|
---|
Category:Letter
MONTHYEARIR 05000461/20230042024-02-0202 February 2024 Integrated Inspection Report 05000461/2023004 ML23361A1572024-01-24024 January 2024 Audit Plan in Support of Review of License Amendment Request Regarding Revision of Technical Specifications Related to Reactor Water Cleanup Isolation ML24004A0792024-01-18018 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0041 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000461/20234022023-12-27027 December 2023 Security Baseline Inspection Report 05000461/2023402 ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 IR 05000461/20235012023-12-0505 December 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000461/2023501 ML23284A2512023-11-22022 November 2023 Amendment No. 250 to Adopt TSTF-332 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000461/20230032023-11-0808 November 2023 Integrated Inspection Report 05000461/2023003 ML22300A2212023-11-0202 November 2023 Preliminary Decommissioning Cost Estimate and Fuel Management Plan RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans IR 05000461/20233012023-09-12012 September 2023 NRC Initial License Examination Report 05000461/2023301 RS-23-090, Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2023-09-0707 September 2023 Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs IR 05000461/20234202023-08-29029 August 2023 Security Baseline Inspection Report 05000461/2023420 RS-23-081, Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2023-08-21021 August 2023 Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation IR 05000461/20230022023-08-0404 August 2023 Integrated Inspection Report 05000461/2023002 RS-23-085, Supplemental Information Related to Request for Partial Site Release2023-08-0303 August 2023 Supplemental Information Related to Request for Partial Site Release ML23209A8102023-07-28028 July 2023 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23198A0152023-07-27027 July 2023 License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23202A0992023-07-24024 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2023004 ML23200A2592023-07-24024 July 2023 June 27, 2023, Clinton Power Station License Renewal Environmental Pre-application Public Meeting-Meeting Summary IR 05000461/20234012023-07-19019 July 2023 Cyber Security Inspection Report 05000461/2023401 ML23194A1662023-07-19019 July 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Partial Site Release ML23191A8772023-07-11011 July 2023 Operator Licensing Examination Approval Clinton Power Station July 2023 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-073, Request for Partial Site Release2023-06-0707 June 2023 Request for Partial Site Release IR 05000461/20230102023-05-26026 May 2023 Triennial Fire Protection Inspection Report 05000461/2023010 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23143A3182023-05-23023 May 2023 Information Meeting (Open House) with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Clinton Power Station, Unit 1 IR 05000461/20230012023-05-0404 May 2023 Integrated Inspection Report 05000461/2023001 ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000461/20220062023-03-0101 March 2023 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2022006) RS-23-039, Request for License Amendment to Revise Technical Specifications Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air2023-03-0101 March 2023 Request for License Amendment to Revise Technical Specifications Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air ML23031A2972023-03-0101 March 2023 Issuance of Amendment No. 248 Adoption of TSTF-269, Revision 2 RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 ML23039A1852023-02-10010 February 2023 Integrated Inspection Report 05000461/2022004 07201046/2022001 RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000461/20220112023-01-27027 January 2023 Biennial Problem Identification and Resolution Inspection Report 05000461/2022011 RS-23-002, Application to Adopt TSTF-332, ECCS Response Time Testing2023-01-13013 January 2023 Application to Adopt TSTF-332, ECCS Response Time Testing ML23005A0682023-01-0505 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000461/2023010 ML22341A6042022-12-0808 December 2022 Confirmation of Initial License Examination IR 05000461/20224022022-12-0606 December 2022 Security Baseline Inspection Report 05000461/2022402 RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI 2024-02-02
[Table view] Category:Inspection Report
MONTHYEARIR 05000461/20230042024-02-0202 February 2024 Integrated Inspection Report 05000461/2023004 IR 05000461/20234022023-12-27027 December 2023 Security Baseline Inspection Report 05000461/2023402 IR 05000461/20235012023-12-0505 December 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000461/2023501 IR 05000461/20230032023-11-0808 November 2023 Integrated Inspection Report 05000461/2023003 IR 05000461/20233012023-09-12012 September 2023 NRC Initial License Examination Report 05000461/2023301 IR 05000461/20234202023-08-29029 August 2023 Security Baseline Inspection Report 05000461/2023420 IR 05000461/20230022023-08-0404 August 2023 Integrated Inspection Report 05000461/2023002 IR 05000461/20234012023-07-19019 July 2023 Cyber Security Inspection Report 05000461/2023401 IR 05000461/20230102023-05-26026 May 2023 Triennial Fire Protection Inspection Report 05000461/2023010 IR 05000461/20230012023-05-0404 May 2023 Integrated Inspection Report 05000461/2023001 IR 05000461/20220062023-03-0101 March 2023 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2022006) ML23039A1852023-02-10010 February 2023 Integrated Inspection Report 05000461/2022004 07201046/2022001 IR 05000461/20220112023-01-27027 January 2023 Biennial Problem Identification and Resolution Inspection Report 05000461/2022011 IR 05000461/20224022022-12-0606 December 2022 Security Baseline Inspection Report 05000461/2022402 IR 05000461/20224032022-11-28028 November 2022 Material Control and Accounting Program Inspection Report 05000461/2022403 (Public) IR 05000461/20220032022-11-10010 November 2022 Integrated Inspection Report 05000461/2022003 IR 05000461/20220052022-08-22022 August 2022 Updated Inspection Plan for Clinton Power Station (Report 05000461/2022005) IR 05000461/20220022022-07-27027 July 2022 Integrated Inspection Report 05000461/2022002 IR 05000461/20220102022-06-0606 June 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000461/2022010 IR 05000461/20224012022-05-24024 May 2022 Security Baseline Inspection Report 05000461/2022401 IR 05000461/20220012022-04-28028 April 2022 Integrated Inspection Report 05000461/2022001 IR 05000461/20223012022-04-13013 April 2022 NRC Initial License Examination Report 05000461/2022301 IR 05000461/20210062022-03-0202 March 2022 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2021006) IR 05000461/20210042022-02-0404 February 2022 Integrated Inspection Report 05000461/2021004 IR 05000461/20215012022-01-0303 January 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000461/2021501 IR 05000461/20210032021-10-29029 October 2021 Integrated Inspection Report 05000461/2021003 IR 05000461/20210132021-09-0303 September 2021 Temporary Instruction Report 05000461/2021013 IR 05000461/20210052021-09-0101 September 2021 Updated Inspection Plan for Clinton Power Station; Report 05000461/2021005 IR 05000461/20214022021-08-23023 August 2021 Security Baseline Inspection Report 05000461/2021402 IR 05000461/20210112021-08-20020 August 2021 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000461/2021011 IR 05000461/20210022021-08-0909 August 2021 Integrated Inspection Report 05000461/2021002 IR 05000461/20214402021-07-15015 July 2021 Supplemental Inspection Report 05000461/2021440 and Assessment Follow Up Letter (Cover Letter Only) IR 05000461/20210122021-06-28028 June 2021 Biennial Problem Identification and Resolution Inspection Report 05000461/2021012 IR 05000461/20213012021-04-29029 April 2021 NRC Initial License Examination Report 05000461/2021301 IR 05000461/20214012021-04-29029 April 2021 Security Baseline Inspection Report 05000461/2021401 (Cover Letter Only) IR 05000461/20210012021-04-26026 April 2021 Integrated Inspection Report 05000461/2021001 IR 05000461/20210102021-03-18018 March 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000461/2021010 IR 05000461/20200102021-03-11011 March 2021 Triennial Fire Protection Inspection Report 05000461/2020010 IR 05000461/20200062021-03-0404 March 2021 Annual Assessment Letter for Clinton Power Station Unit 1 (Report 05000461/2020006) IR 05000461/20200042021-02-0909 February 2021 Integrated Inspection Report 05000461/2020004; 07201046/2020001 IR 05000461/20204022020-11-19019 November 2020 Security Baseline Inspection Report 05000461/2020402 IR 05000461/20204202020-11-13013 November 2020 Security and Incident Response Inspection Report 05000461/2020420 ML20314A0952020-11-13013 November 2020 Security Inspection Report 05000461/2020420 Cover Letter - IP 92707 IR 05000461/20200032020-11-0909 November 2020 Integrated Inspection Report 05000461/2020003 IR 05000461/20204042020-11-0202 November 2020 EA-20-004 Clinton Power Station - Final Significance Determination for a Security-Related Preliminary Greater than Green Finding with Assessment Follow-Up; NRC Security Inspection Report 05000461/2020404 IR 05000461/20204032020-09-0303 September 2020 Special Inspection Report 05000461/2020403 and Preliminary Greater than Green (Cover Letter Only) IR 05000461/20200052020-09-0101 September 2020 Updated Inspection Plan for Clinton Power Station, Unit 1 (Report 05000461/2020005) IR 05000461/20200022020-08-11011 August 2020 Integrated Inspection Report 05000461/2020002 IR 05000461/20200012020-05-13013 May 2020 Integrated Inspection Report 05000461/2020001 IR 05000461/20204012020-03-0505 March 2020 Security Baseline Inspection Report 05000461/2020401 (Cover Letter Only) 2024-02-02
[Table view] |
See also: IR 05000461/2010402
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE ROAD, SUITE 210
LISLE, IL 60532-4352
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
March 11, 2010
Mr. Charles G. Pardee
Senior Vice President, Exelon Generation Company, LLC
President and Chief Nuclear Officer (CNO), Exelon Nuclear
4300 Winfield Road
Warrenville IL 60555
SUBJECT: CLINTON POWER STATION
NRC SECURITY BASELINE INSPECTION REPORT 05000461/2010402(DRS)
Dear Mr. Pardee:
On February 4, 2010, the U. S. Nuclear Regulatory Commission (NRC) completed a security
baseline inspection at your Clinton Power Station. The inspection covered one or more of the
key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The
enclosed inspection report documents the inspection results, which were discussed on
February 4, 2010, with Mr. F. A. Kearney and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and
compliance with the Commissions rules and regulations and with the conditions of your license.
The inspector reviewed selected procedures and records, observed activities, and interviewed
personnel.
No findings of significance were identified.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be
available electronically for public inspection in the NRC Public Document Room or from the
Publicly Available Records System (PARS) component of NRC's Agencywide Documents
Access and Management System (ADAMS), accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
However, because of the security-related concerns contained in the enclosure, and in
accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public
inspection.
Enclosure contains Sensitive Unclassified
Non-Safeguards Information. When separated
from enclosure, this transmittal document is
decontrolled.
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
C. Pardee -2-
Should you have any questions concerning this inspection, we will be pleased to discuss them
with you.
Sincerely,
/RA/
Eric Duncan, Chief
Plant Support Branch
Division of Reactor Safety
Docket Nos. 50-461
License Nos. NPF-62
Nonpublic Enclosure: Inspection Report 05000461/2010402(DRS)
w/Attachment: Supplemental Information
cc w/encl: S. Coker, NSIR/DSO/DDSO/ST
C. Williamson, Clinton Station Security Manager
J. Klinger, State Liaison Officer
Illinois Emergency Management Agency
cc w/o encl: Distribution via ListServ
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
C. Pardee -2-
Should you have any questions concerning this inspection, we will be pleased to discuss
them with you.
Sincerely,
/RA/
Eric Duncan, Chief
Plant Support Branch
Division of Reactor Safety
Docket Nos. 50-461
License Nos. NPF-62
Nonpublic Enclosure: Inspection Report 05000461/2010402(DRS)
w/Attachment: Supplemental Information
cc w/encl: S. Coker, NSIR/DSO/DDSO/ST
C. Williamson, Clinton Station Security Manager
J. Klinger, State Liaison Officer
Illinois Emergency Management Agency
cc w/o encl: Distribution via ListServ
DISTRIBUTION:
Susan Bagley
RidsNrrDorlLpl3-2 Resource
RidsNrrPMClinton Resource
RidsNrrDirsIrib Resource
Cynthia Pederson
Steven Orth
Jared Heck
Allan Barker
Carole Ariano
Linda Linn
DRSIII
DRPIII
Patricia Buckley
Tammy Tomczak
ROPreports Resource
DOCUMENT NAME: G:\DRS\Work in Progress\CLI 2010 402 DRS OUO - Cover Letter.doc
Publicly Available Non-Publicly Available Sensitive Non-Sensitive
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE RIII RIII RIII
NAME TEck:co DFunk ED for EDuncan
DATE 03/10/10 03/11/10 03/11/10
OFFICIAL RECORD COPY
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION