Other: L-2015-177, Fuel Transition Small Break LOCA Summary Report, ANP-3345NP, Revision 1, L-2015-206, ANP-3428NP, Revision 0, St. Lucie Unit 2 Fuel Transition: Response to SNPB-RAI-1, Attachment 4 to L-2015-206, L-2015-259, ANP-3440NP, Revision 1, Response to NRC Questions SRXB-RAI-1 and Snpb RAI-2 Thru Snpb RAI-20., L-2015-279, RAI Response Clarification for SRXB-RAI-1 and Snpb RAI-2 Thru RAI-20 for the Technical Specification LAR and Exemption Request Regarding the Transitioning to Areva Fuel, ML15197A339, ML15219A184, ML15279A226, ML15356A184, ML15356A185
|
MONTHYEARML15002A0912014-12-30030 December 2014 St. Lucie, Unit 2 - Application for Technical Specification Change and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Request L-2014-366, ANP-3352NP, Revision 0, St. Luice, Unit 2, Fuel Transition License Amendment Request, Technical Report2014-12-31031 December 2014 ANP-3352NP, Revision 0, St. Luice, Unit 2, Fuel Transition License Amendment Request, Technical Report Project stage: Request ML15084A0112015-03-23023 March 2015 St. Lucie, Unit 2 - Supplemental Information for Technical Specification Change and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Request L-2015-166, Request for Additional Information Reply for Technical Specification Changes and Exemption Request Regarding the Transitioning to Areva Fuel2015-06-0202 June 2015 Request for Additional Information Reply for Technical Specification Changes and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Request ML15181A2902015-06-18018 June 2015 St. Lucie, Unit 2 - Resubmittal of the Areva Small Break LOCA Summary Report within the Application for Technical Specification Change and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Request L-2015-177, Fuel Transition Small Break LOCA Summary Report, ANP-3345NP, Revision 12015-06-30030 June 2015 Fuel Transition Small Break LOCA Summary Report, ANP-3345NP, Revision 1 Project stage: Other ML15188A3402015-07-13013 July 2015 Summary of Closed Meeting with Florida Power and Light Company and Areva Regarding Request for Additional Information for the License Amendment and Exemption Requests Re. the Transitioning to Areva Fuel Project stage: RAI ML15219A1842015-07-30030 July 2015 RAI Response to SNPB-RAI-1 for the Technical Specification LAR and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Other L-2015-206, ANP-3428NP, Revision 0, St. Lucie Unit 2 Fuel Transition: Response to SNPB-RAI-1, Attachment 4 to L-2015-2062015-07-31031 July 2015 ANP-3428NP, Revision 0, St. Lucie Unit 2 Fuel Transition: Response to SNPB-RAI-1, Attachment 4 to L-2015-206 Project stage: Other ML15197A3392015-08-31031 August 2015 Request for Withholding Proprietary Information from Public Disclosure for the License Amendment Request and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Other ML15233A0362015-09-0404 September 2015 Redacted Request for Additional Information Regarding Proposed License Amendment Request and Exemption Request to Allow the Transition to Areva Fuel Project stage: RAI ML15224B3192015-09-21021 September 2015 Request for Withholding Information from Public Disclosure for the St. Lucie Plant, Unit 2 Project stage: Withholding Request Acceptance L-2015-259, ANP-3440NP, Revision 1, Response to NRC Questions SRXB-RAI-1 and Snpb RAI-2 Thru Snpb RAI-20.2015-10-0202 October 2015 ANP-3440NP, Revision 1, Response to NRC Questions SRXB-RAI-1 and Snpb RAI-2 Thru Snpb RAI-20. Project stage: Other ML15279A2262015-10-0202 October 2015 St. Lucie, Unit 2 - RAI Response to SRXB-RAI-1 and Snpb RAI-2 Thru RAI-20 for the Technical Specification LAR and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Other L-2015-279, RAI Response Clarification for SRXB-RAI-1 and Snpb RAI-2 Thru RAI-20 for the Technical Specification LAR and Exemption Request Regarding the Transitioning to Areva Fuel2015-11-0303 November 2015 RAI Response Clarification for SRXB-RAI-1 and Snpb RAI-2 Thru RAI-20 for the Technical Specification LAR and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Other L-2015-300, ANP-3352NP, Revision 1, Transition License Amendment Request, Technical Report.2015-11-30030 November 2015 ANP-3352NP, Revision 1, Transition License Amendment Request, Technical Report. Project stage: Request ML15356A1842015-12-0808 December 2015 St. Lucie, Unit 2 - RAI Response for Snpb RAI-9 for the Technical Specification LAR and Exemption Request Regarding the Transitioning to Areva Fuel Project stage: Other ML15356A1852015-12-31031 December 2015 ANP-3456NP, Revision 0, Response to SLU2 NRC Snpb RAI-9, Licensing Report. Project stage: Other 2015-06-18
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML23166A0042023-06-15015 June 2023 Summary of Meeting Concerning 2023 Annual Assessment of the Saint Lucie and the Turkey Point Nuclear Plants ML23107A2312023-04-18018 April 2023 Summary Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests ML23097A1642023-04-17017 April 2023 Summary of March 23, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23066A0872023-03-15015 March 2023 Summary of Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23069A0282023-03-15015 March 2023 Summary of January 31, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23044A4172023-03-0606 March 2023 Summary of January 17, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML22357A0742023-01-19019 January 2023 Summary of December 1, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests ML22350A7082023-01-17017 January 2023 Summary of November 21, 2022, Presubmittal Meeting with Florida Power and Light on St. Lucie License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components ML22327A2402022-12-0808 December 2022 Summary of October 27, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests ML22263A0122022-09-27027 September 2022 Summary of August 29, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests (EPID Nos. L-2021-LLI-0000 and L 2021 Lli 0002) ML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22229A5252022-08-24024 August 2022 Summary of August 11, 2022, Mtg. with Florida Power & Light/Nextera on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Request (EPIDs L-2021-LLI-0000 & -0002) ML22145A3932022-05-25025 May 2022 Public Meeting Summary 2021 Annual Assessment Meeting 20220434 ML22020A4032022-02-0707 February 2022 Summary of November 17, 2021, Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests (EPIDs L-2021-LLI-0000 and L-2021-LLI-0002) ML22020A4052022-01-24024 January 2022 Summary of January 14, 2022, Teleconference with Florida Power & Light Co. Regarding Verbal Authorization of Request for Alternative to the Requirements of ASME Code for Examination of Closure Head CEDM Housing 27 Canopy Seal Weld ML21342A3752022-01-0606 January 2022 Summary of Meeting with Florida Power and Light/Nextera on Proposed Improved Technical Specification Conversions ML21337A1962021-12-16016 December 2021 Public Scoping Meeting Summary for the Environmental Review of the Subsequent License Renewal Application for St. Lucie Plant, Units 1 and 2 ML21337A2062021-11-0303 November 2021 Environmental Scoping Meeting Related to the St. Lucie Plant, Units 1 and 2, Subsequent License Renewal Application ML21173A2922021-07-0909 July 2021 5-20-21 St. Lucie Plant Units 1 & 2 Subsequent License Renewal Environmental Pre-Application Meeting Summary ML21176A0552021-06-29029 June 2021 Subsequent License Renewal Application - 2nd Public Meeting Summary of Pre-Submittal Meeting ML21159A1352021-06-0808 June 2021 Public Meeting Summary Regarding the Saint Lucie Nuclear Plant, Units 1 and 2, Docket No. 50-335 and 389, and the Turkey Point Nuclear Generating Station Units 3 and 4, Docket No. 50-250 and 50-251; Meeting Number 20210505 ML21127A2182021-05-11011 May 2021 Subsequent License Renewal Application - Public Meeting Summary of Pre-Submittal Meeting ML21092A1022021-04-13013 April 2021 Summary of Pre-Application Meeting to Discuss Planned License Amendments Regarding Conversion to Improved Technical Specifications for the Turkey Point Nuclear Generating, Unit Nos.3 and 4 and St. Lucie Plant, Unit Nos. 1 and 2 Facilities ML20044E6802020-02-20020 February 2020 Summary of February 10, 2020, Teleconference with Florida Power and Light Company St, Lucie, Unit 2 - Regarding Verbal Authorization of Request to Use ASME Code Case N-513-4 for Alternate Repair of Intake Cooling Water System ML20034F2862020-02-0303 February 2020 Summary of January 29, 2020, NRC-NMFS Teleconference Regarding St. Lucie Endangered Species Act Consultation ML19221B6742019-08-13013 August 2019 Summary of Teleconference with Florida Power & Light Company Regarding Verbal Authorization of Request for Alternative Repair of the 2B Boric Acid Makeup Pump ML19149A5942019-07-0808 July 2019 Summary of March 13, 2019, Meeting with Florida Power & Light Company Regarding a Planned License Amendment Request for St. Lucie Plant, Unit 2 ML19121A6102019-05-0101 May 2019 Public Meeting Summary - St Lucie Nuclear Plant, Docket Nos. 50-389 and 50-335 ML18242A3552018-09-21021 September 2018 Summary of Meeting with Florida Power & Light Company Regarding Planned License Amendment Requests for Turkey Point Nuclear Generating Unit Nos. 3 and 4 and St. Lucie Plant, Unit Nos. 1 and 2 ML18135A2462018-05-31031 May 2018 Summary of April 24, 2018, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of License Amendment Request to Adopt Standard Technical Specification 3.0.6 ML18136A9052018-05-31031 May 2018 Summary of April 25, 2017, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of Exemption Requests to Support Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML18144A1452018-05-24024 May 2018 Public Meeting Summary - St. Lucie Nuclear Plant Docket Nos. 50-335 and 50-389 ML18122A1952018-05-17017 May 2018 Summary of Meeting with Florida Power & Light Company Regarding a Planned License Amendment Request for St. Lucie Nuclear Plant Unit 2 ML17310B2062017-11-20020 November 2017 Summary of September 20, 2017, Meeting with Florida Power & Light Company and NextEra Energy Regarding Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML17291A0452017-11-0606 November 2017 Summary of Meeting with Florida Power and Light Company, Regarding Planned License Amendment Requests for St. Lucie Plants, Units 1 and 2 and Turkey Point Nuclear Generating Unit Nos. 3 and 4 ML17216A1732017-09-0707 September 2017 Notice of Meeting with Florida Power & Light Company and NextEra Energy to Discuss Closing Out Generic Safety Issue-191 and Generic Letter 2004-02 ML16097A1302016-04-0404 April 2016 March 29, 2016 Summary of Public Meeting - 2015 Annual Assessment Regarding Saint Lucie ML15188A3402015-07-13013 July 2015 Summary of Closed Meeting with Florida Power and Light Company and Areva Regarding Request for Additional Information for the License Amendment and Exemption Requests Re. the Transitioning to Areva Fuel ML15086A2232015-03-27027 March 2015 Summary of Meeting Concerning the Annual Assessment of St. Lucie Nuclear Plant, Units 1 and 2 ML14163A6522014-06-19019 June 2014 Summary of May 29, 2014, Public Meeting with NextEra Energy, Inc. and Florida Power & Light Company Regarding Proposed Amendment to Transition Fuel Type at St. Lucie Unit 2 ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13107B4002013-04-17017 April 2013 Summary of Public Meeting, Florida Power & Light, St. Lucie Nuclear Plant ML13095A3472013-04-11011 April 2013 3/14/2013 - Summary of Meeting with Florida Power & Light Co., to Discuss Insights About the Performance of the Steam Generators at St. Lucie Plant, Unit No. 2 After Three Operating Cycles ML13084A0302013-04-0404 April 2013 9/13/2012 - Summary of Conference Call with Florida Power & Light Co. Re. the Findings of the Fall 2012 Steam Generator Tube Inspections at Saint Lucie Plant, Unit No. 2 ML13077A4482013-03-27027 March 2013 7/27/11 Summary of Conference Call with Florida Power and Light Co. Re Findings of the Spring 2011 SG Tube Inspections for St. Lucie Unit 2 ML12326A8162012-11-21021 November 2012 11/9/2012 - Summary of Meeting with the Florida Power and Light Company Regarding the St. Lucie Nuclear Plant ML12258A0802012-09-14014 September 2012 NRC Conference Call St. Lucie Unit 2 Steam Generator Inspection September 13, 2012 ML12171A3082012-06-18018 June 2012 E-mail Re Draft Summary of 05-31-12 Phone Call ML12150A2992012-06-0505 June 2012 May 17, 2012, Summary of Teleconference Held Between the U.S. Nuclear Regulatory Commission, U.S. Fish and Wildlife Service, and Florida Power & Light Co. to Discuss the Terms of the Biological Opinion at the St. Lucie Plant, Units 1 and 2 ML12171A1932012-05-23023 May 2012 5/16/2012 - Public Meeting Summary - Category 3- Annual Assessment Meeting - St. Lucie Nuclear Plant 2023-06-15
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 13, 2015 LICENSEE: Florida Power and Light Company FACILITY: St. Lucie Plant, Unit No. 2
SUBJECT:
SUMMARY
OF JUNE 11, 2015, CLOSED MEETING WITH FLORIDA POWER AND LIGHT COMPANY AND AREVA REGARDING REQUEST FOR ADDITIONAL INFORMATION FOR THE LICENSE AMENDMENT AND EXEMPTION REQUESTS REGARDING THE TRANSITIONING TO AREVA FUEL (TAC NOS. MF5494 AND MF5495)
On June 11, 2015, a closed meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Florida Power and Light Company (FPL, the licensee) and AREVA at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss the NRC staff's draft request for additional information (RAI) provided to the licensee by e-mail dated May 8, 2015, and the licensee's pr:oposed plan to respond to the RAI for the proposed amendment' and exemption requests regarding the St. Lucie Plant, Unit No. 2 (SL-2) transition to AREVA fuel. This*
meeting was closed to the public due to the proprietary information that was discussed. The meeting notice and agenda, dated June 1, 2015, are available in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML15149A498. The meeting slides, dated July 11, 2015, are available in ADAMS under Accession No .. ML15182A126. A list of attendees is enclosed.
During this meeting, the RAI (SNPB-RAl-1 ), the proposed contents of the RAI response, and the planned schedule for its submittal were discussed. The licensee provided slides that were used as talking points for the discussion. The NRC staff reiterated to the licensee that no regulatory .
decisions would be made at the meeting. The NRC staff also reiterated that it will need the licensee to provide more clarification in the RAI response than what was provided in the original application, and the licensee indicated that it will provide more clarity and detailed responses .
The licensee indicated that a control rod ejection analysis was performed for Westinghouse fuel under Extended Power Uprate (EPU) conditions for SL-2 and that it plans to provide a similar analysis with the AREVA XN-NF-78 method and provide a comparison of ~esults in its response.
The NRC was very concerned that a point kinetics one-dimensional (1D) model was being proposed, which may not be capable of demonstrating that control rod ejection is.not affected by thermal conductivity degradation (TCD). Additionally, the NRC staff noted that the analysis results using the 1D model provided in the license amendment request (LAR) are very close to the fuel design limits. The NRC staff indicated that it preferred a three-dimensional (3D) analysis using the ARCADIA code. The licensee indicated that it may be able to do this in several months with ARCADIA, when the code has been approved for control rod ejection analysis. The licensee also indicated that most approved methods are 1D methods.
The licensee indicated that point-kinetics are conservative and offset the decrease in limits, and that the 3D method would provide further information that demonstrates that the point kinetics
model is conservative. The NRC staff indicated that there would likely be another RAI involving effects to adjacent assemblies, TCD, and point kinetics modeling compared to 3D modeling.
The NRC staff asked the licensee to identify its expected path forward and the licensee's proposed response date. The licensee requested that the NRC staff allow 7 weeks from the date of the meeting for it to submit the information, which was acceptable to the NRC staff. The NRC staff also reiterated that due to the complexity of the license amendment and exemption requests, there will be additional RAls, including (but not limited to) one involving TCD and other subject matter as described above.
Please direct any inquiries to Robert L. Gladney at 301-415-1022 or Robert.Gladney@nrc.gov.
~~/. . .f;_
Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-389
Enclosure:
List of Attendees cc w/enclosure: Distribution via Listserv
LIST OF ATTENDEES JUNE 11 2015, CLOSED MEETING I
WITH FLORIDA POWER AND LIGHT COMPANY AND AREVA ST. LUCIE PLANT, UNIT NO. 2 AREVA FUEL TRANSITION LICENSE AMENDMENT AND EXEMPTION REQUESTS U.S. NUCLEAR REGULATORY COMMISSION FLORIDA POWER AND LIGHT COMPANY Jeremy Dean William Cross Mathew Panicker Jay Kabadi Robert Gladney Farideh Saba Shana Helton Jennifer Whitman AREVA Jerald Holm Rick Williamson Ahron Kercher Greg Kessler Kevin Segard * .
Tim Lindquist *
Meeting Summary ML15188A340. Meeting Notice ML15149A498 Mee f mg Sl"d 1 es ML15182A126 LAR ML15002A091 *e-ma1'I OFFICE DORL/LPL 1-2/PM DORL/LPL2-2/LA DSS/SNPB/BC DORL/LPL2-2/BC DORL/LPL2-2/PM NAME RGladney BClayton JDean* SHelton FSaba (RGladney for)
DATE 07/10/15 07/10/15 07/10/15 07/13/15 07/13/15