Special Rept 1-SR-89-004:on 891130,limiting Condition for Operation Established for Sprinkler Sys of North & South RHR & HPCI Room.Caused by Need to Resolve Engineering Design Concerns.Resolution Determined
ML20005H249
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 01/12/1990
From: Harness J
CAROLINA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
1-SR-89-004, 1-SR-89-4, BSEP-90-0050, BSEP-90-50, NUDOCS 9001240333
Download: ML20005H249 (1)


Text

r .

1

^ CD&L  !

Carolina Power & Light Company Brunswick Nuclear Project i P. O. Box 10429 Southport, NC 28461-0429 Janusry 12, 1990 -

FILE: B09-135100 SERIAL: BSEP/90-0050 10CFR50.73 -

.i U.S. Nuclear Regulatory Conmiission '!

ATTN Document Control Desk Washington, DC 20555 BRUNSWICK STEAM ELECTRIC PLANT UNITS 1 AND 2 DOCKET NOS. 50-325 AND 50-324 LICENSE NOS. DPR-71 AND DPR-62

SPECIAL REPORT PER TECilNICAL SPECIIICATION 3.7.7.2
AND PURSUANT TO TECIINICAL SPECIFICATION 6.9.2 (1-SR-89-004)

Gentlemen:

During Unit 1 power operation a limiting condition for operation (LCO) vas established on November 30, 1989, for the sprinkler system of the units' north and south Residual lleat Removal and the liigh Pressure Coolant Injection Room.

This was done to permit replacement of the sprinkler heads with heads having a higher temperature rating. Due to a need for an engineering resolution of some design concerns the specified 14 day time frame of the LCO was exceeded on December 14, 1989.

A resolution was determined and the LCO was cancelled on December 25, 1989.

Very truly yours.

l < W J. L. Harness, General Manager Brunswick Steam Electric Plant TMJ/cj Enclosure cc: Mr. S. D. Ebneter Mr. E. G. Tourigny BSEP NRC Resident Office 9001240333 900112 4 47, DR ADOCK 0500 fr