MONTHYEARML11126A0882008-01-12012 January 2008 Drawing No. LR-M041B, Revision 1, Piping & Instrument Diagram Primary Service Water System. Job Code 12501 Project stage: Other ML11126A0902008-01-15015 January 2008 Drawing No. LR-OS41A1, Revision 1, Operational Schematic Emergency Diesel Generator Systems. Project stage: Other L-11-131, Drawing No. LR-OS041A2, Revision 1, Operational Schematic Emergency Diesel Generator Systems.2008-01-15015 January 2008 Drawing No. LR-OS041A2, Revision 1, Operational Schematic Emergency Diesel Generator Systems. Project stage: Other ML11126A0682008-05-0505 May 2008 Drawing No. LR-M-037E, Revision 28, Piping & Instrument Diagram Clean Liquid Radioactive Waste System. Project stage: Other ML11126A0652008-08-0606 August 2008 Drawing No. LR-M036B, Revision 1, Piping & Instrument Diagram Component Cooling Water System. Project stage: Other ML11126A0592008-10-0909 October 2008 Drawing No. LR-M033A, Revision 1, Piping & Instrument Diagram High Pressure Injection. Project stage: Other ML11126A0632008-10-10010 October 2008 Drawing No. LR-M033B, Revision 1, Piping & Instrument Diagram Decay Heat Train 1. Project stage: Other ML11126A0702008-10-10010 October 2008 Drawing No. LR-M033C, Revision 1, Piping & Instrument Diagram Decay Heat Train 2. Project stage: Other ML11126A0742008-11-0606 November 2008 Drawing No. LR-M043, Revision 1, Piping & Instrument Diagram Auxiliary Building Chilled Water System. Project stage: Other ML11126A0832008-12-18018 December 2008 Drawing No. LR-M038C, Revision 2, Piping & Instrument Diagram Gaseous Radioactive Waste System. Job Code 12501 Project stage: Other ML11126A0712009-04-0707 April 2009 Drawing No. LR-M034, Revision 1, Piping & Instrument Diagram Emerg. Core Cooling System Ctmt. Spray & Core Flooding Systems. Project stage: Other ML11126A0892009-04-0707 April 2009 Drawing No. LR-OS002, Revision 1, Operational Schematic Makeup and Purification System. Project stage: Other ML1024505652010-08-27027 August 2010 License Renewal Application and Ohio Coastal Management Program Consistency Certification Project stage: Other ML1025100842010-09-14014 September 2010 Y20100173 - Gray'S Engineering and Consulting, Inc. - Letter Aerotest Operations, Inc Project stage: Other ML1104500462011-02-17017 February 2011 Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station - Fire Protection Project stage: RAI ML11126A0792011-02-25025 February 2011 Drawing No. LR-M900A, Revision 0, Instrument Air System Piping Schematic. Project stage: Other ML1104205972011-02-28028 February 2011 Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station - Section 2.4 Project stage: RAI ML1106801722011-03-17017 March 2011 Request for Additional Information on the Reactor Vessel Surveillance Aging Management Program, Time-Limited Aging Analyses for Neutron Embrittlement of the Rv and Internals, and Other TLAAs for the Review of the Davis-Besse Nuclear Power S Project stage: RAI L-11-078, Reply to Request for Additional Information for the Review of License Renewal Application (TAC ME4640) Amendment No. 12011-03-18018 March 2011 Reply to Request for Additional Information for the Review of License Renewal Application (TAC ME4640) Amendment No. 1 Project stage: Response to RAI ML1107007322011-03-18018 March 2011 Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station-Section 2.2 & 2.3 Project stage: RAI ML11068A0002011-03-21021 March 2011 Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station - Section 4.7 (TAC Number ME4640) Project stage: RAI L-11-089, Reply to Request for Additional Information for the Review License Renewal Application2011-03-23023 March 2011 Reply to Request for Additional Information for the Review License Renewal Application Project stage: Response to RAI L-11-079, Reply to Request for Additional Information for the Review of the License Renewal Application2011-03-23023 March 2011 Reply to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI ML1108206242011-03-30030 March 2011 Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station-Section 2.1 (Tac No. ME4640) Project stage: RAI ML1109002952011-03-31031 March 2011 Safety Evaluation Report Related to the License Renewal of Salem Nuclear Generating Station Project stage: Approval ML1108204902011-04-0505 April 2011 Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station - Batch 1 Project stage: RAI ML11110A1072011-04-15015 April 2011 Drawing No. M-045, Rev. 56, Chemical Addition Systems Project stage: Other ML11110A1062011-04-15015 April 2011 Drawing No. M-042C, Rev. 33, Sampling System Sh. 3 Project stage: Other ML11110A1052011-04-15015 April 2011 Drawing No. M-040A, Rev. 76, Reactor Coolant System Details Project stage: Other ML11110A0952011-04-15015 April 2011 Drawing No. M-039B, Rev. 18, Miscellaneous Liquid Radioactive Waste Project stage: Other ML11110A0942011-04-15015 April 2011 Drawing No. M-039A, Rev. 33, Miscellaneous Liquid Radioactive Waste Project stage: Other ML11110A0932011-04-15015 April 2011 Drawing No. M-037D, Rev. 21, Clean Liquid Radioactive Waste System Project stage: Other ML11110A0922011-04-15015 April 2011 Drawing No. M-037C, Rev. 30, Clean Liquid Radioactive Waste System Project stage: Other ML11110A0912011-04-15015 April 2011 Drawing No. M-011, Rev. 61, Domestic Water System Project stage: Other ML11110A0892011-04-15015 April 2011 Drawing No. M-0060, Rev. 52, Auxiliary Feedwater System Project stage: Other L-11-114, Drawing No. M-042B, Rev. 35, Sampling System Sh. 2 Local Grab Samples2011-04-15015 April 2011 Drawing No. M-042B, Rev. 35, Sampling System Sh. 2 Local Grab Samples Project stage: Other L-11-107, Reply to Request for Additional Information on Reactor Vessel Surveillance Aging Management Program & Time-Limited Aging Analyses for Neutron Embrittlement for Review of License Renewal Application & License Renewal Application...2011-04-15015 April 2011 Reply to Request for Additional Information on Reactor Vessel Surveillance Aging Management Program & Time-Limited Aging Analyses for Neutron Embrittlement for Review of License Renewal Application & License Renewal Application... Project stage: Response to RAI ML11110A0882011-04-15015 April 2011 Reply to Request for Additional Information for the Review of the License Renewal Application, Sections 2.2 & 2.3, License Renewal Application Amendment No. 3, and Revised License Renewal Project stage: Response to RAI ML1110500912011-04-19019 April 2011 Scoping and Screening Audit Report Regarding the Davis-Besse Nuclear Power Station License Renewal Application Project stage: Other ML1109807182011-04-20020 April 2011 Request for Additional Information for the Review of the Davis-Bessie Nuclear Power Station - Batch 2 Project stage: RAI L-11-115, Reply to Request for Additional Information for the Review of the License Renewal Application and License Renewal Application Amendment No. 42011-04-20020 April 2011 Reply to Request for Additional Information for the Review of the License Renewal Application and License Renewal Application Amendment No. 4 Project stage: Response to RAI ML11126A0482011-04-29029 April 2011 Drawing No. LR-M020A, Revision 1, Piping & Instrument Diagram, Water Treatment & Intake Structure Auxiliary Steam System. Project stage: Other ML11126A0392011-04-29029 April 2011 Drawing No. LR-M015A, Revision 1, Piping & Instrument Diagram Instrument Air System Project stage: Other ML11126A0402011-04-29029 April 2011 Drawing No. LR-M015D, Revision 1, Piping & Instrumentation Diagram Station Air System Project stage: Other ML11126A0412011-04-29029 April 2011 Drawing No. LR-M015F, Revision 0, Piping & Instrumentation Diagram Station Air System Containment Project stage: Other ML11126A0422011-04-29029 April 2011 Drawing No. LR-M019, Revison 1, Piping & Instrument Diagram, Nitrogen Supply System. Project stage: Other ML11126A0442011-04-29029 April 2011 Drawing No. LR-M024G, Revision 1, Piping & Instrument Station, No. 1 Main and Auxiliary Turbine Driven Feed Pumps. Project stage: Other ML11126A0452011-04-29029 April 2011 Drawing No. LR-M024H, Revision 1, Piping & Instrument Diagram, No. 2 Main and Auxiliary Turbine Driven Feed Pumps. Project stage: Other ML11126A0462011-04-29029 April 2011 Drawing No. LR-M027A, Revision 1, P & Id - HV & A/C Air Flow Diagram, Auxiliary Building Non Radioactive Areas and Control Room. Project stage: Other ML11126A0472011-04-29029 April 2011 Drawing No. M-027B, Rev. 43, P & ID-HV & A/C Air Flow Diagram, Auxiliary Building Non Radioactive Areas. Project stage: Other 2011-02-25
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 ML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23353A1192023-12-19019 December 2023 Operator Licensing Examination Approval Davis Besse Nuclear Power Station, January 2024 L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station L-23-243, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 IR 05000346/20234032023-11-0202 November 2023 Security Baseline Inspection Report 05000346/2023403 ML23293A0612023-11-0101 November 2023 Letter to the Honorable Marcy Kaptur, from Chair Hanson Responds to Letter Regarding Follow Up on Concerns Raised by Union Representatives During the June Visit to the Davis-Besse Nuclear Power Plant L-23-215, Changes to Emergency Plan2023-10-19019 October 2023 Changes to Emergency Plan ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000346/20234012023-09-13013 September 2023 Security Baseline Inspection Report 05000346/2023401 (Public) L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual IR 05000346/20230112023-08-30030 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000346/2023011 ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000346/20230052023-08-24024 August 2023 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2023005) L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments IR 05000346/20230502023-08-0303 August 2023 Special Inspection Report 05000346/2023050 IR 05000346/20230902023-08-0101 August 2023 EA-23-002 Davis-Besse Nuclear Power Station - NRC Inspection Report No. 05000346/2023090 (Public) ML23178A2742023-08-0101 August 2023 Letter to the Honorable Marcy Kaptur from Chair Hanson Responds to Letter Regarding the License Transfer Application for the Davis-Besse Nuclear Power Station L-23-175, Submittal of Fifth Ten Year Inservice Testing Program2023-08-0101 August 2023 Submittal of Fifth Ten Year Inservice Testing Program IR 05000346/20230022023-07-27027 July 2023 Integrated Inspection Report 05000346/2023002 ML23193A7842023-07-13013 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000346/2023402 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML23160A2342023-06-13013 June 2023 Confirmation of Initial License Examination L-23-034, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-13013 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models IR 05000346/20235012023-06-13013 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000346/2023501 L-23-135, Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-05-31031 May 2023 Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) ML23131A2732023-05-15015 May 2023 Notification of NRC Supplemental Inspection 95001 and Request for Information L-23-101, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station - 20222023-05-12012 May 2023 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station - 2022 L-23-131, Readiness for Resumption of NRC Supplemental Inspection2023-05-12012 May 2023 Readiness for Resumption of NRC Supplemental Inspection IR 05000346/20230102023-05-0909 May 2023 Commercial Grade Dedication Inspection Report 05000346/2023010 ML23123A1272023-05-0303 May 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Davis-Besse Nuclear Power Station IR 05000346/20230012023-05-0101 May 2023 Integrated Inspection Report 05000346/2023001 and 07200014/2022001 L-23-092, Occupational Radiation Exposure Report for Year 20222023-04-27027 April 2023 Occupational Radiation Exposure Report for Year 2022 ML23111A1972023-04-26026 April 2023 Information Meeting with Question and Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of Davis-Besse Nuclear Power Plant Station ML23114A1062023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300157, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-14014 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML23096A1382023-04-11011 April 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report L-23-061, Submittal of the Decommissioning Funding Status Reports2023-03-31031 March 2023 Submittal of the Decommissioning Funding Status Reports L-23-037, and Perry Nuclear Power Plant - Independent Spent Fuel Storage Installation Changes, Tests, and Experiments2023-03-29029 March 2023 and Perry Nuclear Power Plant - Independent Spent Fuel Storage Installation Changes, Tests, and Experiments L-23-066, Annual Notification of Property Insurance Coverage2023-03-21021 March 2023 Annual Notification of Property Insurance Coverage ML23066A2892023-03-14014 March 2023 Request for Threshold Determination Under 10 CFR 50.80 and 10 CFR 72.50 for an Amendment to the Voting Agreement ML23066A2592023-03-14014 March 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2, Davis Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 2024-02-02
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 9, 2013 Mr. Raymond A. Lieb, Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
SCHEDULE REVISION FOR SAFETY REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1, LICENSE RENEWAL APPLICATION (TAG NO ME4640)
Dear Mr. Lieb:
By letter dated August 27, 2010, FirstEnergy Nuclear Operating Company (FENOC) submitted an application pursuant to Title 10 of the Code of Federal Regulations (1 0 CFR)
Part 51 and 10 CFR Part 54, to renew operating license NPF-003 for the Davis-Besse Nuclear Power Station, Unit 1 (Davis-Besse), for review by the U.S. Nuclear Regulatory Commission (NRC) staff. This letter is to inform you of a change in the safety review schedule for the Davis-Besse license renewal review.
Enclosed is the NRC staff's revised safety review schedule for the Davis-Besse license renewal application (LRA). The schedule has been updated to reflect changes in the ACRS second subcommittee meeting and the final ACRS full committee meeting on the SER and includes to-be-determined (TBD) milestones. By letter dated October 8, 2013, FENOC requested to postpone the schedule in order to allow sufficient time to adequately assess the new cracks that were identified as part of routine inspections at the concrete shield building. In addition, this would also allow the identification of the potential impacts, if any, to the LRA.
The NRC will continue to follow established review procedures and the enclosed schedule to complete the reviews required by 10 CFR Part 54. For questions on the revised safety schedule, please contact Mr. Juan Uribe, Project Manager for the Davis-Besse LRA safety review, by telephone at 301-415-3809 or by e-mail at juan.uribe@nrc.gov .
.i~C Lubinsk~
1 Docket No. 50-346
Enclosure:
fi Ohn W Division of License Renewal Office of Nuclear Reactor Regulation Revised Safety Review Schedule cc w/encl: Listserv
October 9, 2013 Mr. Raymond A. Lieb, Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
SCHEDULE REVISION FOR SAFETY REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1, LICENSE RENEWAL APPLICATION (TAC NO ME4640)
Dear Mr. Lieb:
By letter dated August 27, 2010, FirstEnergy Nuclear Operating Company (FENOC) submitted an application pursuant to Title 10 of the Code of Federal Regulations (1 0 CFR)
Part 51 and 10 CFR Part 54, to renew operating license NPF-003 for the Davis-Besse Nuclear Power Station, Unit 1 (Davis-Besse), for review by the U.S. Nuclear Regulatory Commission (NRC) staff. This letter is to inform you of a change in the safety review schedule for the Davis-Besse license renewal review.
Enclosed is the NRC staff's revised safety review schedule for the Davis-Besse license renewal application (LRA). The schedule has been updated to reflect changes in the ACRS second subcommittee meeting and the final ACRS full committee meeting on the SER and includes to-be-determined (TBD) milestones. By letter dated October 8, 2013, FENOC requested to postpone the schedule in order to allow sufficient time to adequately assess the new cracks that were identified as part of routine inspections at the concrete shield building. In addition, this would also allow the identification of the potential impacts, if any, to the LRA.
The NRC will continue to follow established review procedures and the enclosed schedule to complete the reviews required by 10 CFR Part 54. For questions on the revised safety schedule, please contact Mr. Juan Uribe, Project Manager for the Davis-Besse LRA safety review, by telephone at 301-415-3809 or by e-mail at juan.uribe@nrc.gov.
Sincerely, IRA by Melanie Galloway for/
John W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-346
Enclosure:
Revised Safety Review Schedule cc w/encl: Listserv ADAMS Accession No.* ML13281A845 OFFICE PM:DLR/RPB BC:DLR/RPB1 LA: DLR/RPB2 D:DLR NAME JUri be YDiaz YEdmonds JLubinski DATE 10/9/13 10/9/13 10/9/13 10/9/13
DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION UPDATED SAFETY REVIEW SCHEDULE Schedule Actual Milestones Date Date Receive license renewal application (LRA) 08/30/2010 08/30/2010 Publish Federal Register Notice (FRN) -LRA receipt and 09/17/2010 09/20/2010 availability Publish FRN -LRA acceptability and opportunity for hearing 10/20/2010 10/25/2010 Public Meeting -license renewal process and environmental 11/04/2010 11/04/2010 seeping Deadline for filing hearing requests and petitions for intervention 12/24/2010 12/24/2010 Audit -seeping and screening methodology 01/24/2011 01/24/2011 Audit -aging management programs (AMPs) 02/14/2011 02/14/2011 Inspection -seeping, screening, and AMPs 04/2011 04/25/2011 Safety Requests for Additional Information (RAis) -Issued 04/29/2011 04/29/2011 Safety RAis -First Round Responses Received 05/30/2011 05/30/2011 Issue draft supplemental environmental impact statement 10/2013 (SEIS)
Public Meeting-draft SEIS 11/2013 End of comment period for the draft SEIS 12/2013 Issue safety evaluation report (SER) with open items(s) 7/2012 07/31/2012 Advisory Committee on Reactor Safeguards (ACRS) 09/19/2012 09/19/2012 subcommittee meeting on SER with open item(s)
Issue SER 9/2013 09/03/2013 ACRS second subcommittee meeting on SER TBD*
ACRS full committee meeting on SER TBD*
Issue final SEIS 6/2014 NRR Decision TBD*
Commission Decision (hearing pending) TBD*
ENCLOSURE
SUBJECT:
SCHEDULE REVISION FOR SAFETY REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION (LRA)
(TAC NO ME4640)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRarb Resource RidsNrrDirRapb Resource RidsNrrDirRasb Resource RidsNrrDirRerb Resource RidsNrrDirRpob Resource RidsNrrDraApla Resource EKeegan SCuadrado JUri be YDiaz DWrona BHarris, OGC EBrown AWang MMahoney DMclntyre, OPA VMitlyng,OPA TRiley,OCA EWilliamson, OGC RRihm, EDO JCameron, Rill