ML19340A135
ML19340A135 | |
Person / Time | |
---|---|
Site: | Oconee |
Issue date: | 05/31/1978 |
From: | DUKE POWER CO. |
To: | |
Shared Package | |
ML19340A131 | List: |
References | |
NUDOCS 8001100600 | |
Download: ML19340A135 (16) | |
Text
. . , -
L/
DUKE POWER COMPANY OCONEE NUCLEAR STATION UNIT 3, CYCLE 3 STARTUP TESTING
SUMMARY
MAY 1978 8001100[CO
DUKE POWER COMPANY OCONEE NUCLEAR STATION UNIT 3, CYCLE 3 STARTUP TESTING
SUMMARY
I. INTRODUCTION The Cycle 3 Startup Test Program for. 0conee Unit.3 consisted of pre-
~
critical tests, zero power physics tests, and power escalation tests.
This report provides a summary of the zero power.and power escalation test results and includes, where appropriate, comparisons of measured and predicted values of important core parameters.
The zero power physics testing was initiated on November 28, 1577, and was completed on December 3,1977. Testing was conducted with the reactor at Hot Zero Power conditions (532'F, 2155 psig, and 0% FP). The core para-meters measured included all-rods-out critical boron concentration, iso-thermal temperature and moderator coefficients of reactivity, individual control rod groups and total group reactivity worths, ejected rod worth measurements, and differential boron worth measurements. The measurements and results are further described in Section II.
- Following satisfactory completion of zero power physics. testing, the power escalation testing began on December 3,1977, and was completed on Febru-ary 5,1978. The power escalation tests included core power distribution measurements at approximately 40% FP, 75% FP and 100% FP, power imbalance detector correlation tests, and measurements of reactivity coefficients at power.Section III describes the individual tests in more detail and summarizes the results of these tests.
. . . - . . . . . . . . . . --. . .- . .- .- - -=
I ,
. - II. 'ZER POWER, PHYSICS TESTING- .
7 A; -Initial Criticality 4 Cycle 3 initial criticality was achieved on Oconee 3 at 9:45- *
. hours on November _ 29, 1977 by first withdrawing control rods (Group ;
i _7l to 75% withdrawn and Group 8 to _37.5% withdrawn) and initiating +
r a' continuous but regulated feed and t1eed deboration of the Reactor Coolant System. Inverse multiplication plots versus boron i concentration and time were maintained, and the feed'and bleed was terminated when these plots reached a value of approximately .
o 0.03. Criticality was' achieved with equilibrium conditions reached at 9:45 hours with Control Rod Group 7 at-75% withdrawn and a F Reactor Coolant System boron concentration of 1239 ppm.
This measured critical boron concentration of 1239 ppm met the acceptance criterion of'1236 ppm 1100 ppm.
, B. All Regulating Rods 0ut Boron' Concentration L
E The-all rods out configuration was achieved by boration of Control 4
Rod Group 7 to 100% withdrawn, and then achieving an equilibrium
, boron condition within the Reactor Coolant System. The Reactor Coolant System boron concentration at these equilibrium ' conditions was sampled and measured to' be 1245 ppm. ;
} This value of 1245 ppm met thd acceptance criterion of 1261 ppm 1100 ppm.-
4:
C.. Temperature Coefficients of Reactivity The hot zero power temperature coefficients .of reactivity were
!- measured at:two control rod configurations - all rods out (Group 8 inserted)~and Groups 5-7 fully inserted. The test consisted of.
[ sequentially changing the RCS temperature by -5 F, +10*F, and. -5 F
- and by measuring the associated changes in the core reactivity. The temperature coefficient was obtained by dividing the reactivity -
F changes by the corresponding temperature changes.. The moderator-
, coefficient of reactivity was obtained by subtracting the predicted
- isothermal Doppler coefficient from the' temperature coefficient.
s
[
-The measured moderator and temperature coefficients of reactivity.
F :are shown in Table 1 along with their predicted values. The test E satisfactorily met the acceptance criteria requiring the measured and predicted-reactivity coefficients to agree within a tolerance i- of +0.4!x 10 " (AK/K)/ F and reniring the measured moderator co-t effTcient to be less than +0.5 x 10 4 (LK/K)/*F.
+
.' D . Control ~RodWorthMeasurements j 1
Group' integral and differential worths'were obtained for Control i
~ Rod Groups 5;through 7 with Group 8 at 37.5% withdrawn by debora-tion 1from an all-rods-out_ configurytion. _ The measured reactivity.
- w. -~N . y y c -
worths of the Regulating Control Rod Groups 5 through 7 met the acceptance criteria requiring the predicted worth of the individual groups to be within +15% of the measured value and the predicted total worth of the regulating groups to be within 110% of the measured value. Table 2 illustrates the control rod worth measure-ment data as well as comparisons to pertinent predicted values.
E. Boron Worth Measurements A measured differential boron worth of 1.13%(AK/K)/100 ppm was ob-tained, which met the acceptance criterion of 1.02%(AK/K)/100ppmb 110% of measured value.
F. Ejected Rod Worth Measurement In order to measure the worst case ejected control rod worth, Rod 4 in Control Rod Group 6 (predicted to be the most reactive rod) was borated out of the core while Control Rod Group 5 was main-tained at 81% withdrawn and Control Rod Group 8 at 37.5% withdrawn.
The measured worth of rod 6-4 was 0.83% AK/K which met the accep-tance criteria requiring the ejected rod worth to be less than or equal to 1% aK/K and to be within +20% of measured of the predicted
~~
value of 0.73% aK/K.
A second set of ejected rod worth measurements were performed by in-dividually swapping rod 6-2, 6-4, 6-6 and 6-8 out of the core and compensating by moving Control Rod Group 5. These four rods are in core symmetry and are predicted to be the highest worth rods and also of equal magnitude due to core symmetry. The test is designed to assure that the maximum worth. ejected rod was indeed measured and also to give an. indication of any asymmetric radial power distribution.
The results of this test indicated that an asymetric power distribu-tion did exist. At this time the control rod drive power supplies for rods 6-4 and 6-6 were checked and verified to be in order. Since all zero power physics testing met the acceptance criteria, it was decided to begin power escalation in order to further characterize the power distribution asymmetry.
III. POWER ESCALATION SEQUENCE TESTING A. Evaluation of the Asymmetric Power Distribution The asynynetric power distribution identified by the deviation among measured symmetric ejected rod worths during zero power physics testing developed into a power tilt as power was escalated to 25%
FP. At 25% FP Control Rod Groups 5 and 6 were borated to 100% with-drawn and Group 7 to 80% withdrawn in order to determine the effects.
of all-rods-out, but the tilt did not decrease. Group 8 rods were then exercised and it was determined that rod 8-3 was unlatched.
The reactor was shut down to allow recoupling of the rod. Ejected rod worth measurements at zero power were repeated with the maximum worth rod meeting the acceptance criteria. Power was increased to-the 40% FP power escalation sequence testing plateau and the measured tilt haa decreased to within the Technical Specification limit.
Normal power escalation sequence testing then continued.
B. Core Power Distribution Results Core power distribution measurements were perfonned at 40% FP, 75%
FP, and 100% FP in order to verify that the measured power distri-bution is consistent with the predicted distribution. Corrected instrument readings from the incore instrumentation were.taken from
. the process computer while the plant was operating at these power plateaus and were then compared to calculated power distributions at comparable- burn-up, rod pattern, boron concentration, and power l evels.
The results of these comparisons are shown on the enclosed eighth core maps of radial and total peaking factors. (Figures 1-6). The following acceptance criteria were used at the three power level testing plateaus.
40% FP Acceptance Criteria The largest measured radial peak i 110% of the largest predicted ;
radial peak.
The largest measured total peak i 115% of the largest predicted
, total peak.
75% FP and 100% FP Acceptanc.e Criteria ,
I The largest measured radial peak 1 105% of the largest predicted i radial peak. j l
.i I
l 1
TheTlargest measured total peak < 107.5% of the largest predicted total peak.
These acceptance criteria for the core power distribution measure-ments'at 40% FP, 75% FP, and 100% FP were met.
During the execution of the core power distribution test, the following. parameters were checked:
- 1. SPND background readings and background corrections
- 2. Reactor power imbalance values
- 3. Worst case extrapolated minimum DNBR
- 4. - -Quadrant power tilt
- 5. Extrapolated worst case maximum linear heat rate
- 6. .Non-extrapolated worst case maximum linear heat rate
- 7. Tilt and imbalance values from back-up incore detectors.
Table 3 provides the results of the minimum DNBR and maximum linear heat rate measurements and extrapolations and shows that all values, both extrapolated and measured, met the acceptance criteria.
C. Power Imbalance Detector Correlation Test Results 3 The Power Imbalance Detector Correlation Test was performed initially at the 40% testing plateau in order to verify that the out-of-core detectors measurement of offset was sufficiently conservative with respect to the incore measured offset to assure that the tolerance assumed in the safety analysis would be met during full power opera-tion. All four out-of-core detectors were verified to satisfy the desired offset correlation.
Following several days operation at full power, the power imbalance detector correlation test-at 75% FP was performed to varify that the out-of-core detectors measure core offset within the tolerances assumed in the Safety Analysis (i.e., out-of-core offset = incore offset +3.5%).
The test verified that all four out-of-core detectors satisfy the_
-desired offset correlation. A comparison of incore detector imbalance to back-up recorder imbalance showed that for all values of imbalance measured the maximum' difference was well within the +7.5% acceptance criteria for incore tc back-up incore calculated offset.
D. Reactivity Coefficient at Power The temperature coefficient of reactivity and the power coefficient of reactivity were measured at the 100% FP testing plateau. The measured temperature coefficient was -1.84 x 10 4 (AK/K)/*F which met the acceptance criterion of being less than -0.143 x 10 4 (AK/K)
/*F for power levels above 95% FP. A maximum negative temperature coefficient limit of -1.54 x 10 4 (AK/K)/*F was established -for the beginning of this fuel cycle in order. to assure that the end-of-cycle moderator temperature coefficient value is not more negative than the value used_in the FSAR steamline break analysis. When this limit' is extrapolated from beginning-of-cycle for which .it is speci-fied to 43 EFPD at which time the measurement was made, the maximum negative temperature coefficient limit becomes -1.72 x 10 4 ( AK/K)/* F.
The measured value exceeded this acceptance criterion. It should be 4o- , e - , - y , , -
i o .
l i~ ~
recognized.that although the acceptance criterion was exceeded when the temperature ' coefficient was measured at 43' EFPD, the test only determines if a. limiting value might be approached later l- in the cycle. There currently exists a large margin between the l
existing temperature coefficient and the limit. -The~ situation is
'under evaluation to determine if and when the maximum negative limit will be approached.
! 'The measured power-Doppler coefficient was -1.59 x 10~ ( AK/K)/%FP.
This -value is more negativ~e than the upper limit of'-0.55 x 10 l ( AK/K)/%FP, and therefore, met the acceptance criterion.
! Table 1 also contains the values of the reactivity coefficients measured at the 100% FP testing plateau.
l l'
i 1
l l
.l I
l
- i. !
s TABLE 1
SUMMARY
'0F REACTIVITY COEFFICIENTS x
' CONDITIONS MEASURED VALUE PREDICTED VALUE ACCEPTANCE CRITERION-
-HOT'ZER0 POWER GPS 5&60100%WD
. TEMPERATURE GP-7087.7%WD +0.034 x 10 4(AK/K)/ F -0.15 x 10 4(AK/K)/ F Predicted +0.4 x 10 4(AK/K)/ F
- COEFFICIENT #1' 1245 ppmb HOT ZERO POWER GPS 5860700%WD -
Predicted +0.4 x 10 4( AK/K)/
MODERATOR .
GP.7087.1%WD +0.22 x 10 4(AK/K)/ F +0.04 x 10 4(AK/K)/ F Less than T0.5 x-10 4(AK/K)/ r.
COEFFICIENT #1 1245 ppmb HOT ZERO POWER GPS 6&700%WD -
TEMPERATURE GP 505.13%WD- -0.71 x 10 4(aK/K)/'F -0.85 x 10 4(AK/K)/ F Pre'dicted 4044 x 10 4(AK/K)/ F -
COEFFICIENT #2 GP 8037.5%WD 992 ppmb ,
HOT ZERO POWER GPS 6&700%WD Predicted +0.4 x 10 4(aK/K)/*F MODERATOR GP 505.13%WD -0.52 x 10 4(AK/K)/ F -0.66 x 10 4(AK/K)/ F Less than T0.5 x 10 4(AK/K)/*F C0 EFFICIENT #2 GP 8037.5%WD 992 ppmb HOT FULL POWER 4 TEMPERATURE 43 EFPD -1.84 x 10 '*( AK/K)/ F N/A Less than -0.143 x 10 C0 EFFICIENT Greater than -1.72 x4 ( 10{aK AK/K)/*C HOT FULL POWER POWER-D0PPLER 43 EFPD -1.59 x 104(aK/K)/%FP N/A Less than -0.55 x 104(AK/K)/%FP-COEFFICIENT
-7,
4 TABLE 2
SUMMARY
OF CONTROL R0D WORTH MEASUREMENTS
~
CONTROL R0D PREDICTED MEASURED .% DEVIATION GROUP WORTH WORTH FROM MEASURED
.(%AK/K) (%AK/K) i Group 7 0.68 0.71 - 4.2%
Group 6 0.98 1.08 - 9.2%
Group 5 0.98 0.98 0.0%
1.
TOTAL-5-7 2.64 2.77 - 4.7%
4 4
4 b
4 I
a l
4 a
i 7
4 i
4
---M ge e t9- -
y ,,yawww g ,y h -- e v-y
a ,
MAXIMUM WORST- . MAXIMUM WORST ACCEPTABLE MINIMUM 2
CASE ACCEPTABLE CASE WORST WORST ACCEPTABLEc MAXIMUM . WORST EXTRA- . CASE CASE WORST.
-LINEAR CASE IWORST EXTRA I' P0 LATED EXTRAP. _ EXTRA'- CASE POWER HEAT : MAXIMUM CASE POLATION MAXIMUM MAXIMUM POLA1ED- EXTRAP.
. LEVEL? RATEL LHR MINIMUM POWER LHR LHR. ~ MINIMUM MINIMUM' ~
%FP (KW/FT). -(KW/FT). DNBR LEVEL (KW/FT)' (KW/FT)_ DNBR DNBR 38.9 4.87- -15.5 9.23- 85.0 10.54 20.15' 3.20 1.30 74.8 8.97 15.5 4.53 105.5' 12.65 20.15 2.60 1.30
~
-100.0. 11.34 15.5 3.44 105.5 11.96 20.15 2.97 1.30-1-The extrapo.: . n power level is the overpower trip setpoint of the next power
. level-platers- *A the escalation sequence. .
3Eg A11 cases e: :- -: ted ' to .105. 5%FP >< gn
. EE 24 Co M M-DE
@b c sq g gx "'
m Ei n 52 '
EI$E Oo-EE
- P SEE-mo T
i
1,4 FIGURE:1 40%'FP RADIAL PEAKING FACTORS' 8 9 10 11 12 13 14- 15 0.82. 0.90- 0.79 0.98 1.53 0.88 0.47 0.72-H. 0.82 0.97 0.77 0.96 1.40 0.87 0.48 0.69 1.40 1.05 1.11 1.05 0.96 0.76 0.73 K 1.41 0.95 1.08 0.98 0.95 0.78 0.78 0.77 1.22 1.06 1.03 1.16 0.73 L 0.67 1.14 0.99 0.98 1.33- 0.75
-1.36 -1 .31 1.05 1.10 M 1.36 .1.29 1.06 1.15 Largest Measured Peak = 1.53 1.23 1.17 0.79 Largest Predicted-Peak = 1.41 N 1.29 1.14 0.80 Deviation From Predicted = +8.51%
0.91 Measured 0 0.91 Predicted
~
Core Conditions for Pre <icted Core Conditions for Measured Peaking Factors: Peaking Factors
-Group.6 = 87.1% wd Group 6-='86.3% wd Group 7 = -15.8% wd i Group 7 = L12.6% wd
- Group 8 = 35.3% wd' Group 8 = 25.5% wd
~
Imbalance'= +0.89% FP Imbalance = -0.14% FP
. Core Burnup = 2 EFPD Core Burnup = 0.6 EFPD~
4 -
t
FIGURE 2 40% FP TOTAL PEAKING FACTORS 8 9 10 11 12 13 14 15 1.00 1.06 0.94 1.11 1.81 ~1.02 0.52 0.90
-H 0.99 'l.17 0.97 1.18 1.71 1.06 0.55 0.86 1.68 1.21 -1.34 1.22 1.12 0.84 0.84 K 1.66 1.14 1.34- 1.25 1.19 0.96 0.98 0.89- 1.46 1.36 1.19 1.33 0.84 L 0.77 1.46 1.43 1.23- 1.63 0.95 1.60 1.54 1.20 1.30 M 1.73 1.69 1.34 1.43 Largest Measured Peak = 1.81 -1.47 1.23 0.94 Largest-Predicted Peak = 1.73 N 1.70 1.45 1.03 Deviation From Predicted = +4.62%
1.08 Measured 0 1.17 Predicted
- Core Conditions for Predicted Core Conditions for Measured
- Peaking Factors- Peaking Factors Group 6 = 87.1%:wd Group 6 = 86.3% wd 4 : Group 7 = 15.8% wd Group 7 = 12.6% wd
-Group 8 = 35.3% wd Group 8 = 25.5% wd Imbaleace = +0.89%'FP. Imbalance = -0.14% FP Core Burnup ='2 EFPD_
Core Burnup = 0.6 EFPD
- 11'-
~
FIGURE 3 75% FP RADIAL PEAKING-FACTORS.
9 10 -11 12 13 14 15 0.87 0.95 0.84- 1.02 1.38 0. 91 0.49 0.78 H 0.82 0.96- 0.78 0.96 1.38 0.87 0.49 0.70 c 1.33 1.04 1.14 1.08 0.98 0.78 0.76 K 1.38 0.94 1.08 0.98 0.96 0.79 0.79 0.81 1.25 1.04 1 . 04 1.12 0.74
.L 0. 68 1.14 0.99' O.98 1.31 0.75 1.39 1.33 1.08 1.li M 1.35 1.29 1.06 1.14 Largest Measured Peak = 1.39 1.27 1.19 0.80 I Largest Predicted Peak.= 1.38 N 1.~ 29 1.14 0.81 '!
. Deviation From Predicted = +0.72%
0.93 Measured 0 0.92 Predicted I
i- Core Conditions for Predicted
' Core Conditions for Measured Peaking Factors Peaking Factors-4 Group 6 = 87.1% wd- Group ~6 = 87.0% wd Group.7 = '.5.8%_wd . Group 7 = 13.0% wd Group 8 = 25.5%-wd . Group 8 = 18.0% wd Imbalance = +2.22% FP ~ Imbalance = -2.3% FP Core Burnup =.3 EFPD Core Burnup = 3.3 EFPD f
FIGURE 4
'75%-FP TOTAL. PEAKING FACTORS
~
8- -
9 10' .11 12 13 14 15
-1 .01 1.08 0.97 1.15 1.56 1.04 0.58 0.81
~H- 0.99 ~1.17 0.97 1.18 1.71 1.06 0.54 -0.86 1.55 1.15 1.32- 1.20 .1.10 0.89 0.88 K 1.66 1.14 1.34 1.25 1.19 .0.96 0.98 1.01 1.41 1.32 1.18 -1.32 0.87 L 0.77 1.46 1.46 1.23 1.63 0.95 i
1.60 1.56 1.23 1.30 l M 1.73- 1.69 1.34 1.43 !
l 1
Largest Measured Peak = 1.60 -1.52 1.39 0.95 )
Largest Predicted Peak = 1.73 N 1.70 1.45 1.03 Deviation From Predicted = -7.51% ~
1.09 Measured- l 0 1.17 Predicted l I
Core Conditions for Predicted Core Conditions for Measured Peaking ~. Factors - Peaking Factors Group _6 = 87.1% wd' -Group 6 = 87.0% wd
. Group 7 = 15.8% wd ' Group 7 = 13.0% wd Group 8 = 25.5% wd-- Group 8 = 18.0% wd Imbalance = +2.22% FP Imbalance ~= -2.3% FP Core Burnup = 3 EFPD Core Burnup = 3.3 EFPD 13 --
FIGURE 5 100% FP RADIAL PEAKING FACTORS-8 9 10 11 12 13 14 15
-0.85 0.94 0.84 1.00 1.35 0.91 0.52 0.71 H. 0.81 0.95 0.78 0.96 1.36 0.87 0.49 0.72 1.31 1.04 1.11 1.05 0.96 0.77 0.77 K- 1.35' O.94 1.07 0.98 0.96 0.80 0.80 0.85 1.21 1.00~ 1.01 1.01 0.74 L- 0.68 1.14 1.00 0.99 1.30 0.77' 1.34 1.29 1.05 1.08 M 1.33 1.28 1.06 1.14 Largest Measured Peak-=-1.35 1.32 1.15 0.79 Largest Predicted Peak = 1.36 N 1.28 1.14 0.83 Deviation From Predicted = -0.73%
0.93 Measured 0- 0.92 Predicted l
Core Conditions-for Predicted Core-Conditions for Measured Peaking Factors' Peaking Factors Group 6 = 87.1% wd 'roup 6 = 88.0% wd.
1 Group:7_= 15.8% wd Group 7 = 14.0%_wd i Group 8 = '19.1% wd . Group 8 = 10.6% wd
~ Imbalance =:-0.1%'FP Imbalance = -1.95% FP LCore'Burnup = 4 EFPD Core Burnup_= 3.3 EFPD
- ?
l.
" l l
FIGURE 6-100%FP TOTAL PEAKING FACTORS 8 9 10 11 12 13 14 15 0.98 1.06 0.96 1.09 1.53 1.02 0.61 0.82 H~
0.96 1.14- .0.96 1.17 1.69 1.06 0.56 0.90 1.54 1.14- 1.27 1.24 1.08 0.88 0.86. .
K 1.63 1.11 1.32 1.24 1.21 1.00 1.C?
l l
1.05 1.39. 1.30 1.18 1.32 0.84 O.77 1.45 1.43 1.30 1.68 0.99 1.60 1.56 1.23 1.29
'" ' 1.71 1.66 1.37 1.48 Largest Measured Peak = 1.60 1.45 1.38 0.94 ,
Largest Predicted Peak = 1.71 N 1.70 1.49 1.08 Deviation from Predicted = -6.43%
1.10 Measured 0
1.21 Predicted
-Core Conditions for Predicted Core Conditions for Measured Peaking Factors Peaking Factors Group 6 = 87.1% WD Group 6 = 88.0% WD Group 7 =~ 15.8% WD Group 7 = 14.0% WD
. Group 8 = -19.1%'WD Group 8 = 10.6% WD Imbalance = -0.~% FP Imbalance = -1.95% FP Core.Burnup = 4 EFPD Core Burnup = 3.3 EFPD