IR 05000440/2021012

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Programs) Inspection Report 05000440/2021012
ML21273A047
Person / Time
Site: Perry 
Issue date: 09/30/2021
From: Karla Stoedter
NRC/RGN-III/DRS/EB2
To: Penfield R
Energy Harbor Nuclear Corp
References
IR 2021012
Download: ML21273A047 (24)


Text

SUBJECT:

PERRY NUCLEAR POWER PLANT - DESIGN BASIS ASSURANCE INSPECTION (PROGRAMS) INSPECTION REPORT 05000440/2021012

Dear Mr. Penfield:

On August 5, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Perry Nuclear Power Plant and discussed the results of this inspection with Ms. A. Zelaski, Plant General Manager (representing) and other members of your staff. The results of this inspection are documented in the enclosed report.

Three findings of very low safety significance (Green) are documented in this report. Three of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Perry Nuclear Power Plant.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Perry Nuclear Power Plant.

September 30, 2021 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Karla K. Stoedter, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 05000440 License No. NPF-58

Enclosure:

As stated

Inspection Report

Docket Number:

05000440

License Number:

NPF-58

Report Number:

05000440/2021012

Enterprise Identifier:

I-2021-012-0019

Licensee:

Energy Harbor Nuclear Corp.

Facility:

Perry Nuclear Power Plant

Location:

Perry, OH

Inspection Dates:

June 28, 2021 to August 05, 2021

Inspectors:

K. Barclay, Reactor Inspector

B. Daley, Senior Reactor Inspector

E. Sanchez Santiago, Senior Reactor Inspector

Approved By:

Karla K. Stoedter, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at Perry Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Perform Valve Stroke Time Testing in accordance with American Society of Mechanical Engineers Requirements Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000440/2021012-01 Open/Closed None (NPP)71111.21N.02 A self-revealed Green finding and associated non-cited violation of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, subsection 55a (f) was identified due to the licensee's failure to retest or declare reactor core isolation cooling valve 1E51-F019 inoperable, as required by the American Society of Mechanical Engineers (ASME) Code, following surveillance testing performed on July 24, 2018. Specifically, the licensee used an inappropriate method for calculating the valve stroke time which resulted in them incorrectly concluding the valve met the surveillance test acceptance criteria. The valve subsequently failed to open during next scheduled surveillance test performed on October 22, 2018.

Failure to Perform Surveillance Testing in accordance with the Required Frequency in the ASME OM Code Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000440/2021012-02 Open/Closed

[H.3] -

Change Management 71111.21N.02 The inspectors identified a finding and associated non-cited violation of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, subsection 55a (f) for the failure to perform stroke time testing on three reactor core isolation cooling valves in accordance with the frequency established in the ASME OM Code. Specifically, the licensee updated their probabilistic risk assessment (PRA) and did not update the inservice testing program to reflect changes in valve testing frequency caused by the PRA update. As a result, the licensee did not recognize the testing frequency for three RCIC valves, which also served as containment isolation valves, had changed from every two years to quarterly.

Failure to Establish a Program to Ensure Motor Operated Valves Continue to be Capable of Performing Their Design Basis Safety Functions Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000440/2021012-03 Open/Closed None (NPP)71111.21N.02 The inspectors identified a Green finding and associated NCV of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Subsection 55a(b)(3)(ii), for the licensees failure to establish a program that ensured the design basis safety functions of certain motor-operated valves (MOVs) would be met. Specifically, the licensee did not implement the Joint Owners Group MOV Periodic Verification Program in accordance with MPR-2524-A, Joint Owners Group (JOG) Motor Operated Valve Periodic Verification Program Summary, for reactor core isolation cooling steam supply isolation valves 1E51-F063 and 1E51-F064.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.21N.02 - Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements POV Review (IP Section 03)

For the valves listed below, the inspectors:

a.

Determined whether the sampled power operated valves (POVs) are being tested and maintained in accordance with NRC regulations along with the licensees commitments and/or licensing bases.

b.

Determined whether the sampled POVs are capable of performing their design-basis functions.

c.

Determined whether testing of the sampled POVs is adequate to demonstrate the capability of the POVs to perform their safety functions under design-basis conditions.

d.

Evaluated maintenance activities including a walkdown of the sampled POVs (if accessible).

(1)1B21-F028C, Main Steam Line 'C' Outboard Isolation Valve (2)1B21-F041B, Automatic Depressurization System Valve (3)1E22-F004, High Pressure Core Spray Injection Valve (4)1E22-F012, High Pressure Core Spray Pump Minimum Flow Valve (5)1E51-F019, Reactor Core Isolation Cooling Minimum Flow Valve (6)1E51-F063, Reactor Core Isolation Cooling Steam Supply Inboard Isolation Valve (7)1E12-F048A, Residual Heat Removal 'A' Heat Exchanger Bypass Valve (8)1P45-F130B, Essential Service Water Pump 'B' Discharge Valve

INSPECTION RESULTS

Failure to Perform Valve Stroke Time Testing in accordance with American Society of Mechanical Engineers Requirements Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000440/2021012-01 Open/Closed None (NPP)71111.21N.02 A self-revealed Green finding and associated non-cited violation of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, subsection 55a

(f) was identified due to the licensee's failure to retest or declare reactor core isolation cooling valve 1E51-F019 inoperable, as required by the American Society of Mechanical Engineers (ASME) Code, following surveillance testing performed on July 24, 2018. Specifically, the licensee used an inappropriate method for calculating the valve stroke time which resulted in them incorrectly concluding the valve met the surveillance test acceptance criteria. The valve subsequently failed to open during next scheduled surveillance test performed on October 22, 2018.
Description:

On July 24, 2018, the licensee performed surveillance test SVI-E51-T2001, "RCIC Pump and Valve Operability Test," Revision 42, on Reactor Core Isolation Cooling Pump Minimum Flow Valve 1E51-F0019. During the test, the valve was slow to start opening when the valve's control switch was taken to the open direction. The delayed valve response resulted in the valve's stroke time being unsatisfactory when measured with a stop watch. However, SVI-E51-T2001, Section 2.0, "Precautions and Limitations," Step 11 allowed the licensee to use a computer point to calculate the stroke time. This section specifically stated, "If the stroke time of a valve is unsatisfactory when using a stopwatch, ICS data may be used, if available. If this is done, write "ICS" in the initial power block (along with the initials), and determine the stroke time per PDB-C0010." The inspectors noted the licensee implemented Step 11 of the procedure and obtained a satisfactory valve stroke time. As a result, the licensee took no further action to address the valve's slow stroke time. This licensee documented the valve's delayed opening in corrective action document CR-2018-06590, "RCIC Min Flow Valve slow to open during the performance of SVI-E51-T2001."

Subsequently, on October 22, 2018, when performing the aforementioned procedure, valve 1E51-F019 failed to operate when operations personnel attempted to open the valve using the control switch. Per the surveillance procedure, the valve was declared inoperable, and the operators attempted to operate the valve a second time with the same results. The red pen light did not illuminate, and ICS received no open signal during both attempts to open the valve. Troubleshooting identified mechanical binding for the "open" contactor within the motor control center bucket. The licensee performed an apparent cause evaluation and determined the valve failure was due to a less than adequate preventive maintenance frequency that would lubricate the moving parts of the motor control center bucket. The licensee also determined that early identification of the valve's performance degradation did not occur because the use of ICS data to determine the valve's stroke time masked potential valve performance issues and performance trending for this valve was less than adequate.

During the inspection, the inspectors reviewed the surveillance procedure to determine whether the timing methodology used when the stopwatch stroke time was slow complied with regulatory requirements. The inspectors identified that using the ICS data as discussed in the procedure did not meet the requirements documented in the ASME OM Code.

Specifically ASME OM Code 2001, "Code for Operation and Maintenance of Nuclear Power Plants," Subsection ISTC, "Inservice Testing of Valves in Light Water Reactor Nuclear Power Plants," defined full stroke time as the time interval from the initiation of the actuating signal to the indication of the end of the operating stroke. The inspectors determined the ICS value measured the time the valve actually moved but did not capture the time that elapsed between the initiation signal and the beginning of valve movement. To account for the time ICS is unable to capture, the licensee applied a correction factor. The inspectors reviewed the basis for the correction factor and concluded the correction factor did not represent the actual time from initiation of the actuation signal to the start of valve movement. As a result, the use of ICS data to calculate valve stroke time could not be used to demonstrate compliance with the ASME Code inservice testing requirements.

For instances when the acceptance criteria is not met, ASME OM Code Subsection ISTC-5122, "Stroke Acceptance Criteria," stated, in part, "test results shall be compared to the initial reference values or reference values established in accordance with ISTC-3310 or ISTC-3320. ISTC-5123, "Stroke Test Corrective Action," paragraph (b), stated, in part, "valves with measured strokes times that do not meet the acceptance criteria of ISTC-5122 shall be immediately retested or declared inoperable. During the July 24, 2018, test, the licensee did not perform a retest or declare the valve inoperable in accordance with the aforementioned ASME OM Code requirements. This caused the licensee to fail to recognize a degraded condition that resulted in a subsequent failure of the valve to operate.

The inspectors communicated the failure to meet the ASME OM Code requirements to the licensee. They entered the issue into their corrective action program. The licensee had previously updated their procedure to eliminate the option to use an alternate method for calculating stroke times.

Corrective Actions: The licensee revised procedure SVI-E51-T2001, "RCIC Pump and Valve Operability Test," to eliminate Section 2.0 Step 11, which is the step that described the option to use an alternate method to calculate stoke times. The licensee was also performing a review to determine if additional actions needed to be taken as a result of the violation identified by the inspectors.

Corrective Action References: CR-2021-05197, "2021 DBAI POV Inspection:E51F0016 Stroke Time Testing Method for SVI-E51-T2001" CR-2018-06590, "RCIC Min Flow Valve slow to open during the performance of SVI-E51-T2001" CR-2018-09241, "E51-F0019 RCIC minimum flow valve failed to operate during SVI"

Performance Assessment:

Performance Deficiency: The licensee's failure to retest or declare reactor core isolation cooling valve 1E51-F019 inoperable after the stroke time exceeded the acceptance criteria was contrary to the requirements of 10 CFR 50.55a and the ASME OM Code. Specifically, the licensee did not use the correct stroke time value when comparing the test results to the acceptance criteria due to incorrect surveillance procedure guidance.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Procedure Quality attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to use the correct stroke time value caused the licensee to fail to take the required actions of either retesting the valve or declaring it inoperable when the acceptance criteria was not met. This slow stroke time represented a degraded condition which was not addressed until the valve failed surveillance testing in October 2018.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 2, "Mitigating Systems," the finding screened as having very low safety significance (Green)because the finding did not affect the design or qualification of a mitigating structure, system or component, did not represent a loss of a probabilistic risk assessment (PRA) function of a single train technical specification (TS) system for greater than its TS allowed outage time, did not represent a loss of the PRA function of two separate TS systems for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, did not represent a loss of a PRA system and/or function as defined in the plant risk information book or the licensee's PRA for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, and did not represent a loss of the PRA function of one or more non-TS trains of equipment designated as risk-significant in accordance with the licensee's maintenance rule program for greater than 3 days.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Title 10 CFR 50.55a Section (f), Preservice and Inservice Testing Requirements stated, in part, that systems and components of boiling and pressurized water-cooled nuclear power reactors must meet the requirements for preservice and inservice testing (referred to in this paragraph

(f) collectively as inservice testing) of the ASME BPV Code and ASME OM Code.

ASME OM Code 2001, Code for Operation and Maintenance of Nuclear Power Plants, Subsection ISTC, Inservice Testing of Valves in Light-Water Reactor Nuclear Power Plants, ISTC-2000 Supplemental Definitions, defines full-stroke time as the time interval from the initiation of the actuating signal to the indication of the end of the operating stoke.

ISTC-5122, Stoke Test Acceptance Criteria, states, in part, test results shall be compared to the initial reference values or reference values established in accordance with ISTC-3300, ISTC-3310, or ISTC-3320. ISTC-5122 (b), states, valves with reference stroke times of less than or equal to 10 seconds shall exhibit no more than a plus or minus 25 percent, nor plus or minus a 1 second change in stoke time, whichever is greater, when compared to the reference value.

ISTC-5123, Stroke Test Corrective Action, paragraph (b), states, in part, valves with measured stroke times that do not meet acceptance criteria of ISTC-5122 shall be immediately retested or declared inoperable.

Contrary to the above, on July 24, 2018, the licensee failed to meet the requirements for inservice testing of the ASME OM Code. Specifically, after valve 1E51-F019 failed to meet the acceptance criteria of ISTC-5122, the licensee failed to immediately retest it or declare it inoperable.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Perform Surveillance Testing in accordance with the Required Frequency in the ASME OM Code Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000440/2021012-02 Open/Closed

[H.3] - Change Management 71111.21N.02 The inspectors identified a finding and associated non-cited violation of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, subsection 55a

(f) for the failure to perform stroke time testing on three reactor core isolation cooling valves in accordance with the frequency established in the ASME OM Code. Specifically, the licensee updated their PRA and did not update the inservice testing program to reflect changes in valve testing frequency caused by the PRA update. As a result, the licensee did not recognize the testing frequency for three RCIC valves, which also served as containment isolation valves, had changed from every two years to quarterly.
Description:

During a review of completed surveillances for valve 1E51-F063, "Reactor Core Isolation Cooling Inboard Steam Supply Isolation Valve," the inspectors identified the licensee was not performing the surveillances at the correct frequency. In accordance with the latest revision of the licensee's PRA program completed on January 15th, 2020, this valve was classified as medium risk significance. Per the licensee's inservice testing program, all motor operated valves (MOVs) classified as medium and high PRA risk significant will be categorized as HSSC (high safety significant) to implement ASME OM Code 2012, Mandatory Appendix III, Subsection III-3720 requirements. Subparagraph III-3620(a) required consideration of more frequent test intervals for MOVs with high safety significance. The licensee's inservice test program implemented the Mandatory Appendix III, Subsection III-3720 requirements by assigning a quarterly surveillance testing frequency interval to HSSC valves. However, valve 1E51-F063 was being tested on a 24-month frequency.

The licensee determined the cause for failing to perform the surveillance testing at the correct frequency was because they failed to update their inservice testing program after the PRA was updated in January 2020. The licensee performed an extent of condition review and identified two additional valves with an incorrect surveillance frequency; 1E51-F064, "Reactor Core Isolation Cooling Steam Supply Outboard Isolation Valve," and 1E51-F068, "Reactor Core Isolation Cooling Turbine Exhaust Isolation Valve." All three valves were being stroke time tested at a 24-month frequency instead of quarterly. Valves 1E51-F063 and 1E51-F064 were last tested on April 1, 2021, and were within the quarterly surveillance test frequency when the inspectors identified this issue. However, the inspectors found previous tests for both valves were performed at greater than a quarterly frequency. The inspectors determined valve 1E51-F068 was last tested on January 21, 2020. The licensee immediately performed a stroke time test of 1E51-F068, verified the complete test for 1E51-F063 and 1E51-F064 had been performed, and determined all three valves were operable. The licensee entered this issue into their corrective action program and corrected the testing interval for the aforementioned valves.

Corrective Actions: The licensee performed stroke time testing of the valves that were outside of their required frequency. All impacted valves were determined to be operable based on successful completion of the surveillance requirements.

Corrective Action References: CR-2021-05254, "2021 DBAI POV Inspection: Valves 1E51F0063, 1E51F0064, 1E51F0068 Exercise and Stroke Time Requirements did not change from PRA update in 2020"

Performance Assessment:

Performance Deficiency: The licensee failed to update the valve test table in their inservice testing program plan when changes were made to the significance of the valves in the program. This resulted in the licensee failing to meet the testing frequency requirements of the ASME OM Code. Specifically, valves E51-F063, E51-F063 and E51-F068 were not tested on a quarterly basis for four to five consecutive quarters.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Procedure Quality attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, the licensee missed surveillance testing of three valves for four to five consecutive quarters. These valves were classified as high safety significance, therefore the failure to perform the surveillance testing at the correct periodicity affected the reasonable assurance the safety significant valves would perform their safety function.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 3, "Barrier Integrity," the finding screened as having very low safety significance (Green)because the finding did not represent an actual open pathway in the physical integrity of reactor containment; did not represent the failure of containment pressure control equipment; did not represent the failure of containment heat removal components; and did not involve the actual reduction in function of hydrogen igniters in the reactor containment.

Cross-Cutting Aspect: H.3 - Change Management: Leaders use a systematic process for evaluating and implementing change so that nuclear safety remains the overriding priority.

Specifically, when the licensee made changes to their PRA, they did not used a systematic approach to ensure the inservice testing program was updated as appropriate.

Enforcement:

Violation: Title 10 CFR 50.55a, Section (f), Preservice and Inservice Testing Requirements, states, in part, that systems and components of boiling and pressurized water-cooled nuclear power reactors must meet the requirements for preservice and inservice testing (referred to in this paragraph

(f) collectively as inservice testing) of the ASME BPV Code and ASME OM Code.

ASME OM Code 2012,"Code for Operation and Maintenance of Nuclear Power Plants,"

Mandatory Appendix III, "Preservice and Inservice Testing of Active Electric Motor Operated Valve Assemblies in Light-Water Reactor Power Plants," Section III-3721, "HSSC MOVs,"

stated, HSSC MOVs shall be tested in accordance with paragraph III-3300. Section III-3600, "MOV Exercising Requirements," states, HSSC MOVs that can be operated during plant operation shall be exercised quarterly, unless the potential increase in core damage frequency and large early release associated with a longer exercise interval is small.

Contrary to the above, from January 2020, the licensee failed to meet the requirements for inservice testing of the ASME OM Code. Specifically, for HSSC valves E51-F063 and E51-F064, the licensee performed an exercise test on January 31, 2020, but did not exercise these valves again until April 8, 2021, which exceeded the quarterly testing requirement. For HSSC valve E51-F068, the licensee performed an exercise test on January 31, 2020, but did not exercise this valve again until July 9, 2021, which exceeded the quarterly testing requirement.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Establish a Program to Ensure Motor Operated Valves Continue to be Capable of Performing Their Design Basis Safety Functions Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000440/2021012-03 Open/Closed None (NPP)71111.21N.02 The inspectors identified a Green finding and associated NCV of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Subsection 55a(b)(3)(ii), for the licensees failure to establish a program that ensured the design basis safety functions of certain motor-operated valves (MOVs) would be met. Specifically, the licensee did not implement the Joint Owners Group MOV Periodic Verification Program in accordance with MPR-2524-A, Joint Owners Group (JOG) Motor Operated Valve Periodic Verification Program Summary, for reactor core isolation cooling steam supply isolation valves 1E51-F063 and 1E51-F064.

Description:

During the inspection, the inspectors reviewed Calculation MOVC-0076, Revision 0, which performed an Electric Power Research Institute (EPRI) Performance Prediction Methodology (PPM) Evaluation for valves 1E51-F063 and 1E51-F064 to determine the predicted thrust necessary to close the valve under steam blowdown conditions. The inspectors found that the EPRI PPM software had issued a Type 1 damage warning because the disk seat design radius for both valves did not meet the minimum EPRI PPM default radius.

EPRI TR-103237-R1-T1 (Non-Proprietary Version), "EPRI MOV Performance Prediction Program," states the following about a Type 1 Warning, The conditions at the interface are likely to produce material damage, and the friction coefficient cannot be reliably bounded. Although thrust results are generated by the model to carry the calculation to completion, the valve is considered to be unpredictable at all subsequent stroke positions. Type 1 warnings are only generated for contacts involving a Stellite sharp edge above the appropriate load thresholds.

The licensee adjusted the disk seat design radius inputs for both valves to meet the minimum EPRI PPM default radius and clear the errors. The licensee credited valve 1E51-F063 with the minimum radius because it had previously closed against a reduced differential pressure during performance testing conducted in October 1987. The licensees review of EPRI TR-103255, "July 1994 EPRI Gate Valve Design Effects Testing Results Report," found that stroking an MOV under reduced differential pressure and flow conditions will tend to chamfer the sharp edges. The inspectors review did not identify a similar reduced differential pressure test for valve 1E51-F0064, and Calculation MOVC-0076 provided no basis for changing the disk seat design radius inputs to clear the Type 1 error.

TR-103244, "EPRI MOV PPM Implementation Guide," Revision 1, which incorporated the Agencys Safety Evaluation comments for the EPRI PPM program, provided instructions for handling a Type 1 damage warning error. Specifically, TR-103244 provided corrective options which included performing a design basis test of the valve or modifying the valve and increasing the chamfer or radii. Crediting a past valve cycling with rounding of the sharp edges was not listed as an acceptable option for correcting a Type 1 error.

The inspectors found the unpredictable EPRI MOV PPM results were carried forward into the JOG MOV program for gate valves 1E51-F063 and 1E51-F064. Specifically, MPR-2524-A, Chapter 7, Implementation of JOG MOV Periodic Verification Approach, Step 5, Coefficient of Friction Threshold Screen, evaluates to determine if the valve is set up using a coefficient of friction (COF) that is susceptible to increase. For each combination of disk-to-seat material and fluid type tested in the JOG Program, a threshold COF is determined. The threshold is the value above which the COF does not increase, based on testing in the JOG MOV PV Program. Valves that are set up (and margin evaluated) using a COF greater than or equal to the applicable threshold COF are not susceptible to degradation and can be classified as a Class A or B, subject to inputs in previous steps. Valves that are set up using a COF less than the applicable threshold COF are susceptible to increases and are classified as Class C.

Perry used the unpredictable results from the EPRI PPM evaluation to calculate a COF and justify a Class A classification for 1E51-F063 and 1E51-F064. The inspectors, in consultation with the Office of Nuclear Reactor Regulation (NRR) mechanical engineers and MOV specialists, concluded the Class A classification was not appropriate because the valves did not have a valid COF. Specifically, the valves had never been tested at the design differential pressure and the EPRI PPM results were unpredictable and not a valid input for the JOG MOV PV Program.

The licensee performed an operability determination and concluded valves 1E51-F063 and 1E51-F064 remained capable of closing during a high energy line break event. Specifically, the licensee used engineering judgment to determine component wear for the period of time the valves have been installed and informed their conclusions by using wear chamfering data gathered during a 2003 valve maintenance evolution on 1E51-F064. The inspectors did not identify any deficiencies associated with the overall conclusions of the operability determination.

Corrective Actions: The licensee entered the issue into their corrective action program, performed an operability determination, and created corrective action assignments to inspect and / or remove sharp edges from 1E51-F063 and 1E51-F064 during their next refueling outage.

Corrective Action References: CR-2021-05435, "2021 DBAI POV Inspection: JOG Classification of RCIC Steam Supply Isolation Valves" CR-2021-05408, "2021 DBAI POV Inspection: RCIC Steam Supply Isolation Valves Questionable Calculation Justification"

Performance Assessment:

Performance Deficiency: The licensees use of unpredictable EPRI PPM results for the RCIC steam supply isolation valves was contrary to the JOG MOV PV Program and was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the inspectors concluded that there was reasonable doubt regarding the availability, reliability or capability of the RCIC valves because the licensee was required to use a different approach while performing the operability determination. The inspectors compared the finding with the examples listed in IMC 0612, Power Reactor Inspection Reports, Appendix E, Example of Minor Issues. Example 3.m was found to be similar in that the licensee was not applying justified assumptions when performing a calculation. The example concluded that the reasonable doubt standard was met, when, through the process of completing an operability determination, the licensee used a different approach because the original approach resulted in unfavorable margin. For this finding, Perry needed to use engineering judgement associated with valve wear, instead of the original valve dimensions, until maintenance can be performed during the next refueling outage.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 2, "Mitigating Systems," the finding screened as having very low safety significance (Green)because the finding did not affect the design or qualification of a mitigating SSC, did not represent a loss of the PRA function of a single train TS system for greater than its TS allowed outage time, did not represent a loss of the PRA function of two separate TS systems for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, did not represent a loss of a PRA system and/or function as defined in the PRIB or the licensee's PRA for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, and did not represent a loss of the PRA function of one or more non TS trains of equipment designated as risk-significant in accordance with the licensee's maintenance rule program for greater than 3 days.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Title 10 of the Code of Federal Regulations (10 CFR), subsection 50.55a(b)(3)(ii)required, in part, that licensees must establish a program to ensure that MOVs continue to be capable of performing their design basis safety functions.

Contrary to the above, as of July 16, 2021, the licensee did not establish a program that ensured MOVs were capable of performing their design basis safety functions. Specifically, the licensee did not follow the requirements of the Joint Owners Group MOV Periodic Verification Program to properly classify RCIC Valves 1E51-F063 and 1E51-F064, which have a design basis safety function to close in the event of a high energy line break on the steam supply line to the RCIC turbine. Proper valve classification is necessary to determine the appropriate test type and frequency to ensure the valves are capable of performing all their design basis safety functions. The licensee classified the valve as Class A when they did not meet the criteria for this classification.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On August 5, 2021, the inspectors presented the design basis assurance inspection (programs) inspection results to Ms. A. Zelaski, Plant General Manager (representing)and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2-0030-00000

Environmental Conditions for Drywell Area

K

93C1805.06-01

Evaluation of Seat Ring for Valves 1E12-F0048A and B

for Indicated Overthrust Condition

AOV-8

Determination of Valve Required Thrust, Actuator

Capability and Margin for AOVs: 1B21F0028A, B, C & D

B21-008

MSIV Air Closure per SIL 477

B21-025

Inboard/Outboard MSIV Stroke Time Acceptance Criteria

CL-MOV-1E51-1

MOV 1E51-F063/F064 Maximum Differential Pressure

CLMOV-3

Generic Letter 89-10 Program

E51-028

RCIC Pump Minimum Flow Requirements

2/08/1999

EQ-008

Limitorque D.C. Actuator-EQ Life Analysis

EQ-030

Qualified Life at 145 Degrees F Continuous in Drywell

& 1 A-01

EQ-128

MSIV NAMCO Limit Switch EQ Life Analysis

EQ-168

Extend Limitorque Containment Qualification to 180 Days

& 1 A-01

FSPC-0019

Division 2 AC Motor Operated Valve (MOV) Power Fuse

Sizing

FSPC-0019 A-04

Division 2 MOV Power Fuse Determination

MOV1E51-03

1E51-F010, F013, F019, F022, F031, F059, F068, F077 &

F078 Maximum Differential Pressure

2, 2.5 & 2.7

MOVC-0029

DC MOV Torque Capability Using Limitorque and BWR

Owner's Group Methodology

& 5

Addendum 2

MOVC-0044

Required Thrust Calculation for Globe Motor Operated

Valves (MOVs)

2/19/2001

MOVC-0063

Required Torque/Thrust Calculation for Edward

(Rockwell) Globe Valves

MOVC-0076

EPRI PPM Evaluation of Borg-Warner 10" ANSI Class

1500 Flex Wedge Gate Valves 1E51F0063/64

& 0.1

PSTG-0001

PNPP Class 1E Power Distribution System Voltage Study

SQ-0015

Qualification of Valves 1E51-F063, 1E51-F064

1, 1 A-01,

DCC 2 &

DCC 3

71111.21N.02

Calculations

SQ-0049

Motor Operated Valve 1E51-F0019 Qualification

2, 2.1, 2.2 &

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

A-01

TAF-81565 Scan

Pressure Locking and thermal Binding of Gate Valves

2/05/2000

TAF-81565 Scan

Pressure Locking and Thermal Binding of Gate Valves

2/23/1993

CR 2012-01789

Two MSIV Failed Stroke Time Testing

03/13/2021

CR 2017-02721

MSIV Stroke per SVI

03/11/2017

CR 2017-06730

Updated Industry Guidance to Address Part 21 Issue with

Anchor Darling Double Disc Gate Valves

06/20/2017

CR 2018-05939

NRC EQ DBAI: Accounting for Heat Rise in EQ

Component Evaluation

06/28/2018

CR 2018-10269

Reactor Core Isolation Cooling Mitigating Systems

Performance Index Basis Document & Probabilistic Risk

Analysis Model Inaccuracy

11/16/2018

CR 2019-02398

MSIV Stroke Times Unsat

03/16/2019

CR 2020-07503

Level 4 Worker Protection Event CP-4.1.3 Clearance

Development Milestone not Met

09/27/2020

Corrective Action

Documents

CR 2021-02297

SBI-B21-T9000 Acceptance Criteria

03/27/2021

CR 2021-05077

21 DBAI POV Inspection: Grease Spot from Valve

Lubricant on Insulation

06/30/2021

CR 2021-05097

21 DBAI POV Inspection: NRC Walkdown - Proximity

to Handwheel for 1E12F0048A to Scaffold Pole

06/30/2021

CR 2021-05151

21 DBAI POV Inspection: NOP-ER-3204 Misalignment

with ISTP for Perry

07/06/2021

CR 2021-05169

21 DBAI POV Inspection: Corrective Maintenance

Documentation for MSIV Stroke Times from 2017

07/07/2021

CR 2021-05197

21 DBAI POV Inspection: E51F0019 Stroke Time

Testing Method for SVI-E51-T2001

07/07/2021

CR 2021-05254

21 DBAI POV Inspection: Valves 1E51F0063,

1E51F0064, 1E51F0068 Exercise and Stroke Time

Requirements did not Change from PRA Update in 2020

07/09/2021

CR 2021-05375

21 DBAI POV Inspection: Calculation SQ-0049 Normal

Close Thrust Value for Diaphragm Disk

07/14/2021

Corrective Action

Documents

Resulting from

Inspection

CR 2021-05408

21 DBAI POV Inspection: RCIC Steam Supply Isolation

07/15/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Valves Questionable Calculation Justification

CR 2021-05410

21 DBAI POV Inspection: PSTG-0001 not Updated

from PERP that Change MOV Motor

07/15/2021

CR 2021-05435

The Basis for Classification of the RCIC Steam Supply

Isolation Valves 1E51F0063 (Inboard) and 1E51F0064

(Outboard) for the Joint Owners Group Program on Motor

Operated Valve Periodic Verification (JOG) will Need to

be Reviewed against the Resolution of the Calculation

Issue Documented by CR 2021-05408 2021 DBAI POV

Inspection: RCIC Steam Supply Isolation Valves

Questionable Calculation Justification

07/16/2021

CR 2021-5067

21 DBAI POV Inspection: Housekeeping Deficiencies in

RHR A HX Room

06/30/2021

2-0004-00000

Environmental Conditions for Auxiliary Building

L

206-0051-00000

Class 1E DC System

DDD

208-0065-00014

High Pressure Core Spray System Pump Injection Shutoff

MOV F004

R

208-0075-00016

Reactor Core Isolation Cooling System Minimum Flow to

Suppression Pool MOV F0019

U

208-0075-00024

Reactor Core Iso Cooling System Stm Sply Line Iso Inbrd

Valve F063

CC

235-0075-00003A

MOV Data Sheet - 1E51F019 Min. Flow to Suppression

Pool

G

235-0075-00003B

MOV Data Sheet 1E51-F0019

235-0075-00009A

MOV Data Sheet - 1E51F063 RCIC Steam Supply

Inboard Isolation Valve

L

2-0631-00000

Reactor Core Isolation Cooling System

HH

2-0632-00000

Reactor Core Isolation Cooling System

LL

40-0426-00003

Motor Operated Valve Assembly Gate 10 inch,

1500 LB-CS

A

4549-40-1047

Sheet 7

2" 900# Globe Valve Assembly

1A

Drawings

4549-40-1047

Sheet 8

Valve Assembly

0A

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4549-40-1049

Sheet 1

Valve Assembly

A

DCC 01 SQ-0049

Design Control Change to SQ-0049: Motor Operated

Valve 1E51-F0019 Qualification, R 2

07/09/1996

11-0328-000

Replacement of the Carbon Steel 1E51F0019 RCIC

Minimum Flow Line Valve with a Stainless Steel Valve

11-0328-001

Replacement of the Carbon Steel 1E51F0019 RCIC

Minimum Flow Line Valve with a Stainless Steel Valve

DCC 02 SQ-0049

Design Control Change to SQ-0049: Motor Operated

Valve 1E51-F0019 Qualification, Revision 2

10/04/1997

MOV-3 DCC-008

Generic Letter 89-10 Program

04/07/1999

Engineering

Changes

PERP 478

Replacement of 80 ftlbs Start, 3400 rpm, 210 frame AC

Electric Motor for SB-2 Valve Actuator

Engineering

Evaluations

600787197

Motor Operated Valve JOG Program Basis

09/21/2012

MIDAS MOV Software Report 1E51F0063

03/18/2021

MIDAS MOV Software Report 1E51F0019 - Pre-Test

Setup for WO 200644972

03/19/2017

MIDAS MOV Software Report 1E51F0063 - Pre-Test

Setup for WO 200464450

03/20/2021

MIDAS MOV Software Report 1E51F0019 - Thrust and

Torque Calculation

01/15/2021

MIDAS MOV Software Report 1E51F0063 - Thrust and

Torque Calculation

01/15/2021

NRC Safety Evaluation for EPRI Topical Report

TR-103237 (Revision 1)

03/15/1996

MOV Test Report 1E51F0063-10

MOV Test Report 1E51F0019-006

MOV Test Report 1E51F0019-005

MOV Report 1E51F0063-009

MIDAS MOV Software Report 1E51F0019

03/18/2017

10-2917

Vendor Manual 0425-100E Model 952 Contactor

L

1E22F004-008

MOV Report

Miscellaneous

Change Notice

Revision to the Technical Specification Bases for

03/30/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

21-023

SR 3.6.1.3.10

Change Request

03-051

Modification to TS Bases 3.6.1.3.10 when the 100 scfh

and 25 sfch Limits are Applied

05/24/2003

Correspondence

Transmittal of the Non-Proprietary Versions of All NRC

Staff Comments and EPRI Responses on the EPRI MOV

Performance Prediction Methodology

04/05/1996

EPRI TR-103237-

R1-T1

EPRI MOV Performance Prediction Program Topical

Report (Non-Proprietary Version)

EPRI TR-103244-

R1

EPRI MOV Performance Prediction Program

Implementation Guide

EPRI TR-103255

EPRI Performance Prediction Program - Gate Valve

Design Effects Testing Results

07/1994

ISTP R-24

Pump and Valve Inservice Testing Program Plan

NORM-ER-3601

Valve - Motor Operated

& 10

NORM-ER-3602

Valve - Air Operated

OE-2015-1305

IN 15-13, Main Steam Isolation Valve Failure Events

2/02/2016

OE-2017-03

Evaluation of NRC IN 2017-03

07/01/2017

PY-CEI/NRR-

0904 L

Perry Nuclear Power Plant Annual Report of

CFR 50.59 Safety Evaluations for 1987

08/31/1988

RAD 21-00488

Type C Local Leak Rate Test of 1B21 MSL Penetrations

03/29/2021

Revision

Notification

601194675

PM Revision for RCIC Pump Min Flow Valve

11/07/2018

Revision

Notification:

600936099

PM Revision for 125 V Division 1 Reserve Battery

Charger

2/02/2014

SSC-001

Safe Shutdown Capability Report

WCAP-18629-P

Energy Harbor Contact Integrating Thermal Monitor

Thermal Environmental Report for Perry Nuclear Power

Plant

Operability

Evaluations

SAP 600595320

IN 2010-03: Failures of Motor-Operated Valves due to

Degraded Stem Lubricant

Procedures

ARI-H13-P601-

21

RCIC & LPCS

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EOP-SPI 6.6

RCIC Injection and Pressure Control

FTI-F0016

Motor Operated Valve Diagnostic Testing

FTI-F0019

Engineering Review of MOV Test Results

IOI-0011

Shutdown from Outside Control Room

MPP

Perry Operations Manual: Motor Operated Valve Program

Plan

NOBP-ER-3601A

Motor Operated Valve Program Torque and Thrust

Requirement and Actuator Capability

NOBP-ER-3601C

Motor Operated Valve Program Periodic Verification

NOBP-ER-3601D

Motor Operated Valve Program Diagnostic Test

Preparation and Evaluation

NOP-ER-2008

Appendix J Program

NOP-ER-3204

Inservice Testing Program

NORM-ER-2001

Preconditioning Structures, Systems and Components

ONI-C61

Evacuation of the Control Room

ONI-P54

Fire

PAP-1101

Inservice Testing of Pumps and Valves

PDB-C0007

Valves Potentially Susceptible to Pressure Locking or

Thermal Binding

PDB-C0010

ICS Valve Stroke Time Correction Times

PMI-0030

Maintenance of Limitorque Valve Operators

PTI-E51-P0005

Dynamic Diagnostic Testing of RCIC System Valves

SOI-C61

Remote Shutdown System

SOI-E51

Reactor Core Isolation Cooling System

SVI-E51-T1272

RCIC System Low Pressure Operability Test

SVI-E51-T2001

RCIC Pump and Valve Operability Test

& 45

SVI-E51-T9104

Type C Local Leak Rate Test of 1E51 Penetration P104

SVI-E51-T9422

Type C Local Leak Rate Test of 1E51 Penetration P422

TAI-1101-2

Inservice Testing of ASME OM Code Valves

03-003686-000

1E51F0064 RCIC Steam Supply Outboard Isolation Leak

Repair

05/17/2003

200560762

MSIV Full Stroke Operability Test

03/19/2015

Work Orders

200635134

MSIV Full Stroke Operability Test

03/11/2017

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

200637728

MSIV Full Stroke Operability Test

04/08/2015

200643856

Type C Local Leak Rate Test of 1B21 MSL Penetrations

03/13/2017

200643869

SVI-E51T9104 Type C Local Leak Rate Test of 1E51

Penetration P104

03/20/2017

200644390

HPCS Containment Isolation Valve Leak Rate Test

03/06/2017

200644915

Partial PMI-0030 1E51F0063

03/14/2017

200644937

HPCS Waterleg Pump and Associated Valves Cold

Shutdown Operability Test

03/05/2017

200644972

Static MOV Test and Limitorque Maintenance 1E51F0019

03/27/2016

200648070

SVI-E51T9422 Type C Local Leak Rate Test of 1E51

Penetration P422

03/25/2021

200694811

Partial PMI-0030 1E51F0063

03/21/2019

200696003

SVI-E51T9104 Type C Local Leak Rate Test of 1E51

Penetration P104

03/20/2017

200708624

HPCS Waterleg Pump and Associated Valves Cold

Shutdown Operability Test

03/12/2019

200708660

HPCS Containment Isolation Valve Leak Rate Test

03/12/2019

200709140

MSIV Full Stroke Operability Test

03/16/2019

200709311

Type C Local Leak Rate Test of 1B21 MSL Penetrations

03/17/2019

200710412

Partial PMT SVI-E51-T2001

03/27/2017

200712704

Safety Relief Valve Set Pressure Testing

03/27/2019

200712769

HPCS Waterleg Pump and Associated Valves Cold

Shutdown Operability Test

03/25/2021

200718796

SVI-E51T2001 RCIC Pump and Valve Operability Test

07/25/2018

200728988

SVI-E51T2001 RCIC Pump and Valve Operability Test

10/26/2019

200728990

SVI-E51T2001 RCIC Pump and Valve Operability Test

04/21/2020

200731306

SVI-E12T2001 RHR A Pump and Valve Operability

09/24/2019

200738377

SVI-E51T2001 RCIC Pump and Valve Operability Test

07/21/2020

200740485

SVI-E51T2001 RCIC Pump and Valve Operability Test

01/31/2020

200750875

SVI-E51T2001 RCIC Pump and Valve Operability Test

10/19/2020

200769783

T/S Repair RCIC Min Flow Valve

10/24/2018

200779935

HPCS Waterleg Pump and Associated Valves Cold

Shutdown Operability Test

03/11/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

200783359

MSIV Full Stroke Operability Test

03/16/2021

200783960

HPCS Containment Isolation Valve Leak Rate Test

03/15/2021

200784128

Type C Local Leak Rate Test of 1B21 MSL Penetrations

04/01/2021

200792383

SVI-E51T2001 RCIC Pump and Valve Operability Test

01/19/2021

200847374

Replace 2" SRV Air Supply Hose; Hose Damaged and

Leaking

03/25/2021

200847948

SVI-E51T1272 RCIC System Low Pressure Operability

Test

04/02/2021

200858798

RCIC Pump and Valve Operability Test

07/09/2021

MOV1E22-01

1E22-F001, F004, F010, F011, F012, F015 and F023

delta p

2