Forwards Addl Info Re 781219 Response to Violations Noted in IE Insp Rept 50-348/78-27.Discusses Control Room Drawings & Controlled Manuals Located in Plant Maint Dept
ML19261B866
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 02/12/1979
From: Clayton F
ALABAMA POWER CO.
To: Long F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19261B864 List:
References
NUDOCS 7903070448
Download: ML19261B866 (2)


Text

, ,

% Aatama Power Comtuny

. 600 Norm 1&n Street Po9 Or+ ice Ocx 2641 4 B;rmingNm. Autuma 35291 1eeepr <;ne 205 3?3 5141 L'j%"i"; ,

A Alabama Power

'I]

tw munw m ewinc system February 12, 1979 Joseph M. Farley Muclear Plant NRC Inspection of September 12-15, 1978 Revision to Corrective Action Completion Dates Mr. F. J. Long, Chief Reactor Operations and Nuclear Support Branch U. S. Nuclear Regulatory Commission 101 Parietta Street, N.W.

Suite 3100 Atlanta, Georgia 30303 Re: RII: WAR 50-348/78-27

Dear Mr. Long:

This refers to apparent deficiencies (343/78-27-08) and (343/78-27-13) in the subject inspection report and the associated corrective actions described in my letter to you dated December 19, 1978, hereafter referred to as reference 2.

Deficiency (343/78-27-03) dealt with Control Room drawings affected by change notices (CN's) and not annotated as required by FNP-0-AP-4. The corrective action described in reference 2, item B, was completed for Con-trol Room drawings prior to February 1, 1979.

Deficiency (348/ 78-27-13) dealt with controlled manuals located in the plant Maintenance Department that were not controlled in accordance with FNT-0-AP-4. The corrective action described in reference 2, item D, was com .

plcted for all cont rolled manuals in the thintenance Department nrior to February 1, 1979.

At this time, all identified deficiencies have ocen corrected. However, due to an underestinate of the time required,those portions of the above corrective actions which were intended to determine if similar deficiencies existed elsewhere in the plant and to correct any deficiencies found have not been totally completed.

7003 070 Lf'{il 9900 V6

Mr. F. J. Long Page Two February 12, 1979 Full compliance for all plant groups will be verified by April 1, 1979.

Yours very truly, Y L F. L. Claytgn, Jr.

FLCJr/TSE:bhj cc: Mr. R. A. Thomas Mr. G. F. Trowbridge

.