IR 05000397/2018007
| ML18129A382 | |
| Person / Time | |
|---|---|
| Site: | Columbia |
| Issue date: | 05/09/2018 |
| From: | James Drake NRC/RGN-IV/DRS/EB-2 |
| To: | Sawatzke B Energy Northwest |
| Drake J | |
| References | |
| IR 2018007 | |
| Preceding documents: |
|
| Download: ML18129A382 (14) | |
Text
May 9, 2018
SUBJECT:
COLUMBIA GENERATING STATION - NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION REPORT (NRC INSPECTION REPORT 05000397/2018007)
Dear Mr. Sawatzke:
On April 26, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the Columbia Generating Station and discussed the results of this inspection with Mr. Alex Javorik, Vice President of Engineering, and other members of your staff. The results of this inspection are documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
James F. Drake, Acting Chief Engineering Branch 2 Division of Reactor Safety
Docket: 50-397 License: NPF-21
Enclosure:
Inspection Report 05000397/2018007
Enclosure U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Number:
05000397
License Number:
Report Number:
Enterprise Identifier: I-2018-007-0002
Licensee:
Energy Northwest
Facility:
Columbia Generating Station
Location:
Richland, Washington
Inspection Dates:
April 9, 2018, to April 26, 2018
Inspectors:
J. Mateychick, Senior Reactor Inspector (Team Lead)
B. Correll, Reactor Inspector
S. Makor, Reactor Inspector
G. Pick, Senior Reactor Inspector
Approved By:
J. Drake, Chief
Engineering Branch 2
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees performance by conducting a Triennial Fire Protection Baseline Inspection at Columbia Generating Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC and self-revealed findings, violations, and additional items are summarized in the table below.
List of Findings and Violations
The NRC inspectors did not identify any finding or violation of more than minor significance.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.05T - Fire Protection (Triennial)
The inspectors evaluated the design, operational status, and material condition of the licensees fire protection program, including assumptions made in plant and area specific fire protection analyses, by verifying that the licensees program includes:
- (1) Adequate controls for combustibles and ignition sources inside the plant;
- (2) Adequate fire detection and suppression capability;
- (3) Passive fire protection features in good material condition;
- (4) Adequate compensatory measures for out-of-service, degraded or inoperable fire protection equipment, systems, or features;
- (5) Adequate protection to ensure the post-fire capability to safely shutdown the plant, including implementation of NRC/industry fire-induced circuit failure analysis guidance;
- (6) Feasible and reliable manual actions when appropriate to achieve safe shutdown; and
- (7) Adequate review and documentation of fire protection program changes.
Fire Protection Inspection Requirements (Four Samples)
The inspectors evaluated fire protection program implementation in the following selected areas:
Fire Area
Description R-1D Reactor Building Northwest 471 Elevation RC-3 Cable Chase RC-4 Division 1 Electrical Equipment Room RC-14 Division 1 Switchgear Room
The inspectors reviewed and evaluated the following fire protection inspection requirements:
- (1) Fire brigade drill performance
- (2) Protection of safe shutdown capabilities
- (3) Passive fire protection
- (4) Active fire protection
- (5) Protection from damage from fire suppression activities
- (6) Alternative shutdown capability
- (7) Circuit analysis
- (8) Communications
- (9) Emergency lighting (Fixed and Portable 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> units)
- (10) Cold shutdown repairs
- (11) Compensatory measures
a. Compensatory measures for degraded fire protection components
b. Compensatory measures for components necessary to achieve safe and stable conditions
- (12) Review and documentation of fire protection plan changes
- (13) Control of transient combustibles and ignition sources
- (14) Sample of fire protection corrective action documents
B.5.b Inspection Activities (One Sample)
The inspectors evaluated feasibility of the B.5.b mitigating strategies by determining the following:
- Procedures are being maintained and adequate
- Equipment is properly staged and is being maintained and tested
- Station personnel are knowledgeable and can implement the procedures
The inspectors evaluated feasibility of the following B.5.b Mitigating Strategies:
ABN-TSG-008
Initiation of Drywell or Wetwell Spray Through the Residual Heat Removal System ABN-TSG-010 Spent Fuel Pool Makeup Through the Residual Heat Removal System Via Fire Water or Condensate Transfer
INSPECTION RESULTS
The NRC inspectors did not identify any finding or violation of more than minor significance.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On April 26, 2018, the inspectors presented the fire protection inspection results to Mr. A. Javorik, Vice President of Engineering, and other members of the licensee staff.
DOCUMENTS REVIEWED
Cable Routing Data Components
Residual Heat Removal System, Standby Service Water System
(RHR-P-2B, RHR-V-6B, RHR-FCV-64B, RHR-V-4B, SW-P-1B, RHR-V-3B, SW-V-12B)
Calculations
Number
Title
Revision or
Date
FP-02-07-02
Hydraulic Analysis of Fire Water Supply System
FPF 2.11
Emergency Lighting Monthly Inspections and
Appendix R Lamp Positioning
ME-02-02-23
Post-Fire Safe Shutdown Flooding Analysis -
Radwaste Building
MSE-EJJ-10-01
Expert Panel Identification and Review of Multiple
Spurious Operation Scenarios
April 23, 2010
NE-02-85-19
Post-Fire Safe Shutdown Analysis
NE-02-94-35
System Impact on Post-Fire Safe Shutdown
TM-2160
B.5.b Implementation
Action Requests (AR-)
378859*
379297*
379315*
378806*
378968*
379317*
379319*
378940*
378989
379316*
379320*
335821
374802
377838
378937*
340250
377836
378917*
379403*
379349*
378917*
- Issued as a result of inspection activities.
Drawings
Number
Title
Revision
2-217A-28
Cable Chase - Zone 2 System 66 (Preaction)
2-217A-29
Cable Chase - Zone 2 System 66 (Preaction)
2-217A-30
Cable Chase - Zone 2 System 66 (Preaction)
2-217A-31
Cable Chase - Zone 2 System 66 (Preaction)
A529
Reactor Building Stair No. A5
A530
Reactor Building Stair No. A6
Drawings
Number
Title
Revision
C 896
FP-TK-110 Water Storage Tank Plan Sections and
Details
D00292, Sheet 36
Fire Detection and Alarm System Installation Diagram
- Radioactive Waste and Control Building El 467
FM892-8
Sprinkler and Hose Station Plans EL 467-0
and 471-0 and Miscellaneous Floors
Access-Egress for Post-Fire Safe Shutdown Activities
Access-Egress for Post-Fire Safe Shutdown Activities
Access-Egress for Post-Fire Safe Shutdown Activities
M521-1
Flow Diagram Residual Heat Removal Loop A
115
M521-2
Flow Diagram Residual Heat Removal Loop B
115
EWD-88-E-007
Electrical Wiring Diagram Diesel Generator (DG)
Building H&V System DG2 Room Normal Supply
Fan DMA-FN-22
EWD-88E-020A
Electrical Wiring Diagram Diesel Generator
Building H&V System DG2 Room Normal Air
Dampers DMA-AD-22/1 and DMA-AD-22/2
EWD-88E-029A
Electrical Wiring Diagram Diesel Generator
Building H&V System DG2 Room Air Handling
Unit DMA-AH-22 Outlet Heater DMA-EHC-22
EWD-88E-034
Electrical Wiring Diagram Diesel Generator Building
H&V System Annunciator DMA-ANN-PNL/DGHV2
EWD-9E-019
Electrical Wiring Diagram Residual Heat Removal
System Motor Operated Valve (MOV)
RHR-V-4B (E12-F004B)
PFSS-2
Appendix R Post-Fire Safe Shutdown (PFSS)
Division 2 Boundaries of Line Diagram
EWD-9E-097
Electrical Wiring Diagram Residual Heat Removal
System Miscellaneous Relay Circuits (Division 2)
Drawings
Number
Title
Revision
E948-1A
Appendix R Post-Fire Safe Shutdown Protected
Raceways Whittaker Cable Support Diagram
E948-2A
Appendix R Post-Fire Safe Shutdown Protected
Raceways Reactor Building Elevations 501-0 and
2-0
E948-3
Appendix R Post-Fire Safe Shutdown Protected
Raceways Radwaste Building - Elevations 467-0 and
25-0
EWD-9E-004
Electrical Wiring Diagram Residual Heat Removal
System Pump RHR-P-2B Breaker RHR-CB-P2B
EWD-9E-099
Electrical Wiring Diagram Residual Heat Removal
System Miscellaneous Relay Circuits (Division 2)
EWD-9E-100
Electrical Wiring Diagram Residual Heat Removal
System Miscellaneous Relay Circuits (Division 2)
E502-2
Main One Line Diagram
EWD-9E-003
Electrical Wiring Diagram Residual Heat Removal
System Pump RHR-P-2B (E12-C002B)
EWD-7E-020
Electrical Wiring Diagram High Pressure Core Spray
System MOV HPCS-V-15 (E22-F015)
EWD-7E-023
Electrical Wiring Diagram High Pressure Core Spray
System Pump HPCS-P-1 (E-22-C001)
EWD-7E-022
Electrical Wiring Diagram High Pressure Core
Spray System Pump HPCS-P-1 (E22-C001)
Breaker HPCS-CB-P1
EWD-7E-003
Electrical Wiring Diagram High Pressure Core
Spray System Standby Water Leg Pump HPCS-P-3
(E22-C003)
EWD-7E-018
Electrical Wiring Diagram High Pressure Core Spray
System MOV HPCS-V-11 (E22-F011)
M520
Flow Diagram High Pressure Core Spray (HPCS)
System and Low Pressure Core Spray Systems
Reactor Building
104
Drawings
Number
Title
Revision
EWD-7E-017
Electrical Wiring Diagram High Pressure Core Spray
System MOV HPCS-V-10 (E22-F0101)
EWD-58E-022
Electrical Wiring Diagram Standby Service Water
System MOV SW-V-12B
EWD-58E-021
Electrical Wiring Diagram Standby Service Water
System, MOV-SW-V-12B
EWD-58E-004
Electrical Wiring Diagram Standby Service Water
System SW-P-1B Breaker SW-CB-P1B
EWD-58E-004B
Electrical Wiring Diagram Standby Service Water
System SW-P-1B Breaker SW-CB-P1B
M524-2
Flow Diagram Standby Service Water System
Reactor, Radwaste, DG Buildings and Yard
20
EWD-9E-022
Electrical Wiring Diagram Residual Heat Removal
System MOV RHR-V-6B (E12-F006B)
EWD-58E-014
Electrical Wiring Diagram Standby Service Water
System MOV SW-V-2B
EWD-58E-015
Electrical Wiring Diagram Standby Service Water
System MOV SW-V-2B
E542-22D
Connection Wiring Diagram Supervisory
Panel E-CP-C2 (Division 2) Rear Sub-Panel Lower
Half
E542-22E
Connection Wiring Diagram, Supervisory
Panel E-CP-CS2 (Division 2) Right Sub-Panel
EWD-58E-004
Electrical Wiring Diagram Standby Service Water
System W-P-1B Breaker SW-CB-P1B
EWD-58E-004B
Electrical Wiring Diagram Standby Service Water
System SW-P-1B Breaker SW-CB-P1B
PFSS-2
Appendix R Post-Fire Safe Shutdown (PFSS)
Division 2 Boundaries One Line Diagram
EWD-9E-006
Electrical Wiring Diagram Residual Heat Removal
Drawings
Number
Title
Revision
System Pump RHR-P-2C Breaker RHR-CB-P2C
EWD-6E-008
Electrical Wiring Diagram Reactor Core Isolation
Cooling System MOV RCIC-V-45 (E51-F045)
EWD-6E-008A
Electrical Wiring Diagram Reactor Core Isolation
Cooling System MOV RCIC-V-45 (E51-F045)
6E013
Reactor Core Isolation Cooling System Miscellaneous
Relay Circuits Sheet 4
EWD-9E-057
Electrical Wiring Diagram Residual Heat Removal
System MOV RHR-FCV-64B (E12-F064B)
EWD-9E-123
Electrical Wiring Diagram Residual Heat Removal
System Annunciator
EWD-9E-004A
Electrical Wiring Diagram Residual Heat Removal
System Pump RHR-P-2B Breaker RHR-CB-P2B
EWD-9E-004
Electrical Wiring Diagram Residual Heat Removal
System Pump RHR-P-2B Breaker RHR-CB-P2B
EWD-41-003
Electrical Wiring Diagram Reactor Water Cleanup
System RWCU-FT-37, RWCU-PT-5, and
RWCU-TS-20
EWD-46E-252C
Electrical Wiring Diagram AC Electrical Distribution
System Power Panel E-PP-8AF Circuit Details
EWD-9E-019
Electrical Wiring Diagram Residual Heat Removal
System MOV-RHR-V-4B (E12-F004B)
EWD-58E-047
Electrical Wiring Diagram Standby Service Water
System MOV RHR-V-68B (E12-F068B)
EWD-1E-038
Electrical Wiring Diagram Nuclear Boiler System
Automatic Depressurization Safety Relief
Valve MS-RV-3D (B22-F013V)
EWD-1E-038A
Electrical Wiring Diagram Nuclear Boiler System
Automatic Depressurization Safety Relief
Valve M-RV-3D (B22-F013V)
Drawings
Number
Title
Revision
H-4649-D
Sections - 20 x 10 Type A Head - 3 Stage
H-4650-D
Fire Pump - Vertical Turbine Model EBA
M515-1
Flow Diagram - Fire Protection System
110
M515-2
Flow Diagram - Fire Protection System Details
M515-4
Flow Diagram - Fire Protection System General
Services Building and Turbine Generator Building
M515-5
Flow Diagram - Fire Protection System Reactor
Building, Diesel Generator Building, and Radwaste
Building
M573-2
Flow Diagram - Potable Water Cold and Fire
Protection Systems Pump houses
M585
General Arrangement Plans and Sections Circulating
Water Pump House
M827
Heating Ventilation and Air Conditioning - Sections
and Details Radwaste and Control Building
M932-1
Fire Main Ring Header
Modification
Number
Title
Revision
16302-1
Disabled HPCS-V-10 and HPCS-V11 in Place
Procedures
Number
Title
Revision
ABN-EDMG
Extensive Damage Mitigation Guidelines (EDMG)
20/002
ABN-CR-EVAC
Control Room Evacuation and Remote Cooldown
ABN-FIRE
Fire
ABN-RHR-SDC-
Residual Heat Removal Alternate Shutdown Cooling
015
ABN-TSG-008
Initiation of Drywell or Wetwell Spray Through the
Residual Heat Removal System
006
Procedures
Number
Title
Revision
ABN-TSG-010
Spent Fuel Pool Makeup Through the Residual Heat
Removal System Via Fire Water or Condensate
Transfer
006
OI-18
Equipment Operator Rounds
014/001
Reactor 471 Pre-fire Plans
Radwaste (RW) 467 Pre-fire Plans
PPM 1.3.10
Plant Fire Protection Program Implementation
034/002
PPM 1.3.10A
Control of Ignition Sources
017/001
PPM 1.3.10B
Active Fire System Operability and Impairment
Control
015/002
PPM 1.3.10C
Control of Transient Combustibles
20/001
PPM 1.3.85
On-Line Fire Risk Management
005/001
PPM 15.1.12
Fire Main Header Flush and Hydrant Inspection
PPM 15.1.29
B.5.b Pumper Truck and Monitor Nozzle Operability
PPM 15.2.2
Function and Sensitivity Check of Ionization Detectors 18
PPM 15.2.5
Zone 66 Ionization Detector Visual Inspections,
Function and Sensitivity Tests
PPM 15.2.25
Manual Pull Stations - CFT
PPM 15.2.33
Power Generation Control Complex Halon Initiator
Replacement
PPM 15.2.36
Power Generation Control Complex Halon System
U679 Through U894 - Sensitivity Check, Actuation
Test and CFT
PPM 15.2.39
Emergency Lighting 8-Hour EBU and Essential
Fluorescent Lighting
003/003
PPM 15.2.40
Emergency Lighting 8-Hour EBU Discharge - Annual
007/002
PPM 15.2.41
Annual Surveillance of 8-Hour Portable Lanterns
005/003
PPM 15.3.2
Hose Station Inspection and Change out
Procedures
Number
Title
Revision
PPM 15.3.5
Fire Damper Operational Inspection
PPM 15.3.6
Control Room Halon Pressure Check, Weight Check,
Flow Test, and Power Generation Control Complex
Barrier Inspection
PPM 15.3.9
Fire Pump Drive Inspection/Maintenance of
PPM 15.3.10
Fire Pump Drive Inspection/Maintenance of
PPM 15.3.17
Fire Door Operability - Semiannual, Annual, Biennial
PPM 15.4.2
Fire Main Hydraulic Data Acquisition
PPM 15.4.6
Essential Fire Rated Penetration Seal, and Essential
Fire and Flood Barrier Operability Inspection
PPM 15.4.8
Fire Protection System Annual Functional Test
SWP-FPP-01
Nuclear Fire Protection Program (FPP)
Vendor Documents
Number
Title
Date
CVI 02,02,01,
Sheet 99
NEDO-10466-A, Power Generation Control Complex
Design Criteria and Safety Evaluation
February
1979
CVI 29,00,36
Johnston Vertical Deep well Pumps - Installation,
Operation, and Maintenance Manual
June 23, 1993
Work Orders
2013384-01
2013384-01
2013384-01
2013384-01
2013384-01
2013384-01
2013398-01
2035208-01
2057483-01
2066673-01
2066673-17
2066673-32
2066673-45
2066678-01
2066678-04
2066678-05
2076515-01
2078563-01
2083090-09
2083772-01
2084026-01
2084026-01
2088624-01
2094033-01
2094034-01
2094035-01
2094036-01
2094037-01
2100740-01
2100771-01
2100855-01
2102264-01
2104060-01
2108154-01
2109260-21
2109260-22
2116464-01
2119050-01
SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002
By: JMM Yes No
Publicly Available Sensitive
OFFICE
RI:EB2
RI:EB2
SRI:EB2
SRI:EB2
BC:DRP/A
ABC:DRS/EB2
NAME
BCorrell
SMakor
GPick
JMateychick
MHaire
JDrake
SIGNATURE
/RA/
/RA-E/
/RA/
/RA/
/RA/
/RA/
DATE
05/03/18
05/04/18
05/07/18
05/03/18
05/09/18
05/09/18
May 9, 2018
Mr. Brad Sawatzke
Chief Executive Officer
Energy Northwest
MD 1023, P.O. Box 968
Richland, WA 99352
SUBJECT:
COLUMBIA GENERATING STATION - NRC TRIENNIAL FIRE
PROTECTION BASELINE INSPECTION REPORT (NRC INSPECTION
REPORT 05000397/2018007)
Dear Mr. Sawatzke:
On April 26, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at
the Columbia Generating Station and discussed the results of this inspection with Mr. Alex
Javorik, Vice President of Engineering, and other members of your staff. The results of this
inspection are documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for
Withholding.
Sincerely,
/RA/
James
- F. Drake, Acting Chief
Engineering Branch 2
Division of Reactor Safety
Docket: 50-397
License: NPF-21
Enclosure:
Inspection Report 05000397/2018007
U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Number:
05000397
License Number:
Report Number:
Enterprise Identifier: I-2018-007-0002
Licensee:
Energy Northwest
Facility:
Columbia Generating Station
Location:
Richland, Washington
Inspection Dates:
April 9, 2018, to April 26, 2018
Inspectors:
- J. Mateychick, Senior Reactor Inspector (Team Lead)
- B. Correll, Reactor Inspector
- S. Makor, Reactor Inspector
- G. Pick, Senior Reactor Inspector
Approved By:
- J. Drake, Chief
Engineering Branch 2
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees
performance by conducting a Triennial Fire Protection Baseline Inspection at Columbia
Generating Station in accordance with the Reactor Oversight Process. The Reactor
Oversight Process is the NRCs program for overseeing the safe operation of commercial
nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for
more information. NRC and self-revealed findings, violations, and additional items are
summarized in the table below.
List of Findings and Violations
The NRC inspectors did not identify any finding or violation of more than minor significance.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs)
in effect at the beginning of the inspection unless otherwise noted. Currently approved
IPs with their attached revision histories are located on the public website at
http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection
activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor
Inspection Program - Operations Phase. The inspectors reviewed selected procedures and
records, observed activities, and interviewed personnel to assess licensee performance and
compliance with Commission rules and regulations, license conditions, site procedures, and
standards.
REACTOR SAFETY
71111.05T - Fire Protection (Triennial)
The inspectors evaluated the design, operational status, and material condition of the
licensees fire protection program, including assumptions made in plant and area specific
fire protection analyses, by verifying that the licensees program includes:
(1) Adequate controls for combustibles and ignition sources inside the plant;
(2) Adequate fire detection and suppression capability;
(3) Passive fire protection features in good material condition;
(4) Adequate compensatory measures for out-of-service, degraded or inoperable fire
protection equipment, systems, or features;
(5) Adequate protection to ensure the post-fire capability to safely shutdown the plant,
including implementation of NRC/industry fire-induced circuit failure analysis guidance;
(6) Feasible and reliable manual actions when appropriate to achieve safe shutdown; and
(7) Adequate review and documentation of fire protection program changes.
Fire Protection Inspection Requirements (Four Samples)
The inspectors evaluated fire protection program implementation in the following selected
areas:
Fire Area
Description
R-1D
Reactor Building Northwest 471 Elevation
RC-3
Cable Chase
RC-4
Division 1 Electrical Equipment Room
RC-14
Division 1 Switchgear Room
The inspectors reviewed and evaluated the following fire protection inspection requirements:
(1) Fire brigade drill performance
(2) Protection of safe shutdown capabilities
(3) Passive fire protection
(4) Active fire protection
(5) Protection from damage from fire suppression activities
(6) Alternative shutdown capability
(7) Circuit analysis
(8) Communications
(9) Emergency lighting (Fixed and Portable 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> units)
(10) Cold shutdown repairs
(11) Compensatory measures
a. Compensatory measures for degraded fire protection components
b. Compensatory measures for components necessary to achieve safe and stable
conditions
(12) Review and documentation of fire protection plan changes
(13) Control of transient combustibles and ignition sources
(14) Sample of fire protection corrective action documents
B.5.b Inspection Activities (One Sample)
The inspectors evaluated feasibility of the B.5.b mitigating strategies by determining the
following:
Procedures are being maintained and adequate
Equipment is properly staged and is being maintained and tested
Station personnel are knowledgeable and can implement the procedures
The inspectors evaluated feasibility of the following B.5.b Mitigating Strategies:
ABN-TSG-008
Initiation of Drywell or Wetwell Spray Through the Residual Heat
Removal System
ABN-TSG-010
Spent Fuel Pool Makeup Through the Residual Heat Removal System
Via Fire Water or Condensate Transfer
INSPECTION RESULTS
The NRC inspectors did not identify any finding or violation of more than minor significance.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On April 26, 2018, the inspectors presented the fire protection inspection results to
Mr.
- A. Javorik, Vice President of Engineering, and other members of the licensee staff.
DOCUMENTS REVIEWED
Cable Routing Data Components
Residual Heat Removal System, Standby Service Water System
(RHR-P-2B, RHR-V-6B, RHR-FCV-64B, RHR-V-4B, SW-P-1B, RHR-V-3B, SW-V-12B)
Calculations
Number
Title
Revision or
Date
FP-02-07-02
Hydraulic Analysis of Fire Water Supply System
FPF 2.11
Emergency Lighting Monthly Inspections and
Appendix R Lamp Positioning
ME-02-02-23
Post-Fire Safe Shutdown Flooding Analysis -
Radwaste Building
MSE-EJJ-10-01
Expert Panel Identification and Review of Multiple
Spurious Operation Scenarios
April 23, 2010
NE-02-85-19
Post-Fire Safe Shutdown Analysis
NE-02-94-35
System Impact on Post-Fire Safe Shutdown
TM-2160
B.5.b Implementation
Action Requests (AR-)
378859*
379297*
379315*
378806*
378968*
379317*
379319*
378940*
378989
379316*
379320*
335821
374802
377838
378937*
340250
377836
378917*
379403*
379349*
378917*
- Issued as a result of inspection activities.
Drawings
Number
Title
Revision
2-217A-28
Cable Chase - Zone 2 System 66 (Preaction)
2-217A-29
Cable Chase - Zone 2 System 66 (Preaction)
2-217A-30
Cable Chase - Zone 2 System 66 (Preaction)
2-217A-31
Cable Chase - Zone 2 System 66 (Preaction)
A529
Reactor Building Stair No. A5
A530
Reactor Building Stair No. A6
Drawings
Number
Title
Revision
C 896
FP-TK-110 Water Storage Tank Plan Sections and
Details
D00292, Sheet 36
Fire Detection and Alarm System Installation Diagram
- Radioactive Waste and Control Building El 467
FM892-8
Sprinkler and Hose Station Plans EL 467-0
and 471-0 and Miscellaneous Floors
Access-Egress for Post-Fire Safe Shutdown Activities
Access-Egress for Post-Fire Safe Shutdown Activities
Access-Egress for Post-Fire Safe Shutdown Activities
M521-1
Flow Diagram Residual Heat Removal Loop A
115
M521-2
Flow Diagram Residual Heat Removal Loop B
115
EWD-88-E-007
Electrical Wiring Diagram Diesel Generator (DG)
Building H&V System DG2 Room Normal Supply
Fan DMA-FN-22
EWD-88E-020A
Electrical Wiring Diagram Diesel Generator
Building H&V System DG2 Room Normal Air
Dampers DMA-AD-22/1 and DMA-AD-22/2
EWD-88E-029A
Electrical Wiring Diagram Diesel Generator
Building H&V System DG2 Room Air Handling
Unit DMA-AH-22 Outlet Heater DMA-EHC-22
EWD-88E-034
Electrical Wiring Diagram Diesel Generator Building
H&V System Annunciator DMA-ANN-PNL/DGHV2
EWD-9E-019
Electrical Wiring Diagram Residual Heat Removal
System Motor Operated Valve (MOV)
RHR-V-4B (E12-F004B)
PFSS-2
Appendix R Post-Fire Safe Shutdown (PFSS)
Division 2 Boundaries of Line Diagram
EWD-9E-097
Electrical Wiring Diagram Residual Heat Removal
System Miscellaneous Relay Circuits (Division 2)
Drawings
Number
Title
Revision
E948-1A
Appendix R Post-Fire Safe Shutdown Protected
Raceways Whittaker Cable Support Diagram
E948-2A
Appendix R Post-Fire Safe Shutdown Protected
Raceways Reactor Building Elevations 501-0 and
2-0
E948-3
Appendix R Post-Fire Safe Shutdown Protected
Raceways Radwaste Building - Elevations 467-0 and
25-0
EWD-9E-004
Electrical Wiring Diagram Residual Heat Removal
System Pump RHR-P-2B Breaker RHR-CB-P2B
EWD-9E-099
Electrical Wiring Diagram Residual Heat Removal
System Miscellaneous Relay Circuits (Division 2)
EWD-9E-100
Electrical Wiring Diagram Residual Heat Removal
System Miscellaneous Relay Circuits (Division 2)
E502-2
Main One Line Diagram
EWD-9E-003
Electrical Wiring Diagram Residual Heat Removal
System Pump RHR-P-2B (E12-C002B)
EWD-7E-020
Electrical Wiring Diagram High Pressure Core Spray
System MOV HPCS-V-15 (E22-F015)
EWD-7E-023
Electrical Wiring Diagram High Pressure Core Spray
System Pump HPCS-P-1 (E-22-C001)
EWD-7E-022
Electrical Wiring Diagram High Pressure Core
Spray System Pump HPCS-P-1 (E22-C001)
Breaker HPCS-CB-P1
EWD-7E-003
Electrical Wiring Diagram High Pressure Core
Spray System Standby Water Leg Pump HPCS-P-3
(E22-C003)
EWD-7E-018
Electrical Wiring Diagram High Pressure Core Spray
System MOV HPCS-V-11 (E22-F011)
M520
Flow Diagram High Pressure Core Spray (HPCS)
System and Low Pressure Core Spray Systems
Reactor Building
104
Drawings
Number
Title
Revision
EWD-7E-017
Electrical Wiring Diagram High Pressure Core Spray
System MOV HPCS-V-10 (E22-F0101)
EWD-58E-022
Electrical Wiring Diagram Standby Service Water
System MOV SW-V-12B
EWD-58E-021
Electrical Wiring Diagram Standby Service Water
System, MOV-SW-V-12B
EWD-58E-004
Electrical Wiring Diagram Standby Service Water
System SW-P-1B Breaker SW-CB-P1B
EWD-58E-004B
Electrical Wiring Diagram Standby Service Water
System SW-P-1B Breaker SW-CB-P1B
M524-2
Flow Diagram Standby Service Water System
Reactor, Radwaste, DG Buildings and Yard
20
EWD-9E-022
Electrical Wiring Diagram Residual Heat Removal
System MOV RHR-V-6B (E12-F006B)
EWD-58E-014
Electrical Wiring Diagram Standby Service Water
System MOV SW-V-2B
EWD-58E-015
Electrical Wiring Diagram Standby Service Water
System MOV SW-V-2B
E542-22D
Connection Wiring Diagram Supervisory
Panel E-CP-C2 (Division 2) Rear Sub-Panel Lower
Half
E542-22E
Connection Wiring Diagram, Supervisory
Panel E-CP-CS2 (Division 2) Right Sub-Panel
EWD-58E-004
Electrical Wiring Diagram Standby Service Water
System W-P-1B Breaker SW-CB-P1B
EWD-58E-004B
Electrical Wiring Diagram Standby Service Water
System SW-P-1B Breaker SW-CB-P1B
PFSS-2
Appendix R Post-Fire Safe Shutdown (PFSS)
Division 2 Boundaries One Line Diagram
EWD-9E-006
Electrical Wiring Diagram Residual Heat Removal
Drawings
Number
Title
Revision
System Pump RHR-P-2C Breaker RHR-CB-P2C
EWD-6E-008
Electrical Wiring Diagram Reactor Core Isolation
Cooling System MOV RCIC-V-45 (E51-F045)
EWD-6E-008A
Electrical Wiring Diagram Reactor Core Isolation
Cooling System MOV RCIC-V-45 (E51-F045)
6E013
Reactor Core Isolation Cooling System Miscellaneous
Relay Circuits Sheet 4
EWD-9E-057
Electrical Wiring Diagram Residual Heat Removal
System MOV RHR-FCV-64B (E12-F064B)
EWD-9E-123
Electrical Wiring Diagram Residual Heat Removal
System Annunciator
EWD-9E-004A
Electrical Wiring Diagram Residual Heat Removal
System Pump RHR-P-2B Breaker RHR-CB-P2B
EWD-9E-004
Electrical Wiring Diagram Residual Heat Removal
System Pump RHR-P-2B Breaker RHR-CB-P2B
EWD-41-003
Electrical Wiring Diagram Reactor Water Cleanup
System RWCU-FT-37, RWCU-PT-5, and
RWCU-TS-20
EWD-46E-252C
Electrical Wiring Diagram AC Electrical Distribution
System Power Panel E-PP-8AF Circuit Details
EWD-9E-019
Electrical Wiring Diagram Residual Heat Removal
System MOV-RHR-V-4B (E12-F004B)
EWD-58E-047
Electrical Wiring Diagram Standby Service Water
System MOV RHR-V-68B (E12-F068B)
EWD-1E-038
Electrical Wiring Diagram Nuclear Boiler System
Automatic Depressurization Safety Relief
Valve MS-RV-3D (B22-F013V)
EWD-1E-038A
Electrical Wiring Diagram Nuclear Boiler System
Automatic Depressurization Safety Relief
Valve M-RV-3D (B22-F013V)
Drawings
Number
Title
Revision
H-4649-D
Sections - 20 x 10 Type A Head - 3 Stage
H-4650-D
Fire Pump - Vertical Turbine Model EBA
M515-1
Flow Diagram - Fire Protection System
110
M515-2
Flow Diagram - Fire Protection System Details
M515-4
Flow Diagram - Fire Protection System General
Services Building and Turbine Generator Building
M515-5
Flow Diagram - Fire Protection System Reactor
Building, Diesel Generator Building, and Radwaste
Building
M573-2
Flow Diagram - Potable Water Cold and Fire
Protection Systems Pump houses
M585
General Arrangement Plans and Sections Circulating
Water Pump House
M827
Heating Ventilation and Air Conditioning - Sections
and Details Radwaste and Control Building
M932-1
Fire Main Ring Header
Modification
Number
Title
Revision
16302-1
Disabled HPCS-V-10 and HPCS-V11 in Place
Procedures
Number
Title
Revision
ABN-EDMG
Extensive Damage Mitigation Guidelines (EDMG)
20/002
ABN-CR-EVAC
Control Room Evacuation and Remote Cooldown
ABN-FIRE
Fire
ABN-RHR-SDC-
Residual Heat Removal Alternate Shutdown Cooling
015
ABN-TSG-008
Initiation of Drywell or Wetwell Spray Through the
Residual Heat Removal System
006
Procedures
Number
Title
Revision
ABN-TSG-010
Spent Fuel Pool Makeup Through the Residual Heat
Removal System Via Fire Water or Condensate
Transfer
006
OI-18
Equipment Operator Rounds
014/001
Reactor 471 Pre-fire Plans
Radwaste (RW) 467 Pre-fire Plans
PPM 1.3.10
Plant Fire Protection Program Implementation
034/002
PPM 1.3.10A
Control of Ignition Sources
017/001
PPM 1.3.10B
Active Fire System Operability and Impairment
Control
015/002
PPM 1.3.10C
Control of Transient Combustibles
20/001
PPM 1.3.85
On-Line Fire Risk Management
005/001
PPM 15.1.12
Fire Main Header Flush and Hydrant Inspection
PPM 15.1.29
B.5.b Pumper Truck and Monitor Nozzle Operability
PPM 15.2.2
Function and Sensitivity Check of Ionization Detectors 18
PPM 15.2.5
Zone 66 Ionization Detector Visual Inspections,
Function and Sensitivity Tests
PPM 15.2.25
Manual Pull Stations - CFT
PPM 15.2.33
Power Generation Control Complex Halon Initiator
Replacement
PPM 15.2.36
Power Generation Control Complex Halon System
U679 Through U894 - Sensitivity Check, Actuation
Test and CFT
PPM 15.2.39
Emergency Lighting 8-Hour EBU and Essential
Fluorescent Lighting
003/003
PPM 15.2.40
Emergency Lighting 8-Hour EBU Discharge - Annual
007/002
PPM 15.2.41
Annual Surveillance of 8-Hour Portable Lanterns
005/003
PPM 15.3.2
Hose Station Inspection and Change out
Procedures
Number
Title
Revision
PPM 15.3.5
Fire Damper Operational Inspection
PPM 15.3.6
Control Room Halon Pressure Check, Weight Check,
Flow Test, and Power Generation Control Complex
Barrier Inspection
PPM 15.3.9
Fire Pump Drive Inspection/Maintenance of
PPM 15.3.10
Fire Pump Drive Inspection/Maintenance of
PPM 15.3.17
Fire Door Operability - Semiannual, Annual, Biennial
PPM 15.4.2
Fire Main Hydraulic Data Acquisition
PPM 15.4.6
Essential Fire Rated Penetration Seal, and Essential
Fire and Flood Barrier Operability Inspection
PPM 15.4.8
Fire Protection System Annual Functional Test
SWP-FPP-01
Nuclear Fire Protection Program (FPP)
Vendor Documents
Number
Title
Date
CVI 02,02,01,
Sheet 99
NEDO-10466-A, Power Generation Control Complex
Design Criteria and Safety Evaluation
February
1979
CVI 29,00,36
Johnston Vertical Deep well Pumps - Installation,
Operation, and Maintenance Manual
June 23, 1993
Work Orders
2013384-01
2013384-01
2013384-01
2013384-01
2013384-01
2013384-01
2013398-01
2035208-01
2057483-01
2066673-01
2066673-17
2066673-32
2066673-45
2066678-01
2066678-04
2066678-05
2076515-01
2078563-01
2083090-09
2083772-01
2084026-01
2084026-01
2088624-01
2094033-01
2094034-01
2094035-01
2094036-01
2094037-01
2100740-01
2100771-01
2100855-01
2102264-01
2104060-01
2108154-01
2109260-21
2109260-22
2116464-01
2119050-01
SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002
By: JMM Yes No
Publicly Available Sensitive
OFFICE
RI:EB2
RI:EB2
SRI:EB2
SRI:EB2
BC:DRP/A
ABC:DRS/EB2
NAME
BCorrell
SMakor
GPick
JMateychick
MHaire
JDrake
SIGNATURE
/RA/
/RA-E/
/RA/
/RA/
/RA/
/RA/
DATE
05/03/18
05/04/18
05/07/18
05/03/18
05/09/18
05/09/18