IR 05000263/2022012

From kanterella
Jump to navigation Jump to search
Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000263/2022012
ML22348A211
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 12/15/2022
From: Richard Skokowski
NRC/RGN-III/DORS/EB2
To: Domingos C
Northern States Power Company, Minnesota
References
IR 2022012
Download: ML22348A211 (11)


Text

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT - TRIENNIAL INSPECTION OF EVALUATION OF CHANGES, TESTS AND EXPERIMENTS BASELINE INSPECTION REPORT 05000263/2022012

Dear Christopher Domingos:

On November 22, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Monticello Nuclear Generating Plant and discussed the results of this inspection with Mr. S. Hafen, Plant Manager and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Richard A. Skokowski, Chief Engineering Branch 2 Division of Operating Reactor Safety Docket No. 05000263 License No. DPR-22

Enclosure:

As stated

Inspection Report

Docket Number:

05000263

License Number:

DPR-22

Report Number:

05000263/2022012

Enterprise Identifier:

I-2022-012-0020

Licensee:

Northern States Power Company, Minnesota

Facility:

Monticello Nuclear Generating Plant

Location:

Monticello, MN

Inspection Dates:

November 14, 2022 to November 22, 2022

Inspectors:

M. Abuhamdan, Reactor Inspector

M. Gangewere, Reactor Inspector

D. Melendez-Colon, Reactor Inspector

E. Sanchez Santiago, Senior Project Engineer

Approved By:

Richard A. Skokowski, Chief

Engineering Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial inspection of evaluation of changes, tests and experiments baseline inspection at Monticello Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.17T - Evaluations of Changes, Tests, and Experiments Sample Selection (IP Section 02.01)

The inspectors reviewed the following evaluations, screenings, and/or applicability determinations for 10 CFR 50.59 from March 2019 through November 2022.

(1) SCR-19-006, Temporarily Isolate B CRV Via RO-4258B
(2) SCR-19-0094, Removal of D311-04 and D312-05 Components from Scope of EQ Program
(3) SCR-20-0047, Evaluation of MOV and IST Program Valve Functions
(4) SCR-20-0050, 11 EDG Droop Modification
(5) SCR-19-0056, OffGas Recombiner Controller Upgrades
(6) SCR-19-0068, Increase Design Temp for RWN60-1 1/2-HJ
(7) SCR-19-0105,03-009 AOV Component Calculation AO-2541A,B and AO-2561A,B
(8) SCR-20-0054, Normally Closed Air Valves
(9) SCR-20-0071, 13 ESW Quarterly Pump and Valve Test New Rev. 64
(10) SCR-20-0104, Use of Uncertainties for HPCI/RCIC Pump Discharge Pressure in Surveillance Acceptance Criteria
(11) SCR-20-0101, Update ISP-RHR-0552-02 to Perform LSFT Testing
(12) SCR-20-0108, New Online LSFT Procedures to Support ECCS Testing Efficiency
(13) SCR-20-0130, (evaluation) Use of Atrium 10XM Lead Test Assemblies
(14) SCR-20-0140, Revise USAR-14 Table 14.7
(15) SCR-21-0012, (evaluation) Evaluation for Implementation of BWROG Rev 4 EOP
(16) SCR-21-0022, Correct ISP-RHR-0552-02 Setpoints
(17) SCR-21-0054, RHR MOV Functional Analysis
(18) SCR-21-0064, 0136 ILRT - Lower Torus Water Temperature Band
(19) SCR-21-0080, Cranes and Heavy Loads - System Operation
(20) SCR-21-0102, RHRSW Pump In-Service Testing
(21) SCR-22-0072, Change to Intercell Acceptance Criteria for D8 Battery
(22) SCR-22-0080, Primary Containment Isolation Valve Exercise
(23) SCR-22-0029, Revision of 2167 Plant Startup

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On November 22, 2022, the inspectors presented the triennial inspection of evaluation of changes, tests and experiments baseline inspection results to Mr. S. Hafen, Plant Manager and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

01-082

Basis for Monticello DBLFPB for 10CFR50.59 Criterion 7

10-082

RHR MOV Functional Analysis

2C

10-117

HPCI MOV Functional Analysis

0A

10-118

RCIC MOV Functional Analysis

0A

11-325

Functional Analysis for Non GL 89-10 Program MOVs13-055

Core Spray and LPCI Flow Delivered to Reactor Vessel for

Safety Analysis

Rev.2

16-006

Hard Pipe Vent D8 Battery HCVS 125VDC Battery

Calculation

Rev.1

16-014

Monticello LOCA Break Spectrum for EPU/EFW with

ATRIUM 10XM Fuel and Revised Modeling Parameters

Rev.1

Calculations18-002

HPCI/RCIC Discharge Pressures for Tech Spec Surveillance

Testing

01001494

Review of Assumptions in Accidents and License Bases

Events for Control of Plant Initial Conditions & Operator

Actions

03/13/2001

01476976

Action Request-Question on the 12 EDG Voltage Regulator

Wiring

06/12/2015

01496761

Potential Non-Conservative Tech Spec for EDG Voltage

2/10/2015

500001496761

Potential Non-Conservative Techl Spec for EDG Voltage

10/14/2015

501000039632

94-142 Weak Link Error

04/13/2020

501000044839

TMOD Extension Form Not Completed for EC

09/30/2022

501000045266

94-142 Additional Weak Link Errors

10/08/2020

501000047373

CFR 50.59 Screening Required

2/25/2020

501000048821

Unable to Adjust Switch to New Setpoint

2/18/2021

501000052371

Prolonged Operation Below 100 MWE

06/25/2021

501000055651

CV-1729 Controller Issue

09/13/2021

501000055698

CV-1729 ECR Testing Not Performed

09/03/2021

501000057242

EC Approved w/o Qual'd 50.50 Review

10/14/2021

501000057287

EOC-EC Approved w/o Qual'd 50.59 Review

10/16/2021

71111.17T

Corrective Action

Documents

501000057444

TCR Roll-Up CAP 10.19

10/19/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

501000059567

CFR 50.59 Screening Required

01/08/2022

501000059582

CFR 50.59 Screening Required

01/07/2022

501000059636

NRC Scaffold Question

01/11/2022

501000060154

1047-01 Tags Hanging >70 Days

01/29/2022

501000060155

FZ-3795 Temporary Configuration > 70 Days

01/29/2022

501000060510

CFR 50.59 Screening Required

2/11/2022

501000062038

CFR 50.59 Screening Required

04/08/2022

501000062298

CFR 50.59 Screening Required

04/15/2022

501000062487

CFR 50.59 Screening Required

04/22/2022

501000062628

Sub-Standard 50.59 Screenings

04/28/2022

501000063094

CFR 50.59 Scm for Tags Hang > 70 Days

05/13/2022

501000063269

Tags Hanging Greater than 70 Days 50.59

05/20/2022

601000002203

Close/Isolate/Abandon Drywell Air Line

03/12/2020

2000014958

B.01.04-05 R55 Complete

2/27/2020

2000015997

ISP-RHR-0552-02 Rev 5 Complete

05/01/2020

2000019462

C.5-2007 rev 23 EOP SAMG Update

01/29/2021

2000019785

C.5-GM-02.01 Rev 24 EOP/SAMG Update

2/22/2021

2000020067

C.5-2001 Rev 1 EOP SAMG Updates

03/11/2021

501000068477

225059-SCR-21-22 Typo

11/14/2022

501000068564

225059: Obs. Re: Clearance Orders

11/17/2022

501000068605

225059: Generic Screening Concern

11/17/2022

Corrective Action

Documents

Resulting from

Inspection

5011000068595

225059: Obs. Re: Scaffolds

11/16/2022

NF-93216-1

Instrument Air Line Isometric

NH-36049-12

P&ID Instrument Air Reactor Building and Drywell

Drawings

NH-36665

P&ID Service Water System & Make-up Intake Structure

104

0000028104

EC 26083 ECN - Battery Connection Resistance

Rev.0

601000000149

601000000149 - 11 EDG Voltage Regulator Droop

Modification

Rev.0

601000000429

OffGas Recombiner Controller Upgrades

Rev.0

601000000661

Replace DC Overloads in EQ Buckets

Rev.0

601000001143

Isolation of FSW D2 via RO-4258B

601000001564

Increase Design Temp for RWN60-1 1/2-HJ

Rev.0

Engineering

Changes

601000002221

Evaluate MOV Functions

2/04/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

60100001549

Revise Calculation 08-055 - RHR Aux Air Compressor

Rev.0

Engineering

Evaluations

600000845060

Evaluate the Impact of the EPG/SAG Revision 4 Changes on

the ATWS Event

19-0068

Increase Design Temp for RWN60-1 1/2-HJ

Rev.0

19-056

OffGas Recombiner Controller Upgrades

Rev.0

20-0101

Update ISP-RHR-0552-02 to Perform LSFT Testing

Rev.0

20-0108

New Online LSFT Procedures to Support ECCS Testing

Efficiency

Rev.0

AWI-09.04.01

Technical Position Number TP 13

601000001552

Drywell Equipment Drain Sump

11/02/2020

601000002969

RHR MOV Functional Analysis

05/01/2021

2000021383

2167 Revision 104 Complete

08/09/2022

2000022857

255-05-III-4A Rev 35 One Time Use TCR

09/29/2021

2000022859

255-05-III-2A Rev 35 Once Time Use TCR

09/29/2021

ANSI 831.1 -

1977Property "ANSI code" (as page type) with input value "ANSI 831.1 -</br></br>1977" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process. EDITION

Power Piping

05/01/1977

B.02.03-01

Reactor Core Isolation Cooling

B.03.02-05

HPCI

IST-BASIS

Pump and Valve In-Service Testing Program Basis

SCR-04-0932

Procedure, Drawing, VTM & Database Changes that are

Editorial as Defined in Part I

Rev. 6

(02/11/2020)

SCR-19-0006

Temporarily Isolate B CRV Via RO-4258B

SCR-19-0094

Removal of D311-04 and D312-05 Components from Scope

of EQ Program

Rev.0

SCR-19-0105

03-009 AOV Component Calculation AO-2541A,B &

AO-2561A,B

SCR-20-0047

Evaluation of MOV and IST Program Valve Functions

SCR-20-0050

EDG Droop Modification

Rev.0

SCR-20-0054

Normally Closed Air Valves

SCR-20-0071

ESW Quarterly Pump and Valve Test New Rev. 64

SCR-20-0104

Use of Uncertainties for HPCI/RCIC Pump Discharge

Pressure in Surveillance Acceptance Criteria

Miscellaneous

SCR-20-0130

Use of ATRIUM 10XM Lead Test Assemblies

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SCR-20-0138

Scaffolding

SCR-20-0140

Revise USAR-14 Table 14.7

Rev.0

SCR-21-0012

Evaluation for Implementation of BWROG Rev 4 EOP

SCR-21-0022

Correct ISP-RHR-0552-02 Setpoints

SCR-21-0054

RHR MOV Functional Analysis

SCR-21-0064

0136 ILRT - Lower Torus Water Temperature Band

SCR-21-0080

Cranes and Heavy Loads - System Operation

Rev.0

SCR-21-0102

RHRSW Pump In-Service Testing

SCR-22-0029

Revision of 2167, Plant Startup

SCR-22-0072

Change to Intercell Acceptance Criteria for DS Battery

Rev.0

SCR-22-0080

PCR 602000026536 Primary Containment Isolation Valve

Exercise

Operability

Evaluations

01496761-01

Potential Non-Conservative Tech Spec for EDG Voltage

10/23/2015

0108

HPCI Pump Flow and Valve Tests with Reactor Pressure

Less than or Equal to 165 psig

0114

RCIC Pump Flow and Valve Tests with Reactor Pressure

Less than or Equal to 165 psig

0136

Integrated Primary Containment Leak Rate Test

255-05-III-2A

Comprehensive 12 RHRSW Pump and Valve Tests

255-05-III-4A

Comprehensive 14 RHRSW Pump and Valve Tests

255-06-IA-1

HPCI Quarterly Pump and Valve Tests

110

255-06-III-1

HPCI Comprehensive Pump and Valve Tests

255-08-IA-1

RCIC Quarterly Pump and Valve Tests

255-08-III-1

RCIC Comprehensive Pump and Valve Tests

255-10-IA-1

Primary Containment Isolation Valve Exercise

and 49

255-11-III-3

ESW Quarterly Pump and Valve Tests

1047-01

Shift Supervisor Checklist

B.08.15-05

Operations Manual Section: Cranes an Heavy Loads

Rev.31

C.5-1100

RPV Control

C.5-1100

RPV Control (MODE 1, 2, 3)

C.5-3502

Containment Spray

Procedures

ESP-125-0614-03

D8 125V DC Battery Check

Rev.6

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EWI-08.03.02

Logic System Testing Program

Rev.10

FG-E-SE-03

50.59 Resource Manual

FG-E-SE-03

50.59 Resource Manual

FP-E-SE-03

CFR 50.59 and 72.48 Processes

FP-G-DOC-04

Procedure Processing

39, 43

FP-MA-FSC-01

Scaffolding

FP-PE-MOV-07

Motor Operated Valve Program

ISP-ECC-0029

Reactor LO-LO Level ECCS Initiation & HI Level RCIC/HPCI

Turbine Trips Trip Unit Test and Calibration Procedure with

LSFT

Rev.0

ISP-ECC-0031

ECCS HIGH Drywell Pressure Sensor with LSFT

Rev.0

ISP-ECC-0033

ECCS Pump Start Permissive Sensor with LSFT

Rev.0

ISP-RHR-0552-02

Reactor Recirculation LOOPS DP, LPCI Select Interlock

Channel Calibration

5, 7, 8

ISP-RHR-0603

Reactor Steam Dome Pressure Low - Channel Calibration

and Channel Functional Test with LSFT

Rev.0

MPS-1100

Specification for the Analysis of Piping and Piping Support

Systems

Rev. 11

Ops Man B.01.04-

Reactor Recirculation System

55, 56

Ops Man B.03.04-

Residual Heat Removal System

QF0501

50.59 Screening

14