Summary of Meeting Concerning the Annual Assessment of St. Lucie Nuclear Plant, Units 1 and 2
ML15086A223
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 03/27/2015
From: Eric Stamm
NRC/RGN-II/DRP/RPB3
To:
Division Reactor Projects II
References
Download: ML15086A223 (15)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 March 27, 2015 MEMORANDUM TO: File FROM: Eric Stamm, Chief, (Acting) /RA by Craig Kontz Acting for/

Reactor Projects Branch 3 Division of Reactor Projects

SUBJECT:

PUBLIC MEETING

SUMMARY

- ST. LUCIE NUCLEAR PLANT DOCKET NOS. 50-335 AND 50-389 On March 17, 2015, the U.S. Nuclear Regulatory Commission (NRC) staff met with members of the public concerning the annual assessment of St. Lucie Nuclear Plant, Units 1 and 2. The purpose of the meeting was to provide opportunities to discuss the annual assessment of St.

Lucie with the public for the period of January 1, 2014, through December 31, 2014. Enclosed is a list of attendees and the St. Lucie annual assessment meeting presentation.

The following NRC staff attended the public meeting:

1. Eric Stamm, Chief (Acting), Region II (RII) Reactor Projects Branch 3, Division of Reactor Projects
2. Joey Ledford, RII, Public Affairs Officer
3. Thomas Morrissey, RII/DRP Senior Resident Inspector, St. Lucie
4. Rogerio Reyes, RII/DRP Resident Inspector, St. Lucie
5. Shana Helton, Chief, Plant Licensing Branch II-2, Division of Operating Reactor Licensing, DORL
6. Audrey Klett, Project Manager, Plant Licensing Branch II-2, DORL
7. Candace Pfefferkorn, General Engineer, Plant Licensing Branch II-2, DORL Docket Nos.: 50-335 and 50-389 License No.: DPR-67, NPF-16

Enclosures:

1. List of Attendees
2. Meeting Presentation

Contact:

Mark Riches, RII/DRP 404-997-4531

___ML15086A223_____ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE MJR4 EJS2 NAME M. Riches E. Stamm DATE 3/27/2015 3/27/2015 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO NRC Strategic Plan Goals Safety - Ensure adequate protection of public health and safety and the environment Security - Ensure adequate protection in the secure use and management of radioactive materials Enclosure 2

Our Mission To license and regulate the nations civilian use of byproduct, source, and special nuclear materials to ensure adequate protection of public health and safety, promote the common defense and security, and protect the environment.

Enclosure 2

Reactor Oversight Process Strategic Perform an ce Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Significance Threshold Threshold Threshold Action Matrix Regulatory Response Enclosure 2

Performance Indicators Use objective data to monitor specific aspects of plant performance.

Each performance indicator has established thresholds.

These thresholds are indicative of a change in safety margin.

Enclosure 2

Significance Threshold Performance Indicators Green Baseline Inspection White Requires additional NRC oversight Yellow Requires more NRC oversight Red Requires most NRC oversight Inspection Findings Green Very low safety issue White Low to moderate safety issue Yellow Substantial safety issue Red High safety issue Enclosure 2

Action Matrix Concept Multiple/Rep Licensee Regulatory Degraded Unacceptable Degraded Response Response Cornerstone Performance Cornerstone Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions Enclosure 2 Information on the Fukushima Accident

ops-experience/japan-dashboard.html

  • Mailbox for comments on staff actions: