MONTHYEARML24185A1262024-07-10010 July 2024 Summary of Meeting with Florida Power and Light on License Amendment Requests Regarding the Spent Fuel Criticality Analysis in Support of Planned Transition to 24-Month Fuel Cycles for St. Lucie, Unit 2 ML24128A2102024-05-0707 May 2024 Public Meeting Summary - 2023 Annual Assessment Meeting Regarding Saint Lucie ML23166A0042023-06-15015 June 2023 Summary of Meeting Concerning 2023 Annual Assessment of the Saint Lucie and the Turkey Point Nuclear Plants ML23107A2312023-04-18018 April 2023 Summary Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests ML23097A1642023-04-17017 April 2023 Summary of March 23, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23069A0282023-03-15015 March 2023 Summary of January 31, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23066A0872023-03-15015 March 2023 Summary of Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23044A4172023-03-0606 March 2023 Summary of January 17, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML22357A0742023-01-19019 January 2023 Summary of December 1, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests ML22350A7082023-01-17017 January 2023 Summary of November 21, 2022, Presubmittal Meeting with Florida Power and Light on St. Lucie License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components ML22327A2402022-12-0808 December 2022 Summary of October 27, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests ML22263A0122022-09-27027 September 2022 Summary of August 29, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests (EPID Nos. L-2021-LLI-0000 and L 2021 Lli 0002) ML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22229A5252022-08-24024 August 2022 Summary of August 11, 2022, Mtg. with Florida Power & Light/Nextera on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Request (EPIDs L-2021-LLI-0000 & -0002) ML22145A3932022-05-25025 May 2022 Public Meeting Summary 2021 Annual Assessment Meeting 20220434 ML22020A4032022-02-0707 February 2022 Summary of November 17, 2021, Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests (EPIDs L-2021-LLI-0000 and L-2021-LLI-0002) ML22020A4052022-01-24024 January 2022 Summary of January 14, 2022, Teleconference with Florida Power & Light Co. Regarding Verbal Authorization of Request for Alternative to the Requirements of ASME Code for Examination of Closure Head CEDM Housing 27 Canopy Seal Weld ML21342A3752022-01-0606 January 2022 Summary of Meeting with Florida Power and Light/Nextera on Proposed Improved Technical Specification Conversions ML21337A1962021-12-16016 December 2021 Public Scoping Meeting Summary for the Environmental Review of the Subsequent License Renewal Application for St. Lucie Plant, Units 1 and 2 ML21337A2062021-11-0303 November 2021 Environmental Scoping Meeting Related to the St. Lucie Plant, Units 1 and 2, Subsequent License Renewal Application ML21173A2922021-07-0909 July 2021 5-20-21 St. Lucie Plant Units 1 & 2 Subsequent License Renewal Environmental Pre-Application Meeting Summary ML21176A0552021-06-29029 June 2021 Subsequent License Renewal Application - 2nd Public Meeting Summary of Pre-Submittal Meeting ML21159A1352021-06-0808 June 2021 Public Meeting Summary Regarding the Saint Lucie Nuclear Plant, Units 1 and 2, Docket No. 50-335 and 389, and the Turkey Point Nuclear Generating Station Units 3 and 4, Docket No. 50-250 and 50-251; Meeting Number 20210505 ML21127A2182021-05-11011 May 2021 Subsequent License Renewal Application - Public Meeting Summary of Pre-Submittal Meeting ML21092A1022021-04-13013 April 2021 Summary of Pre-Application Meeting to Discuss Planned License Amendments Regarding Conversion to Improved Technical Specifications for the Turkey Point Nuclear Generating, Unit Nos.3 and 4 and St. Lucie Plant, Unit Nos. 1 and 2 Facilities ML20044E6802020-02-20020 February 2020 Summary of February 10, 2020, Teleconference with Florida Power and Light Company St, Lucie, Unit 2 - Regarding Verbal Authorization of Request to Use ASME Code Case N-513-4 for Alternate Repair of Intake Cooling Water System ML20034F2862020-02-0303 February 2020 Summary of January 29, 2020, NRC-NMFS Teleconference Regarding St. Lucie Endangered Species Act Consultation ML19221B6742019-08-13013 August 2019 Summary of Teleconference with Florida Power & Light Company Regarding Verbal Authorization of Request for Alternative Repair of the 2B Boric Acid Makeup Pump ML19149A5942019-07-0808 July 2019 Summary of March 13, 2019, Meeting with Florida Power & Light Company Regarding a Planned License Amendment Request for St. Lucie Plant, Unit 2 ML19121A6102019-05-0101 May 2019 Public Meeting Summary - St Lucie Nuclear Plant, Docket Nos. 50-389 and 50-335 ML18242A3552018-09-21021 September 2018 Summary of Meeting with Florida Power & Light Company Regarding Planned License Amendment Requests for Turkey Point Nuclear Generating Unit Nos. 3 and 4 and St. Lucie Plant, Unit Nos. 1 and 2 ML18136A9052018-05-31031 May 2018 Summary of April 25, 2017, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of Exemption Requests to Support Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML18135A2462018-05-31031 May 2018 Summary of April 24, 2018, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of License Amendment Request to Adopt Standard Technical Specification 3.0.6 ML18144A1452018-05-24024 May 2018 Public Meeting Summary - St. Lucie Nuclear Plant Docket Nos. 50-335 and 50-389 ML18122A1952018-05-17017 May 2018 Summary of Meeting with Florida Power & Light Company Regarding a Planned License Amendment Request for St. Lucie Nuclear Plant Unit 2 ML17310B2062017-11-20020 November 2017 Summary of September 20, 2017, Meeting with Florida Power & Light Company and NextEra Energy Regarding Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML17291A0452017-11-0606 November 2017 Summary of Meeting with Florida Power and Light Company, Regarding Planned License Amendment Requests for St. Lucie Plants, Units 1 and 2 and Turkey Point Nuclear Generating Unit Nos. 3 and 4 ML17216A1732017-09-0707 September 2017 Notice of Meeting with Florida Power & Light Company and NextEra Energy to Discuss Closing Out Generic Safety Issue-191 and Generic Letter 2004-02 ML16097A1302016-04-0404 April 2016 March 29, 2016 Summary of Public Meeting - 2015 Annual Assessment Regarding Saint Lucie ML15188A3402015-07-13013 July 2015 Summary of Closed Meeting with Florida Power and Light Company and Areva Regarding Request for Additional Information for the License Amendment and Exemption Requests Re. the Transitioning to Areva Fuel ML15086A2232015-03-27027 March 2015 Summary of Meeting Concerning the Annual Assessment of St. Lucie Nuclear Plant, Units 1 and 2 ML14163A6522014-06-19019 June 2014 Summary of May 29, 2014, Public Meeting with NextEra Energy, Inc. and Florida Power & Light Company Regarding Proposed Amendment to Transition Fuel Type at St. Lucie Unit 2 ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13107B4002013-04-17017 April 2013 Summary of Public Meeting, Florida Power & Light, St. Lucie Nuclear Plant ML13095A3472013-04-11011 April 2013 3/14/2013 - Summary of Meeting with Florida Power & Light Co., to Discuss Insights About the Performance of the Steam Generators at St. Lucie Plant, Unit No. 2 After Three Operating Cycles ML13084A0302013-04-0404 April 2013 9/13/2012 - Summary of Conference Call with Florida Power & Light Co. Re. the Findings of the Fall 2012 Steam Generator Tube Inspections at Saint Lucie Plant, Unit No. 2 ML13077A4482013-03-27027 March 2013 7/27/11 Summary of Conference Call with Florida Power and Light Co. Re Findings of the Spring 2011 SG Tube Inspections for St. Lucie Unit 2 ML12326A8162012-11-21021 November 2012 11/9/2012 - Summary of Meeting with the Florida Power and Light Company Regarding the St. Lucie Nuclear Plant ML12258A0802012-09-14014 September 2012 NRC Conference Call St. Lucie Unit 2 Steam Generator Inspection September 13, 2012 ML12171A3082012-06-18018 June 2012 E-mail Re Draft Summary of 05-31-12 Phone Call 2024-07-10
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 September 4,2009 LICENSEE:
Florida Power &Light Company FACILITY:
St. Lucie Plant, Unit 1
SUBJECT:
SUMMARY
OF AUGUST 25,2009, MEETING WITH FLORIDA POWER & LIGHT COMPANY, ON UPCOMING EXTENDED POWER UPRATE SUBMITTAL On August 25, 2009, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Florida Power &Light Company (FPL) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland.
The purpose of the meeting was to discuss FPL's upcoming extended power uprate (EPU) submittal for St. Lucie, Unit 1. A list of attendees is provided as an enclosure and the licensee's presentation slides are available in the Agencywide Document Management System at Accession No. ML092440256.
The licensee provided an overview of their EPU submittal for St. Lucie, Unit 1. The EPU will be a 12-percent uprate, including a 1.7-percent measurement uncertainty recapture uprate. The original licensed thermal power was 2560 MW, and after a 5.5-percent stretch power uprate in 1981, the current licensed thermal power is 2700. The uprate licensed thermal power would then be 3020 MW. The NRC staff requested that the licensee provide original licensed thermal power plant parameters when providing tables comparing current to EPU plant parameters.
The NRC staff also requested that a summary of the grid stability study be included with the EPU submittal if the actual report will be submitted separately.
St. Lucie, Unit 1, is a Combustion Engineering (now Westinghouse) 2-loop pressurized-water reactor licensed in 1976. Its steam generators were replaced in 1991 and its license was renewed in 2003. Most of the increased power will be from increased flow rate on the secondary side with a slight change in delta 1. The fuel will be changed to a slightly higher enrichment and M5Ž cladding material.
Most plant modifications required for the uprate will be performed pursuant to Title 10 of the Code of Federal Regulations, Section 50.59 and the plant engineering group is concentrating on maintaining or increasing design margins. As part of the EPU submittal, the licensee plans to request license amendments related to Leading Edge Flow Meter installation, upgrades to the containment purge system, and safety injection tank design pressure increase.
For reactor protection system and engineered safety features, the licensee will not change the setpoints and will continue to use the current AREVA methodology.
The CENTS model has been benchmarked against actual startup and operating event data to model the response of the plant during startup and power ascension to the uprate level. The licensee plans to perform individual component and system testing vice an integrated plant test. The NRC staff asked that the licensee provide justification for those transient tests that would not be performed.
-The licensee provided details on how they will address the information required in Review Standard RS-001, "Review Standard for Extended Power Uprates." The NRC staff cautioned the licensee to provide designs and analyses requiring NRC review at the time of the submittal instead of committing to provide them at a later date as other licensees had attempted.
Additionally, the NRC staff asked the licensee to provide information on environmental justice when providing information for an environmental assessment.
The St. Lucie, Unit 1, submittal is forecast for fall 2009 with implementation in fall 2011, pending approval.
Members of the public were not in attendance, and no Public Meeting Feedback forms were received.
Please direct any inquiries to me at 301-415-2788, or Tracy.Orf@nrc.gov.
Tracy J. Off, roject Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.
List of cc w/encl: Distribution via LIST OF ATrENDEES AUGUST 25, 2009, MEETING WITH FLORIDA POWER & LIGHT COMPANY UPCOMING EXTENDED POWER UPRATE SUBMITIAL FOR ST. LUCIE, UNIT 1 Tom Boyce, NRR Richard Bulavinetz, NRR DyLanne Davigneaud, NRR Scott Elkins, RES Hukam Garg, NRR John Huang, NRR Nageswara R. Karipineni, NRR Stephen Klementowicz, NRR Aron Lewin, NRR G. Singh Matharu, NRR Jason Paige, NRR Mathew M. Panicker, NRR Bo Pham, NRR Sheila Ray, NRR Andrea Russell, NRR Summer B. Sun, NRR Alexander Tsirigotis, NRR FLORIDA POWER & LIGHT COMPANY Liz Abbott Dave Brown Jeff Brown Steve Cornell Ken Garner, WEC Dale Graves, Shaw Stone & Webster Jack Hoffman Jay Kabadi Eric Katzman Chris Wasik Enclosure
-2 The licensee provided details on how they will address the information required in Review Standard RS-001, "Review Standard for Extended Power Uprates." The NRC staff cautioned the licensee to provide designs and analyses requiring NRC review at the time of the submittal instead of committing to provide them at a later date as other licensees had attempted.
Additionally, the NRC staff asked the licensee to provide information on environmental justice when providing information for an environmental assessment.
The St. Lucie, Unit 1, submittal is forecast for fall 2009 with implementation in fall 2011, pending approval.
Members of the public were not in attendance, and no Public Meeting Feedback forms were received.
Please direct any inquiries to me at 301-415-2788, or Tracy.Orf@nrc.gov.
IRA! Tracy J. Orf, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.
List of cc w/encl: Distribution via DISTRIBUTION:
PUBLIC CTucci, NRR GMatharu, NRR LPL2-2 r/f RBulavinetz, NRR TOrf, NRR RidsAcrsAcnw_MailCTR DDavigneaud, NRR JPaige, NRR RidsNrrDorlLpl2-2 SElkins, RES MPanicker, NRR RidsNrrPMStLucie HGarg, NRR ARay, NRR RidsNrrLABClayton
...'Huang, NRR ARussell, NRR RidsOgcRp NKaripineni, NRR ASun, NRR RidsNrrDlrRerb SKlementowicz, NRR ATsirigotis, NRR RidsRgn2MailCenter ALewin, NRR DDiaz-Toro, EDO Rgn. 2 ADAMS Accession No. Meeting Summary ML092430038 Slides ML092440256 Notice ML092260029 OFFICE DORL/LPL2-2/PM DORL/LPL2-2/LA DORL/LPL2-2/BC NAME TOrf BClayton TBoyce DATE 09/03/09 09/03/09 09/04/09 OFFICIAL RECORD COpy