 | |||
Details | |||
D00292, Sheet 36 Fire Detection and Alarm System Installation Diagram 0 | |||
- Radioactive Waste and Control Building El 467 | |||
FM892-8 Sprinkler and Hose Station Plans EL 467-0 5 | |||
and 471-0 and Miscellaneous Floors | |||
FM-892-12 Access-Egress for Post-Fire Safe Shutdown Activities 12 | |||
FM-892-13 Access-Egress for Post-Fire Safe Shutdown Activities 10 | |||
FM-892-14 Access-Egress for Post-Fire Safe Shutdown Activities 6 | |||
M521-1 Flow Diagram Residual Heat Removal Loop A 115 | |||
M521-2 Flow Diagram Residual Heat Removal Loop B 115 | |||
EWD-88-E-007 Electrical Wiring Diagram Diesel Generator (DG) 10 | |||
Building H&V System DG2 Room Normal Supply | |||
Fan DMA-FN-22 | |||
EWD-88E-020A Electrical Wiring Diagram Diesel Generator 11 | |||
Building H&V System DG2 Room Normal Air | |||
Dampers DMA-AD-22/1 and DMA-AD-22/2 | |||
EWD-88E-029A Electrical Wiring Diagram Diesel Generator 2 | |||
Building H&V System DG2 Room Air Handling | |||
Unit DMA-AH-22 Outlet Heater DMA-EHC-22 | |||
EWD-88E-034 Electrical Wiring Diagram Diesel Generator Building 2 | |||
H&V System Annunciator DMA-ANN-PNL/DGHV2 | |||
EWD-9E-019 Electrical Wiring Diagram Residual Heat Removal 25 | |||
System Motor Operated Valve (MOV) | |||
RHR-V-4B (E12-F004B) | |||
PFSS-2 Appendix R Post-Fire Safe Shutdown (PFSS) 16 | |||
Division 2 Boundaries of Line Diagram | |||
EWD-9E-097 Electrical Wiring Diagram Residual Heat Removal 13 | |||
System Miscellaneous Relay Circuits (Division 2) | |||
Drawings Title Revision | |||
Number | |||
E948-1A Appendix R Post-Fire Safe Shutdown Protected 0 | |||
Raceways Whittaker Cable Support Diagram | |||
E948-2A Appendix R Post-Fire Safe Shutdown Protected 8 | |||
Raceways Reactor Building Elevations 501-0 and | |||
2-0 | |||
E948-3 Appendix R Post-Fire Safe Shutdown Protected 13 | |||
Raceways Radwaste Building - Elevations 467-0 and | |||
25-0 | |||
EWD-9E-004 Electrical Wiring Diagram Residual Heat Removal 19 | |||
System Pump RHR-P-2B Breaker RHR-CB-P2B | |||
EWD-9E-099 Electrical Wiring Diagram Residual Heat Removal 10 | |||
System Miscellaneous Relay Circuits (Division 2) | |||
EWD-9E-100 Electrical Wiring Diagram Residual Heat Removal 8 | |||
System Miscellaneous Relay Circuits (Division 2) | |||
E502-2 Main One Line Diagram 63 | |||
EWD-9E-003 Electrical Wiring Diagram Residual Heat Removal 22 | |||
System Pump RHR-P-2B (E12-C002B) | |||
EWD-7E-020 Electrical Wiring Diagram High Pressure Core Spray 16 | |||
System MOV HPCS-V-15 (E22-F015) | |||
EWD-7E-023 Electrical Wiring Diagram High Pressure Core Spray 22 | |||
System Pump HPCS-P-1 (E-22-C001) | |||
EWD-7E-022 Electrical Wiring Diagram High Pressure Core 21 | |||
Spray System Pump HPCS-P-1 (E22-C001) | |||
Breaker HPCS-CB-P1 | |||
EWD-7E-003 Electrical Wiring Diagram High Pressure Core 7 | |||
Spray System Standby Water Leg Pump HPCS-P-3 | |||
(E22-C003) | |||
EWD-7E-018 Electrical Wiring Diagram High Pressure Core Spray 17 | |||
System MOV HPCS-V-11 (E22-F011) | |||
M520 Flow Diagram High Pressure Core Spray (HPCS) 104 | |||
System and Low Pressure Core Spray Systems | |||
Reactor Building | |||
Drawings Title Revision | |||
Number | |||
EWD-7E-017 Electrical Wiring Diagram High Pressure Core Spray 15 | |||
System MOV HPCS-V-10 (E22-F0101) | |||
EWD-58E-022 Electrical Wiring Diagram Standby Service Water 21 | |||
System MOV SW-V-12B | |||
EWD-58E-021 Electrical Wiring Diagram Standby Service Water 24 | |||
System, MOV-SW-V-12B | |||
EWD-58E-004 Electrical Wiring Diagram Standby Service Water 27 | |||
System SW-P-1B Breaker SW-CB-P1B | |||
EWD-58E-004B Electrical Wiring Diagram Standby Service Water 3 | |||
System SW-P-1B Breaker SW-CB-P1B | |||
M524-2 Flow Diagram Standby Service Water System 120 | |||
Reactor, Radwaste, DG Buildings and Yard | |||
EWD-9E-022 Electrical Wiring Diagram Residual Heat Removal 21 | |||
System MOV RHR-V-6B (E12-F006B) | |||
EWD-58E-014 Electrical Wiring Diagram Standby Service Water 19 | |||
System MOV SW-V-2B | |||
EWD-58E-015 Electrical Wiring Diagram Standby Service Water 22 | |||
System MOV SW-V-2B | |||
E542-22D Connection Wiring Diagram Supervisory 2 | |||
Panel E-CP-C2 (Division 2) Rear Sub-Panel Lower | |||
Half | |||
E542-22E Connection Wiring Diagram, Supervisory 5 | |||
Panel E-CP-CS2 (Division 2) Right Sub-Panel | |||
EWD-58E-004 Electrical Wiring Diagram Standby Service Water 27 | |||
System W-P-1B Breaker SW-CB-P1B | |||
EWD-58E-004B Electrical Wiring Diagram Standby Service Water 3 | |||
System SW-P-1B Breaker SW-CB-P1B | |||
PFSS-2 Appendix R Post-Fire Safe Shutdown (PFSS) 16 | |||
Division 2 Boundaries One Line Diagram | |||
EWD-9E-006 Electrical Wiring Diagram Residual Heat Removal 14 | |||
Drawings Title Revision | |||
Number | |||
System Pump RHR-P-2C Breaker RHR-CB-P2C | |||
EWD-6E-008 Electrical Wiring Diagram Reactor Core Isolation 23 | |||
Cooling System MOV RCIC-V-45 (E51-F045) | |||
EWD-6E-008A Electrical Wiring Diagram Reactor Core Isolation 5 | |||
Cooling System MOV RCIC-V-45 (E51-F045) | |||
6E013 Reactor Core Isolation Cooling System Miscellaneous 21 | |||
Relay Circuits Sheet 4 | |||
EWD-9E-057 Electrical Wiring Diagram Residual Heat Removal 20 | |||
System MOV RHR-FCV-64B (E12-F064B) | |||
EWD-9E-123 Electrical Wiring Diagram Residual Heat Removal 3 | |||
System Annunciator | |||
EWD-9E-004A Electrical Wiring Diagram Residual Heat Removal 1 | |||
System Pump RHR-P-2B Breaker RHR-CB-P2B | |||
EWD-9E-004 Electrical Wiring Diagram Residual Heat Removal 19 | |||
System Pump RHR-P-2B Breaker RHR-CB-P2B | |||
EWD-41-003 Electrical Wiring Diagram Reactor Water Cleanup 0 | |||
System RWCU-FT-37, RWCU-PT-5, and | |||
RWCU-TS-20 | |||
EWD-46E-252C Electrical Wiring Diagram AC Electrical Distribution 4 | |||
System Power Panel E-PP-8AF Circuit Details | |||
EWD-9E-019 Electrical Wiring Diagram Residual Heat Removal 25 | |||
System MOV-RHR-V-4B (E12-F004B) | |||
EWD-58E-047 Electrical Wiring Diagram Standby Service Water 22 | |||
System MOV RHR-V-68B (E12-F068B) | |||
EWD-1E-038 Electrical Wiring Diagram Nuclear Boiler System 21 | |||
Automatic Depressurization Safety Relief | |||
Valve MS-RV-3D (B22-F013V) | |||
EWD-1E-038A Electrical Wiring Diagram Nuclear Boiler System 4 | |||
Automatic Depressurization Safety Relief | |||
Valve M-RV-3D (B22-F013V) | |||
Drawings Title Revision | |||
Number | |||
H-4649-D Sections - 20 x 10 Type A Head - 3 Stage | |||
H-4650-D Fire Pump - Vertical Turbine Model EBA 2 | |||
M515-1 Flow Diagram - Fire Protection System 110 | |||
M515-2 Flow Diagram - Fire Protection System Details 18 | |||
M515-4 Flow Diagram - Fire Protection System General 2 | |||
Services Building and Turbine Generator Building | |||
M515-5 Flow Diagram - Fire Protection System Reactor 6 | |||
Building, Diesel Generator Building, and Radwaste | |||
Building | |||
M573-2 Flow Diagram - Potable Water Cold and Fire 8 | |||
Protection Systems Pump houses | |||
M585 General Arrangement Plans and Sections Circulating 27 | |||
Water Pump House | |||
M827 Heating Ventilation and Air Conditioning - Sections 41 | |||
and Details Radwaste and Control Building | |||
M932-1 Fire Main Ring Header 6 | |||
Modification Title Revision | |||
Number | |||
16302-1 Disabled HPCS-V-10 and HPCS-V11 in Place 12 | |||
Procedures Title Revision | |||
Number | |||
ABN-EDMG Extensive Damage Mitigation Guidelines (EDMG) 020/002 | |||
ABN-CR-EVAC Control Room Evacuation and Remote Cooldown 37 | |||
ABN-FIRE Fire 40 | |||
ABN-RHR-SDC- Residual Heat Removal Alternate Shutdown Cooling 015 | |||
ALT | |||
ABN-TSG-008 Initiation of Drywell or Wetwell Spray Through the 006 | |||
Residual Heat Removal System | |||
Procedures | |||
Title Revision | |||
Number | |||
ABN-TSG-010 Spent Fuel Pool Makeup Through the Residual Heat 006 | |||
Removal System Via Fire Water or Condensate | |||
Transfer | |||
OI-18 Equipment Operator Rounds 014/001 | |||
PFP-RB-471 Reactor 471 Pre-fire Plans 5 | |||
PFP-RW-467 Radwaste (RW) 467 Pre-fire Plans 5 | |||
PPM 1.3.10 Plant Fire Protection Program Implementation 034/002 | |||
PPM 1.3.10A Control of Ignition Sources 017/001 | |||
PPM 1.3.10B Active Fire System Operability and Impairment 015/002 | |||
Control | |||
PPM 1.3.10C Control of Transient Combustibles 020/001 | |||
PPM 1.3.85 On-Line Fire Risk Management 005/001 | |||
PPM 15.1.12 Fire Main Header Flush and Hydrant Inspection 19 | |||
PPM 15.1.29 B.5.b Pumper Truck and Monitor Nozzle Operability 10 | |||
PPM 15.2.2 Function and Sensitivity Check of Ionization Detectors 18 | |||
PPM 15.2.5 Zone 66 Ionization Detector Visual Inspections, 8 | |||
Function and Sensitivity Tests | |||
PPM 15.2.25 Manual Pull Stations - CFT 9 | |||
PPM 15.2.33 Power Generation Control Complex Halon Initiator 5 | |||
Replacement | |||
PPM 15.2.36 Power Generation Control Complex Halon System 10 | |||
U679 Through U894 - Sensitivity Check, Actuation | |||
Test and CFT | |||
PPM 15.2.39 Emergency Lighting 8-Hour EBU and Essential 003/003 | |||
Fluorescent Lighting | |||
PPM 15.2.40 Emergency Lighting 8-Hour EBU Discharge - Annual 007/002 | |||
PPM 15.2.41 Annual Surveillance of 8-Hour Portable Lanterns 005/003 | |||
PPM 15.3.2 Hose Station Inspection and Change out 13 | |||
Procedures | |||
Title Revision | |||
Number | |||
PPM 15.3.5 Fire Damper Operational Inspection 15 | |||
PPM 15.3.6 Control Room Halon Pressure Check, Weight Check, 9 | |||
Flow Test, and Power Generation Control Complex | |||
Barrier Inspection | |||
PPM 15.3.9 Fire Pump Drive Inspection/Maintenance of 17 | |||
FP-ENG-1 (FP-P-1) | |||
PPM 15.3.10 Fire Pump Drive Inspection/Maintenance of 20 | |||
FP-ENG-110 (FP-P-110) | |||
PPM 15.3.17 Fire Door Operability - Semiannual, Annual, Biennial 9 | |||
PPM 15.4.2 Fire Main Hydraulic Data Acquisition 13 | |||
PPM 15.4.6 Essential Fire Rated Penetration Seal, and Essential 10 | |||
Fire and Flood Barrier Operability Inspection | |||
PPM 15.4.8 Fire Protection System Annual Functional Test 21 | |||
SWP-FPP-01 Nuclear Fire Protection Program (FPP) 8 | |||
Vendor Documents Title Date | |||
Number | |||
CVI 02,02,01, NEDO-10466-A, Power Generation Control Complex February | |||
Sheet 99 Design Criteria and Safety Evaluation 1979 | |||
CVI 29,00,36 Johnston Vertical Deep well Pumps - Installation, June 23, 1993 | |||
Operation, and Maintenance Manual | |||
Work Orders | |||
2013384-01 02013384-01 02013384-01 02013384-01 02013384-01 | |||
2013384-01 02013398-01 02035208-01 02057483-01 02066673-01 | |||
2066673-17 02066673-32 02066673-45 02066678-01 02066678-04 | |||
2066678-05 02076515-01 02078563-01 02083090-09 02083772-01 | |||
2084026-01 02084026-01 02088624-01 02094033-01 02094034-01 | |||
2094035-01 02094036-01 02094037-01 02100740-01 02100771-01 | |||
2100855-01 02102264-01 02104060-01 02108154-01 02109260-21 | |||
2109260-22 02116464-01 02119050-01 | |||
ML18129A382 | |||
SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002 | |||
By: JMM Yes No Publicly Available Sensitive | |||
OFFICE RI:EB2 RI:EB2 SRI:EB2 SRI:EB2 BC:DRP/A ABC:DRS/EB2 | |||
NAME BCorrell SMakor GPick JMateychick MHaire JDrake | |||
SIGNATURE /RA/ /RA-E/ /RA/ /RA/ /RA/ /RA/ | |||
DATE 05/03/18 05/04/18 05/07/18 05/03/18 05/09/18 05/09/18 | |||
May 9, 2018 | |||
Mr. Brad Sawatzke | |||
Chief Executive Officer | |||
Energy Northwest | |||
MD 1023, P.O. Box 968 | |||
Richland, WA 99352 | |||
SUBJECT: COLUMBIA GENERATING STATION - NRC TRIENNIAL FIRE | |||
PROTECTION BASELINE INSPECTION REPORT (NRC INSPECTION | |||
REPORT 05000397/2018007) | |||
Dear Mr. Sawatzke: | |||
On April 26, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at | |||
the Columbia Generating Station and discussed the results of this inspection with Mr. Alex | |||
Javorik, Vice President of Engineering, and other members of your staff. The results of this | |||
inspection are documented in the enclosed report. | |||
The NRC inspectors did not identify any finding or violation of more than minor significance. | |||
This letter, its enclosure, and your response (if any) will be made available for public inspection | |||
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document | |||
Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for | |||
Withholding. | |||
Sincerely, | |||
/RA/ | |||
James | |||
: [[contact::F. Drake]], Acting Chief | |||
Engineering Branch 2 | |||
Division of Reactor Safety | |||
Docket: 50-397 | |||
License: NPF-21 | |||
Enclosure: | |||
Inspection Report 05000397/2018007 | |||
U.S. NUCLEAR REGULATORY COMMISSION | |||
Inspection Report | |||
Docket Number: 05000397 | |||
License Number: NPF-21 | |||
Report Number: 05000397/2018007 | |||
Enterprise Identifier: I-2018-007-0002 | |||
Licensee: Energy Northwest | |||
Facility: Columbia Generating Station | |||
Location: Richland, Washington | |||
Inspection Dates: April 9, 2018, to April 26, 2018 | |||
Inspectors: | |||
: [[contact::J. Mateychick]], Senior Reactor Inspector (Team Lead) | |||
: [[contact::B. Correll]], Reactor Inspector | |||
: [[contact::S. Makor]], Reactor Inspector | |||
: [[contact::G. Pick]], Senior Reactor Inspector | |||
Approved By: | |||
: [[contact::J. Drake]], Chief | |||
Engineering Branch 2 | |||
Division of Reactor Safety | |||
SUMMARY | |||
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees | |||
performance by conducting a Triennial Fire Protection Baseline Inspection at Columbia | |||
Generating Station in accordance with the Reactor Oversight Process. The Reactor | |||
Oversight Process is the NRCs program for overseeing the safe operation of commercial | |||
nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for | |||
more information. NRC and self-revealed findings, violations, and additional items are | |||
summarized in the table below. | |||
List of Findings and Violations | |||
The NRC inspectors did not identify any finding or violation of more than minor significance. | |||
INSPECTION SCOPES | |||
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) | |||
in effect at the beginning of the inspection unless otherwise noted. Currently approved | |||
IPs with their attached revision histories are located on the public website at | |||
http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. | |||
Samples were declared complete when the IP requirements most appropriate to the inspection | |||
activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor | |||
Inspection Program - Operations Phase. The inspectors reviewed selected procedures and | |||
records, observed activities, and interviewed personnel to assess licensee performance and | |||
compliance with Commission rules and regulations, license conditions, site procedures, and | |||
standards. | |||
REACTOR SAFETY | |||
71111.05T - Fire Protection (Triennial) | |||
The inspectors evaluated the design, operational status, and material condition of the | |||
licensees fire protection program, including assumptions made in plant and area specific | |||
fire protection analyses, by verifying that the licensees program includes: | |||
(1) Adequate controls for combustibles and ignition sources inside the plant; | |||
(2) Adequate fire detection and suppression capability; | |||
(3) Passive fire protection features in good material condition; | |||
(4) Adequate compensatory measures for out-of-service, degraded or inoperable fire | |||
protection equipment, systems, or features; | |||
(5) Adequate protection to ensure the post-fire capability to safely shutdown the plant, | |||
including implementation of NRC/industry fire-induced circuit failure analysis guidance; | |||
(6) Feasible and reliable manual actions when appropriate to achieve safe shutdown; and | |||
(7) Adequate review and documentation of fire protection program changes. | |||
Fire Protection Inspection Requirements (Four Samples) | |||
The inspectors evaluated fire protection program implementation in the following selected | |||
areas: | |||
Fire Area Description | |||
R-1D Reactor Building Northwest 471 Elevation | |||
RC-3 Cable Chase | |||
RC-4 Division 1 Electrical Equipment Room | |||
RC-14 Division 1 Switchgear Room | |||
The inspectors reviewed and evaluated the following fire protection inspection requirements: | |||
(1) Fire brigade drill performance | |||
(2) Protection of safe shutdown capabilities | |||
(3) Passive fire protection | |||
(4) Active fire protection | |||
(5) Protection from damage from fire suppression activities | |||
(6) Alternative shutdown capability | |||
(7) Circuit analysis | |||
(8) Communications | |||
(9) Emergency lighting (Fixed and Portable 8 hour units) | |||
(10) Cold shutdown repairs | |||
(11) Compensatory measures | |||
a. Compensatory measures for degraded fire protection components | |||
b. Compensatory measures for components necessary to achieve safe and stable | |||
conditions | |||
(12) Review and documentation of fire protection plan changes | |||
(13) Control of transient combustibles and ignition sources | |||
(14) Sample of fire protection corrective action documents | |||
B.5.b Inspection Activities (One Sample) | |||
The inspectors evaluated feasibility of the B.5.b mitigating strategies by determining the | |||
following: | |||
* Procedures are being maintained and adequate | |||
* Equipment is properly staged and is being maintained and tested | |||
* Station personnel are knowledgeable and can implement the procedures | |||
The inspectors evaluated feasibility of the following B.5.b Mitigating Strategies: | |||
ABN-TSG-008 Initiation of Drywell or Wetwell Spray Through the Residual Heat | |||
Removal System | |||
ABN-TSG-010 Spent Fuel Pool Makeup Through the Residual Heat Removal System | |||
Via Fire Water or Condensate Transfer | |||
INSPECTION RESULTS | |||
The NRC inspectors did not identify any finding or violation of more than minor significance. | |||
EXIT MEETINGS AND DEBRIEFS | |||
The inspectors verified no proprietary information was retained or documented in this report. | |||
On April 26, 2018, the inspectors presented the fire protection inspection results to | |||
Mr. | |||
: [[contact::A. Javorik]], Vice President of Engineering, and other members of the licensee staff. | |||
DOCUMENTS REVIEWED | |||
Cable Routing Data Components | |||
Residual Heat Removal System, Standby Service Water System | |||
(RHR-P-2B, RHR-V-6B, RHR-FCV-64B, RHR-V-4B, SW-P-1B, RHR-V-3B, SW-V-12B) | |||
Calculations Title Revision or | |||
Number Date | |||
FP-02-07-02 Hydraulic Analysis of Fire Water Supply System 2 | |||
FPF 2.11 Emergency Lighting Monthly Inspections and 2 | |||
Appendix R Lamp Positioning | |||
ME-02-02-23 Post-Fire Safe Shutdown Flooding Analysis - 1 | |||
Radwaste Building | |||
MSE-EJJ-10-01 Expert Panel Identification and Review of Multiple April 23, 2010 | |||
Spurious Operation Scenarios | |||
NE-02-85-19 Post-Fire Safe Shutdown Analysis 12 | |||
NE-02-94-35 System Impact on Post-Fire Safe Shutdown 6 | |||
TM-2160 B.5.b Implementation 5 | |||
Action Requests (AR-) | |||
378859* 379297* 379315* 378806* 378968* 379317* 379319* 378940* | |||
378989 379316* 379320* 335821 374802 377838 378937* 340250 | |||
377836 378917* 379403* 379349* 378917* | |||
*Issued as a result of inspection activities. | |||
Drawings Title Revision | |||
Number | |||
2-217A-28 Cable Chase - Zone 2 System 66 (Preaction) 10 | |||
2-217A-29 Cable Chase - Zone 2 System 66 (Preaction) 5 | |||
2-217A-30 Cable Chase - Zone 2 System 66 (Preaction) 7 | |||
2-217A-31 Cable Chase - Zone 2 System 66 (Preaction) 6 | |||
A529 Reactor Building Stair No. A5 6 | |||
A530 Reactor Building Stair No. A6 6 | |||
Drawings Title Revision | |||
Number | |||
C 896 FP-TK-110 Water Storage Tank Plan Sections and 3 | |||
Details | |||
D00292, Sheet 36 Fire Detection and Alarm System Installation Diagram 0 | |||
- Radioactive Waste and Control Building El 467 | |||
FM892-8 Sprinkler and Hose Station Plans EL 467-0 5 | |||
and 471-0 and Miscellaneous Floors | |||
FM-892-12 Access-Egress for Post-Fire Safe Shutdown Activities 12 | |||
FM-892-13 Access-Egress for Post-Fire Safe Shutdown Activities 10 | |||
FM-892-14 Access-Egress for Post-Fire Safe Shutdown Activities 6 | |||
M521-1 Flow Diagram Residual Heat Removal Loop A 115 | |||
M521-2 Flow Diagram Residual Heat Removal Loop B 115 | |||
EWD-88-E-007 Electrical Wiring Diagram Diesel Generator (DG) 10 | |||
Building H&V System DG2 Room Normal Supply | |||
Fan DMA-FN-22 | |||
EWD-88E-020A Electrical Wiring Diagram Diesel Generator 11 | |||
Building H&V System DG2 Room Normal Air | |||
Dampers DMA-AD-22/1 and DMA-AD-22/2 | |||
EWD-88E-029A Electrical Wiring Diagram Diesel Generator 2 | |||
Building H&V System DG2 Room Air Handling | |||
Unit DMA-AH-22 Outlet Heater DMA-EHC-22 | |||
EWD-88E-034 Electrical Wiring Diagram Diesel Generator Building 2 | |||
H&V System Annunciator DMA-ANN-PNL/DGHV2 | |||
EWD-9E-019 Electrical Wiring Diagram Residual Heat Removal 25 | |||
System Motor Operated Valve (MOV) | |||
RHR-V-4B (E12-F004B) | |||
PFSS-2 Appendix R Post-Fire Safe Shutdown (PFSS) 16 | |||
Division 2 Boundaries of Line Diagram | |||
EWD-9E-097 Electrical Wiring Diagram Residual Heat Removal 13 | |||
System Miscellaneous Relay Circuits (Division 2) | |||
Drawings Title Revision | |||
Number | |||
E948-1A Appendix R Post-Fire Safe Shutdown Protected 0 | |||
Raceways Whittaker Cable Support Diagram | |||
E948-2A Appendix R Post-Fire Safe Shutdown Protected 8 | |||
Raceways Reactor Building Elevations 501-0 and | |||
2-0 | |||
E948-3 Appendix R Post-Fire Safe Shutdown Protected 13 | |||
Raceways Radwaste Building - Elevations 467-0 and | |||
25-0 | |||
EWD-9E-004 Electrical Wiring Diagram Residual Heat Removal 19 | |||
System Pump RHR-P-2B Breaker RHR-CB-P2B | |||
EWD-9E-099 Electrical Wiring Diagram Residual Heat Removal 10 | |||
System Miscellaneous Relay Circuits (Division 2) | |||
EWD-9E-100 Electrical Wiring Diagram Residual Heat Removal 8 | |||
System Miscellaneous Relay Circuits (Division 2) | |||
E502-2 Main One Line Diagram 63 | |||
EWD-9E-003 Electrical Wiring Diagram Residual Heat Removal 22 | |||
System Pump RHR-P-2B (E12-C002B) | |||
EWD-7E-020 Electrical Wiring Diagram High Pressure Core Spray 16 | |||
System MOV HPCS-V-15 (E22-F015) | |||
EWD-7E-023 Electrical Wiring Diagram High Pressure Core Spray 22 | |||
System Pump HPCS-P-1 (E-22-C001) | |||
EWD-7E-022 Electrical Wiring Diagram High Pressure Core 21 | |||
Spray System Pump HPCS-P-1 (E22-C001) | |||
Breaker HPCS-CB-P1 | |||
EWD-7E-003 Electrical Wiring Diagram High Pressure Core 7 | |||
Spray System Standby Water Leg Pump HPCS-P-3 | |||
(E22-C003) | |||
EWD-7E-018 Electrical Wiring Diagram High Pressure Core Spray 17 | |||
System MOV HPCS-V-11 (E22-F011) | |||
M520 Flow Diagram High Pressure Core Spray (HPCS) 104 | |||
System and Low Pressure Core Spray Systems | |||
Reactor Building | |||
Drawings Title Revision | |||
Number | |||
EWD-7E-017 Electrical Wiring Diagram High Pressure Core Spray 15 | |||
System MOV HPCS-V-10 (E22-F0101) | |||
EWD-58E-022 Electrical Wiring Diagram Standby Service Water 21 | |||
System MOV SW-V-12B | |||
EWD-58E-021 Electrical Wiring Diagram Standby Service Water 24 | |||
System, MOV-SW-V-12B | |||
EWD-58E-004 Electrical Wiring Diagram Standby Service Water 27 | |||
System SW-P-1B Breaker SW-CB-P1B | |||
EWD-58E-004B Electrical Wiring Diagram Standby Service Water 3 | |||
System SW-P-1B Breaker SW-CB-P1B | |||
M524-2 Flow Diagram Standby Service Water System 120 | |||
Reactor, Radwaste, DG Buildings and Yard | |||
EWD-9E-022 Electrical Wiring Diagram Residual Heat Removal 21 | |||
System MOV RHR-V-6B (E12-F006B) | |||
EWD-58E-014 Electrical Wiring Diagram Standby Service Water 19 | |||
System MOV SW-V-2B | |||
EWD-58E-015 Electrical Wiring Diagram Standby Service Water 22 | |||
System MOV SW-V-2B | |||
E542-22D Connection Wiring Diagram Supervisory 2 | |||
Panel E-CP-C2 (Division 2) Rear Sub-Panel Lower | |||
Half | |||
E542-22E Connection Wiring Diagram, Supervisory 5 | |||
Panel E-CP-CS2 (Division 2) Right Sub-Panel | |||
EWD-58E-004 Electrical Wiring Diagram Standby Service Water 27 | |||
System W-P-1B Breaker SW-CB-P1B | |||
EWD-58E-004B Electrical Wiring Diagram Standby Service Water 3 | |||
System SW-P-1B Breaker SW-CB-P1B | |||
PFSS-2 Appendix R Post-Fire Safe Shutdown (PFSS) 16 | |||
Division 2 Boundaries One Line Diagram | |||
EWD-9E-006 Electrical Wiring Diagram Residual Heat Removal 14 | |||
Drawings Title Revision | |||
Number | |||
System Pump RHR-P-2C Breaker RHR-CB-P2C | |||
EWD-6E-008 Electrical Wiring Diagram Reactor Core Isolation 23 | |||
Cooling System MOV RCIC-V-45 (E51-F045) | |||
EWD-6E-008A Electrical Wiring Diagram Reactor Core Isolation 5 | |||
Cooling System MOV RCIC-V-45 (E51-F045) | |||
6E013 Reactor Core Isolation Cooling System Miscellaneous 21 | |||
Relay Circuits Sheet 4 | |||
EWD-9E-057 Electrical Wiring Diagram Residual Heat Removal 20 | |||
System MOV RHR-FCV-64B (E12-F064B) | |||
EWD-9E-123 Electrical Wiring Diagram Residual Heat Removal 3 | |||
System Annunciator | |||
EWD-9E-004A Electrical Wiring Diagram Residual Heat Removal 1 | |||
System Pump RHR-P-2B Breaker RHR-CB-P2B | |||
EWD-9E-004 Electrical Wiring Diagram Residual Heat Removal 19 | |||
System Pump RHR-P-2B Breaker RHR-CB-P2B | |||
EWD-41-003 Electrical Wiring Diagram Reactor Water Cleanup 0 | |||
System RWCU-FT-37, RWCU-PT-5, and | |||
RWCU-TS-20 | |||
EWD-46E-252C Electrical Wiring Diagram AC Electrical Distribution 4 | |||
System Power Panel E-PP-8AF Circuit Details | |||
EWD-9E-019 Electrical Wiring Diagram Residual Heat Removal 25 | |||
System MOV-RHR-V-4B (E12-F004B) | |||
EWD-58E-047 Electrical Wiring Diagram Standby Service Water 22 | |||
System MOV RHR-V-68B (E12-F068B) | |||
EWD-1E-038 Electrical Wiring Diagram Nuclear Boiler System 21 | |||
Automatic Depressurization Safety Relief | |||
Valve MS-RV-3D (B22-F013V) | |||
EWD-1E-038A Electrical Wiring Diagram Nuclear Boiler System 4 | |||
Automatic Depressurization Safety Relief | |||
Valve M-RV-3D (B22-F013V) | |||
Drawings Title Revision | |||
Number | |||
H-4649-D Sections - 20 x 10 Type A Head - 3 Stage | |||
H-4650-D Fire Pump - Vertical Turbine Model EBA 2 | |||
M515-1 Flow Diagram - Fire Protection System 110 | |||
M515-2 Flow Diagram - Fire Protection System Details 18 | |||
M515-4 Flow Diagram - Fire Protection System General 2 | |||
Services Building and Turbine Generator Building | |||
M515-5 Flow Diagram - Fire Protection System Reactor 6 | |||
Building, Diesel Generator Building, and Radwaste | |||
Building | |||
M573-2 Flow Diagram - Potable Water Cold and Fire 8 | |||
Protection Systems Pump houses | |||
M585 General Arrangement Plans and Sections Circulating 27 | |||
Water Pump House | |||
M827 Heating Ventilation and Air Conditioning - Sections 41 | |||
and Details Radwaste and Control Building | |||
M932-1 Fire Main Ring Header 6 | |||
Modification Title Revision | |||
Number | |||
16302-1 Disabled HPCS-V-10 and HPCS-V11 in Place 12 | |||
Procedures Title Revision | |||
Number | |||
ABN-EDMG Extensive Damage Mitigation Guidelines (EDMG) 020/002 | |||
ABN-CR-EVAC Control Room Evacuation and Remote Cooldown 37 | |||
ABN-FIRE Fire 40 | |||
ABN-RHR-SDC- Residual Heat Removal Alternate Shutdown Cooling 015 | |||
ALT | |||
ABN-TSG-008 Initiation of Drywell or Wetwell Spray Through the 006 | |||
Residual Heat Removal System | |||
Procedures | |||
Title Revision | |||
Number | |||
ABN-TSG-010 Spent Fuel Pool Makeup Through the Residual Heat 006 | |||
Removal System Via Fire Water or Condensate | |||
Transfer | |||
OI-18 Equipment Operator Rounds 014/001 | |||
PFP-RB-471 Reactor 471 Pre-fire Plans 5 | |||
PFP-RW-467 Radwaste (RW) 467 Pre-fire Plans 5 | |||
PPM 1.3.10 Plant Fire Protection Program Implementation 034/002 | |||
PPM 1.3.10A Control of Ignition Sources 017/001 | |||
PPM 1.3.10B Active Fire System Operability and Impairment 015/002 | |||
Control | |||
PPM 1.3.10C Control of Transient Combustibles 020/001 | |||
PPM 1.3.85 On-Line Fire Risk Management 005/001 | |||
PPM 15.1.12 Fire Main Header Flush and Hydrant Inspection 19 | |||
PPM 15.1.29 B.5.b Pumper Truck and Monitor Nozzle Operability 10 | |||
PPM 15.2.2 Function and Sensitivity Check of Ionization Detectors 18 | |||
PPM 15.2.5 Zone 66 Ionization Detector Visual Inspections, 8 | |||
Function and Sensitivity Tests | |||
PPM 15.2.25 Manual Pull Stations - CFT 9 | |||
PPM 15.2.33 Power Generation Control Complex Halon Initiator 5 | |||
Replacement | |||
PPM 15.2.36 Power Generation Control Complex Halon System 10 | |||
U679 Through U894 - Sensitivity Check, Actuation | |||
Test and CFT | |||
PPM 15.2.39 Emergency Lighting 8-Hour EBU and Essential 003/003 | |||
Fluorescent Lighting | |||
PPM 15.2.40 Emergency Lighting 8-Hour EBU Discharge - Annual 007/002 | |||
PPM 15.2.41 Annual Surveillance of 8-Hour Portable Lanterns 005/003 | |||
PPM 15.3.2 Hose Station Inspection and Change out 13 | |||
Procedures | |||
Title Revision | |||
Number | |||
PPM 15.3.5 Fire Damper Operational Inspection 15 | |||
PPM 15.3.6 Control Room Halon Pressure Check, Weight Check, 9 | |||
Flow Test, and Power Generation Control Complex | |||
Barrier Inspection | |||
PPM 15.3.9 Fire Pump Drive Inspection/Maintenance of 17 | |||
FP-ENG-1 (FP-P-1) | |||
PPM 15.3.10 Fire Pump Drive Inspection/Maintenance of 20 | |||
FP-ENG-110 (FP-P-110) | |||
PPM 15.3.17 Fire Door Operability - Semiannual, Annual, Biennial 9 | |||
PPM 15.4.2 Fire Main Hydraulic Data Acquisition 13 | |||
PPM 15.4.6 Essential Fire Rated Penetration Seal, and Essential 10 | |||
Fire and Flood Barrier Operability Inspection | |||
PPM 15.4.8 Fire Protection System Annual Functional Test 21 | |||
SWP-FPP-01 Nuclear Fire Protection Program (FPP) 8 | |||
Vendor Documents Title Date | |||
Number | |||
CVI 02,02,01, NEDO-10466-A, Power Generation Control Complex February | |||
Sheet 99 Design Criteria and Safety Evaluation 1979 | |||
CVI 29,00,36 Johnston Vertical Deep well Pumps - Installation, June 23, 1993 | |||
Operation, and Maintenance Manual | |||
Work Orders | |||
2013384-01 02013384-01 02013384-01 02013384-01 02013384-01 | |||
2013384-01 02013398-01 02035208-01 02057483-01 02066673-01 | |||
2066673-17 02066673-32 02066673-45 02066678-01 02066678-04 | |||
2066678-05 02076515-01 02078563-01 02083090-09 02083772-01 | |||
2084026-01 02084026-01 02088624-01 02094033-01 02094034-01 | |||
2094035-01 02094036-01 02094037-01 02100740-01 02100771-01 | |||
2100855-01 02102264-01 02104060-01 02108154-01 02109260-21 | |||
2109260-22 02116464-01 02119050-01 | |||
ML18129A382 | |||
SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002 | |||
By: JMM Yes No Publicly Available Sensitive | |||
OFFICE RI:EB2 RI:EB2 SRI:EB2 SRI:EB2 BC:DRP/A ABC:DRS/EB2 | |||
NAME BCorrell SMakor GPick JMateychick MHaire JDrake | |||
SIGNATURE /RA/ /RA-E/ /RA/ /RA/ /RA/ /RA/ | |||
DATE 05/03/18 05/04/18 05/07/18 05/03/18 05/09/18 05/09/18 | |||
}} | }} |
Latest revision as of 04:31, 21 October 2019
ML18129A382 | |
Person / Time | |
---|---|
Site: | Columbia |
Issue date: | 05/09/2018 |
From: | James Drake NRC/RGN-IV/DRS/EB-2 |
To: | Sawatzke B Energy Northwest |
Drake J | |
References | |
IR 2018007 | |
Download: ML18129A382 (14) | |
Text
SUBJECT:
COLUMBIA GENERATING STATION - NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION REPORT (NRC INSPECTION REPORT 05000397/2018007)
Dear Mr. Sawatzke:
On April 26, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the Columbia Generating Station and discussed the results of this inspection with Mr. Alex Javorik, Vice President of Engineering, and other members of your staff. The results of this inspection are documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
James F. Drake, Acting Chief Engineering Branch 2 Division of Reactor Safety Docket: 50-397 License: NPF-21 Enclosure:
Inspection Report 05000397/2018007
U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Number: 05000397 License Number: NPF-21 Report Number: 05000397/2018007 Enterprise Identifier: I-2018-007-0002 Licensee: Energy Northwest Facility: Columbia Generating Station Location: Richland, Washington Inspection Dates: April 9, 2018, to April 26, 2018 Inspectors: J. Mateychick, Senior Reactor Inspector (Team Lead)
B. Correll, Reactor Inspector S. Makor, Reactor Inspector G. Pick, Senior Reactor Inspector Approved By: J. Drake, Chief Engineering Branch 2 Division of Reactor Safety Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees performance by conducting a Triennial Fire Protection Baseline Inspection at Columbia Generating Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC and self-revealed findings, violations, and additional items are summarized in the table below.
List of Findings and Violations The NRC inspectors did not identify any finding or violation of more than minor significance.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.05T - Fire Protection (Triennial)
The inspectors evaluated the design, operational status, and material condition of the licensees fire protection program, including assumptions made in plant and area specific fire protection analyses, by verifying that the licensees program includes:
- (1) Adequate controls for combustibles and ignition sources inside the plant;
- (2) Adequate fire detection and suppression capability;
- (3) Passive fire protection features in good material condition;
- (4) Adequate compensatory measures for out-of-service, degraded or inoperable fire protection equipment, systems, or features;
- (5) Adequate protection to ensure the post-fire capability to safely shutdown the plant, including implementation of NRC/industry fire-induced circuit failure analysis guidance;
- (6) Feasible and reliable manual actions when appropriate to achieve safe shutdown; and
- (7) Adequate review and documentation of fire protection program changes.
Fire Protection Inspection Requirements (Four Samples)
The inspectors evaluated fire protection program implementation in the following selected areas:
Fire Area Description R-1D Reactor Building Northwest 471 Elevation RC-3 Cable Chase RC-4 Division 1 Electrical Equipment Room RC-14 Division 1 Switchgear Room The inspectors reviewed and evaluated the following fire protection inspection requirements:
- (1) Fire brigade drill performance
- (2) Protection of safe shutdown capabilities
- (3) Passive fire protection
- (4) Active fire protection
- (5) Protection from damage from fire suppression activities
- (6) Alternative shutdown capability
- (7) Circuit analysis
- (8) Communications
- (9) Emergency lighting (Fixed and Portable 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> units)
- (10) Cold shutdown repairs
- (11) Compensatory measures a. Compensatory measures for degraded fire protection components b. Compensatory measures for components necessary to achieve safe and stable conditions
- (12) Review and documentation of fire protection plan changes
- (13) Control of transient combustibles and ignition sources
- (14) Sample of fire protection corrective action documents B.5.b Inspection Activities (One Sample)
The inspectors evaluated feasibility of the B.5.b mitigating strategies by determining the following:
- Procedures are being maintained and adequate
- Equipment is properly staged and is being maintained and tested
- Station personnel are knowledgeable and can implement the procedures The inspectors evaluated feasibility of the following B.5.b Mitigating Strategies:
ABN-TSG-008 Initiation of Drywell or Wetwell Spray Through the Residual Heat Removal System ABN-TSG-010 Spent Fuel Pool Makeup Through the Residual Heat Removal System Via Fire Water or Condensate Transfer
INSPECTION RESULTS
The NRC inspectors did not identify any finding or violation of more than minor significance.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On April 26, 2018, the inspectors presented the fire protection inspection results to Mr. A. Javorik, Vice President of Engineering, and other members of the licensee staff.
DOCUMENTS REVIEWED
Cable Routing Data Components
Residual Heat Removal System, Standby Service Water System
(RHR-P-2B, RHR-V-6B, RHR-FCV-64B, RHR-V-4B, SW-P-1B, RHR-V-3B, SW-V-12B)
Calculations Title Revision or
Number Date
FP-02-07-02 Hydraulic Analysis of Fire Water Supply System 2
FPF 2.11 Emergency Lighting Monthly Inspections and 2
Appendix R Lamp Positioning
ME-02-02-23 Post-Fire Safe Shutdown Flooding Analysis - 1
Radwaste Building
MSE-EJJ-10-01 Expert Panel Identification and Review of Multiple April 23, 2010
Spurious Operation Scenarios
NE-02-85-19 Post-Fire Safe Shutdown Analysis 12
NE-02-94-35 System Impact on Post-Fire Safe Shutdown 6
TM-2160 B.5.b Implementation 5
Action Requests (AR-)
378859* 379297* 379315* 378806* 378968* 379317* 379319* 378940*
378989 379316* 379320* 335821 374802 377838 378937* 340250
377836 378917* 379403* 379349* 378917*
- Issued as a result of inspection activities.
Drawings Title Revision
Number
2-217A-28 Cable Chase - Zone 2 System 66 (Preaction) 10
2-217A-29 Cable Chase - Zone 2 System 66 (Preaction) 5
2-217A-30 Cable Chase - Zone 2 System 66 (Preaction) 7
2-217A-31 Cable Chase - Zone 2 System 66 (Preaction) 6
A529 Reactor Building Stair No. A5 6
A530 Reactor Building Stair No. A6 6
Drawings Title Revision
Number
C 896 FP-TK-110 Water Storage Tank Plan Sections and 3
Details
D00292, Sheet 36 Fire Detection and Alarm System Installation Diagram 0
- Radioactive Waste and Control Building El 467
FM892-8 Sprinkler and Hose Station Plans EL 467-0 5
and 471-0 and Miscellaneous Floors
FM-892-12 Access-Egress for Post-Fire Safe Shutdown Activities 12
FM-892-13 Access-Egress for Post-Fire Safe Shutdown Activities 10
FM-892-14 Access-Egress for Post-Fire Safe Shutdown Activities 6
M521-1 Flow Diagram Residual Heat Removal Loop A 115
M521-2 Flow Diagram Residual Heat Removal Loop B 115
EWD-88-E-007 Electrical Wiring Diagram Diesel Generator (DG) 10
Building H&V System DG2 Room Normal Supply
Fan DMA-FN-22
EWD-88E-020A Electrical Wiring Diagram Diesel Generator 11
Building H&V System DG2 Room Normal Air
Dampers DMA-AD-22/1 and DMA-AD-22/2
EWD-88E-029A Electrical Wiring Diagram Diesel Generator 2
Building H&V System DG2 Room Air Handling
Unit DMA-AH-22 Outlet Heater DMA-EHC-22
EWD-88E-034 Electrical Wiring Diagram Diesel Generator Building 2
H&V System Annunciator DMA-ANN-PNL/DGHV2
EWD-9E-019 Electrical Wiring Diagram Residual Heat Removal 25
System Motor Operated Valve (MOV)
RHR-V-4B (E12-F004B)
PFSS-2 Appendix R Post-Fire Safe Shutdown (PFSS) 16
Division 2 Boundaries of Line Diagram
EWD-9E-097 Electrical Wiring Diagram Residual Heat Removal 13
System Miscellaneous Relay Circuits (Division 2)
Drawings Title Revision
Number
E948-1A Appendix R Post-Fire Safe Shutdown Protected 0
Raceways Whittaker Cable Support Diagram
E948-2A Appendix R Post-Fire Safe Shutdown Protected 8
Raceways Reactor Building Elevations 501-0 and
2-0
E948-3 Appendix R Post-Fire Safe Shutdown Protected 13
Raceways Radwaste Building - Elevations 467-0 and
25-0
EWD-9E-004 Electrical Wiring Diagram Residual Heat Removal 19
System Pump RHR-P-2B Breaker RHR-CB-P2B
EWD-9E-099 Electrical Wiring Diagram Residual Heat Removal 10
System Miscellaneous Relay Circuits (Division 2)
EWD-9E-100 Electrical Wiring Diagram Residual Heat Removal 8
System Miscellaneous Relay Circuits (Division 2)
E502-2 Main One Line Diagram 63
EWD-9E-003 Electrical Wiring Diagram Residual Heat Removal 22
System Pump RHR-P-2B (E12-C002B)
EWD-7E-020 Electrical Wiring Diagram High Pressure Core Spray 16
System MOV HPCS-V-15 (E22-F015)
EWD-7E-023 Electrical Wiring Diagram High Pressure Core Spray 22
System Pump HPCS-P-1 (E-22-C001)
EWD-7E-022 Electrical Wiring Diagram High Pressure Core 21
Spray System Pump HPCS-P-1 (E22-C001)
Breaker HPCS-CB-P1
EWD-7E-003 Electrical Wiring Diagram High Pressure Core 7
Spray System Standby Water Leg Pump HPCS-P-3
(E22-C003)
EWD-7E-018 Electrical Wiring Diagram High Pressure Core Spray 17
System MOV HPCS-V-11 (E22-F011)
M520 Flow Diagram High Pressure Core Spray (HPCS) 104
System and Low Pressure Core Spray Systems
Reactor Building
Drawings Title Revision
Number
EWD-7E-017 Electrical Wiring Diagram High Pressure Core Spray 15
System MOV HPCS-V-10 (E22-F0101)
EWD-58E-022 Electrical Wiring Diagram Standby Service Water 21
System MOV SW-V-12B
EWD-58E-021 Electrical Wiring Diagram Standby Service Water 24
System, MOV-SW-V-12B
EWD-58E-004 Electrical Wiring Diagram Standby Service Water 27
System SW-P-1B Breaker SW-CB-P1B
EWD-58E-004B Electrical Wiring Diagram Standby Service Water 3
System SW-P-1B Breaker SW-CB-P1B
M524-2 Flow Diagram Standby Service Water System 120
Reactor, Radwaste, DG Buildings and Yard
EWD-9E-022 Electrical Wiring Diagram Residual Heat Removal 21
System MOV RHR-V-6B (E12-F006B)
EWD-58E-014 Electrical Wiring Diagram Standby Service Water 19
System MOV SW-V-2B
EWD-58E-015 Electrical Wiring Diagram Standby Service Water 22
System MOV SW-V-2B
E542-22D Connection Wiring Diagram Supervisory 2
Panel E-CP-C2 (Division 2) Rear Sub-Panel Lower
Half
E542-22E Connection Wiring Diagram, Supervisory 5
Panel E-CP-CS2 (Division 2) Right Sub-Panel
EWD-58E-004 Electrical Wiring Diagram Standby Service Water 27
System W-P-1B Breaker SW-CB-P1B
EWD-58E-004B Electrical Wiring Diagram Standby Service Water 3
System SW-P-1B Breaker SW-CB-P1B
PFSS-2 Appendix R Post-Fire Safe Shutdown (PFSS) 16
Division 2 Boundaries One Line Diagram
EWD-9E-006 Electrical Wiring Diagram Residual Heat Removal 14
Drawings Title Revision
Number
System Pump RHR-P-2C Breaker RHR-CB-P2C
EWD-6E-008 Electrical Wiring Diagram Reactor Core Isolation 23
Cooling System MOV RCIC-V-45 (E51-F045)
EWD-6E-008A Electrical Wiring Diagram Reactor Core Isolation 5
Cooling System MOV RCIC-V-45 (E51-F045)
6E013 Reactor Core Isolation Cooling System Miscellaneous 21
Relay Circuits Sheet 4
EWD-9E-057 Electrical Wiring Diagram Residual Heat Removal 20
System MOV RHR-FCV-64B (E12-F064B)
EWD-9E-123 Electrical Wiring Diagram Residual Heat Removal 3
System Annunciator
EWD-9E-004A Electrical Wiring Diagram Residual Heat Removal 1
System Pump RHR-P-2B Breaker RHR-CB-P2B
EWD-9E-004 Electrical Wiring Diagram Residual Heat Removal 19
System Pump RHR-P-2B Breaker RHR-CB-P2B
EWD-41-003 Electrical Wiring Diagram Reactor Water Cleanup 0
System RWCU-FT-37, RWCU-PT-5, and
RWCU-TS-20
EWD-46E-252C Electrical Wiring Diagram AC Electrical Distribution 4
System Power Panel E-PP-8AF Circuit Details
EWD-9E-019 Electrical Wiring Diagram Residual Heat Removal 25
System MOV-RHR-V-4B (E12-F004B)
EWD-58E-047 Electrical Wiring Diagram Standby Service Water 22
System MOV RHR-V-68B (E12-F068B)
EWD-1E-038 Electrical Wiring Diagram Nuclear Boiler System 21
Automatic Depressurization Safety Relief
Valve MS-RV-3D (B22-F013V)
EWD-1E-038A Electrical Wiring Diagram Nuclear Boiler System 4
Automatic Depressurization Safety Relief
Valve M-RV-3D (B22-F013V)
Drawings Title Revision
Number
H-4649-D Sections - 20 x 10 Type A Head - 3 Stage
H-4650-D Fire Pump - Vertical Turbine Model EBA 2
M515-1 Flow Diagram - Fire Protection System 110
M515-2 Flow Diagram - Fire Protection System Details 18
M515-4 Flow Diagram - Fire Protection System General 2
Services Building and Turbine Generator Building
M515-5 Flow Diagram - Fire Protection System Reactor 6
Building, Diesel Generator Building, and Radwaste
Building
M573-2 Flow Diagram - Potable Water Cold and Fire 8
Protection Systems Pump houses
M585 General Arrangement Plans and Sections Circulating 27
Water Pump House
M827 Heating Ventilation and Air Conditioning - Sections 41
and Details Radwaste and Control Building
M932-1 Fire Main Ring Header 6
Modification Title Revision
Number
16302-1 Disabled HPCS-V-10 and HPCS-V11 in Place 12
Procedures Title Revision
Number
ABN-EDMG Extensive Damage Mitigation Guidelines (EDMG) 020/002
ABN-CR-EVAC Control Room Evacuation and Remote Cooldown 37
ABN-FIRE Fire 40
ABN-RHR-SDC- Residual Heat Removal Alternate Shutdown Cooling 015
ABN-TSG-008 Initiation of Drywell or Wetwell Spray Through the 006
Residual Heat Removal System
Procedures
Title Revision
Number
ABN-TSG-010 Spent Fuel Pool Makeup Through the Residual Heat 006
Removal System Via Fire Water or Condensate
Transfer
OI-18 Equipment Operator Rounds 014/001
PFP-RB-471 Reactor 471 Pre-fire Plans 5
PFP-RW-467 Radwaste (RW) 467 Pre-fire Plans 5
PPM 1.3.10 Plant Fire Protection Program Implementation 034/002
PPM 1.3.10A Control of Ignition Sources 017/001
PPM 1.3.10B Active Fire System Operability and Impairment 015/002
Control
PPM 1.3.10C Control of Transient Combustibles 020/001
PPM 1.3.85 On-Line Fire Risk Management 005/001
PPM 15.1.12 Fire Main Header Flush and Hydrant Inspection 19
PPM 15.1.29 B.5.b Pumper Truck and Monitor Nozzle Operability 10
PPM 15.2.2 Function and Sensitivity Check of Ionization Detectors 18
PPM 15.2.5 Zone 66 Ionization Detector Visual Inspections, 8
Function and Sensitivity Tests
PPM 15.2.25 Manual Pull Stations - CFT 9
PPM 15.2.33 Power Generation Control Complex Halon Initiator 5
Replacement
PPM 15.2.36 Power Generation Control Complex Halon System 10
U679 Through U894 - Sensitivity Check, Actuation
Test and CFT
PPM 15.2.39 Emergency Lighting 8-Hour EBU and Essential 003/003
Fluorescent Lighting
PPM 15.2.40 Emergency Lighting 8-Hour EBU Discharge - Annual 007/002
PPM 15.2.41 Annual Surveillance of 8-Hour Portable Lanterns 005/003
PPM 15.3.2 Hose Station Inspection and Change out 13
Procedures
Title Revision
Number
PPM 15.3.5 Fire Damper Operational Inspection 15
PPM 15.3.6 Control Room Halon Pressure Check, Weight Check, 9
Flow Test, and Power Generation Control Complex
Barrier Inspection
PPM 15.3.9 Fire Pump Drive Inspection/Maintenance of 17
PPM 15.3.10 Fire Pump Drive Inspection/Maintenance of 20
PPM 15.3.17 Fire Door Operability - Semiannual, Annual, Biennial 9
PPM 15.4.2 Fire Main Hydraulic Data Acquisition 13
PPM 15.4.6 Essential Fire Rated Penetration Seal, and Essential 10
Fire and Flood Barrier Operability Inspection
PPM 15.4.8 Fire Protection System Annual Functional Test 21
SWP-FPP-01 Nuclear Fire Protection Program (FPP) 8
Vendor Documents Title Date
Number
CVI 02,02,01, NEDO-10466-A, Power Generation Control Complex February
Sheet 99 Design Criteria and Safety Evaluation 1979
CVI 29,00,36 Johnston Vertical Deep well Pumps - Installation, June 23, 1993
Operation, and Maintenance Manual
Work Orders
2013384-01 02013384-01 02013384-01 02013384-01 02013384-01
2013384-01 02013398-01 02035208-01 02057483-01 02066673-01
2066673-17 02066673-32 02066673-45 02066678-01 02066678-04
2066678-05 02076515-01 02078563-01 02083090-09 02083772-01
2084026-01 02084026-01 02088624-01 02094033-01 02094034-01
2094035-01 02094036-01 02094037-01 02100740-01 02100771-01
2100855-01 02102264-01 02104060-01 02108154-01 02109260-21
2109260-22 02116464-01 02119050-01
SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002
By: JMM Yes No Publicly Available Sensitive
OFFICE RI:EB2 RI:EB2 SRI:EB2 SRI:EB2 BC:DRP/A ABC:DRS/EB2
NAME BCorrell SMakor GPick JMateychick MHaire JDrake
SIGNATURE /RA/ /RA-E/ /RA/ /RA/ /RA/ /RA/
DATE 05/03/18 05/04/18 05/07/18 05/03/18 05/09/18 05/09/18
May 9, 2018
Mr. Brad Sawatzke
Chief Executive Officer
Energy Northwest
MD 1023, P.O. Box 968
Richland, WA 99352
SUBJECT: COLUMBIA GENERATING STATION - NRC TRIENNIAL FIRE
PROTECTION BASELINE INSPECTION REPORT (NRC INSPECTION
REPORT 05000397/2018007)
Dear Mr. Sawatzke:
On April 26, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at
the Columbia Generating Station and discussed the results of this inspection with Mr. Alex
Javorik, Vice President of Engineering, and other members of your staff. The results of this
inspection are documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for
Withholding.
Sincerely,
/RA/
James
- F. Drake, Acting Chief
Engineering Branch 2
Division of Reactor Safety
Docket: 50-397
License: NPF-21
Enclosure:
Inspection Report 05000397/2018007
U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Number: 05000397
License Number: NPF-21
Report Number: 05000397/2018007
Enterprise Identifier: I-2018-007-0002
Licensee: Energy Northwest
Facility: Columbia Generating Station
Location: Richland, Washington
Inspection Dates: April 9, 2018, to April 26, 2018
Inspectors:
- J. Mateychick, Senior Reactor Inspector (Team Lead)
- B. Correll, Reactor Inspector
- S. Makor, Reactor Inspector
- G. Pick, Senior Reactor Inspector
Approved By:
- J. Drake, Chief
Engineering Branch 2
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees
performance by conducting a Triennial Fire Protection Baseline Inspection at Columbia
Generating Station in accordance with the Reactor Oversight Process. The Reactor
Oversight Process is the NRCs program for overseeing the safe operation of commercial
nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for
more information. NRC and self-revealed findings, violations, and additional items are
summarized in the table below.
List of Findings and Violations
The NRC inspectors did not identify any finding or violation of more than minor significance.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs)
in effect at the beginning of the inspection unless otherwise noted. Currently approved
IPs with their attached revision histories are located on the public website at
http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection
activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor
Inspection Program - Operations Phase. The inspectors reviewed selected procedures and
records, observed activities, and interviewed personnel to assess licensee performance and
compliance with Commission rules and regulations, license conditions, site procedures, and
standards.
REACTOR SAFETY
71111.05T - Fire Protection (Triennial)
The inspectors evaluated the design, operational status, and material condition of the
licensees fire protection program, including assumptions made in plant and area specific
fire protection analyses, by verifying that the licensees program includes:
(1) Adequate controls for combustibles and ignition sources inside the plant;
(2) Adequate fire detection and suppression capability;
(3) Passive fire protection features in good material condition;
(4) Adequate compensatory measures for out-of-service, degraded or inoperable fire
protection equipment, systems, or features;
(5) Adequate protection to ensure the post-fire capability to safely shutdown the plant,
including implementation of NRC/industry fire-induced circuit failure analysis guidance;
(6) Feasible and reliable manual actions when appropriate to achieve safe shutdown; and
(7) Adequate review and documentation of fire protection program changes.
Fire Protection Inspection Requirements (Four Samples)
The inspectors evaluated fire protection program implementation in the following selected
areas:
Fire Area Description
R-1D Reactor Building Northwest 471 Elevation
RC-3 Cable Chase
RC-4 Division 1 Electrical Equipment Room
RC-14 Division 1 Switchgear Room
The inspectors reviewed and evaluated the following fire protection inspection requirements:
(1) Fire brigade drill performance
(2) Protection of safe shutdown capabilities
(3) Passive fire protection
(4) Active fire protection
(5) Protection from damage from fire suppression activities
(6) Alternative shutdown capability
(7) Circuit analysis
(8) Communications
(9) Emergency lighting (Fixed and Portable 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> units)
(10) Cold shutdown repairs
(11) Compensatory measures
a. Compensatory measures for degraded fire protection components
b. Compensatory measures for components necessary to achieve safe and stable
conditions
(12) Review and documentation of fire protection plan changes
(13) Control of transient combustibles and ignition sources
(14) Sample of fire protection corrective action documents
B.5.b Inspection Activities (One Sample)
The inspectors evaluated feasibility of the B.5.b mitigating strategies by determining the
following:
- Procedures are being maintained and adequate
- Equipment is properly staged and is being maintained and tested
- Station personnel are knowledgeable and can implement the procedures
The inspectors evaluated feasibility of the following B.5.b Mitigating Strategies:
ABN-TSG-008 Initiation of Drywell or Wetwell Spray Through the Residual Heat
Removal System
ABN-TSG-010 Spent Fuel Pool Makeup Through the Residual Heat Removal System
Via Fire Water or Condensate Transfer
INSPECTION RESULTS
The NRC inspectors did not identify any finding or violation of more than minor significance.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On April 26, 2018, the inspectors presented the fire protection inspection results to
Mr.
- A. Javorik, Vice President of Engineering, and other members of the licensee staff.
DOCUMENTS REVIEWED
Cable Routing Data Components
Residual Heat Removal System, Standby Service Water System
(RHR-P-2B, RHR-V-6B, RHR-FCV-64B, RHR-V-4B, SW-P-1B, RHR-V-3B, SW-V-12B)
Calculations Title Revision or
Number Date
FP-02-07-02 Hydraulic Analysis of Fire Water Supply System 2
FPF 2.11 Emergency Lighting Monthly Inspections and 2
Appendix R Lamp Positioning
ME-02-02-23 Post-Fire Safe Shutdown Flooding Analysis - 1
Radwaste Building
MSE-EJJ-10-01 Expert Panel Identification and Review of Multiple April 23, 2010
Spurious Operation Scenarios
NE-02-85-19 Post-Fire Safe Shutdown Analysis 12
NE-02-94-35 System Impact on Post-Fire Safe Shutdown 6
TM-2160 B.5.b Implementation 5
Action Requests (AR-)
378859* 379297* 379315* 378806* 378968* 379317* 379319* 378940*
378989 379316* 379320* 335821 374802 377838 378937* 340250
377836 378917* 379403* 379349* 378917*
- Issued as a result of inspection activities.
Drawings Title Revision
Number
2-217A-28 Cable Chase - Zone 2 System 66 (Preaction) 10
2-217A-29 Cable Chase - Zone 2 System 66 (Preaction) 5
2-217A-30 Cable Chase - Zone 2 System 66 (Preaction) 7
2-217A-31 Cable Chase - Zone 2 System 66 (Preaction) 6
A529 Reactor Building Stair No. A5 6
A530 Reactor Building Stair No. A6 6
Drawings Title Revision
Number
C 896 FP-TK-110 Water Storage Tank Plan Sections and 3
Details
D00292, Sheet 36 Fire Detection and Alarm System Installation Diagram 0
- Radioactive Waste and Control Building El 467
FM892-8 Sprinkler and Hose Station Plans EL 467-0 5
and 471-0 and Miscellaneous Floors
FM-892-12 Access-Egress for Post-Fire Safe Shutdown Activities 12
FM-892-13 Access-Egress for Post-Fire Safe Shutdown Activities 10
FM-892-14 Access-Egress for Post-Fire Safe Shutdown Activities 6
M521-1 Flow Diagram Residual Heat Removal Loop A 115
M521-2 Flow Diagram Residual Heat Removal Loop B 115
EWD-88-E-007 Electrical Wiring Diagram Diesel Generator (DG) 10
Building H&V System DG2 Room Normal Supply
Fan DMA-FN-22
EWD-88E-020A Electrical Wiring Diagram Diesel Generator 11
Building H&V System DG2 Room Normal Air
Dampers DMA-AD-22/1 and DMA-AD-22/2
EWD-88E-029A Electrical Wiring Diagram Diesel Generator 2
Building H&V System DG2 Room Air Handling
Unit DMA-AH-22 Outlet Heater DMA-EHC-22
EWD-88E-034 Electrical Wiring Diagram Diesel Generator Building 2
H&V System Annunciator DMA-ANN-PNL/DGHV2
EWD-9E-019 Electrical Wiring Diagram Residual Heat Removal 25
System Motor Operated Valve (MOV)
RHR-V-4B (E12-F004B)
PFSS-2 Appendix R Post-Fire Safe Shutdown (PFSS) 16
Division 2 Boundaries of Line Diagram
EWD-9E-097 Electrical Wiring Diagram Residual Heat Removal 13
System Miscellaneous Relay Circuits (Division 2)
Drawings Title Revision
Number
E948-1A Appendix R Post-Fire Safe Shutdown Protected 0
Raceways Whittaker Cable Support Diagram
E948-2A Appendix R Post-Fire Safe Shutdown Protected 8
Raceways Reactor Building Elevations 501-0 and
2-0
E948-3 Appendix R Post-Fire Safe Shutdown Protected 13
Raceways Radwaste Building - Elevations 467-0 and
25-0
EWD-9E-004 Electrical Wiring Diagram Residual Heat Removal 19
System Pump RHR-P-2B Breaker RHR-CB-P2B
EWD-9E-099 Electrical Wiring Diagram Residual Heat Removal 10
System Miscellaneous Relay Circuits (Division 2)
EWD-9E-100 Electrical Wiring Diagram Residual Heat Removal 8
System Miscellaneous Relay Circuits (Division 2)
E502-2 Main One Line Diagram 63
EWD-9E-003 Electrical Wiring Diagram Residual Heat Removal 22
System Pump RHR-P-2B (E12-C002B)
EWD-7E-020 Electrical Wiring Diagram High Pressure Core Spray 16
System MOV HPCS-V-15 (E22-F015)
EWD-7E-023 Electrical Wiring Diagram High Pressure Core Spray 22
System Pump HPCS-P-1 (E-22-C001)
EWD-7E-022 Electrical Wiring Diagram High Pressure Core 21
Spray System Pump HPCS-P-1 (E22-C001)
Breaker HPCS-CB-P1
EWD-7E-003 Electrical Wiring Diagram High Pressure Core 7
Spray System Standby Water Leg Pump HPCS-P-3
(E22-C003)
EWD-7E-018 Electrical Wiring Diagram High Pressure Core Spray 17
System MOV HPCS-V-11 (E22-F011)
M520 Flow Diagram High Pressure Core Spray (HPCS) 104
System and Low Pressure Core Spray Systems
Reactor Building
Drawings Title Revision
Number
EWD-7E-017 Electrical Wiring Diagram High Pressure Core Spray 15
System MOV HPCS-V-10 (E22-F0101)
EWD-58E-022 Electrical Wiring Diagram Standby Service Water 21
System MOV SW-V-12B
EWD-58E-021 Electrical Wiring Diagram Standby Service Water 24
System, MOV-SW-V-12B
EWD-58E-004 Electrical Wiring Diagram Standby Service Water 27
System SW-P-1B Breaker SW-CB-P1B
EWD-58E-004B Electrical Wiring Diagram Standby Service Water 3
System SW-P-1B Breaker SW-CB-P1B
M524-2 Flow Diagram Standby Service Water System 120
Reactor, Radwaste, DG Buildings and Yard
EWD-9E-022 Electrical Wiring Diagram Residual Heat Removal 21
System MOV RHR-V-6B (E12-F006B)
EWD-58E-014 Electrical Wiring Diagram Standby Service Water 19
System MOV SW-V-2B
EWD-58E-015 Electrical Wiring Diagram Standby Service Water 22
System MOV SW-V-2B
E542-22D Connection Wiring Diagram Supervisory 2
Panel E-CP-C2 (Division 2) Rear Sub-Panel Lower
Half
E542-22E Connection Wiring Diagram, Supervisory 5
Panel E-CP-CS2 (Division 2) Right Sub-Panel
EWD-58E-004 Electrical Wiring Diagram Standby Service Water 27
System W-P-1B Breaker SW-CB-P1B
EWD-58E-004B Electrical Wiring Diagram Standby Service Water 3
System SW-P-1B Breaker SW-CB-P1B
PFSS-2 Appendix R Post-Fire Safe Shutdown (PFSS) 16
Division 2 Boundaries One Line Diagram
EWD-9E-006 Electrical Wiring Diagram Residual Heat Removal 14
Drawings Title Revision
Number
System Pump RHR-P-2C Breaker RHR-CB-P2C
EWD-6E-008 Electrical Wiring Diagram Reactor Core Isolation 23
Cooling System MOV RCIC-V-45 (E51-F045)
EWD-6E-008A Electrical Wiring Diagram Reactor Core Isolation 5
Cooling System MOV RCIC-V-45 (E51-F045)
6E013 Reactor Core Isolation Cooling System Miscellaneous 21
Relay Circuits Sheet 4
EWD-9E-057 Electrical Wiring Diagram Residual Heat Removal 20
System MOV RHR-FCV-64B (E12-F064B)
EWD-9E-123 Electrical Wiring Diagram Residual Heat Removal 3
System Annunciator
EWD-9E-004A Electrical Wiring Diagram Residual Heat Removal 1
System Pump RHR-P-2B Breaker RHR-CB-P2B
EWD-9E-004 Electrical Wiring Diagram Residual Heat Removal 19
System Pump RHR-P-2B Breaker RHR-CB-P2B
EWD-41-003 Electrical Wiring Diagram Reactor Water Cleanup 0
System RWCU-FT-37, RWCU-PT-5, and
RWCU-TS-20
EWD-46E-252C Electrical Wiring Diagram AC Electrical Distribution 4
System Power Panel E-PP-8AF Circuit Details
EWD-9E-019 Electrical Wiring Diagram Residual Heat Removal 25
System MOV-RHR-V-4B (E12-F004B)
EWD-58E-047 Electrical Wiring Diagram Standby Service Water 22
System MOV RHR-V-68B (E12-F068B)
EWD-1E-038 Electrical Wiring Diagram Nuclear Boiler System 21
Automatic Depressurization Safety Relief
Valve MS-RV-3D (B22-F013V)
EWD-1E-038A Electrical Wiring Diagram Nuclear Boiler System 4
Automatic Depressurization Safety Relief
Valve M-RV-3D (B22-F013V)
Drawings Title Revision
Number
H-4649-D Sections - 20 x 10 Type A Head - 3 Stage
H-4650-D Fire Pump - Vertical Turbine Model EBA 2
M515-1 Flow Diagram - Fire Protection System 110
M515-2 Flow Diagram - Fire Protection System Details 18
M515-4 Flow Diagram - Fire Protection System General 2
Services Building and Turbine Generator Building
M515-5 Flow Diagram - Fire Protection System Reactor 6
Building, Diesel Generator Building, and Radwaste
Building
M573-2 Flow Diagram - Potable Water Cold and Fire 8
Protection Systems Pump houses
M585 General Arrangement Plans and Sections Circulating 27
Water Pump House
M827 Heating Ventilation and Air Conditioning - Sections 41
and Details Radwaste and Control Building
M932-1 Fire Main Ring Header 6
Modification Title Revision
Number
16302-1 Disabled HPCS-V-10 and HPCS-V11 in Place 12
Procedures Title Revision
Number
ABN-EDMG Extensive Damage Mitigation Guidelines (EDMG) 020/002
ABN-CR-EVAC Control Room Evacuation and Remote Cooldown 37
ABN-FIRE Fire 40
ABN-RHR-SDC- Residual Heat Removal Alternate Shutdown Cooling 015
ABN-TSG-008 Initiation of Drywell or Wetwell Spray Through the 006
Residual Heat Removal System
Procedures
Title Revision
Number
ABN-TSG-010 Spent Fuel Pool Makeup Through the Residual Heat 006
Removal System Via Fire Water or Condensate
Transfer
OI-18 Equipment Operator Rounds 014/001
PFP-RB-471 Reactor 471 Pre-fire Plans 5
PFP-RW-467 Radwaste (RW) 467 Pre-fire Plans 5
PPM 1.3.10 Plant Fire Protection Program Implementation 034/002
PPM 1.3.10A Control of Ignition Sources 017/001
PPM 1.3.10B Active Fire System Operability and Impairment 015/002
Control
PPM 1.3.10C Control of Transient Combustibles 020/001
PPM 1.3.85 On-Line Fire Risk Management 005/001
PPM 15.1.12 Fire Main Header Flush and Hydrant Inspection 19
PPM 15.1.29 B.5.b Pumper Truck and Monitor Nozzle Operability 10
PPM 15.2.2 Function and Sensitivity Check of Ionization Detectors 18
PPM 15.2.5 Zone 66 Ionization Detector Visual Inspections, 8
Function and Sensitivity Tests
PPM 15.2.25 Manual Pull Stations - CFT 9
PPM 15.2.33 Power Generation Control Complex Halon Initiator 5
Replacement
PPM 15.2.36 Power Generation Control Complex Halon System 10
U679 Through U894 - Sensitivity Check, Actuation
Test and CFT
PPM 15.2.39 Emergency Lighting 8-Hour EBU and Essential 003/003
Fluorescent Lighting
PPM 15.2.40 Emergency Lighting 8-Hour EBU Discharge - Annual 007/002
PPM 15.2.41 Annual Surveillance of 8-Hour Portable Lanterns 005/003
PPM 15.3.2 Hose Station Inspection and Change out 13
Procedures
Title Revision
Number
PPM 15.3.5 Fire Damper Operational Inspection 15
PPM 15.3.6 Control Room Halon Pressure Check, Weight Check, 9
Flow Test, and Power Generation Control Complex
Barrier Inspection
PPM 15.3.9 Fire Pump Drive Inspection/Maintenance of 17
PPM 15.3.10 Fire Pump Drive Inspection/Maintenance of 20
PPM 15.3.17 Fire Door Operability - Semiannual, Annual, Biennial 9
PPM 15.4.2 Fire Main Hydraulic Data Acquisition 13
PPM 15.4.6 Essential Fire Rated Penetration Seal, and Essential 10
Fire and Flood Barrier Operability Inspection
PPM 15.4.8 Fire Protection System Annual Functional Test 21
SWP-FPP-01 Nuclear Fire Protection Program (FPP) 8
Vendor Documents Title Date
Number
CVI 02,02,01, NEDO-10466-A, Power Generation Control Complex February
Sheet 99 Design Criteria and Safety Evaluation 1979
CVI 29,00,36 Johnston Vertical Deep well Pumps - Installation, June 23, 1993
Operation, and Maintenance Manual
Work Orders
2013384-01 02013384-01 02013384-01 02013384-01 02013384-01
2013384-01 02013398-01 02035208-01 02057483-01 02066673-01
2066673-17 02066673-32 02066673-45 02066678-01 02066678-04
2066678-05 02076515-01 02078563-01 02083090-09 02083772-01
2084026-01 02084026-01 02088624-01 02094033-01 02094034-01
2094035-01 02094036-01 02094037-01 02100740-01 02100771-01
2100855-01 02102264-01 02104060-01 02108154-01 02109260-21
2109260-22 02116464-01 02119050-01
SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002
By: JMM Yes No Publicly Available Sensitive
OFFICE RI:EB2 RI:EB2 SRI:EB2 SRI:EB2 BC:DRP/A ABC:DRS/EB2
NAME BCorrell SMakor GPick JMateychick MHaire JDrake
SIGNATURE /RA/ /RA-E/ /RA/ /RA/ /RA/ /RA/
DATE 05/03/18 05/04/18 05/07/18 05/03/18 05/09/18 05/09/18