Letter Sequence RAI |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
Results
Other: ML070370281, ML073100027, ML073510180, ML080360067, ML080430700, ML080500171, ML080530256, ML081010450, ML081010451, ML081120502, ML081700294, ML081720078, ML081760295, ML082040065, ML082050462, ML082100425, ML082810470, ML083120308, ML083240224, ML083250083, ML090130718, ML090340528, ML090720951, ML090760630, ML091320366, ML092020345, ML092430520, ML092440518, ML092460495, ML092460496, ML092460497, ML092460498, ML092460500, ML092540483, ML092680057, ML12319A076, ML13044A498
|
MONTHYEARML0711503712007-04-24024 April 2007 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Steam Dryer Evaluations Project stage: Request ML0712905652007-05-16016 May 2007 Withholding Information from Public Disclosure, Response to Nuclear Regulatory Commission (NRC) Request for Additional Information - Round 12 for Browns Ferry EPU: Supplemental to SBWB-64 Project stage: RAI ML0716303492007-06-15015 June 2007 Meeting with the Tennessee Valley Authority Concerning the Status of Browns Ferry Nuclear Plant, Units 1, 2 and 3, Steam Dryer Review Project stage: Meeting ML0718700242007-07-0303 July 2007 Technical Specifications (TS) Change TS-461 - Modification of Restart Large Transient Testing License Condition 2. (G) 2 - Supplement 1 Project stage: Request ML0717801902007-07-0505 July 2007 Request for Additional Information for Extended Power Uprate - Round 13 (TS-431 and TS-418 (TAC Nos. MD5262, MD5263, and MD5264) Project stage: RAI ML0719004762007-07-10010 July 2007 Meeting with the Tennessee Valley Authority (TVA) Concerning the Pending ACRS Meeting on the Browns Ferry Extended Power Uprate Project stage: Meeting ML0721501562007-07-18018 July 2007 Slides from Meeting with Tennessee Valley Authority on the Browns Ferry Power Uprate ACRS Presentation Project stage: Meeting ML0721303712007-07-27027 July 2007 Technical Specifications Changes TS-431 and TS-418, Extended Power Uprate - Steam Dryer Evaluations Project stage: Request ML0721400442007-08-0808 August 2007 Summary of Meeting with Tennessee Valley Authority on the Browns Ferry Power Uprate ACRS Presentation Project stage: Meeting ML0724805472007-08-31031 August 2007 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 13 Request for Additional Information (RAI) - Containment Overpressure Project stage: Request ML0727606602007-10-0909 October 2007 Request for Additional Information for Extended Power Uprate - Round 14 (TS-418) Project stage: RAI ML0728902372007-10-18018 October 2007 Request for Withholding Information from Public Disclosure Concerning Round 13 Request for Additional Information for Browns Ferry Nuclear Plant (Tac Nos. MD5262, MD5263 and MD5264) Project stage: RAI ML0729603112007-10-22022 October 2007 Technical Specification (TS) Changes TS-431 & TS-418, Extended Power Uprate - EPU Large Transient Testing Project stage: Request ML0731000272007-11-0909 November 2007 Request for Schedule Regarding Analysis for Steam Dryers on Extended Power Uprate Amendment Requests (TAC Nos. MD5262, MD5263, and MD5264) (TS-431 and TS-418-S) Project stage: Other ML0732303482007-11-15015 November 2007 Units 1, 2, and 3 - Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 13 Request for Additional Information (RAI) - Containment Overpressure APLA-35/37 Project stage: Request ML0733304832007-11-21021 November 2007 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Preliminary Findings on Steam Dryer Stress Analysis Project stage: Request ML0735101802007-12-14014 December 2007 Technical Specifications Changes TS-431 and TS-418 - Extended Power Uprate - Schedule Regarding Analysis for Steam Dryers Project stage: Other ML0734607572007-12-19019 December 2007 Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear Plant (Tac No. MD5262, MD5263 and MD5264) Project stage: Withholding Request Acceptance ML0735400102008-01-25025 January 2008 Summary of Meeting with Tennessee Valley Authority on Steam Dryer Portion of the Extended Power Uprate Review (TAC Nos. MD5262, MD5263, and MD5264), Browns Ferry Units 1, 2, and 3 Project stage: Meeting ML0801504182008-01-25025 January 2008 Plants, Units 1, 2, and 3 - (Public Version) - Summary of December 10, 2007 Meeting with TVA on Steam Dryer Portion of the Extended Power Uprate Review Project stage: Meeting ML0803205212008-01-25025 January 2008 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) Response to Round 15 Request for Additional Information (RAI) - APLA-38/40, SRXB-71, and SRXB-72 Project stage: Request ML0803600672008-01-25025 January 2008 Steam Dryer RAI 15 Status, Slides Project stage: Other ML0802501652008-01-30030 January 2008 Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear Plant (Tac Nos. MD5262, MD5263, and MD5264) Project stage: Withholding Request Acceptance ML0803805602008-01-31031 January 2008 Technical Specifications (TS) Change TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 15 Request for Additional Information (RAI) Regarding Steam Dryer Analyses Project stage: Request ML0804307002008-02-11011 February 2008 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Schedule Regarding EPU Project stage: Other ML0803503812008-02-14014 February 2008 Summary of Meeting with Tennessee Valley Authority - on Extended Power Uprate Review Project stage: Meeting ML0805302562008-02-21021 February 2008 Unit 1 - Technical Specifications (TS) Change TS-431 - Extended Power Uprate (EPU) - Fuels Methods Commitments Project stage: Other ML0806501012008-02-21021 February 2008 Response to Round 16 Request for Additional Information SRXB-73 Project stage: Request ML0804506472008-02-27027 February 2008 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0803506982008-02-29029 February 2008 Request for Additional Information for Extended Power Uprate - Round 16 (TS-431 and TS-418) (TACs MD5262, MD5263, MD5264) Project stage: RAI ML0807104982008-03-0606 March 2008 (BFN) - Units 1, 2, and 3 - Technical Specifications (TS) Change TS-418 and TS-431 - Extended Power Uprate (EPU) - Response to Round 16 Request for Additional Information (RAI) - SRXB-74/86 and SRXB-87 Through SRXB-90 Project stage: Request ML0811205102008-03-20020 March 2008 Summary of March 20, 2008, Meeting with Tennessee Valley Authority Regarding Steam Dryer Portion of the Extended Power Uprate Review (TAC Nos. MD5262, MD5263, and MD5264) - Slides Project stage: Meeting ML0810104512008-04-0404 April 2008 Technical Specifications (TS) Changes TS-431 and TS-418 Extended Power Uprate (EPU) BFN Steam Monitoring Plan Project stage: Other ML0810104502008-04-0404 April 2008 (BFN) - Units 1, 2, and 3 - Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 15 and Round 16 Requests for Additional Information (RAI) Regarding Steam Dryer Analyses Project stage: Other ML0817602952008-04-0909 April 2008 Units 1, 2, & 3 - Technical Specifications Changes TS-431 and TS-418 - Extended Power Uprate - Confirmation of Commitment Completions Project stage: Other ML0811205022008-04-16016 April 2008 CDI Incoming Letter Dated April 16, 2008 Regarding NRC Presentation Entitled, Tennessee Valley Authority Browns Ferry Nuclear Plant - Extended Power Uprate Steam Dryers. Project stage: Other ML0811302312008-04-17017 April 2008 Public Slides - Summary of April 17, 2008, Meeting Regarding Steam Dryer Portion of the Extended Power Uprate Review, Project stage: Meeting ML0811200332008-04-30030 April 2008 Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Withholding Information from Public Disclosure for Round 15 Fuels Responses Project stage: Withholding Request Acceptance ML0812806272008-05-0101 May 2008 Technical Specifications Change TS-418, Extended Power Uprate Supplemental Response to Round 16 Request for Additional Information - SRXB-87 & SRXB-89 Project stage: Supplement ML0813502222008-05-0202 May 2008 Request for Additional Information for Extended Power Uprate - Round 17 (TS-431 and TS-410) Project stage: RAI ML0805001712008-05-0202 May 2008 - Schedule Regarding Analysis for Steam Dryers on Extended Power Uprate Amendment Requests (TAC Nos. MD5262, MD5263, and MD5264) (TS-431 and TS-418) Project stage: Other ML0812804712008-05-0202 May 2008 Request for Additional Information for Extended Power Uprate - Round 17 Project stage: RAI ML0813602912008-05-22022 May 2008 Summary of April 17, 2008, Meeting Regarding Steam Dryer Portion of the Extended Power Uprate Review Project stage: Meeting ML0815805532008-05-22022 May 2008 Summary of 5/22/08 Meeting Regarding Containment Overpressure Portion of the Extended Power Uprate Review - Browns Ferry - Handouts Project stage: Meeting ML0810604452008-06-0202 June 2008 Request for Withholding Information from Public Disclosure for Partial Round 13 Responses (Tacs. MD5262, MD5263 and MD5264) Project stage: Withholding Request Acceptance ML0810606162008-06-0202 June 2008 Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear Plant Project stage: Withholding Request Acceptance ML0810607222008-06-0202 June 2008 Request for Withholding Information from Public Disclosure for Partial Response to Round 13 Project stage: Withholding Request Acceptance ML0816403252008-06-0303 June 2008 Units 2 & 3 - Technical Specifications Change TS-418 - Extended Power Uprate - Supplemental Response to Round 16 Request for Additional Information - SRXB-88 Project stage: Supplement ML0812607122008-06-0505 June 2008 Summary of Meeting with TVA Steam Dryer Portion of the Extended Power Uprate Review Project stage: Meeting ML0817002942008-06-12012 June 2008 Technical Specifications Changes TS-431 and TS-418 - Extended Power Uprate - Response to ACRS Conclusions and Recommendations Regarding Containment Overpressure Credit Project stage: Other 2008-01-30
[Table View] |
|
---|
Category:Letter
MONTHYEARML24032A4762024-02-0101 February 2024 Final Report of a Part 21 Evaluation Associated with Starter Contactors for the BFN Unit 1 High Pressure Coolant Injection Suppression Pool Inboard Suction Valve ML24023A2802024-01-23023 January 2024 Final Report of a Deviation or Failure to Comply Associated with a Relay in the Reactor Core Isolation Cooling Condensate Pump CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24016A3042024-01-16016 January 2024 Final Report of a Part 21 Evaluation Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump CNL-23-071, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-472024-01-11011 January 2024 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-47 ML24022A1732024-01-0303 January 2024 Receipt and Availability of the Subsequent License Renewal Application ML23319A1992024-01-0303 January 2024 Issuance of Amendment Nos. 333, 356, and 316 Regarding the Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves ML23355A2062023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23348A3942023-12-14014 December 2023 Interim Part 21 Report of a Potential Deviation or Failure to Comply Associated with Starter Contactors for the High Pressure Coolant Injection Suppression Pool Inboard Suction Valve IR 05000259/20230102023-12-11011 December 2023 Commercial Grade Dedication Inspection Report 05000259/2023010 and 05000260/2023010 and 05000296/2023010 ML23335A0722023-12-0101 December 2023 Interim Report of a Deviation or Failure to Comply Associated with a Relay in the Unit 2 Reactor Core Isolation Cooling Condensate Pump ML23334A2492023-11-30030 November 2023 Site Emergency Plan Implementing Procedure Revision CNL-23-070, Submittal of Fifth 10-Year Interval Inservice Testing Program Plan2023-11-29029 November 2023 Submittal of Fifth 10-Year Interval Inservice Testing Program Plan ML23331A2532023-11-27027 November 2023 Summary Report for 10 CFR 50.9 Evaluations, Technical Specifications Bases Changes, Technical Requirement Manual Changes, and NRC Commitment Revisions CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23325A1102023-11-21021 November 2023 Anchor Darling Double Disc Gate Valve Commitment Revision ML23320A2542023-11-16016 November 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump IR 05000259/20230032023-11-13013 November 2023 Integrated Inspection Report 05000259/2023003, 05000260/2023003 and 05000296/2023003 IR 05000259/20230402023-11-0202 November 2023 Supplemental Inspection Supplemental Report 05000259 2023040 and Follow-Up Assessment Letter ML23292A2532023-10-18018 October 2023 BFN 2024-301, Corporate Notification Letter (210-day Ltr) ML23282A0022023-10-0606 October 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump ML23278A0122023-10-0505 October 2023 Updated Final Safety Analysis Report, Amendment 30 ML23271A1702023-09-28028 September 2023 Site Emergency Plan Implementing Procedure Revision ML23270A0702023-09-26026 September 2023 SLRA Pre-Application Meeting Summary 09-13-2023 ML23257A1232023-09-22022 September 2023 Administrative Changes to Technical Specification Pages Issued for License Amendment Nos. 332, 355, and 315 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23263B1042023-09-20020 September 2023 Special Report 260/2023-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation ML23205A2132023-09-0808 September 2023 Issuance of Amendment Nos. 332, 355, and 315 Regarding the Revision of Technical Specifications to Adopt TSTF-566-A and TSTF-580-A, Rev. 1 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000259/20230052023-08-29029 August 2023 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023005, 05000260/2023005 and 05000296/2023005 ML23233A0432023-08-18018 August 2023 Enforcement Action EA-22-122 Inspection Readiness Notification ML23219A1542023-08-17017 August 2023 Request to Use Later Edition of ASME Code for Operation and Maintenance and Alternative Requests BFN-IST-01 Through 05 for the Fifth 10-Year Interval Inservice Testing Program ML23228A1642023-08-16016 August 2023 Site Emergency Plan Implementing Procedure Revision ML23228A0202023-08-15015 August 2023 (BFN) Unit 1 - Special Report 259/2023-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation IR 05000259/20230022023-08-10010 August 2023 Integrated Inspection Report 05000259/2023002, 05000260/2023002, 05000296/2023002 and 07200052/2023001 ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills ML23171A8862023-07-24024 July 2023 Issuance of Amend. Nos. 331, 354, and 314; 365 and 359 Regarding Adoption of TSTF-541-A, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML23201A2182023-07-20020 July 2023 Registration of Use of Cask to Store Spent Fuel (MPC-298 and -299) ML23159A2552023-07-20020 July 2023 Proposed Alternative to the Requirements of the ASME Code Regarding Volumetric Inspection of Standby Liquid Control Nozzles ML23199A3072023-07-18018 July 2023 Site Emergency Plan Implementing Procedure Revision CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions IR 05000259/20233012023-07-18018 July 2023 NRC Operator License Examination Report Nos. 05000259/2023301, 05000260/2023301, and 05000296/2023301 2024-02-01
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23332A0042023-11-27027 November 2023 NRR E-mail Capture - Request for Additional Information Related to Proposed Revised Alternative 0-ISI-47 ML23243A9892023-08-29029 August 2023 Inspection Information Request ML23124A0082023-05-0303 May 2023 NRR E-mail Capture - Request for Additional Information Related to Proposed Alternative Requests for the 5th 10-Year Inservice Testing Interval for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML23041A0022023-02-0909 February 2023 NRR E-mail Capture - Request for Additional Information Related to TVA Alternative Request BFN-0-ISI-32 (CNL-22-025) ML22299A0292022-10-26026 October 2022 NRR E-mail Capture - Request for Additional Information for Relief Request BFN-2-ISI-003 Re Weld Examination Coverage ML22292A2722022-10-19019 October 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Adopt TSTF-505 and TSTF-439 for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML22208A2172022-07-15015 July 2022 NRR E-mail Capture - Request for Additional Information Related to TVA Relief Request BFN-21-ISI-02 (CNL-21-081) ML22174A2722022-06-24024 June 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML22168A0802022-06-17017 June 2022 NRR E-mail Capture - Request for Confirmation of Information and Additional Information Related to Tva'S Request to Use Control Bay Chiller Cross-Tie ML22160A4742022-06-0303 June 2022 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Re LAR to Use Advanced Framatome Methodologies in Support of Atrium 11 Fuel ML22168A0392022-05-13013 May 2022 NRR E-mail Capture - Draft Request for Confirmation of Information and Additional Information Related to Tva'S Request to Use Control Bay Chiller Cross-Tie ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Revised the TVA Plants' Radiological Emergency Plans ML22047A1612022-02-16016 February 2022 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Expand the SFP Criticality Safety Analysis for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML22025A4132022-01-25025 January 2022 RP Inspection Doc Request ML21343A4232021-12-0909 December 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000259/2022010, 05000260/2022010, and 05000296/2022010) and Request for Information (RFI) ML21173A1042021-06-21021 June 2021 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Request to TS 3.8.6 ML21041A5422021-02-10010 February 2021 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Request to Adopt 10 CFR 50.69 ML21041A5432021-02-0505 February 2021 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Draft Request for Additional Information Regarding 10 CFR 50.69 LAR ML21026A1652021-01-26026 January 2021 Document Request for Browns Ferry Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021-02 ML20296A3782020-10-22022 October 2020 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Request to Incorporate TMRE ML20297A3012020-10-22022 October 2020 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Request to Adopt TSTF-425 ML20294A3762020-09-23023 September 2020 NRR E-mail Capture - Draft Request for Additional Information - Browns Ferry Nuclear Plant, Units 1, 2, and 3, Request to Adopt TSTF-425 ML20266G4472020-09-22022 September 2020 Notification of Inspection and Request for Information ML20224A4732020-08-11011 August 2020 Requalification Program Inspection Browns Ferry Nuclear ML20195B1302020-07-13013 July 2020 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Alternative Request No. 0-ISI-47 ML20149K3212020-05-27027 May 2020 RP Inspection Document Request, Browns Ferry 2020-003 ML20254A3032020-05-13013 May 2020 Request for Supporting Information for the Browns Ferry, Units 1, 2, and 3 Seismic Probabilistic Risk Assessment Audit Review ML20054B8592020-02-20020 February 2020 Emergency Preparedness Program Inspection Request for Information ML20014E6552020-01-14014 January 2020 01 RP Inspection Document Request ML19196A0752019-07-12012 July 2019 NRR E-mail Capture - Final RAIs Browns Ferry Nuclear, Units 1, 2, 3 - Application to Revise Technical Specifications to Adopt TSTF-542 Revision 2, Reactor Pressure Vessel Water Inventory Control ML19116A0712019-06-0303 June 2019 Request for Additional Information Related Resubmittal of Proposed Alternative Request No. 1-ISI-27 for the Period of Extended Operation ML18331A5442018-12-0606 December 2018 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus License Amendment Request (EPID L-2018-LLA-0048) - (Non-Proprietary) ML18317A1642018-11-20020 November 2018 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus License Amendment Request (EPID L-2018-LLA-0048) - Non-Proprietary ML18263A1412018-09-11011 September 2018 NRR E-mail Capture - Browns Ferry Unit 1: RAI Associated with Relief Request 1-ISI-28 ML18138A1102018-05-17017 May 2018 Enclosurequest for Additional Information (Letter to E. D. Schrull Request for Additional Information Regarding Tennessee Valley Authority'S Decommissioning Funding Plan Update for Browns Ferry and Sequoyah Isfsis) ML18108A1872018-04-18018 April 2018 Information Request for the Cyber-Security Baseline Security Inspection, Notification to Perform Inspection 05000259/2018411, 05000260/2018411, and 05000296/2018411 ML18057A6372018-02-23023 February 2018 NRR E-mail Capture - Request for Additional Information Related to TVA Fleet Topical Report TVA-NPG-AWA16 - EPIC: L-2016-TOP-0011) ML17216A0062017-08-18018 August 2017 Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Related to LAR to Revise Modifications and Implementations Related to NFPA 805 for Fire Protection for Light Water Reactor Generating Plants (CAC Nos. MF9814-MF9816) ML17163A0502017-06-0808 June 2017 NRR E-mail Capture - RAI for Browns Ferry RR 3-ISI-28 CAC No. MF9257 ML17150A0792017-05-23023 May 2017 NRR E-mail Capture - Request for Additional Information Related to TVA Fleet LAR for EAL Change to Adopt NEI-99-01 Rev.6 (CAC Nos. MF9054 - MF9060) ML16288A0182016-10-27027 October 2016 Browns Ferry Nuclear Plant, Units 2 and 3 - RAI Related to Relief Request for the Use of Alternatives to Certain American Society of Mechanical Engineers, Boiler and Pressure Vessel Code, Section XI Requirements (CAC Nos. MF7795 and MF7796) ML16236A0732016-08-31031 August 2016 Request for Additional Information Related to License Amendment Request to Add New Technical Specification 3.3.8.3 ML16203A0272016-07-25025 July 2016 Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Related to License Amendment Request for Adding New Specifications to Technical Specification 3.3.8.3 (CAC Nos. MF6738, MF6739, and MF6740) ML16187A2932016-07-21021 July 2016 Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate (CAC Nos. MF6741, MF6742, and MF6743) ML16194A2292016-07-21021 July 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate ML16154A5442016-06-21021 June 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate ML16146A6352016-06-13013 June 2016 Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate ML16145A1582016-06-0303 June 2016 Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate (SBPB-RAI 4) (CAC Nos. MF6741, MF6742, and MF6743) ML16144A6452016-06-0303 June 2016 Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Non-proprietary Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate (EMCB-RAI) ML16119A1332016-05-0606 May 2016 Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate (SNPB-RAI) (CAC Nos. MF6741, MF6742, and MF6743) 2023-08-29
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 9,2009 Mr. Preston D. Swafford Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
BROWNS FERRY NUCLEAR PLANT, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION FOR EXTENDED POWER UPRATE - ROUND 24 (TAC NO. MD5262) (TS-431)
Dear Mr. Swafford:
By letter dated June 28,2004, the Tennessee Valley Authority (TVA, the licensee) submitted an amendment request for Browns Ferry Nuclear Plant (BFN), Unit 1, as supplemented by letters dated August 23, 2004, February 23, April 25, June 6, December 19, 2005, February 1 and 28, March 7, 9, 23, and 31, April 13, May 5,15, and 16, June 15, 23, and 27, July 6,21,26, and 31, August 4, 16, 18, and 31, September 1, 15, and 22, October 3, 5, and 13, November 7, December 1,5,11, and 21,2006, January 31, February 16 and 26, April 6, 18, and 24, July 27, September 24, November 15 and 21, December 14, 2007, January 25 and 31, February 11 and 21, March 6, April 4 and 9, May 1, June 3,12, and 16, August 15, September 2 and 19, October 3,17, and 31, November 11 and 14, December 15, 2008, January 9,16, and 23, February 18 and 24, March 11, 12, and 27, April 3, 10, 21, and 29, and May 7, 2009. The proposed amendment would change the BFN operating license for Unit 1 to increase the maximum authorized power level by approximately 15 percent.
Enclosed is a non-proprietary version Request for Additional Information (RAI). A proprietary version of the RAI was provided in separate correspondence. Your response to our RAI is needed before the Nuclear Regulatory Commission staff can complete the review. This request was discussed with Mr. Denzel Housely of your staff on May 20, 2009, and it was agreed that TVA would respond by June 5,2009.
If you have any questions, please contact me at (301) 415-2315.
Sincerely, IRA!
Eva A. Brown, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-259
Enclosure:
RAI Non-Proprietary Version cc w/enclosure: Distribution via ListServ
REQUEST FOR ADDITIONAL INFORMATION EXTENDED POWER UPRATE ROUND 24 TENNESSEE VALLEY AUTHORITY (TVA)
BROWNS FERRY NUCLEAR PLANT UNIT 1 DOCKET NO. 50- 259 EMCB (Unit 1 only) 208. It appears that the main steam line (MSL) strain gage measurements in Unit 1 were reduced by subtracting:
((
1]
In Enclosure 3 of a letter dated July 27, 2007, the licensee provide acoustic circuit model (ACM), Rev. 4 (described in Continuum Dynamics Incorporated (CDI) Report 07-09P, Rev. 0), which was benchmarked using Quad Cities 2 (QC2) MSL and steam dryer measurements. The licensee used the QC2 benchmark data to compute the frequency dependent bias errors and uncertainties for Unit 1.
((
II Address the apparent inconsistency with the conclusion that the CDI 07-09 bias and uncertainties are conservative [1.=[= = = = = = = = = = = = = = = = = =
11 209. While conducting the steam dryer inspections during the Unit 2 Cycle 15 refueling outage, the licensee found the TB-3/4-01, TB-3/4-02, and TB-3/4-03 tie bars to be broken. The inspections also revealed that the TB-5/6-01, TB-5/6-02, and TB-1/2-02 tie bars were bent. Deformation of the center divider plate between banks 3 and 4 was also observed by the licensee. In addition, crack-like indications were noted on the TB-4/5-02 and TB-1/2-01 tie bars. This recent operating experience provides an
-2 opportunity to confirm the accuracy of the current approach of dynamic stress analysis of boiling-water reactor steam dryer using the ACM Revision 4 to predict the dryer pressure loading for each planned dryer configuration for the three Browns Ferry units.
Therefore, TVA is requested to provide a Unit 2 dryer stress analysis for the existing dryer configuration, based on the dryer pressure loading for the current licensed thermal power [105 percent original licensed thermal power], as predicted by the ACM Rev. 4 Code, in order to demonstrate the analytical predictability of the above noted deformations of the tie bars and the center divider plate, as well as failures of certain tie bars.
- ML091380530 NRR-088 OFFICE LPL2-2/PM LPL2-2/LA DElEMCB/BC LPL2-2/BC NAME EBrown BClayton MKhanna TBoyce DATE 06/09/09 06/03/09 06/3109 06/09/09