IR 05000263/2023002
| ML23219A155 | |
| Person / Time | |
|---|---|
| Site: | Monticello |
| Issue date: | 08/07/2023 |
| From: | Hironori Peterson NRC/RGN-III/DORS/RPB3 |
| To: | Hafen S Northern States Power Company, Minnesota |
| References | |
| IR 2023002 | |
| Download: ML23219A155 (1) | |
Text
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT-INTEGRATED INSPECTION REPORT 05000263/2023002
Dear Shawn Hafen:
On June 30, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Monticello Nuclear Generating Plant. On July 20, 2023, the NRC inspectors discussed the results of this inspection with G. Brown, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Hironori Peterson, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket No. 05000263 License No. DPR22
Enclosure:
As stated
Inspection Report
Docket Number:
05000263
License Number:
Report Number:
Enterprise Identifier:
I2023002-0056
Licensee:
Northern States Power Company, Minnesota
Facility:
Monticello Nuclear Generating Plant
Location:
Monticello, MN
Inspection Dates:
April 01, 2023 to June 30, 2023
Inspectors:
S. Bell, Health Physicist
N. Bolling, Project Engineer
J. Cassidy, Senior Health Physicist
E. Fernandez, Senior Reactor Inspector
T. McGowan, Senior Resident Inspector
V. Myers, Senior Health Physicist
J. Nance, Operations Engineer
C. Norton, Senior Resident Inspector
J. Reed, Health Physicist
Approved By:
Hironori Peterson, Chief
Reactor Projects Branch 3
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Monticello Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
Type Issue Number Title Report Section Status LER 05000263/2022001-00 LER 2022001-00 for Monticello Nuclear Generating Plant, Loss of Control Room Envelope Operability 71153 Closed
PLANT STATUS
The unit began the inspection period at 80 percent rated thermal power in coast down. The licensee took the unit offline on April 15, 2023. The licensee commenced a reactor startup and brought the unit critical on May 13, 2023. The licensee increased reactor power and synchronized to the grid on May 14, 2023, to end refuel outage 31. The licensee continued to increase reactor power and reached rated thermal power on May 16, 2023. On May 26, 2023, the licensee lowered reactor power to 80 percent to perform a control rod pattern adjustment and returned to rated thermal power the same day. The unit remained at rated thermal power until the end of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of summer (extreme heat and potential drought) for the following systems:
cooling tower structures 11 and 12, division 1 and division 2 125-volt dc battery rooms, and intake structure traveling screens that are required to be protected from the seasonal extreme weather conditions on June 21, 2023
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (4 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Protected reactor vent path, RV271D (SRV D) on April 17, 2023
- (2) Protected make up source, condensate service pumps 11 and 12 on April 17, 2023
- (3) Uninterruptible power supply, Y81 after testing on May 9, 2023
- (4) Meteorological tower walkdown on May 16, 2022
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Fire zone (FZ) 2B, east hydraulic control unit area on April 15, 2023
- (2) FZ 19C, feedwater pipe chase on April 17, 2023
- (3) FZ 16, corridor, turbine building east and west, elevations 911' and 931' on April 18, 2023
- (4) FZ 17, turbine building north cable corridor 941' on April 19, 2023
- (5) FZ 9, main control room on April 27, 2023
Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the onsite fire brigade training and performance during an announced fire drill on June 17, 2023
71111.08G - Inservice Inspection Activities (BWR)
BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding
Activities (IP Section 03.01)
The inspectors verified that the following nondestructive examination and welding activities were performed appropriately:
(1)
1. Ultrasonic examination (UT) residual heat removal (RHR) pipe-to penetration
weld component ID: W1
2. Ultrasonic examination (UT) RHR pipe-to penetration weld component ID: W2
3. Magnetic particle examination (MT) carbon steel variable spring /slide
component ID: H1WA
4. Visual examination (VT3) RHR seismic restraint component ID: SR79
5. Visual examination (VT3) RHR box restraint component ID: H4
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the control room during shutdown operations including taking the generator offline, and a transition from Mode 1 to Mode 3 using a planned scram of the mode switch for refuel outage 31 on April 14, 2023
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated operations crew 1 just in time training for reactor startup, turbine overspeed test, and reactor vessel pressure test in support of refuel outage (RFO) 31 on April 12, 2023
71111.12 - Maintenance Effectiveness
Aging Management (IP Section 03.03) (1 Sample)
The inspectors evaluated the effectiveness of the aging management program for the following SSCs that did not meet their inspection or test acceptance criteria:
- (1) Physical inspection of pipe penetration RWN53-HC, condensate drip tank to waste collector tank, extent of condition for November 22, 2022, failure of control rod drive suction pipe failure on April 26, 2023
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Observed and validated risk mitigating actions were used during reactor pressure vessel head detention and lift on April 17, 2023
- (2) Contingency to refill of emergency diesel generator day tanks on April 18, 2023
- (3) Reviewed the planning for, and observed, the risk mitigation strategies implemented for deenergizing and isolating Bus 16, division 2 - 4.16 KV safety-related Bus, on April 17 and 18, 2023
- (4) Observed and evaluated risk management actions associated with recirculation pump 11 speed control issues on May 15 and 16, 2023
- (5) Observed and evaluated risk management actions associated with Y81 UPS inverter unexpected static switch transfer (partial group II isolation) on May 04, 2023
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
(1)
===501000072718, Failure to complete asfound diagnostic on MO2397 reactor water cleanup isolation valve within American Society of Mechanical Engineers (ASME)required interval (2)501000073646 Jet pump flow discrepancy (3)501000072235, RHR 11 pump failed to start manually (4)501000072261, Fuse 10A-F19A (panel C32) found open
71111.20 - Refueling and Other Outage Activities
Refueling/Other Outage Sample (IP Section 03.01)===
- (1) The inspectors evaluated refueling outage 31 activities from April 14,2023 to May 14, 2023
71111.24 - Testing and Maintenance of Equipment Important to Risk
The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:
Post-Maintenance Testing (PMT) (IP Section 03.01) (10 Samples)
(1)1624 Relay, PMT/ return to service, time delay tripping relay, work orders
===7000856320010 and 7000856320030
- (2) Bus 16 relay testing following relay preventative maintenance on April 24, 2023 (3)011302, automatic depression system bypass timer test following maintenance on May 2, 2023 (4)138605, 'B' loop RHR service water system external pipe inspection following maintenance window on May 2, 2023 (5)138601, 'B' loop emergency diesel generator emergency service water external pipe inspection following maintenance on May 2, 2023 (6)0456, Testing following drywell and suppression chamber valve seal replacement on May 2, 2023 (7)025504-IA2, 'B' loop RHR system cold shutdown valve operability tests following maintenance window on May 2, 2023 (8)025504-1A12, 'B' loop RHR system quarterly pump and valve tests following maintenance window on May 2, 2023 (9)0127, Drywell-torus vacuum breaker functional test following maintenance on May 5, 2023
- (10) HPCI torus suction check valve operability test following inspection and maintenance on May 5, 2023 Surveillance Testing (IP Section 03.01)===
- (1) Source range monitor and Intermediate range monitor functional and logic system functional test, on April 14, 2023
- (2) Core spray, shutdown pump and valve operability testing during cavity flood up on April 18, 2023
- (3) Alternate shut down system functional test for diesel generator 12, on April 25, 2023
- (4) Low pressure emergency core cooling system (ECCS) automatic initiation and loss of auxiliary power test, division 2 on May 04, 2023
- (5) Control rod drive scram insertion time test on May 08, 2023
- (6) HPCI pump flow and valve tests with reactor pressure less than or equal to 165 psig on May 14, 2023
Inservice Testing (IST) (IP Section 03.01) (2 Samples)
- (1) Reactor coolant pressure boundary leakage test on May 8, 2023
- (2) Control rod drive scram insertion time test on May 8, 2023
Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)
- (1) P506 (FLEX) portable diesel fire pump testing, on June 21,
RADIATION SAFETY
71124.01 - Radiological Hazard Assessment and Exposure Controls
Radiological Hazard Assessment (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.
Instructions to Workers (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.
Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)
The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:
- (1) Workers exiting the radiologically controlled area (RCA) at Unit 1 during a refueling outage
- (2) Radioactive material inventory of the spent fuel pool, 1027' reactor building
Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)
The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:
(1)
1R31 Turbine building stop valves/control valves/bypass valves; radiological work
permits (RWP) 235211 and associated radiation protection job plan (2)
1R31 Refuel floor activities; RWP 235700 and associated radiation protection job plan (3)
1R31 Control rod drive change out; RWP 235509 and associated radiation protection job plan (4)
1R31 Drywell checklist activities and associated radiation protection job plan
High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (4 Samples)
The inspectors evaluated licensee controls of the following high radiation areas and very high radiation areas:
- (1) Reactor building 935' drywell access area
- (2) Reactor building 935' 'A' RHR
- (3) Reactor building 1027' reactor head stand area
- (4) Radioactive waste building 935' barrel storage aisle Radiation Worker Performance and Radiation Protection Technician Proficiency (IP
Section 03.06) (1 Sample)
- (1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.
71124.03 - InPlant Airborne Radioactivity Control and Mitigation
Temporary Ventilation Systems (IP Section 03.02) (1 Sample)
The inspectors evaluated the configuration of the following temporary ventilation systems:
- (1) Reactor building 1027' reactor head stand
71124.05 - Radiation Monitoring Instrumentation
Walkdowns and Observations (IP Section 03.01) (8 Samples)
The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:
- (1) Portable ion chambers in the radiation protection instrument calibration facility
- (2) Portable neutron radiation instruments ready for use
- (3) Portable friskers in the radiation protection instrument calibration facility
- (4) Tool and equipment monitor at the primary RCA exit
- (5) Whole-body contamination monitors at the primary RCA exit
- (6) Portal monitors at the guardhouse exit
- (7) High range dose rate meters in the radiation protection instrument calibration facility
- (8) Wide range gaseous monitor in the reactor building
Calibration and Testing Program (IP Section 03.02) (13 Samples)
The inspectors evaluated the calibration and testing of the following radiation detection instruments:
- (1) AFC-90L air sample calibrator 13116
- (2) AMP100 A10003
- (3) ARGOS 5AB Zeus AZ14
- (4) ISolo 532278
- (5) DMC 2000 EDMG30047
- (6) FastScan 1 whole-body counter
- (7) HPGe (A) detector 1
- (8) Model 93 - 9316 dose rate meter
- (9) AMS4 8 serial number: 02657
- (10) H809 air sampler R2
- (11) Gem-5 portal monitor PM1
- (12) RO7 dose rate meter RO79
- (13) SAM11 SAM4 Effluent Monitoring Calibration and Testing Program Sample (IP Section 03.03) (2 Samples)
The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:
- (1) Wide range gas monitor for the site stack release
- (2) Containment area high range radiation monitor in the drywell
OTHER ACTIVITIES-BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===
- (1) April 01, 2022 through March 31, 2023 BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)
- (1) October 1, 2022 through April 30, 2023
BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)
- (1) April 01, 2022 through March 31, 2023
OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)
- (1) October 1, 2022 through April 30, 2023 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
- (1) October 1, 2022 through April 30, 2023
71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
- (1) Reviewed and evaluated licensee corrective actions for 501000052353, Startup delay-deviation in predictors experienced during RFO 30
- (2) The inspectors reviewed the licensees corrective actions related to the onsite monitoring well that indicated tritium activity above the Offsite Dose Calculation Manual and Nuclear Energy Institute Groundwater Protection Initiative reporting levels. Specifically, the inspectors -
reviewed the methodology used to quantify the amount of radioactive material leaked to groundwater reviewed the methodology used to characterize the plume of contaminated groundwater onsite, including observation of collection and analysis of contaminated groundwater.
assessed whether contaminated groundwater migrated offsite.
walked down the recovery system, including the temporary above ground storage locations and processing using temporary hoses to move the contaminated groundwater around the site.
reviewed incidental spills that occurred as a result of handling more than one million gallons of contaminated groundwater.
discussed future plans for longer term treatment of the collected contaminated groundwater.
reviewed the criteria, methodology, and requirements for reporting leaks and spills that contain licensed radioactive materials.
- (3) The inspectors reviewed the safety culture work environment at Monticello to ensure that an environment exists where individuals can raise safety concerns without fear of retaliation.
71153 - Follow-Up of Events and Notices of Enforcement Discretion Event Follow-up (IP Section 03.01)
- (1) The inspectors evaluated dropped blade guide over reactor core and recovery on April 23, 2023.
Event Report (IP Section 03.02) (1 Sample)
The inspectors evaluated the following licensee event reports (LERs):
- (1) LER 2022001-00, Monticello Nuclear Generating Plant, Loss of Control Room Envelope Operability (ADAMS Accession No. ML22189A111). On May 13, 2022, the licensee identified an unplanned loss of control room operability, TS limiting condition of operation (LCO) 3.7.4.B, due to excessive through wall steam leakage from an air ejector that exceeded alternate source term limits. The inspectors determined that the licensee took timely corrective actions to mitigate the steam leakage and exit LCO.
The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER therefore no performance deficiency was identified. The inspectors did not identify a violation of NRC requirements. This LER is closed.
Reporting (IP Section 03.05) (1 Sample)
- (1) The inspectors reviewed and evaluated the following licensee event notification (EN)made by the station to the NRC Headquarters Operations Center:
Review and assessment of the licensee's non-emergency report made under 10 CFR 50.73(a)(1) and 10 CFR 50.73 (a)(2)(iv)(A) for an invalid actuations of Division 2 primary containment isolation logic that occurred while in a refueling outage on April 28, 2023, and May 4, 2023, as documented in NRC EN
INSPECTION RESULTS
Assessment 71152A During the refuel outage April 15 through May 14, 2023, the inspectors conducted a baseline problem identification and resolution sample to evaluate safety-conscious work environment (SCWE) in accordance with Inspection Procedure (IP) 71152, Problem Identification and Resolution, Section 3.04 using guidance provided in IP 93100, Safety-Conscious Work Environment Issue of Concern Follow-up, as applicable to determine whether a chilled work environment existed at the site. Inspection activities included, daily corrective action document reviews, individual worker interviews, work activity observations, an interview with the Employee Concerns Program representative, and review of independent safety culture assessment. The inspectors assessed that individuals exhibited a readiness to raise safety concerns and admit to errors without of a fear of retaliation. No SCWE issues were identified.
Observation: Onsite Monitoring Well with Tritium Activity Above Reporting Levels 71152A On November 22, 2022, the licensee reported an onsite monitoring well that indicated tritium activity above the Offsite Dose Calculation Manual and Nuclear Energy Institute Groundwater Protection Initiative reporting levels. Since that date, the licensee identified the location of the underground leak, repaired the leak, and implemented a recovery system to remove contaminated groundwater from the beneath the plant.
The inspectors determined -
the methodology used to quantify the amount of radioactive material leaked to groundwater was adequate.
the methodology used to characterize the plume of contamination onsite, including observation of collection and analysis of contaminated groundwater was adequate.
contaminated groundwater did not migrate offsite.
the recovery system, including the temporary above ground storage locations and processing using temporary hoses to move the contaminated groundwater around the site, was adequate.
incidental spills that occurred as a result of handling more than one million gallons of contaminated groundwater did not require new strategies to mitigate groundwater contamination.
future plans for longer term treatment of the collected contaminated groundwater would likely be able to meet NRC requirements.
the criteria, methodology, and requirements for reporting leaks and spills that contain licensed radioactive materials were consistent with the industry initiative and were performed in accordance with NRC requirements.
The inspectors concluded the licensee developed a holistic plan with significant input from contracted vendor with expertise in groundwater management and cleanup. The inspectors noted a high level of support (time and resources) from all levels of the organization to recover and store the contaminated groundwater onsite and prevent any uncontrolled release from the site.
Observation: Assessment of Corrective Actions for Deviation in Core Thermal Predictors during Startup form RFO 30 71152A In 2021, during the startup from refuel outage (RFO) 30, the licensee loaded the control rod sequence from RFO 29 into the rod worth minimizer. This resulted in two core thermal predictors exceeding thermal limits. The licensee was forced to hold power below 100 megawatts with the turbine online while a correction to the sequence was developed and implemented. Holding at this power threatened turbine integrity and placed the unit at risk for transient initiation. The licensee documented this issue in corrective action program item 501000052353. Corrective actions included a requirement to develop sequences for the new core designs when starting up after an RFO. The inspectors reviewed the startup sequence after RFO 31 to verify that the sequence was prepared and verified for the new core design.
The inspectors observed start up activities in the control room. No issues were identified.
Minor Performance Deficiency 71153 Minor Performance Deficiency: On April 23, 2023, during Monticellos refuel outage 31 core component movement activities, cell 1407 (containing a control blade, fuel support piece and two half blade guides (HBG)), was lifted using a Westinghouse multi-lift tool. During this activity, the two HBGs dropped from the lift tool. This resulted in one HBG coming to rest on the drywell radiation shield and the other on the shroud steam dam and a Westinghouse inspection tool. The blade guides did not contact nuclear fuel. The Westinghouse multi-lift tool is designed to lift a fuel support piece containing a control blade, fuel support piece, and a full blade guide. The performance deficiency was the licensee's use of the Westinghouse multi-lift tool to lift the two HBGs, for which it was not designed.
Screening: The inspectors determined the performance deficiency was minor. HBGs do not have sufficient mass to damage fuel when dropped in water from any height at any location over the core. The performance deficiency could not reasonably be viewed as a precursor to a significant event; if left uncorrected, it would not have the potential to lead to a more significant event; and it did not adversely affect a cornerstone objective.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On July 20, 2023, the inspectors presented the integrated inspection results to G. Brown, Plant Manager, and other members of the licensee staff.
On April 20, 2023, the inspectors presented the radiation protection baseline inspection results to K. Nyberg, Director Site Performance & Operations Support, and other members of the licensee staff.
On April 28, 2023, the inspectors presented the Inservice Inspection Activities for Monticello M1R31 Outage inspection results to J. Ohotto, General Manager Fleet Operations, and other members of the licensee staff.
On May 25, 2023, the inspectors presented the groundwater protection inspection results to C. Domingos, Site Vice President, and other members of the licensee staff.
On June 8, 2023, the inspectors presented the Radiation Protection inspection results to S. Hafen, Plant Manager, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Procedures
1150
Summer Readiness
Corrective Action
Documents
501000071357
Old MEET Tower Booms Still Up
03/14/2023
Drawings
NH362411
Reactor Pressure Relief
29201
Operability Testing of the Uninterruptible Power Supply
1308
MET Tower Inspection Procedure
B.08.0905
Condensate Storage System
Ops Man B
09.1305
20 Volt Uninterruptible AC Power Supply Startup
Procedures
Ops Man
B.05.1604
Meteorological Monitoring
STRATEGY
A.302-B
East HCU Area
STRATEGY
A.309
Control Room
STRATEGY
A.316
Corridor, Turbine Building East and West (Elevations 911'
and 931')
STRATEGY
A.317
Turbine Building North Cable Corridor 941'
Fire Plans
STRATEGY
A.319-C
Feedwater Pipe Chase
Miscellaneous
A.341
Fire Brigade Drill Guide, Biocide Pump Fire (Drill Guide
"41.01")
06/17/2023
2176
Fire Drill Procedure
Procedures
STRATEGY
A341
Sodium Hypochlorite Building (Bleach House)
501000071050
SWMIC Pitting Detected Line SW1018-GF
03/01/2023
Corrective Action
Documents
501000071164
CV1728, Evidence of Erosion and Pitting
03/07/2023
Corrective Action
Documents
Resulting from
501000072311
Torus External General Visual Examination Where Various
Locations of Coating Degradation was Noted Such that the
Base Metal was Exposed
04/13/2023
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
501000072468
Thread Damage Observed while Performing IWE Program
Required VT1 Exams on the Bolted Connections for the
Drywell Equipment Hatch
04/19/2023
Inspection
501000072621
Examinations Performed per ASME XI Inservice Inspection
(ISI) Program. Visual Exam (VT3) of SR79 (Seismic
Restraint for RHRSW piping) Found Relevant Crack Like
Indications in the Weld Area
04/18/2023
201UT022
UT Report of Past Relevant Indication on T.H. Meridional
Weld Component ID: W7
05/03/2021
21UT050
UT Report of Past Relevant Indication on Pipe-toPipe Weld
Component ID: W2
05/05/2021
MN23MT-002
Magnetic Particle Examination (MT) of CS Variable Spring
/Slide Component ID: H1WA
04/25/2023
MN23UT-001
Ultrasonic Examination (UT) of RHR Pipe-to Penetration
weld Component ID: W2
04/20/2023
MN23VT-006
Visual Examination (VT3) of RHR Seismic Restraint
Component ID: SR79
04/21/2023
MNUT002
Ultrasonic Examination (UT) of RHR Pipe-to Penetration
weld Component ID: W1
4/20/2023
NDE Reports
MNVT007
Visual Examination (VT3) of RHR Box Restraint
Component ID: H4
04/20/2023
FPPE-NDE300
Dry Magnetic Particle Examination - Yoke/Coil
FPPE-NDE4001
Ultrasonic Examination of Ferritic Pipe Welds - Supplement
FPPE-NDE420
Ultrasonic Thickness Examination
FPPE-NDE530
Visual Examination, VT3
PDI-UT1
PDI Generic Procedure for the Ultrasonic Examination of
Ferritic Pipe Welds
G
Procedures
PEI-01.02.05
Monticello Nuclear Generating Plant 5th Interval ISI
Detailed Schedule
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
LP MTLOR-JIT-
20S
SEG MTLOR-
JIT-011S
Reactor Vessel Pressure Test Simulator Exercise Guide
Miscellaneous
SEG MTLOR-
JIT-2023002S
Startup JIT
2167
Plant Startup
108
Procedures
204
Plant Shutdown
Work Orders
70012174330
RWN53-HC Perform Inspection
04/22/2023
501000072461
2401 Breaker Cubicle FME
04/18/2023
501000072462
Racking Shutter Stuck Mid-Position
04/18/2023
501000073154
Y81 Failure Caused Plant Transient
05/04/2023
Corrective Action
Documents
501000073594
Recirc Speed Adjust Not Raising
05/15/2023
2000005747
Operational Decision-Making Evaluation Checklist/11
05/15/2023
2000005747
Operational Decision-Making Evaluation Checklist/Y81,
UPS Inverter
05/11/2023
Miscellaneous
QF2007
FPWM1RM-01
Planning and Approval of High Risk or Scheduled Risk
Work
485814-OCD
4KV Bus 14 Maintenance
485816-OCD
4KV Bus 16 Maintenance
210
Master RPV Disassembly Procedure
20
Remove RPV Head
Ops Man
B.09.0605
Operations Manual Section: 4.16 kV Station Auxiliary
System Operation
Tagout 14KV
485814-OCD
Bus Isolated Per 485814-OCD (This Tag does NOT
Ground Bus 14, and does NOT Isolate Power to Breaker
Secondary Contacts)
04/18/2023
Procedures
Tagout 14KV
485816-OCD
Bus Isolated Per 485816-OCD (This Tag Section does
NOT Ground Bus 16, and does NOT Isolate Power to
Breaker Secondary Contacts)
04/19/2023
Work Orders
7001109170055
Contingency Refuel Day Tanks
Corrective Action
501000072235
RHR Pump Failed to Start Manually
04/12/2023
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
501000072261
Fuse 10A-F 19 (Panel C32) Found Open
04/12/2023
501000072718
Mech PM Done Prior to AsFound Diagnostic
04/24/2023
Documents
501000073646
Jet Pump Flow Discrepancy
05/17/2023
NX790546-3
S/D RHR System
Drawings
NX79050464
RHR S/D System
501000073372
CRD 3023 Position Indication Faulty
05/09/2023
501000073404
CRD 3023 Bad Reed Switches
05/09/2023
Corrective Action
Documents
501000073405
SCRAM Time App Errors During 0081
05/09/2023
Drawings
NH36248
(M122)
P&ID Core Spray System
Miscellaneous
Relay Field Test -
Test Values
Record CT Ratio
200/5; Switch
BKR 408
Monticello, 4.16 kV - Card HMN1 2615A; Switch BKR 408;
CT Ratio 1200/5; Breaker Ser. No. 1416 BT
04/20/2023
0081
Control Rod Drive SCRAM Insertion Time Test
0108
HPCI Pump Flow and Valve Tests with Reactor Pressure
Less Than or Equal to 165 PSIG
011302
ADS System Bypass Timer Test
27
Drywell-Torus Vacuum Breaker Inspection, Functional Tests
and Calibration of Position Indication Alarm Systems
25504-IA12
RHR Quarterly Pump and Valve Tests
105
25504-IA2
RHR System Cold Shutdown Valve Operability Tests
25506-IA4
HPCI 31 Torus Suction Check Valve Operability Test
25520-II C1
Reactor Coolant Pressure Boundary Leakage Test
041901
ASDS Cycle Functional Test for Diesel Generator 12
Switches
0456
Drywell and Suppression Chamber Valve Seal
Replacement
138601
EDG-ESW External Pipe Inspection Loop A and B
138605
RHRSW External Pipe Inspection Loop A and B
Procedures
OSP-ECC-
056602
Low Pressure ECCS Automatic Initiation and Loss of
Auxiliary Power Test - Division 2 Outage
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
P506 Portable Diesel Pump Testing
SRM and IRM Functional and Logic System Functional Test
25503-IA2A
Core Spray - Shutdown Pump and Valve Operability Test
4850408-PM
2408, Bus 14/16 Tie Breaker Relay Calibration,
Maintenance, and Test Tripping
04/20/2023
7000854600010
Bus 16 Outage Relay Maintenance
Work Orders
7000856320030
24 RLY, PMT (Post-Maintenance Test) / RTS (Return to
Service)
04/21/2023
ALARA Plans
RWP 235506, 1R31 Drywell Checklist Activities, Work in
Progress Review and Associated Station ALARA
Committee Notes
04/19/2023
501000056045
Percent of Current PCE's from Uncontaminated Areas
09/15/2021
501000060298
Dose Rate Increase Following RWCU 'B' Backwash
2/10/2022
501000060815
Potential Trend in Airborne Radiation Levels
2/24/2022
501000060850
Radiological Condition Not as Expected
2/24/2022
501000063752
Irradiated Material in the Spent Fuel Pool
06/13/2022
501000064920
Equipment Reliability is Negatively Affecting Station
Collective Radiation Exposure
07/21/2022
501000066983
Contamination Found in RCA Clean Area
10/06/2022
501000068896
1001' RWCU Vault Air Sample >1.0 DAC
2/01/2022
Corrective Action
Documents
501000069147
Gap in Radiation Protection Survey Documentation
2/12/2022
Corrective Action
Documents
Resulting from
Inspection
501000072454
Ram Tags Not Per FPRP-NISP-04
04/18/2023
Radioactive Material Unconditional Release Log
04/15/2023
General Area Alpha Characterization
Undated
21 Annual Dose Report
Undated
21 1R30 Outage ALARA Report
Undated
Miscellaneous
High Radiation Area/Locked High Radiation Area Posting
and Boundary Checklist
04/16/2023
AWI-.04.05.13
Control of Items in the Spent Fuel Pool
Procedures
FPRP-NISP-02
Radiation and Contamination Surveys
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
FPRP-NISP-05
Access Controls for High Radiation Areas
FPRP-SAC-01
Station ALARA Committees
FPRP-SEN-02
Radiological Work Planning and Controls
R.06.02
Unconditional Release of Equipment or Material
R.06.09
Storage and Inventory of Radioactive Material Outside the
Power Block
1R31 Refueling Outage Posting Change Matrix
04/15/2023
1R30 Refueling Outage Initial Shutdown Surveys for the
Drywell
Various
1R31 Refueling Outage Shutdown Surveys for the Drywell
Various
Reactor Building 962' General Area Surveys (09/25/2021,
09/22/2022, 03/26/2022, and 04/01/2023)
Various
Radiation
Surveys
VSDS-
M2023041917
Turbine Control Valves
04/19/2023
235211
1R31 Turbine Building Stop Valves/Control Valves/Bypass
Valves RWP and Associated Radiation Protection Job Plan
235506
1R31 Drywell Checklist Activities RWP and Associated
Radiation Protection Job Plan
235509
1R31 Control Rod Drive Changeout RWP and associated
Radiation Protection Job Plan
Radiation Work
Permits (RWPs)
235700
1R31 Refuel Floor Activities RWP and associated Radiation
Protection Job Plan
606000001645
Radiological Hazard Assessment and Exposure Controls
2/10/2022
Self-Assessments
606000001645
InPlant Airborne Control and Mitigation
2/10/2022
Alpha Monitoring Program
Procedures
FP-RP-RPP-01
Respiratory Protection Program
Radiation
Surveys
Air Sample Analysis for Turbine Stop/Control Valve
Replacement
04/19/2023
2657
AMS-4 8
01/06/2022
13116
Air Sampler Calibrator AFC -90L
03/18/2021
310280 / R-2
H-809 Air Sampler
2/26/2023
2278
ISolo Calibration
2/06/2022
Calibration
Records
9316
Model 93 Dose Rate Meter
01/04/2022
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
A10003
AMP-100
01/28/2022
AZ-14
ARGOS 5AB Zeus
2/09/2023
EDMG30040
DMC-2000GN
2/16/2023
FastScan 1
Whole-Body Counter
10/21/2022
HPGE 'A'
Detector 1
High Purity Germanium Detector
05/03/2023
PM-1
Gem-5 Portal Monitor
03/29/2023
RO-79
RO-7 Dose Rate Meter
01/09/2023
SAM-4
SAM-11 Tool and Equipment Monitor
04/15/2023
501000062766
Smear Counter Efficiency Calculation Error
05/04/2022
501000063790
RP Instrument Failure
06/11/2022
Corrective Action
Documents
501000070730
HPGe Report Software Mislabeling Co-60
2/16/2023
501000074267
Beta Correction Factors Not Posted
06/07/2023
501000074272
Ni-63 Sealed Source Leak Tests
06/07/2023
Corrective Action
Documents
Resulting from
Inspection
501000074307
Frisker Source Checks Lowest Range Only
06/07/2023
5XLB Analysis of
Ni-63 Leak Test
Calculation
Technical White Paper
Technical Basis
Document 12002
Ni-63 Detection Capability of the Tennelec 5XLB
Technical Basis
Document 19002
Sensitivity Study of ARGOS 4/5, PM7, and GEM-5 Monitors
for Passive Whole-Body Counting
Technical Basis
Document 19003
Neutron DLR, SRD, and Rem Ball Characterization
Engineering
Evaluations
Technical Basis
Document 22001
Neutron Factor for Drywell Startup/Power Entries
0163
Stack Wide Range Gas Monitor Calibration
248
Reactor Building Vent Wide Range Gas Monitor Calibration
2802
Containment High Range Radiation Detectors Calibration
Procedure
Procedures
FP-RP-ICC-01
Instrument Control and Calibration/Function Check
Frequencies of RP Instruments
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
R.09.61
Sam-11/LAM Operation and Calibration
R.09.62
ARGOS Contamination Monitors: Function Check and
Calibration
R.09.72
Model 3030P Alpha-Beta Smear Counter Operation
QF0445
NRC and Data Collection and Submittal - SSFFs (April 2022
through March 2023)
Miscellaneous
QF0445
NRC Data Collection and Submittal - RCS Total Leakage
(April 2022 through March 2023)
71151
Procedures
FP-PA-PI-02
NRC and MOR Performance Indicator Reporting
0501000073805
FRAC Tank Notifications Missing the Mark
0501000073805
501000052353
Startup Delay-Deviation in Predictors
05/20/2021
501000073752
Pump in T-GW-13 Found Tripped
05/21/2023
501000073770
Pump in T-GW-16 Found Tripped
05/21/2023
501000073788
FRAC Tank Overflow Due to Gauge Issue
05/22/2023
501000073795
FRAC Tank Farm in ISFSI Parking
05/22/2023
501000073804
FRAC Tank Overflowed While Filling
05/22/2023
501000073826
[Four] 4 Hour Non-Emergency Event Notification
05/23/2023
501000073833
Groundwater Transfer - Incorrect Risk
05/23/2023
501000073852
State Report Recorded Incident Date
05/23/2023
501000073870
Elevation - GW Mitigation Efforts
05/23/2023
Corrective Action
Documents
501000073892
FRAC Tank #20 Level Gauge Removed
05/24/2023
501000073778
RAM Labels Not Filled Out on FRAC Tanks
05/22/2023
501000073787
FRAC Tack Overflowing from Weather
05/22/2023
501000073791
Berms at MW-12 and FRAC Tanks Folded
05/22/2023
501000073807
NRC Request for Observation - Construction of Retention
Ponds
05/22/2023
501000073809
Unable to Locate Level Gauge Calibration
05/23/2023
501000073823
No Definition of "Abnormal Discharge"
05/23/2023
501000073824
ODCM-02.01 2.4.1 Incorrect Reference
05/23/2023
501000073843
Procedure 0369 Incorrect ODCM Reference in A.1
05/23/2023
501000073859
Basis for Monitoring Well Purge Volume
05/24/2023
501000073860
Shift Manager Not Properly Notified
05/23/2023
Corrective Action
Documents
Resulting from
Inspection
501000073875
NRC Question on Lake Tank Level Monitor
05/24/2023
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
501000073876
NEI 07-07 Periodic Briefings
05/24/2023
501000073885
Minimum Dilution Flow
05/25/2023
501000073902
Monitoring Well Label Degraded
05/24/2023
501000073905
RP Notification for FRAC Tank Filling
05/25/2023
501000073911
Evaluate Installation of Anti-Siphon
05/25/2023
501000073917
Question on NEI 07-07
05/26/2023
Engineering
Evaluations
601000004237
Intermediate Groundwater Storage
Miscellaneous
ODCM-08.01
Reporting Requirements
0369
Temporary Outdoor Radioactive Liquid Tanks Level
Instrumentation Functional Test
2300
Reactivity Adjustment
5148
Monitoring Well Sample Log
FP-OP-REP-01
Event Reporting and Notification Process
Procedures
I.05.50
Sampling Groundwater Monitoring Wells
700116710
Water Removal
700117970
Groundwater Processing - Water Demand Demineralizer
Skid and Transfer
700117970
Groundwater Processing
Work Orders
700166710
Sample at Lake Tank
Corrective Action
Documents
501000072688
Two Half Blade Guides, HBGs, Released
04/23/2023
Work Orders
2000014849
Foreign Material Recovery Plan
04/23/2023