ML20217J457

From kanterella
Jump to navigation Jump to search
Insp Repts 50-266/98-10 & 50-301/98-10 on 980310-18. Violations Noted.Major Areas Inspected:Review of Measuring & Test Equipment Procedures
ML20217J457
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 04/01/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20217J443 List:
References
50-266-98-10, 50-301-98-10, NUDOCS 9804060306
Download: ML20217J457 (7)


See also: IR 05000266/1998010

Text

'

U.S. NUCLEAR REGULATORY COMMISSION

REGION 111.

Docket Nos:

50-266; 50-301

License Nos:

DPR-24; DPR-27

Report Nos:

50-266/98010(DRS); 50-301/98010(DRS)

Licensee:

Wisconsin Electric Company

Facility:

Point Beach Nuclear Plant

Units 1 and 2

Location:

6612 Nuclear Road

Two Rivers, WI 54241-9516

Dates:

March 10 - 18,1998

Inspector

Rogelio Mendez, Reactor Engineer, Rlli

Approved by:

John Jacobson, Chief

Lead Engineers Branch

9804060306'900401

PDR

ADOCK 05000266

0

PDR

.

1

'

EXECUTIVE SUMMARY

Point Beach Nuclear Plant

NRC Inspection Report 50-266/98010; 50-301/98010

The inspection included a review of measuring and test equipment (M&TE) procedures. In

addition, the ir,t,pector reviewed the calibration of M&TE; condition reports associated with

M&TE; and disposition of out-of-tolerance, lost or damaged M&TE.

'

Maintenance

The overall control of M&TE was acceptable. The licensee had made several changes

.

to improve the control of M&TE by storing them in a locked room and requiring full-time

attendants to dispense the instruments (Section M3.2).

The M&TE procedures were weak. Three M&TE procedures contained conflicting

.

information and did not contain adequate guidance for proper M&TE control. For

example, the licensee 'was in the process of developing one procedure to control M&TE

for operations, engineering, electrical / mechanical maintenance, and instrumentation and

controls (l&C) (Section M3.1).

Evaluations of some lost, damaged, or out-of-tolerance M&TE were not performed or

.

inadequately performed (Section M3.2). One violation of NRC requirements was

identified.

l

l

4

l

l

i

2

1

f

&

.h

.

ERRort Details

This inspection included a review of measuring and test equipment (M&TE) procedures. In

addition, the inspector reviewed the calibration of M&TE; condition reports (CRs) associated

with M&TE; and disposition of out-of-tolerance, lost or damaged M&TE.

11. Maintenance

M3

Maintenance Procedures and Documentation -

M3.1 M&TE Procedures

a.

Insoection Scoce (62702)

The inspector reviewed the following M&TE procedures:

MWP 112,"MOV Load Sensing Equirment Calibration," Revision 1, June 1,

.

1994

NP 8.7.1, " Maintenance - Control of Measuring and Test Equipment," Revision 2,

.

August 29,1997

NP 8.7.2," Calibration and Control of Measuring and Test Equipment

.-

(Instrumentation and Control)," Revision 1, June 27,1997

OM 5.4.9," Control of Operations Department Measuring and Test Equipment,"

.

Revision 0, June 14,1995

b.

Observations and Findinas

The present M&TE procedures provided guidance for the control of M&TE in the areas

of electrical / mechanical, instrumentation and controls and operations. The engineering

staff used electrical / mechanical maintenance procedure NP 8.7.1, although the

procedure did not state whether its use included the engineering department.

The licensee recognized that the three M&TE procedures were not providing adequate

guidance and included conflicting requirements. As a consequence, the procedures

were being revised to improve the control of M&TE and to develop one procedure that

would be used by maintenance, engineering, and operations. In addition, the inspector

noted that current procedures contained conflicting information. For example,

operations procedure OM 5.4.9 stated that M&TE that cannot be located shall be treated

and evaluated as cut-of-tolerance, while the electrical / mechanical procedure NP 8.7.1,

stated that lost equipment will be treated as out-of-tolerance only when the equipment

exceeded its recalibration frequency by 25 percent, and the instrument and control (l&C)

procedure NP 8.7.2 did not include guidance or requirements for lost M&TE. In addition,

none of the procedures required that the M&TE be signed out. Although all the

3

4

.

,

procedures required that evaluations for out-of-tolerance M&TE be performed, none

included guidance when as-found data could not be determined. Finally, none of the

present procedures provided guidance for the control of M&TE that was checked out for

extended periods of time.

c.

Conclusion

The licensee's M&TE control procedures were weak. The procedures contained

conflicting information and did not contain adequate guidance for proper M&TE control.

For example, the licensee was in the process of developing one M&TE procedure that

should improve the control of M&TE.

M3.2 M&TE Program

a.

Insoection Scoce (62700)

The inspector reviewed M&TE calibration records and CRs.

b.

Observations and findinas

In early 1997, the licensee determined that the M&TE area was poorly controlled.

Maintenance personnel would not sign out M&TE and would keep the equipment for

extended periods of time without locking up the equipment. As a result, the licensee

implemented a number of corrective actions and controis that included storing M&TE in

a locked room and requiring full-time attendants to dispense and log out M&TE. In

addition, a number of CRs were written that identified problems in this area. The

corrective actions were effective and the control of M&TE improved.

The inspector noted, through a review of log records, that most of the M&TE was

returned at the end of the day and that the control of M&TE was acceptable.

The inspector reviewed calibration records and noted that in all cases M&TE was

calibrated within its calibration frequency. However, in some cases, the evaluations

were not performed for lost or damaged M&TE and for M&TE found out-of-tolerance, or

the evaluation was inadequate. In an audit report issued in January 1998, the licensee

identified that the fo!!owing operations M&TE were lost: OPSDH-002, OPSDP-001,

OPSSW-009, and OPSTW-002. Procedure OM 5.4.9, Section 3.4, stated in part,

"M&TE which cannot be located for recalibration when scheduled shall be treated as

out-of-tolerance and evaluated as such." As of March 13,1998, the licensee had not

evaluated these instruments as being out-of-tolerance. Additionally, the inspector noted

that electrical / mechanical maintenance load cell MCLC-001, calibrated on October 17,

1996, had an as-found slope of 1.441. Procedure MWP 112 stated that if the as-found

slope was not within 1.348-1.244, then the load cell was out-of-tolerance. The licensee

did not evaluate this instrument as being out-of-tolerance, as required by procedure

NP 8.7.1, Moreover, M&TE MCCP-007 was damaged and sent out for repairs on

January 28,1998, but the CR that would initiate the evaluation was not issued until

- March 13,1998. For another instrument, MCMA-003, the licensee issued CR 98-0654

4

,

.

I

on February 13,1998, because the DC current and voltage circuits were not functional.

~

In the evaluation and operability determination, the licensee concluded that MCMA-003

was functional when it was used during post maintenance testing and that damage to

the M&TE occurred during shipment to a commerciallaboratory. Consequently, the

licensee did not consider the instrument to be out-of-tolerance and no further action was

taken. However, the inspector noted that as-found data could not be obtained due to

the damage to the DC circuit. Therefore, the licensee could not determine how much

the instrument was actually within or outside of the required tolerance. Although

required by procedure NP 8.7.1, the inspector noted that the CR did not include an

evaluation or require a retest of plant equipment that was tested with instrument

MCMA-003. For the seven M&TE mentioned above, the licensee did not evaluate the

use of these instruments and, as a consequence, failed to take proper corrective

actions.

Title 10 of Code of Federal Regulations, Part 50, Appendix B, Criterion XVI, Corrective

Action," requires, in part, that measures be established to assure that conditions

adverse to quality, such as deficiencies and deviations are promptly identified and

corrected in the case of significant conditions adverse to quality, the measures shall

assure that the cause of the conditions is determined and corrective action taken to

preclude repetition. The failure to evaluate lost, damaged, or out-of-tolerance M&TE is

a violation of 10 CFR Part 50, Appendix B, Criterion XVI (VIO 50-266 /98010-01(DRS);

50-301/98010-01(DRS)).

c.

Conclusions

The calibration of M&TE was acceptable and corrective actions were, in general, good.

,

The licensee improved control of M&TE by storing the M&TE in a locked room and

requiring full time attendants to dispense and log out M&TE. However, evaluations for

out-of-tolerance M&TE were not performed or were inadequate. One violation of NRC

requirements was identified.

V. Management Meetings

X1

Exit Meeting Summary

The inspectors presented the inspection results to members of licensee management at the

conclusion of the inspection on March 18,1998. The licensee acknowledged the findings

presented.

The inspectors asked the licensee whether any materials examined during the inspection

should be considered proprietary. No proprietary information was identified.

5

L. m.-- - - - -

-

-

' ' ---

'

- - - - -

-

--

-

-

--

-- -

-

-

-

-

.

.

PARTIAL LIST OF PERSONS CONTACTED

Licensee

W. B. Fromm, Maintenance Manager

F. A. Flentje, Regulatory Specialist

G. R. Sherwood, Maintenance Field Services Manager

NEG

F. Brown, Senior Resident inspector

LIST OF INSPECTION PROCEDURES USED

IP 62700:

Maintenance implementation

IP 62702:

Maintenance Program

LIST OF ITEMS OPENED

50-266/98010-01(DRS); 50-301/98010-01(DRS)

VIO

Corrective Action

)

6

a

.

a

.

LIST OF ACRONYMS USED

CFR

Code of Federal Regulations

CR

Condition Reports

DRS

. Division of Reactor Safety

I&C

Instrumentation and Controls

M&TE

Measuring and Test Equipment

NOV

Notice of Violation

NRC

Nuclear Regulatory Commission

PARTIAL LIST OF DOCUMENTS REVIEWED

MWP 112, "MOV Load Sensing Equipment Calibration," Revision 1, June 1,1994

NP 8.7.1, " Maintenance - Control of Measuring and Test Equiprnent," Revision 2, August 29,

1997

NP 8.7.2," Calibration and Control of Measuring and Test Equipment (Instrumentation and

Control)," Revision 1, June 27,1997

OM 5.4.9, " Control of Operations Department Measuring and Test Equipment," Revision 0,

June 14,1995

1

7

.

-

-

1