MONTHYEARIR 05000263/20240042025-01-30030 January 2025 Integrated Inspection Report 05000263/2024004 IR 05000263/20244042025-01-0606 January 2025 Material Control and Accounting Program Inspection Report 05000263/2024404 (Public) IR 05000263/20244032024-12-0606 December 2024 – Security Baseline Inspection Report 05000263/2024403 IR 05000263/20244022024-12-0606 December 2024 – Security Baseline Inspection Report 05000263/2024402; Independent Spent Fuel Storage Installation Security Inspection Report 07200058/2024401 IR 05000263/20243012024-11-27027 November 2024 NRC Initial License Examination Report 05000263/2024301 IR 05000263/20240032024-11-13013 November 2024 Integrated Inspection Report 05000263/2024003 IR 05000263/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000263/2024011 IR 05000263/20240052024-08-30030 August 2024 Updated Inspection Plan and Follow-Up Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2024005) IR 05000263/20244202024-08-21021 August 2024 Security Baseline Inspection Report 05000263/2024420 - Cover Letter IR 05000263/20240022024-08-14014 August 2024 Integrated Inspection Report 05000263/2024002 IR 05000263/20244012024-05-30030 May 2024 Public - Monticello Nuclear Generating Plant - Cyber Security Inspection Report 05000263/2024401 IR 05000263/20240102024-05-13013 May 2024 Age-Related Degrading Inspection Report 05000263/2024010 IR 05000263/20240012024-04-29029 April 2024 Plan - Integrated Inspection Report 05000263/2024001 IR 05000263/20230062024-02-28028 February 2024 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2023006) IR 05000263/20230042024-01-31031 January 2024 Integrated Inspection Report 05000263/2023004 ML24022A1382024-01-22022 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2024401 IR 05000263/20234022023-12-13013 December 2023 Security Baseline Inspection Report 05000263/2023402 IR 05000263/20230032023-11-13013 November 2023 Integrated Inspection Report 05000263/2023003 and 07200058/2023001 IR 05000263/20230102023-09-0707 September 2023 Commercial Grade Dedication Inspection Report 05000263/2023010 IR 05000263/20230052023-08-30030 August 2023 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2023005) IR 05000263/20230022023-08-0707 August 2023 Plant–Integrated Inspection Report 05000263/2023002 IR 05000263/20235012023-07-13013 July 2023 Emergency Preparedness Inspection Report 05000263/2023501 IR 05000263/20230012023-05-0404 May 2023 Integrated Inspection Report 05000263/2023001 IR 05000263/20234012023-05-0404 May 2023 – Security Baseline Inspection Report 05000263/2023401 IR 05000263/20220062023-03-0101 March 2023 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2022006) IR 05000263/20220042023-01-17017 January 2023 Integrated Inspection Report 05000263/2022004 IR 05000263/20220122022-12-15015 December 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000263/2022012 IR 05000263/20220132022-11-21021 November 2022 Biennial Problem Identification and Resolution Inspection Report 05000263/2022013 IR 05000263/20223012022-11-21021 November 2022 NRC Initial License Examination Report 05000263/2022301 IR 05000263/20220032022-11-17017 November 2022 Reissue - Monticello Nuclear Generating Plant - Integrated Inspection Report 05000263/2022003 ML22307A1822022-11-14014 November 2022 Integrated Inspection Report 05000263/2022003 IR 05000263/20224032022-10-19019 October 2022 Security Baseline Inspection Report 05000263/2022403 (Public) IR 05000263/20220052022-08-29029 August 2022 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2022005) IR 05000263/20220022022-07-28028 July 2022 Integrated Inspection Report 05000263/2022002 IR 05000263/20220012022-05-10010 May 2022 Generation Plant - Integrated Inspection Report 05000263/2022001 IR 05000263/20224022022-05-0505 May 2022 Security Baseline Inspection Report 05000263/2022402; Independent Spent Fuel Storage Installation Security Inspection Report 07200058/2022401 IR 05000263/20224012022-03-28028 March 2022 Generation Plant - Cyber Security Inspection Report 05000263/2022401 IR 05000263/20210062022-03-0202 March 2022 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2021006) IR 05000263/20210042022-01-28028 January 2022 Integrated Inspection Report 05000263/2021004 and 07200058/2021001 IR 05000263/20214022021-12-16016 December 2021 Triennial Material Control and Accounting Report 05000263/2021402 IR 05000263/20214202021-11-15015 November 2021 Security Baseline Inspection Report Cover Letter 05000263 2021420 IR 05000263/20210032021-10-27027 October 2021 Plan, Integrated Inspection Report 05000263/2021003 IR 05000263/20210102021-10-0808 October 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000263/2021010 IR 05000263/20210112021-09-29029 September 2021 Plan - Temporary Instruction 2515/194 Inspection; Ibspection Report 05000263/2021011 IR 05000263/20215012021-09-0101 September 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000263/2021501 IR 05000263/20210052021-09-0101 September 2021 Updated Inspection Plan for Monticello Nuclear Generating Plant 2 (Report 05000263/2021005) IR 05000263/20210022021-08-0303 August 2021 Integrated Inspection Report 05000263/2021002 IR 05000263/20210012021-04-30030 April 2021 Integrated Inspection Report 05000263/2021001 IR 05000263/20200062021-03-0404 March 2021 Annual Assessment Letter for the Monticello Nuclear Generating Plant (Report 05000263/2020006) IR 05000263/20200102021-03-0202 March 2021 Reissue - Monticello Nuclear Generating Plant - Biennial Problem Identification and Resolution Inspection Report 05000263/2020010 2025-01-06
[Table view] Category:Letter
MONTHYEARIR 05000263/20240042025-01-30030 January 2025 Integrated Inspection Report 05000263/2024004 ML25006A1522025-01-16016 January 2025 Section 106 Consultation of Monticello SLR-Shakopee ML25006A1502025-01-16016 January 2025 Section 106 Consultation for Monticello SLR-Lower Sioux Indian Community ML25006A1512025-01-16016 January 2025 Section 106 Consultation for Monticello SLR-Mille Lacs Band of Ojibwe ML25010A0722025-01-10010 January 2025 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000263/2025002 IR 05000263/20244042025-01-0606 January 2025 Material Control and Accounting Program Inspection Report 05000263/2024404 (Public) ML24310A3442024-12-30030 December 2024 Transmittal Letter for Renewed License ML24270A1552024-12-19019 December 2024 Issuance of Amendment No. 213 Revise Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (Ptlr), and Update Neutron Fluence Methodology ML24354A2952024-12-18018 December 2024 ISFSI and Monticello Nuclear Generating Plant - Independent Spent Fuel Storage Installation Decommissioning Funding Plans L-MT-24-045, 2024 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462024-12-13013 December 2024 2024 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 ML24353A1192024-12-12012 December 2024 Usepa Monticello Re-license Feis Comments (1) IR 05000263/20244022024-12-0606 December 2024 – Security Baseline Inspection Report 05000263/2024402; Independent Spent Fuel Storage Installation Security Inspection Report 07200058/2024401 IR 05000263/20244032024-12-0606 December 2024 – Security Baseline Inspection Report 05000263/2024403 ML24324A0082024-12-0404 December 2024 Letter to Minnesota State Historic Preservation Office Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renewal Application IR 05000263/20243012024-11-27027 November 2024 NRC Initial License Examination Report 05000263/2024301 L-MT-24-042, Update to the Technical Specifications Bases2024-11-22022 November 2024 Update to the Technical Specifications Bases ML24323A2142024-11-21021 November 2024 – Relief Request RR-017, Inservice Inspection (ISI) Impracticality During the Fifth Ten-Year Interval ML24318C5002024-11-19019 November 2024 Letter to Robert Blanchard Tribal Chairman Bad River Band of Lake Superior Chippewa Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5102024-11-18018 November 2024 Letter to Louis Taylor Chairman Lac Courte Oreilles Band of Lake Superior Chippewa Indians Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5092024-11-18018 November 2024 Letter to Doreen Blaker President Keweenaw Bay Indian Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5012024-11-18018 November 2024 Letter to Catherine Chavers Tribal Chairwoman Bois Forte Band Chippewa Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5202024-11-18018 November 2024 Letter to Grant Johnson President Prairie Island Indian Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5182024-11-18018 November 2024 Letter to Gena Kakkak Chairwoman Menominee Indian Tribe of Wisconsin Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5222024-11-18018 November 2024 Letter to Darrell Seki Chairman Red Lake Nation Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5282024-11-18018 November 2024 Letter to Jamie Azure Chairman Turtle Mountain Band of Chippewa Indians Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5322024-11-18018 November 2024 Letter to Robert Vanzile Jr Chairman Sokaogon Chippewa Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24312A1732024-11-18018 November 2024 Ltr. to Shawn Hafen, Site Vice President, Monticello Nuclear Generating Plant, Re., NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5032024-11-18018 November 2024 Letter to Anthony Reider President Flandreau Santee Sioux Tribe NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5232024-11-18018 November 2024 Letter to Alonzo Denney Chairman Santee Sioux Nation Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5022024-11-18018 November 2024 Letter to Reggie Wassana Governor Cheyenne and Arapaho Tribes NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5162024-11-18018 November 2024 Letter to James Williams Jr Chairman Lac Vieux Desert Band of Lake Superior Chippewa Indians Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5212024-11-18018 November 2024 Letter to Nicole Boyd Chairwoman Red Cliff Band of Lake Superior Chippewa Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5312024-11-18018 November 2024 Letter to Virgil Wind Chief Executive Mille Lacs Band of Ojibwe Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5292024-11-18018 November 2024 Letter to Kevin Jensvold Tribal Chairman Upper Sioux Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5042024-11-18018 November 2024 Letter to Jeffrey Stiffarm President Fort Belknap Indian Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5112024-11-18018 November 2024 Letter to John Johnson President Lac Du Flambeau Band of Lake Superior Chippewa Indians Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24312A3512024-11-18018 November 2024 Letter to Amy Spong, Deputy State Historic Preservation Officer, Re., NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5172024-11-18018 November 2024 Letter to Robert Larsen President Lower Sioux Indian Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5072024-11-18018 November 2024 Letter Timothy Rhodd Chairman Iowa Tribe of Kansas and Nebraska Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5252024-11-18018 November 2024 Letter to J Garrett Renville Tribal Chairman Sisseton Wahpeton Oyate of the Lake Traversee Re NOA Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5262024-11-18018 November 2024 Letter to Lonna Johnson Street Chairperson Spirit Lake Nation Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5192024-11-18018 November 2024 Letter to Michael Laroque President Minnesota Chippewa Tribe Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5302024-11-18018 November 2024 Letter to Michael Fairbanks Chairman White Earth Nation Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5052024-11-18018 November 2024 Letter to Bruce Savage Tribal Chairperson Found Du Lac Band of Lake Superior Chippewa Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5062024-11-18018 November 2024 Letter to Robert Deschampe Tribal Chair Grand Portage Band of Lake Superior Chippewa Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5152024-11-18018 November 2024 Letter to Faron Jackson Sr Chairman Leech Lake Band of Ojibwe Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24312A3462024-11-18018 November 2024 Letter to Jaime Loichinger Director Office of Federal Agency Programs, Achp NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5242024-11-18018 November 2024 Letter to Cole Miller Chairman Shakopee Mdewakaton Sioux Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24312A3202024-11-18018 November 2024 Letter to Durell Cooper Tribal Chairman Apache Tribe of Oklahoma Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5272024-11-18018 November 2024 Letter to Thomas Fowler Chairman St. Croix Chippewa of Wisconsin Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR 2025-01-06
[Table view] |
Text
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT - EMERGENCY PREPAREDNESS BIENNIAL EXERCISE INSPECTION REPORT 05000263/2021501
Dear Mr. Conboy:
On August 12, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Monticello Nuclear Generating Plant and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Patricia J. Pelke, Chief Operations Branch Division of Reactor Safety Docket No. 05000263 License No. DPR-22
Enclosure:
As stated
Inspection Report
Docket Number:
05000263
License Number:
DPR-22
Report Number:
05000263/2021501
Enterprise Identifier:
I-2021-501-0017
Licensee:
Northern States Power Company, Minnesota
Facility:
Monticello Nuclear Generating Plant
Location:
Monticello, MN
Inspection Dates:
August 09, 2021 to August 12, 2021
Inspectors:
M. Garza, Emergency Preparedness Inspector
G. Hansen, Senior Emergency Preparedness Inspector
S. Hedger, Emergency Preparedness Inspector
P. Zurawski, Senior Resident Inspector
Approved By:
Patricia J. Pelke, Chief
Operations Branch
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an emergency preparedness biennial exercise inspection at Monticello Nuclear Generating Plant, in accordance with the Reactor Oversight Process.
The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19),inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
REACTOR SAFETY
71114.01 - Exercise Evaluation
Inspection Review (IP Section 02.01-02.11) (1 Sample)
- (1) The inspectors evaluated the Biennial Emergency Plan Exercise on August 10, 2021. The exercise scenario simulated an event at the Monticello Nuclear Generating Plant that initiated with the declaration and notification of a Notice of Unusual Event due to the unplanned loss of Control Room indications for 15 minutes or longer, specifically the loss of all torus level input to control room indicators and plant process computer system (PPCS). The scenario conditions simulated the escalation of the significance of the event, requiring the declaration and notification of an Alert and a Site Area Emergency. The Site Area Emergency was the highest classification level reached, as planned, during the exercise.
71114.08 - Exercise Evaluation Scenario Review
Inspection Review (IP Section 02.01 - 02.04) (1 Sample)
- (1) The inspectors reviewed and evaluated the proposed scenario for biennial emergency plan exercise on July 7,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12)===
- (1) April 01, 2020 through June 30, 2021 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
- (1) April 01, 2020 through June 30, 2021 EP03: Alert And Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
- (1) April 01, 2020 through June 30,
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On August 12, 2021, the inspectors presented the emergency preparedness biennial exercise inspection results to Thomas Conboy and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
501000030432
EP Drill - Conflicting Procedural Guidance
08/06/2019
501000031629
EP-Drill - CR/TSC Communication Improvement
09/10/2019
501000031654
EP Exercise - Initial Communication with Shift Manager
09/10/2019
501000031678
EP Drill - Unclear Definition of Intact
09/10/2019
501000031682
EP Drill Team Work with the State EOC
09/10/2019
501000031692
EP Drill - Offsite Communication Procedures
09/10/2019
501000031700
EP Drill - OSC Briefing Effectiveness
09/10/2019
501000031710
EP Drill - Rad Protection Surveys
09/10/2019
501000038380
Emergency Notification Form Auto Population
03/03/2020
501000039354
EP Notification Form Error 3-23-20
04/02/2020
501000041918
EP Drill-Notification Completion Time
06/30/2020
501000045279
NUE Follow-up Actions
10/08/2020
501000046482
EP Table-Top Drill - Escalation Criteria
11/17/2020
501000053359
Seals Missing from OSC EP Cabinet
06/24/2021
Corrective Action
Documents
501000053609
EP Drill - Procedure May Not Be Adequate
06/29/2021
Miscellaneous
Monticello Nuclear Generating Plant Emergency Plan
A.2-101
Classification of Emergencies
A.2-106
Activation and Operation of the TSC
A.2-107
Activation and Operation of the OSC
A.2-109
Activation and Operations of the Back-up OSC
A.2-201
On-Site Protective Action
A.2-205
Personnel Accountability
A.2-206
Work Control During Emergencies
A.2-213
Responsibilities of the Emergency Director
A.2-401
Emergency Exposure Control
A.2-402
On-Site Radiological Monitoring
A.2-501
Communications during an Emergency
A.2-504
Emergency Communicator Duties in the TSC and OSC
A.2-801
Responsibilities of the Emergency Manager
71114.01
Procedures
A.2-802
Activation and Operation of EOF
71114.08
Miscellaneous
Monticello Nuclear Generating Plant Emergency Plan Exercise
06/09/2021
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Scenario
Emergency Response Organization (ERO) Drill Participation
Performance Indicator Records
04/01/2020-
06/30/2021
Drill and Exercise Participation (DEP) Performance Indicator
Records
04/01/2020-
06/30/2021
71151
Miscellaneous
Alert Notification System (ANS) Reliability Performance
Indicator Records
04/01/2020-
06/30/2021