Schedule Revision and Project Manager Change for the Review of the Davis-Besse Nuclear Power Station License Renewal Application
ML15054A534
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 02/27/2015
From: Chris Miller
Division of License Renewal
To: Lieb R
FirstEnergy Nuclear Operating Co
Keegan E, 415-8517
References
TAC ME4613, TAC ME4640
Download: ML15054A534 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 27, 2015 Mr. Raymond A. Lieb, Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760

SUBJECT:

SCHEDULE REVISION AND PROJECT MANAGER CHANGE FOR THE REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION (TAC NOS. ME4613 and ME4640)

Dear Mr. Lieb:

By letter dated August 27, 2010, FirstEnergy Nuclear Operating Company submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 51 (10 CFR Part 51) and (10 CFR Part 54), to renew operating license NPF-003 for the Davis-Besse Nuclear Power Station, Unit 1 (Davis-Besse), for review by the U.S. Nuclear Regulatory Commission (NRC) staff. This letter is to inform you of a change in the environmental review schedule for the Davis-Besse license renewal review.

Regarding the staffs environmental review, by letter dated January 29, 2015, the staff issued a letter revising the environmental review schedule. This revision established a February 2015 issuance date for the final Supplemental Environmental Impact Statement (SEIS). Due to issues related to technical review of the SEIS, the staff needs additional time to complete the final SEIS. The new issuance date for the final SEIS is March 2015.

Enclosed is the NRC staff's revised review schedule for the Davis-Besse license renewal If you have any questions related to the revised environmental schedule, please application.

contact Elaine Keegan at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov.

In addition, this letter provides notification of a change to the Safety Project Manager assigned to Davis-Besse license renewal review. Effective March 2, 2015, Mr. Richard Plasse will be the Safety Project Manager for Davis-Besse.

All correspondence for the Project Manager associated with the safety review for the Davis-Besse license renewal should be sent to:

Mr. Richard Plasse, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-11F1 Washington, DC 20555 Mr. Richard Plasse may be reached at 301-415-1427 or by e-mail at Richard.Plasse@nrc.gov.

Sincerely,

/RA Jane E. Marshall/

Christopher G. Miller, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosure:

Revised Schedule cc w/encl: Listserv

ML15054A534

  • concurred via email OFFICE LA:DLR*

PM:RPB2:DLR BC:RPB2:DLR BC:RPB1:DLR D:DLR NAME IBetts EKeegan BWittick YDiaz-Sanabria CMiller (JMarshall for)

DATE 02/25/2015 2/27/15 2/27/15 2/27/15 2/27/15

ENCLOSURE DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 - LICENSE RENEWAL APPLICATION SCHEDULE REVISION Milestones Schedule Date Actual Date Receive license renewal application (LRA) 08/30/10 08/30/10 Publish Federal Register Notice (FRN) - LRA receipt and availability 09/17/10 09/20/10 Publish FRN - LRA acceptability and opportunity for hearing 10/20/10 10/25/10 Publish FRN - intent to conduct environmental scoping 10/20/10 10/28/10 Public Meeting - license renewal process and environmental scoping 11/04/10 11/04/10 Deadline for filing hearing requests and petitions for intervention 12/24/10 12/24/10 Environmental scoping periods ends 12/27/10 12/27/10 Audit - scoping and screening methodology 01/24/11 01/24/11 Audit - aging management programs (AMPs) 02/14/11 02/14/11 Audit - environmental 03/07/11 03/07/11 Inspection - scoping, screening, and AMPs 04/2011 04/25/11 Environmental Requests for Additional Information (RAIs) - Issued 04/08/11 02/23/11 Safety RAIs - Issued 04/29/11 04/29/11 Environmental RAIs - Response Received 05/13/11 03/23/11 Safety RAI - Responses Received 05/30/11 05/30/11 Issue safety evaluation report (SER) with open item(s) 07/2012 07/31/12 ACRS subcommittee meeting on SER with open item(s) 09/19/12 09/19/12 Issue SER 09/2013 09/03/13 Issue draft Supplemental Environmental Impact Statement (SEIS) 02/2014 02/26/14 Public Meeting - draft SEIS 03/2014 03/25/14 End of comment period for the draft SEIS 04/2014 04/21/14 Issue final SEIS 03/2015 Issue Supplemental SER 05/2015 ACRS second subcommittee meeting on SER 06/26/15 ACRS full committee meeting on SER 11/05/15 Decision - Director, Office of Nuclear Reactor Regulation TBD Commission decision (hearing pending)

TBD

Letter to R. Lieb from C. Miller dated February 27, 2015

SUBJECT:

SCHEDULE REVISION AND PROJECT MANAGER CHANGE FOR THE REVIEW OF THE DAVIS-BESSE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION (TAC NO. ME4613)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource Listserv Emmanuel.Sayoc@nrc.gov Elaine.Keegan@nrc.gov Richard.Plasse@nrc.gov Brian.Wittick@nrc.gov Yoira.Diaz-Sanabria@nrc.gov John.Lamb@nrc.gov David.McIntyre@nrc.gov Eva.Brown@nrc.gov Brian.Harris@nrc.gov Daniel.Kimble@nrc.gov Adam.Wilson@nrc.gov Jamnes.Cameron@nrc.gov Viktoria.Mitlyng@nrc.gov