Schedule Revision for the Review of the Davis-Besse Nuclear Power Station License Renewal Application TAC No. ME4613)
ML15022A253
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 01/29/2015
From: Chris Miller
Division of License Renewal
To: Lieb R
FirstEnergy Nuclear Operating Co
Sayoc E, NRR/DLR/RPB1, 301-415-4084
References
TAC ME4613, TAC ME4640
Download: ML15022A253 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 29, 2015 Mr. Raymond A. Lieb, Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1, LICENSE RENEWAL APPLICATION (TAC NO.

ME4613 AND ME4640)

Dear Mr. Lieb:

By letter dated August 27, 2010, FirstEnergy Nuclear Operating Company submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating license NPF-003, for the Davis-Besse Nuclear Power Station, Unit 1 (Davis-Besse), for review by the U.S. Nuclear Regulatory Commission (NRC) staff. This letter is to inform you of a change in the review schedule for the Davis-Besse license renewal review.

Regarding the staffs safety review, the scheduled dates for the Advisory Committee on Reactor Safeguards (ACRS) second subcommittee meeting on the Safety Evaluation Report (SER) and the ACRS full committee meeting on the SER are revised from both TBD to June 26, 2015, and November 5, 2015, respectively. The safety review schedule is being revised to align the staffs ongoing review of safety open items with ACRS meeting availability.

Regarding the staffs environmental review, the scheduled date for Issue Final Supplemental Environmental Impact Statement (FSEIS) is revised from January 2015 to February 2015. The environmental review schedule is being revised because staff needs additional time to complete and issue the FSEIS.

Enclosed is the NRC staff's revised review schedule for the Davis-Besse license renewal application. If you have any questions related to the revised environmental schedule, please contact Elaine Keegan at 301-415-8517 or by e-mail at elaine.keegan@nrc.gov, or to the revised safety schedule, please contact Emmanuel Sayoc at 301-415-4084 or by e-mail at emmanuel.sayoc@nrc.gov.

Sincerely,

/RA/

Christopher G. Miller, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosure:

Revised Schedule cc w/encl: Listserv

ML15022A253

  • concurred via email OFFICE LA:DLR:RPB1*

PM:RPB2:DLR PM:RPB1:DLR BC:RPB2:DLR BC:RPB1:DLR D:DLR NAME YEdmonds EKeegan ESayoc BWittick YDiaz-Sanabria CMiller DATE 1/26/15 1/27/15 1/27/15 1/28/15 1/28/15 1/29/15

ENCLOSURE DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 LICENSE RENEWAL APPLICATION SCHEDULE REVISION Milestones Schedule Date Actual Date Receive license renewal application (LRA) 08/30/10 08/30/10 Publish Federal Register Notice (FRN) - LRA receipt and availability 09/17/10 09/20/10 Publish FRN - LRA acceptability and opportunity for hearing 10/20/10 10/25/10 Publish FRN - intent to conduct environmental scoping 10/20/10 10/28/10 Public Meeting - license renewal process and environmental scoping 11/04/10 11/04/10 Deadline for filing hearing requests and petitions for intervention 12/24/10 12/24/10 Environmental scoping periods ends 12/27/10 12/27/10 Audit - scoping and screening methodology 01/24/11 01/24/11 Audit - aging management programs (AMPs) 02/14/11 02/14/11 Audit - environmental 03/07/11 03/07/11 Inspection - scoping, screening, and AMPs 04/2011 04/25/11 Environmental Requests for Additional Information (RAIs) - Issued 04/08/11 02/23/11 Safety RAIs - Issued 04/29/11 04/29/11 Environmental RAIs - Response Received 05/13/11 03/23/11 Safety RAI - Responses Received 05/30/11 05/30/11 Issue safety evaluation report (SER) with open item(s) 07/2012 07/31/12 Advisory Committee on Reactor Safeguards (ACRS) subcommittee meeting on SER with open item(s) 09/19/12 09/19/12 Issue draft supplemental environmental impact statement (SEIS) 02/2014 02/26/14 Public Meeting - draft SEIS 03/2014 03/25/14 End of comment period for the draft SEIS 04/2014 04/21/14 Issue final SEIS 02/2015 Issue Supplemental SER 05/15 ACRS second subcommittee meeting on the SER 06/15 ACRS full committee meeting on the SER 11/15 Decision - Director, Office of Nuclear Reactor Regulation TBD Commission decision (hearing pending)

TBD

Letter to R. Lieb from C. Miller dated January 29, 2015

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1, LICENSE RENEWAL APPLICATION (TAC NO.

ME4613)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource Listserv Emmanuel.Sayoc@nrc.gov Elaine.Keegan@nrc.gov Richard.Plasse@nrc.gov Brian.Wittick@nrc.gov Yoira.Diaz-Sanabria@nrc.gov John.Lamb@nrc.gov David.McIntyre@nrc.gov Eva.Brown@nrc.gov Brian.Harris@nrc.gov Daniel.Kimble@nrc.gov Adam.Wilson@nrc.gov Jamnes.Cameron@nrc.gov Viktoria.Mitlyng@nrc.gov