|
---|
Category:LICENSEE EVENT REPORT (SEE ALSO AO
MONTHYEARML17326A2011999-08-23023 August 1999 LER 99-004-00:on 990724,reactor Tripped Due to Main Transformer Bushing Flashover.Plant Was Brought to SS & Components Were Tested & Performed Satisfactorily.With 990823 Ltr ML20029C7321994-04-22022 April 1994 LER 94-004-00:on 940221,discovered Corrosion of Three Nuts on One of Incor Instrumentation Reactor Vessel Head.Caused by Increase of Wet Boric Acid.Leaking Flanges Repaired.W/ 940422 Ltr ML20046B4731993-07-30030 July 1993 LER 93-005-00:on 930630,TS 3.0.3 Entered Due to Both Containment Spray Sys Inoperable.Replaced CCW Outlet Valve Actuator Connecting Link Assembly from Number 11 SDC Heat exchanger.W/930730 Ltr ML20046A4911993-07-22022 July 1993 LER 93-003-00:on 930625,SG Tripped Due to Low Water Level. Caused by Insufficient Feedwater Addition Due to Inadequate Communication.Reemphasis on Improved Communication Stressed. W/930722 Ltr ML20045G8611993-07-0909 July 1993 LER 93-003-00:on 930610,dual Unit Trip Occurred Due to Partial Loss of Offsite Power.Flashover Protection Relay for Breaker 552-61 Replaced & Training for Personnel W/ Access to Relays Will Be reinforced.W/930709 Ltr ML20045G7281993-07-0808 July 1993 LER 93-002-00:on 930608,inadvertent Arw Actuation Sys & RPS Actuations Experienced During Performance of Awf Sys Large Flow Surveillance Testing.Caused by Failure to Note Differential Pressure Condition.Valve opened.W/930708 Ltr ML20045G8661993-07-0808 July 1993 LER 93-004-00:on 930611,reactor Tripped Due to Turbine Trip Resulting from Inadequate Procedure.Procedure Changes Made to Open Appropriate FW Heater High Level Dump Valves During Plant startup.W/930708 Ltr ML20045E7361993-06-29029 June 1993 LER 93-002-01:on 930205,software Vendor Discovered Error in User Manual for Updating Basss data-input Library.Caused by Failure of QA Procedures to Require Independent Review of User Manuals.Manual Surveillances performed.W/930629 Ltr ML20029B1261991-02-28028 February 1991 LER 91-001-00:on 910129,tubing in Air Start Sys for Emergency Diesel Generator Failed During Seismic Event. Caused by Error in Design of EDG Air Start Sys.Permanent Mod to Sys installed.W/910228 Ltr ML20028H8011991-01-24024 January 1991 LER 90-002-01:on 900116,determined That 891211 Reconstitution of More than One Spent Fuel Assembly Per Time in Violation of Fuel Handling Incident Safety Analysis. Caused by Deficient procedure.W/910124 Ltr ML20044A1861990-06-20020 June 1990 LER 87-002-01:on 861203,section of Thin Wall Found on Main Steam Line W/Readings Below Allowable Min of 0.95 Inches. Caused by Grinding of Edge of Pipe to Achieve Proper fit-up for Welding.Relief from IWB-3610 granted.W/900620 Ltr ML20043G1071990-06-13013 June 1990 LER 89-019-01:on 891128,determined That for Approx 10 Yrs, from 1979-1989,requirement to Lock HPSI Discharge Header Isolation Valves Shut Not Implemented.Caused by Inadequate Mgt Attention.Test Procedures modified.W/900613 Ltr ML20043F1221990-06-0404 June 1990 LER 90-017-00:on 900505,pin Hole Leak Observed in Discharge Piping of Saltwater Pump 13.Caused by Localized Corrosion. Leaking Spool Piece Removed & Blank Flange Installed. W/900604 Ltr ML20043A7871990-05-21021 May 1990 LER 90-016-00:on 900421,determined That Waste Gas Decay Tank (Wgdt) 13 Discharged Instead of (Wgdt) 11 for Discharge Permit Issued.Caused by Inadequate Communications.Training Performed for Operators Re event.W/900521 Ltr ML20043A3441990-05-14014 May 1990 LER 90-014-00:on 900413 & 19,unit Entered Tech Spec Limiting Condition of Operation 3.0.3 Due to Potential Inoperability of Three Out of Four Reactor Protection Sys Delta T Power Channels.Caused by Lack of Procedure guidance.W/900514 Ltr ML20043A3401990-05-14014 May 1990 LER 90-013-00:on 900413,determined That Axial Shape Index Channels Out of Spec & Inoperable.Caused by Inadequate Understanding of Design Basis for Excore/Incore Comparison. Design Basis for Excore/Incore improved.W/900514 Ltr ML20042G4521990-05-0707 May 1990 LER 90-015-00:on 900407,discovered That Relay Contact Which Actuates Reactor Trip Breaker Shunt Trip Not Adequately Functionally Tested.Caused by Failure to Examine Circuit in Detail When Test developed.W/900507 Ltr ML20042F5801990-05-0404 May 1990 LER 90-012-00:on 900406,identified That Procedure for LOCA Would Not Ensure post-LOCA Core Flush Would Be Initiated in Time to Prevent Boron Precipitation.Caused by Personnel Error.Configuration Mgt Program strengthened.W/900504 Ltr ML20012E9931990-03-29029 March 1990 LER 90-008-00:on 900227,determined That Surveillance Procedure M-280-0 Did Not Include Steps to Fully Test Control Room Recorder for Hydrogen Analyzers.Caused by Personnel Error.Procedure Revised on 900308.W/900329 Ltr ML20012F0001990-03-28028 March 1990 LER 89-006-01:on 890508,containment Iodine Filters Outside Design Basis Due to Equipment Qualification.Recalculation of Total Integrated Radiation Dose to Cables for Filter Fans Demonstrated Cable qualified.W/900328 Ltr ML20012E9951990-03-28028 March 1990 LER 89-014-01:on 890723,determined That Salt Water Header Not Capable of Withstanding Seismic Event Intact.Caused by Inadequate Welding of Blind Spool Pieces in Pipe.Insp Revealed Spools Capable as installed.W/900328 Ltr ML20012E0101990-03-26026 March 1990 LER 90-009-00:on 900224,failure to Meet Action Requirement Re Tech Spec 3.7.12.Caused by Personnel Error.Cables Removed from Doorway in Charging Pump Room & Not Allowed to Be Placed in doorway.W/900326 Ltr ML20012C4971990-03-15015 March 1990 LER 90-007-00:on 900216,discovered That Supervised Circuits Associated W/Fire Detection Instruments Located in Reactor Coolant Pump Bays Not Been Included in Surveillance Test Procedure.Caused by Personnel error.W/900315 Ltr ML20012C4861990-03-12012 March 1990 LER 90-006-00:on 900209,determined That Four Fire Dampers Missing.Caused by Not Identifying Penetrations as Requiring Dampers When Fire Hazards Analysis of Plant Conducted.Hourly Fire Watch Continued.Missing Dampers installed.W/900312 Ltr ML20012B8991990-03-12012 March 1990 LER 89-023-01:on 891220,determined That Pipe Rupture in nonsafety-related Svc Water Subsystem Could Result in Rapid Draining of Subsystems That Serve Auxiliary Bldg.Task Force Formed to Determine Corrective actions.W/900312 Ltr ML20012B4221990-03-0606 March 1990 LER 89-012-01:on 891227,core Alterations Performed W/Only One of Two Containment Vent Valves Closed.Caused by Procedural Deficiency.Procedures Revised to Include Valve & Surveillance Test Program Instruction revised.W/900306 Ltr ML20011F2701990-02-27027 February 1990 LER 90-001-01:on 900109,determined That Surveillance Tests Used to Perform Channel Calibr Tests for Acoustic Flow Monitoring Devices Inadequate.Caused by Personnel Error & Inadequate Procedures.Swapped Leads restored.W/900227 Ltr ML20011F2091990-02-27027 February 1990 LER 89-026-00:on 891128,determined That Particulate Levels in Samples Taken from Lower Third of Tanks Exceeded Allowable Limits.Caused by Inadequate Sampling Technique. Tanks Cleaned & Filled W/Clean fuel.W/900227 Ltr ML20006F8601990-02-22022 February 1990 LER 90-004-00:on 900123,discovered Fire Barrier Penetration Seal Open for Indeterminate Time W/O Performing Tech Spec 3.7.12.a Required Actions.Caused by Personnel Error. Temporary Fire Seal installed.W/900222 Ltr ML20006E0521990-02-0808 February 1990 LER 90-001-00:on 891221,discovered That Acoustic Indications for One PORV & One Safety Valve Were Reversed During Surveillance Test.Caused by Personnel Error.Swapped Leads Restored to Proper configuration.W/900208 Ltr ML20006B4801990-01-26026 January 1990 LER 89-022-00:on 891227,core Alterations Performed W/Only One of Two Containment Vent Valves Closed,Violating Tech Specs.Caused by Procedural Deficiency.Surveillance Test Procedure Revised to Include Deleted valves.W/900126 Ltr ML19354D8931990-01-17017 January 1990 LER 89-024-00:on 891218,determined That Wires Which Connect Actuation Device Logic Relay Contacts to Remainder of Circuit Not Tested During Channel Calibr Test.Caused by Inadequate Test.Test Program Upgrade underway.W/900117 Ltr ML20005F1921990-01-10010 January 1990 LER 89-025-00:on 891208,Tech Spec Action Statement Entered When Ventilation Ducts Penetrating Fire Barrier Could Not Be Accessed to Determine If Fire Dampers Installed.On 891211, Fire Watch Missed.Caused by Personnel error.W/900110 Ltr ML20005E3971989-12-28028 December 1989 LER 89-019-00:on 891128,discovered That HPSI Discharge Header Isolation Valves Not Locked Shut When RCS in Water Solid Condition,Resulting in Operation Outside Design Basis. Procedure Revised to Require Valves closed.W/891228 Ltr ML19351A4551989-12-13013 December 1989 LER 89-020-00:on 891113,determined That Some Solenoid Valves & Valve Power Supplies for Saltwater Sys May Not Be Able to Perform Design Function After Design Basis Seismic Event. Cause Undetermined.Power Supplies upgraded.W/891213 Ltr ML20005D6611989-12-0606 December 1989 LER 89-018-00:on 891106,discovered That Many Air Operated Control Valves & piston-operated Dampers Which Utilize safety-related Air Accumulators Would Not Have Performed as Expected After Loss of air.W/891206 Ltr ML19325F3951989-11-10010 November 1989 LER 89-002-01:on 890228,discovered That Fire Barrier Penetration Inoperable & Action Statement Requirements Not Satisfied.Caused by Inadequate Administrative Controls. Penetration Returned to Operable status.W/891115 Ltr ML19325E8221989-11-0303 November 1989 LER 89-007-01:on 890505,evidence of Reactor Coolant Leakage from 120 Pressurizer Vessel Heater Penetrations Discovered. Caused by IGSCC of Inconel 600.All Penetrations Using J-welds & Inconel 600 Visually inspected.W/891103 Ltr ML19324B2511989-10-27027 October 1989 LER 89-012-01:on 890720,discovered That Master Solenoid to Switchgear Room Halon Sys Disconnected Since 890629.Caused by Personnel Error Resulting from Lack of Written Procedure. Procedure Revised to Apply Temporary mods.W/891027 Ltr ML19325C3281989-10-10010 October 1989 LER 89-016-00:on 890908,determined That as-found Condition of Resistance Temp Detectors Did Not Match Tested Configuration.Cause Not Stated.Subj Detectors Will Be Sealed,Per Environ Qualification requirements.W/891010 Ltr ML19325C3701989-10-0909 October 1989 LER 89-017-00:on 890907,determined That Discrepancy in Acceptance Criteria of Surveillance Test Procedure M-452-0 Resulted in Failure to Fully Comply W/Requirements of Tech Spec 3.9.12.Main Cause undetermined.W/891009 Ltr ML20024F3771983-08-25025 August 1983 LER 83-044/03L-0:on 830808,diesel Generator 12 Tripped on Low Jacket Cooling Water Pressure While Verifying Operability.Cause Not Stated.Coolant Jacket Vented & Large Amount of Air Found.No Evidence of leakage.W/830825 Ltr ML20024F5731983-08-25025 August 1983 LER 83-040/03L-0:on 830727,control Room Air Conditioner 11 Discovered W/Damaged Condenser Fan.Caused by Loose Set Screws Securing Fan in Position.Set Screws Restored. W/830825 Ltr ML20024E6761983-08-0404 August 1983 Updated LER 83-011/03X-1:on 830207,during Surveillance Testing ESFAS a Logic Sequencer Failed,Rendering Diesel Generator 12 Inoperable.Caused by Intermittent Operation of Module Test Push Button.Part replaced.W/830804 Ltr ML20024E1721983-07-14014 July 1983 Updated LER 81-015/03X-1:on 810226,sample Pump for Control Room Radiation Monitor Found Out of Svc,Rendering Automatic Recirculation of Control Room Ventilation Sys on High Radiation Inoperable.Caused by seizure.W/830714 Ltr ML20024D0071983-07-0808 July 1983 LER 83-035/03L-0:on 830610,during Normal Power Operation,Esf Actuation Sys Channel Zg Steam Generator Level Tripped. Caused by Failed Vitro Isolator Module.Module Replaced.W/ 830708 Ltr ML20024D0091983-07-0808 July 1983 LER 83-033/03L-0:on 830603,fire Detection Instrumentation in Containment Southeast Electrical Penetration Determined Inoperable.Repair Impossible Due to Inaccessability of Protecto wire.W/830708 Ltr ML20024B8231983-06-23023 June 1983 LER 83-029/03L-0:on 830524,during Normal Operation, Surveillance Testing Indicated Neither Spent Fuel Pool Exhaust Fans 11 or 12 Would Maintain Required Negative Pressure.Caused by Clogged HEPA filters.W/830623 Ltr ML20024C0141983-06-22022 June 1983 Updated LER 81-080/03X-1:on 811116,discovered Weep from Cracked Weld on Spent Fuel Cooling Pump Discharge Vent Line 12.Caused by Inadequate Support of Vent Line.Support Assembly installed.W/830622 Ltr ML20024A8881983-06-16016 June 1983 LER 83-032/03L-0:on 830523,containment Isolation Sys B Logic Module Would Not Actuate.Caused by Defective Vitro Labs Std Logic Module.Module Replaced.Failed Module Returned to Vitro Labs for Repair & testing.W/830616 Ltr 1999-08-23
[Table view] Category:RO)
MONTHYEARML17326A2011999-08-23023 August 1999 LER 99-004-00:on 990724,reactor Tripped Due to Main Transformer Bushing Flashover.Plant Was Brought to SS & Components Were Tested & Performed Satisfactorily.With 990823 Ltr ML20029C7321994-04-22022 April 1994 LER 94-004-00:on 940221,discovered Corrosion of Three Nuts on One of Incor Instrumentation Reactor Vessel Head.Caused by Increase of Wet Boric Acid.Leaking Flanges Repaired.W/ 940422 Ltr ML20046B4731993-07-30030 July 1993 LER 93-005-00:on 930630,TS 3.0.3 Entered Due to Both Containment Spray Sys Inoperable.Replaced CCW Outlet Valve Actuator Connecting Link Assembly from Number 11 SDC Heat exchanger.W/930730 Ltr ML20046A4911993-07-22022 July 1993 LER 93-003-00:on 930625,SG Tripped Due to Low Water Level. Caused by Insufficient Feedwater Addition Due to Inadequate Communication.Reemphasis on Improved Communication Stressed. W/930722 Ltr ML20045G8611993-07-0909 July 1993 LER 93-003-00:on 930610,dual Unit Trip Occurred Due to Partial Loss of Offsite Power.Flashover Protection Relay for Breaker 552-61 Replaced & Training for Personnel W/ Access to Relays Will Be reinforced.W/930709 Ltr ML20045G7281993-07-0808 July 1993 LER 93-002-00:on 930608,inadvertent Arw Actuation Sys & RPS Actuations Experienced During Performance of Awf Sys Large Flow Surveillance Testing.Caused by Failure to Note Differential Pressure Condition.Valve opened.W/930708 Ltr ML20045G8661993-07-0808 July 1993 LER 93-004-00:on 930611,reactor Tripped Due to Turbine Trip Resulting from Inadequate Procedure.Procedure Changes Made to Open Appropriate FW Heater High Level Dump Valves During Plant startup.W/930708 Ltr ML20045E7361993-06-29029 June 1993 LER 93-002-01:on 930205,software Vendor Discovered Error in User Manual for Updating Basss data-input Library.Caused by Failure of QA Procedures to Require Independent Review of User Manuals.Manual Surveillances performed.W/930629 Ltr ML20029B1261991-02-28028 February 1991 LER 91-001-00:on 910129,tubing in Air Start Sys for Emergency Diesel Generator Failed During Seismic Event. Caused by Error in Design of EDG Air Start Sys.Permanent Mod to Sys installed.W/910228 Ltr ML20028H8011991-01-24024 January 1991 LER 90-002-01:on 900116,determined That 891211 Reconstitution of More than One Spent Fuel Assembly Per Time in Violation of Fuel Handling Incident Safety Analysis. Caused by Deficient procedure.W/910124 Ltr ML20044A1861990-06-20020 June 1990 LER 87-002-01:on 861203,section of Thin Wall Found on Main Steam Line W/Readings Below Allowable Min of 0.95 Inches. Caused by Grinding of Edge of Pipe to Achieve Proper fit-up for Welding.Relief from IWB-3610 granted.W/900620 Ltr ML20043G1071990-06-13013 June 1990 LER 89-019-01:on 891128,determined That for Approx 10 Yrs, from 1979-1989,requirement to Lock HPSI Discharge Header Isolation Valves Shut Not Implemented.Caused by Inadequate Mgt Attention.Test Procedures modified.W/900613 Ltr ML20043F1221990-06-0404 June 1990 LER 90-017-00:on 900505,pin Hole Leak Observed in Discharge Piping of Saltwater Pump 13.Caused by Localized Corrosion. Leaking Spool Piece Removed & Blank Flange Installed. W/900604 Ltr ML20043A7871990-05-21021 May 1990 LER 90-016-00:on 900421,determined That Waste Gas Decay Tank (Wgdt) 13 Discharged Instead of (Wgdt) 11 for Discharge Permit Issued.Caused by Inadequate Communications.Training Performed for Operators Re event.W/900521 Ltr ML20043A3441990-05-14014 May 1990 LER 90-014-00:on 900413 & 19,unit Entered Tech Spec Limiting Condition of Operation 3.0.3 Due to Potential Inoperability of Three Out of Four Reactor Protection Sys Delta T Power Channels.Caused by Lack of Procedure guidance.W/900514 Ltr ML20043A3401990-05-14014 May 1990 LER 90-013-00:on 900413,determined That Axial Shape Index Channels Out of Spec & Inoperable.Caused by Inadequate Understanding of Design Basis for Excore/Incore Comparison. Design Basis for Excore/Incore improved.W/900514 Ltr ML20042G4521990-05-0707 May 1990 LER 90-015-00:on 900407,discovered That Relay Contact Which Actuates Reactor Trip Breaker Shunt Trip Not Adequately Functionally Tested.Caused by Failure to Examine Circuit in Detail When Test developed.W/900507 Ltr ML20042F5801990-05-0404 May 1990 LER 90-012-00:on 900406,identified That Procedure for LOCA Would Not Ensure post-LOCA Core Flush Would Be Initiated in Time to Prevent Boron Precipitation.Caused by Personnel Error.Configuration Mgt Program strengthened.W/900504 Ltr ML20012E9931990-03-29029 March 1990 LER 90-008-00:on 900227,determined That Surveillance Procedure M-280-0 Did Not Include Steps to Fully Test Control Room Recorder for Hydrogen Analyzers.Caused by Personnel Error.Procedure Revised on 900308.W/900329 Ltr ML20012F0001990-03-28028 March 1990 LER 89-006-01:on 890508,containment Iodine Filters Outside Design Basis Due to Equipment Qualification.Recalculation of Total Integrated Radiation Dose to Cables for Filter Fans Demonstrated Cable qualified.W/900328 Ltr ML20012E9951990-03-28028 March 1990 LER 89-014-01:on 890723,determined That Salt Water Header Not Capable of Withstanding Seismic Event Intact.Caused by Inadequate Welding of Blind Spool Pieces in Pipe.Insp Revealed Spools Capable as installed.W/900328 Ltr ML20012E0101990-03-26026 March 1990 LER 90-009-00:on 900224,failure to Meet Action Requirement Re Tech Spec 3.7.12.Caused by Personnel Error.Cables Removed from Doorway in Charging Pump Room & Not Allowed to Be Placed in doorway.W/900326 Ltr ML20012C4971990-03-15015 March 1990 LER 90-007-00:on 900216,discovered That Supervised Circuits Associated W/Fire Detection Instruments Located in Reactor Coolant Pump Bays Not Been Included in Surveillance Test Procedure.Caused by Personnel error.W/900315 Ltr ML20012C4861990-03-12012 March 1990 LER 90-006-00:on 900209,determined That Four Fire Dampers Missing.Caused by Not Identifying Penetrations as Requiring Dampers When Fire Hazards Analysis of Plant Conducted.Hourly Fire Watch Continued.Missing Dampers installed.W/900312 Ltr ML20012B8991990-03-12012 March 1990 LER 89-023-01:on 891220,determined That Pipe Rupture in nonsafety-related Svc Water Subsystem Could Result in Rapid Draining of Subsystems That Serve Auxiliary Bldg.Task Force Formed to Determine Corrective actions.W/900312 Ltr ML20012B4221990-03-0606 March 1990 LER 89-012-01:on 891227,core Alterations Performed W/Only One of Two Containment Vent Valves Closed.Caused by Procedural Deficiency.Procedures Revised to Include Valve & Surveillance Test Program Instruction revised.W/900306 Ltr ML20011F2701990-02-27027 February 1990 LER 90-001-01:on 900109,determined That Surveillance Tests Used to Perform Channel Calibr Tests for Acoustic Flow Monitoring Devices Inadequate.Caused by Personnel Error & Inadequate Procedures.Swapped Leads restored.W/900227 Ltr ML20011F2091990-02-27027 February 1990 LER 89-026-00:on 891128,determined That Particulate Levels in Samples Taken from Lower Third of Tanks Exceeded Allowable Limits.Caused by Inadequate Sampling Technique. Tanks Cleaned & Filled W/Clean fuel.W/900227 Ltr ML20006F8601990-02-22022 February 1990 LER 90-004-00:on 900123,discovered Fire Barrier Penetration Seal Open for Indeterminate Time W/O Performing Tech Spec 3.7.12.a Required Actions.Caused by Personnel Error. Temporary Fire Seal installed.W/900222 Ltr ML20006E0521990-02-0808 February 1990 LER 90-001-00:on 891221,discovered That Acoustic Indications for One PORV & One Safety Valve Were Reversed During Surveillance Test.Caused by Personnel Error.Swapped Leads Restored to Proper configuration.W/900208 Ltr ML20006B4801990-01-26026 January 1990 LER 89-022-00:on 891227,core Alterations Performed W/Only One of Two Containment Vent Valves Closed,Violating Tech Specs.Caused by Procedural Deficiency.Surveillance Test Procedure Revised to Include Deleted valves.W/900126 Ltr ML19354D8931990-01-17017 January 1990 LER 89-024-00:on 891218,determined That Wires Which Connect Actuation Device Logic Relay Contacts to Remainder of Circuit Not Tested During Channel Calibr Test.Caused by Inadequate Test.Test Program Upgrade underway.W/900117 Ltr ML20005F1921990-01-10010 January 1990 LER 89-025-00:on 891208,Tech Spec Action Statement Entered When Ventilation Ducts Penetrating Fire Barrier Could Not Be Accessed to Determine If Fire Dampers Installed.On 891211, Fire Watch Missed.Caused by Personnel error.W/900110 Ltr ML20005E3971989-12-28028 December 1989 LER 89-019-00:on 891128,discovered That HPSI Discharge Header Isolation Valves Not Locked Shut When RCS in Water Solid Condition,Resulting in Operation Outside Design Basis. Procedure Revised to Require Valves closed.W/891228 Ltr ML19351A4551989-12-13013 December 1989 LER 89-020-00:on 891113,determined That Some Solenoid Valves & Valve Power Supplies for Saltwater Sys May Not Be Able to Perform Design Function After Design Basis Seismic Event. Cause Undetermined.Power Supplies upgraded.W/891213 Ltr ML20005D6611989-12-0606 December 1989 LER 89-018-00:on 891106,discovered That Many Air Operated Control Valves & piston-operated Dampers Which Utilize safety-related Air Accumulators Would Not Have Performed as Expected After Loss of air.W/891206 Ltr ML19325F3951989-11-10010 November 1989 LER 89-002-01:on 890228,discovered That Fire Barrier Penetration Inoperable & Action Statement Requirements Not Satisfied.Caused by Inadequate Administrative Controls. Penetration Returned to Operable status.W/891115 Ltr ML19325E8221989-11-0303 November 1989 LER 89-007-01:on 890505,evidence of Reactor Coolant Leakage from 120 Pressurizer Vessel Heater Penetrations Discovered. Caused by IGSCC of Inconel 600.All Penetrations Using J-welds & Inconel 600 Visually inspected.W/891103 Ltr ML19324B2511989-10-27027 October 1989 LER 89-012-01:on 890720,discovered That Master Solenoid to Switchgear Room Halon Sys Disconnected Since 890629.Caused by Personnel Error Resulting from Lack of Written Procedure. Procedure Revised to Apply Temporary mods.W/891027 Ltr ML19325C3281989-10-10010 October 1989 LER 89-016-00:on 890908,determined That as-found Condition of Resistance Temp Detectors Did Not Match Tested Configuration.Cause Not Stated.Subj Detectors Will Be Sealed,Per Environ Qualification requirements.W/891010 Ltr ML19325C3701989-10-0909 October 1989 LER 89-017-00:on 890907,determined That Discrepancy in Acceptance Criteria of Surveillance Test Procedure M-452-0 Resulted in Failure to Fully Comply W/Requirements of Tech Spec 3.9.12.Main Cause undetermined.W/891009 Ltr ML20024F3771983-08-25025 August 1983 LER 83-044/03L-0:on 830808,diesel Generator 12 Tripped on Low Jacket Cooling Water Pressure While Verifying Operability.Cause Not Stated.Coolant Jacket Vented & Large Amount of Air Found.No Evidence of leakage.W/830825 Ltr ML20024F5731983-08-25025 August 1983 LER 83-040/03L-0:on 830727,control Room Air Conditioner 11 Discovered W/Damaged Condenser Fan.Caused by Loose Set Screws Securing Fan in Position.Set Screws Restored. W/830825 Ltr ML20024E6761983-08-0404 August 1983 Updated LER 83-011/03X-1:on 830207,during Surveillance Testing ESFAS a Logic Sequencer Failed,Rendering Diesel Generator 12 Inoperable.Caused by Intermittent Operation of Module Test Push Button.Part replaced.W/830804 Ltr ML20024E1721983-07-14014 July 1983 Updated LER 81-015/03X-1:on 810226,sample Pump for Control Room Radiation Monitor Found Out of Svc,Rendering Automatic Recirculation of Control Room Ventilation Sys on High Radiation Inoperable.Caused by seizure.W/830714 Ltr ML20024D0071983-07-0808 July 1983 LER 83-035/03L-0:on 830610,during Normal Power Operation,Esf Actuation Sys Channel Zg Steam Generator Level Tripped. Caused by Failed Vitro Isolator Module.Module Replaced.W/ 830708 Ltr ML20024D0091983-07-0808 July 1983 LER 83-033/03L-0:on 830603,fire Detection Instrumentation in Containment Southeast Electrical Penetration Determined Inoperable.Repair Impossible Due to Inaccessability of Protecto wire.W/830708 Ltr ML20024B8231983-06-23023 June 1983 LER 83-029/03L-0:on 830524,during Normal Operation, Surveillance Testing Indicated Neither Spent Fuel Pool Exhaust Fans 11 or 12 Would Maintain Required Negative Pressure.Caused by Clogged HEPA filters.W/830623 Ltr ML20024C0141983-06-22022 June 1983 Updated LER 81-080/03X-1:on 811116,discovered Weep from Cracked Weld on Spent Fuel Cooling Pump Discharge Vent Line 12.Caused by Inadequate Support of Vent Line.Support Assembly installed.W/830622 Ltr ML20024A8881983-06-16016 June 1983 LER 83-032/03L-0:on 830523,containment Isolation Sys B Logic Module Would Not Actuate.Caused by Defective Vitro Labs Std Logic Module.Module Replaced.Failed Module Returned to Vitro Labs for Repair & testing.W/830616 Ltr 1999-08-23
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217G6971999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Calvert Cliffs Npp,Units 1 & 2.With ML20216J8731999-09-10010 September 1999 Rev 52 to QA Policy for Calvert Cliffs Nuclear Power Plant ML20212A4441999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Ccnpp,Units 1 & 2. with ML17326A2011999-08-23023 August 1999 LER 99-004-00:on 990724,reactor Tripped Due to Main Transformer Bushing Flashover.Plant Was Brought to SS & Components Were Tested & Performed Satisfactorily.With 990823 Ltr ML20210S6091999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Ccnpp,Units 1 & 2. with ML20210N6001999-07-27027 July 1999 ISI Summary Rept for Calvert Cliffs Unit 2. Page 2 of 3 in Encl 1 of Incoming Submittal Not Included ML20210B7941999-07-15015 July 1999 SER Denying Licensee Request for Changes to Current Ts,Re Deletion of Tendon Surveillance Requirements for Calvert Cliffs LD-99-039, Part 21 Rept Re Defect of Abb 1200A 4kV Vacuum Breakers. Initially Reported on 990625.Defect Results in Breaker Failing to Remain in Closed Position.Root Cause Evaluation & Corrective Action Plan Being Developed.Licensee Notified1999-06-30030 June 1999 Part 21 Rept Re Defect of Abb 1200A 4kV Vacuum Breakers. Initially Reported on 990625.Defect Results in Breaker Failing to Remain in Closed Position.Root Cause Evaluation & Corrective Action Plan Being Developed.Licensee Notified ML20209F1721999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Calvert Cliffs Npp.With LD-99-035, Part 21 Rept Re Abb 1200A 4KV Vacuum Breakers Performing Trip Free Operation When Close Signal Received by Breaker. Defect Results in Breaker Failing to Remain in Closed Position.Root Cause & CAP Being Developed1999-06-25025 June 1999 Part 21 Rept Re Abb 1200A 4KV Vacuum Breakers Performing Trip Free Operation When Close Signal Received by Breaker. Defect Results in Breaker Failing to Remain in Closed Position.Root Cause & CAP Being Developed ML20196C6981999-06-21021 June 1999 Safety Evaluation Concluding That Use of ASME Section XI Code Including Summer 1983 Addenda as Interim Code for Third 10-year Insp Interval at Calvert Cliffs Units 1 & 2 Until Review of 1998 Code Completed,Would Be Acceptable ML20195K2811999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Ccnpp,Units 1 & 2. with ML20206R5871999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Ccnpp,Units 1 & 2. with ML20195B3891999-04-30030 April 1999 0 to CENPD-279, Annual Rept on Abb CE ECCS Performance Evaluation Models ML20205N2951999-04-13013 April 1999 Special Rept:On 990314,fire Detection Sys Was Removed from Svc to Support Mod to Replace SRW Heat Exchangers in Unit 2 SRW Room During Unit 2 Refueling Outage.Contingency Measure 15.3.5.A.1 Will Continue Until Fire Detection Sys Restored ML20210T5211999-04-0101 April 1999 Rev 0 to Ccnpp COLR for Unit 2,Cycle 13 ML20205P5441999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2.With ML20204H6471999-03-21021 March 1999 SER Re License Renewal of Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20207M8321999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Calvert Cliffs Nuclear Power Plant.With ML20203D4311999-02-0505 February 1999 Safety Evaluation Accepting Procedure Established for long-term Corrective Action Plan Related to Containment Vertical Tendons ML20199G4671999-01-20020 January 1999 SER Accepting USI A-46 Implementation for Plant ML20206Q3221999-01-11011 January 1999 Special Rept:On 981226,wide Range Noble Gas Effluent RM Was Removed from Operable Status.Caused by Failure of mid-range Checksource to Properly Reseat.Completed Maint & post-maint Testing & RM Was Returned to Operable Status on 990104 ML20207L0451999-01-0808 January 1999 Cost-Benefit Risk Analyses:Radwaste Sys for Light Water Reactors ML20199F4781999-01-0808 January 1999 Safety Evaluation Concluding That Bg&E Performed Appropriate Evaluations of Operational Configurations of safety-related power-operated Gate Valves to Identify Valves Susceptible to Pressure Locking.Concludes GL 95-07 Actions Were Addressed ML20198S7591999-01-0707 January 1999 SER Accepting Quality Assurance Program Description Change for Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20207M2281998-12-31031 December 1998 1998 Annual Rept for Bg&E. with ML20199E2931998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Calvert Cliffs Npp. with ML20206R9911998-12-0808 December 1998 Rept of Changes,Tests & Experiments (10CFR50.59(b)(2)). with ML20198B2631998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2.With ML20195H1001998-11-16016 November 1998 Safety Evaluation of First Containment Insp Interval Iwe/Iwl Program Alternative ML20196E2211998-10-31031 October 1998 Non-proprietary Rev 03-NP to CEN-633-NP, SG Tube Repair for Combustion Engineering Designed Plant with 3/4 - .048 Wall Inconel 600 Tubes Using Leak Limiting Alloy 800 Sleeves ML20195E5281998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Calvert Cliffs Nuclear Power Station,Units 1 & 2.With ML20154Q7191998-10-21021 October 1998 Special Rept:On 980923,unit 1 Wrngm Was Removed from Operable Status.Caused by Failure of Process Flow Transducer.Completed Maint to Remove Process Flow Transducer Input to Wrngm Microprocessor & Completed Formal Evaluation ML20154G3931998-10-0505 October 1998 Safety Evaluation Concluding That Flaw Tolerance Evaluation for Assumed Flaw in Inboard Instrument Weld of Pressurizer Meets Rules of ASME Code ML20154M5841998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Calvert Cliffs Nuclear Plant,Units 1 & 2.With ML20153C2571998-09-18018 September 1998 Special Rept:On 980830,wide Range Noble Gas Monitor (Wrngm) Channel Was Removed from Operable Status.Caused by Need to Support Performance of Required 18-month Channel Calibr.Will Return Wrngm to Operable Status by 980925 ML20153C1091998-09-18018 September 1998 Part 21 Rept Re Defective Capacity Control Valves.Trentec Personnel Have Been in Contact with Bg&E Personnel Re Condition & Have Requested Potentially Defective Valves ML20151U5441998-09-0404 September 1998 Bg&E ISI Summary Rept for Calvert Cliffs ML20151T5281998-09-0101 September 1998 Special Rept:On 980819,declared Rv Water Level Monitor Channel a Inoperable.Caused by Failure of Three Heated Junction Thermocouples (Sensors) in Lower Five Sensors. Channel a & B Rv Water Level Probes Will Be Replaced ML20151Y1191998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Calvert Cliffs Nuclear Power Plant Units 1 & 2.With ML20237D4981998-08-19019 August 1998 Safety Evaluation Accepting Licensee Request for Extension of Second ten-year Inservice Insp Interval ML18066A2771998-08-13013 August 1998 Part 21 Rept Re Deficiency in CE Current Screening Methodology for Determining Limiting Fuel Assembly for Detailed PWR thermal-hydraulic Sa.Evaluations Were Performed for Affected Plants to Determine Effect of Deficiency ML20237B9371998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Calvert Cliffs Nuclear Power Plant ML20237D5941998-07-22022 July 1998 Rev 2 to Ccnpp COLR for Unit 2,Cycle 12 ML20236L7521998-07-0606 July 1998 Safety Evaluation Granting Bg&E 980527 Request for Relief from Requirement of Section IWA-5250 of ASME Code for Calvert Cliffs Unit 2.Alternatives Provide Reasonable Assurance of Operational Readiness ML20236F7791998-06-30030 June 1998 Safety Evaluation Authorizing Request for Temporary Relief from Requirement of Subsection IWA-5250 of ASME Code,Section XI for Plant,Unit 1 ML20236R0881998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Calvert Cliffs Nuclear Power Plant,Units 1 & 2 ML20236X3101998-06-19019 June 1998 Rev 1 to Calvert Cliffs Nuclear Power Plant COLR for Unit 2,Cycle 12 ML20249A9571998-06-15015 June 1998 Special Rept:On 980430,fire Detection Sys Was Removed from Svc to Support Mod to Purge Air Sys 27-foot Elevation & 5-foot Elevation East Piping Penetration Rooms.Installed Temporary Alteration & Returned Fire Detection Sys to Svc ML20249A7711998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Ccnpp,Units 1 & 2 1999-09-30
[Table view] |
Text
\
g
ELECTRIC CHARLES CENTER
- P.O. BOX 1475 e BALTIMORE, MARYLAND 21203 1475 j i
CALVERT Clifft NUCLEAR POWER PLANT DEPARTMENT
$s ? u $ ,"lu'o" ? $ " * * *
, )
December 13, 1989 U. S. Nuclear Regulatory Commission Docket No. 50-317 '
Document Control Desk License No. DPR 53 Washington, D. C. 20555 t
Dear Sirs:
The attached LER 89 020 is being sent to you as required under 10 CPR 50.73. i Please note that this is a partial'LER and a supplement will be issued by February 7,1990. The supplement will list a more complete descriptionco f the root cause analysis, and corrective actions for this event.
Should you have any questions regarding this report, we would be pleased to discuss them with you.
Very truly yours, ,
La L. B. Russell Manager Calvert Cliffs Nuclear Power Plant Department LBR:CDS:sdw cc: William T. Russell Director, Office of Management Information and Program Control Messrs: G. C. Creel C. H. Cruse R. E. Denton J. R. Lemons l
jfh21gjy@ f[ [ g2 b f
,\
l
C perm 3es u s Nucts_a at ov. Tony COMMisslot;
, LPPR0Vf D OM6 to 3160010s
. LICENSEE EVENT REPORT (LER) * * *'au ' '81
- B ACILITV NAME til (KBCkt1 NOutin (26 PAGE $3 Calvert Cliffs Unit 1 0161010 l 013 l 1l7 1!oFlol9 Non-Seismic Solenoid Valves and Solenoid Valve Power Supplies on Class I System Results in a Condition Outside the Plant's Design Basis _
IVtWT DAtt (St Lin NUMBtR IG) DEPORT Daf t 171 OTHt$t S ACILITill INVOLVED (el MONT H DAY vtAm vtAR 8',O[,'$*k "tjf,7, MONT H day vtAm #AciLivv4AMas pocklT NvMetsosi Calvert Cliffs Unit 2 0l6l0l0l0 131118 1l 1 1! 3 8 98l9 0l2 l 0 O! O 1l2 1l3 8l 9 0 g6 t o l0 iot l l
,,g ,,,,, sHis etPoRt ss eveMisstD evasuaNs so THE nsoutRtMtNis or 10 Cea k scmece one e more o* rw roue..nont111 "00'
- S 20 402161 to 406tsi 60 736ei(210el 73.?Itti r0 mi.imoi s0 m.im a ni.imM v3m.i (105 010 t O *0 40*iait1Hiii 50 3*isital 60 tsi H Hviii o Hgge,,',* 'a4*;e, ct, 20 406saH1 Hili) 60 736 ell 210) 60 73ielltHveelli Al J66A1 70 4066sitlibel x 60.73te H2}M M 73iet(21te64al(0) 20 404teH1Hel 90 73teH2HM 60.734etG Hal LICEN5f t CONT ACT D')ft THi$ LIR (1))
NiMt TILIPHONE NVMDIR A8tt & CODE Crain D. Sly - Licensinn Engineer 310 l1 21 6101- l 4181518 COMPLif t ONE LINI FOR E ACH COMPONINT F AILURt Ot&CRISED IN THit DEPORT (131 Clust S v At t M COMPONENT
" "I' "'
Caust s y fTIM COMPONENT "$'g$C '
$C t0 PR O NPR I i i i i l i I I I I I I I 1 i i l l I I I I I I I I I SUPPLIMENT AL fttPORT E RPICTE D (14i MONTH DAv vtAR
$v8MibSiON T vu ur ., v <,n.. ex*ucreo svowssiON oArro G No ol9 oly 9lo AestRAC1<t..,,,,. . .. ,,,,...,,,,.,..c....-,no.
On November 13, 1989, a condition was discovered at Calvert Cliffs Units 1 and 2 which was concluded to be outside the design basis of the plant as described in the Updated Final Safety Analysis Report (UFSAR). Certain solenoid valves (SV) and some SV power supplies associated with our Saltwater System may not have been able to perform their intended design function after a design basis seismic event.
At the time of the discovery, Unit I was in cold shutdown with reactor pressure and temperature at atmospheric and 116 F, respectively. Unit 2 Reactor Coolant System was at atmospheric pressure with the core off-loaded.
The root cause of the event is still under investigation.
Short term corrective actions have been initiated to upgrade the deficient SV power supplies and replace the non seismic SVs with SVs that are built to withstand a seismic event.
Additional corrective actions shall be submitted in a supplement to this LER.
N..C Seem 366 (9 831
anc . A n wucts:c, a:ucionv couwinnioi I UCENBEE EVENT REPORT (LER) TEXT CCNTINUATION Arenono ove no am-om (ILPIRIS' 4'3hN ,
FActLtty h4mL m puckav ,suust,i m g , gg , ,
naa "ea p =,n Calvert cliffs Unit 1 0 15101010l 31117 81 9 ol2 I o -
ol o of2 0' o 19 text u . <,,,. , m cr , = uon I. DESCRIPTION OF EVENTS On November 13, 1989, a condition was discovered at Calvert Cliffs Units 1 and 2 which was concluded to be outside the design basis of the plant as described in the . Updated Final Safety Analysis Report (UFSAR). Certain solenoid valves (SV) and some SV power supplies associated with our Saltwater System may not have been able to perform their intended design function after a design basis seismic event.
At the time of the discovery, Unit I was in cold shutdown with reactor pr6ssure and temperature at atmospheric and 116 F, rer.pectively. Unit 2 Reactor Coolant 1 Syctem was at atmospheric pressure with the core off-loaded.
The UFSAR Section SA.2, " Classes of Structures Systems and Equipments," states, in part; "Throughout the context of this section, Class I shall mean Category 1 (Seismic) structures, systems 6 equipment. Class I structures, systems, and equipment are those whose failure could cause uncontrolled release of radioactivity or those essential for immediate and long term operation following a loss of coolant incident."
Contrary to the above statement, it was discovered that portions of the electrical supplies to five SVs in Class 1 applications may not have been able to withstand a seismic event. It was also discovered that four solenoid valves in Class 1 applications were not built to withstand a seismic event. The condition was discovered during a re'riew to determine the ability of Saltwater System instrument air components to withstand a seismic event. Upon discovery of the condition, the Control Room notified the NRC at 1614 hours0.0187 days <br />0.448 hours <br />0.00267 weeks <br />6.14127e-4 months <br /> on November 13, 1989.
The investigation started on November 13, 1989 when it was discovered that several SVs were listed in the Calvert Cliffs Q. List as safety related (SR), but were listed on the electrical schematic diagrams as non-safety related (NSR). A walkdown was later performed to ascertain if the SVs are actually provided power from a SR source. It was determined that the power sources were indeed SR, but that the cables were not routed through a fully seismically qualified path. The SV's power sources were found to satisfy all other requirements of SR cabling with the exception of the incomplete seismically-qualified cable paths. The af fected SVs are listed in Table 1.
During the review of the Saltwater System instrument air supply, four SVs were found which were not built to withstand a seismic event. As part of the review, analyses were performed to determine if the SVs could survive a seismic event.
These analyses included design reviews and destructive examination of the solenoid valves.
~
se ,o. . . a. m mee-< >
(C &h
Is8tc eem astA U $ NUClL13 Lt!ULi10av comeMitsloss LICENSEE EVENT CEPORT (LER) TEXT CCNTINUATION uProvto ove wo mo-oio.
tKPillll l'31*l C ACILITY twARIk 06 DOC 8Lt1 NUMht M (H Lim NUMDth 146 PA06 OI
.t.. = =
t'alvert C11ffs Unit 1 o [6 j o l 0 l 0 l 311 l 7 8 l9 -
O p l0 -
0l0 0l3 0F 0 l9 nxw - ., . , 4 ., mc w w nn The analyses showed that this type of_SV could be compromised during a seismic event because the core tube could "crin:p. " This valve type was intended for use in commercial design and not intended by the vendor for nucicar service. The valves are listed in Table 2.
These issues are the responsibility of the project team previously established to address several outstanding Facility Change Requests (FCRs) and the air accumulator failures discussed in LER 317/89-018. The proj ect team was established to assure that corrective actions to associated with these issues are coordinated and implemented in manner which will ensure the safe operation of the Units. The efforts of this project team are currently underway.
11, CAUSE OF EVENTS We are currently conducting a root cause investigation of those events. The results of the investigation will be provided in a supplement to this LER.
III. ANALYSIS OF EVENTS The Saltwater System is designed to provide cooling water for the Service Water and Component Cooling Water Heat Exchangers, and ECCS Pump Room Coolers. The Component Cooling and Service Water Systems are designed to remove heat from the plants' varjous auxiliary systems during normal and shutdown conditions and remove heat during a LOCA. (Figure 1)
During the recirculation mode after a LOCA, should a piping rupture occur in the common discharge header of the Saltwater System, the alternate (overboard)
Saltwater System flow path to the bay would be employed. (Figure 2) The valves used to position this lineup are air operated with accumulators supplied by the Instrument Air System. Most of the valves would have to be repositioned from their failed position for the alternate discharge path lineup. Some of these valves cannot be manually operated after a LOCA because they would be located in a ,
very high radiation area.
Table 1 shows a list of SVs having an incomplete scismically supported path for their power cables. All of these valves are associated with the Saltwater System Alternate Discharge Path. Failure of the SVs would result in a loss of air pressure to the associated CVs. The CVs would fail to the closed position.
Failure of these valves to open during a LOCA and concurrent piping rupture of the Saltwater System normal discharge header would have resulted in the loss of the plants' ultimate heat sink. We believe that this event has a very low probability of occurring. A PRA is currently underway to help evaluate the significance of such a scenario.
I l
l l
arc .on . *u r um imam" ~
8,hc Feem MSA UO NUCLtG RtIUL& TORY ConseA10 BION I-t LICENSEE EVENT REPORT (LE] TEXT C2NTINUATl:N uenovioous No vio-e m E xPIRt $. S'31'ge 8&Citif y h&htt (t) DDCkti NUteD&R (26 '
ttR NUM$lR IS) PACI (31 "ew =,n Calvert Cliffs Unit 1
. , =
015l0lolo13l1l7 8 19 d 2l0 -
0 10 0l4 0F 0l9 text m m .an.,w we mim(m Table 2 is a list of SVs which were not built to withstand a seismic event. All of these valves are associated with the Service Water Heat Exchanger Saltwater
- Outlet Throttle Valves. Failure of these SVs after a seismic event could have a wide range of effects on the ability of the Saltwater System to removo residual ;
heat from the Service Water System Heat Exchangers. If the throttle valves were to fail open, there is a danger of saltwater pump failure due to pump runout. If the throttle valves failed to the closed position, no cooling water would be available to the Service Water Heat Exchangers.
Operators are trained to maintain Saltwater Pump discharge pressure greater than 13 psig at all times to prevent damage or losa of the Saltwater Pumps. Although this would normally be done by throttling CVs $210 and 5212, steps exist in various operating procedures that direct the throttling of the Saltwater Pump discharge valves to maintain proper discharge pressure. Therefore, had the failure of the Service Water Heat Exchanger throttle valves occurred, causing them to open, operators would have been dispatched to throttle the Saltwater Pump discharge valves.
The Saltwater Pump Discharge Valves are cecessible to operators after a LOCA.
Thus, we believe that the consequences of the failure of the CVs to the open position would be mitigated by manual control of these throttle valves. The consequences of the failure of the CVs to the closed position will be addressed in the supplement to this LER.
This event is considered reportable per 10 CFR 50.73(a)(2)(ii)(B), "Any event or condition that resulted in the nuclear power plant being in a condition that was outside the design basis of the plant,"
IV. CORRECTIVE ACTIONS FCR 89-0180 was initiated to upgrade the electrical circuits of the SVs in Table 1 to SR.
FCR 89 95 was initiated to replace the SVs in Table 2 with seismically qualified SVs.
Additional corrective actions will be provided in a supplement to this LER.
IV. ADDITIONAL INFVRMATION There has been one previous similar event involving Saltwater System components being outside the design basis. The event is discussed in LER 317/89 008. The root cause of that event was poor maintenance practices.
There has been one previous similar events involving a potential loss of instrument air to Saltwater System components. The event is currently being investigated and is discussed in LER 317/89 018. The root cause of the event is still under investigation.
, ,,,, . . . . cu. -n m m
ane sena u.s. wucuaniovatonv commmion !
LICENSEE EVENT REPORT (LER) TEXT CZNTINUATIIN <moveo owe no s'io-em EXPIRE S: $ #316 PactLtTV 1840 4 (1) DOCOLif Nutl$th til LI A NumSIR lll PAot (Si
- n. "uw :tr:,n Calvert Cliffs Unit 1 0 l6 l0 l0 l0 l 3l1 l 7 8l9 -
Q 2l 0 -
0l0 0l5 OF ol 9 vaxi a w wi.w =ac s m.imm IDENTIFICATION OF COMPONENTS REFERRdD TO.IN THIS LER IEEE 803 IEEE 805 Comoonent Ells PUNCT SYSTEM ID Saltwater System N/A NN
-Instrument Air N/A LD Component Cooling System N/A CC Service Water System N/A BI ECCS N/A BP, BQ, BE Heat Exchanger HX N/A Solenoid Valve PSV N/A Control Valve Air Operated V N/A l
wac voxw snea 'u 5- m " 8 8 41 "" * "'
( 19 83s
I i aHec teem sena U S NUCLti'. L.61 ult.TDRV CoMM196lDN !
LICENSEE EVENT REPORT (LER) TEXT CENTINUATION uPxovio ous No mo4in l
, (KPIR($ l'31%
. ACsLtiv hAMt Ill DDCkti NUMDth G6 LIR NUM9th 16) PAGI (3) vsaa " br,0. 0'Jf.3 1
Calvert Cliffs Unit 1 o l6 lo lo l0 l 3l1 l7 8l9 -
0 l 2l 0 -
0]O 0l6 or 0 l9 .
TEKT (# mswo spece a newest, use emeanal NRC Farm NWat (171 I TABLE 1 SOLENOID VALVES HAVING INCOMPLETE SEISMIC SUPPORT FOR POWER CABLES SV No. CV CV Safety. CV Failure '
CV No. Function Related Position Position Comments SV 5149 Saltwater Alternate Closed Closed Must Open for CV-5149 Discharge Valve Alternate Discharge Lineup SV 5155 SRW Hx 12 Outlet Closed Closed Must Open for CV-5155 to Alternate Alternate Discharge Path (1st) Discharge Lineup SV-5156 GRW Hx 12 Outlet Closed Closed Must Open for to Alternate Alternate Discharge Path (2nd) Discharge Lineup SV-5165 Component Cooling Hx 12 Closed Closed Must Open for Outlet to Alternate Alternate Discharge Path (1st) Discharge Lineup SV 5166 Component Cooling Hx 12 Closed Closed Must Open for Outlet to Alternate Alternate Discharge Path (2nd) Discharge Lineup
- Alternate discharge lineup is required during the recirculation mode after a LOCA only if a piping rupture should occur in the common normal discharge header of the saltwater system.
. .u.. . cro, i.... m. s.., oom g,07.M
unce . senA u s wuctim a.ucioRv com mo=~ !
UCENSEE EVENT 9EPORT (LER) TEXT CONTINUATION crehovip owe =o. sisoaio4
, exemts soi e facility ha.4 He pogggy wungle (2)
Lim =Mik 168 PA05 (3p
.a ann;r =J,y:
Calvert Cliffs Unit 1 0 l6 l0 l0 l0 l3 l Il7 gl9 -
012 l 0 -
010 0l7 0F Ol9 int w noe non e w = omnew oc w ma w Ino TABLE 2 SOLENOID VALVES NOT BUILT TO VITHSTAND A SEISMIC EVENT SV No. CV CV Safety. CV Failure CV No. Function Related Position Position Comments SV 5210 SRW llX 11 Open Full Open Must Close for CV-5210 Saltwater Outlet (Throttled) Alternate Throttle Valve Discharge Path SV 5210A SRW Hx 12 Open Full Open Must Close for CV-5210 Saltwater Outlet (Throttled) Alternate Throttle Valve Discharge Path SV-5212 SRW lix 12 Open Full Open Must Close for CV-5212 Saltwater Outlet (Throttled) Alternate (1st) Throttle Valve Discharge Path SV 5212A SRW lix 12 Open Full Open Must Close for CV 5212 Saltwater Outlet (Throttled) Alternate
-(1st) Throttle Valve Discharge Path ne raru m. . a ve. m n ~n ~ ~
4
7 I
assic tsee seta u 6 t;UCL4111 E6IULatonY CommMEB40N LICENSEE EVENT REPORT (LER) TEXT CENTINUATION unovto owe no am-o*
, tarints- av =
' ACJ41TT hAMG 4H Docksi espaatta tai tin uusiesth ten thot tai
'I'" No NysIn 0F calvert cit tra tintt 1 o ls lo lo lo 13 l 117 al 9 -
01210 -
olo ok o l9 TEXT M m** T e 8esurer uss ess3Luvy_Egwit?1 m
F10URE I SALT WATER SYSTEW h0RW AL SUPPLY / DISCHARGE PATH O C jo ! lo l 5170 5177 EAL T m ATER _
PUWPG
- C OOL rROW .L h . it 5174 5175 IN T A* F STRUCTURE '
[) ._
5173 h 0.t? .
Y -
8 i
1 3
ECCS AIR C OOLE R hD.ll I
3 I
8 FROW IWT AKE STRUCTURE '
r
[3 ..
f I I 5170 5171 h 0.13 1I
/. B B g'-i /% 1, i jg i rROW thi AKE STRUCTURE '
r [ ~
ew O
5160 5165 IT R IPPE. 0 Orri cr i f h D.Il g y COWP0hENT
]
J % %; C * ,%",? "" l% H l =
d ~- 5162 3163 5709
._ A -
THROTTLE 5145
= l% 00gy h Hx lgl 7 h 5160 SF06
> __ THROTTLE VALVE
{
! a 5 B B y l Sib 6
- uBl55 i
i E WE RDE NC Y
[
DISCHAR GE t TO BAY SE RVICE
%l
- y0,ERr" l H %l 5152 5712 sis 3
' THROTTLE I I V AL VE SE RVICE
- a : N "V!a l,"* N 5150 5210 THROTTLE I i o II AIR OPER ATED DIAPHR AGW BUTTERFLY V ALVE ICLOSE 01 VALVE II TO BAY lgl AIR OPER ATED P!5T0h DUTitRFLY VALVE 10PENI
.3 -
- n. . u o., ,,
. e n o. nu
( . . _ - - . _ _ _ _ .
=c asea v s auc66a arvatoay co==iesio
' LICENSEE EVENT REPORT (LER) TEXT CONTINUATION o*Rovio ca e wo em-o*
- e. , exames swa FACE,1)V IEAMS til DOCh&T NutSim (31 PA06 (Si (th WUMDER ($1
'sA" ve a :
Nwa a 0F calvert clif fs 11 nit 1 0 151010l'131117 a 19 ,
012l0 -
0l0 0 19 019 Si[T tr mee asese a emmeer, ese eswomw mac h Asad W ttM FIGURE P SALT WATER SYSTEM ALTERNATE SUPPLY / DISCHARGE PATH Q
ldl lwl 5l70 5177 SAL T W ATER 1 PUMPS O O '
rROW
- 1 l C OOL RN .62 5173 INT AKE STRUCTURE '
3 ./.
Sl?* 5175 I l h 0.12 . O O
! ,. I ECCS AIR I, i T I COOLE R hD.ll 3 I rROW 5170 5671 INT AKE e
[) l L lI STRUCTURE ' +
N O.13 I I Tm 5 5 p3 rROW 1NT AKE STRUCTURE '
r [ 'N O
5166 5165 ITR IPPE D Orrn cr ji h 0.ii If g ] ))
y j COWPONENT COOL h HX gH ,,,,,, ,
n o a 5162 5163 5208
{ -
5649
< 'o t C0CL ING HX 1 o I y i I h 0.4 4 3 3 5160 5206 Y
1ra n E 8 8 y lw' lwl :
Sib 6 5 tSS E WE R 0E N C Y DISCHAR GE TO BAY B SE RVICE BB
%h WATER HX g
y n Hn 1 5152 5212 5:53 SE RVICE I
n 1 WATER HX i,,i g) 8 i N O.11 I i 5:50 5280 j n l AIR OPER ATED DlAPelR ADW BUTTERFLY VALVE ICLOSEDI B Y TO BAY jgl AIR DPERATED PISTON BUTTERFLY VALVE 80*Eh!
,,,,o.... . . . m.....-.
~., _ .. - - - . _ . _ _ . . _ . . - _ . , , - - _ . - .