ML20081C289

From kanterella
Jump to navigation Jump to search
Simulator Four Yr Certification Rept,Mar 1995
ML20081C289
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 03/31/1995
From:
COMMONWEALTH EDISON CO.
To:
Shared Package
ML20081C281 List:
References
NUDOCS 9503170192
Download: ML20081C289 (15)


Text

. .

QUAD CITES SIMULATOR FOUR YEAR CERTIFICATION REPORT MARCH,1995 I. Introduction The Quad Cities Simulator is used to conduct NRC Licensing Examinations and is therefore required to meet criteria established in 10CFR 55.45. A report identifying simulator testing status must be submitted to the commission every four years on the anniversary of the simulator certification. The r,.t.Td Cities Simulator was certified March 26, 1991.

The Quad Cities Simulator is owned and operated by Comed and Iowa Gas and Electric Companies for the training and testing of Quad Cities Nuclear Power Plant operators. Because of the near duplication between the two Quad Cities units, the simulator is considered a plant specific simulator for both Quad Cities Unit One and Unit Two, hereafter referred to as the Quad Cities Simulator. The Quad Cities Simulator models Quad Cities Unit one with Unit One being considered the reference plant. The simulator was constructed by Link-Miles Simulation Corporation and was declared ready for training in April 1990.

This report summarizes the simulator testing performed since the last certification report submitted to the NRC. A full report including test data for any certification year is available upon request. For the purpose of this report, a certification year starts on March 18 of a year and ends on March 18 of the following year.

II. References Title 10, Code of Federal regulations, Part 55, " Operator Licenses",

Subpart E, section 45.

U. S. Nuclear Regulatory Guide 1.149, " Nuclear Power Plant Simulation Facilities for Use in Operator License Examinations".

ANSI /ANS 3.5 1985, " Nuclear Power Plant Simulators'for Use in Operator Training".

III. Reporting Requirements The requirements for this report as outlined in 10CFR 55.45 are:

A. Paragraph 55.45 (b) (5) (ii) : Identify any uncorrected performance test failure, and submit a schedule for correction of such performance failures, if any.

1 9503170192 950309 PDR ADOCK 05000254 R PDR

B. Par graph 55.45 (b) (5) (vi) : A descripticn of performance testing completed for the simulator facility.

C. Paragraph 55.45 (b) (5) (vi) : A description of performance test, if different, to be conducted on the simulation facility during the subsequent four year period.

D. Paragraph 55.45 (b) (5) (vi) : A schedule for the conduct of approximately 25 percent of the performance test per year for the subsequent four years.

IV. Implementation:

A. Identify any uncorrected performance test failures.

1. All certified performance test failures discovered during testing have been corrected.

B. Provide a description of performance testing completed for the simulation facility.

1. Computer Real Time Test This test verifies that the simulator computer remains in "Real Time" while doing complicated calculations. This test was performed annually.
a. Certification year 1991-1992 test was satisfactory. l
b. Certification year 1992-1993 test was satisfactory.  !
c. Certification year 1993-1994 test was satisfactory. J
d. Certification year 1994-1995 test was satisfactory. ]

1

2. Steady State Test )

The steady state test is divided into two parts, a one hour i stability test and full and interim power tests. The stability test verifies the computed values do not deviate more than two percent in an hours time. The power test compares simulator computed data to actual plant data over the power range. These test are performed annually.

a.1) Certification year 1991-1992 Stability Test satisfactory 1

2) Certification year 1992-1993 Stability Test satisfactory )
3) Certification year 1993-1994 Stability Test satisfactory
4) Certification year 1994-1995 Stability Test satisfactory 2

(Steady State Test Continued) i b.1) Certification year 1991-1992 power tests at g

25%, 50%, 75% and 100% power were satisfactory.

2) Certification year 1992-1993 power tests at 25%, 50%, 75% and 100% power were satisfactory.
3) Certification year 1993-1994 power tests at i 25%, 50%, 75% and 100% power were satisfactory.
4) Certification. year 1994-1995 power tests at ,

25%, 75% and 100% power were satisfactory.

r

3. Normal Operations Test Normal plant operations specified in ANSI /ANS-3.5 1985, section 3.1.1. are performed on the simulator as a test to ensure the procedures can be performed using only operator actions nornal to. the reference plant operation. The i evolutions consist of startups, shutdowns, power operations j and surveillance tests. These tests were performed over the four year certification period as indicated below:
a. For certification year 1991-1992, all Normal Operation tests were performed satisfactorily,
b. For certification year 1992-1993, Power Operation tests were performed satisfactorily. I
c. For certification year 1993-1994, Surveill.ance tests were .

performed satisfactorily.

d. For certification year 1994-1995, Plant shutdowns and  ;

selected Surveillance tests were performed 1 satisfactorily.  !

4. Transient Tests  !

Transient tests, as specified in ANSI /ANS-3.5 1985 Appendix  !

B, were performed, plotted and then evaluated to be l consistent to actual plant transients, UFSAR or best guess opinion. Transient tests were performed and evaluated l annually.

a. Certification year 1991-1992 tests were satisfactory.
b. Certification year 1992-1993 tests were satisfactory. ,
c. Certification year 1993-1994 tests were satisfactorv. i
d. Certification year 1994-1995 tests were satisfactory.

l 3

l

- _\

-t

5. Malfunction Testo ,

Malfunction' tests were performed using Acceptance Test Procedures at a rate of about 25% per year. Since the last  ;

NRC report, all malfunctions have been tested and any noted i discrepancies have been corrected.  !

a. Certification year 1991-1992 Malfunction Tests were I

satisfactory.

b. Certification y3ar 1992-1993 Malfunction' Tests were satisfactory.
c. Certification year 1993-1994 Malfunction Tests were ,

satisfactory. l

d. Certification year 1994-1995 Malfunction Tests were satisfactory. .

C. A description of performance tests, if different, to be conducted  !

on the simulation facility during the subsequent four-year period. ,

I

1. Refer to section IV.D. for a complete listing of performance testing to be completed in the next four year period. No new i performance tests have been added.

i t

D. A description of approximately 25 percent of performance tests ,

per year for the subsequent four years.  ;

1. The following tests will be performed annually:
a. Computer Real Time Test
b. Steady State Tests ~at full power and interim power levels at which valid reference plant data is available.
c. 100% Power One Hour Stability Test  ;
d. Transient Tests: l

-Manual reactor Trip j

-Simultaneous Trip of All Reactor Feed Pumps j

-Simultaneous Closure of All MSIV's

-Simultaneous Trip of All Recirculation Pumps

-Single Recirculation Pump Trip i

-Main Turbine Trip (Maximum power that does not result )

in a immediate reactor trip)-

-Maximum Rate Power Ramp

-Maximum Size LOCA combined with a Loss of Offsite j Power

-Maximum Size Unisolable Steam Line Rupture  !

-Simultaneous Closure of All MSIV's combined with a Single Stuck Open Safety / Relief Valve (Inhibit high pressure ECCS pumps) ,

4 l

w

'2. The following tests will be performed during the 1995-1996 certification year:

a. Normal Operation Tests: .

-Normal Reactor Startup to full power conditions

-Reactor Startup from, cold conditions to hot standby conditions

-Reactor Startup from hot standby to full power conditions

-Reactor Startup to power conditions with less than full reactor coolant flow

-Any other Normal Operations Test that, due to plant modification or procedure changes, warrant immediate testing to validate simulator performance

b. Approximately 25 percent of the certified malfunctions per.the attached malfunction test schedule
3. The following tests will be performed during the 1996-1997 certification' year: l i
a. Normal Operation Tests:

-Hot Scram Recovery to rated power conditions

-Hot Standby Operations

-Power Load Changes

-Power Operations with Less than Full reactor Coolant  ;

Flow

-Any other Normal Operation Test that, due to plant ,

modification or procedure changes, warrant immediate j testing to validate simulator performance l

b. Approximately 25 percent of the certified malfunctions l per the attached malfunction test schedule
4. The following tests will be performed during the 1997-1998 ,

certification year: l

a. Normal Operation Tests:

-All Surveillance tests covered by the criteria:

1) Safety Related System
2) Required Frequency of Monthly or Less l 3) Have Observable Results On Control Board Indicators

- Any other Nornal Operation Test that, due to plant )

modification or procedure changes, warrant immediate i testing to validate simulator performance

b. Approximately 25 percent of all certified malfunctions per the attached malfunction test schedule 5
1 t
  • - l t
  • ?

'5. The following tests will be performed during the. 1998-1999- j certification year: j

a. Normal Operation Tests:

-Normal Reactor Shutdown'to cold conditions ,

-Reactor Shutdown to Hot' Standby conditions I

-Reactor Shutdown from Hot Standby to cold conditions: '!

-Reactor Shutdown with less than full coolant flow l conditions 1 I

i -Any other Normal Operation Test that, due to plant.

modification ~or procedure l changes, warrants immediate i testing to validate simulator performance 1

b. Approximately 25 percent of all certified-malfunctions per the attached malfunction test schedule e

l I

i i

)

i I

6

a-O O 4

4 0

1 a

l B

QUAD CITIES SIMULATOR CERTIFIED MALFUNCTION TESTING SCHEDULE 1995 TO 1999 i

7 l

l

i.

-r i

-l SIMULATOR MALFUNCTION' TEST SCHEDULE. j ANNUAL TESTING PERIOD

-MALF MALFUNCTION 3/95- 3/96- 3/97- 3/98- i NO. DESCRIPTION 3/96 3/97 3/98 3/99 ..

1 AD01 Relief Valve Setpoint Drift' X l

.AD02 Relief Valve ADS Solenoid Fail X 2 AD03 ADS 110 Second Timer Fails l To Start X '

AD07 Relief Valve Sticks X j CRO1 Fuel Element Failure X '

CR02 Gross Fuel Element Failure X j

.CSO1 Core Spray Pump Trip X l CS02 Core Spray Fump Reduced Capacity X ,

CS03 Core Spray Injection Valve Fails To Auto Open _ X CSO4 Core Spray Logic Fails To Initiate X  !

CS07 Core Spray Injection Valve Binding X  ;

CUO1 RWCU Pump Trip X l CUO3 RWCU System Leak At Regen Heat  !

Exchanger Inlet X i

DG01 Diesel Gen Trips And Locks Out X l DG02 Diesel Gen Output Breaker Trip X i DG03 Diesel Engine Fails To Start X DG04 Diesel Engine Auto Start Failure X j i

ED01 345 KV Switchyard Breaker Trip X ,

ED02 Loss Of Reserve Auxiliary Transformer X ED03 4.16 KV BUS Failure X ED04 4.16 KV Breaker Fails To Close X ED05 480 VAC BUS Failure X ED06 480 VAC Breaker Fails To Close X i ED07 480 VAC BUS Tie Breaker Trip X ED09 120/240 VAC Instrument BUS Failure X ED10 120/240 VAC Essential Service 1 BUS Failure X ED12 250 VDC MCC Failure X ED13' 125 VDC BUS Failure X l ED14 48/24 VDC BUS Failure X 8

5 e

, r SIMULATOR MALFUNCTION TEST SCHEDULE ANNUAL TESTING PERIOD  !

MALF MALFUNCTION 3/95- 3/96- 3/97- 3/98- l NO. DESCRIPTION 3/96 3/97 3/98 3/99 >

EG01 Main Generator Trip X  !

1EG02 Main Generator Lockout Relay -i Fails To Trip X >

EG04 : Main' Generator Stator Coolant i

, Runback Failure X l EGOS Main Generator Stator Coolant  !

Pump Trip X

'FP01 Diesel Fire Pump Trip X l l

FW01 Reactor Feed Pump Trip X FWO2 Standby Reactor Feed Pump  !

' Auto Start Failure X l FWO3 Reactor Feed Pump Fails

  • To Auto Trip X ,

FWO4 Reactor Feed Pump Reduced Capacity X FWO6 Reactor Feed Pump Flow Transmitter Failure X FWO7 Feedwater Level Control Valve Failure- X FWO8 Feedwater Level Control Valve i Lock Up X I

FWO9 FW Line Rupture Inside The Drywell Before The Check Valve X  ;

FW10 FW Line Rupture'Inside The  !

Drywell After The Check Valve X  ?

FW11 FW Line Rupture Outside The Drywell In The Steam Tunnel X '

FW12 FW Line Rupture Outside Drywell j At FW Reg Valve Inlet X y

.FW14 LP FW Heater Al Tube Rupture X FW15 LP FW Heater B Tube Rupture X ,

FW16 HP FW Heater D Tube Rupture X l FW17 Condensate / Condensate Booster l Pump Trip X FW18 Condensate Booster Pump Reduced Capacity X FW19 Condensate Pump Reduced Capacity X 9

4 i

SIMULATOR MALFUNCTION TEST SCHEDULE ANNUAL TESTING PERIOD MALF MALFUNCTION 3/95- 3/96- 3/97- 3/98-NO. DESCRIPTION 3/96 3/97 3/98 3/99 FW21 Hotwell Makeup Control Valve Failure X FW22 Hotwell Reject Control Valve Failure X HP01 HPCI Turbine Trip X HP02 HPCI Turbine Fails To Auto Trip X HP03 HPCI Main Pump Reduced Capacity X HPO4 HPCI Minimum Flow Valve Fails To Auto Open X HP09 HPCI Flow Controller Failure X HP10 Inadvertent HPCI Initiation X HP11 HPCI Failure Tc Initiate X HP13 HPCI Steamline Rupture Inside The HPCI Room X HP14 Partial Group Four Isol. Actuation X HP15 Group Four Isolation Fails To Actuate X HP16 Safe Shutdown Pump Trip X HP17 HPCI Injection Valve Binding X HV01 Reactor Building Ventilation Fails To Auto Isolate X IA01 Instrument Air Compressor Trip X IA02 Reactor Building Instrument Air System Rupture X IA03 Service Air To Instrument Air Backup Failure X IA04 Turbine Building Instrument Air System Rupture X IA05 Scram Air Header Leak X IA07 Drywell Nitrogen Compressor Trip X IA08 Drywell Nitrogen System Leak Inside The Drywell X MC01 Circulating Water Pump Trip X MCO2 Circulating Water Pump Discharge Valve Fails To Open X i

10 l

l

SIMULATOR MALFUNCTION TEST SCHEDULE j l

, ANNUAL TESTING PERIOD '

MALF MALFUNCTION 3/95- 3/96- 3/97- 3/98- ,

NO. DESCRIPTION 3/96 3/97 3/98 3/99  !

t MC03 Circulating Water Pump Discharge l i

Valve Fails To Close X MC04 Main Condenser Tube Sheet Blockage X MC07 Main Condenser Tube Leak X e MC08 Main Condenser Air Inleakage X MC09 SJAE Regulator Failure X MC10 SJAE Suction Valve Fails Closed X '

MC11 SJAE Suction Valve Fails To Auto Close X MS01 Main Steam Isolation Valve Closure X MS02 Main Steam Isolation Valve Fails i To Close X MS03 Main Steam Isolation Valve Slow .

Closure Time X MS05 Main Steamline Break Inside Drywell After Restrictor X MS06 Relief Valve Seat Eroded X  !

MSO9 Main Steamline Break In The Steam Tunnel X MS10 Main Steam Leak In The Turbine Building X MS12 Loss Of Extraction Steam To LP FW Heater B X MS13 Loss Of Extraction Steam To LP FW Heater C X MS14 Loss Of Extraction Steam To HP FW Heater D X MS16 Relief Valve Tailpipe Break In '

The Suppression Chamber X ,

NM01 SRM Channel Failure X NM02 Flow Converter Failure X NM03 SRM Detector Stuck X i NMOS IRM Channel Failure X NM06 IRM Channel Out Of Calibration X '

NM07 IRM Detector Stuck X NM08 APRM Channel Failure X NM10 RBM Channel Failure X r 11 1

. - - . _ _ _ . _ ___ _ a

.' l y .  ;

?

I i

l SIMULATOR MALFUNCTION TEST SCHEDULE  ;

ANNUAL TESTING PERIOD ,

MALF MALFUNCTION 3/95- 3/96- '3/97.- 3/98-

'NO. DESCRIPTION 3/96 3/97 3/98 3/99 ,

NM14 LPRM Detector Failure X l

PC01 Drywell Cooler Blower Trip X PC04 Drywell Vacuum Breaker Fails Open X  !

PC07 Suppression Pool Flange Leak X l PC08 Standby Gas Treatment Fan Trip X l PC09 Standby Gas Treatment Fan Fails To  :

Auto Start X  ;

PC11 Standby Gas Treatment Flow  !

Controller Failure X  ;

RC01 RCIC Turbine Mechanical Trip X l RCO2 RCIC Turbine Electrical Trip X 1 RC04 RCIC Turbine Failure To Auto Start X RC05 RCIC Pump Reduced Capacity X  !

RC06 RCIC Flow Controller Failure- X  !

RC07 RCIC Injection Valve Fails To Auto l Open X l RC10 RCIC Isolation Valve Binding X l RC11 RCIC Steamline Rupture At Turbine {

, Inlet X i RC12 Group Five Isolation Actuation X t RC13 Group Five Isolation Fails  !

To Actuate X i RC14 RCIC Injection Valve Binding X i i

RD01 Control Rod Uncoupled X ,

RD02 Control Rod Stuck X i RD03 Control Rod Drift In X i RD04 Control Rod Drift Out X RDOS Control Rod Scram X RD06 Control Rod Accumulator Trouble X RD07 CRD Hydraulic Pump Trip X i RD08 CRD Hydraulic Pump Reduced '

Capacity X RD13 Scram Disch Volume Hydraulic Lock X RD32 Manual Alternate Rod Insert Circuit Failure X RD :3 Scram Disch Volume Drain Valves Stick Open X 12

'l

. o i 9

SIMULATOR MALFUNCTION TEST SCHEDULE y ANNUAL TESTING PERIOD MALF MALFUNCTION 3/95- 3/96- 3/97- 3/98-NO. DESCRIPTION 3/96 3/97 3/98 3/99 RH01 RHR Pump Trip X RH02 RHR Pump Reduced Capacity X RH03 RHR Inboard Injection Valve Fails To Auto Open X RH06 RHR Logic Fails To Initiate X ,

RH07 RHR Injection Valve Binding X RH08 RHR Minimum Flow Valve Binding X RM01 Area Radiation Monitor Failure X RM02 Process Radiation Monitor Failure X RP02 Auto Scram Circuit Failure X  ;

RP03 Manual Scram Circuit Failure X RPO4 RPS MG Set Trip X RP05 Group One Isolation Actuation X RP06 Group One Isolation Fails To Actuate X RP07 Group Two Isolation Actuation X RP08 Group Two Isolation Fails To Actuate X RP09 Group Three Isolation Actuation X RP10 Group Three Isolation Fails To Actuate X RR01 Recirc Pump Drive Motor Breaker Trip X RR02 Recirc Pump Field Breaker Trip X RR04 Recirc Pump Reduced Capacity X RR06 Recirc Pump Inboard Seal Failure X RR07 Recirc Pump Outboard Seal Failure X RR08 Master Renirc Flow Controller Failure X RR09 Recirc FL 3 Speed Signal Failure X RR10 Recirc L:Np Suction Pipe Rupture X RR11 Recirc Loop Discharge Pipe Rupture X RR12 Reference Leg Pipe Rupture At RPV Nozzle X RR13 Variable Leg Pipe Rupture At RPV Nozzle X RR14 Recirc Loop Flow Transmitter Failure X 13

SIMULATOR MALFUNCTION TEST SCHEDULE ANNUAL TESTING PERIOD MALF MALFUNCTION 3/95- 3/96- 3/97- 3/98-NO. DESCRIPTION 3/96 3/97 3/98 3/99 '

RR15 FW Level Control Level Transmitter Failure X  :

RR16 FW High Level Trip Level Instrument Failure X RR17 Analog Trip System Level  ;

Transmitter Failure X RR18 ECCS Level Instrument Failure X  !

RR19 ATWS Level Transmitter Failure X RR20 Fuel Zone Level Transmitter Failure X i

~

RR21 ATWS Pressure Transmitter Failure X RR23 RX Pressure Transmitter Failure X RR25 RHR 100 psig Interlock Fails Low X ,

RR26 RHR 100 psig Interlock Fails High X  :

SLO 1 SBLC Pump Trip X i SLO 2 SBLC Pump Disch Line Relief Valve ,

Fails Open X SWO1 Service Water Pump Trip X SWO3 Recirc AG Set Oil Cooler Service Water Flow Blockage X SWO4 RER Service Water Pump Trip X SWO5 RHR Service Water Pump Reduced Capacity X SWO6 RBCCW Pump Trip X SWO7 R.BCCW Pump Reduced Capacity X SW11 TBCCW Pump Trip X l SW12 TBCCW Pump Reduced Capacity X <

SW15 Diesel Generator Cooling Water Pump Trip X TC01 Main Turbine Trip X TC02 Mai.1 Turbine Auto Trip Logic Fails To Actuate X TC05 EHC Pump Trip X TC06 Main Turbine Stop Valve Fails Open X TC07 Main Turbine Stop Valve Fails '

Closed X TC08 Main Turbine Control Valve Failure X t

14 l l

j

/

SIMULATOR MALFUNCTION TEST SCHEDULE ANNUAL TESTING PERIOD MALF MALFUNCTION 3/95- 3/96- 3/97- 3/98-NO. DESCRIPTION 3/96 3/97 3/98 3/99 TC09 Main Turbine Bypass Valve Failure X TC11 EHC Pressure Regulator Failure X

"'U01 Main Turbine Journal Bearing High Temperature X >

TUO2 Main Turbine Journal Bearing High Vibration X TUO4 Main Turbine AC Oil Pump Trip X -

TUO5 Main Turbine AC Oil Pump Fails l To Auto Start X  :

TUO6 Main Turbine DC Oil Pump Trip X

b L

b r

15 L