ML20204D831
ML20204D831 | |
Person / Time | |
---|---|
Site: | Point Beach |
Issue date: | 03/12/1999 |
From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
To: | |
Shared Package | |
ML20204D820 | List: |
References | |
50-266-99-04, 50-266-99-4, NUDOCS 9903240293 | |
Download: ML20204D831 (25) | |
See also: IR 05000266/1999004
Text
. . _ _ _ __ __ __ _ . _ _ . _ - . . . . . ___.
'
4 .
4
U.S. NUCLEAR REGULATORY COMMISS!ON
l
'
REGION lil
!
,
l
Docket No: 50-266
License No: DPR-24
Report No: 50-266/99004(DRP)
Licensee: Wisconsin Electric Power Company
Facility: Point Beach Nuclear Plant, Unit 1
Location: 6610 Nuclear Road
Two Rivers, WI 54241
Dates: January 5 through February 22,1999
Inspectors: F. Brown, Senior Resident inspector
P. Simpson, Resident inspector
' Approved by: R. Lanksbury, Chief -
Reactor Projects Branch 5
Division of Reactor Projects
4
,,...
9903240293 990312
g
.
DR ADOCK O
_ .. . . _. . _ . ._ -. _ - ._ . _ . . - _. _. -_.__ _ ___ _.._.__.m
.
.~ ..
4
TABLE OF CONTENTS
Page No. 1
Execu tive Summary . . . .. . . . . . .. . . .. .... . . . . . .. . . ... . . . . . .. . .. . . . . . . ... ........... .. .. .. ..... . . ... . . 1
1.0 Loss of Flow Path for Safety injection (SI) Pumps Minimum Flow Lines ... .... ... . 3
1.1 Identification of the issue on January 5,1999 .. . ... ....... . . ...... ..... . .. 3
1.2 . Licensee Response and issuance of a Notice of Enforcement Discretion ... 4
1.3. Review of Licensee Documentation . . ...... .. . . . . .. . .. . 5
2.0 Conduct of Operations Associated with the Unit 1 Downpower . .. .. . . . . ............ 6
,
'3.0 Recovery of Full SI System Operability and Other Short-Term Actions . . .... . . . . . 7
3.1. Actions to Recover SI System Normal Flow Paths . . .. . .... . . . . 7
3.2 Other Short-Term Corrective Actions .. . .... ... . . .. .. . .. .. . .. 8
4.0 Refueling Water Storage Tank (RWST) Line Freeze Protection Circuit Failure . 10
4.1 Heat Trace and Pipe Design .. .. . ... ... . .... .. . .... ... .... . .. .... . . . . 10
4.2 History of Word Order 9819891 for the Failed Heat Trace Circuit .. . . 11
4.3 Maintenance and Testing of the Facade Freeze Protection System . ... ,. 12 -
5.0 Safety Function of the St Minimum Flow Path ... .. . .. . . . .. . . .. . . .. . . . 13 i
6.0 Follow-up Assessment of the Ice Plug in the RWST Inlet Line . . ... .. . . . . . . . . 14
- 7.0 Prior Licensee Cold Weather-Related Corrective Actions ....... ... . ... .... ....... .. 16
8.0 Corrective Actions identified During This inspection .. .. . . .. . ... . . 18 1
9.0 - Miscellaneous issues . . ... .... ... ... . . . . . . .. . .. .. ... ... .......... . . .. .... . . . . 18 ,
,
Exit Meeting S u m m ary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . .. . 19
!
!
I
- - - ,
e a , ,. n , , - .- - . , , . , , , - ,- - -,. .l-
.
l
.
.
l
! l
1
i
EXECUTIVE SUMMARY
! Point Beach Nuclear Plant, Unit 1
l NRC Inspection Report 50-266/99004(DRP)
This special inspection was conducted following the identification that a safety-related flow path
for the safety injection system was blocked with ice.
Operations
.
Plant operators failed to respond appropriately to an alarm for L temperature on an I
exposed length of safety-related pipe (RWST inlet line). Actions taken included writing
a routine priority work order and defeating the temperature recorder and alarm for the
affected pipe. Because the work order did not specify the safety-related function of the
affected pipe, the licensee's maintenance, production planning, and management i
organizations failed to initiate prompt corrective actions until the NRC questioned I
system operability. The ineffective corrective actions for this condition adverse to quality I
were considered to be an apparent violation. (Section 4.2)
i
. The inspectors identified that a failed heat trace circuit on the Unit 1 RWST inlet line had l
the potentia l to affect safety injection (SI) system operability under the cold outdoor ;
temperatures being experienced at the plant. The licensee followed-up on the
int.pectors' concern and identified that the SI pump minimum flow path was blocked by ,
l
ice. The licensee declared both trains of Si and both trains of containment spray l
inoperable, and commenced a unit shutdown in accordance with the Technical
Specifications. (Section 1.1)
l
. Operators reduced Unit 1 power by approximately 80 percent without significant
problem. All regulatory requirements and most licensee expectations for the conduct of
operations were met. (Section 2.0)
. The inspectors identified that an alarm was not associated with the pipe cited in the l
facade freeze protection procedure for the given alarm. The licensee found several
more errors after the inspectors questioned the accuracy of the procedure. The
inspectors concluded that the licensee had failed to maintain the procedure current
following modification work. This failure was considered to be a non-cited violation of ,
plant Technical Specifications. The licensee's failure to identify the procedure and
alarm inconsistency also reflected poorly on the thoroughness of the immediate
corrective actions following the Si line freeze-up identified 3 days earlier. (Section 3.2)
.
The operations department procedure for placing the facade freeze protection system
into service and operating it did not specify minimum material condition requirements.
(Section 4.3)
. Out-of-service heat trace elements were only documented by work order. A formal
assessment of the impact of the degraded condition, such as by the formal operability
, determination program, was not required by plant procedures. (Section 4.3)
i
l
1
l
- - . . - -. ._. - -- _ -. .. .-. . . -
c - -
(
-
.
The licensee had experienced equipment challenges from inadequate cold weather
preparations and freeze protection system failures from 1994 to the most recent
inspection period. The licensee took appropriate, timely corrective actions for each
l individual problem. However, not until late December 1998, had the licensee identified
l the need to perform a root cause evaluation of the continuing equipment problems with J
! the facade freeze protection system. The inspectors concluded that the licensee's l
'
corrective actions had been adequate, but had not been broad enough in scope to
prevent the January 5,1999, event. (Section 7.0)
l *
The licensee's intermediate-term corrective actions for the frozen SI minimum flow path' )
! were appropriate. Long-term corrective actions had not been identified at the end of the ]
inspection. (Section 8.0)
1
Maintenance l
,
Significant weaknesses were identified in the facade freeze protection system ,
maintenance program and its implementation. (Section 4.3) l
Enaineerina
The licensee's technical evaluations which supported a Notice of Enforcement
I
'
Discretion for continued operation of the facility with the frozen SI system line were
thorough and accurate. One weakness was noted with the licensee's safety evaluation,
but the validity of the evaluation's conclusion was not affected. All commitments
associated with the requested discretion were satisfied. (Section 1.3)
- The common Si system minimum flow path was protected from freezing by a nonsafety-
related heat trace circuit susceptible to a single failure. The licensee did not have
controlled drawings or installation records for the facade freeze protection heat trace
system. This made assessing the potentialimpact of faulty or failed heat trace elements
difficult. (Section 4.1)
- The SI pump minimum flow function was required to prevent pump failure during a
limited set of small- to intermediate-size RCS pipe failures. The licensee performed
simulator runs which indicated that operator actions would prevent the core from
becoming uncovered during a small-break loss-of-coolant accident, even if both SI
,
pumps failed. However, the simulated failure mechanism provided earlier warning of a
problem with Si than would have occurred in the plant as a result of the frozen line.
(Section 5.0)
- The licensee concluded that the normal minimum flow path for the SI pumps was
unavailable for an indeterminate period of time due to the frozen RWST inlet line.
l Based on tests performed after this event, the licensee concluded that sufficient flow
would have been established through failed low pressure boundary valves to have
assured the safety-related function of the SI pumps during any previously analyzed
accident scenario. However, the design and licensing basis does not credit the
. structural failure of low pressure system boundary valves to ensure that an emergency
core cooling system function is operable. (Section 6.0)
2
l
_. -_ . _ _ _ . _ _ _ . _ _
'
. *
.
I
I
Report Details
1.0 Loss of Flow Path for Safety Inlection (SI) Pumos Minimum Flow Lines
.
1.1 Identification of the issue on Januarv 5.1999
During the licensee's morning management meeting, one of the topics discussed was a i
problem with one channel of the Unit 1 "A" steam generator (SG) pressure reactor
protection system logic. The instrument line for a transmitter had frozen, and the {
channel had become inoperable. Material distributed at this meeting included a list of
'
" Priority Equipment." This list identified open work orders for conditions which the
operations department determined had the potential to affect operation of the plant, and
for which assistance from other departments was requested. The inspectors reviewed
this list, paying particular attention to potential cold weather issues. The inspectors
noted that work order (WO) 9819891 was on the priority equipment list. In describing
the condition that needed to be addressed, the WO stated that the freeze protection
alarm system had indicated a low temperature for the Unit 1 "RWST [ refueling water ,
storage tank) Inlet Line," that the alarm system temperature monitoring point had been l
placed in bypass (would no longer alarm), and that the heat trace for this line was "non-
function (al)." The repair completion date identified for this item was April 19,1999. The
inspectors were concerned because the common minimum flow line for the two Unit 1
safety injection (SI) pumps returned to the Unit 1 RWST through a line labeled as the
"RWST inlet line." This section of pipe was located in the unheated facade, an area
between the reactor containment and the primary auxiliary building (PAB) where the
RWST was located.
After the morning meeting, the inspectors walked-down the Unit 1 SI system to
determine whether the line identified on WO 9819891 affected the SI pump minimum
flow function. The inspectors determined, based upon the system walk-down and the
WO tag hanging on the facade freeze protection alarm panel, that the line affected by
the non-functional heat trace was part of the common flow-path for the minimum flow
function of the two Unit 1 SI pumps. Using a controlled copy of the Si piping diagram
and a copy of the priority equipment list, ;he inspectors described to the assistant
operations manager their concern that WO 9819891 appeared to indicate that a section
of pipe with a safety-related flow function was located in an area currently exposed to
sub-zero degrees Fahrenheit (*F) temperatures without operational freeze protection
and with the temperature alarm function in bypass. The inspectors questioned how this
condition had been evaluated for operability ramifications, and what the current basis
was for considering the SI minimum flow function to be operable. The inspectors'
discussion with the assistant operations manager was completed at approximately
10:45 a.m., Central Standard Time. The assistant operations manager then promptly
engaged the assistance of the shift technical advisor to evaluate the inspectors'
concerns.
l At approximately 12:00 noon, the assistant operations manager informed the inspectors
i
that the plant staff had confirmed that at least a portion of the common minimum flow
line from the Unit 1 SI pumps to the RWST was without operable freeze protection.
3
!
l
l
_ __ - ~_ __ . - __ _~_ _ .. _
!
,
.
.
- Operators were preparing to test the flow path to determine whether the SI pump
,
minimum flow function was operable. After two attempts to pass flow through the
- RWST inlet line were unsuccessful, the licensee concluded at 12:40 p.m. that the line
l
,
was blocked. Both trains of SI were declared inoperable because the support function
- of ensuring minimum cooling flow through the pumps during the initial stages of some
small-break loss-of-cooling accidents (LOCAs) was not available. The licensee also 1
identified that both Unit 1 containment spray pumps used the plugged RWST return line.
At 12:40 p.m., the licensee declared both SI pumps and both containment spray pumps ,
inoperrble. In accordance with Technical Specification (T/S) 15.3.0.B.1, the licensee
l
i
was required to initiate actions within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to have the plant in hot shutdown within '
7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> after declaring the SI pumps and containment spray pumps inoperable. At
- approximately 1
- 20 p.m., the operations manager informed the inspectors that actions 1
'
had been initiated to place the unit in hot shutdown, and that the shutdown would
commence at 2:00 p.m.
1
4
Conclusions
The inspectors identified that a failed heat trace circuit on the Unit 1 RWST inlet line had
.
'
the potential to affect safety injection system operability under the cold outdoor )
temperatures being experienced at the plant. The licensee followed-up on the l
inspectors' concern and identified that the Si pump minimum flow path was blocked by l
ice. The licensee declared both trains of Si and both trains of containment spray i
.
inoperable, and commenced a unit shutdown in accordance with the Technical
- Specifications.
! 1
>
1.2 Licensee Response and Issuance of a Notice of Enforcement Discretion (NOED)
- While operators prepared to shut down Unit 1, the licensee evaluated alternate methods
of establishing a minimum flow path for at leas. one of the SI pumps. The licensee
quickly concluded that there was reasonable assurance that the containment spray
pumps would perform their safety function with the blocked RWST return line, but these
pumps could not be declared operable until a written operability determination (OD) was
developed, reviewed, and approved as required by plant procedures. At approximately ,
1:40 p.m., the licensee concluded that the plugged Si and containment spray pump
minimum flow path placed the plant in a condition outside of its design basis. A 1-hour
report was made at 2:12 p.m., pursuant to 10 CFR 50.72(b)(1)(ii)(B).
During preparation for the plant shutdown, the licensee staff was informed by the
Wisconsin Electric electrical distribution control center that the local grid was heavily
loaded because of the increased electrical power demand due to the extreme cold
weather in the service area. The start of the plant shutdown was delayed from 2:00 to
3:00 p.m. while grid stability was evaluated. A unit shutdown was then commenced at
3:06 p.m. Inspector observations of shutdown activities are discussed in Paragraph 2.0 !
below. A 1-hour report for the T/S-required shutdown was made at 3:15 p.m., pursuant
In parallel with the shutdown, the licensee identified an alternate minimum flow path,
involving the SI system full flow test line, which could be used to return one Si pump to
!
4 j
1
1
!
I
-
. .
,
.
an operable status. The licensee concluded that physical system alignments and tests
could be completed prior to the expiration of the T/S 15.3.0.B.1-required time for placing
the plant in hot shutdown (7:40 p.m. based on the time of identification of
12:40 p.m. and the 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> specified in the T/S). However, the licensee determined that
the written ODs, emergency operating procedure (EOP) changes, and supporting
10 CFR 50.59 safety evaluation (SE) required by plant procedures could not be
completed within the specified time to shutdown.
At 4:30 p.m., the licensee initiated a conference call with NRC Region lli and the Office
of Nuclear Reactor Regulation to request an NOED for a one-time,6-hour extension of
the shutdown provisions of T/S 15.3.0.B.1. The basis for this request was the licensee's
desire to avoid the plant transient associated with a shutdown of the plant. Additionally, l
the licensee informed the NRC staff that replacement of the plant's power output was l
not a certainty given the cold weather and system loads. Wisconsin Electric had l
entered a grid pow ondition of " Yellow" at the time the Unit 1 downpower was started. l
The licensee statec uat there was little increase in risk associated with the requested !
NOED because the physical plant changes required to exit the T/S 15.3.0.B.1 action ,
statement would be completed prior to the expiration of the allowed outage time and l
associated shutdown action statement. The additional 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> would be required to !
complete, review, and approve required paperwork. The licensee explained the
proposed alternate Si system minimum flow path for one Si pump, and the technical <
l
basis for considering the containment spray pumps to be operable. At 6:20 p.m., the
NRC notified the plant that the requested NOED had been granted consistent with the
guidance of NRC Manual Chapter 9900, " Technical Guidance, Operations - Notice of i
The basis for considering containment spray operable was the physical configuration of l
the pumps and the recirculation through the system chemical addition piping. The
'
licensee also determined that the pumps' discharge valves would open prior to the
pumps' receiving a start signal, consequently, the pumps would not be subjected to a
shutoff head flow condition.
At 6:32 p.m., the licensee established the alternate minimum flow path for the "B" train
SI pump. Crew briefings on the abnormal SI system configurations commenced at
8:30 p.m. for the on-shift crew, and continued at each oncoming shift turnover meeting.
At 12:26 a.m on January 6,1999, the licensee completed the development, review, and
approval of ODO, EOP changes, and an SE for the existing configuration of the two Si
pumps. The "B" train SI pump and the two containment spray pumps were declared
operable but degraded, and T/S 15.3.0.B.1 was exited prior to the time allowed by the
NOED extension. The unit remained in a 72-hour limiting condition for operation for the
inoperable "A" train Si pump in accordance with T/S 15.3.3.A.2.b.
1.3 Review of Licensee Documentation
The inspectors reviewed the licensee's OD, SE, and NOED written request for accuracy
and technical adequacy. The inspectors determined that all three were complete,
a curate, and without major flaws. One issue was identified with the written SE.
Sr 'cifically, when evaluating the use of tha full flow test line as an alternate SI pump
minimum flow bypass line, the licensee acknowledged that portions of the line were not
5
.
- .
'
,
\
l
l
I classified as safety-related. The SE concluded that this did not impact the use of this ;
l alternate flow path because the applicable pipe and components had originally been ;
l- purchased and installed to equivalent standards as the safety-related portions of the SI 1
system. The pipe and components were being controlled as Seismic Class 1,
" Augmented Quality." The SE did not address whether the system had been modified,
through either design changes or through parts replacement, in a manner which
affected its ability to function under accident conditions during the period when
safety-related quality control program elements were not being implemented. The
inspectors considered the failure to address this issue a weakness, but concluded that it
did not invalidate the findings of the SE. This conclusion was based on the very limited
number of active and passive components in the applicable portion of the system, and
the low probability of the failure (based upon their nature) of any of these items.
The inspectors reviewed the work plan used to establish the altemate SI pum? minimum
flow path. The work plan was adequate to achieve the desired results. The inspectors
reviewed shift logs and turnover notes, and verified that required briefings were
performed to ensure that operating crews were aware of the alternate Si minimum flow
bypass configuration. Based on these reviews, the inspectors concluded that the
licensee satisfied the commitments referenced in the NOED.
Conclusions !
The licensee's technical evaluations which supported the continued operation of the
facility with the frozen SI system line were thorough and accurate. One weakness was j
noted with the licensee's safety entuation, but the validity of the evaluation's
conclusions were not affected. All commitments associated with the NOED were
satisfied.
2.0 Conduct of Operations Associated with the Unit 1 Downoower
The control room crew referred to Operating Procedure 3A, " Normal Power Operation to
Low Power Operation," Revision 43, to commence the Unit 1 shutdown. The licensee
terminated the shutdown at approximately 20 percent power once the NOED was
_
'
granted. The inspectors noted that the Unit 1 shutdown was conducted and controlled
well, as evidenced by the use of pre-job briefs, formal communications, and self-
checking. The operating supervisor (a senior reactor operator) in charge of the reactor
shutdown evolution displayed good command and control of the activities.
4
A change of shift occurred during the shutdown. The off-going control room crew
placed the plant in a stable configuration prior to conducting a turnover with the
oncoming crew. The inspectors observed the operators exchange detailed equipment
status information and perform a control board walkdown prior to assuming the shift. In
addition, the oncoming operating supervisor conducted a brief with the oncoming control
(reactor) operators covering precautions, limitations, and reactivity control. The j
!- inspectors concluded that the change of control room crews was conducted smoothly j
'
i and effectively.
l i
At the point in the shutdown evolution when a SG feedwater pump needed to be
secured, the control room crew decided to secure the "A" pump. As discussed in
l
6
l
.
. . . . _ _-
- .- -
_ - . - ._ .. . - -. -- .-- - -.
,
-
I
( Section 01.2 of Inspection Report (IR) 50-266/98019(DRP); 50 301/98019(DRP), the
l "A" pump had experienced a bearing failure on November 14,1998. As part of its return !
j to service following repairs, temporary procedure changes and a temporary modification
'
to the "A" pump discharge valve had to be made. During the January 5,1999, Unit 1 ,
shutdown, operators thought those changes were necessary on a one-time b_. .s in I
'
. order for engineering staff to gather pump start data. However, during the return to full
l power on January 6,1999, operators learned that in order to restart the "A" SG
feedwater pump, the temporary procedure changes and the temporary modification to
the "A" pump discharge valve needed to be implemented. This resulted in a delay of 1
i
2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> while support personnel recreated, approved, and implemented the temporary l
l procedure changes and the temporary modification. The inspectors concluded that l
l ineffective communications occurred between the operations and engineering
departments regarding operational requirements for the "A" SG feedwater pump, l
I
resulting in en unnecessary distraction to the control room crew.
The inspectors observed during the shutdown that the duty shi't superintendent (the
lead senior reactor operator) and the duty operating supervisor were both heavily
involved with developing and implementing compensatory measures for the plugged
l RWST inlet line. Attachment 1 of Operations Manual 1.1," Conduct of Plant
Operations," Revision 1.1, tasked the duty shift superintendent with providing a." big
picture" overview cf shift and plant activities and the duty operating supervisor with
providing oversight of control room activities. Industry events have shown the value of
having a senior reactor operator (SRO) who is not directly involved with ongoing j
activities providing an independent overview of critical plant evolutions such as a time l
constrained reactor shutdown. While no actual safety impact resulted in this case, the
inspectors were concerned that although industry experience had been integrated into
the station conduct of operations procedure, the licensee did not provide an
independent overview in the control room.
The inspectors discussed these observations with the operations manager. The
operations manager acknowledged them and planned to address them with the
operations department staff.
Conclusions
- Operators reduced Unit 1 power by approximately 80 percent without significant
problem. All regulatory requirements and most licensee expectations for the conduct of
operations were met.
i 3.0 Recovery of Full SI System Operability and Other Short-Term Actions
3.1 Actions to Recover SI System Normal Flow Paths
1
'
The licensoe isolated the two Si pumps from the pump minimum flow line using manual
valves when the alternate minimum flow path was established at 6:32 p.m. on
January 5,1999. This was done, in part, to prevent over-pressurization of portions of
the RWST inlet line which would not normally be exposed to Si system pressure, but
which could be because of the plugged RWST intet line. External heating of the blocked
RWST inlet line was commenced at approximately 2:00 p.m. using a space heater. This
7
- -
>
9
[
heater was located to direct heat on the outside of the pipe lagging at the base of the
vedical run of the RWST inlet line. At approximately 10:30 p.m., an electric weld
machine was used to establish a high current (between 200 and 300 amperes (amps)),
low voltage electrical circuit through a portion of the vertical section of the RWST fill line.
At 10:34 p.m., a 58-gallon per minute (gpm) flow was established through the RWST fill
line using a normal RWST recirculation flow path and the refueling water recirculation
pump, P-33.
The licensee declared the "A" train SI pump and system operable at 9:08 p.m. on
January 6, following completion of an engineering assessment that there was no
freezing or thawing-related damage to the RWST inlet line, realignment of the "A" train
manual isolation for the normal minimum flow line, and performance of an Si pump test
run with flow to the RWST, With the "A" SI pump and both containment spray pumps
fully operable, and the "B" SI pump operable but degraded (with the alternate minimum
flow path), the licensee exited the T/S 15.3.3.A.2.b 72-hour action statement. At
11:01 p.m. on January 9, the licensee completed valve manipulations and testing
necessary to return the "B" SI pump to a fully operable condition using its normal
minimum flow path. This activity had been sequenced to the completion of repair and
modification work on electrical buses affecting the emergency power supply for the
redundant ("A" train) Si equipment.
3.2 Other Short-Te rm Corrective Actions
On January 8, the licensee documented in Condition Report (CR) 99-0076 that two
facade freeze protection system recorder points indicated temperatures below freezing
and that a low current to the associated heat tracing existed. The control room crew, in
screening the CR, used Operating Instruction (OI) 106, " Facade Freeze Protection
System Operation," Revision 11, to associate the recorder points with a circuit
description. It was necessary to use 01106 since the freeze protection system
component labels only provided a circuit number and not a physical description of the
equipment protected. Using Ol 106, the licensee identified that one of the affected
circuits was for the Unit 1 turbine-driven auxiliary feedwater (AFW) pump (1P-29) steam
supply from the "B" SG. The operators checked the steam trap in the affected 1P-29
steam supply line and noted that it had a large differential temperature which they
interpreted as meaning the line upstream was not frozen. On this basis, the CR
screener concluded that AFW pump 1P-29 was operable but requested that an OD be
performed to address the low heat tracing current.
The inspectors reviewed CR 99-0076 on' January 9 and questioned how the facade
freeze prota>ction system related to the steam supply for 1P-29. The inspectors walked
down the accessible portions of the 1P-29 steam supply from the "B" SG and could not
-find any heat tracing associated with those lines. The inspectors did locate a line in the
Unit 1 facade connected to a temperature element and a heat tracing circuit labeled with
designators that matched those in question. The inspectors informed the control room
crew that it appeared that 01106 inaccurately described the defective circuit
documented on CR 99-0076. The control room crew informed the system engineer
performing the CR 99-0076 OD of the inspectors' observations.
8
- - . . - - - -.. - - -.- -- -...--.
., . ,
t
- ;
t
The inspectors met with management from the operations and engineering departments
later that day to discuss the inspectors' field observations and express concem about j
( the accuracy of Ol 106 and the lack of apparent licensee action to evaluate the extent of
- the inaccuracy. This was of concem because the licensee was using Ol 106 to identify
- ' which plant systems were affected by freeze protection circuits that were not working ,
properly. The licensee acknowledged the inspectors' concerns. '
l
<
- The licensee promptly compared the freeze protection circuits described in 01106 to the
l actual field configuration. Many circuits were found to be improperly described. The
j licensee corrected Ol 106 to eliminate the errors or to indicate that the circuit would
I have to be walked down if it alarmed. One error identified was that the circuit Ol 106
i
had described as the 1P-29 steam supply from the "B" SG was actually the Unit 1 "B"
- SG relief valve stack drains and "B" SG main steam isolation valve steam trap bypass to
j the blowdown tank line.
i-
l Pie licensee had classified Ol 106 as a procedure required by T/S 15.6.8. The
j .nspectors were told by several plant staff, including supervisory personnel, that Ol 106
w's known to be out-of-date and to contain potentially inaccurate information. A partial
caut;e for this condition was that some of the facade freeze protection circuits had been ;
modifad prior to the onset of winter weather, but the modification package close-out
work had not been completed. Because there were no final drawings to use in updating ;
j'
.
the operating procedure, plant engineering and operational staff had accepted that the
- questionable procedure would continue to be used. The failure to maintain a required ;
l procedure current following system modification was a non-repetitive Severity Level IV i
j violation of T/S 15.6.8 which has been entered into the licensee's corrective action 4
I
j program (condition report 99-0075) and is being treated as a Non-Cited Violation,
l consistent with the NRC Enforcement Policy (NCV 266/99004-01(DRP)). Corrective
t
actions taken for this condition included a prompt change to 01106 to correct some
known errors and to flag circuits of questionable accuracy, an intermediate-term .
, commitment to accurately characterize all facade freeze protection circuits and to l
update 01106 accordingly, and a long-term commitment to ensure that operating
, procedures were updated prior to the release of any modified system for operation.
! Conclusions
[ l
i The inspectors identified that an alarm was not associated with the pipe cited in the j
i facade freeze protection procedure for the given alarm. The licensee found several j
' '
more errors after the inspectors questioned the accuracy of the procedure. The
! inspectors concluded that the licensee had failed to maintain the procedure current
- following modification work. This failure was considered to be a non-cited violation of
plant Technical Specifications. The licensee's failure to identify the procedure and
.' alarm inconsistency also reflected poorly on the thoroughness of the immediate
corrective actions following the Si line freeze-up identified three days earlier.
4'
.
9
,
-
i
i,, , - - - - - - - - - - - . , , - --- -
. . - .. .- _-. -_ - - - .-
, . .
l
!
4.0 RWST Une Freeze Protection Circuit Failure
4.1 Heat Trace and Pioe Desian
l
l The. facade freeze protection system was one of three heat tracing systems installed at !
!
the facility. The facade freeze protection system and the boric acid heat trace system
(located inside the PAB) each monitored temperatures on various components and had
alarm panels in the PAB (although alarm coverage was not comprehensive in that some
circuits were not monitored). The third system provided protection for portions of the
primary chemical and volurm control system gas strippers and the radiological waste
processing systems located in the facade. This system had no alarm capability. j
The RWST inlet line located in the facade was a nominal 2-inch diameter, schedule 10,
stainless steel pipe. The line left the PAB approximately 1 foot below the floor of the
6.5- foot elevation (plant designation). The pipe ran horizontally for approximately ;
5 feet, then ran vertically up the external side of the RWST wall. This vertical length of l
!
pipe was approximately 75 feet long. The pipe turned and entered the RWST near the
top of the tank. The tank was heated (to approximately 50*F) and insulated. The
vertical run of the RWST inlet line was approximately 1 foot from the tank, and was i
supported by two uninsulated pipe supports attached to the RWST. The fill line was
insulated with asbestos lagging.
Two heat trace circuits were installed on the RWST inlet line. Each circuit was carried in
a piece of conduit which entered the inlet line insulation approximately half way up the
vertical length of pipe. Each heat trace circuit had a thermocouple-type temperature ,
probe installed on the pipe, under the insulation, somewhere along the length of the j
heat trace. There were no controlled drawings or installation notes to indicate where the ;
heat trace was routed under the insulation on the inlet line, or where the thermocouples
were physically located. The pipe insulation had not yet been removed at the
completion of the inspection because of the need to establish appropriate asbestos
controls and the desire to minimize heat loss from the pipe.
The failed section of heat trace was designated as 1-FF-1-228, with the associated
thermocouple being designated as point 133 on the facade freeze protection alarm
panel in the PAB. The other heat trace circuit was designated as 1-FF-1-07A, with the
associated thermocouple being designated as point 126 on the alarm pan 61.
The licensee thought, based on experience with similar heat trace circuits and the
available indication, that one heat trace circuit ran upward on the vertical RWST inlet
line from the point the conduit entered the lagging, and the other circuit ran downward.
This configuration would not provide any overlap in the heat trace function. Therefore, if
a single circuit failed, the other circuit would not provide direct heating of the entire pipe
run.
Conclusions
The common SI system minimum flow path was protected from freezing by a heat trace
circuit susceptible to a single failure. The licensee did not have controlled drawings or
l
!-
10
~
1
- i
l
l
l
1
r installation records for the facade freeze protection heat trace system. This made
assessing the potentialimpact of faulty or failed heat trace elements difficult. I
4.2 History of WO 9819891 for the Failed Heat Trace Circuit !
I
A PAB auxiliary operator reported that facade freeze protection system point 133 was in )
l alarm (indicated temperature of 35'F or less) on December 22,1998. Ambient
temperatures were below O'F at the time. Several other alarms were also received,
including one on the Unit 1 SG blowdown line flow indicators. This latter iesue was ,
recognized to be a challenge to the continued operation of Unit 1. Operating l
Instruction 100, Section 4.3, " Alarm Response," provided instructions for dealing with
points in alarm. The actions taken by the auxiliary operator included placing point 133 in )
bypass (this removed the alarm and record keeping functions of the alarm panel from '
service for this heat trace element), and informing the control room of the condition.
The operator did not take any of the compensatory actions described in 1
Paragraph 4.3.12 of 01106. This paragraph stated that circulating system fluids
through the pipe or adding heat lamps should be " considered."
One of the onshift reactor operators (ROs) was an acknowledged expert on the facade
freeze protection system. He recognized that the Si pump minimum flow function was
associated with the RWST inlet line; however, he did not consider the alarm to represent
an immediate safety concern. The operators told the inspectors that this conclusion was
based on the operable 1-FF-1-07A heat element, heat conduction because of the
proximity of the pipe to the heated RWST, and the fact that there was no known history
of this line freezing. The RO initiated WO tag 144850 for the alarming point and then
. discussed the alarm condition and the WO tag with the duty shift supervisor (DSS). The l
DSS was also familiar with the Si pump minimum flow function associated with the
RWST inlet line; however, the DSS also failed to annotate the WO tag as being a high
priority item affecting plant safety equipment, and to direct that a CR and OD be l
initiated. The WO tag was then routed in a routine manner to the work control center i
SRO, who was also responsible for assessing the impact of the observed condition on l
equipment operability, for determining whether a CR should be written, and for l
assigning a priority or verifying the initial priority given to the WO. The WO was I
assigned a priority of "6" (routine woik).
As a result of the freeze protection problems being experienced on December 22,1998,
the RO most familiar with the system and the system engineer (who had been assigned
responsibility for the system on December 21,1998) performed a walk-down of large
portions of the system. Although they were reported to have specifically looked at the
I
RWST inlet line, neither individual identified any need to reassess the priority assigned
to WO 9819891 or to initiate a written operability review.
On December 22, a general note regarding the need to perform facade freeze
protection system corrective maintenance in a prompt manner was added to the " Priority
Equipment" list by the operations department. This note remained on the list through
December 29. On that date, plant work control and maintenance personnel requested
that the operations department provide more detail on the issue referenced in the note
so that the issue could be effectively addressed. An on-shift DSS added two equipment
, identifiers, one of which was for 1FF-1-22B (the RWST inlet line heat trace), to the
l
l 11
. ._. - _ . . _ . . _ __ . . _ - - _ _. _. _
,
. ,
.
l priority equipment list distributed on the morning of December 30. The DSS selected
the term "non-function (al) heat trace" to describe the condition for 1FF-1-228. He later
- stated that this term was arbitrary, in that he was not aware of any details other than the
alarm condition stated on the original WO tag (and hence in the subsequently developed
electronic WO file). The priority equipment list of December 31 included the equipment
designator and the WO number for the RWST inlet line heat tracing. The lists for
January 1,4, and 5,1999, included the equipment designator, the WO number, the
description (referenced in Paragraph 1.1 of this report), the new priority of "5"
(mandatory work), and the proposed completion date of April 19,1999. A status code
"10," indicating validation of the work and finalization of the prioritization, but no work
planning activities initiated, was also listed. The work priority had been upgraded from
"6" to "5" when the item was specifically identified on the priority equipment list;
however, having the WO on the list did not accelerate the completion of the corrective
maintenance for the failed heat trace circuit.
On December 22, the licensee was aware that a temperature recorder for a section of
safety-related pipe, located in an area exposed to extreme low temperatures, was
indicating near freezing temperatures. The only substantive action taken between
December 22,1998, and January 5,1999, (when the NRC recognized the potential
significance of the condition and questioned Si system operability) was to remove the
temperature recorder associated with the pipe from service. The licensee's failure to
promptly address the low temperature on the safety-related pipe, a condition adverse to
quality, was an apparent violation of 10 CFR Part 50, Appendix B, Criterion XVI,
" Corrective Action," which requires that measures be established to assure that
conditions adverse to quality are promptly identified and corrected (Escalated
Enforcement Itam (EEI) 266/99004-02(DRP)).
Conclusions
Plant operators failed to respond appropriately to an alarm for low temperature on an
exposed length of safety-related pipe. Actions taken included writing a routine priority
work order and defeating the temperature recorder and alarm for the affected pipe.
Because the work order did not specify the safety-related functica of the affected pipe,
the licensee's' maintenance, production planning, and management organizations failed
to initiate prompt corrective actions until the NRC questioned system operability. The
ineffective corrective actions for this condition adverse to quality were considered to be
a violation of 10 CFR Part 50, Appendix B, Criterion XVI.
4.3 Maintenance and Testino of the Facade Freeze Protection System
The licensee repaired the facade freeze protection system once it failed, instead of
performing preventive maintenance to prevent failure of the system. The maintenance
department had a planned diagnostic work procedure ("Callup E-A") which required
amperage checks for all facade freeze protection circuits. The scheduled completion
date for this "callup" work activity of May 18,1998, would likely have allowed time for
.
correction of any identified deficiencies prior to the onset of cold weather. On August 2,
I the WO for Callup E-A was annotated by an engineer with " Defer performance of this
W.O. until the revised callup E-A check list is issued." The "callup" work activity was not
initiated until around December 16 and the breaker and thermostat circuit containing the
12
l
~~ __ -._ -.---- _-. - -_.-- .- -.- - .-
, . ,
L ,
!
1FF-1-228 heat trace were tested around December 18. A current of 4.5 amps was
measured for the circuit test.' The design value listed for this circuit was 8.4 amps, but
no acceptance criteria were provided in the callup WO package. The electricians who !
performed the "callup" work activity initiated individual WOs to fix the circuits with 0 amp i
readings, but since this circuit read greater than zero amps, no action had been taken
,
'
as of January 13,1999. The WO for Callup E-A was still open at that time (not all
circuits had been tested, and some circuits could not be identified with certainty), and
the electricians interviewed by the licensee's. event assessment team stated that all
anomalous readings would have eventually been provided to engineering personnel for
evaluation. The most recent completion of Callup E-A prior to the winter of 1998 was
l ~ September 24,1997. The licensee stated that the electrical circuit containing the
L 1FF-1-228 heat trace was functional, with an indicated current of 8 amps.
l Operations Department Periodic Check 49, Part 4, " Auxiliary Buildings Miscellaneous
( and Facades," Revision 10, (a non-nuclear type procedure) and Ol 106 (a procedure
l required by T/S) provided instructions for placing the facade freeze protection system in
service. These procedures had been completed on October 5,1998. The system
'
check-out and operating procedures did not contain any tests or checks which would
identify the passive failure (that is, breakers not opened on a short circuit current) of a
section of heat trace. The licensee expected a work order to be written for any non-
functional equipment, as indicated by observable failures, and the DSS to be informed
so that an appropriate priority could be established for corrective maintenance. There
were no minimum material condition (system operability) requirements for placing the .
facade freeze protection system in operation.
Conclusions I
l
Significant weaknesses were identified in the facade freeze protection system
maintenance program and its implementation. The operations department procedure
for placing the facade freeze protection system into service and operating it did not
specify minimum material condition requirements. Out-of-service heat trace elements
were only documented by work order. A formal assessment of the impact of the
degraded condition, such as by the formal operability determination program, was not j
required.
5.0 Safety Function of the SI Minimum Flow Path ,
l
Point Beach's safety-related emergency core cooling systems consisted of two
intermediate-head safety injection trains, two accumulators, and two low-head residual
. heat removal trains. The licensee was committed to being capable of handling any size l
reactor coolant system (RCS) pipe break. For some range of small-to-intermediate pipe - l
break sizes (the range was not specified in the plant's design or licensing bases), there
would be a period of time between the automatic start of the SI pumps and the
depressurization of the RCS to below the Si pump shutoff head. During this period of
time, the only flow through the SI pumps would be through the minimum flow
- recirculation line to the RWST. This minimum flow ensured adequate cooling of the
pumps. The absence of cooling flow would lead to binding within the pump, or seal l
failure, in a short period of time. The licensee's SI pumps could operate indefinitely with
. 225 gpm of recirculation flow. At 70 gpm of flow, the pump vendor certified that the
l l
l
13
!
1
,n, ,- , - ,, , . - . ,- , , - - , -
- _ _ . - _ -. -- -
,
- j
-
\
l
SI pumps would remain fully operable for 15 minutes. At no-flow conditions, the
licensee's SI pumps, which were close-toleranco, multi-stage, high horsepower pumps,
could failin less than 2 minutes.
1
The ice plug in the RWST inlet line had no direct impact on the operation of the plant. j
The plug would have had safety consequence during a certain range of LOCAs that '
involved a slow depressurization of the RCS. If the time it took to depressurize from
1800 pounds per square inch - gauge (psig) (the time of pump start) to below 1500 psig
(approximate start of injection) had exceeded approximately 2 minutes (assuming no )
alternate minimum flow path), both Si pumps would likely have failed catastrophically.
Assuming no operator action, this would have delayed the start of injection until the RCS
reached approximately 700 psig, at which time the accumulator outlet check valves
would have opened. This condition would be outside the plant's design basis, in that the
licensee's accident analysis assumed that at least one SI pump was always operable.
Following the event, the licensee performed unannounced simulator drills for three
separate crews where the SI pumps were both rendered inoperable. In each case, the
i crew took action to lower RCS pressure manually so that the accumulators could inject.
The licensee informed the inspectors that the core was not uncovered during any of the
simulations. However, the inspectors noted that the method of failing the pumps in the
simulator provided earlier warning to the operators of system failure than would have
occurred if failure had resulted from the frozen Si line.
Conclusions
1
The Si pump minimum flow function was required to prevent pump failure dunng a i
limited set of small- to intermediate-size RCS pipe failures. The licensee performed
simulator runs which indicated that operator actions would prevent the core from
becoming uncovered during a small-break loss-of-coolant accident, even if both S1
'
pumps failed. However, the simulated failure mechanism provided earlier warning of a
problem with Si than would have occurred in the plant as a result of the frozen line.
6.0 Follow-up Assessment of the Ice Plua in the RWST Inlet Line
The licensee demonstrated that the flow path through the RWST inlet line was operable
on December 12,1998, during performance of activities per in-service Test
Procedure 01 "High Head Safety injection Pumps and Valves (Quarterly), Unit 1." The
next scheduled date for performing this test was March 10,1999. No other scheduled
activities that could have established flow through the RWST inlet line were identified in
the licensee's planning system.
The licensee concluded that flow through the RWST inlet line was blocked on the
morning of January 5,1999, when the low-head (approximately 120 psig) P-33 pump
could not establish recirculation flow to the RWST. There were no data available to the
inspectors which indicated the location or thickness of the ice plug. The licensee
evaluated the temperatures recorded at point 126 (the operating heat trace on the
RWST inlet line), at point 133 before it was placed in bypass on December 22,1998,
and ambient air temperatures recorded in the station logs. From this evaluation, the
licensee determined that the pipe temperature at point 133 dropped below freezing on
14
-- -- - - - - - . - . - . - - . - - - - - .
,
- . . .
.
l
. three occasions. The first was for a period of about 2 days starting on December 22. l
The second was fora period of about 3 days starting on December 30. The third and
final period began on January 5,1999, and ended that evening. This evaluation was of
limited use in bounding the potential periods of pipe freezing because the licensee could
i
not determine how closely the temperature at point 133 reflected the temperature at the
l point in the pipe at which the ice plug actually formed.
Based on an engineering assessment, the licensee concluded that an ice plug of 2 pipe
i diameters (approximately 4 inches) would effectively block flow in the pipe at the shutoff
head of the Si pumps. An orifice installed in the SI pump minimum flow bypass lines off
of each pump (before they joined) normally maintained pressure in the downstream pipe l
i at values below 150 psig. Shutoff head pressure of the SI pumps was approximately )
l 1500 psig. The existence of the ice plug would have eliminated the pressure drop l
through the orifice, and would have resulted in pressurizing the entire minimum flow j
path to pump shutoff head pressure. The licensee calculated that the stainless steel :
'
'
pipe in the RWST inlet line would not have failed at SI shutoff head pressure. Based on
this assessment, the minimum flow function was considered inoperable.
i
The inspectors questioned whether the closed isolation valves which normally isolate the
Si minimum flow bypass flow path from other systems connected to the RWST inlet line
would have withstood the SI shutoff head pressure. The licensee concluded that SI
pump shutoff head pressure would have caused the failure of pressure boundary l
! diaphragms in three normally closed isolation valves on the RWST inlet line. The I
licensee performed tests which indicated that sufficient flow would have been created I
through these failed diaphragms such that the SI pumps would not have failed during a i
small- to intermediate-break LOCA. The licensee further concluded that the loss of I
water from the RWST through the failed valvos would have had no adverse impact on
the RWST inventory for a small-break LOCA. The licensee therefore concluded that the
SI system remained operable, but degradediwhile the RWST inlet line was frozen. The
calculations and test results supporting the licensee's operability determination were
reviewed by the inspectors. No problems were identified; however, the inspectors noted
that the design and licensing basis does not credit the structural failure of low presture .
system boundary valves to ensure that an emergency core cooling system function is l
Conclusions ,
.The licensee concluded that the normal minimum flow path for the Si pumps was
unavailable for an indeterminate period of time due to the frozen RWST inlet line.
Based on tests performed after this event, the licensee concluded that sufficient flow l
would have been established through failed low pressure boundary valves to have
assured the safety-related function of the SI pumps during any previously analyzed
accident scenario. However, the design and licensing basis does not credit the
structural failure of low pressure system boundary valves to ensure that an emergency
core cooling system function is operable.
i 15
i
-.
E3 . .
-.
7.0 Prior Licensee Cold Weather-Related Corrective Actions
The inspectors reviewed the docket for recent cold weather problems at Point Beach.
The results of that review are listed below.
In IR 50-266/93018(DRP); 50-301/93018(DRP), issued on January 31,1994, the
licensee's preparations for cold weather were discussed. The licensee
experienced problems with SG blowdown flow sensing lines freezing, inadequate
main steam isolation valve solenoid-operator enclosure heating, and low
operating air pressures for several 345-kilovolt switchyard breakers. The
licensee corrected each problem.
in IR 50-266/96002(DRP); 50-301/96002(DRP), issued on April 17,1996,
problems with low operating air pressures for some 345-kilovolt switchyard
breakers during cold weather were discussed. The identical problem had been
discussed in IR 50-266/93018(DRP); 50-301/93018(DRP). The inspectors were
concerned that the air leaks introduced a common mode failure mechanism that
could affect offsite power availability. The licensee replaced the breakers with a
new type less susceptible to cold weather air leaks.
In IR 50-266/97003(DRP); 50-301/97003(DRP), issued on February 22,1997,
the licensee's cold weather preparations and implementation of the freeze
protection program were discussed. The inspectors concluded that the licensee
was adequately prepared for cold weather; however, the inspectors identified the
lack of a formal mechanism to identify heat lamp use in the facade, the lack of
an oversight individual for the cold weather / freeze protection program, and the
untimely resolution of facade freeze protection system deficiencies which created
operator workarounds.
In IR 50-266/97021(DRP); 50-301/97021(DRP), issued on December 22,1997,
the licensee's preparations for cold weather were discussed and independent
verification checks were performed of selected cold weather protection
equipment. The inspectors did not identify any problems. The inspectors
documented that the licensee had reduced the corrective maintenance backlog
for facade freeze protection system components and had been installing new
heat trace wiring to upgrade portions of the system.
On December 15,1997, the NRC completed an inspection of the licensee's
implementation of 10 CFR 50.65 as documented in IR 50-266/97025(DRS);
50-301/97025(DRS). The inspectors identified that the licensee had failed to
include the facade freeze protection system in the scope of the maintenance rule
and issued a severity level IV violation (VIO 50-266/97025-01(DRS);
' 50-301/97025-01(DRS)). In a follow-up inspection (IR 50-266/98022(DRS);
50-301/98022(DRS), the inspectors reviewed the licensee's corrective actions
and closed the violation. The inspectors concluded that the scoping deficiency
was properly corrected, portions of the facade freeze protection system were in
the program, and acceptable system performance criteria were established.
During the current inspection, the inspectors were told that the RWST inlet line
heat trace had been missed in the reclassification of the system. Subsequently,
16
a
_ _ - ____ ___ . _ _ _. _ _ . _ _ . . _ _
+
- 4
i
.
the licensee placed the entire facade freeze protection system into the
maintenance rule program, and planned to remove portions of the system only
after a case-by-case evaluation was performed.
On January 8,1998, the Unit 1 high voltage station auxiliary transformer isolated,
as documented in IR 50-266/97026(DRP); 50-301/97026(DRP). The licensee's
event investigation team determined that a short circuit in the bus ductwork
l occurred because of water-saturated and moisture-damaged insulation. The
i root cause of that condition was determined to be the failure of installed strip
- heaters. A work order had been initiated in August 1996 to repair the strip
l heater supply breaker; however, it had been inappropriately classified and was
'
-
still in the licensee's minor maintenance backlog as of January 8,1998. The
licensee implemented corrective actions to preclude recurrence, such as
reviewing the minor maintenance backlog Mr other inappropriately classified
work orders (none were identified) and conducting a periodic review of the
material condition of all strip heater breakers. The licensee subsequently
eliminated the minor maintenance program.
Documented in IR 50-266/98021(DRP); 50-301/98021(DRP), issued on
January 15,1999, are the results of the inspectors' walkdown of portions of the
plant subject to severe cold weather conditions and their review of cold weather ;
preparations. While no immediate safety issues were identified, the inspectors I
were concerned with the cold weather preparation program. Also, as a result of
equipment problems caused by severe cold weather, the licensee had identified
-deficiencies with the operation of the facade freeze protection system. Some
were repetitive from previous years. In response, the licensee entered the
deficiencies into the corrective action systr.n and in late December 1998, plant j
management directed that a root cause 2 valuation be conducted. The j
inspectors had decided to track the lic'. nsee's evaluation of the inspector-
identified issues and the corrective r,ctions for the . licensee-identified facade
freeze protection system deficienr..es as Inspection Followup Item !
(IFI) 50-266/98021-01(DRP); 50 301/98021-01(DRP).
The inspectors retrieved all of the cold weather-related CRs from the licensee's
corrective action database from January 1,1994, to January 5,1999. The inspectors
reviewed the conditions identified in the CRs, the licensee's corrective actions, and the
timeliness of the corrective actions. The CRs that the inspectors reviewed are listed in
the " List of Documents Reviewed" section at the end of this inspection report.
The licensee identified and documented via CRs a variety of cold weather related
concerns over the time period reviewed. In each case, the licensee developed and
implemented, in a timely manner, appropriate corrective action for the concerns
documented in each CR. Some instances of repeated problems previously identified in
CRs did occur, but these typically were prior to completion of planned corrective actions
to prevent reoccurrence. The inspectors did not identify any direct, specific precursors
for the January 5,1999, event from the corrective action database review. However,
l
while the licensee's corrective actions were appropriate for each CR, the actions were
I narrowly focused on resolving the specific concern identified in the associated CR.
.
(- 17
_, _ __ .--
.- .. . - - - _ . _ _. - _ _ - . - . - _ -
. -
l
Conclusions
The licensee had experienced equipment challenges from inadequate cold weather
j preparations and freeze protection system failures from 1994 to the most recent
inspection period. The licensee took appropriate, timely corrective actions for each
-
individual problem; however, not until late December 1998, had the licensee identified
the need to perform a root cause evaluation of the continuing equipment problems with
the facade freeze protection system. The inspectors concluded that the corrective
actions had been adequate, but had not been broad enough in scope to prevent the
January 5,1999, event.
8.0 Corrective Actions identified Durina This Inspection
The inspectors reviewed the intermediate-term corrective actions being taken by the
licensee to address the material condition problems and design and procedural
problems with the facade freeze protection system. Many of these correctiva actions
were described in the licensee event report for the plugged RWST inlet line
(LER 50-266/99001-00). No significant shortcomings were identified. Plant
management was aggressive in its efforts to resolve many of the facade freeze
protection problems discussed in this report.
The licensee informed the inspectors that the Common Cause Event investigation Team
chartered to investigate this event would provide broad, long-term corrective action
recommendations to address any generic cold weather preparation or other
programmatic issues that it identified. The licensee indicated that any such corrective
actions would be provided in a supplement to the LER for this event.
9.0 Miscellaneous issues
(Closed) LER 50-266/99001-00: Safety injection recirculation line to RWST frozen. The
contents of the LER were substantially consistent with the findings of the inspectors. No
significant problems were noted with the corrective actions included in the LER. The
licensee stated that a supplemental LER will be issued to document the findings of its
event investigation team.
(Closed) IFl 50 266/98021-011DRP): 50-301/98021-01(DRP): Plant's cold weather
preparation program. The inspector concerns identified in this item will be tracked to
resolution using eel 50-266/99004-02(DRP).
1
18
. . - . .. _ .. _ _ . . _ .- . . - . .- .
.
'
.
i
l TEMPERATURES AT POINT BEACH
l WHILE WORK ORDER 9819891 WAS OPEN
!
Date Shift 1 Shift 2 Shift 3
12/22/98 -0.5' F -1.2 * F 2.2*F
12/23/98 8 8 16
12/24/98 6 11 16
12/25/98 12.8 15.7 26.8
12/26/98' 28 11 17
12/27/98 24 29 31
12/28/98 15 14 33.7
12/29/98 36.5 28 12
12/30/98 0 -6 4
12/31/98 5 3 7
1/1/99 0 -1.6 13.5
1/2/99 19 22 21.8
1/3/99 22 14.5 18
1/4/99 9 5 7
1/5/99 -9.4 -14.1 4
All readings listed above were recorded in the licensee's " Safeguards Shift Log." Temperatures
were measured at the plant meteorological tower and may vary slightly from actual
temperatures in the facade area.
V Manaaement Meetinas
X1 Exit Meeting Summary
The inspectors presented the inspection results to members of licensee management at the
conclusion of the inspection on Februng 22,1999. The licensee acknowledged the findings
presented. The inspectors asked the licensee whether any materials examined during the
inspection should be considered proprietary. No proprietary information was identified.
l
l
!
19
!
.. _. _ _ . _. - - - _ _.-._.__ _..__ _. _ __ _ _ . _ _ _ _ _ _ . _
s - *
[
l I
! :
! PARTIAL LIST OF PERSONS CONTACTED
i
Licensee
J. G. Schweitzer, System Engineering Manager
J. R. Anderson, Operations Manager i
M. E. Reddemann, Site Vice President
R. G. Mende, Plant Manager
R. P. LaRhette, Manager - Quality Assurance j
i
INSPECTION PROCEDURES USED
IP 40500: Effectiveness of Licensee Controls in identifying, Resolving, and Preventing .
Problems
IP 71707: Plant Operations l
IP 71714: Cold Weather Preparations j
ITEMS OPENED, CLOSED, AND DISCUSSED
Ooened
i
50-266/99004-01(DRP) NCV Failure to maintain a required pror,edure current
following installation of modificatlon work
.
50-266/99004-02(DRP) eel Failure to address the low temperature of a safety-
related pipe
Closed l
50-266/99004-01(DRP) NCV Failure to maintain a required procedure current
following installation of modification work
50-266/99001-00 LER Safety injection recirculation line to RWST frozen
50-266/98021-01(DRP) IFl Plant's cold weather preparation program
50-301/98021-01(DRP)
I
r 20
l
p...
i
.. I
i
LIST OF ACRONYMS USED
l
amp Ampere
CFR Code of Federal Regulations -
CR Condition Report.-
DRP Division of Reactor Projects
DSS _ Duty Shift Supervisor l
l eel Escalated Enforcement item l
l EOP Emergency Operating Procedure '
'F. Degrees Fahrenheit-
gpm Gallons Per Minute
IFl Inspection Followup Item
IP Inspection Procedure
IR . inspection Report
LOCA Loss-of-Coolant Accident
NOED Notice of Enforcement Discretion
NRC Nuclear Regulatory Commission
01 Operating Instruction
PAB Primary Auxiliary Building
psig Pounds Per Square Inch - Gauge
R.O Reactor Operator
RWST Refueling Water Storage Tank
SE . Safety Evaluation
SI. Safety injection
SRO Senior Reactor Operator
T/S Technical Specification
URI Unresolved Item
VIO Violation
WO !
Work Order
.
'
.
c
l
21
l
. - - -. - . .- -
f ,. ,..' o
.
LIST OF DOCUMENTS REVIEWED
Cor.dition Reports
CR 94-011, " Air Leakage on 345 kilovolt Switchyard Breakers," dated January 21,1994
.
CR 94-012 " Unit 2 Seal Well Outlet Valve Failed to Close Electrically," dated
.
January 20,1994
!
l *
CR 94-078, "G-01 Room Intake Louvers Blowing Open," dated February 23,1994
i
a
CR 94-594 " Freeze Protection Circuits Appear incorrect on Drawings," dated
Novemt* ' 1994
.
CR 94-595, " Steam Generator Blowdown Flow Indicator Enclosures and Sensing Lines ,
'
i not Monitored for Freeze Protection," dated November 27,1994
- CR 94-600, " Damaged Insulation on Facade Freeze Conductor," dated November 28, s
1994
a CR 95-011, " Unit 2 Steam Generator Blowdown Flow Indication Frozen," dated
January 4,1995
. CR 94-077, " Unit 1 Steam Generator Blowdown Flow Indicator Frozen," dated
February 13,1995
. CR 95-079, " Cold Weather Concerns in Emergency Diesel Generator Building," dated ,
February 11,1995 ;
- CR 95-623, " Unit 1 Steam Generator Blowdown Tank Level Indicator and Tank Bypass
Valve Frozen in Cold Weather," dated December 9,1995
a CR 95-624, " Steam Generator Flow Indicators Freeze Up," dated December 10,1995
+- CR 94-627, " Tornado Dampers Forced Open by High Winds," dated December 9,1995
-
CR 96-030, " Steam Generator Blowdown Instrumentation Freezes," dated January 20, .
l
1996
. : CR 96-1866, " Unit 2 Steam Generator Steam Header Blowdown Control Valve Slow to
Operate Due to its Heat Tracing Being De-energized," dated December 27,1996
.- CR 97-0158, " Steam Generator Blowdown Flow Indicator Frozen," dated January 17,
1997-
+- CR 97-0630, " Unit 1 Steam Generator Blowdown isolation Valve Frozen," dated
February 25,1997
'
.- CR 97-2783, " Freeze Protection Wiring incorrectly Labeled," dated September 10,1997
22
.. . - - - -- -.
, ._ . _ . - . . - ._._._ _.._._ ._ ._._.___ ____ __._..__ _._.-_____
F s.,...
l.'
4
- CR 97-2918, "Potentially Incorrect Quality Assurance Scoping," dated September 17,-
1997
- - CR 97-2978, " Freeze Protection Circuit 1-FF-01-18A," dated September 20,1997
- CR 97-3807, " Replacement of Facade Freeze Protection Systems Heat Traco Circuits," I
'
dated November 18,1997
+
CR 97-3950, " Facade Freeze Protection Reorder Points / Circuits Bypassed," dated
December 3,1997
l
- CR 97-3995, " Potential for Containment Atmosphere Post-Accident Sample System to
Freeze Up," dated December 8,1997
+
CR 98-0065, "No Status of Temporary Freeze Protection Provided," dated January 11,
.
1998
a CR 98-0070, "G-03 Room Louvers Not Working," dated January 11,1998
.
CR 98-1661, " Freeze Protection Systems Unnecessarily Left in Service During Warm
Weather," dated April 23,1998
- CR 98-4172, " Blowdown Level Transmitter Frozen Due to Facade Temperature," dated
December 28,1998 l
a CR 98-4192, " Steam Generator Blowdown Flow Indicators Frozen," dated December 22,
1998
-* CR 98-4207, "Lakeshore Trailer Complex Well House Pipes Froze," dated
December 23,1998
. CR 99-0019, " Gravity Louvers Allow Snow into G01/G02 Diesel Room," dated ,
- January 2,1999
! * CR 99-0031, " Unit 2 Steam Generator Blow Down Lines Froze Up," dated January 5, I
1999
- CR 99-0036, " Unit 1 "B" Steam Generatar Pressure Sensing Line Frozen," dated
January 5, .1999
! Quality Condition Reports
l
! * QCR 94-010, " Deficiencies Noted in RWST Level Transmitter Freeze Protection
Scheme," c%ted February 23,1994
,
s
5
l 23
,
_ _ _ _ _ _. - __ _ _ _