Letter Sequence RAI |
---|
EPID:L-2021-LLA-0021, License Amendment Request to Approve Pilgrim Nuclear Power Station Independent Spent Fuel Storage Installation Only Emergency Plan (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement
|
MONTHYEARNG-20-0090, Certification of Permanent Removal of Fuel from the Reactor Vessel for Duane Arnold Energy Center2020-10-12012 October 2020 Certification of Permanent Removal of Fuel from the Reactor Vessel for Duane Arnold Energy Center Project stage: Request NG-20-0083, Registration of Independent Spent Fuel Installation Storage Casks2020-10-12012 October 2020 Registration of Independent Spent Fuel Installation Storage Casks Project stage: Request L-21-008, License Amendment Request to Approve Pilgrim Nuclear Power Station Independent Spent Fuel Storage Installation Only Emergency Plan2021-02-18018 February 2021 License Amendment Request to Approve Pilgrim Nuclear Power Station Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: Request L-21-090, Discharge Monitoring Report Cnpdes) Permit No. PA00256152021-02-23023 February 2021 Discharge Monitoring Report Cnpdes) Permit No. PA0025615 Project stage: Request ML21069A3312021-03-15015 March 2021 Acceptance of Requested Licensing Action Re Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: Acceptance Review L-21-057, Supplemental Information to Update - License Amendment Request to Approve the Pilgrim Nuclear Power Station Independent Fuel Storage Installation Only Emergency Plan2021-05-20020 May 2021 Supplemental Information to Update - License Amendment Request to Approve the Pilgrim Nuclear Power Station Independent Fuel Storage Installation Only Emergency Plan Project stage: Supplement ML21158A1232021-06-24024 June 2021 License Amendment No. 46, Revised License Termination Plan Project stage: Request ML21158A1262021-06-24024 June 2021 Letter - Humboldt Bay Power Plant Unit 3 - Issuance of Amendment No. 46 Re License Termination Plan Project stage: Approval ML21158A1132021-06-28028 June 2021 License Amendment Application - Revision of the License Termination Plan - May 3, 2021 Request for Additional Information Response Clarification Call Project stage: RAI NG-21-0010, License Amendment Request (TSCR-192): Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme2021-06-28028 June 2021 License Amendment Request (TSCR-192): Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme Project stage: Request ML21161A1072021-07-0909 July 2021 Request for Additional Information Regarding Pilgrim License Amendment Request ISFSI Only Emergency Plan Project stage: RAI ML21223A2412021-08-16016 August 2021 Letter to A. Sterdis, HDI, from A. Snyder, NRC - Pilgrim Nuclear Power Station - Request for Additional Information Regarding Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: RAI ML21223A2392021-08-16016 August 2021 Request for Additional Information Regarding Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: Request ML21223A2422021-08-16016 August 2021 Enclosure - Pilgrim Nuclear Power Station - Request for Additional Information Regarding Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: RAI ML21238A2752021-08-26026 August 2021 Clarification Call Regarding RAI License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: RAI L-21-098, Response to Request for Additional Information (RAI) - License Amendment Request to Approve the Pilgrim Nuclear Power Station Independent Fuel Storage Installation Only Emergency Plan2021-09-0707 September 2021 Response to Request for Additional Information (RAI) - License Amendment Request to Approve the Pilgrim Nuclear Power Station Independent Fuel Storage Installation Only Emergency Plan Project stage: Response to RAI ML21257A3832021-09-15015 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Follow-on Request Re Request for Additional Information 2 Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Pl Project stage: RAI ML21257A3792021-09-15015 September 2021 Clarification Call 2 Re Request for Additional Information Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: Request ML21257A3822021-09-15015 September 2021 Summary of Clarification Cal with Holtec Decommissioning International, Llc. Regarding Second Follow-On Emergency Preparedness Request for Additional Information Project stage: RAI ML21287A6192021-10-14014 October 2021 E-mail from S. Phillips, MEMA, to A. Snyder, NRC, Pilgrim Nuclear Power Station, Commonwealth of Massachusetts Consultation Response to Amendment Review for Emergency Preparedness Project stage: Request ML21265A3032021-10-21021 October 2021 Enclosure 2 - Pilgrim ISFSI Only SER Input Final Project stage: Other ML21251A1622021-10-21021 October 2021 Ioep Amendment No. 257 Project stage: Request ML21251A1732021-10-21021 October 2021 Enclosure 1 - Pilgrim Amendment No. 257 ISFSI Only Emergency Plan Project stage: Other ML21251A1722021-10-21021 October 2021 Issuance of Amendment No. 257 ISFSI Only Emergency Plan Cover Letter Project stage: Approval ML21335A0712021-12-0101 December 2021 Request for Additional Information - Duane Arnold Energy Center ISFSI Only Emergency Plan Project stage: RAI ML21335A0702021-12-0101 December 2021 Cover Letter to B. Coffey from K. Conway - Duane Arnold Energy Center RAI Re License Amendment Request for ISFSI Only Emergency Plan Project stage: RAI ML21335A0662021-12-0101 December 2021 Request for RAI License Amendment Request ISFSI Only EP Project stage: Request ML22357A1002023-03-31031 March 2023 And Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendments Standard Emergency Plan and Consolidated Emergency Operations Facility Project stage: Approval 2021-05-20
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML21300A0272021-10-28028 October 2021 Clarification Call, Summary of October 21, 2021, Clarification Call with Pacific Gas and Electric Company Regarding Final Status Survey Report HBL-21-010, Survey Unit OOL01-03 ML21287A2512021-10-26026 October 2021 Meeting Summary 2021-10-13 Humboldt Bay Independent Spent Fuel Storage Installation (ISFSI) ML21217A0702021-08-0505 August 2021 Summary of Clarification Call with Pacific Gas and Electric Company Regarding Trailer City Final Status Survey Report ML21158A1132021-06-28028 June 2021 License Amendment Application - Revision of the License Termination Plan - May 3, 2021 Request for Additional Information Response Clarification Call ML19296A0952019-10-28028 October 2019 Summary of the August 26, 2019, Public Meeting Near the Humboldt Bay Power Plant Regarding the Establishment and Operation of Community Advisory Boards ML13357A8082013-12-24024 December 2013 B. Watson Memo Meeting Summary of December 5, 2013 Humboldt Bay on License Termination Plan ML13357A7952013-12-24024 December 2013 B. Watson Memo Meeting Summary of December 5, 2013 Meeting with PG&E on Humboldt Bay Emergency Plan ML13274A0572013-10-0202 October 2013 August 20, 2013 Summary of Meeting for Humboldt Bay ML1107001862011-03-15015 March 2011 Summary of Public Meeting with Pacific Gas & Electric to Discuss Decommissioning Actions Related to Humboldt Bay, Unit 3 ML0731201642007-10-23023 October 2007 Summary of Meeting to Discuss Humboldt Bay Power Plant Unit 3 Plans and Schedule for the Fossil Repowering Project ML0706105072007-03-15015 March 2007 Summary of Meeting with Pacific Gas & Electric to Discuss for Decommissioning and License License Termination of Humboldt Bay (Hbpp), Unit 3 and Plans for the Fossil Repowering Project and Its Interface with Hbpp ML0503303912005-02-0202 February 2005 Summary of Meeting with Pacific Gas and Electric Company to Discuss the Application for the Humboldt Bay ISFSI (Tac No. L23683) ML0502403142005-01-25025 January 2005 Summary of Meeting Between the Nuclear Regulatory Commission Staff and Pacific Gas and Electric Regarding the Humboldt Bay Power Plant Special Nuclear Material Control and Accountability Project ML0412101482004-04-29029 April 2004 Summary of Meeting with Pacific Gas & Electric and Holtec Regarding Plans Related to the Installation of a Single-Failure-Proof Crane at Humboldt Bay ML0402801032004-01-26026 January 2004 Memorandum to L. Camper from J.R. Hall - 12/19/2003 Summary of Meeting with Pacific Gas and Electric Company Regarding the Humboldt Bay Independent Spent Fuel Storage Installation License Application (TAC No. L23589) ML0320601582003-07-24024 July 2003 Summary of Meeting with Pacific Gas and Electric Company Regarding a Proposed Independent Spent Fuel Storage Installation at Humboldt Bay 72-27 (TAC L23589) ML0203505932002-02-0101 February 2002 Memo to C. L. Miller from: T. J. Kobetz Subject: Summary of the January 24, 2002, Meeting Between the Nuclear Regulatory Commission Staff and Pacific Gas and Electric, Co. Enclosures: 1.) Attendance List; and 2) PG&E Project Slides ML0200802402002-01-0808 January 2002 Memo to C. L. Miller from: T. J. Kobetz Subject: Summary of the December 21, 2001, Meeting Between the Nuclear Regulatory Commission and Pacific Gas and Electric Company (TAC No. L23358) Attachment: Attendance List ML0037739982000-11-30030 November 2000 Memo to S. Shankman from: T.J. Kobetz Subject: Summary of the November 17, 2000, Meeting Between the NRC and Pacific Gas and Electric Co. Attachments: 1.) Attendance List; 2.) Pge Slides ML17252A0301976-03-24024 March 1976 Summary of Meeting Regarding BWR Feedwater Nozzle Cracking 2021-08-05
[Table view] Category:Memoranda
MONTHYEARML21158A1132021-06-28028 June 2021 License Amendment Application - Revision of the License Termination Plan - May 3, 2021 Request for Additional Information Response Clarification Call ML19296A0952019-10-28028 October 2019 Summary of the August 26, 2019, Public Meeting Near the Humboldt Bay Power Plant Regarding the Establishment and Operation of Community Advisory Boards ML19120A2172019-04-26026 April 2019 Memo to File Environmental Assessment and Finding of No Significant Impact for Energy Northwest Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72,30(b) and 72.30(c) for Humboldt Bay ISFSI ML18173A0082018-06-20020 June 2018 Cancelling Numerous Inspection Report Numbers ML18022A1512018-01-16016 January 2018 Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay Independent Spent Fuel Storage Installation License ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning ML16106A1212016-04-26026 April 2016 Notice of Availability of Environmental Assessment and Finding of No Significant Impact for the License Termination Plan for Humboldt Bay Power Plant, Unit 3 ML14206A9492014-07-28028 July 2014 Memo to Anderson, Work Request for Humboldt Bay Emergency Plan ML14099A4862014-04-14014 April 2014 Memo to Gene Carpenter, NRR Requesting Technical Assistance on Review of Financial Information for the Humboldt Bay License Termination Plan ML13357A8082013-12-24024 December 2013 B. Watson Memo Meeting Summary of December 5, 2013 Humboldt Bay on License Termination Plan ML13357A7952013-12-24024 December 2013 B. Watson Memo Meeting Summary of December 5, 2013 Meeting with PG&E on Humboldt Bay Emergency Plan ML13319A8952013-11-19019 November 2013 Public Meeting Notice to Discuss the Proposed Submittal of Humboldt Bay Emergency Plan Changes Requiring Prior NRC Approval ML13319A9202013-11-19019 November 2013 Notice of Public Meeting on Humboldt Bay License Termination Plan ML13274A0572013-10-0202 October 2013 August 20, 2013 Summary of Meeting for Humboldt Bay ML13191A1842013-07-30030 July 2013 Memo to Cindy Bladey Humboldt Bay Power Plant Unit 3- Notice of Public Meeting on License Termination Plan ML13198A5442013-07-18018 July 2013 August 20, 2013 Meeting Notice to Discuss Humboldt Bay Decommissioning Process, License Termination Plan and Obtain Public Comments ML13136A3222013-05-21021 May 2013 Memo Request for Technical Assistance on License Termination Plan for Humboldt Bay ML13133A2502013-05-15015 May 2013 C. Mckenney Memo Request for Technical Assistance on License Termination Plan for Humboldt Bay ML13017A3692013-01-18018 January 2013 Notice of Meeting with Licensee to Discuss License Termination Plan Submittal and Possible Fourth 20.2002 Alternate Disposal Request ML12191A3362012-11-21021 November 2012 Memo Notice of Environmental Assessment and Finding of No Significant Impact Related to Exemption from the Implementation Deadline for New Emergency Preparedness Planning Regulations - Huboldt Bay Power Plant Unit 3 ML12240A3192012-08-28028 August 2012 Memo Request for Technical Assistance on Proposed Exemption from the Revised Emergency Planning Rule for the Humboldt Bay Power Plant ML12130A3562011-07-15015 July 2011 ROI, Case No. 4-2011-020 ML1117216592011-06-23023 June 2011 C. Mckenney Memo Request for Technical Assistance on Review of Proposed Disposal in Accordance with 10 CFR 20.2002 for the Humboldt Bay Power Plant ML1107001862011-03-15015 March 2011 Summary of Public Meeting with Pacific Gas & Electric to Discuss Decommissioning Actions Related to Humboldt Bay, Unit 3 ML1103800482011-02-0909 February 2011 Notice of Meeting with Pacific Gas & Electric to Discuss the License Termination Plan for the Site and a Possible 20.2002 Alternate Disposal Request ML12130A3552010-12-22022 December 2010 ROI, Case No. 4-2010-044 ML1028700822010-11-0202 November 2010 Memo to Cindy Bladey Submitting FRN - Notice of Environmental Assessment and Finding of No Significant Impact for Exemption of Material in Accordance with 10 CFR Part 20.2002 for Proposed Disposal Procedures - Humboldt Bay Power Plant, Unit ML1018900822010-07-13013 July 2010 Meeting Notice - Humboldt Bay Power Plant, Unit 3 ML12130A3542010-07-0202 July 2010 Report of Investigation (Roi), Case No. 4-2010-002 ML1013401762010-05-20020 May 2010 Memo to File on Basis for Categorical Exclusion from NEPA Analysis of Humboldt Bay Power Plan Unit 3 Amendment Deletion of Fuel Storage Pool Liner Water Level ML12130A3512009-04-23023 April 2009 Memorandum to Regional Administrator, Region IV, Case No. 4-2009-026F ML0810505062008-04-25025 April 2008 Memo to Lesar Re Humboldt Bay Security After Fuel Move Environmental Assessment ML0615702672006-06-22022 June 2006 Fr Notice of EA and Finding of No Significant Impact Related Issuance of a License Amendment for Humboldt Bay Power Plant Unit 3 (TAC L52673) ML0503303912005-02-0202 February 2005 Summary of Meeting with Pacific Gas and Electric Company to Discuss the Application for the Humboldt Bay ISFSI (Tac No. L23683) ML0502403142005-01-25025 January 2005 Summary of Meeting Between the Nuclear Regulatory Commission Staff and Pacific Gas and Electric Regarding the Humboldt Bay Power Plant Special Nuclear Material Control and Accountability Project ML0402801032004-01-26026 January 2004 Memorandum to L. Camper from J.R. Hall - 12/19/2003 Summary of Meeting with Pacific Gas and Electric Company Regarding the Humboldt Bay Independent Spent Fuel Storage Installation License Application (TAC No. L23589) ML0320601582003-07-24024 July 2003 Summary of Meeting with Pacific Gas and Electric Company Regarding a Proposed Independent Spent Fuel Storage Installation at Humboldt Bay 72-27 (TAC L23589) ML0203505932002-02-0101 February 2002 Memo to C. L. Miller from: T. J. Kobetz Subject: Summary of the January 24, 2002, Meeting Between the Nuclear Regulatory Commission Staff and Pacific Gas and Electric, Co. Enclosures: 1.) Attendance List; and 2) PG&E Project Slides NRC Generic Letter 1989-111989-06-30030 June 1989 NRC Generic Letter 1989-011: Resolution of Generic Issue 101 Boiling Water Reactor Water Level Redundancy 2021-06-28
[Table view] |
Text
LICENSEE:
Pacific Gas and Electric Company FACILITY:
Humboldt Bay Power Plant, Unit 3
SUBJECT:
SUMMARY
OF MAY 3, 2021, REQUEST FOR ADDITIONAL INFORMATION RESPONSE CLARIFICATION CALL WITH PACIFIC GAS AND ELECTRIC COMPANY REGARDING PROPOSED REVISION TO THE HUMBOLDT BAY POWER PLANT, UNIT 3 LICENSE TERMINATION PLAN The U.S. Nuclear Regulatory Commission (NRC) conducted a clarification call with Pacific Gas and Electric Company, the licensee, on May 3, 2021. The purpose of the meeting was a clarification teleconference to ensure NRC staff understands certain aspects of the request for additional information (RAI) responses that were submitted on April 29, 2021 (Agencywide Document Access and Management System Accession No. ML21119A214) for the Humboldt Bay Power Plant, Unit 3 proposed license application request to revise the License Termination Plan.
The meeting began with opening remarks by the NRC staff, followed by introductions of the attendees. A list of attendees is enclosed.
The NRC staff reviewed RAI response to ensure understanding related to the bounding dose provided in RAI response 1 b paragraphs (last paragraph on page 3 of 4 and last paragraph on page 4 of 4) based on its data set. Also, the NRC staff stated it was unclear whether the licensee could reanalyze samples if needed at the present time.
Regarding the bounding dose it determined from the quality assurance data set, the Licensee stated it would review its calculations and supplement the RAI response, if needed. Regarding reanalysis, the Licensee stated that it believes it has obtained all the samples relevant for demonstrating the Final Status Survey of the site but it neglected to archive its samples such that additional analysis of the samples is not possible.
The licensee explained that if it determines it needs to update its RAI response after checking its bounding dose estimate, it would provide a supplement by the end of May 2021.
The NRC staff informed the Licensee that the NRC staff believes that it will be able maintain its current review schedule provide any supplemental information is submitted by the end of May 2021.
June 28, 2021
Pacific Gas and Electric Company At this meeting, the NRC staff made no regulatory decisions regarding the merits of the proposed physical security plan change at Pilgrim.
Please direct any inquiries to me at (301) 415-6822 or Amy.Snyder@nrc.gov.
Sincerely, Amy M. Snyder, Senior Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery and Waste Programs Office of Nuclear Reactor Regulation Docket No. 50-133
Enclosure:
List of Attendees Signed by Snyder, Amy on 06/28/21
ML21158A108; Ltr ML21158A113 OFFICE NMSS/DUWP/RDB NMSS/DUWP/RDB NMSS/DUWP/RDB NAME ASnyder BWatson ASnyder DATE Jun 7, 2021 Jun 8, 2021 Jun 28, 2021