IR 05000440/2022010

From kanterella
Jump to navigation Jump to search
Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000440/2022010
ML22272A058
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 09/29/2022
From: Richard Skokowski
NRC/RGN-III/DORS
To: Penfield R
Energy Harbor Nuclear Corp
References
IR 2022010
Download: ML22272A058 (10)


Text

SUBJECT:

PERRY NUCLEAR POWER PLANT - TRIENNIAL INSPECTION OF EVALUATION OF CHANGES, TESTS AND EXPERIMENTS BASELINE INSPECTION REPORT 05000440/2022010

Dear Mr. Penfield:

On September 22, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Perry Nuclear Power Plant and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Richard A. Skokowski, Chief Engineering Branch 2 Division of Operating Reactor Safety Docket No. 05000440 License No. NPF-58

Enclosure:

As stated

Inspection Report

Docket Number:

05000440

License Number:

NPF-58

Report Number:

05000440/2022010

Enterprise Identifier:

I-2022-010-0051

Licensee:

Energy Harbor Nuclear Corp.

Facility:

Perry Nuclear Power Plant

Location:

Perry, OH

Inspection Dates:

September 19, 2022 to September 22, 2022

Inspectors:

M. Abuhamdan, Reactor Inspector

J. Bozga, Senior Reactor Inspector

E. Magnuson, Reactor Inspector

Approved By:

Richard A. Skokowski, Chief

Engineering Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial inspection of evaluation of changes, tests and experiments baseline inspection at Perry Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.17T - Evaluations of Changes, Tests, and Experiments Sample Selection (IP Section 02.01)

The inspectors reviewed the following evaluations, screenings, and/or applicability determinations for Title 10 of the Code of Federal Regulations (10 CFR) 50.59 from June 2019 thru September 2022.

(1) Evaluation: 21-01636, Off Gas Vault Refrigeration System Abandonment Project
(2) Evaluation: 19-01265, Manual Lockout Switch for Main Turbine Mechanical and Electrical Trips
(3) Evaluation: 19-01015, MSIV closure
(4) Screening: 19-00119, Evaluation of Calculations that Previously Used a Higher than Minimum Specified Design Concrete Compressive Strength
(5) Screening: 21-01037, SIPE (Structural Integrity Pipe Evaluation) Software, Version 4.01 / RFCA PY20210126
(6) Screening: 19-01535, Calculation Updates Associated with ECP 18-0087
(7) Screening: 20-00337, Installation of Hilti Drop-In Anchors
(8) Screening: 20-00212, Swap Dryer and Separator in Upper Pool
(9) Screening: 20-00327, Miscellaneous pipe support calculations for replacement of PSA Mechanical Snubbers with Lisega Hydraulic Snubbers
(10) Screening: 20-00380, Analysis E12G010C Evaluation of Temporary Lead Shielding
(11) Screening: 19-01544, Interim Flooding Protection for Plant Structures - Ground Level Vulnerabilities
(12) Screening: 19-01415, Temporary Roof Protection for Flood Mitigation
(13) Screening: 19-01689, Roof Modifications to Handle PMP, EC 18-0072-001
(14) Screening: 22-00914, RHR System Heat Exchanger "B" Loop Performance Test Evaluation
(15) Screening: 19-02205, 1G33F0039 Valve Replacement
(16) Screening: 22-00595, Evaluation of Required Minimum Thickness of Partition Plate for Division 3 DG Jacket Water Heat Exchanger,1E22B5002
(17) Screening: 14-04299, Transfer Security Loads to Unit 2 480 Volt Power Supply
(18) Screening: 13-03461, Installation of isolation valves and appendages on P52 instrument air piping inside drywell to isolate MSIV accumulators - 1 B21A0001A/B/C/D and SRV accumulators - 1 B21A0004R/N/G/K/C/D/H/M/S/J
(19) Screening: 22-00639, Replace Unit 1 and Unit 2 TSC UPS Units and Install Additional Batteries
(20) Screening: 21-01727, Diesel Generator Fuel Oil Storage Tank Level Instrumentation Upgrade
(21) Screening: 20-01006, Exclude Vehicle Barrier System's vehicle arrest gates from design control

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On September 22, 2022, the inspectors presented the triennial inspection of evaluation of changes, tests and experiments baseline inspection results to Mr. R. Penfield, Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1:14.01.18

Evaluation of Calculations that Previously Used a Higher

than Minimum Specified Design Concrete Compressive

Strength

1C41-A00 1-0004

Structural Qualification 1C41-A001-004

Addendum

1C41-A001-0001

Structural Qualification 1C41-A001-001

Addendum

1C41-A001-0002

Structural Qualification 1C41-A001-002

Addendum

1C41-A001-0003

Structural Qualification 1C41-A001-003

Addendum

1H51-P1377-OD

Johnson Controls Incorporated Installation/Fabrication

1H51-P1377-0D

Addendum

1H51-P1378-OD

Johnson Controls Incorporated Installation/Fabrication

1H51-P1378-0D

Addendum

1N27G006A A-01

Pipe Stress Analysis of Feedwater System

3.1.2.1

Normal Operation Offgas System Releases

3.2.15.11

MSIV Closure

3.2.15.2.1

Control Rod Drop Accident Radiological Analysis Using

Alternative Source Terms

3.2.15.2.1

Control Rod Drop Accident Radiological Analysis Using

Alternative Source Terms

3.2.15.2.1 A-03

Control Rod Drop Accident Radiological Analysis Using

Alternative Source Terms

50:26.000

EVALUATION OF ROOF DRAIN CAPACITY

50:65.000

Evaluation of Structural Roof Capacity for USAR Described

PMP Event

50:65.000 A-02

Evaluation of Safety Structure Roof Scupper Capacity and

Membrane Capability for USAR Described PMP Event

50:87.000

PNPP Local Intense Precipitation Study Calculation

71111.17T

Calculations

E12-089

Required ESW Flow for the RHR HXs

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

E12-102

RHR System Heat Exchanger "B" Loop Performance Test

Evaluation

E12-102

RHR System Heat Exchanger "B" Loop Performance Test

Evaluation

E22-037

Design Basis Heat Load & Required ESW Flow for the

HPCS DGJW HX

E22-046

Evaluation of Required Minimum Thickness of Partition Plate

for Division 3 DG Jacket Water Heat Exchanger, 1E22B5002

EA-0084

Analysis E12G010C Evaluation of Temporary Lead Shielding

Addendum

ECA-017

Environmental Conditions Analysis OGB

G33-026 A-07

Proto-Flo Model of RWCU

M52-002

TSC-UPS Battery Room/ Electrical Equipment Area Cooling

and Heating Load Calculations

MOV Report

1G33F0039-007

MOV Report for replacement RWCU Valve 1G33F0039

MOVC-0076

EPRI PPM Thrust Calculation for MOVs 1E51F0063 and

1E51F0064

X0449

Johnson Controls Incorporated Installation/Fabrication

1H51-P1377-00

Addendum

X0450

Johnson Controls Incorporated Installation/Fabrication

1H51-P1378

Addendum

2019-01050

Issues with Motor Received for RWCU Containment Isolation

Gate Valve/Actuator Replacement

2/05/2019

2019-01050

ECP 18-0081 for G33F0039 Requires Revision

2/04/2019

22-03894

Division III Emergency Diesel Generator Jacket Water Heat

Exchanger Partition Plate Thickness Degradation

05/06/2022

Corrective Action

Documents

22-04839

Service Building and TSC UPS Battery Room Fire Barrier

Discrepancies

06/14/2022

Corrective Action

Documents

Resulting from

Inspection

22-07010

22 NRC 50.59 Inspection - Minor Errors in Calculation

3.2.15.11, Rev. 1

09/15/2022

Engineering

2-0214-002

Installation of Isolation Valves and Appendages on P52

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Instrument Air Piping Inside Drywell to Isolate MSIV

Accumulatio-1B21A001A, 1B21A001C and SRV

Accumulators 1B21A004R, 1B21A004N, 1B21A004G,

1B21A004K and 1B21A004C

18-0072-001

Roof Modifications to Handle PMP

19-0155-000

Installation of Flood Barriers at Plant Doors

19-0173-001

Manual Lockout Switch for Main Turbine Mechanical and

Electrical Trips

19-0178-001

Interim Flooding Protection for Plant Structures - Ground

Level Vulnerabilities

19-0178-002

Temporary Protection for Roof Water Levels During Probable

Maximum Precipitation

19-0178-006

Restoration for Protection for Roof Water Levels During

Probable Maximum Precipitation

19-0246-001

1G33F0039 Valve Replacement

21-0154-001

Replace both TSC UPS Units

21-0174-001

Off Gas Vault Refrigeration System Abandonment Project

21-0192

Diesel Fuel Oil Storage Tank Level Instrumentation Upgrade

DEER 14-01-01

Transfer Security Loads to Unit 2 480 Volt Power Supply

DEER 20-01-01

Exclude Vehicle Barrier System's Vehicle Arrest Gates From

Design Control

Changes

DSDS-35

RWCU Motor Operated Containment Isolation Gate Valve

Safety Related 6 lnch ASME Class 2

0079-0236-Calc-

2

Installation Verification Calculation for Version 4.0 of the

EPRI PPM Software, Computer Service Tag No. G5J0NV2

ASME 1974 Ed -

Sect III -

Division 1

ASME 1974 Ed - Sect III - Division 1, Rules for Construction

of Nuclear Power Plant Components, Subsection ND class 3

Components

1974 Ed

Commitment

L01916

ESW HEAT EXCHANGER TESTING FREQUENCY

11/11/2014

Miscellaneous

Docket No. 50-

440, PY-

CEI/NRR-1734L,

PY-CEI/NRR-

Perrys correspondence to GL89-13

04/08/1994,

03/01/1991,

01/26/1990

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

28L, and PY-

CEI/NRR-1121

L-19-068

Response to Request for Additional Information Regarding

Request for Deferral of Actions Related to Beyond-Design-

Basis External Events Flooding Actions

03/20/2019

NORM-ER-3420

Nuclear Operating Reference Material, Emergency Diesel

Generator

NORM-ER-3507

Nuclear Operating Reference Material, FENOC Heat

Exchangers

Operability

Evaluations

2015-08036

Prompt Functionality Assessment for Flooding Challenges

NOBP-SS-3140

Nuclear Operating Business Practice, Use of Digital

Signature

NOP-ER-2006

Service Water Reliability Management Program

PTI-E12-P0003

RHR Heat Exchangers B and D Performance Testing

PTI-E22-P0007

HPCS Diesel Generator Jacket Water Heat Exchanger

Performance Testing

Procedures

PTI-N32-P0001

Turbine Overspeed Protection Devices Trip Weekly Test

200415912

(4Y) HPCS Diesel Generator Jacket Water Heat Exchanger

Performance Testing

2/16/2010

200442907

(4Y) HPCS Diesel Generator Jacket Water Heat Exchanger

Performance Testing

05/12/2015

Work Orders

200645158

(4Y) HPCS Diesel Generator Jacket Water Heat Exchanger

Performance Testing

08/27/2019