IR 05000440/2006009: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 3: Line 3:
| issue date = 05/05/2006
| issue date = 05/05/2006
| title = IR 05000440-06-009(DRS); 01/17/2006 - 03/23/2006; Perry Nuclear Power Plant; Component Design Bases Inspection
| title = IR 05000440-06-009(DRS); 01/17/2006 - 03/23/2006; Perry Nuclear Power Plant; Component Design Bases Inspection
| author name = Stone A M
| author name = Stone A
| author affiliation = NRC/RGN-III/DRS/EB2
| author affiliation = NRC/RGN-III/DRS/EB2
| addressee name = Pearce L W
| addressee name = Pearce L
| addressee affiliation = FirstEnergy Nuclear Operating Co
| addressee affiliation = FirstEnergy Nuclear Operating Co
| docket = 05000440
| docket = 05000440
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:May 4, 2006Mr. L. William PearceVice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant 10 Center Road, A290 Perry, OH 44081SUBJECT:PERRY NUCLEAR POWER PLANT NRC COMPONENT DESIGN BASES INSPECTION (CDBI) INSPECTION REPORT 05000440/2006009(DRS)
[[Issue date::May 4, 2006]]
 
Mr. L. William PearceVice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant 10 Center Road, A290 Perry, OH 44081
 
SUBJECT: PERRY NUCLEAR POWER PLANT NRC COMPONENT DESIGN BASES INSPECTION (CDBI) INSPECTION REPORT 05000440/2006009(DRS)


==Dear Mr. Pearce:==
==Dear Mr. Pearce:==
Line 30: Line 25:
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. Specifically, this inspection focused on the design of components that are risk significant and have low design margin.Based on the results of this inspection, three NRC-identified findings of very low safetysignificance, which involved violations of NRC requirements were identified. However, becausethese violations were of very low safety significance and because they were entered into your corrective action program, the NRC is treating the issues as Non-Cited Violations in accordancewith Section VI.A.1 of the NRC's Enforcement Policy. Additionally, a licensee identifiedviolation is listed in Section 4OA7 of this report.If you contest the subject or severity of a Non-Cited Violation, you should provide a responsewithin 30 days of the date of this inspection report, with the basis for your denial, to the U.S.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. Specifically, this inspection focused on the design of components that are risk significant and have low design margin.Based on the results of this inspection, three NRC-identified findings of very low safetysignificance, which involved violations of NRC requirements were identified. However, becausethese violations were of very low safety significance and because they were entered into your corrective action program, the NRC is treating the issues as Non-Cited Violations in accordancewith Section VI.A.1 of the NRC's Enforcement Policy. Additionally, a licensee identifiedviolation is listed in Section 4OA7 of this report.If you contest the subject or severity of a Non-Cited Violation, you should provide a responsewithin 30 days of the date of this inspection report, with the basis for your denial, to the U.S.


Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-
Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission -
0001, with a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission -
Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office ofEnforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector Office at the Perry Nuclear Power Plant.
Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office ofEnforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector Office at the Perry Nuclear Power Plant.


W. Pearce-2-In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letterand its enclosure will be available electronically for public inspection in the NRC PublicDocument Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
W. Pearce-2-In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letterand its enclosure will be available electronically for public inspection in the NRC PublicDocument Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).


Sincerely,/RA/Ann Marie Stone, ChiefEngineering Branch 2 Division of Reactor Safety Docket No. 50-440License No. NPF-58
Sincerely,
 
/RA/Ann Marie Stone, ChiefEngineering Branch 2 Division of Reactor Safety Docket No. 50-440License No. NPF-58Enclosure:Inspection Report 05000440/2006009(DRS) w/Attachment: Supplemental Informationcc w/encl:G. Leidich, President - FENOCJ. Hagan, Chief Operating Officer, FENOC D. Pace, Senior Vice President Engineering and Services, FENOC Director, Site Operations Director, Regulatory Affairs M. Wayland, Director, Maintenance Department Manager, Regulatory Compliance T. Lentz, Director, Performance Improvement J. Shaw, Director, Nuclear Engineering Department D. Jenkins, Attorney, FirstEnergy Public Utilities Commission of Ohio Ohio State Liaison Officer R. Owen, Ohio Department of Health
===Enclosure:===
Inspection Report 05000440/2006009(DRS)  
 
===w/Attachment:===
Supplemental Informationcc w/encl:G. Leidich, President - FENOCJ. Hagan, Chief Operating Officer, FENOC D. Pace, Senior Vice President Engineering and Services, FENOC Director, Site Operations Director, Regulatory Affairs M. Wayland, Director, Maintenance Department Manager, Regulatory Compliance T. Lentz, Director, Performance Improvement J. Shaw, Director, Nuclear Engineering Department D. Jenkins, Attorney, FirstEnergy Public Utilities Commission of Ohio Ohio State Liaison Officer R. Owen, Ohio Department of Health


=SUMMARY OF FINDINGS=
=SUMMARY OF FINDINGS=
Line 172: Line 161:
05000440/2006009-01NCVADS and MSIV Air Accumulators Stress AnalysisDeficiencies (Section 1R21.3.b.1)05000440/2006009-02NCVNon-conservative Safety-Related Air Storage Tank SizingCalculation (Section 1R21.3.b.2)05000440/2006009-03URIInadequate Response for Minimum Pump Flow Settings(Section 1R21.4.b.1)05000440/2006009-04NCVInadequate Procedures for Controlling Flow into ReactorVessel (Section 1R21.6.b.1)
05000440/2006009-01NCVADS and MSIV Air Accumulators Stress AnalysisDeficiencies (Section 1R21.3.b.1)05000440/2006009-02NCVNon-conservative Safety-Related Air Storage Tank SizingCalculation (Section 1R21.3.b.2)05000440/2006009-03URIInadequate Response for Minimum Pump Flow Settings(Section 1R21.4.b.1)05000440/2006009-04NCVInadequate Procedures for Controlling Flow into ReactorVessel (Section 1R21.6.b.1)
===Closed===
===Closed===
: [[Closes finding::05000440/FIN-2006009-01]]NCVADS and MSIV Air Accumulators Stress AnalysisDeficiencies (Section 1R21.3.b.1)
05000440/2006009-01NCVADS and MSIV Air Accumulators Stress AnalysisDeficiencies (Section 1R21.3.b.1)05000440/2006009-02NCVNon-conservative Safety-Related Air Storage Tank SizingCalculation (Section  1R21.3.b.2)05000440/2006009-04NCVInadequate Procedures for Controlling Flow into ReactorVessel (Section 1R21.6.b.1)  
: [[Closes finding::05000440/FIN-2006009-02]]NCVNon-conservative Safety-Related Air Storage Tank SizingCalculation (Section  1R21.3.b.2)
 
: [[Closes finding::05000440/FIN-2006009-04]]NCVInadequate Procedures for Controlling Flow into ReactorVessel (Section 1R21.6.b.1)  
3
: 3
==LIST OF DOCUMENTS REVIEWED==
==LIST OF DOCUMENTS REVIEWED==
The following is a list of licensee documents reviewed during the inspection, includingdocuments prepared by others for the licensee.
The following is a list of licensee documents reviewed during the inspection, includingdocuments prepared by others for the licensee.
: Inclusion on this list does not imply that NRCinspectors reviewed the documents in their entirety, but rather that selected sections or portionsof the documents were evaluated as part of the overall inspection effort.
: Inclusion on this list does not imply that NRCinspectors reviewed the documents in their entirety, but rather that selected sections or portionsof the documents were evaluated as part of the overall inspection effort.
: Inclusion of a document in this list does not imply NRC acceptance of the document, unless specifically statedin the inspection report.1R21Component Design Bases InspectionCalculationsNumberTitleRevision860602BLow Pressure Air Storage Tank SizingRevision 1CL-MOV-1E22-11E22-F001, F004, F010, F011, F015 and F023 Max DPRevision 2
: Inclusion of a
: CL-MOV-1E51-31E51-F010, F013, F019, F022, F031, F059, F068, F077, andF078 Max DPRevision 2CL-MOV-1G33-1MOV 1G33F0001, 1G33F0004 Max DPRevision 3E12-088Residual Heat Removal System Hydraulic CalculationRevision 1
: E22-C031E22N0656 Leave-as-is Zone and Reset CalculationRevision 0, DCC 1E22-001HPCS System NPSH CalculationRevision 0,DCC 1-5E22-11E22 Pump Suction SwitchoverRevision 0,DCC-01E22-025Minimum Flow Required to Create Turbulent Flow on BothTube and Shell Side of HPCS JW Heat ExchangerE22-029SVI-E22-T2001-HPCS Pump Performance Test AcceptanceCriteriaRevision 6E22-037Design Basis Heat Load & Required ESW Flow for HPCSDGJW HXRevision 2E22-039Evaluate the Test Data Recorded During the Performance ofPTI-E22-P0007Revision 1E22-041Div 3 DG JW HX Thermal Performance Test ResultsAugust 27, 2003Revision 0E22-042Div. 3 EDG Jacket Water Heat Exc. Performance TestEvaluation August 25, 2004Revision 0
: CalculationsNumberTitleRevisionAttachment
: 4E51-C03RCIC-CST Low Level Transfer Trip 1E51-N635A(E)Revision 6E51-11NPSHa For RCIC Pump When Pumping from S.P.Revision 1,DCC-01ECA-068PSA-RCIC Room Heatup During Station BlackoutRevision 1
: EPG-21ECCS/RCIC NPSH Requirements vs. Temperatures ofSuppression PoolRevision 0EPG04P45-1RHR Loop B Containment FloodRevision 3EPGSAG-WS10RPV VariablesRevision 4
: EPGSAG-WS13Vortex LimitsRevision 0
: MOVC-0029DC MOV Torque Capability & Stroke Time Calculation usingLimitorque Method and also by using BWR Owners Group
: DC Motor Performance Methodology.Revision 5, Add. 2MOVC-0043Required Thrust Calculation for Gate Motor Operated Valves(MOVs)Revision 4MOVC-0044Globe Valve Required Thrust CalculationRevision 4MOVC-0068EPRI PPM Evaluation of Borg Warner 6" ANSI Class 1500Flex Wedge Gate Valves - 1G33F0001, 1G33F0004, and
: 1E51F0013Revision 0, DCC 1MOVC-0073AC MOV Actuator Degraded Voltage Torque/ThrustCapability using Commonwealth Edison (Com Ed) MethodRevision 7M39-014HPCS Pump Room Cooler Air Flow Rate and PerformanceEvaluations at Design Basis ConditionsRevision 1M39-015HPCS Pump Room Cooler Performance TestRevision 0P11-012P11 Level Setpoints in CST for E22 and E51 InstrumentsRevision 1
: P45-056ESW Pump Performance Test Acceptance CriteriaRevision 0,PIN 1-2,
: DCC 1-5P45-057ESW System Thermal Hydraulic ModelRevision 2,PIN 1-3P45-059ESW Flow to Division 3 ComponentsRevision 1,PIN 1-6
: CalculationsNumberTitleRevisionAttachment
: 5P45-075Minimum Branch Flow Rates for P45 SurveillanceAcceptance CriteriaRevision 0,PIN 1-2P45-081Eval. Of NPSH and Submergence Requirements for theESW System PumpsRevision 0P52-003Overpressurization of Isolated Piping and ComponentsRevision 1P57-R13Required Air Volume for ADS and MSIV Accumulators Revision 2,PIN 1-2PRDC-0012Load Evaluation, Battery Sizing and End of Cycle BatteryVoltage Determination for Division 1 & 2 Batteries During a Station Blackout (SBO)Revision 1PRMV-0014(686-85-18) Division 3 HPCS Diesel Generator(1E22S001)/EH1301 Protective Relaying Setpoint,Revision 3PRMV-0016 High Pressure Core Spray Motor 1E22C001 ProtectiveRelays SetpointsRevision 3PSA-002Probabilistic Evaluation for Loss of Normal ESW IntakeDuring Periods with Warm Lake Water Temperatures Revision 1PSTG-0014Electrical Load Determination of Division 1, 2, & 3 DieselGeneratorsRevision 1PSTG-0017Division 1, 2, & 3 Emergency Diesel Generators 7 DayAverage kW Loading for Fuel Oil ConsumptionRevision 7R44-007DG Air Start Check ValvesRevision 0R44-008DG Air Start Check ValvesRevision 0
: R45-014Assessment of Fuel Oil Transfer from Fuel Oil Storage Tankto Day TankRevision 0R45-009Determine Fuel Oil Volume for Standby and HPCS DieselGenerators for 7 day SupplyRevision 6SQ-0014Modification 1G33F0001/F0004; Justification F039/F040Revision 3SQ-0048Valves 1E22-F0012 and F0059 Thrust LimitsRevision 3
: SQ-0067Seismic Qualification of Valves:
: 1E51-F0022, -F0045; 1G33-F0031, -F0102, -F0104, and -F0107 Revision 0
: 6Condition/Issue Reports Generated Due to the InspectionNumberTitleDate06-00184Calculation E22-029, R-6 Has an Apparent Error in its Methodology1/13/0606-00237Frequency Variation In EDG Loading Calc.
: PSTG-0014, R/71/17/06
: 06-00296Issue with Full Qualification of HPCS1/19/06
: 06-00428Potential Missed Surveillance (1P45)1/27/0606-00476 Editorial Changes to PRA Model Basic Events1/31/06
: 06-00482 125VDC Short Circuit Analysis for Paralleling of Unit 1/2 Batteries2/1/06
: 06-00493Question Regarding HPCS Jacket Water Flow2/1/06
: 06-00494Tour Resulted In Questions2/1/06
: 06-00519 Functional Location Reference Information for Calculation inCurator/filenet Incomplete
: 2/1/0606-00527Excessive Maintenance Notification Tags on the Div 1/2 DGs2/2/0606-00632Review of ESW "C" Motor Oil Analysis2/9/06
: 06-00696 Reactor Core Isolation Cooling System Pump Room Temperature2/10/06
: 06-00701 FO Transfer Pump Seismic Qualification Did Not Consider MotorStarting Torque
: 2/13/0606-00703 Commitment in
: IEB 88-04 Response Not Implemented2/13/0606-00704 Procedure Step Potentially Conflicts with Calculation Assumption2/13/0606-00722PEI-SPI's Appear to Be Open-ended2/14/06
: 06-00734EDG Load Margin Relative to Cable & Transformer Load Losses2/14/06
: 06-00745 Incorrect Date Entered on Work Order Data Sheet2/15/06
: 06-00746Operator Actions From Memory Tracking Mechanism2/15/06
: 06-00751Lube Oil Results Not Evaluated In Accordance with TAI-2000-32/14/06
: 06-00754HPCS Pump Curves in TAF and Vendor Manual Do Not Match2/14/06
: 06-00761Material Condition of ESWPH2/15/06
: 06-0076924 hour SBO Coping Analysis2/16/06
: 06-00776Lube Oil Sample Analysis Result Parameter Out-Of-Spec2/16/06
: 06-00779HPCS Division 3 EDG Operating Procedure Incorrectly Displayed the Operating Mode of the Ground Fault Protection
: 2/16/06
: Condition/Issue Reports Generated Due to the InspectionNumberTitleDateAttachment
: 706-00813Question on Basis of Min Flow Adequacy2/16/0606-00815Maximum Drywell Temperature Affects ADS Accumulator Pressure2/16/06
: 06-00817Affects Drywell Backpressure Not Addressed in Calc P57-132/19/06
: 06-00827Gauge Reading Low2/18/06
: 06-00866Error found In Calculation P52-003 Revision 12/18/06
: 06-00872PEI-SPI Procedural Compliance2/22/06
: 06-00873Procedural Enhancement Potential2/22/06
: 06-00876Question on Use of Pump Runout Flow in Calc E22-0112/24/06
: 06-00898HPCS Pump Motor Protective Calculations Had Incorrectly PortrayedProtection and Coordination
: 2/23/0606-00970Calculation
: MOV-1E22-1 Reference List Contains Errors2/28/0606-00973Regarding Potential Noncompliance with ASME Code2/28/06
: 06-00974Bending stress Not Considered in Calc P52-003 R/12/28/06
: 06-00983ADS Solenoid Valve Overcurrent Protection3/01/06
: 06-00984Calculation
: PRMV-0016, R/3 for HPCS Motor Protection3/1/06
: 06-00985Diesel Generator Neutral Grounding Resistors3/1/06
: 06-00993Drawing 302-0351 / 302-0355 Discrepancies2/28/06
: 06-00997Bending Stress Not Considered in Calc P52-003 R/1 for Tanks 3/1/06
: 06-01015DG Neutral Grounding Resistors, Capacitive Current Evaluation3/2/06
: 06-01017Calculation
: PRMV-0001 (DG Ground Fault Protection)3/2/06
: 06-01044Code Questions For ADS Accumulators3/3/04
: 06-01054 Testing Frequency of Battery D-1-B 3/3/04Condition/Issue Reports Reviewed During the InspectionNumberTitleDate 99-02677RCIC Minflow Orifice May Be Too Small11/8/9900-03380Sluice Gate Opening Without Prealignment of ESW to the Swayle11/1/00 01-02848LPCI Injection Outside the Shroud May Not Have Adequate Flow7/24/01
: Condition/Issue Reports Reviewed During the InspectionNumberTitleDate Attachment
: 2-03972HPCS Pump Failed to Start10/23/0202-04355Div 2 DG Experienced Load Instability During the First Main. Run. 11/14/0202-04772LOOP and Generator Trip Due to Underfrequency8/14/03
: 03-00547Div 2 DG Wire to Brushes Losing It's Insulator2/3/03
: 03-04373Determine if the Cause of Diesel 3 DG Inoperability Existed inOperable Div 1 and Div 3 DGs03-04764RHR-A/LPCS Water-Leg Pump Not Supplying Adequate Pressure8/14/0303-05065ESW Pump A Failed9/1/03
: 03-05580Re-Review of SOER 97-1 Due to Air-Bound Waterleg Pump10/3/03
: 04-03680RCIC Test Return to CST Valve Did Not Pass PMT7/15/04
: 04-04917OE8987 Review Indicates Possible Air Void in Abandoned RHR toRCIC Suction Pipe
: 9/22/0404-06462Review of
: CR-03-04764 TS 3.5.1.1 ECCS Venting Concern12/9/0405-00230Some ABB Breaker 10 Year Overhaul Had Not Been Performed1/11/05
: 05-01899Chemistry Program Improvement for MIC Monitoring and Control3/7/05
: 06-00236Calc P
: RDC-0012 Requires Revision to Clarify SRV Coil Resistance1/16/0606-00052125vdc Control Circuit Coordination Calculation (P
: RDC-0004)2/10/06 DrawingsNumberTitleRevision022-0027Environmental Conditions for Diesel Generator AreasRevision JJ206-0010Main One Line Diagram 13.8kV and 4.16kVRevision Z
: 206-0017One Line Diagram Class 1E 4.16kV Bus EH11 & EH12Revision EE
: 206-0020Main One Line Diagram 480VRevision DD
: 206-0025One Line Diagram Class 1E 480V Bus EF1CRevision XXX
: 206-0027One Line Diagram Class 1E 480V Bus EF1DRevision VVV
: 206-0029One Line Diagram Class 1E 480V Bus EF1ERevision KK
: 256-0050Electrical One Line Diagram Class 1E DC system Division 3Revision N
: DrawingsNumberTitleRevisionAttachment
: 256-0051Electrical One Line Diagram Class 1E DC System Revision CC256-0052Electrical One Line Diagram Non-class 1E DC System BusD2A and D2BRevision Y302-0271Safety Related Instrument AirRevision M302-0348Standby Diesel Engine Mounted Piping1R43-C001B Div 2Revision F302-0349Standby Diesel - Engine Control Panel1H51-P054B Division 2Revision H302-0351Diesel Generator Starting AirRevision AA302-0357Div 1 & Div 2 Diesel Air Dryer Diagrams 1R44-D001A & Band 1R44-D002A & BRevision G302-0358Div 3 Diesel Starting Air / Air Dryer Diagram 1E22-S001Revision E302-0360Division 3 Diesel Jacket Water Cooling SystemRevision D
: 2-0631Reactor Core Isolation CoolingRevision BB
: 2-0632Reactor Core Isolation CoolingRevision
: JJ
: 2-0701High Pressure Core SprayRevision EE
: 2-0791Emergency Service Water SystemRevision RR
: B-208-066,Sheets 100-119High Pressure Core Spray Power Supply SystemVariousB-208-206, Sheet 53Metal Clad Switchgear 4.16 kV Stand By Diesel Bkr. EH1102Protective RelayingRevision
: JB-208-216,Sheets 1-47Standby Diesel GeneratorVariousD-206-018One Line Diagram Class 1E 4.16kV Bus EH13Revision
: ZD-206-051One Line Diagram Class 1E DC SystemRevision ZZ
: D-206-051Metal Clad Switchgear 4.16 kV Stand By Diesel Bkr. Revision Z
: D-206-050One Line Diagram Class 1E DC System, Div. 3Revision YSRV Accumulator Tank Assy. Details-Vendor:
: BishopricRevision 7
: 10Engineering Changes/ModificationsNumberTitleDateDCC-01Div 1, 2, 3 D/G Voltage Controlled Overcurrent and Load TestOverload Protection
: 8/17/93ECP 00-5013Safety Related Upgrade of the ESW Sluice Gate Sealing System10/1/01ECP 02-0224Setpoint Change to Adjust Low Flow Alarms for ESW HeatExchangers
: 1/17/05ECP 02-0283RCIC High Pressure Alarm Setpoint 1E51N08521/17/05ECP 03-0013High Pressure Core Spray Pump Breaker Modification11/19/03
: ECP 04-0263Emergency Service Water (ESW) "C" Pump Upgrade Modification4/7/05Miscellaneous DocumentsNumberTitleRevision/Date741-S-1414Pump Curve 14, High Pressure Core Spray, MPL 1E22C0001, Byron Jackson Curve, 4/19/78BWROG-8836/WAZ2BWR Owners Group Response to
: GL 88-04, "Safety-Related Pump Loss"
: 6/7/881E22-B5002Heat Exchanger Trend DataF-C4350-3Test of Electrical Cables, The Franklin Institute ResearchLaboratories, Final Report
: 7/1/76G1-22GE Task Report:
: Containment System ResponseRevision 0G1-45GE Task Report:
: Station BlackoutRevision 0
: G289File for Ideal Electric Generator Manual SM1001/30/78
: GAI Vendor Print4549-94Q-76-1-0Final Report on the ASME Section III Analysis of Class 3Nuclear Safety Related Shop Fabricated Tanks for Perry Nuclear Power Plant", SDRC Report number 7584
: 2/16/77MPL E22-S001Purchase Specification Data Sheet Engine Generator forHigh Pressure Core Spray SystemRevision 1NEDC-30865GE EQ Report-Perry Main Steam SRV Actuator Cylinder Air Valve, MPL Numbers B21-F041, F047, and F051Revision 0PY-CEI/NRR-1734-LImplementation of Generic Letter 89-13, "Service WaterSystem Problems Affecting Safety Related Equipment"
: 4/8/94PY-CEI/NRR-1118-LRAI-NRC Bulletin 88-04, "Safety Related Pump Loss"1/9/90 
===Miscellaneous===
: DocumentsNumberTitleRevision/DateAttachment
: 11PY-CEI/NRR-1081-LRAI-NRC Bulletin 88-04, "Safety Related Pump Loss"12/13/89PY-CEI/NRR-0879-LRAI-NRC Bulletin 88-04, "Safety Related Pump Loss"7/11/88QR-5804Qualification Tests for Rockbestos Firewall III ChemicallyCross-Linked Polyethylene Construction for Class 1E
: Service in Nuclear Generating StationsRevision 3SP-301-SO1-00ECCS Motors, General Electric Company EnvironmentalQualification Report
: NEDC-30197, Book No. S01, 7/18/83SP-504-4549-00Conformed Specification for the TanksRevision 7SP-559-4549-0005.15 kV Power Cable SpecificationRevision I
: SP-560-4549-00Specification Class 1E Small Power and Control CablesRevision XX
: SP-562-4549-00Class 1E Diesel Generator UnitsRevision 1
: TAF 81834Pump Curves
: 600270036Develop MIC Program Documents For Fleet12/21/05
: 200068834Inspection Report for the ECC "A" Heat Exchanger3/2/05
: 200094880Inspection Report for the RHR "C" Heat Exhanger3/17/05Perry Project Design Criteria Volumes 1 and 2, by GilbertAssociates, Inc.Revision 5EQ for Class 1E Safety Related Service, SmallEmergency Service Water Pump MotorsRevision 2Deviation Analysis Report, Isolated Drywell Systems areUnprotected by Relief Valves
: 9/7/89Perry Evaluation of SOER 97-18/23/98Breaker Overhaul Tasks listed by Voltage Class/Due Date3/1/06Operability DeterminationsNumberTitleDateCR 06-00296 HPCS Pump Performance Due to DG Droop Adjustment1/20/06CR 06-00974 ADS Air Accumulators Design Stress3/4/06
: CR 06-00997 MSIV Air Accumulators Design Stress3/4/06
: 2ProceduresNumberTitleRevisionARI-E22-P001HPCS Diesel Generator Control PanelRevision 4ARI-H13-P601-0018-D1RHR A Pump Room Sump Level HighRevision 11ARI-H13-P601-0018-D2RHR B Pump Room Sump Level HighRevision 11ARI-H13-P601-0018-D3RHR C Pump Room Sump Level HighRevision 11ARI-H13-P601-0018-E1HPCS Pump Room Sump Level HighRevision 11
: ARI-H13-P601-0018-E2LPCS Pump Room Sump Level HighRevision 11
: ARI-H13-P601-0018-E3RCIC Pump Room Sump Level HighRevision 11
: ISTPPump and Valve Inservice Testing Program PlanRevision 9
: ONI-SPI C-4EH13 System OperationRevision 0
: ONI-SPI D-1Maintaining System AvailabilityRevision 0
: ONI-SPI D-3Cross-Tying Unit 1 and 2 BatteriesRevision 0
: PDB-C0010ICS Valve Stroke Time Correction TimesRevision 3
: PEI-B13RPV Control (Non-ATWS)Revision L
: PEI-B13RPV Control (ATWS)Revision J
: PEI-B13RPV FloodingRevision J
: PEI-B13Emergency DepressurizationRevision H
: PEI-T23Containment ControlRevision G
: PEI-SPI 4.2RHR Loop B Flood Alternate InjectionRevision 1PEI-SPI 4.6Fast Fire Water Alternate Injection Revision 1
: PEI-SPI 5.1HPCS Injection PreventionRevision 0
: PEI-SPI 5.2LPCS and LPCI Injection PreventionRevision 0
: PEI-SPI 5.3Feedwater Injection PreventionRevision 1
: PEI-SPI 6.1LPCI A Outside the Shroud InjectionRevision 1
: PEI-SPI 6.2LPCI B Outside the Shroud InjectionRevision 1
: PEI-SPI 6.3LPCS Runout InjectionRevision 0
: PEI-SPI 6.4HPCS Runout InjectionRevision 1
: ProceduresNumberTitleRevisionAttachment
: 13PEI-SPI 6.5RHR C Runout InjectionRevision 1SOI-P45/49Emergency Service Water and Screen Wash SystemsRevision 11
: SOI-R42Div 1 DC Distribution, Buses
: ED-1-A and
: ED-2-A: Batteries, Chargers, and SwitchgearRevision 10SOI-R42 Div 2Div 2 DC Distribution, Buses
: ED-1-B and
: ED-2-B: Batteries, Chargers, and SwitchgearRevision 6SOI-R43Division 1 and 2 Diesel Generator SystemRevision 25SOI-E22AHPCS SystemRevision 15
: SOI-E22BDivision 3 Diesel GeneratorRevision 16
: SOI-E51RCIC SystemRevision 20
: SVI-E51-T1298RCIC Actuation Logic System Functional TestRevision 6
: SVI-G33-T2003RWCU Cold Shutdown Isolation Valves OperabilityTestRevision 2SVI-P57-T2201Safety Related Air 1P57-F555B & F556B Leak RateTestRevision 2SVI-P57-T2004Safety Related Air 1P57-F572B & F574B Leak RateRevision 1SVI-R43-T1317Diesel Generator Start and Load Division 1Revision 12
: SVI-R43-T1318Diesel Generator Start and Load Division 2Revision 10
: TAI-0501Heat Exchanger Performance MonitoringRevision 1Surveillances (completed)NumberTitleDate performed1E22F0012 Diagnostic Test Results4/6/041E51F0022 Diagnostic Test Results6/14/05
: 1G33F0001 Diagnostic Test Results3/15/05PTI-P57-P00001ADS Air Leak Test
: SVI-633-T9131Type C Local Leak Rate Test of 1G33 Penetration P1313/26/05
: SVI-E22-T1319Diesel Generator Start and Load Division 3 12/14/05
: Surveillances (completed)NumberTitleDate performedAttachment
: 14SVI-E22-T2001HPCS Pump and Valve Operability Test 6/4/05, 8/27/05, 11/15/05, 1/15/05SVI-E51-T2001RCIC Pump and Valve Operability Test 8/10/05, 12/1/05, 1/20/06SVI-P45T2003HPCS ESW Pump and Valve Operability Test 8/26/05, 11/18/05SVI-R42-T5202Surveillance Instruction, Weekly 125V Battery Voltage andCategory A Limits Check (Unit 1)
: 2/13/06SVI-R42-T5203Surveillance Instruction, Weekly 125V Battery Voltage andCategory A Limits Check (Unit 2)
: 2/13/06SVI-R42-T5211Service Test of Battery Capacity, Division 1 (Unit 1) 2/13/06Work OrdersNumberTitleDate200035272Relay IFC66K 50/51A(C) HPCS Pump 1E22C0019/22/04200035273Relay IFC66K 50/51B HPCS Pump 1E22C0019/22/04
: 200109234Replace Entire125 volt Battery 1B and Rack (all cells) 2/25/05
: 200143564BKR L2207 Overhaul to Remove Breaker Interference Plate8/1/05
: 200149124Replace Cells 1 and 53 in 125 volt Battery 1B7/29/05
: 15
==LIST OF ACRONYMS==
USEDADAMSAgencywide Documents Access and Management SystemADSAutomatic Depressurization System
ASMEAmerican Society of Mechanical Engineers
ATWSAnticipated Transient Without Scram
BWRBoiling Water Reactor
CDBIComponent Design Bases Inspection
CRCondition Report
CFRCode of Federal Regulations
DCDirect Current
DGDiesel Generator
DRSDivision of Reactor Safety
ECPEngineering Change Package
ESWEssential Service Water
FDegree Fahrenheit GEGeneral Electric
GLGeneric Letter
gpmgallons per minute
HPCSHigh Pressure Core Spray
IEEEInstitute of Electrical and Electronics Engineers
IMCInspection Manual Chapter
ISTInservice Testing
kVKilovolt
: [[LOCAL]] [[oss of Coolant Accident]]
: [[LPCI]] [[Low Pressure Coolant Injection]]
LPCSLow Pressure Core Spray
MOVMotor-Operated Valve
MSIVMain Steam Isolation Valve
NCVNon-Cited Violation
NPSHNet Positive Suction Head
NRCNuclear Regulatory Commission
OAOther Activities
PARSPublicly Available Records
PEIPlant Emergency Instruction
PRAProbabilistic Risk Assessment psigpounds per square inch gauge
psidpounds per square inch differential
RCICReactor Core Isolation Cooling
RHRResidual Heat Removal
RISRegulatory Information Summary
RPVReactor Pressure Vessel
SDPSignificance Determination Process
SPARStandardized Plant Analysis Risk
SRVSafety Relief Valve
TSTechnical Specifications
USARUpdated Safety Analysis Report
: [[URIU]] [[nresolved Item]]
}}
}}

Revision as of 19:45, 13 July 2019

IR 05000440-06-009(DRS); 01/17/2006 - 03/23/2006; Perry Nuclear Power Plant; Component Design Bases Inspection
ML061250451
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 05/05/2006
From: Ann Marie Stone
NRC/RGN-III/DRS/EB2
To: Pearce L
FirstEnergy Nuclear Operating Co
References
IR-06-009
Download: ML061250451 (38)


Text

May 4, 2006Mr. L. William PearceVice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant 10 Center Road, A290 Perry, OH 44081SUBJECT:PERRY NUCLEAR POWER PLANT NRC COMPONENT DESIGN BASES INSPECTION (CDBI) INSPECTION REPORT 05000440/2006009(DRS)

Dear Mr. Pearce:

On March 23, 2006, the U.S. Nuclear Regulatory Commission (NRC) completed a baselineinspection at your Perry Nuclear Power Plant. The enclosed report documents the inspection findings which were discussed on March 3, 2006, with you, and on March 23, 2006, with Mr. J. Shaw, and other members of your staff. The inspection examined activities conducted under your license as they relate to safety and tocompliance with the Commission's rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. Specifically, this inspection focused on the design of components that are risk significant and have low design margin.Based on the results of this inspection, three NRC-identified findings of very low safetysignificance, which involved violations of NRC requirements were identified. However, becausethese violations were of very low safety significance and because they were entered into your corrective action program, the NRC is treating the issues as Non-Cited Violations in accordancewith Section VI.A.1 of the NRC's Enforcement Policy. Additionally, a licensee identifiedviolation is listed in Section 4OA7 of this report.If you contest the subject or severity of a Non-Cited Violation, you should provide a responsewithin 30 days of the date of this inspection report, with the basis for your denial, to the U.S.

Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission -

Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office ofEnforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector Office at the Perry Nuclear Power Plant.

W. Pearce-2-In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letterand its enclosure will be available electronically for public inspection in the NRC PublicDocument Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/Ann Marie Stone, ChiefEngineering Branch 2 Division of Reactor Safety Docket No. 50-440License No. NPF-58Enclosure:Inspection Report 05000440/2006009(DRS) w/Attachment: Supplemental Informationcc w/encl:G. Leidich, President - FENOCJ. Hagan, Chief Operating Officer, FENOC D. Pace, Senior Vice President Engineering and Services, FENOC Director, Site Operations Director, Regulatory Affairs M. Wayland, Director, Maintenance Department Manager, Regulatory Compliance T. Lentz, Director, Performance Improvement J. Shaw, Director, Nuclear Engineering Department D. Jenkins, Attorney, FirstEnergy Public Utilities Commission of Ohio Ohio State Liaison Officer R. Owen, Ohio Department of Health

SUMMARY OF FINDINGS

IR 05000440/2006009(DRS); 01/17/2006 - 03/23/2006; Perry Nuclear Power Plant; ComponentDesign Bases Inspection.The inspection was a 4-week onsite baseline inspection that focused on the design ofcomponents that are risk significant and have low design margin. The inspection was conducted by regional engineering inspectors and two consultants. Three Green Non-Cited Violations were identified. The significance of most findings is indicated by their color (Green,

White, Yellow, Red) using Inspection Manual Chapter 0609, "Significance Determination Process (SDP)." Findings for which the SDP does not apply may be Green, or be assigned a severity level after NRC management review. The NRC's program for overseeing the safeoperation of commercial nuclear power reactors, is described in NUREG-1649, "ReactorOversight Process," Revision 3, dated July 2000.A.Inspector-Identified and Self-Revealed Findings

Cornerstone: Mitigating Systems

Green.

The inspectors identified a Non-Cited Violation of 10 CFR Part 50, Appendix B,Criterion III, "Design Control," having very low safety significance (Green) involving aninadequate stress analysis performed for the automatic depressurizati on system (ADS)air accumulators. Specifically, the licensee failed to account for all the related stresses in the ADS accumulator stress analysis calculation. Inclusion of these additional stresses resulted in a higher stress than allowed by the American Society of Mechanical Engineers Code. Additionally, the accumulators' certification of design, as required by the Code,Section III, was incorrect as it was not based on the maximum designpressure the accumulators would be subject to under accident conditions. The licensee's corrective actions included performing an operability determination thatconcluded the ADS accumulators would not fail structurally under design conditions. The finding was more than minor because the failure to adequately evaluate the designrequirements of the accumulators could have led to structural failure of the tanks, which would have prevented the ADS valves from functioning as designed and could have affected the mitigating systems cornerstone objective of design control. The finding wasof very low safety significance based on the results of the licensee's analysis and screened as Green using the SDP Phase 1 screening worksheet. (Section 1R21.3.b.1)Green. The inspectors identified a Non-Cited Violation of 10 CFR Part 50, Appendix B,Criterion III, "Design Control," having very low safety significance (Green) involving thesizing of the main steam isolation valve and automatic depressurization system (ADS)air storage tank. The inspectors identified that the licensee failed to correctly specify in a design calculation the required minimum differential air pressure required to actuate the ADS valves when manually operated. This resulted in a safety-related air systemcalculation that was non-conservative when determining the long-term air volume requirements in the air storage tank. The licensee's corrective actions included verifying that adequate design margin existed for the air tank capacity and entered thisperformance deficiency into their corrective action program for resolution.

3The finding was more than minor because the failure to adequately evaluate air storagetank sizing could result in over-predicting the tank's capacity as verified by the surveillance test's acceptance criteria (i.e., creating design margin capability that wouldnot exist) and could have affected the mitigating systems cornerstone objective ofdesign control. The finding was of very low safety significance based on the results of the licensee's analysis and screened as Green using the SDP Phase 1 screening worksheet. (Section 1R21.3.b.2)Green. The inspectors identified a Non-Cited Violation of Technical SpecificationRequirement 5.4.1, which requires, in part, that written procedures/instructions be established, implemented, and maintained covering the emergency operatingprocedures required to implement the requirements of NUREG-0737 and NUREG-0737,Supplement 1. The anticipated transient without scram (ATWS) special plant instructions issued to provide for injection outside the shroud were inadequate because the procedures inappropriately limited the ability to control reactor water level (or reactorpressure if reactor water level is unknown). The licensee entered this performance deficiency into their corrective action program for resolution.This finding was more than minor because the procedure deficiency affected the abilityof the licensee to use the low pressure coolant injection sub-systems to prevent undesirable consequences of large power excursions associated with an ATWS, and was associated with the mitigating systems procedure quality attribute of the mitigatingsystems cornerstone objective. The finding was of very low safety significanc e becauseno actual initiating event or transient occurred and screened as Green using the SDP Phase 1 screening worksheet. (Section 1R21.6.b.1)

B.Licensee-Identified Violations

One violation of very low safety significance, which was identified by the licensee, hasbeen reviewed by the inspectors. Corrective actions taken or planned by the licensee have been entered into the licensee's corrective action program. This violation and corrective action tracking numbers are listed in Section 4OA7 of this report.

4

REPORT DETAILS

1.REACTOR SAFETYCornerstone: Initiating Events, Mitigating Systems, and Barrier Integrity1R21Component Design Bases Inspection (71111.21).1Introduction The objective of the component design bases inspection is to verify that design baseshave been correctly implemented for the selected risk significant components and that operating procedures and operator actions are consistent with design and licensing bases. As plants age, their design bases may be difficult to determine and an important design feature may be altered or disabled during a modification. The Probabilistic RiskAssessment (PRA) model assumes the capability of safety systems and components toperform their intended safety function successfully. This inspectible area verifies aspects of the initiating events, mitigating systems and barrier integrity cornerstones forwhich there are no indicators to measure performance. Specific documents reviewed during the inspection are listed in the attachment to the report..2Inspection Sample Selection ProcessThe inspectors selected risk significant components and operator actions for reviewusing information contained in the licensee's PRA and the Perry Standardized Plant Analysis Risk (SPAR) Model, Revision 3.21. In general, the selection was based upon the components and operator actions having a risk achievement worth of greater than2.0 and/or a risk reduction worth of greater than 1.005. The operator actions selectedfor review included actions taken by operators both inside and outside of the control room during postulated accident scenarios. Since all plant components were not modeled in the licensee's PRA, additional resources were used in the selection process such as the licensee's maintenance rule program, where an expert panel identified additional systems/components that also were considered risk significant.The inspectors performed a margin assessment and detailed review of the selected risk-significant components to verify that the design bases have been correctly implemented and maintained. This design margin assessment considered original design, reductions caused by design modifications or power uprates, or reductions due to degraded material conditions. Equipment reliability issues were also considered in the selection ofcomponents for detailed review. These included items such as failed performance test results, significant corrective action, repeated maintenance activities, maintenance rule (a)(1) status, components requiring an operability evaluation, NRC resident inspectorinput of problem equipment, system health reports, and the plant health committeeissues list. Consideration was also given to the uniqueness and complexity of the design, operating experience, and the available defense in depth margins. As practical, the inspectors performed walkdowns of the components to evaluate the as-built design and material condition. A summary of the reviews performed and the specific inspection findings identified are included in the following sections of the report.

5.3 Component Design

a. Inspection Scope

The inspectors reviewed the Updated Safety Analysis Report (USAR), TechnicalSpecifications (TS), com ponent/system design basis documents, drawings, and otheravailable design basis information, to determine the performance requirements of the selected components. The inspectors used applicable industry standards, such as the American Society of Mechanical Engineers (ASME) Code and the Institute of Electrical and Electronics Engineers (IEEE) Standards, to evaluate acceptability of the systems'design. The review was to verify that the selected components would function as required and support proper operation of the associated systems. The attributes thatwere needed for a component to perform its required function included process medium, energy sources, control systems, operator actions, and heat removal. The attributes toverify that the component condition and tested capability were consistent with the designbases and were appropriate may include installed configurati on, system operation,detailed design, system testing, equipment/environmental qualification, equipmentprotection, component inputs/outputs, operating experience, and componentdegradation.For each of the components selected, the inspectors reviewed the maintenance history,system health report, and condition reports (CRs). Walkdowns were conducted for allaccessible components to assess material condition and to verify the as-built condition was consistent with the design. Other attributes reviewed are included as part of the scope for each individual component. The components (17 samples) listed below were reviewed as part of this inspectioneffort:High Pressure Core Spray (HPCS) Pump: The inspectors reviewed vortexingcalculations for HPCS pump suction alignment to the suppression pool and condensate storage tank. Hydraulic calculations were reviewed to ensure design requirements for flow and pressure were translated as acceptance criteria for pump in-service testing (IST). The inspectors reviewed calculations related to pump's net positive suction head (NPSH) to ensure the pump was capable of functioning as required. The pump motor's calculations for voltage/frequency, current ratings, protective relaying settings, and cable feeder size were reviewed to ensure the motor was able to drive the associated pump. Design change history and IST results were reviewed to assess potential component degradation and impact on design margins. In addition, the licensee responses and actions to Bulletin 88-04, "Potential Safety-Related Pump Loss," were reviewed to assess implementation of operating experience. A modification to replace the pump breaker was also reviewed.Division 3 Diesel Generator (DG) for HPCS: The inspectors reviewed electricalloading calculations, including voltage and frequency, current ratings, and short circuit ratings for all operating modes. Protective relaying calculations were reviewed to assess adequacy of protection during test mode and during emergency operation. Test results were reviewed to ensure the adequacy of 6current ratings for full loading and emergency loading. Operating andsurveillance test procedures were reviewed to assess whether component operation and alignments were consistent with design and licensing bases assumptions. HPCS Minimum Flow Valve: The inspectors reviewed the motor-operated valve(MOV) calculations, including required thrust, degraded voltage, maximum differential pressure, setpoint, and valve weak link analysis, to ensure the valve was capable of functioning under design conditions. Diagnostic and IST results were reviewed to verify acceptance criteria were met and performance degradation would be identified.Division 3 Essential Service Water (ESW) Pump: The inspectors reviewedcalculations related to pump flow, head, and NPSH requirements to ensure the pump was capable of functioning as required. Design change history and IST results were reviewed to assess potential component degradation and impact on design margins. The inspectors reviewed the control and power design drawings to verify the availability of both control and power required for operability. Inaddition, the licensee responses and actions to Generic Letter (GL) 89-13, "Service Water System Problems Affecting Safety-Related Equipment," were reviewed to assess implementation of operating experience. A modification to change pump shaft materials and other design improvements for this pump was reviewed to ensure the change did not adversely affect the design function of the pump.HPCS DG Heat Exchanger: The inspectors reviewed the ESW hydraulicanalysis that verified the DG jacket water heat exchanger would receive minimum design cooling water flow, in accordance with the flow value specified in the thermal evaluation of the heat exchanger. The inspectors reviewed thermal performance testing, and trending of data, that was performed to verify heat transfer capability. The inspectors interviewed maintenance personnel toascertain whether the condition of the heat exchanger and attached piping was meeting the guidance of GL 89-13. The inspectors reviewed periodic surveillance tests to verify coolant temperatures were within acceptable limits and performance degradation would be identified.Swayle Manual Valves: The inspectors reviewed the seismic and hydrauliccalculations for the ESW function using the Swalye valves, IST program, operator rounds, and test procedures to ensure the manual Swayle valves were capable of functioning as required. Maintenance activities were reviewed to verify the periodic operation of the valve. Operator actions and operatingprocedures were reviewed as the Swayle valves' operation was necessary with opening of the intake bay sluice gates under certain conditions to allow the ESW system to continue it's safety-related function. A modification to the sluice gatesto install an air seal system was reviewed based on this inter-related function.Residual Heat Removal (RHR) Cross-tie to ESW Valves: The inspectorsreviewed the hydraulic calculation to verify decay heat can be removed by ESW in the emergency lineup when injecting into the reactor vessel. Since the cross-7tie valves were not normally used, the inspectors verified that the cross-tie valvesand associated connecting pipe were inspected to verify that the system wouldpass design flow. The inspectors performed a walk through of the emergency operating procedures associated with these valves to assess operator knowledge level, adequacy of procedures, and availability of special equipmentwhere required. Additionally, the inspectors performed an assessment of the radiological conditions to be expected during the performance of the above emergency operating procedures. Reactor Core Isolation Cooling (RCIC) Pump: The inspectors reviewedvortexing calculations for the RCIC pump suction alignment to the suppression pool, and condensate storage tank. The inspectors reviewed hydraulic calculations to ensure design requirements for flow and pressure were translated as acceptance criteria in IST pump testing. The inspectors reviewed calculations related to the pump's NPSH requirements and minimum flow requirements to ensure the pump was capable of functioning as required. Testing was reviewed to assess potential component degradation and impact on design margins. In addition, the licensee responses and actions to Bulletin 88-04 was reviewed to assess implementation of operating experience. A modification to raise the setpoint of the pump's suction relief valve as corrective action to inadvertent valve lifting events was reviewed.RCIC Room Cooler: The inspectors reviewed the RCIC room cooler thermalsizing and the loss of ventilation calculations to ensure that the heat gains in theroom were properly accounted for and that a conservative starting temperature was used. The inspectors reviewed data to ensure that the room temperature was within acceptable limits. A walkdown was performed to verify cleanliness of the air filters, and preventive maintenance work orders were reviewed to ensure filters were changed on an appropriate frequency.RCIC Test Return Valve: The inspectors reviewed MOV calculations, includingrequired thrust, degraded voltage, maximum differential pressure, and valve weak link analysis, to ensure the valve was capable of functioning under design conditions. Diagnostic and IST test results were reviewed to verify acceptance criteria were met and performance degradation would be identified. The inspectors reviewed test results to verify the valve would receive an automatic close signal during a RCIC pump test if the system received an initiation signal. Regulatory Information Summary (RIS) 2001-15, "Performance of DC-Powered Motor-Operated Valve Actuators," was reviewed to ensure it was properly evaluated and implemented as appropriate. Automatic Depressurization System (ADS) Valves: The inspectors reviewedcalculations used for sizing of the air storage tank, structural support capability ofthe individual safety relief valve (SRV) accumulators, ASME Code stress analysis, solenoid valve operating current and voltage, and associated circuit protection to ensure the ADS valves were capable of functioning under design conditions. The inspectors reviewed vendor design specifications for the SRV accumulators to verify compliance with Code requirements. The inspectors also reviewed the air leak rate testing procedure, and recently completed leak rate 8testing performed for the air system c onnected to the accumulators to verify thatthe acceptance criteria were appropriate and data was within the defined criteria.Reactor Water Cleanup Suction Inboard Isolation Valve: The inspectorsreviewed the MOV calculations, including required thrust, degraded voltage, maximum differential pressure, and valve weak link analysis, to ensure the valve was capable of functioning under design conditions. Local leak rate, diagnostic, and IST test results were reviewed to verify acceptance criteria were met and performance degradation would be identified.Division 2 Diesel Generator: The inspectors reviewed calculations for dieselloading, fuel oil consumption, and vortexing for the fuel oil tanks. Seismic qualification documents for the E22-S001 electrical cabinets were also reviewed.

The inspectors performed a review of system normal operating procedures andsurveillance test procedures to assess whether component operation and alignments were consistent with design and licensing bases assumptions.Diesel Generator Output Breakers: The inspectors reviewed the electricaldrawings that described the circuits used to control the generator outputs bymeans of the DG output breakers. Corrective actions for DG output breaker problems were reviewed. Division 1 and 2 DG Air Start Check Valves: The inspectors reviewed the airleak rate testing procedure and recently completed leak rate testing performed for the diesel generator air start check valves to verify acceptance criteria were met and performance degradation would be identified.4.16 kV 1E Bus EH12: The repair and replacement program established as partof the corrective actions for 4.16 kV breakers problems was reviewed. Unit 1 and 2 Safety-Related Batteries: The inspectors reviewed electricalcalculations, including voltage at the valve terminals under various accident scenarios, battery float and equalizing voltages, and overall battery capacity.

The inspectors performed a walk through of the off-normal operating procedures associated with cross-tying Unit 1 and 2 safety-related batteries to assess operator knowledge level, adequacy of procedures, and availability of specialequipment where required. The following review did not constitute an inspection sample:

Unit 1 and 2 Non-Safety Related Battery: These batteries were initially selectedbased on an initial review of the licensee's PRA, which indicated a high risk ranking. Subsequent questioning by the inspectors determined that the riskranking was in error (high ranking was mis-identified, should have been identified as the safety-related batteries), such that inspection activities were limited and this component will not be counted as a completed sample. The inspectors didwalkdowns of the non-safety related batteries, reviewed maintenance and surveillance schedules and records, and performed a walk through of the off-normal operating procedures associated with cross-tying Unit 1 and 2 non-safety related batteries.

b. Findings

Two findings of very low safety significance associated with Non-Cited Violations(NCVs) were identified. b.1ADS and MSIV Air Accumulators Stress Analysis DeficienciesIntroduction: The inspectors identified a Non-Cited Violation (NCV) of 10 CFR Part 50,Appendix B, Criterion III, "Design Control," having very low safety significance (Gr een)involving the stress analysis performed for the ADS backup air accumulators.

Specifically, the licensee failed to account for all the related stresses in the ADS accumulator stress analysis calculation. Inclusion of these additional stresses resulted in a higher stress than allowed by the American Society of Mechanical Engineers (ASME) Code. Additionally, the accumulators' certification of design, as required by the Code,Section III, was incorrect as it was not based on the maximum design pressurethe accumulators would be subject to under accident conditions.

Description:

The ADS used a number of the reactor SRVs to reduce reactor pressureduring a small break loss-of-coolant-accident (LOCA) in the event of a HPCS failure.

Each ADS valve has a backup accumulator to store air to provide the motive force to stroke the valve if the normal non-safety related air system was unavailable. Therewere no relief valves on the air accumulators to relieve internal pressure, which also have check valves to prevent flow out of the accumulators back into the air system.

Since this created a closed volume, any increase in ambient temperature would result in a corresponding increase in internal pressure. The accumulators were designed per the requirements of ASME Code,Section III,Division 1, 1974 Edition, up to and including the Winter, 1975 Addenda. The inspectors reviewed the original stress analysis performed for the tanks (accumulators) GAI Vendor Print 4549-94Q-76-1-0, "Final Report on the ASME Section III Analysis of Class 3Nuclear Safety Related Shop Fabricated Tanks for Perry Nuclear Power Plant." This analysis used an accumulator pressure of 150 pounds per square inch (psi) for internal pressure. The inspectors noted that the certification of design, and the vesselnameplate information for the accumulators listed a maximum ambient temperature of 330 degrees Fahrenheit (F), and a vessel design pressure of 180 pounds per squareinch gauge (psig). The internal pressure used in the stress analysis, however, did not take into account the affect of heating the enclosed air volume due to the maximum ambient drywell temperature. The licensee provided Calculation P52-003, "Overpressurization of Isolated Piping andComponents," which evaluated the affect of the pressure increase on the ADS accumulators during a thermal overpressure event caused by a rapid increase in drywell temperature up to 330 F. This calculation was completed prior to initial plant startupwhen this issue was initially identified, however, the actions taken did not adequately resolve the concern. The calculation determined that for an ambient drywelltemperature of 330 F the accumulators should have been designed to withstand aninternal pressure of 308.4 psig.The certification of design for the accumulators listed an internal design pressure of 180psi at a temperature of 330 F, with a hydrostatic test pressure of 270 psi. Because the 10maximum pressure of 308.4 psig was not specified in the ASME certification of designand the vessel nameplates as a design condition, the inspectors determined that the airaccumulators were not in compliance with ASME Code,Section III. Paragraph NA-3252of the ASME Code, "Contents of Design Specification", item

(b) required, in part that thedesign requirements shall be included in design specification. The licensee initiated CR 06-01044 to address this issue.

The tank specification for the accumulators, SP-504-4549-00, "Conformed Specification for the Tanks," had design requirements in paragraph 2:06.3.1.a.(2) for accelerationloading requirements and combined loading design limits for safe shutdown building acceleration. The paragraph stated that the tanks located inside the reactor buildingshall withstand the maximum acceleration created by safe shutdown earthquake combined with SRV discharge and small break accident loads. The inspectors noted that the ASME Code,Section III, Division I, Class 3 Stress Report, supplied by the ADSaccumulator vendor as part of original construction, performed an analysis that evaluated loading conditions that included both the design pressure of the tanks and themaximum allowable nozzle loads consisting of axial loads and bending moments caused by seismic plus operating loads, as required by the tank specification. The inspectors noted that the stress analysis contained in Calculation P52-003 was non-conservative asit only considered the hoop stresses in the accumulator caused by the increase in internal pressure, but did not include the maximum allowable nozzle loads when calculating the maximum stresses the accumulators would be subject to under design conditions. The licensee subsequently performed an operability determination that evaluated theeffect of not including the nozzle loads in the stress analysis. The operabilitydetermination concluded that the accumulators would maintain pressure integrity using the Level D stress criteria for Class 3 vessels from the 2004 Edition of ASME Code.

Level D rules were intended to maintain pressure boundary integrity, but will permitstructural deformation. The licensee determined that Calculation P52-003 needed to be revised to include all required stresses and issued CR 06-00974 to track resolution. The inspectors and the Office of Nuclear Reactor Regulation reviewed the licensee's operability determination and concluded that there would be no affect on operability ofthe ADS system when accounting for the higher stresses in the accumulators. The useof the Level D stress criteria was acceptable for operability, however, the accumulatorswere considered nonconforming that would require further action by the licensee to return them to within Code compliance. Since Calculation P52-003 also evaluated the pressure integrity of the main steamisolation valve (MSIV) accumulators, the inspectors had similar concerns with the stress analysis for these accumulators. As a result, the licensee issued CR 06-00997 and an operability determination that concluded the MSIV accumulators were structurallyqualified to ASME Code Level D faulted limits. The inspectors reviewed the operabilitydetermination, and agreed with the licensee that the accumulators were operable, butnonconforming. The operability determination discussed the piping systems attac hed tothe accumulators, and determined that they would maintain structural integrity as well.Analysis: The inspectors determined that the failure to account for the stresses relatedto the dynamic structural loading in the accumulators was a performance deficiency and a finding. The inspectors determined that the finding was more than minor in 11accordance with Inspection Manual Chapter (IMC) 0612, "Power Reactor InspectionReports," Appendix B, "Issue Dispositioning Screening," because it was associated with the attribute of design control, which affected the mitigating systems cornerstoneobjective of ensuring the availability and reliability of the ADS valves to res pond toinitiating events to prevent undesirable consequences. Specifically, the failure to account for all the stresses related to the dynamic structural loading in the accumulators resulted in not knowing that the material yield stresses exceeded the ASME Code allowable stress limits.The inspectors evaluated the finding using IMC 0609, Appendix A, "SignificanceDetermination of Reactor Inspection Findings for At-Power Situations," Phase 1 screening, and determined that the finding screened as Green because it was not adesign issue resulting in loss of function per Part 9900, Technical Guidance, "OperabilityDeterminations & Functionality Assessments for Resolution of Degraded or Nonconforming Conditions Adverse to Quality or Safety," did not represent an actual loss of a system's safety function, did not result in exceeding a TS allowed outage time,and did not affect external event mitigation. The basis for this conclusion was that despite the loss of design margin in the ADS accumulator structural capability tomaintain pressure integrity, the ADS system would have performed its safety function asconcluded in the operability determination.Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, "Design Control,"required, in part, that design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program.Contrary to the above, as of February 28, 2006, the licensee's design control measuresfailed to provide for verifying or checking the adequacy of design by validating that the calculated stress value for ADS air accumulators would be higher than that assumed by the structural analysis. Specifically, Calculation P52-003 did not evaluate the increasedpressure stress in the accumulators in combination with stresses due to seismic plus operating loads, and only considered the hoop stresses in the accumulator caused by the increase in internal pressure resulting from an ambient temperature increase. This resulted in the accumulator's structural analysis being non-conservative, and not in accordance with the requirements of ASME Code,Section III, Paragraph NA-3252. Because this violation was of very low safety significance and it was entered into the licensee's corrective action program, this violation is being treated as a NCV, consistent with Section VI.A.1 of the NRC Enforcement Policy (NCV 05000440/2006009-01(DRS)). The licensee entered the finding into their corrective action program as CR 06-00974 to revise the affected calculation, and CR 06-01044 to evaluate ASME Code requirements for the accumulators. The licensee performed an operability determination andconcluded that the accumulators, while currently nonconforming, will remain operable.

b.2Non-conservative Safety-Related Air Storage Tank Sizing CalculationIntroduction: The inspectors identified a Non-Cited Violation (NCV) of 10 CFR Part 50,Appendix B, Criterion III, "Design Control," having very low safety significance (Gr een)involving the sizing of the P57 air storage tank. Specifically, the inspectors identified 12that the licensee failed to correctly specify the minimum differential air pressure requiredto actuate the ADS valves when manually operated.Description: The inspectors reviewed Calculation P57-13, "Required Air Volume forMSIV and ADS Accumulators," whose purpose was to determine the long-term air volume in the P57 air storage tank required for the ADS and MSIV air actuators. The accumulator sizing calculation was based on 90 psig, the minimum air pressure to stroke the valve. However, General Electric (GE) Design Specification Data Sheet stated in paragraph 3.1.18.2.2, that for the ADS function, the differential air pressurerequired to stroke the valve at 0 psig inlet pressure was 95 psid to account for drywell backpressure. Drywell pressure would be elevated above ambient pressure during accident conditions and a station blackout event where ADS was credited with manual vessel depressurization. Since drywell pressure during an accident could be as high as 30 psi, 125 psi would be required to operate the valves as they must overcome the exhaust pressure, which would be exposed to the elevated drywell pressure. By not accounting for the drywell backpressure and the use of a lower minimum air pressure (90 versus 95) when evaluating the accumulator capacity, the inspectors determined that the calculation was non-conservative when calculating the long-term air volumerequirements in the P57 air storage tank. Although the licensee indicated there may bea supportable basis for the use of the lower minimum air pressure, the inspectors concluded the calculation must account for the backpressure in containment when determining the minimum actuation pressure of the valve.Additionally, calculation P57-13 determined the leakage rate acceptance criteria forprocedure PTI-P57-P0001, "Loss of Air Test for Safety Related Instrument Air System."

Since the calculation assumed that only 90 psi were required to stroke an ADS valve, the acceptance criteria would be non-conservative. Since a higher pressure was required to operate the valves, the licensee reviewed the last several completed tests to ensure that sufficient air pressure remained in the tanks to stroke the valves as required during a design basis event. The review determined that the indicated leakage rates were well below the leakage rate acceptance criteria. Based on the normal 150 psig of air maintained in the P57 storage tank and the low indicated leakage rates, the inspectors concluded that the ADS air system had sufficient capacity for operability.Analysis: The inspectors determined that failure to correctly specify the minimumdifferential air pressure required to actuate the ADS valves when manually operated was a performance deficiency and a finding. The inspectors determined that the finding was more than minor in accordance with IMC 0612, Appendix B, "Issue Dispositioning Screening," because it was associated with the attribute of design control, which affected the mitigating systems cornerstone objective of ensuring the availability andreliability of the ADS valves to respond to initiating events to prevent undesirableconsequences. Specifically, the failure to properly account for minimum air pressure in the calculation that was used as the basis of ADS air system testing could result inover-predicting the air storage tanks' performance (i.e., creating design margin capability that would not exist), which could potentially render the ADS valves incapableof performing its required safety function.The inspectors evaluated the finding using IMC 0609, Appendix A, "SignificanceDetermination of Reactor Inspection Findings for At-Power Situations," Phase 1 screening, and determined that the finding screened as Green because it was not a 13design issue resulting in loss of function per Part 9900, Technical Guidance, did notrepresent an actual loss of a system's safety function, did not result in exceeding a TSallowed outage time, and did not affect external event mitigation. The basis for this conclusion was that despite the loss of design margin in the air storage tanks' capacity, the ADS system would have performed its safety function as the P57 air storage tankwas maintained at 150 psig and recent testing indicated low leakage from the air system.Enforcement: 10 CFR Part 50, Appendix B, Criterion III, "Design Control," required, inpart, that measures shall be established to assure that applicable regulatory requirements and the design basis are correctly translated into specifications, drawings, procedures, and instructions.Contrary to the above, as of February 17, 2006, the licensee failed to assure that theADS minimum air pressure operability limits were correctly translated into specifications,drawings, procedures, and instructions. Specifically, the minimum air pressure requirements as specified in the GE Design Specification Data Sheet for SRVs were not incorporated into Calculation P57-13, which in turn resulted in non-conservative acceptance criteria for PTI-P57-P0001 air storage tank pressure drop test. Because this violation was of very low safety significance and it was entered into the licensee's corrective action program, this violation is being treated as a NCV, consistent with Section VI.A.1 of the NRC Enforcement Policy (NCV 05000440/2006009-02(DRS)). The licensee verified the air storage tank contained a sufficient volume and air pressure to support ADS operation and initiated CR 06-00817 to revise the affected documents.

.4 Operating Experience

a. Inspection Scope

The inspectors reviewed four operating experience issues (4 samples) to ensure theseissues, either NRC generic concerns or identified at other facilities, had been adequatelyaddressed by the licensee. The operating experience issues listed below were reviewed as part of this inspection effort:Gas voids due to improper venting or gas intrusion in emergency core coolingsystems and other safety related piping systems such as RCIC and RHR. Responses to related experience at Beaver Valley and Limerick were also reviewed for applicability;RIS 2001-05, "Performance of DC-Powered Motor-Operated Valve Actuators";Bulletin 88-04, "Potential Safety-Related Pump Loss"; andGL 89-13, "Service Water System Problems Affecting Safety-RelatedEquipment."

b. Findings

One unresolved item was identified associated with NRC Bulletin 88-04 concerningminimum flow for safety-related pumps.

14 b.1Inadequate Response for Minimum Pump Flow SettingsIntroduction: The inspectors identified an unresolved item (URI) concerning thelicensee's response to Bulletin 88-04, "Potential Safety-Related Pump Loss," regarding establishing minimum flow requirements for the safety-related pumps. The licensee recognized that the conditions reported in the bulletin were present in safety-related pumps, but did not determine appropriate minimum pump flow values to minimize and manage, or to eliminate, the potential for pump damage. At the end of the inspection,the licensee was evaluating current minimum flow values with the pump manufacturer.

The inspectors needed this information to complete the assessment of this issue.

Description:

Bulletin 88-04, in part, identified a concern regarding the adequacy ofminimum flow capacities for safety-related centrifugal pumps. The Bulletin required licensees to evaluate the capability of safety-related pumps to run long-term at minimumrecirculation flow rates. The Bulletin stated that many licensees had accounted for thermal considerations in setting the minimum recirculation flow rates, but had failed to consider flow instability effects. The latter consideration could necessitate a considerable increase in minimum flow settings, especially for pump operation for extended periods of time. This potential increase occurred because centrifugal pumps demonstrated a flow condition described as hydraulic instability or impeller recirculationat some flow point below approximately 50 percent of the best efficiency point on the characteristic pump curve. These unsteady flow phenomena become progressively more pronounced if flow was further decreased, and could result in pump damage when operated for extended periods of time. The inspectors reviewed the licensee's responses to Bulletin 88-04, which were described in four letters to the NRC; one in1988, one in 1989, and two in 1990. The latter three responses were specific to the RCIC pump, where no concerns were identified by the inspectors.The inspectors identified two concerns with the licensee's 1988 response to the Bulletin:

The licensee did not properly verify the minimum flow settings with the pumpmanufacturer in accordance with what was stated in their response to the Bulletin. The licensee had concluded that the original, manufacturer-supplied minimum recirculation flows contained in the pump purchase specifications were adequate to meet the issues discussed in Bulletin 88-04. The licensee stated on page 2 of the response, "In all cases but one, theminimum flow capacities exceeded the values specified by the manufacturer.

The exception is the minimum flow capacity provided for the RCIC pump." The inspectors verified that the licensee had adequately addressed minimum flow for the RCIC pump. The inspectors requested documentation to establish the technical bases for the current minimum flow settings for the RHR, low pressure core spray (LPCS), and HPCS pumps, particularly how they accounted for flow instability. The licensee was unable to provide any documentation thataddressed this issue during the inspection. The adequacy of RHR, LPCS, andHPCS pumps' minimum flows was provided to the licensee by GE, as part of the original plant design, and since the licensee had been assigned these settings prior to Bulletin 88-04, it was likely that these settings did not account for flow instability considerations. With the exception of the RCIC pump, the inspectors 15concluded that the existing minimum flow settings for the safety-related pumpsaccounted only for thermal effects. The inspectors questioned whether the current minimum flow settings werereviewed and approved by the pumps' manufacturer (Byron-Jackson), asspecified in the licensee's response to the Bulletin. The licensee had not contacted the pump manufacturer and relied upon information provided by GE to conclude that no changes were needed for pumps in these three systems. Thelicensee contacted the pumps' manufacturer (now Flowserve) to perform a new analysis of the RHR, LPCS, and HPCS pumps' minimum flow settings inresponse to Bulletin 88-04. This issue was entered into the licensee's corrective action program as CR 06-00813.In the licensee's response to the Bulletin, it was stated "SOI/SVI procedurerevisions will be provided for those systems which do not presently containadequate caution. These cautions will limit pump minimum flow operation to amaximum of 30 minutes and assure that pump discharge is transferred to the full flow test line whenever possible." The licensee further stated that the review and approval of necessary procedure changes will be completed by October 5, 1988. When the inspectors reviewed the safety-related pump procedures, there was no evidence that any precautions related to minimum flow were ever implemented in the appropriate RHR, LPCS, or HPCS pump procedures. There were, however,precautions related to minimum flow incorporated into the RCIC pump procedure, which were considered appropriate by the inspectors. This issue was entered into the licensee's corrective action program as CR 06-00703 to determine if the 30 minute limitation still needed to be incorporated into therespective pump procedures.In response to these concerns, the inspectors prompted the licensee's engineeringdepartment to issue on March 2, 2006, a standing order to control room operators to be aware of the concerns for operation of safety-related pumps for extended periods of time while on minimum flow. Since operating a pump on minimum flow was considered a long-term degradation mechanism, issuance of the standing order provided confidence that the pumps would not be damaged prior to the pump manufacturer completing their analysis.As a result of the response to Bulletin 88-04, the RHR, LPCS, and HPCS pumps wereoperated since original plant start-up with an increased potential for unusual wear and aging. Based on the licensee's discussion with the pump manufacturer, the NRC concluded that additional review and evaluation were required to assess whether or not the licensee has established adequate minimum flow requirements for the RHR, LPCS,and HPCS pumps since they may operate at minimum flow conditions for extended periods of time under accident conditions. Therefore, this issue is considered an unresolved item (URI 05000440/2006009-03(DRS)) pending completion of an analysis to assess the pumps minimum flow requirements and subsequent NRC review.

16.5Modifications

a. Inspection Scope

The inspectors reviewed four permanent plant modifications related to the selected risksignificant components to verify that the design bases, licensing bases, and performance capability of the components have not been degraded throughmodifications. The Engineering Change Packages (ECPs) listed below were reviewed as part of this inspection effort:ECP 00-5013, "Safety-Related Upgrade of the ESW Sluice Gate SealingSystem";ECP 02-0283, "RCIC High Pressure Alarm Setpoint 1E51N0852"; ECP 03-0013, "High Pressure Core Spray Pump Breaker Modification"; andECP 04-0263, "Emergency Service Water (ESW) "C" Pump UpgradeModification (1P45C0002)."

b. Findings

No findings of significance were identified..6Risk Significant Operator Actions

a. Inspection Scope

The inspectors performed a margin assessment and detailed review of five risksignificant, time critical operator actions (5 samples). These actions were selected from the licensee's PRA rankings of human action importance based on risk achievement worth and Birnbaum values. Where possible, margins were determined by the review of the assumed design basis and USAR response times and performance times documented by job performance measures results. For the selected operator actions, the inspectors performed a walk through of associated procedures with a plant operator to assess operator knowledge level, adequacy of procedures, and availability of specialequipment where required. The following operator actions were reviewed:*Actions to terminate and prevent injection into the reactor pressure vessel (RPV)during an anticipated transient without scram (ATWS);*Actions to prepare for injection into the RPV during an ATWS;

  • Actions to initiate suppression pool cooling.

b. Findings

One finding of very low safety significance associated with a NCV was identified. b.1Inadequate Procedures for Controlling Flow into Reactor VesselIntroduction: The inspectors identified a NCV of Technical Specification 5.4.1, havingvery low safety significance (Green), for failing to maintain adequate procedures and/orinstructions for controlling injection into the reactor pressure vessel under conditions where the reactor would not shutdown without relying on the injection of boron.Description: Plant Emergency Instruction (PEI) flowcharts (RPV Control - ATWS andRPV Flooding) align low pressure coolant injection (LPCI) to inject through the RHR shutdown cooling return path (outside the shroud injection) to control either reactor water level or reactor pressure under conditions when the reactor was not shutdown without relying on the injection of boron. Procedures PEI-SPI 6.1(6.2), "LPCI A(B)

Outside the Shroud Injection," provided the necessary instructions for controlling thisinjection flow-path. These procedures were revised in January of 2003 to address corrective actions specified by CR 01-02848. The corrective actions were meant to address the incorrect assumption in Calculation EPGSAG-WS10, "RPV Variables," that the RHR pump minimum flow valves would be closed over the range of reactorpressures used in the calculation. To address this issue, the procedures established a flow band, with a minimum value of 2100 gallons per minute (gpm) to ensure the pumps' minimum flow requirement was met with the minimum flow valves closed, and a maximum value (dependent on whether the flow path was through the RHR heatexchanger or not) of either 7800 or 8500 gpm. There were no provisions in the procedure for reducing flow below 2100 gpm. The establishment of a minimum injection flow rate of 2100 gpm forced the operator intoan "on/off" level control strategy that would lead the operator to terminate flow when flowrates less than 2100 gpm were needed (e.g., RPV level or pressure was at the top of the desired control band) and reestablish flow when RPV level approached -25 inches or RPV pressure approached the minimum steam cooling pressure. This stopping and restarting of injection flow could cause rapid changes in the temperature of the coolant entering the core region, thus increasing the potential for large power excursions thatcould damage the fuel. The BWR Owner's Group Emergency Procedure and Severe Accident Guidelines as well as the Perry Specific Technical Guidelines specify that injection, into a reactor that is not shutdown without relying on boron injection, must becontrolled so as to minimize boron dilution and changes in core inlet subcooling, thus preventing the undesirable consequences of large power excursions. By allowing a continuous injection at flow rates that would maintain RPV water level in the desired level band, colder water entering the RPV would mix with the warmer water in the region outside the shroud. This slow, relatively constant injection rate would minimize the temperature changes of the water entering the core region thus preventing large powerexcursions.Analysis: The inspectors determined that the establishment of a minimum injection flowrate, contrary to both the Boiling Water Reactor (BWR) Owner's Group Emergency Procedure and Severe Accident Guidelines as well as the Perry Specific Technical Guidelines, was a performance deficiency and a finding. The inspectors determined 18that the finding was more than minor in accordance with IMC 0612, Appendix B, "IssueDispositioning Screening," because it was associated with the attribute of procedure quality, which affected the mitigating systems cornerstone objective of ensuring theability of the licensee to use the LPCI sub-systems to prevent undesirableconsequences associated with an ATWS. Specifically, the procedure's "on/off" level control strategy may not prevent large power excursions caused by rapid changes in the temperature of the coolant entering the core region.The inspectors evaluated the finding using IMC 0609, "Significance DeterminationProcess," Appendix A, "Significance Determination of Reactor Inspection Findings for At-Power Situations," Phase 1 screening, and determined that the finding screened asGreen because it was not a design issue resulting in loss of function per Part 9900, Technical Guidance, did not represent an actual loss of a system's safety function, didnot result in exceeding a TS allowed outage time, and did not affect external event mitigation.Enforcement: Technical Specification 5.4.1, required, in part, that writtenprocedures/instructions be established, implemented, and maintained covering the emergency operating procedures required to implement the requirements of NUREG-0737, "Clarification of TMI Action Plan Requirements," and NUREG-0737,Supplement 1. The BWR Owner's Group Emergency Procedure and Severe Accident Guidelines as well as the Perry Specific Technical Guidelines specify that injection, into a reactor that is not shutdown without relying on boron injection, must be controlled soas to minimize boron dilution and changes in core inlet subcooling, thus preventing the undesirable consequences of large power excursions. Contrary to the above, in January of 2003, the licensee revised the procedures andinstructions for controlling injection into the reactor pressure vessel under conditions where the reactor is not shutdown without relying on the injection of boron by establishing a level control strategy that did not minimize changes in core inlet subcooling, thus increasing the potential for large power excursions that could damagethe fuel. Because this violation was determined to be of very low safety significance and it was entered into the licensee's corrective action program, this violation is being treated as a NCV, consistent with Section VI.A of the NRC Enforcement Policy (NCV 05000440/2006009-04). The licensee entered the finding into their corrective action program as CR 06-00872 to assess the affected documents.

OTHER ACTIVITIES (OA)

4OA2Problem Identification and Resolution.1Review of Condition Reports

a. Inspection Scope

The inspectors reviewed a sample of the selected component problems that wereidentified by the licensee and entered into the corrective action program. The inspectors reviewed these issues to verify an appropriate threshold for identifying issues and to evaluate the effectiveness of corrective actions related to design issues. In addition, condition reports written on issues identified during the inspection were reviewed to 19verify adequate problem identification and incorporation of the problem into thecorrective action program. The specific corrective action documents that were sampled and reviewed by the inspectors are listed in the attachment to this report.

b. Findings

No findings of significance were identified.4OA6Meetings, Including Exits.1Exit MeetingThe inspectors presented the inspection results to Mr. W. Pearce and other members oflicensee management at the conclusion of the inspection on March 3, 2006, and withMr. J. Shaw on March 23, 2006. Proprietary information was reviewed during the inspection and will be handled in accordance with NRC policy.4OA7Licensee-Identified ViolationsThe following violation of very low safety significance (Green) was identified by thelicensee and is a violation of NRC requirements which meet the criteria of Section VI ofthe NRC Enforcement Policy, NUREG-1600, for being dispositioned as an NCV. Cornerstone: Mitigating Systems Criterion III, "Design Control," of 10 CFR Part 50, Appendix B requires, in part, thatmeasures shall be established to assure that applicable regulatory requirements and the design basis are correctly translated into specifications, drawings, procedures, and instructions. The licensee did not adequately translate design basis information into a HPCS system calculation. Specifically, Calculation E22-029, "SVI-E22-T2001- HPCSPump Performance Test Acceptance Criteria," had an error in its methodology as the latest revision of the calculation did not properly account for the Division III, dieselgenerator governor +/- 2 percent droop adjustment (frequency). The licensee failed to consider how the frequency adjustment could affect the design and licensing basis of the HPCS pump's capability to perform under reduced DG frequency. This wasidentified in the licensee's corrective action program as CR 06-00184 and CR 06-00296.

The inspectors reviewed the licensee's operability determination and verified that theHPCS pump remained capable of performing its design function. The inspectors determined that the finding was more than minor because if the licensee had notrecognized the error, the pump could have degraded below its' design requirement. The inspectors determined that the finding was of very low safety significance because it did not represent an actual loss of system safety function since the HPCS pump met its design requirement.ATTACHMENT:

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

W. Pearce, Site Vice President
P. Chatterjee, Electrical Engineer
H. Conrad, Nuclear Engineer
D. Gartner, Lead Instrumentation Engineer
J. Hagan, Senior Vice President Operations
T. Hilston, Design Engineering Supervisor
K. Howard, Design Engineering Manager
D. Jondle, Probabilistic Risk Assessment
J. Lausberg, Regulatory Compliance Manager
D. Pace, Senior Vice President Engineering
J. Powers, Fleet Engineering Director
J. Rinckel, Vice president Oversight
K. Russell, Regulatory Compliance
J. Shaw, Engineering Director
S. Seman, NSSS Supervisor
R. Siembor, Mechanical Engineer
J. Tufts, Operations Superintendent
F. Von Ahn, Plant Manager
J. Zarea, Lead Electrical EngineerNuclear Regulatory Commission
C. Pederson, Director, Division of Reactor Safety
A. M. Stone, Chief, Engineering Branch 2, DRS
R. Powell, Senior Resident Inspector
M. Franke, Resident Inspector

2

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000440/2006009-01NCVADS and MSIV Air Accumulators Stress AnalysisDeficiencies (Section 1R21.3.b.1)05000440/2006009-02NCVNon-conservative Safety-Related Air Storage Tank SizingCalculation (Section 1R21.3.b.2)05000440/2006009-03URIInadequate Response for Minimum Pump Flow Settings(Section 1R21.4.b.1)05000440/2006009-04NCVInadequate Procedures for Controlling Flow into ReactorVessel (Section 1R21.6.b.1)

Closed

05000440/2006009-01NCVADS and MSIV Air Accumulators Stress AnalysisDeficiencies (Section 1R21.3.b.1)05000440/2006009-02NCVNon-conservative Safety-Related Air Storage Tank SizingCalculation (Section 1R21.3.b.2)05000440/2006009-04NCVInadequate Procedures for Controlling Flow into ReactorVessel (Section 1R21.6.b.1)

3

LIST OF DOCUMENTS REVIEWED

The following is a list of licensee documents reviewed during the inspection, includingdocuments prepared by others for the licensee.

Inclusion on this list does not imply that NRCinspectors reviewed the documents in their entirety, but rather that selected sections or portionsof the documents were evaluated as part of the overall inspection effort.
Inclusion of a