Forwards Revision to 790917 Schedule Re Implementation of Mods Proposed in Fire Protection Program re-evaluation.All Sprinkler Sys Mods Completed by End of Second Refueling Outage
ML19253B594
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 10/10/1979
From: Clayton F
ALABAMA POWER CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
NUDOCS 7910160454
Download: ML19253B594 (3)


Text

'

Alabama Power Company 600 North 18th Street Post Office Box 2641 Birmingham. Alabama 35291 Telephone 205 323-5341 mk hboWc7 ,";/fint AlabamaPower the southern eMrc system October 10, 1979 Director of Nuclear Reactor Regulation U. S. Nuclear Ragulatory Commission Washington, D.C. 20555 Attn: Mr. Darrell G. Eisenhut

Dear Mr. Eisenhut:

RE: Letter from F. L. Clayton to Director of Nuclear Reactor Regulation dated September 17, 1979 In the referenced letter Alabama Power Company submitted a revised schedule for implementing modifications proposed in the Farley Nuclear Plant Fire Protection Program Reevaluation. The date for having sprinkler systems (item 1) completed for Unit 1 was inadvertently changed.

The attached is a corrected schedule indicating a completion of all sprinkler systems by the end of the second refueling outage.

If you have any questions, please advise.

Yours very truly, F. L. Clayto , Jr.

FLCJr/HRF:bhj Attachment cc: Mr. R. A. Thomas Mr. G. F. Trowbridge 1154 282

(

7910100 a31' F

(STATUS AS OF 9-28-79)

TABLE 4.2-2 IMPLDIENTATION DATES FOR PROPOSED MODIFICATIONS Unit 1 Unit 2

1. Sprinkler (All systems) End of 2nd refueling outage Before fuel load Roca 224, Area 16 Complete N/A
2. Yard Hydrants 11/1/79 N/A
3. Fortable Extinguishers Complete Before fuel load
4. Hose Stations 10/1/75 Before fuel load
5. Smoke Detectors 9/1/80 9/1/80
6. UL Rated Doors Complete Before fuel load
7. Penetration Serls 9/1/80 Before fuel load
8. Portable Smoke Removal Complete N/A ,
9. Tern. Cabinet Water Complete Before fuel load Protection
10. Damper Rewotl: End of 2nd Before fuel load refueling outage
11. Eight Hour Battery Packs Complete Before fuel load
12. Hose Stations in CTMT Complete Before fuel load
13. RCP Oil Collection End of 2nd Before fuel load refueling outage
14. Fire Pump Barriers Complete N/A
15. DG Pot Transformer Complete Complete Circuit
16. Barriers 9/1/30 Six (6) months after fuel load (Note 3)
17. Inside Water Supply Complete Before fuel load
18. HSP Switch End of 2nd Before fuel load Relocation refueling outage Y0b

Item Date Unit 1 Unit 2

19. HSP Instrument Mods. End of 2nd Before fuel load refueling outage
20. Barriers in S. W. Complete Complete Structure
21. Fireproof Control Room Complete N/A Kit
22. Modify New Fuel End of 2nd N/A Storage Racks reF;eling outage
23. Reroute B Train Aux. Complete N/A Feed Pump Room Cooler (added subsequent to Anendment 4)

Note 1 All administrative commitments will be complete 90 days after -

1st refueling outage.

Note 2 The 2nd refueling will be after 9/1/80.

Note 3 If installea prior to fuel load, the kaowool will be damaged by additional cable running.