Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 27,2011 Mr. Barry S. Allen, Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760

SUBJECT:

SCHEDULE REVISION FOR THE SAFETY REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION, LICENSE RENEWAL APPLICATION (TAC NO.

ME4640)

Dear Mr. Allen:

By letter dated August 27,2010, FirstEnergy Nuclear Operating Company (FENOC) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew Operating License NPF-003 for the Davis-Besse Nuclear Power Station, Unit 1 (Davis-Besse), for review by the U.S. Nuclear Regulatory Commission (NRC or the staff).

Enclosed is the NRC staffs revised safety review schedule for the Davis-Besse license renewal application (LRA). The staff has revised the review schedule due to the large number of open items (Ols) that could not be resolved within the original schedule. Reasons for the large number of open items include:

  • delay in responses to requests for additional information (RAls)
  • large number of follow-up RAls

Additionally, resolution of the Class 1 valves 01 will not occur until information on the fatigue analysis of the Class 1 valves is provided and reviewed by the staff. Your staff agreed to provide information on the fatigue analysis for the Class 1 valves on May 31, 2012, and this will delay the completion of the Safety Evaluation Report.

To support the revised schedule milestones, your responses to the staffs RAls must be complete and provided in a timely manner. After receiving the RAI responses, the staff will review and incorporate the responses into its safety review. The timeliness of your responses is necessary to maintain the schedule, and any delay could result in additional revisions to the enclosed schedule with the potential of leaving milestone schedule dates to be determined (TBD) until responses are received and appropriately factored into a new schedule. Any additional RAts that the staff requires beyond the date of this letter will be considered open items for the safety review. We request that you inform the NRC staff as early as possible should potential delays arise in your support of this schedule.

B.Allen - 2 We would like to emphasize that the NRC staff will make every effort to meet the revised schedule milestones. The NRC will continue to follow established review procedures and the enclosed schedule to complete the reviews required by 10 CFR Parts 54 and 51.

If you have any questions on the revised schedule, please contact Mr. Samuel Cuadrado de Jesus, Project Manager for the review of the Davis-Besse LRA safety review, by telephone at 301-415-2946 or bye-mail at samuel. cuadradodejesus@nrc.gov.

Sincerely, elanie A. Galloway, Acting Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosure:

As stated cc w/encl: Listserv

DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION UPDATED SAFETY REVIEW SCHEDULE Schedule Actual Milestones Date Date Receive license renewal application (LRA) 08/30/10 08/30/10 Publish Federal Register Notice (FRN) - LRA receipt and availability 09/17/10 09/20/10 Publish FRN - LRA acceptability and opportunity for hearing 10/20/10 10/25/10 Publish FRN - intent to conduct environmental scoping 10/20/10 10/28/10 Public Meeting - license renewal process and environmental scoping 11/04110 11/04/10 Deadline for filing hearing requests and petitions for intervention 12/24/10 12/24/10 Environmental scoping periods ends 12/27/10 12/27/10 Audit - scoping and screening methodology 01/24/11 01/24/11 Audit - aging management programs (AMPs) 02/14/11 02/14/11 Audit - environmental 03/07/11 03/07111 Inspection - scoping, screening, and AMPs 04/2011 04/25/11 Environmental Requests for Additional Information (RAls) - Issued 04/08/11 02/23/11 Environmental RAls - Responses Received 05/13/11 03/23/11 Safety RAls - Issued 04/29/11 04/29/11 Safety RAls - Responses Received 05/30/11 05/30/11 Issue draft supplemental environmental impact statement (SEIS) 01/2012 Public Meeting - draft SEIS 02/2012 End of comment period for the draft SEIS 04/2012 Issue safety evaluation report (SER) with open items(s) 03/09/2012 ACRS subcommittee meeting on SER with open item(s) 04/10/2012 Issue final SEIS 07/2012 Issue SER 10/2012 ACRS full committee meeting on SER 12/2012 NRR Decision TBD Commission Decision (hearing pending) TBD ENCLOSURE

ML11353A015 '"concurrence via e-mail OFFICE LA:DLRlRPB1'" PM:DLR/RPB1 BC:DLR/RPB2 BC:DLR/RPB1 NAME SFigueroa SCuadrado  ! DWrona DMorey DATE 12/20/11 12/21/11 12/21/11 12/21/11 OFFICE AD:DLR NAME MGalloway DATE 12/27/11

Letter to Barry S. Allen from Melanie A. Galloway dated December 27,2011

SUBJECT:

SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO.1, LICENSE RENEWAL APPLICATION (TAC NO. ME4613)

DISTRIBUTION:

E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource PCooper SCuadrado DMorey DWrona Almboden BHarris BHarris, OGC AWang MMahoney ICouret,OPA VMitlyng,OPA TReillY,OCA EWiliiamson,OGC RRihm, EDO JCameron, Rill