ML17234A730
ML17234A730 | |
Person / Time | |
---|---|
Site: | Monticello |
Issue date: | 08/21/2017 |
From: | Robert Daley NRC/RGN-III |
To: | Gardner P Northern States Power Company, Minnesota |
References | |
IR 2017007 | |
Download: ML17234A730 (20) | |
See also: IR 05000263/2017007
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, IL 60532-4352
August 21, 2017
Mr. Peter A. Gardner
Site Vice President
Monticello Nuclear Generating Plant
Northern States Power Company, Minnesota
2807 West County Road 75
Monticello, MN 55362-9637
SUBJECT: MONTICELLO NUCLEAR GENERATING PLANTTRIENNIAL FIRE
PROTECTION INSPECTION REPORT 05000263/2017007
Dear Mr. Gardner:
On July 14, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed a Triennial
Fire Protection Inspection at your Monticello Nuclear Generating Plant. The enclosed
inspection report documents the inspection results, which were discussed on July 14, 2017,
with Mr. P. Gardner and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and
compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed
personnel.
The NRC inspectors documented one finding of very-low safety significance (Green) in this
report. This finding was determined to involve a violation of NRC requirements. However,
because of its very-low safety significance and because the issue was entered into your
Corrective Action Program, the NRC is treating the issue as a Non-Cited Violation in
accordance with Section 2.3.2 of the NRC Enforcement Policy.
If you contest the violation or significance of this Non-Cited Violation, you should provide
a response within 30 days of the date of this inspection report, with the basis for your denial,
to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington,
DC 20555 0001; with copies to the Regional Administrator, Region III; the Director, Office of
Enforcement; and the NRC resident inspector at the Monticello Nuclear Generating Plant.
P. Gardner -2-
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for
Withholding.
Sincerely,
/RA/
Robert C. Daley, Chief
Engineering Branch 3
Division of Reactor Safety
Docket No. 50-263
License No. DPR-22
Enclosure:
Inspection Report 05000263/2017007
cc: Distribution via LISTSERV
P. Gardner -3-
Letter to Peter A. Gardner from Robert C. Daley dated August 21, 2017
SUBJECT: MONTICELLO NUCLEAR GENERATING PLANTTRIENNIAL FIRE
PROTECTION INSPECTION REPORT 05000263/2017007
DISTRIBUTION:
RidsNrrDorlLpl3
RidsNrrPMMonticello
RidsNrrDirsIrib Resource
Cynthia Pederson
DRPIII
DRSIII
ROPreports.Resource@nrc.gov
ADAMS Accession Number ML17234A730
OFFICE RIII RIII RIII RIII
NAME IKhan for RDaley
AShaikh:cl
DATE 08/17/17 08/21/17
OFFICIAL RECORD COPY
U. S. NUCLEAR REGULATORY COMMISSION
REGION III
Docket No: 50-263
License No: DPR-22
Report No: 05000263/2017008
Licensee: Xcel Energy, Northern States Power Company (Operator)
Facility: Monticello Nuclear Generating Plant
Location: Monticello, MN
Dates: June 12 - July 14, 2017
Inspectors: I. Hafeez, Reactor Inspector
I. Khan, Reactor Inspector
A. Shaikh, Senior Reactor Inspector (Lead)
Approved by: Robert C. Daley, Chief
Engineering Branch 3
Division of Reactor Safety
Enclosure
SUMMARY
Inspection Report 05000263/2017007; 06/12/2017-07/14/2017; Monticello Nuclear Generating
Plant; Routine Triennial Fire Protection Baseline Inspection.
This report covers an announced Triennial Fire Protection Baseline Inspection. The inspection
was conducted by Region III inspectors. One finding was identified by the inspectors. The
finding was considered a Non-Cited Violation of U.S. Nuclear Regulatory Commission (NRC)
regulations. The significance of most findings is indicated by their color (i.e., greater than
Green, or Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609,
Significance Determination Process, dated April 29, 2015. Cross-cutting aspects were
determined using IMC 0310, Aspects Within the Cross Cutting Areas. Findings for which the
Significance Determination Process does not apply may be Green or be assigned a severity
level after NRC management review. All violations of NRC requirements are dispositioned in
accordance with the NRCs Enforcement Policy dated November 1, 2016. The NRCs program
for overseeing the safe operation of commercial nuclear power reactors is described in
NUREG-1649, Reactor Oversight Process, Revision 6, dated July 2016.
Cornerstone: Initiating Events
Green. The inspectors identified a finding of very-low significance (Green) and an
associated Non-Cited Violation of License Condition 2.C.4 of the Monticello Nuclear
Generating Plant, Unit No. 1, Renewed Facility Operating License for implementing an
alternative compensatory measure that was adverse to safety shutdown. Specifically,
the licensee approved the installation of a temporary fuel oil pump, in lieu of a
continuous fire watch, which reduced the defense in depth of the Fire Protection
Program.
The inspectors determined that the use of a temporary fuel oil pump in the event of
a fire, in lieu of a continuous fire watch, constituted an adverse change to the Fire
Protection Program, was contrary to License Condition 2.C.4 and a performance
deficiency. The performance deficiency was more-than-minor because it affected the
Protection Against External Factors attribute of the Initiating Events Cornerstone and
adversely affected the cornerstone objective to limit the likelihood of events that upset
plant stability and challenge critical safety functions during shutdown as well as power
operations. Specifically, the use of the alternative compensatory measure reduced the
defense in depth of the Fire Protection Program by failing to provide compensatory
measures to reduce the likelihood of occurrence of a fire and failing to provide prompt
detection of a fire. In accordance with IMC 0609, Significance Determination Process,
Attachment 0609.04, Initial Characterization of Findings, Table 2 the inspectors
determined the finding affected the Initiating Events cornerstone. The finding degraded
fire protection defense-in-depth strategies, and the inspectors determined, using
Table 3, that it could be evaluated using Appendix F, Fire Protection Significance
Determination Process. The inspectors determined that the finding represented a
low degradation and was screened as having very-low safety significance (Green) in
Task 1.3.1 of IMC 0609, Appendix F, because repair activities were in place that would
have maintained safe shutdown (SSD) conditions and were reasonably achievable.
This finding had a cross-cutting aspect in the Conservative Bias component of the
Human Performance cross-cutting area. Specifically, the licensee implemented an
alternate compensatory measure that only focused on the emergency diesel generator
operability and hence, the post-SSD strategy of the plant without considering the
2
defense in depth requirements of their Fire Protection Program to prevent, detect,
and suppress a fire that could affect equipment needed for SSD of the plant.
(Section 1R05.11b)
3
REPORT DETAILS
1. REACTOR SAFETY
Cornerstones: Initiating Events and Mitigating Systems
1R05 Fire Protection (71111.05T)
The purpose of the Fire Protection Triennial Baseline Inspection was to conduct a
design-based, plant specific, risk-informed, onsite inspection of the licensees Fire
Protection Programs defense-in-depth elements used to mitigate the consequences
of a fire. The Fire Protection Program shall extend the concept of defense-in-depth to
fire protection in plant areas important to safety by:
preventing fires from starting;
rapidly detecting, controlling and extinguishing fires that do occur;
providing protection for structures, systems, and components important to safety
so that a fire that is not promptly extinguished by fire suppression activities will
not prevent the safe-shutdown (SSD) of the reactor plant; and
taking reasonable actions to mitigate postulated events that could potentially
cause loss of large areas of power reactor facilities due to explosions or fires.
The inspectors evaluation focused on the design, operational status, and material
condition of the reactor plants Fire Protection Program, post-fire SSD systems, and
B.5.b mitigating strategies. The objectives of the inspection were to assess whether
the licensee had implemented a Fire Protection Program that: (1) provided adequate
controls for combustibles and ignition sources inside the plant; (2) provided adequate
fire detection and suppression capability; (3) maintained passive fire protection features
in good material condition; (4) established adequate compensatory measures for
out-of-service, degraded or inoperable fire protection equipment, systems or features;
(5) ensured that procedures, equipment, fire barriers and systems exist so that the
post-fire capability to safely shutdown the plant was ensured; (6) included feasible and
reliable operator manual actions when appropriate to achieve SSD; and (7) identified fire
protection issues at an appropriate threshold and ensured these issues were entered
into the licensees Problem Identification and Resolution Program.
In addition, the inspectors review and assessment focused on the licensees post-fire
SSD systems for selected risk-significant fire areas. Inspector emphasis was placed on
determining that the post-fire SSD capability and the fire protection features were
maintained free of fire damage to ensure that at least one post-fire SSD success path
was available. The inspectors review and assessment also focused on the licensees
B.5.b-related license conditions and the requirements of Title 10 of the Code of Federal
Regulations (CFR), Part 50.54 (hh)(2). Inspector emphasis was to ensure that the
licensee could maintain or restore core cooling, containment, and spent fuel pool cooling
capabilities utilizing the B.5.b mitigating strategies following a loss of large areas of
power reactor facilities due to explosions or fires. Documents reviewed are listed in the
Attachment to this report.
4
The fire areas and fire zones and B.5.b mitigating strategies selected for review during
this inspection are listed below and in Section 1R05.13. The fire areas and fire zones
selected constituted four inspection samples and the B.5.b mitigating strategies selected
constituted two inspection samples, respectively, as defined in Inspection
Procedure 71111.05T.
Fire Area Fire Zone Description
II 1A Residual Heat Removal and Core Spray Pump Room, Division II
I 1B Residual Heat Removal and Core Spray Pump Room, Division I
I 2B Control Rod Drive Hydraulic Control Unit Area
X 30 Turbine Operating Floor
.1 Protection of Safe Shutdown Capabilities
a. Inspection Scope
For each of the selected fire areas, the inspectors reviewed the fire hazards analysis,
SSD analysis, and supporting drawings and documentation to verify that SSD
capabilities were properly protected.
The inspectors also reviewed the licensees design control procedures to ensure that
the process included appropriate reviews and controls to assess plant changes for any
potential adverse impact on the Fire Protection Program and/or post-fire SSD analysis
and procedures.
b. Findings
No findings of significance were identified.
.2 Passive Fire Protection
a. Inspection Scope
For the selected fire areas, the inspectors evaluated the adequacy of fire area barriers,
penetration seals, fire doors, electrical raceway fire barriers, and fire-rated electrical
cables. The inspectors observed the material condition and configuration of the
installed barriers, seals, doors, and cables. The inspectors reviewed approved
construction details and supporting fire tests. In addition, the inspectors reviewed
license documentation, such as U.S. Nuclear Regulatory Commission (NRC) Safety
Evaluation Reports, and deviations from NRC Regulations and the National Fire
Protection Association standards to verify that fire protection features met license
commitments.
The inspectors walked down accessible portions of the selected fire areas to observe
material condition and the adequacy of design of fire area boundaries (including walls,
fire doors, and fire dampers) to ensure they were appropriate for the fire hazards in the
area.
5
The inspectors reviewed the installation, repair, and qualification records for a sample of
penetration seals to ensure the fill material was of the appropriate fire rating and that the
installation met the engineering design.
b. Findings
No findings of significance were identified.
.3 Active Fire Protection
a. Inspection Scope
For the selected fire areas, the inspectors evaluated the adequacy of fire suppression
and detection systems. The inspectors observed the material condition and
configuration of the installed fire detection and suppression systems. The inspectors
reviewed design documents and supporting calculations. In addition, the inspectors
reviewed license basis documentation, such as, NRC Safety Evaluation Reports,
deviations from NRC Regulations, and National Fire Protection Association standards
to verify that fire suppression and detection systems met license commitments.
b. Findings
No findings of significance were identified.
.4 Protection from Damage from Fire Suppression Activities
a. Inspection Scope
For the selected fire areas, the inspectors verified that redundant trains of systems
required for hot shutdown would not be subject to damage from fire suppression
activities or from the rupture or inadvertent operation of fire suppression systems
including the effects of flooding. The inspectors conducted walkdowns of each of the
selected fire areas to assess conditions such as the adequacy and condition of floor
drains, equipment elevations, and spray protection.
b. Findings
No findings of significance were identified.
.5 Alternative Shutdown Capability
a. Inspection Scope
The inspectors reviewed the licensees systems required to achieve alternative SSD to
determine if the licensee had properly identified the components and systems necessary
to achieve and maintain SSD conditions. The inspectors also focused on the adequacy
of the systems to perform reactor pressure control, reactivity control, reactor coolant
makeup, decay heat removal, process monitoring, and support system functions.
6
The inspectors conducted selected area walkdowns to determine if operators could
reasonably be expected to perform the alternate SSD procedure actions and that
equipment labeling was consistent with the alternate SSD procedure. The review also
looked at operator training as well as consistency between the operations shutdown
procedures and any associated administrative controls.
b. Findings
No findings of significance were identified
.6 Circuit Analyses
a. Inspection Scope
The inspectors verified that the licensee performed a post-fire SSD analysis for the
selected fire areas and the analysis appropriately identified the structures, systems, and
components important to achieving and maintaining SSD. Additionally, the inspectors
verified that the licensee's analysis ensured that necessary electrical circuits were
properly protected and that circuits that could adversely impact SSD due to hot shorts,
shorts to ground, or other failures were identified, evaluated, and dispositioned to ensure
spurious actuations would not prevent SSD.
The inspectors' review considered fire and cable attributes, potential undesirable
consequences, and common power supply/bus concerns. Specific items included the
credibility of the fire threat, cable insulation attributes, cable failure modes, and
actuations resulting in flow diversion or loss of coolant events.
The inspectors also reviewed cable raceway drawings for a sample of components
required for post-fire SSD to verify that cables were routed as described in the cable
routing matrices.
The inspectors reviewed circuit breaker coordination studies to ensure equipment
needed to conduct post-fire SSD activities would not be impacted due to a lack of
coordination. Additionally, the inspectors reviewed a sample of circuit breaker
maintenance records to verify that circuit breakers for components required for post-fire
SSD were properly maintained in accordance with procedural requirements.
The inspectors verified for cables that are important to SSD, but not part of the
success path, and that do not meet the separation/protection requirements of
Section III.G.2 of 10 CFR Part 50, Appendix R, that the circuit analysis considered the
cable failure modes. In addition, the inspectors have verified that the licensee has
either: (1) determined that there is not a credible fire scenario (through fire modeling),
(2) implemented feasible and reliable manual actions to assure SSD capability, or
(3) performed a circuit fault analysis demonstrating no potential impact on SSD
capability exists.
b. Findings
No findings of significance were identified.
7
.7 Communications
a. Inspection Scope
The inspectors reviewed, on a sample basis, the adequacy of the communication system
to support plant personnel in the performance of alternative SSD functions and fire
brigade duties. The inspectors verified that plant telephones, page systems, sound
powered phones, and radios were available for use and maintained in working order.
The inspectors reviewed the electrical power supplies and cable routing for these
systems to verify that either the telephones or the radios would remain functional
following a fire.
b. Findings
No findings of significance were identified.
a. Inspection Scope
The inspectors performed a plant walkdown of selected areas in which a sample of
operator actions would be performed in the performance of alternative SSD functions.
As part of the walkdowns, the inspectors focused on the existence of sufficient
emergency lighting for access and egress to areas and for performing necessary
equipment operations. The locations and positioning of the emergency lights were
observed during the walkdown and during review of manual actions implemented for
the selected fire areas.
b. Findings
No findings of significance were identified.
.9 Cold Shutdown Repairs
a. Inspection Scope
The licensee did not credit any repairs in order to achieve cold shutdown. Therefore, no
reviews were performed by the inspectors for this procedure section.
b. Findings
No findings of significance were identified.
8
.10 Compensatory Measures
a. Inspection Scope
The inspectors conducted a review to verify that compensatory measures were in place
for out-of-service, degraded or inoperable fire protection and post-fire SSD equipment,
systems, or features (e.g., detection and suppression systems, and equipment, passive
fire barriers, pumps, valves or electrical devices providing SSD functions or capabilities).
The inspectors also conducted a review of the adequacy of short term compensatory
measures to compensate for a degraded function or feature until appropriate corrective
actions were taken.
b. Findings
No findings of significance were identified.
.11 Review and Documentation of Fire Protection Program Changes
a. Inspection Scope
The inspectors reviewed changes to the approved Fire Protection Program to verify that
the changes did not constitute an adverse effect on the ability to safely shutdown. The
inspectors also reviewed the licensees design control procedures to ensure that the
process included appropriate reviews and controls to assess plant changes for any
potential adverse impact on the Fire Protection Program and/or post-fire SSD analysis
and procedures.
b. Findings
Implementation of Inadequate Alternate Compensatory Measure for Degraded Fire
Barrier
Introduction: The inspectors identified a finding of very-low significance (Green) and
associated Non-Cited Violation (NCV) of License Condition 2.C.4 of the Monticello
Nuclear Generating Plant, Unit No. 1, Renewed Facility Operating License. The
licensee implemented an alternative compensatory measure that was determined to be
adverse to safety shutdown. Specifically, the licensee approved the installation of a
temporary fuel oil pump, in lieu of a continuous fire watch, which reduced the defense in
depth of the Fire Protection Program.
Background: The inspectors reviewed Fire Protection Engineering Evaluation (FPEE)
FPEE-14-002, Revision 2, Establish Alternate Compensatory Measures for the
replenishment of Emergency Diesel Generator (EDG) Fuel Oil and Alternate Nitrogen,
which approved an alternative compensatory measure for a non-conforming fire barrier
in Fire Area 15E. Fire Area 15E contains redundant SSD Equipment, diesel fuel oil
transfer pumps P-11 and P-77, without separation as required by Section III.G.2 of
10 CFR Part 50, Appendix R. This issue was identified during the 2014 Triennial Fire
Protection Inspection (Inspection Report 05000263/2017008), and the licensee entered
this issue into the Corrective Action Program (CAP) as CAP 01394150, NRC TIA 2012-03
Final Response EDG Fuel Oil Supply. The inspectors reviewed Operations Manual
Section B.08.05-05 Step G.2 and determined it required a continuous fire watch to be
established in Fire Area 15E due to the condition described in CAP 01394150. The
9
inspectors reviewed FPEE-14-002 and determined that this evaluation approved
installation of a temporary fuel oil pump in the event of a fire in lieu of a continuous fire
watch. The inspectors determined that this alternative compensatory measure failed to
meet the objectives of a continuous fire watch, namely reducing the likelihood of the
occurrence of a fire and providing prompt detection of a fire. The use of the alternative
compensatory measure reduced the defense in depth of the Fire Protection Program,
and, therefore, was determined to be adverse to SSD.
Analysis: License Condition 2.C.4 states that NSPM may make changes to the
approved Fire Protection Program without prior approval of the Commission only if
those changes would not adversely affect the ability to achieve and maintain SSD in
the event of a fire. The inspectors determined that the use of a temporary fuel oil pump
in the event of a fire, in lieu of a continuous fire watch, constituted an adverse change
to the Fire Protection Program, was contrary to License Condition 2.C.4 and a
performance deficiency. Specifically, the alternative compensatory measure reduced
the defense in depth of the Fire Protection Program by failing to provide a means to
reduce the likelihood of a fire and failing to provide for detection of a fire. The inspectors
determined that the performance deficiency was more-than-minor because it affected
the Protection Against External Factors attribute of the Initiating Events Cornerstone and
adversely affected the cornerstone objective to limit the likelihood of events that upset
plant stability and challenge critical safety functions during shutdown as well as power
operations. Specifically, the use of the alternative compensatory measure reduced the
defense in depth of the Fire Protection Program by failing to provide compensatory
measures to reduce the likelihood of occurrence of a fire and failing to provide prompt
detection of a fire.
In accordance with Inspection Manual Chapter 0609, Significance Determination
Process, Attachment 0609.04, Initial Characterization of Findings, Table 2 the
inspectors determined the finding affected the Initiating Events cornerstone. The finding
degraded fire protection defense-in-depth strategies, and the inspectors determined,
using Table 3, that it could be evaluated using Appendix F, Fire Protection Significance
Determination Process. The inspectors determined that the finding represented a low
degradation and was screened as having very-low safety significance (Green) in
Task 1.3.1 of Inspection Manual Chapter 0609, Appendix F, because repair activities
were in place that would have maintained SSD conditions and were reasonably
achievable. The licensee entered this issue into the CAP as CAP 501000000439,
2017 FP TRI: Inappropriate Alt Comp Meas. The licensee implemented a modification
in 2015 to install a permanent fire barrier to provide separation between diesel oil pumps
P-11 and P-77.
This finding had a cross-cutting aspect in the Conservative Bias component of the
Human Performance cross-cutting area. Specifically, the licensee implemented an
alternate compensatory measure that only focused on the EDG operability and hence,
the post-SSD strategy of the plant without considering the defense in depth requirements
of their Fire Protection Program to prevent, detect, and suppress a fire that could affect
equipment needed for SSD of the plant.
Enforcement: License Condition 2.C.4 states that NSPM may make changes to the
approved Fire Protection Program without prior approval of the Commission only if those
changes would not adversely affect the ability to achieve and maintain SSD in the event
of a fire.
10
Contrary to the above, from April 23, 2014, to July 1, 2015, the licensee implemented an
alternative compensatory measure that adversely affected the ability to achieve and
maintain SSD in the event of a fire. Specifically, the alternative compensatory measure
reduced the defense in depth of the Fire Protection Program by failing to provide a
means to reduce the likelihood of a fire and failing to provide detection for a fire.
Because this violation was of very-low safety significance and it was entered into
the licensees CAP as Action Request 501000000439, this violation is being treated
as an NCV, consistent with Section 2.3.2 of the NRC Enforcement Policy.
(NCV 05000263/2017007-01, Inappropriate Alternative Compensatory Measure)
.12 Control of Transient Combustibles and Ignition Sources
a. Inspection Scope
The inspectors reviewed the licensee's procedures and programs for the control of
ignition sources and transient combustibles to assess their effectiveness in preventing
fires and in controlling combustible loading within limits established in the fire hazards
analysis. A sample of hot work and transient combustible control permits were also
reviewed. The inspectors performed plant walkdowns to verify that transient
combustibles and ignition sources were being implemented in accordance with
the administrative controls.
b. Findings
No findings of significance were identified.
.13 B.5.b Inspection Activities
a. Inspection Scope
The inspectors reviewed the licensees preparedness to handle large fires or explosions
by reviewing selected mitigating strategies. This review ensured that the licensee
continued to meet the requirements of their B.5.b-related License Conditions and
10 CFR 50.54(hh)(2) by determining that:
procedures were being maintained and adequate;
equipment was properly staged, maintained, and tested;
station personnel were knowledgeable and could implement the procedures; and
additionally, inspectors reviewed the storage, maintenance, and testing of
B.5.b-related equipment.
The inspectors reviewed the licensees B.5.b-related License Conditions and evaluated
selected mitigating strategies to ensure they remain feasible in light of operator training,
maintenance/testing of necessary equipment and any plant modifications. In addition,
the inspectors reviewed previous inspection reports for commitments made by
the licensee to correct deficiencies identified during performance of Temporary
Instruction 2515/171 or subsequent performances of these inspections.
The B.5.b mitigating strategies selected for review during this inspection are listed
below. The offsite and onsite communications, notifications/emergency response
organization activation, initial operational response actions and damage assessment
11
activities identified in Table A.3-1 of Nuclear Energy Institute 06-12, B.5.b Phase II
and III Submittal Guidance, Revision 2, are evaluated each time due to the mitigation
strategies scenario selected.
Revision 2, Licensee Strategy (Table)
Section
3.4.10 Portable Sprays (Table A.8-5.10)
3.4.5 Makeup to Condensate Storage Tank (Table A.8-5.5)
b. Findings
No findings of significance were identified.
4. OTHER ACTIVITIES
4OA2 Identification and Resolution of Problems (71152)
a. Inspection Scope
The inspectors reviewed the licensees CAP procedures and samples of corrective
action documents to verify that the licensee was identifying issues related to the Fire
Protection Program at an appropriate threshold and entering them in the CAP. The
inspectors reviewed selected samples of condition reports, design packages, and fire
protection system non-conformance documents.
b. Findings
No findings of significance were identified.
4OA6 Management Meetings
.1 Exit Meeting Summary
On August 3, 2017, the inspectors presented the inspection results to Mr. P. Gardner,
and other members of the licensee staff. The licensee acknowledged the issues
presented. The inspectors confirmed that none of the potential report input discussed
was considered proprietary.
ATTACHMENT: SUPPLEMENTAL INFORMATION
12
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee
A. Kouba, Regulatory Affairs Engineer
B. Dixon, Engineering Supervisor
M. Lingenfelter, Site Engineering Director
A. Ward, Regulatory Affairs Manager
P. Young, Program Engineering Manager
P. Nordmeir, Fire Protection Program Owner/Fleet Lead
J. Johnson, Fire Protection Systems Engineer
P. Gardner, Site Vice President
U.S. Nuclear Regulatory Commission
R. Daley, Branch Chief, EB3
D. Krause, Resident Inspector
P. Zurawski, Senior Resident Inspector
LIST OF ITEMS OPENED, CLOSED AND DISCUSSED
Opened
05000263/2017007-01 NCV Inadequate Fire Barrier Inspection Procedure
(Section 1R05.2b)
Closed
05000263/2017007-02 NCV Implementation of Inadequate Alternate Compensatory
Measure for Degraded Fire Barrier (Section 1R05.11b)05000263/2017007-01 NCV Inadequate Fire Barrier Inspection Procedure
(Section 1R05.2b)
Discussed
None
LIST OF ACRONYMS USED
CAP Corrective Action Program
CFR Code of Federal Regulations
EDG Emergency Diesel Generator
IMC Inspection Manual Chapter
NCV Non-Cited Violation
NRC U.S. Nuclear Regulatory Commission
SSD Safe Shutdown
Attachment
LIST OF DOCUMENTS REVIEWED
The following is a list of documents reviewed during the inspection. Inclusion on this list does
not imply that the NRC inspectors reviewed the documents in their entirety, but rather, that
selected sections of portions of the documents were evaluated as part of the overall inspection
effort. Inclusion of a document on this list does not imply NRC acceptance of the document or
any part of it, unless this is stated in the body of the inspection report.
CALCULATIONS
Number Description or Title Revision
05-084 Combustible Loading Calculation 002A
CORRECTIVE ACTION PROGRAM DOCUMENTS ISSUED DURING INSPECTION
Number Description or Title Date
501000000439 2017 Fire Protection Inappropriate Alt Comp Measure 07/10/2017
501000000489 2017 Fire Protection 0275-02 description error 07/11/2017
501000000492 2017 Fire Protection Inspection Battery Room Door Testing 07/11/2017
501000000146 2017 Fire Protection Inspection Fire hose Hydrostatic Test 06/28/2017
501000000232 2017 Fire Protection Inspection Operators Had Trouble 06/28/2017
Locating ASDS Panel Keys
01560947 2017 Fire Protection Inspection Location Description for RHR 06/13/2017
Aux Compressor
015660992 2017 Fire Protection Inspection USAR J.05 Typo 06/13/2017
501000000338 Grout Installation Fire Watch Requirements 07/05/2017
501000000416 8053 Procedure has Incorrect Terminology 07/05/2017
CORRECTIVE ACTION PROGRAM DOCUMENTS REVIEWED DURING INSPECTION
Number Description or Title Date
01427709 Crack in Fire Penetration FZ-3395 04/21/2014
01426153 Fire Hazard Found in Reactor Building 04/09/2014
01426122 Combustible Loading Issues Identified in B RHR Room 04/09/2014
01426116 Fire Penetrations Have Cosmetic Cracks 04/09/2014
01488072 Radio dead-zone areas in the Plant need to be identified 07/13/2015
DRAWINGS
Date or
Number Description or Title
Revision
NH-36246 Residual Heat Removal(A) 03/20/2012
NH-36248 Core Spray(A) 03/20/2012
NH-85509 P&ID Service Condensate System Radwaste Building 80
NQ-193744-1-1 Plant Administration Building Fire Main B
NX-16991-14 Fire Hazards Analysis, Plan View Administration Building A
Elevation 928-0
NX-7823-4-11C 11 RHR CTMT Spray INBD ISOL MO-2029, Scheme B3333 76
NX-7905-46-14E 11 RHR CTMT Spray OTBD ISOL MO-2020, Scheme B3339 78
NX-7905-46-15E 11 RHR CTMT Spray INBD ISOL MO-2022, Scheme B3709 76
2
DRAWINGS
Date or
Number Description or Title
Revision
NX-7905-46-16 Residual Heat Removal System Elementary Diagram (10-6) 77
FS-0014 Nelson Firestop Concrete Floor or Wall Cables 3
FS-0001 Nelson Firestop Concrete Floor or Wall Metallic Pipe or 2
Conduit
FS-0008 Nelson Firestop Concrete Floor or Wall Metallic Pipe or 4
Conduit
NQ-158852 Schematic of Pre-Action Fire Protection Systems A
PROCEDURES
Date or
Number Description or Title
Revision
0275-03 Fire Door Inspection 41
0273-02 Fire Barrier Wall, Damper and Floor Inspection 40
2204 Plant Shutdown 70
2B4328-A1 Cable and Raceway Information System Electrical Cable 06/28/2017
Schedule from C-03 to C-292
A.8-05.05 Make Up to CST 5
A.8-05.10 Portable Sprays 6
B.03.04-05 Operations Manual Section: Residual Heat Removal System 83
B3309-C03/1 Cable and Raceway Information System Electrical Cable 06/28/2017
Schedule from C-03 to C-292
B3333-C41/1 Cable and Raceway Information System Electrical Cable 06/27/2017
Schedule from B3309 to C-03
C41-JX105D/3 Cable and Raceway Information System Electrical Cable 06/27/2017
Schedule from C-41 to JX105D
0275-02 Fire Barrier Wall, Damper, and Floor Inspection 40
0275-03 Fire Door Inspections 41
1216-01 Fire Door Inspections 58
4024-PM Fire Door Maintenance 52
A.3-02-C Fire Zone 2-C West HCU Area Strategy A.3-02-C 12
A.3-02-B Fire Zone 2-B West HCU Area Strategy A.3-02-C 13
0274 Fire Hose Hydrostatic Test - Interior Hose Stations 30
C.4-B.08.05.A Plant Fire 32
8053 Fire Barrier Penetration Sealing and Visual Inspection 35
8053-01 Fire Barrier Penetration Utility Sealing 11
A.8-01.01 Extensive Damage Mitigation Strategy Overview 7
A.8-03.01 Initial Response Actions 5
A.8-05.05 Make Up to CST 5
A.8-03.01 Initial Response Actions 5
A.8-05.10 Portable Sprays 6
3
WORK ORDERS
Date or
Number Description or Title
Revision
00532058 IC-V-EF-31, Inspect, Clean and Test Smoke Detector 8
00532057 IC-RE-1, Inspect, Clean and Test Smoke Detector 8
00551198 OSP-FIR-1489; B.5.b Quarterly Equipment Inventory 04/25/2017
00553313 OPS-FIR, 1216-01 Fire Door Inspections- Daily 04/25/2017
00548794 OSP-P507 Engine Run Test, #12 Portable Diesel Water 06/07/2017
Pump
00548793 OSP-P507 Engine Run Test, #11 Portable Diesel Water 03/23/2017
Pump
00548397 Quarterly PM for Portable Diesel Generator 03/08/2017
00540051-01 1061 EMERG LIGHTING QTRLY OPER ABILITY TEST 09/27/2016
00549800-01 1061 EMERG LIGHTING QTRLY OPER ABILITY TEST 03/07/2017
00553313-01 1216-01 Fire Door Inspections - Daily 05/30/2017
0054946-01 PM 4024 (Inspect Fire Doors - Accessible Only) 02/13/2017
00533867-01 0275-02 Fire Barrier Wall/Damper/Flr Insp-SCAF 04/10/2017
00502605-01 0275-03 Fire Door Inspections 05/16/2016
00491058-01 0275-02 Fire Barrier Wall/Damper/Flr Insp-Scaf 04/04/2015
00463677-01 MECH-FIR, 0274 Fire Hose Hydro Test Interior Hose STA 11/14/2014
0034403 0275-01 Fire Barrier Penetration Vis Insp 05/19/2009
00414101 ENG-FIR, ENG 0275-01 Fire Barrier Penetration Seal Vis 05/14/2011
Insp
00441332-01 0275-01 Fire Barrier Penetration Seal Vis Insp 03/21/2013
00491059-01 0275-01 Fire Barrier Penetration Seal Vis Insp 04/11/2015
00470489-01 Inspect/Repair Fire Penetration RB-516 in A RHR Room 12/21/2012
00546861-01 P-507 - OSP-FIR-0609 Pump Flow Test 05/30/2017
00553371-01 P-507 - OSP-FIR-0609 Engine Run Test 05/30/2017
00551198-01 1490 - B.5.B Equipment Quarterly Inventory 04/19/2017
OTHER DOCUMENTS
Date or
Number Description or Title
Revision
FPEE-16-002 Alternate Compensatory Measure for Non-Functional Fire 2
Doors 3, 9, 31, and 414
Strategy A.3-07-A 125V Division I Battery Room 7
Strategy A.3-07-C 125V Division II Battery Room 8
QF-1128 Time Critical Operator Actions 1
Strategy A.3-01-A Fire Zone 1-A #12 RHR & Core Spray Pump Room 8
Strategy A.3-01-B Fire Zone 1-B #11 RHR & Core Spray Pump Room 9
Strategy A.3-02-B Fire Zone 2-B East HCU Area 13
Strategy A.3-09 Fire Zone Control Room 10
Strategy A.3-11 Fire Zone 11 Admin Bldg HVAC Room 12
Strategy A.3-30 Fire Zone 30 Turbine Deck 15
NFPA-80 National Fire Protection Association 2007 Edition
LCN 4010 Series LCN Closers 03/03/2007
4
OTHER DOCUMENTS
Date or
Number Description or Title
Revision
MPS-0924 Installation of Electrical and Mechanical Penetration Seals 9
03-5917 Fire Qualification Test on Retrofit Penetration Seals 06/30/1980
LCN 4010 LCN 4010 Series Closer Vendor Manual April 2006
E-81N301 Oversize Door Frame Certification 11/23/1983
5