PNO-III-97-094:on 971129,unit 1 Reactor Restarted.Unit Scheduled to Remain Online Until Routine Refueling Outage Planned for Early 1998
ML20206R567
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 12/01/1997
From: Frederick Brown, Mccormickbarge
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
References
PNO-III-97-094, PNO-III-97-94, NUDOCS 9901200007
Download: ML20206R567 (1)


.-, . - , ._ . . _ . .. . .. . - . - - - - _ _ -.- . _ _ . - ._ ~ .- . . - .-

s e

,8 .

December 1, 1997 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE PNO-III-97-094 This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. The information is as initially received without verification or evaluation, and is basically all that is ,

known by Region III staff (Lisle, Illinois) on this date.  !

Facility Licensee Emergency Classification Wisconsin Electric Power Co. Notification of Unusual Event Point Beach 1 Alert Two Rivers, Wisconsin Site Area Emergency Dockets: 50-266 General Emergency X Not Applicable

Subject:

UNIT 1 RESTART On November 29, 1997, the Point Beach Unit 1 reactor was restarted. It was shut down on February 18, 1997, to repair a component cooling water '

pump and a service water pump. The Unit 1 outage was extended by the licensee's decision to focus efforts on addressing performance issues and i completing maintenance and modification activities associated with Unit  !

2, which returned to service in August, 1997. As a result of the extended )

outage, other work on Unit 1 was also done, including performing modifications to the auxiliary feedwater system and replacing the low ]

pressure turbines.

Unit 1 is scheduled to remain online until a routine refueling outage planned for early 1998.

Unit 2 was shut down November 15, 1997, for reactor protection system testing. Necessary modifications to the auxiliary feedwater system are i currently underway to support dual unit operations. These modifications l were already made on Unit 1.

NRC Region III (Chicago) residen inspectors monitored the restart activities in the control room.

The State of Wisconsin will be notified.

The information in this preliminary notification has been reviewed with licensee management. This information is current as of 10:00 a.m. (CST) on December 1, 1997.

Contact:

J. MCCORMICK-BARGER F.D. BROWN (630)829-9872 (920)755-2309 9901200007 971201 '~

PDR I&E PNO-III-97-094 PDR s h p?$'l