Revised Schedule for Extended Power Uprate Amendment Request Review
ML092540483
Person / Time
Site: Browns Ferry  
Issue date: 09/18/2009
From: Leeds E
Plant Licensing Branch II
To: Swafford P
Tennessee Valley Authority
Brown E, NRR/DORL, 415-2315
References
TAC MD5262, TAC MD5263, TAC MD5264, TS-431
Download: ML092540483 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 18, 2009 Mr. Preston D. Swafford Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801

SUBJECT:

BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3 - REVISED SCHEDULE FOR EXTENDED POWER UPRATE AMENDMENT REQUEST REVIEW (TAC NOS. MD5262, MD5263, AND MD5264) (TS-431)

Dear Mr. Swafford:

This letter is to inform you of the decision of the U.S. Nuclear Regulatory Commission (NRC) to delay the review of the Browns Ferry Nuclear Plant (BFN) Unit 1 and Units 2 and 3 applications extended power uprate requests dated June 28 and June 24, 2009, respectively. As you are aware, in a Staff Requirements Memorandum dated January 8, 2009, the Commission directed the Office of Nuclear Reactor Regulation (NRR) staff to continue to work towards resolving concerns regarding the application of containment accident pressure (CAP) credit by the Advisory Committee on Reactor Safeguards (ACRS).

On March 18, 2009, the ACRS issued a letter to NRC staff providing recommendations to facilitate resolution of their CAP concerns. The NRC staff responded to the ACRS on June 4, 2009. As a part of that response, NRC staff indicated that we may consider a delay in issuance of licensing actions that use CAP while resolving the CAP issues.

On July 16, 2009, your staff chose to answer the recommendations made to the NRC staff for the BFN units. During the August 11, 2009, public meeting various options were discussed to support completion of the technical review. The NRR staff has reviewed all the proposed options and the ACRS' recommendations. As was discussed with your staff on September 11, 2009, the NRC has determined that additional time is warranted to develop additional regulatory guidance to ensure the technical adequacy of the BFN extended power uprate (EPU) submittals. The development of this guidance is essential to provide the technical and regulatory consistency as well as the schedule certainty needed to complete this review.

Therefore, the NRC staff will be focused on closing out the other outstanding technical issues associated with the steam dryers and fire protection for the applications. Once appropriate guidance has been completed, the NRR staff will coordinate with your staff the remaining information needed to support completion of the EPU reviews. As indicated during the conference call, it is expected that the guidance will be available in the spring of 2010.

P. Swafford

- 2 Should you have any additional questions, please feel free to contact the Browns Ferry Project Manager, Ms. Eva Brown at (301) 415-2315.

Sincerely, Eric J. L ds, Director Office of Nuclear Reactor Regulation Docket No. 50-259, 50-260, and 50296 cc: Distribution via Listserv

P. Swafford

- 2 Should you have any additional questions, please feel free to contact the Browns Ferry Project Manager, Ms. Eva Brown at (301) 415-2315.

Sincerely, IRA!

Eric J. Leeds, Director Office of Nuclear Reactor Regulation Docket No. 50-259, 50-260, and 50-296 cc: Distribution via Listserv cc: Distribution via Listserv Distribution PUBLIC RidsNrrAdro RidsNrrOd LPL2-2 RlF RidsNrrAdes TAlexion RidsNrrDorlLpl2-2 RidsNrrDe RLobel RidsNrrPMbrownsFerry RidsNrrDss TRoss, RII RidsAcrsAcnw_MailCTR RidsNrrDorl MStutzke, RES RidsOgcRp RidsNrrDra DDiaz-Toro, EDO RidsRgn2MailCenter RidsNrrDssScvb MRubin RidsNrrDraAfpb RidsNrrDraApla PQualls, RIV RidsNrrLABClayton (Hard Copy)

SLingam RNease, RII ADAMS Accession No' ML092540483 NRR-106 OFFICE LPL2-2/PM LPL-WB/LA LPL2-2/BC DSS/D CA)

DORL\\D NRR/D NAME EBrown BClayton EBrown for TBoyce SBahadur JGiitter ELeeds DATE 09/11/09 09/11/09 09/11/09 09/11/09 09/11/09 09/18/09 OFFICIAL RECORD COpy