PNO-III-97-017, on 970218,Unit Shut Down Because of Possible Problem W/Impeller of CCW Pump & Bearing Problem W/Sw Pump Motor.Unit 2 Shut Down for Refueling & SG Replacement. Resident Inspectors Have Been Monitoring Repair

From kanterella
Jump to navigation Jump to search
PNO-III-97-017:on 970218,Unit Shut Down Because of Possible Problem W/Impeller of CCW Pump & Bearing Problem W/Sw Pump Motor.Unit 2 Shut Down for Refueling & SG Replacement. Resident Inspectors Have Been Monitoring Repair
ML20138F518
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 03/03/1997
From: Michael Kunowski, Mccormickbarge
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
References
PNO-III-97-017, PNO-III-97-17, NUDOCS 9705050425
Download: ML20138F518 (2)


_ .. _ _ .--

1 RECEIVED March 3. 1997 im MR 12 AM 8: 09 PRELIMINARY NOTIFICATION OF gCNbhURRENCE PNO-III-97-017 This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. The information is as initially received without verification or evaluation, and is basically all that is known by Region III staff (Lisle. Illinois) on this date.

Facility Licensee Emergency Classification Wisconsin Electric Power Co. Notification of Unusual Event Point Beach 1 Alert Two Rivers. Wisconsin Site Area Emergency Dockets: 50-266 General Emergency X Not Applicable i

Subject:

OUTAGE FOR PUMP REPAIR AND OTHER MAINTENANCE On February 18. 1997. Unit 1 was shut down because of a possible problem with the impeller of a Component Cooling Water (CCW) pump and a bearing problem with a Service Water (SW) pump motor.

Inspections and repairs of the CCW pump and the SW pump motor were completed on February 24 but the unit remained shutdown for additional maintenance activities, including verification of operability of a Residual Heat Removal system check valve. Unit 2 is shut down for refueling and steam generator replacement.

On February 25. Unit 1 left cold shutdown in preparation for restart. As of March 3. the startup continues to be delayed, however, pending resolution of a potential bearing problem on the G03 emergency diesel generator (EDG) (Unit 1 Train B). The G04 EDG (Unit 2 Train B) was taken out of service due to a generator outboard bearing problem. The licensee's initial review indicates that the G04 bearing damage (fluting) was caused by the flow of electrical current through the bearing assembly. Although no bearing degradation has been noted on G03 to date, the licensee is reviewing the potential for a similar problem with G03.

PNO-III-97-017 9705050425 970303 PDR I&E PNO-III-97-017 PDR lE34 oh

. l The resident inspectors have been monitoring the repair and inspection i activities.  !

The State of Wisconsin will be notified. The information in this  !

preliminary notification has been reviewed with licensee management. l 1

This information is current as of 9 a.m. on March 3. 1997. '