Letter Sequence RAI |
|---|
TAC:ME4640, Steam Generator Tube Integrity (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval
Other: L-11-114, Drawing No. M-042B, Rev. 35, Sampling System Sh. 2 Local Grab Samples, L-11-131, Drawing No. LR-OS041A2, Revision 1, Operational Schematic Emergency Diesel Generator Systems, L-11-334, Reply to Request Additional Information for the Review of the License Renewal Application Amendment No. 21, L-12-337, Review of the Safety Evaluation Report with Open Items Related to the License Renewal, L-12-341, Firstenergy Nuclear Operating Cos Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-12-444, Submittal of Contractor Equivalent Margins Assessments for Reactor Vessel Welds (Nonproprietary Versions), L-12-456, Notification of Closure of Commitments Related to the Review of the License Renewal Application, L-13-257, Notification of Completion of a License Renewal Commitment Related to the Review of License Renewal Application TAC No. ME4640) and License Renewal Application Amendment No. 45), L-13-330, License Renewal Application Amendment No. 46 - Annual Update, L-13-341, Review of the Safety Evaluation Report Related to the License Renewal of Davis-Besse Nuclear Power Station, L-14-085, License Renewal Application (TAC No. ME4640) Amendment No. 48, L-14-206, License Renewal Application Amendment No. 50 - Annual Update, L-15-120, Notification of Completion of License Renewal Commitments Related to the Review of the Davis-Besse Nuclear Power Station, Unit No. 1, License Renewal Application and License Renewal Application Amendment No. 55, L-15-139, License Renewal Reactor Vessel Internals Inspection Plan, L-15-214, License Renewal Application Amendment No. 59 - Annual Update, L-15-309, License Renewal Application Amendment No. 60, L-15-310, C-CSS-099.20-069, Rev 0, Shield Building Laminar Cracking Limits, ML111050091, ML11110A089, ML11110A091, ML11110A092, ML11110A093, ML11110A094, ML11110A095, ML11110A105, ML11110A106, ML11110A107, ML11122A014, ML11126A017, ML11126A018, ML11126A019, ML11126A020, ML11126A021, ML11126A022, ML11126A023, ML11126A024, ML11126A025, ML11126A026, ML11126A032, ML11126A033, ML11126A034, ML11126A035, ML11126A036, ML11126A037, ML11126A038, ML11126A039, ML11126A040, ML11126A041, ML11126A042, ML11126A043... further results
|
MONTHYEARML11126A0842003-01-22022 January 2003 Drawing No. LR-M039A, Revision 3, Piping & Instrument Diagram Miscellaneous Liquid Radioactive Waste. Job Code 12501 Project stage: Other ML11126A0762003-01-22022 January 2003 Drawing No. LR-M047, Revision 1, Piping & Instrument Diagram Radwaste Drumming Station Project stage: Other ML11126A0552003-08-12012 August 2003 Drawing No. LR-M030B, Revision 1, Reactor Coolant System Instrumentation Project stage: Other ML11126A0862005-08-23023 August 2005 Drawing No. LR-M040D, Revision 2, Piping & Instrument Diagram Reactor Coolant Pump & Motor. Job Code 12501 Project stage: Other ML11126A0882008-01-12012 January 2008 Drawing No. LR-M041B, Revision 1, Piping & Instrument Diagram Primary Service Water System. Job Code 12501 Project stage: Other ML11126A0902008-01-15015 January 2008 Drawing No. LR-OS41A1, Revision 1, Operational Schematic Emergency Diesel Generator Systems Project stage: Other L-11-131, Drawing No. LR-OS041A2, Revision 1, Operational Schematic Emergency Diesel Generator Systems2008-01-15015 January 2008 Drawing No. LR-OS041A2, Revision 1, Operational Schematic Emergency Diesel Generator Systems Project stage: Other ML11126A0682008-05-0505 May 2008 Drawing No. LR-M-037E, Revision 28, Piping & Instrument Diagram Clean Liquid Radioactive Waste System Project stage: Other ML11126A0652008-08-0606 August 2008 Drawing No. LR-M036B, Revision 1, Piping & Instrument Diagram Component Cooling Water System Project stage: Other ML11126A0592008-10-0909 October 2008 Drawing No. LR-M033A, Revision 1, Piping & Instrument Diagram High Pressure Injection Project stage: Other ML11126A0632008-10-10010 October 2008 Drawing No. LR-M033B, Revision 1, Piping & Instrument Diagram Decay Heat Train 1 Project stage: Other ML11126A0702008-10-10010 October 2008 Drawing No. LR-M033C, Revision 1, Piping & Instrument Diagram Decay Heat Train 2 Project stage: Other ML11126A0742008-11-0606 November 2008 Drawing No. LR-M043, Revision 1, Piping & Instrument Diagram Auxiliary Building Chilled Water System Project stage: Other ML11126A0832008-12-18018 December 2008 Drawing No. LR-M038C, Revision 2, Piping & Instrument Diagram Gaseous Radioactive Waste System. Job Code 12501 Project stage: Other ML11126A0712009-04-0707 April 2009 Drawing No. LR-M034, Revision 1, Piping & Instrument Diagram Emerg. Core Cooling System Ctmt. Spray & Core Flooding Systems Project stage: Other ML11126A0892009-04-0707 April 2009 Drawing No. LR-OS002, Revision 1, Operational Schematic Makeup and Purification System Project stage: Other ML1104500462011-02-17017 February 2011 Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station - Fire Protection Project stage: RAI L-11-037, Independent Spent Fuel Storage Installation - Changes, Tests, and Experiments2011-02-17017 February 2011 Independent Spent Fuel Storage Installation - Changes, Tests, and Experiments Project stage: Request ML11126A0792011-02-25025 February 2011 Drawing No. LR-M900A, Revision 0, Instrument Air System Piping Schematic Project stage: Other ML1104205972011-02-28028 February 2011 Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station - Section 2.4 Project stage: RAI ML1106801722011-03-17017 March 2011 Request for Additional Information on the Reactor Vessel Surveillance Aging Management Program, Time-Limited Aging Analyses for Neutron Embrittlement of the Rv and Internals, and Other TLAAs for the Review of the Davis-Besse Nuclear Power s Project stage: RAI L-11-078, Reply to Request for Additional Information for the Review of License Renewal Application (TAC ME4640) Amendment No. 12011-03-18018 March 2011 Reply to Request for Additional Information for the Review of License Renewal Application (TAC ME4640) Amendment No. 1 Project stage: Response to RAI ML1107007322011-03-18018 March 2011 Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station-Section 2.2 & 2.3 Project stage: RAI ML11068A0002011-03-21021 March 2011 Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station - Section 4.7 (TAC Number ME4640) Project stage: RAI L-11-079, Reply to Request for Additional Information for the Review of the License Renewal Application2011-03-23023 March 2011 Reply to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI L-11-089, Reply to Request for Additional Information for the Review License Renewal Application2011-03-23023 March 2011 Reply to Request for Additional Information for the Review License Renewal Application Project stage: Response to RAI ML1108206242011-03-30030 March 2011 Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station-Section 2.1 (Tac No. ME4640) Project stage: RAI ML1109002952011-03-31031 March 2011 Safety Evaluation Report Related to the License Renewal of Salem Nuclear Generating Station Project stage: Approval ML1108204902011-04-0505 April 2011 Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station - Batch 1 Project stage: RAI ML11110A0882011-04-15015 April 2011 Reply to Request for Additional Information for the Review of the License Renewal Application, Sections 2.2 & 2.3, License Renewal Application Amendment No. 3, and Revised License Renewal Project stage: Response to RAI L-11-107, Reply to Request for Additional Information on Reactor Vessel Surveillance Aging Management Program & Time-Limited Aging Analyses for Neutron Embrittlement for Review of License Renewal Application & License Renewal Application.2011-04-15015 April 2011 Reply to Request for Additional Information on Reactor Vessel Surveillance Aging Management Program & Time-Limited Aging Analyses for Neutron Embrittlement for Review of License Renewal Application & License Renewal Application. Project stage: Response to RAI L-11-114, Drawing No. M-042B, Rev. 35, Sampling System Sh. 2 Local Grab Samples2011-04-15015 April 2011 Drawing No. M-042B, Rev. 35, Sampling System Sh. 2 Local Grab Samples Project stage: Other ML11110A0892011-04-15015 April 2011 Drawing No. M-0060, Rev. 52, Auxiliary Feedwater System Project stage: Other ML11110A0912011-04-15015 April 2011 Drawing No. M-011, Rev. 61, Domestic Water System Project stage: Other ML11110A0922011-04-15015 April 2011 Drawing No. M-037C, Rev. 30, Clean Liquid Radioactive Waste System Project stage: Other ML11110A0932011-04-15015 April 2011 Drawing No. M-037D, Rev. 21, Clean Liquid Radioactive Waste System Project stage: Other ML11110A0942011-04-15015 April 2011 Drawing No. M-039A, Rev. 33, Miscellaneous Liquid Radioactive Waste Project stage: Other ML11110A0952011-04-15015 April 2011 Drawing No. M-039B, Rev. 18, Miscellaneous Liquid Radioactive Waste Project stage: Other ML11110A1052011-04-15015 April 2011 Drawing No. M-040A, Rev. 76, Reactor Coolant System Details Project stage: Other ML11110A1062011-04-15015 April 2011 Drawing No. M-042C, Rev. 33, Sampling System Sh. 3 Project stage: Other ML11110A1072011-04-15015 April 2011 Drawing No. M-045, Rev. 56, Chemical Addition Systems Project stage: Other ML1110500912011-04-19019 April 2011 Scoping and Screening Audit Report Regarding the Davis-Besse Nuclear Power Station License Renewal Application Project stage: Other ML1109807182011-04-20020 April 2011 Request for Additional Information for the Review of the Davis-Bessie Nuclear Power Station - Batch 2 Project stage: RAI L-11-115, Reply to Request for Additional Information for the Review of the License Renewal Application and License Renewal Application Amendment No. 42011-04-20020 April 2011 Reply to Request for Additional Information for the Review of the License Renewal Application and License Renewal Application Amendment No. 4 Project stage: Response to RAI ML11126A0342011-04-29029 April 2011 Drawing No. LR-M017B, Revision 1, Piping & Instrument Diagram, Diesel Generators Air Start Project stage: Other ML11126A0172011-04-29029 April 2011 Drawing No. LR-M006E, Revision 1, Piping & Instrument Diagram Condensate System Project stage: Other ML11126A0182011-04-29029 April 2011 Drawing No. LR-M007A, Revision 1, Piping & Instrument Diagram Steam Generator Secondary System Project stage: Other ML11126A0192011-04-29029 April 2011 Drawing No. LR-M003A, Revision 1, Piping & Instrument Diagram Main Steam and Reheat System. Sheet 1 Project stage: Other ML11126A0202011-04-29029 April 2011 Drawing No. LR-M003B, Revision 1, Piping & Instrument Diagram Main Steam and Reheat System. Sheet 2 Project stage: Other ML11126A0212011-04-29029 April 2011 Drawing No. LR-M003C, Revision 2, Piping & Instrument Diagram Main Steam and Reheat System. Sheet 3 Project stage: Other 2011-02-17
[Table View] |
Text
~f>.1'\\ REGu{
UNITED STATES
"'~vv\\,;
'1>>0'1>..<.
NUCLEAR REGULATORY COMMISSION
~
Cl 0
WASHINGTON, D.C. 20555-0001 In
~
i 0'
February 9, 2012
LICENSEE' FirstEnergy Nuclear Operating Company FACILITY:
Davis-Besse Nuclear Power Station SUBJECT
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JUNE 16,2011, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION (TAC. NO. ME4640)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company (FENOe or the applicant) held a telephone conference call on June 16, 2011, to discuss and clarify the staff's concerns related to the Davis-Besse Nuclear Power Station license renewal application. provides a listing of the participants and Enclosure 2 contains a deSCription of the staff concerns discussed with the applicant. A brief description on the status of the items is also included.
The applicant had an opportunity to comment on this summary.
Docket No. 50-346 Enclosures' As stated cc w/encls: Listserv
SUMMARY
OF TELEPHONE CONFERENCE CALL DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS June 16, 2011 PARTICIPANTS AFFILIATIONS Samuel Cuadrado de Jesus U.S. Nuclear Regulatory Commission (NRC)
James Medoff NRC Steve Dort FirstEnergy Nuclear Operating Company (FENOC)
Kathy Nesser FENOC John Hartigan FENOC Larry Hinkle FENOC ENCLOSURE 1
SUMMARY
OF TELEPHONE CONFERENCE CALL DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION June 16, 2011 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company (FENOC or the applicant) held a telephone conference call on June 16, 2011, to discuss and clarify the following concerns related to the Davis-Besse Nuclear Power Station (Davis-Besse) license renewal application (LRA).
Discuss absence of a time-limited againg analysis (TLAA) on their bases for non-Class 1!
non-piping components Discussion:
The staff requested the applicant to explain the absence of a TLAA on their bases for non-Class 1, non-piping components.
The applicant responded by explaining that non-Class 1 components reanalyzed as Class 1 components are addressed under the Class 1 Section of the LRA.
The staff understood the applicant's explanation and stated that no request for additional information (RAI) is necessary.
RAI4.1-2 Discussion:
The staff requested the applicant to discuss extension of the scope of RAI 4.1-2 to both the time-dependent J-integral analysis and the time-dependent fatigue flaw growth analysis in Structural Integrity Associates (SIA) Topical Report No. SIR-99-040, Revision 1, "ASME Code Case N-481 of Davis-Besse Reactor Coolant Pumps" (ADAMS Accession No. ML011200090).
The staff stated that the scope of the RAI, as issued, only talked about the fatigue flaw growth analysis in the report, which forms the basis for applying VT-1 or EVT-1 visual examinations of the outside surfaces of the reactor coolant pump (RCP) casing welds in lieu of the ultrasonic test (UT) examinations that would be required by the ASME Section XI Code of Record. The staff also stated that there is a possibility, that 10 CFR SO.SSa may require the applicant to update to a more recent edition of the ASME Section XI Code that has incorporated the visual examinations requirements for the pump casings. If this is the case, the staff stated that it will need to know whether the applicant's current licensing basis (CLB) is still relying on the SIA report to support using the visual methods cited in the updated ASME Section XI Code of Record.
The applicant responded by stating that the response to RAI 4.1-2 as presently drafted only addresses time-dependent fatigue flaw growth analysis. The applicant stated that the response is included in the letter (L-11-203) that is to be sent to the staff on Friday, June 17, 2011.
Because the response was already drafted and already went through the applicant's submittal process, a supplement to the response will be submitted at a later date (most likely with the letter due June 24, 2011) to address the time-dependent J-integral analysis.
ENCLOSURE 2
- 2 In addition, the applicant also stated that the applicable ASME Code for the current (third) 1 O-year inspection interval for Davis-Besse is ASME Section XI, 1995 Edition, through the 1996 Addenda and that the interval does not end until September 20, 2012. Therefore, the Davis-Besse CLB still relies on the SIA Topical Report SIR-99-040.
Action: NRC project manager and applicant's license renewal project manager will discuss submittal date via telephone.
Topic updated safety analysis report (USAR) Appendix SA design basis for reactor coolant pump (Rep) flywheel integrity Discussion:
The staff requested the applicant to discuss their USAR Appendix 5A design basis for RCP flywheel integrity. The staff agrees that the reference temperature nil ductility (RTndt) analysis for the flywheels in that appendix does not need to include a time-dependent neutron fluence-based.6RTndt adjustment in the manner that they are included in the RT ndt analyses for the reactor vessel beltline components (Le., beltline base metals and weld components).
However, USAR Appendix 5A states that the Standard Review Plan (SRP) Section 5.4.1.1 acceptance basis is an 80"F difference basis between the RTndt value and the operating temperature (which according to the USAR Appendix, puts the minimum operating temperature at 120°F). Contrary to this statement, the staff determined that SRP 5.4.1.1 states (recommends) that the difference between the RTndt value and the operating temperature should be at least 100°F, which for full conformance with the SRP basis would dictate a minimum operating temperature of 140°F for the RCP flywheels at Davis-Besse. The USAR Section 5A also states that Section 3.1 of the USAR gives the 120"F operating temperature basis for the flywheels, but the staff could not find any such basis in USAR Section 3.1. The staff further stated that SRP Section 5.4.1.1 on flywheel integrity (which the applicant uses as the USAR Appendix 5A basis) states that the RTndt values for the RCP flywheel plate will be based on actual drop-weight testing results; however, the applicant established the RTndt value for the SA-533 flywheel plates materials using generic application of the RTndt values for their SA-533 plate materials for the reactor vessel (RV) beltline materials (pick 40"F as the highest value. The staff stated that this is a CLB issue.
The applicant responded by stating that its intention was not to completely comply with SRP 5.4.1.1.
The staff suggested that the applicant look into this, not as a license renewal issue, but rather as a CLB issue. The staff stated that no RAI will be issued.
Reactor Vessel Internal fRV!) components Discussion:
The staff stated that the discrepancy between the applicant's Technical Specification (TS) 5.5.4 inspection requirements for its RVI vent valve discs and its plant-specific Pressurized-Water Reactor (PWR) Vessel Internals Program criteria that needs to be discussed. The staff also stated that the adequacy of the aging management reviews (AMRs) for the RVI components will need to be discussed as well.
- 3 The applicant stated that it does not believe that a discrepancy exists between the TS 5.5.4 inspection requirements for its RVI vent valve discs and its plant-specific PWR Vessel Internals Program criteria that is based on MRP-227. The applicant also stated that the TS requires the disc inspection each refueling outage versus MRP-227 that requires the inspection each 10 year interval. Therefore, MRP-227 inspection frequency is satisfied. However, this may require further discussion, as the staff lead reviewer, Ganesh Cheruvenki, was not in attendance.
The AMR of the RVI was briefly discussed. The applicant suggested that an LRA supplement could be submitted that would revise the AMR for RVI and that it would be based on MRP-227 along with the guidance provided in NUREG-1801, Revision 2 (GALL Report). The staff stated that the concerns related to the RVI would be discussed internally (to include Ganesh Cheruvenki) and a response provided to the applicant at a later date.
There was no further discussion, and the call was concluded.
Memorandum to FirstEnergy Nuclear Operating Company from S. CuadradoDeJesus dated February 9, 2012
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JUNE 16, 2011 BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAIf\\IING TO THE DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION (TAC. NO. ME4640)
DISTRIBUTION:
HARD COPY:
DLRRF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb'l Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource PCooper BHarris SCuadrado EMilier MMahoney ICouret, OPA TReilly,OCA BHarris, OGC
'.. ML12018A146
- concurred via email PM:RPB1 :DLR BC:RPB1 :DLR OFFICE LA: RPB1 :DLR*
SCuadrado de Jesus DMorey YEdmonds/lKing for DATE NAME 2/9/12 2/09/12 2/09/12