ML083290215

From kanterella
Jump to navigation Jump to search
IR 05000334-08-008, 05000412-08-008, on 09/15/2008 - 10/10/2008, Beaver Valley Power Station; Component Design Bases Inspection
ML083290215
Person / Time
Site: Beaver Valley
Issue date: 11/24/2008
From: Doerflein L
Engineering Region 1 Branch 2
To: Sena P
FirstEnergy Nuclear Operating Co
References
IR-08-008
Download: ML083290215 (35)


See also: IR 05000334/2008008

Text

November 24, 2008

Mr. Peter P. Sena, III

Site Vice President

FirstEnergy Nuclear Operating Company

Beaver Valley Power Station

Mail Stop A-BV-SEB1

P. O. Box 4, Route 168

Shippingport, PA 15077

SUBJECT: BEAVER VALLEY POWER STATION- NRC COMPONENT DESIGN BASES

INSPECTION REPORT 05000334/2008008 AND 05000412/2008008

Dear Mr. Sena:

On October 10, 2008, The U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at the Beaver Valley Power Station (BVPS) Units 1 and 2. The enclosed inspection

report documents the inspection results, which were discussed on October 10, 2008, with you

and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

In conducting the inspection, the team examined the adequacy of selected components and

operator actions to mitigate postulated transients, initiating events, and design basis accidents.

The inspection involved field walkdowns, examination of selected procedures, calculations and

records, and interviews with station personnel.

This report documents one NRC-identified finding which was of very low safety significance

(Green). The finding was determined to involve a violation of NRC requirements. However,

because of the very low safety significance of the violation and because it was entered into your

correction action program, the NRC is treating it as a non-cited violation (NCV) consistent with

Section VI.A.1 of the NRC Enforcement Policy. If you contest the NCV in this report, you should

provide a response within 30 days of the date of this inspection report, with the basis for your

denial, to the U. S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, D.C. 20555-0001, with copies to the Regional Administrator, Region I; the

Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, D.C.

20555-0001; and the NRC Resident Inspectors at the Beaver Valley Power Station.

P. Sena 2

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter, its

enclosure, and your response (if any) will be available electronically for the public inspection in

the NRC Public Docket Room or from the Publicly Available Records component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Lawrence T. Doerflein, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-334, 50-412

License No. DPR-66, NPF-73

Enclosure: Inspection Report 05000334/2008008 and 05000412/2008008

w/Attachment: Supplemental Information

P. Sena 2

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter, its

enclosure, and your response (if any) will be available electronically for the public inspection in

the NRC Public Docket Room or from the Publicly Available Records component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Lawrence T. Doerflein, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-334, 50-412

License No. DPR-66, NPF-73

Enclosure: Inspection Report 05000334/2008008 and 05000412/2008008

w/Attachment: Supplemental Information

SUNSI Review Complete: LTD (Reviewers Initials) ADAMS ACC#ML083290215

DOCUMENT NAME: T:\DRS\Engineering Branch 2\Mangan\BeaverValley2008CDBIreport.doc

After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure

"N" = No copy

OFFICE RI/DRS RI/DRS RI/DRP RI/DRS

NAME KMangan/DS/KM CCahill/CGC RBellamy/RB LDoerflein/LTD

DATE 11/10/08 11/10/08 11/21/08 11/24/08

OFFICIAL RECORD COPY

P. Sena 3

cc w/encl:

J. Hagan, President and Chief Nuclear Officer

J. Lash, Senior Vice President of Operations and Chief Operating Officer

D. Pace, Senior Vice President, Fleet Engineering

K. Fili, Vice President, Fleet Oversight

P. Harden, Vice President, Nuclear Support

G. Halnon, Director, Fleet Regulatory Affairs

Manager, Fleet Licensing Company

K. Ostrowski, Director, Site Operations

E. Hubley, Director, Maintenance

M. Manoleras, Director, Engineering

R. Brosi, Director, Site Performance Improvement

C. Keller, Manager, Site Regulatory Compliance

D. Jenkins, Attorney, FirstEnergy Corporation

M. Clancy, Mayor, Shippingport, PA

D. Allard, Director, PADEP

C. OClaire, State Liaison to the NRC, State of Ohio

Z. Clayton, EPA-DERR, State of Ohio

Director, Utilities Department, Public Utilities Commission, State of Ohio

D. Hill, Chief, Radiological Health Program, State of West Virginia

J. Lewis, Commissioner, Division of Labor, State of West Virginia

W. Hill, Beaver County Emergency Management Agency

J. Johnsrud, National Energy Committee, Sierra Club

J. Powers, Director, PA Office of Homeland Security

R. French, Director, PA Emergency Management Agency

P. Sena 4

Distribution w/encl: (via e-mail)

S. Collins, RA

M. Dapas, DRA

M. Gamberoni, DRS

D. Roberts, DRS

L. Doerflein, DRS

K. Mangan, DRS

D. Lew, DRP

J. Clifford, DRP

R. Bellamy, DRP

S. Barber, DRP

C. Newport, DRP

S. Williams, RI OEDO

R. Nelson, NRR

N. Morgan, NRR, PM

R. Guzman, NRR Backup

D. Werkheiser, Senior Resident Inspector

D. Spindler, RI

P. Garrett, Resident OA

ROPreportsResource@nrc.gov

Region I Docket Room (with concurrences)

U. S. NUCLEAR REGULATORY COMMISSION

REGION 1

Docket Nos.: 50-334, 50-412

License Nos.: DPR-66, NPF-73

Report No.: 05000334/2008008, 05000412/2008008

Licensee: FirstEnergy Nuclear Operating Company (FENOC)

Facility: Beaver Valley Power Station, Units 1 & 2

Location: Shippingport, PA

Dates: September 15 - October 10, 2008

Inspectors: K. Mangan, Senior Reactor Inspector, Team Leader

S. Pindale, Senior Reactor Inspector

P. Kaufman, Senior Reactor Inspector

J. Tifft, Reactor Inspector

M. Balazik, Reactor Inspector

W. Sherbin, NRC Mechanical Contractor

J. Chiloyen, NRC Electrical Contractor

Approved by: Lawrence T. Doerflein, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY OF FINDINGS

IR 05000334/2008008, 05000412/2008008; 09/15/2008 - 10/10/2008; Beaver Valley Power

Station; Component Design Bases Inspection.

The report covers the Component Design Bases Inspection conducted by a team of five NRC

inspectors and two NRC contractors. One finding of very low risk significance (Green) was

identified, which was considered to be a non-cited violation. The significance of most findings is

indicated by their color (Green, White, Yellow, Red) using IMC 0609, Significance

Determination Process (SDP). Findings for which the SDP does not apply may be Green or be

assigned a severity level after NRC management review. The NRCs program for overseeing

the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor

Oversight Process, Revision 4, dated December 2006.

A. NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

Green. The team identified a finding of very low safety significance involving a non-cited

violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, in that FENOC

did not take adequate corrective action following the identification of a condition adverse

to quality. Specifically, in 2004, 2005 and 2006, FENOC identified that if the Unit 1 river

water (RW) system or the Unit 2 service water (SW) system was aligned to the suction

of the auxiliary feedwater (AFW) pumps it could result in blockage of cooling water flow

for the pumps, but did not take actions to correct the deficiency. FENOC entered the

issue into their corrective action program to correct the non-conformance. In addition,

FENOC developed Operations Department standing orders to limit the use of TS action

statement 3.7.6.a which credited the use of the lineup, and formalized compensatory

actions to address an Appendix R compliance deficiency.

The finding was more than minor because there was reasonable doubt as to the

operability of the AFW system when supplied from RW or SW systems. In addition, the

finding was associated with the design control attribute of the Mitigating Cornerstone and

affected the cornerstone objective of ensuring the availability, reliability, and capability of

systems that respond to initiating events to prevent undesirable consequences. Since

the finding represented a potential loss of safety function, the team conducted

Significance Determination Process (SDP) Phase 2 and Phase 3 analyses which

determined the finding was of very low safety significance (Green).

Finally, the finding had a cross-cutting aspect in the area of Problem Identification and

Resolution, Corrective Action Program Component, because FENOC did not adequately

evaluate this condition adverse to quality, including classifying, prioritizing, and

evaluating for operability when it was identified in February 2004, and again in March

2005 and June 2006. (IMC 0305, Aspect P.1(c)). (Section 1R21.2.1.1)

B. Licensee-Identified Violations

None

ii

Enclosure

REPORT DETAILS

1. REACTOR SAFETY

Cornerstone: Initiating Events, Mitigating Systems, Barrier Integrity

1R21 Component Design Bases Inspection (IP 71111.21) (samples 24)

.1 Inspection Sample Selection Process

The team selected risk significant components and operator actions for review using

information contained in the Beaver Valley Power Station Probabilistic Risk Assessment

(PRA) and the U. S. Nuclear Regulatory Commissions (NRC) Standardized Plant

Analysis Risk (SPAR) model. Additionally, the Beaver Valley Power Station Unit 1 and 2

Significance Determination Process (SDP) Phase 2 Notebook, Revision 2.1a, was

referenced in the selection of potential components and operator actions for review. In

general, the selection process focused on components and operator actions that had a

Risk Achievement Worth (RAW) factor greater than 1.3 or a Risk Reduction Worth

(RRW) factor greater than 1.005. The components selected were located within both

safety-related and non-safety related systems, and included a variety of components

such as pumps, breakers, heat exchangers, electrical busses, transformers, and valves.

The team reviewed a list of components and operator actions based on the risk factors

previously mentioned. Additionally, the team reviewed the previous component design

bases inspection report (05000334/2006008 and 05000412/2006008) and excluded

those components previously inspected. The team then performed a margin

assessment to narrow the focus of the inspection to 24 samples including 18

components, 5 operator actions and 1 operating experience review. The teams

evaluation of possible low design margin included consideration of original design

issues, margin reductions due to modifications, or margin reductions identified as a

result of material condition/equipment reliability issues. The assessment also included

items such as failed performance test results, correction action history, repeated

maintenance, maintenance rule (a)1 status, operability reviews for degraded conditions,

NRC resident inspector insights, system health reports, and industry operating

experience. Finally, consideration was also given to the uniqueness and complexity of

the design and the available defense-in-depth margins. The margin review of operator

actions included complexity of the action, time to complete the action, and extent-of-

training on the action.

The inspection performed by the team was conducted as outlined in NRC Inspection

Procedure (IP) 71111.21. This inspection effort included walkdowns of selected

components, interviews with operators, system engineers and design engineers, and

reviews of associated design documents and calculations to assess the adequacy of the

components to meet design basis, licensing basis, and risk-informed beyond design

basis requirements. A summary of the reviews performed for each component, operator

action, operating experience sample, and the specific inspection findings identified are

discussed in the subsequent sections of this report. Documents reviewed for this

inspection are listed in the Attachment.

2

.2 Results of Detailed Reviews

.2.1 Results of Detailed Component Reviews (18 samples)

.2.1.1 Unit 2 Motor Driven Auxiliary Feedwater Pump (2FE-P23A)

a. Inspection Scope

The team inspected the motor driven auxiliary feedwater (MDAFW) pump to verify the

pump was capable of performing its design basis function. The team reviewed

drawings, calculations, hydraulic analyses, procedures, system health reports, and

design basis documents (DBDs) to evaluate whether the maintenance, testing, and

operation of the MDAFW pump was adequate to ensure the pump could deliver the

design basis flow at the required pressure to the steam generators under transient and

accident conditions. The team reviewed calculations for available net positive suction

head, pump minimum flow, run-out protection, and temperature qualification of

equipment to ensure the pump could operate under all design basis conditions.

Surveillance test results were reviewed to determine if the pump was operating within

established acceptable criteria, and the team also verified that the test acceptance

critieria ensured the pump could meet the design requirements.

The team reviewed electrical calculations, drawings and equipment specifications to

determine whether adequate voltage and current would be available at the pump motor

terminals for starting and running under worst case voltage conditions and to determine

if the motor capacity was adequate for the loading requirements. Protective relay

settings, motor feeder cable ampacity and cable short circuit current capability were also

reviewed to determine whether appropriate electrical protection coordination margins

had been applied and whether the feeder cable had been properly sized for the

maximum loading and short circuit current capability requirements.

The team reviewed the MDAFW lube oil cooling system to assess if the lube oil cooler

would work under design basis conditions. In addition, the team reviewed the adequacy

of water supply sources to the pump including an assessment of the potential for vortex

conditions in the primary plant demineralized water storage tank (PPDWST), and the

ability to transfer the pump suction to alternate water sources, including safety-grade

river water. The team performed a walkdown of the MDAFW pump and supporting

equipment to determine whether the alignment was in accordance with design basis and

procedural requirements, and to assess the material condition of the pump. Finally, the

team reviewed corrective action documents to ensure problems associated with the

pump were appropriately identified and corrected.

b. Findings

Introduction: The team identified a finding of very low safety significance (Green)

involving a non-cited violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective

Action, in that FENOC did not properly evaluate and take adequate corrective actions for

a condition adverse to quality. Specifically, FENOC identified that if the safety-related

Unit 1 river water (RW) system or the Unit 2 service water (SW) system was aligned to

the suction of the auxiliary feedwater (AFW) pumps it could result in blockage of cooling

water flow for the pumps, but did not take actions to correct the deficiency.

Enclosure

3

Discussion: The team reviewed FENOCs response to NRC Information Notice (IN) 2004-01 that described the potential for failure of AFW systems due to plugging of

orifices in the minimum flow recirculation line if the system is aligned to raw water.

FENOCs evaluation concluded that the potential for clogging of AFW components due

to supplying water from the Ohio River via the SW or RW systems did not present a

challenge to plant safe shutdown capability because the lineup was an alternate source

and only used if the safety related primary plant demineralized water storage tank

(PPDWST) was unavailable. In addition, other non-safety related water sources would

be preferentially used instead of the RW/SW system.

In 2005 (CR 05-01577), FENOC questioned whether the potential for this lineup to clog

the AFW pump minimum flow recirculation line orifices and lube oil cooling line orifices

was a concern in relation to regulatory requirements. FENOCs investigation concluded

that there would be reasonable assurance that the AFW system would continue to

function in the RW/SW lineup until the AFW was no longer required, and this lineup

would only be used for beyond design basis event scenarios because it was only

credited as a defense-in-depth system. In 2006 (CR 06-03595), another evaluation

stated that the response to IN 2004-01 should be enhanced because it did not identify

follow-up corrective actions to assess the effect on all plant procedures and analyses

that may credit the RW/SW lineup. FENOC identified during this investigation that BVPS

Unit 2 Updated Final Safety Analysis Report (UFSAR) describes assumptions used in

the reliability analyses for AFW that specifically credited the SW source as a rationale for

not modeling a pipe rupture in the piping from the PPDWST; and concluded that the

turbine driven auxiliary feedwater (TDAFW) pump lube oil cooler orifices in Units 1 and

2, and Unit 1 TDAFW and MDAFW pump minimum flow paths may be susceptible to

plugging if RW/SW lineup was used. Finally, in 2006, FENOC determined that RW

lineup was credited for Appendix R shutdown to cold standby for Unit 1; however,

because other sources of water were available no corrective or compensatory actions

were required.

The team reviewed the design of the AFW system and determined that the safety grade

PPDWST was the credited water source to meet Technical Specification (TS) operability

requirements for both AFW systems. The team reviewed operating procedures and

found they directed operators to use available water sources (non-safety related) to

supply the AFW pumps if the PPDWST became unavailable and the final choice for a

water supply to the pumps was the RW/SW lineup. The team then reviewed the TS, the

TS bases, the UFSAR and associated Safety Evaluation Reports (SERs) to determine if

the licensing and/or design bases credited this lineup. The team found that TS Action

Statement 3.7.6.a credits the RW/SW lineup as the allowed water source if the PPDWST

is not available to allow continued operation of the unit. In addition, the team found that

the UFSAR describes the RW/SW lineup as a long term source of cooling water. The

NRC SER Section 10.4.9 written to discuss how the AFW system meets Appendix A

General Design Criteria credits the RW/SW lineup as the long term safety grade source

of water for AFW. Finally, the team reviewed the SER associated with the Beaver Valley

Unit 1 Appendix R and concluded that the RW lineup was part of the licensing basis for

compliance with the Appendix. Therefore, the team concluded that this lineup was part

of the design and licensing basis of the Beaver Valley Units 1 and 2.

The team then evaluated whether the water from the Ohio River could clog the AFW

components. The team determined there was no impact on AFW pump operability

Enclosure

4

regarding the minimum flow recirculation line orifices. However, the team determined

the orifices in the MDAFW and TDAFW lube oil cooler lines had cross-sectional opening

of approximately 0.26 inches and 0.29 inches, respectively, and the RW/SW rotating

screens openings had cross-sectional opening of approximately 0.5 inch. No other

screens or strainers are in the system. Therefore, the team concluded that it was likely

that debris large enough to block the orifice would pass through the screens and clog the

orifices. The team determined FENOC had incorrectly concluded the RW/SW lineups

were not a licensing and design bases requirement, and the AFW system would

potentially be made inoperable if the RW/SW lineup was placed in service. Therefore,

the team concluded FENOC had taken inadequate corrective measures to correct the

deficiency. FENOC entered the issue into their corrective action program (08-47469 and

08-47692) in order to develop correct actions for the non-conformance. Additionally,

FENOC developed Operations Department standing orders to limit the use of Technical

Specification action statement 3.7.6.a and formalized compensatory actions to address

the Appendix R compliance deficiency.

Analysis: The team determined that the failure to properly evaluate and take effective

corrective measures to address a condition adverse to quality was a performance

deficiency. The finding was more than minor because it was similar to Manual Chapter

(MC) 0612 Appendix E question 3j in that as a result of this issue there was reasonable

doubt as to the operability of the AFW system when supplied from RW or SW systems.

In addition, the finding was associated with the design control attribute of the Mitigating

Cornerstone and affected the cornerstone objective of ensuring the availability, reliability,

and capability of systems that respond to initiating events to prevent undesirable

consequences. Traditional enforcement does not apply because the issue did not have

any actual safety consequences or potential for impacting the NRCs regulatory function,

and was not the result of any willful violation of NRC requirements. In accordance with

NRC Inspection Manual Chapter 0609, Attachment 4, "Phase 1 - Initial Screening and

Characterization of Findings," a Phase 1 SDP screening was performed which

determined the finding was a design deficiency that could represent a loss of system

safety function; therefore, a Phase 2 evaluation was required.

The internal events Phase 2 analysis for core damage frequency (CDF) was conducted

using the Risk-informed Inspection Notebook for Beaver Valley Nuclear Power Plant

Units 1 and 2, Revision 2.1a. Although the RW/SW lineup is mentioned in the

comments of the notebook, it is not explicitly modeled. As a result, a Region I senior

reactor analyst conducted a Phase 3 Risk Assessment, to evaluate the condition. The

analysis used an updated Beaver Valley Units 1 and 2 SPAR model, Rev. 3 plus, dated

July 11, 2008, with modifications to the model to include the respective RW/SW line-up.

The baseline failure of the primary AFW water source was modeled with a failure

probability of low E-8. The total failure of the AFW water supply would require a failure

of both the primary and backup water supply. Assuming a complete failure of the

backup water source, the likelihood of this occurrence would be low E-8. As a result, the

finding represented very low safety significance (Green). Since the refined analysis

resulted in a delta CDF of less then 1E-7, no further review of large early release or

external events was needed to be considered.

The finding has a cross-cutting aspect in the area of Problem Identification and

Resolution, Corrective Action Program Component, because FENOC did not adequately

evaluate this condition adverse to quality, including classifying, prioritizing, and

Enclosure

5

evaluating for operability when it was identified in February 2004, and again in March

2005 and June 2006. (IMC 0305, Aspect P.1(c))

Enforcement: 10 CFR 50, Appendix B, Criteria XVI, Corrective Action, requires, in part,

that measures be established to assure that conditions adverse to quality such as

failures, malfunctions, deficiencies, deviations, defective material and equipment, and

non-conformances are promptly identified and corrected. Contrary to the above,

between February 11, 2004 and October 10, 2008, FENOC identified that if the safety-

related Unit 1 river water (RW) system or the Unit 2 service water (SW) system was

aligned to the suction of the auxiliary feedwater (AFW) pumps it could result in blockage

of cooling water flow for the pumps, but did not take actions to correct the deficiency.

FENOC identified the potential problem in Condition Reports (CR) 2004-01276, 2005-

01577, and 2006-03595; however, the associated evaluations were not adequate.

Because this violation is of very low safety significance and has been entered into the

licensees corrective action program (CR 08-47469 and 08-47692), this violation is being

treated as a non-cited violation, consistent with Section VI.A.1 of the NRC Enforcement

Policy: (NCV 05000334/2008008,05000412/2008008-001, Inadequate Corrective

Action for Potential Blockage of AFW Pump Lube Oil Cooling System Orifices

when supplied by RW/SW)

.2.1.2 Unit 2 Turbine Driven Auxiliary Feedwater Pump (2FE-P22)

a. Inspection Scope

The team inspected the turbine driven auxiliary feedwater (TDAFW) pump to assess its

ability to meet design basis head and flow requirements for injection into the steam

generators. The team reviewed drawings, calculations, hydraulic analyses, procedures,

DBDs, system health reports, preventive maintenance activities, and selected condition

reports to evaluate whether the maintenance, testing, and operation of the TDAFW

pump was adequate to ensure the pump performance would satisfy design basis

requirements under transient and accident conditions. The team verified whether design

inputs were properly translated into system procedures and tests, and reviewed

completed surveillance tests associated with the demonstration of pump operability. The

team also reviewed the design capacity of the PPDWST, and calculations that evaluated

the potential for vortexing at the suction source to ensure the availability of the preferred

water source. In addition, the team reviewed the adequacy of water supply sources to

the pump including an assessment of the potential for vortex conditions, and the ability

to transfer the pump suction to alternate water sources, including safety-grade river

water.

The team reviewed the ability of the TDAFW pump for operation during the blackout

(SBO) as described in the SBO analysis and procedures. This review included an

assessment of room temperature heat up calculations and equipment thermal design

requirements to assess whether the TDAFW pump would operate within design

temperature limits. The team also reviewed the TDAFW pump and turbine lube oil

cooling system to assure the oil cooler would operate under design basis conditions.

Lastly, the team performed field walkdowns to assess the material condition of the

TDAFW pump and supporting equipment.

Enclosure

6

b. Findings

No findings of significance were identified in addition to the finding identified in

section .2.1.1.b.

2.1.3 Auxiliary River Water Pump (1WR-P-9A)

a. Inspection Scope

The team inspected the auxiliary river water pump to verify the pump was capable of

performing its design basis function. The auxiliary river water system is relied upon to

supply cooling water to plant equipment necessary for safe shutdown following a loss of

the safety-related service water intake structure. The team reviewed design documents,

including drawings, calculations, procedures, and the auxiliary river water system DBD.

The team reviewed these documents to ensure the pump was capable of meeting its

design basis requirements, with consideration of allowable pump degradation and pump

submergence requirements to prevent vortexing at minimum river level. To assess the

current condition of the pump, the team interviewed engineers, reviewed system health

and related condition reports, and performed walkdowns of the auxiliary river water

pump house area. Pump surveillance test results were reviewed to determine whether

pump performance was acceptable to ensure design basis requirements could be

achieved.

The team also reviewed electrical calculations, drawings and equipment specifications to

determine whether adequate voltage and current would be available at the pump motor

terminals for starting and running under worst case voltage conditions and to determine

if the motor capacity was adequate for the loading requirements. The team reviewed

protective relay settings, motor feeder cable ampacity and cable short circuit current

capability to determine whether appropriate electrical protection coordination margins

had been applied and whether the feeder cable had been properly sized for the

maximum loading and short circuit current capability requirements. Finally, the auxiliary

river water system operating procedures were reviewed to ensure the system was

operated in accordance with its design basis assumptions.

b. Findings

No findings of significance were identified.

.2.1.4 Unit 1 Quench Spray Pump (QS-1B)

a. Inspection Scope

The team inspected the quench spray (QS) pump to verify the pump was capable of

performing its design basis function. The team reviewed design basis documents,

hydraulic calculations, technical specifications, accident analyses and drawings to

ensure the QS pump was capable of meeting system functional and design bases

requirements. Surveillance test results were reviewed to assess whether the pump was

operated within established acceptable criteria, and the team verified that the test

acceptance criteria ensured the pump could meet the design requirements. The team

reviewed operating and emergency procedures to verify adequate reactor water storage

Enclosure

7

tank inventory was sprayed during a postulated accident. To assess the material

condition of the pump, the team performed walkdowns of the QS pump area, and

reviewed system health reports.

The team also reviewed electrical calculations, drawings and equipment specifications to

determine whether adequate voltage and current would be available at the pump motor

terminals for starting and running under worst case voltage conditions and to determine

if the motor capacity was adequate for the loading requirements. The team reviewed

protective relay settings, motor feeder cable ampacity and cable short circuit current

capability to determine whether appropriate electrical protection coordination margins

had been applied and whether the feeder cable had been properly sized for the

maximum loading and short circuit current capability requirements. Finally, the team

evaluated corrective action reports associated with the system to determine if problems

were being appropriately identified and corrected.

b. Findings

No findings of significance were identified.

.2.1.5 Unit 1 Pressurizer Power Operated Relief Valve (PCV-1RC-455C)

a. Inspection Scope

The team inspected the pressurizer power operated relief valve (PORV) to verify the

valve was capable of performing its design basis function. The team reviewed

thermal/hydraulic analysis for feed and bleed to ensure sufficient relief capacity was

available to remove the required heat load. Design calculations were also reviewed to

determine the adequacy of lift settings of the PORV in order to protect the reactor

coolant system while in the low temperature overpressure protection (LTOP) mode of

operation. Plant operating procedures were reviewed to ensure LTOP operational

controls were consistent with design basis assumptions. The team reviewed the

adequacy of the backup nitrogen supply for the PORV, including sizing of the nitrogen

accumulator, to verify the equipment was capable of cycling each PORV consistent with

design basis analyses. Also, minimum voltage calculations were reviewed to ensure

sufficient voltage would be available at the PORV for actuations when required. The

team reviewed recent surveillance testing of the PORV and pneumatic accumulator to

ensure test acceptance criteria were consistent with design basis assumptions on valve

stroke timing, and accumulator sizing requirements. Finally, the team reviewed

corrective action documents to ensure problems with the PORV were appropriately

identified and corrected.

b. Findings

No findings of significance were identified.

Enclosure

8

.2.1.6 Unit 2 Station Battery (BATT 2-1)

a. Inspection Scope

The team inspected the Unit 2 station battery to verify it was capable of performing its

design basis function. The team verified the battery was adequately sized to supply the

design duty cycle of the 125 VDC system. The team reviewed calculations to verify that

the sizing of the battery would satisfy the design requirements of the safety-related and

risk significant DC loads, and that all operating loads on the battery were included in the

calculation. In particular, the evaluation focused on voltage drop calculations to verify

adequate voltage would remain available for the individual loads required to operate

during design basis events. The team also reviewed the battery room hydrogen

generation calculation to verify that the hydrogen concentration level would stay below

acceptable levels during normal and accident conditions. The team reviewed battery

surveillance test procedures and results to determine whether test acceptance criteria

and frequency requirements satisfied technical specifications (TS) and the Institute of

Electrical and Electronics Engineers (IEEE) standards. Finally, the team performed a

walkdown of the battery and reviewed selected condition reports to verify that design

and testing issues related to the batteries were appropriately identified and corrected,

and to assess the overall material condition of the battery.

b. Findings

No findings of significance were identified.

.2.1.7 Unit 2 Station Battery Charger (#2/1)

a. Inspection Scope

The team inspected the Unit 2 station battery charger to verify it was capable of

performing its design basis function. The team inspected the battery charger to verify its

sizing would satisfy the amperage and voltage requirements of the DC loads during

design basis events. The team reviewed the UFSAR, design basis documents, vendor

drawings, and procedures to identify the design basis requirements for the charger. The

team verified the battery charger was adequately sized to supply the design duty cycle of

the 125 VDC system and that adequate voltage would be maintained for the individual

load devices required to operate during design basis events. In addition, the team

performed a walkdown to visually inspect the physical condition of the battery charger,

and to verify the charger was properly aligned and the panels indicated acceptable

voltage and current. The team interviewed design and system engineers to determine

the design aspects and operating history for the battery chargers. The team reviewed

battery charger surveillance test procedures and results to verify that applicable test

acceptance criteria and test frequency requirements specified for the battery charger

were in accordance with TS and design basis assumptions.

b. Findings

No findings of significance were identified.

Enclosure

9

.2.1.8 Unit 1 DC Switchboard (#1/2)

a. Inspection Scope

The team inspected the DC switchboard to verify that it could meet its design function

requirements as the central distribution point of the DC subsystem. The team reviewed

the UFSAR, design basis documents, vendor drawings, and procedures to identify the

design basis and operational requirements for the switchboard. The team reviewed the

DC protective breaker coordination study to verify that adequate protection existed for

postulated faults in the DC system. A walkdown was performed to evaluate the material

condition of the equipment and to determine if the environment conditions in the

switchboard area were in accordance with design assumptions. The team reviewed

surveillance test procedures and results to determine whether test acceptance criteria

and frequency requirements were in accordance with TS and design basis assumptions.

System and design engineers were interviewed regarding the design aspects and

operating history of the switchboard, and condition reports were reviewed to verify that

design and testing issues related to the DC system were appropriately identified and

corrected.

b. Findings

No findings of significance were identified.

.2.1.9 Unit 1 Emergency Diesel Generator (EDG) Ventilation Fan (1VS-F-22A/B)

a. Inspection Scope

The team inspected the EDG ventilation fan to verify it was capable of performing its

design basis function. The team reviewed the UFSAR, design basis documents, vendor

drawings, and procedures to identify the design basis requirements for the fan. The

team verified the fan would be able to ensure the EDG room temperature remained

within component design assumption ranges for all design basis events. The team also

reviewed drawings and calculations to verify the fan was capable of providing adequate

air flow as required by the DBDs and that appropriate setpoints were established to

ensure system design requirements were maintained. Additionally, the team reviewed

the system interactions with the EDG carbon dioxide (CO2) system to ensure that

neither system would interfere with the design function of the other. Finally, the team

conducted a walkdown of the system, interviewed the system engineer, and reviewed

condition reports in order to assess the material condition of the system and verify that

issues were being appropriately addressed in the corrective action program.

b. Findings

No findings of significance were identified.

Enclosure

10

.2.1.10 Unit 1 4160 Vac Vital Bus (1AE)

a. Inspection Scope

The team inspected the 4160Vac vital bus to verify it was capable of performing its

design basis function. The team reviewed the UFSAR, DBDs and electrical distribution

calculations including load flow, voltage drop, short-circuit and electrical protection

coordination. This review was to verify the adequacy and appropriateness of design

assumptions; and to verify that bus capacity was not exceeded and bus voltages

remained above minimum acceptable values under design basis conditions. The team

reviewed the electrical overcurrent, undervoltage and ground protective relay settings for

selected circuits to verify that the trip setpoints would not interfere with the ability of the

supplied equipment to perform its safety function as assumed in the design basis, and

yet ensure the trip setpoints provided for adequate bus protection. The loss of voltage

and degraded voltage relay surveillances, calibration results, and setpoint calculations

were also reviewed to verify that they satisfied the requirements of the associated TSs.

The 4160 Vac emergency bus 1AE voltage calculation profiles were reviewed to verify

adequate voltage was available to the bus consistent with the design basis assumptions

during worst case offsite grid voltage assumptions. The control logic design drawings of

the 4kV supply breaker to Vital Bus 1AE were reviewed to verify adequate breaker

closing and opening circuit interlocks. In addition, the 125 Vdc voltage drop calculations

were reviewed to ensure that adequate voltage would be available to the breaker control

circuit as well as for the breaker opening and closing coils under all design basis

conditions. The team reviewed system maintenance test results, interviewed system

engineers and conducted field walkdowns to verify that equipment alignment, nameplate

data, and breaker positions were consistent with design drawings, and to assess the

material condition of the bus. Finally, the team reviewed test results of automatic and

manual transfers of AC power sources to verify that they satisfy the design basis timing

and voltage requirements.

b. Findings

No findings of significance were identified.

.2.1.11 Unit 1 4160 Vac to 480 Vac Transformer (1-8N)

a. Inspection Scope

The team inspected the 4160 Vac to 480 Vac transformer to verify it was capable of

performing its design basis function. The team reviewed the system one-line diagram,

nameplate data and design basis descriptions to verify that the loadings of Unit 1 480V

substation transformer 1-8N, and the associated 4160V and 480V circuit breakers were

within the corresponding transformer and switchgear design ratings. The team reviewed

the design assumptions and calculations related to short-circuit currents, voltage drops

and protective relay settings associated with transformer 1-8N and its feeder cables to

verify that the settings were appropriate and output voltage was adequate to meet

design assumptions. The team reviewed a sample of completed maintenance activities

and functional verification test results to verify that the high and low voltage cable

feeders associated with transformer 1-8N had sufficient capacity to supply the current

Enclosure

11

and voltage requirements of the 480 V substation during normal and postulated accident

conditions. The team reviewed a sample of independent short-circuit and voltage drop

calculations to verify that voltage values assumed in design basis documents were

available during design basis events. The team reviewed maintenance test results,

interviewed system engineers and conducted field walkdowns to verify that equipment

alignment and nameplate data were consistent with design drawings, and to assess the

material condition of the transformer.

b. Findings

No findings of significance were identified.

.2.1.12 Unit 2 138 kV to 4.16 kV Station Service Transformer (TR-2A)

a. Inspection Scope

The team inspected the 138 kV to 4.16 kV transformer to verify it was capable of

performing its design basis function. The team reviewed the design basis descriptions,

equipment specifications, drawings, equipment nameplate data, voltage drop

calculations, and short-circuit and load flow studies to evaluate the capability of the

system station service transformer to supply the minimum design voltage and maximum

current requirements of Unit 2 station safeguard loads. The review was also conducted

to verify that the 138kV and 4.16kV feeder cables associated with transformer TR-2A

were adequately sized. Protective relay trip setting calculations were reviewed to verify

adequate electrical protection coordination was provided. Transformer relay settings

were reviewed to verify they protected the transformer from sudden pressure increases,

differential voltage conditions, and phase-to-phase and phase-to-ground over current

conditions. The team also reviewed the rating of the transformer neutral grounding

resistor to verify that the ground relay trip settings were coordinated with the 4.16kV

feeder ground relays to ensure selective tripping. The team reviewed the results of

completed transformer preventive maintenance and relay calibrations to verify that the

test results were within design assumptions. Finally, the team performed a visual

inspection of the observable portions of transformer TR-2A including its neutral

grounding resistor bank to assess the installation configuration and material condition.

b. Findings

No findings of significance were identified.

.2.1.13 Unit 1 Primary Plant Demineralized Water Storage Tank (1WT-TK-10)

a. Inspection Scope

The team inspected the Unit 1 primary plant demineralized water storage tank

(PPDWST) to verify it could meet its design function. The team reviewed the Unit 1

AFW system design basis documents which described PPDWST design requirements,

including capacity, level setpoint basis and minimum/maximum temperature limits. The

team also reviewed the UFSAR to obtain an overall understanding of the design function

of the Unit 1 PPDWST. The team evaluated the PPDWST ability to function as the

preferred safety related water supply for the auxiliary feedwater pumps and determine if

Enclosure

12

the tank had sufficient capacity for reactor decay heat removal and cool down of the unit

to hot standby condition for at least 9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br /> without makeup during a design basis event.

In addition, level instrumentation calibration records, operator surveillance verification

log records for channel checks for level indicators, the tank capacity curve, and vortex

calculations were reviewed to verify sufficient inventory existed for assumed AFW

system design requirements. The team also reviewed level instrumentation uncertainty

analysis calculations to verify appropriate corrections to indicated PPDWST level were

made to ensure Technical Specification requirements were met.

The team also inspected the capability of the tanks external enclosure to protect the

tank during design bases external events such as tornados. The team reviewed

auxiliary feedwater system surveillance tests and operating procedures, mechanical

system calculations, VT-2 visual examination reports, and pipe stress calculations to

verify the tank was capable of meeting design requirements. Finally, the team reviewed

a sample of condition reports, completed system engineer walkdown checklists, and the

Unit 1 AFW system health reports, performed a field walkdown, and interviewed the

system engineer to assess the material condition of the tank, associated attached piping

and level instrumentation, and to verify that deficiencies were being appropriately

identified and corrected.

b. Findings

No findings of significance were identified.

.2.1.14 Unit 2 High Head Safety Injection Pump Suction Valve (2SIS-MOV-863A) and

Normal Charging Line Isolation Valve (2CHS MOV-310)

a. Inspection Scope

The team inspected the high head safety injection pump suction motor operated valve

(MOV) and the normal charging line isolation MOV to verify both could meet their design

function. The team reviewed the UFSAR, design basis documents, vendor drawings,

and procedures to identify the design basis requirements for the valves. The team

performed a review of system operating procedures to assess whether component

operation and alignments were consistent with design and licensing bases assumptions.

Valve testing procedures and valve specifications were also reviewed to verify the

design bases requirements, including worst case system and environmental conditions,

were incorporated into the test acceptance criteria and component design. The team

reviewed periodic verification diagnostic test results and stroke test documentation to

verify acceptance criteria were met, and that the valves safety function, torque switch

settings, performance capability, and design margins were adequately monitored and

maintained in accordance with GL 89-10 guidance and that test frequencies were

correctly determined based on the results as described in GL 96-05. The review

included verifying the valve analysis used the maximum differential pressure expected

across the valves during worst case operating conditions.

The team also evaluated if the valve motors could perform their design function under

worst case design conditions. The team reviewed motor data, electrical control and

schematic diagrams, degraded voltage calculations, thermal overload settings, and

voltage drop calculations to confirm that the motor operated valves would have sufficient

Enclosure

13

voltage and power available to perform its safety function at worst case degraded

voltage conditions. The team interviewed the MOV program and design engineer to gain

an understanding of maintenance issues and overall reliability of the valves and

conducted walkdowns to assess their material condition, and to verify the installed valve

configurations were consistent with the design bases and plant drawings. Previous

component corrective action reports, system health reports, and system engineer

walkdown checklists, were reviewed to verify that deficiencies were appropriately

identified and resolved, and that the valves were properly maintained. Finally, the team

reviewed design changes to assess potential component degradation, and impact on

design assumptions and valve performance.

b. Findings

No findings of significance were identified.

.2.1.15 Unit 2 Recirculation Spray Heat Exchanger (E21C)

a. Inspection Scope

The team inspected the Unit 2 recirculation spray heat exchanger to ensure that it was

capable of removing the required containment heat loads during design basis events.

The team reviewed design basis documents, specification data, the tube plugging limit

evaluation along with current tube plugging status, thermal performance results, service

water full flow tests, heat exchanger cleaning and inspection reports, and the water

hammer analysis calculation to verify that the heat exchanger maintained adequate heat

removal capability and system integrity during all design basis events. Additionally, the

team conducted a walkdown of the heat exchanger, interviewed system and component

engineers, and reviewed system health and condition reports to assess the material

condition of the heat exchanger and overall system health, and to verify issues entered

into the corrective action program were being appropriately addressed. The team also

reviewed Fenocs response to Generic Letter 89-13, Service Water System Problems

Affecting Safety-Related Equipment, to verify that commitments made in the GL

response were being maintained.

b. Findings

No findings of significance were identified.

.2.1.16 Unit 1 Quench Spray Isolation Valve (MOV-1QS-101B) and Unit 2 Charging Pump

Suction Valve (2CHS-LCV-115B)

a. Inspection Scope

The team inspected the Unit 1 quench spray discharge isolation valve and the Unit 2

charging pump suction valve to verify they were capable of meeting their design

functions. The team reviewed MOV calculations, including the weak link analysis,

maximum thrust/torque, maximum differential pressure, and degraded voltage

assumptions, to verify the valves would operate during design basis conditions. The

team interviewed the MOV program and design engineers, and conducted a walkdown

Enclosure

14

to assess the physical condition of the MOVs and to verify nameplate data. To assess

the capability of the valves to operate as required, the team reviewed system health

reports, design basis documents, drawings, condition reports, and work orders.

The team also evaluated if the valve motors could perform their design function under

worst case design conditions. The team reviewed motor data, electrical control and

schematic diagrams, degraded voltage calculations, thermal overload settings, and

voltage drop calculations to confirm that the motor operated valves would have sufficient

voltage and power available to perform their safety function at worst case degraded

voltage conditions. Inservice testing results were reviewed to verify that the stroke time

acceptance criteria were in accordance with the UFSAR and accident analysis

assumptions. To ensure valve performance during design basis events, the team

reviewed the most recent diagnostic testing results. Also, the team reviewed FENOCs

response to Generic Letter 96-05, Periodic Verification of Design-Basis Capability of

Safety-Related Motor-Operated Valves, to verify that commitments applicable to the

valves were being maintained.

b. Findings

No findings of significance were identified.

.2.2 Detailed Operator Action Reviews (5 samples)

The team assessed manual operator actions and selected a sample of five operator

actions for detailed review based upon risk significance, time urgency, and factors

affecting the likelihood of human error. The operator actions were selected from a PRA

ranking of operator action importance based on RAW and RRW values. The non-PRA

considerations in the selection process included the following factors:

$ Margin between the time needed to complete the actions and the time available

prior to adverse reactor consequences;

$ Complexity of the actions;

$ Reliability and/or redundancy of components associated with the actions;

$ Extent of actions to be performed outside of the control room;

$ Procedural guidance to the operators; and

$ Amount of relevant operator training conducted.

.2.2.1 Unit 1 Operators Initiate Bleed and Feed After a Loss of Feedwater

a. Inspection Scope

The team inspected the operator actions associated with initiating reactor coolant

system (RCS) bleed and feed following a total loss of main and auxiliary feedwater. The

team reviewed FENOCs Human Reliability Analysis (HRA) to determine when and how

quickly this action should be accomplished. The team interviewed operators and training

staff, observed operator responses during a simulator run, reviewed emergency and

operating procedures, and walked down applicable panels in the main control room.

The team also reviewed maintenance history and a sample of condition reports

associated with components necessary to complete the operator action to assess the

overall health of the affected components.

Enclosure

15

b. Findings

No findings of significance were identified.

.2.2.2 Unit 1 Operators Initiate a Cooldown and Depressurization After a Small Break Loss-of-

Coolant Accident and High Head Safety Injection System Failure

a. Inspection Scope

The team inspected the operator action to initiate an RCS cooldown and

depressurization after a postulated small break loss-of-coolant accident. The team

reviewed FENOCs HRA to determine when and how quickly this action should be

accomplished. The team interviewed operators and training staff, observed operator

responses during a simulator run, reviewed emergency and operating procedures, and

walked down applicable panels and components in the main control room and in the

plant. In addition, the team reviewed maintenance history and a sample of condition

reports associated with components necessary to complete the operator action to

assess the overall health of the affected components.

b. Findings

No findings of significance were identified.

.2.2.3 Unit 1 Operators Start an Auxiliary River Water (ARW) Pump After a Failure of Both

River Water Pumps

a. Inspection Scope

The team reviewed the operator action to start the Unit 1 ARW pumps, RW-P-1A or

RW-P-1B, when normal river water cooling pumps have failed. The team reviewed the

HRA and PRA studies to determine when and how quickly operators are credited with

establishing auxiliary river water flow to various components, specifically the emergency

diesel generators and reactor coolant pump seals. The team interviewed licensed

operators, reviewed various operating and surveillance procedures and associated

annunciators on the main control room panels, and performed a field walked down of the

ARW pumps and local alarm annunciator panels in the alternate intake structure to

evaluate the ability of the operators to perform the required procedural actions. The

team also observed a simulator scenario to verify that appropriate alarms and

procedures existed to allow the operators to take appropriate action in the required time

to prevent damage to the equipment that is cooled by auxiliary river water. Finally, the

team reviewed maintenance history and a sample of condition reports associated with

components necessary to complete the operator action to assess the overall health of

the affected components.

b. Findings

No findings of significance were identified.

Enclosure

16

.2.2.4 Unit 2 Operators Align Makeup to the Refueling Water Storage Tank, Given a Steam

Generator Tube Rupture with Secondary Leakage

a. Inspection Scope

The team inspected the operator actions associated with aligning makeup to the

refueling water storage tank (RWST), given a steam generator tube rupture. In

particular, the team focused on providing RWST makeup from the spent fuel pool via the

spent fuel pool purification system. The team reviewed FENOCs HRA and design basis

documents to determine when and how quickly this action should be accomplished. The

team interviewed operators and engineering staff, reviewed emergency and operating

procedures, reviewed drawings, and walked down applicable components in the plant to

ensure this remote action could be performed as credited. The team also reviewed

maintenance history and a sample of condition reports associated with components

necessary to complete the operator action to assess the overall health of the affected

components.

b. Findings

No findings of significance were identified.

.2.2.5 Unit 2 Operators Align Spare Battery Charger, Given a Normal Battery Charger Failure

and a Station Battery is Supplying the DC Bus

a. Inspection Scope

The team inspected the operator actions associated with aligning a spare battery

charger, given that the normal battery charger has failed and the associated station

battery is supplying the DC bus. The team reviewed FENOCs HRA and design basis

documents to determine when and how quickly this action should be accomplished. The

team interviewed operators and engineering staff, reviewed emergency and operating

procedures, and walked down applicable components in the plant to ensure this action

could be performed as credited. The team also reviewed the maintenance history

associated with the normal and spare battery chargers to assess overall component

health.

b. Findings

No findings of significance were identified.

.2.3 Review of Industry Operating Experience and Generic Issues (1 sample)

.2.3.1 NRC Information Notice (IN) 2002-29, Recent Design Problems in Safety Functions of

Pneumatic Systems

a. Inspection Scope

The team reviewed FENOCs disposition of IN 2002-29 - Recent Design Problems in

Safety Functions of Pneumatic Systems. This IN discussed recent industry events

where it was discovered that the controls or designs of safety related systems

Enclosure

17

incorporating non-safety related air operated controls were less than adequate. The

team reviewed the disposition of the IN as documented by FENOC in CR 02-09460, for

both units. In this CR, FENOC had evaluated each plant system that has safety related

pneumatic components for adequacy of design. The corrective actions determined that

the design was adequate and additional design modifications were not required. The

team reviewed the corrective actions and determined that the pneumatic components

were identified and handled appropriately.

b. Findings

No findings of significance were identified.

4. OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems (IP 71152)

a. Inspection Scope

The team reviewed a sample of problems that FENOC had identified and entered into

their corrective action program. The team reviewed these issues to verify an appropriate

threshold for identifying issues and to evaluate the effectiveness of corrective actions. In

addition, CRs written on issues identified during the inspection were reviewed to verify

adequate problem identification and incorporation of the problem into the corrective

action system. The specific corrective action documents that were sampled and

reviewed by the team are listed in the attachment.

b. Findings

No findings of significance were identified.

4OA6 Meetings, including Exit

The inspectors presented the inspection results to Mr. Peter Sena, Site Vice President,

and other members of FENOC staff at an exit meeting on October 10, 2008. The

inspectors verified that none of the information in this report is proprietary.

Enclosure

A-1

ATTACHMENT

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

P. Sena Site Vice President

K. Ostrowski Director, Site Operations

R. Brosi Director, Performance Improvement

C. Mancuso Manager, Design Engineering

C. Keller Manager, Regulatory Compliance

R. Bologna Manager, Plant Engineering

R. Mueller Operations Support Shift Manager

B. Murtagh Supervisor, Design Engineering

J. Mauck Compliance Engineer

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED

Opened and Closed

NCV 05000334-412/2008008-001 Inadequate Corrective Action for Potential Blockage of

AFW Pump Lube Oil Cooling System Orifices when

Supplied by RW/SW

LIST OF DOCUMENTS REVIEWED

Calculations:

10080-DMC-0056, SBO Steady State Temperature Calculations, Unit 2, Rev. 0

10080-DMC-0757, PPDWST Inventory Requirements for EPU, Rev. 0

10080-E-068, Station Service Voltage and Load Analysis, Rev. 4

10080-E-074, Station Service Fault Analysis, Rev. 4

10080-E-201-1, DC System Management Battery 2-1/Battery Charger 2-1, Rev. 1

10080-E-221, 4160 and 480 VAC Load Management and Voltage Profile Calculations Relating

to Bus 2AE, Rev. 0

10080-E-221, 4160 and 480 Volt AC Load Management and Voltage Profile Calculations

Relating to Bus 2AE, Rev. 0A9

10080-E-222, 4160 and 480 VAC Load Management and Voltage Profile Calculations Relating

to Bus 2DF, Rev. 0

10080-N-574, Determination of Maximum Differential Pressure Across the QA Category I Motor

Operated Valves in the BVPS-2 Charging System, Rev. 4

10080-N-642, Torque Calculations for 2CHS-LCV115B, 2CHS-LCV115D, Rev. 10A1

10080-N-645, Torque Calculations for 2CHS-MOV310, Rev. 8

10080-N-659, Torque Calculation for 2SIS-MOV863A, Rev. 8

10080-N-676, Addendum No. 8, Maximum Torque Output for Degraded Voltage in Selected SIS

Motor Operated Valves, Rev. 7

Attachment

A-2

10080-N-677, Addendum No. 7, Maximum Torque Output Accounting for Degraded Voltage for

Selected Charging System Motor Operated Valves, Rev. 3

10080-N-677, Maximum Torque Output Accounting for Degraded Voltage for Selected CHS

Motor Operated Valves, Rev. 3A8

10080-N-684, Auxiliary Feedwater Pump Minimum Operating Curves, Rev. 1

10080-E-74.R3, Attachment AB, Design Analysis Transformer Data, 9/3/96

10080-N-779, Main Intake Bay Silt Buildup Limits, Rev. 0

10080-N-797, Documentation of Miscellaneous Unit 2 Containment Conversion Inputs, Rev. 4

10080-N-824, Recirculation Spray Heat Exchanger Inputs for MAAP, Rev. 0

10080-SP-2FWE-004, PPDWST Low and High Levels and Controls, Rev. 6

11700.26-N-122, RWST Volumes, Rev. 0

11700-ESK-130A, 125 VDC System Time-Current Characteristic Curves, dated 2/22/99

12241-B-7A, Service Building-Ventilation, Cooling Loads and Air Flow Rates, Rev. 4A2

12241-B-88, Alternate Intake Structure-Heat Gains and Required Airflow Rates, Rev. 1

12241-NP(B)-381-FA, Service Water System Water Hammer due to Flow into Initially Empty

Recirculation Spray System Coolers, Rev. 1

2706.450-001-003, Motor Operated Gate Valve Weak Link Analysis and Valve Data for

GL 89-10, Rev. D

8700-06.048-0185, Operating Load Condition Weak Link Analysis, Rev. E

8700-DEC-0230, Beaver Valley Unit 1 LTOPS Setpoint Calculation, Rev. 2

8700-DEC-181, Setpoint Inaccuracy Calculation for Emergency Bus Degraded Grid, Rev. 2

8700-DMC-1352, EDG Operating Time with Loss of RW, Rev. 0

8700-DMC-2275, Torque Calculation for MOV-QS-101B, Rev. 6

8700-DMC-2651, Aux Feedwater Pump Room Temperature Transient, Rev. 1

8700-DMC-2783, Determination of Maximum Differential Pressure Across the QA Category I

Motor Operated Valves in the BVPS-1 Containment Quench Spray System, Rev. 2

8700-DMC-2800, Diesel Generator Building Ventilation Adequacy with One of Two Inlet Air

Dampers Closed, Rev. 0

8700-DMC-2806, Maximum Torque Outputs Accounting for Degraded Voltage for Selected

Quench Spray Motor Operated Valves, Rev. 6

8700-DMC-3173, Auxiliary River Water Pump Minimum Operating Point, Rev. 0

8700-DMC-3439, Impact of 3/4 inch Tubing on OPPS Operation, Rev. 0

8700-DMC-3429, PORV Nitrogen Accumulator Pressure in Modes 1-3, Rev. 0

8700-DMC-3523, Quench Spray System Performance, Rev. 2

8700-E-068, Transformer Data, Attachment D, Rev. 4

8700-E-068, Load Flow Report, Attachment J8E, Rev. 4

8700-E-20, 5KV and 480V Cable Size Evaluation for Short Circuit, Rev. 0

8700-E-201, D.C. System Management-Bat-1/Bat-Chg-1, Rev. 1

8700-E-207, Short Circuit Analysis, 125 VDC Class-1E DC System, Rev. 2

8700-E-221, 4160 and 480 Volt AC Load Management and Voltage Profile Calculations

Relating to Bus 1AE, Rev. 1

8700-E-222, 4160 and 480 Volt AC Load Management and Voltage Profile Calculations

Relating to Bus 1DF, Rev. 1A5

8700-E-223, 4160 and 480 Volt AC Load Management and Voltage Profile Calculations

Relating to Non-1E Bus 1A, Rev. 0

8700-E-261, Qualification of Cable Sizing Calculation Program, Rev. 0

8700-E-271, Station Service System Dynamic Stability Study, Rev. 3

8700-E-308, Protective Relay Setting Calculations for 480V Emergency Bus 1N1, Rev. 0

8700-E-309, 480V Emergency Bus 1N Ground Alarm Relay, Rev. 0A6

8700-E-310, Att.4 QS-P-1B 200HP Quench Spray Pump Motor Feeder Breaker 9P5, Rev. 0A5

Attachment

A-3

8700-E-342, Att. 11, Electrical Protective Device Settings Calculation, 4160V Emergency Bus

1AE, Feeder to Emergency Sub 1-8, 1000/1333KVA Transformer 1-8N, Rev. 0

8700-E-68, Station Service Voltage and Load Analysis, Rev. 4

8700-E-74, Station Service Fault Analysis, Rev. 2

8700-SP-1HV-04, Local Temperature Switch Setpoints for the Diesel Generator Building

Exhaust Fans, Rev. 0

8700-SP-1QS-10, Beaver Valley Unit 1 RWST Low-Low Level Uncertainty Calculation, Rev. 2

8700-SP-1WT-01, Unit 1 Primary Plant Demineralized Water Storage Tank (WT-TK-10) Low

Level, Low-Low Level and Indication Uncertainty Calculation, Rev. 3

B-211, Hydrogen Evaluation in Battery Rooms, Rev. 1

Calculation 254, Surface and Buried Pipe Stress Calculation, Demineralized Water to

2FWE-TK210, Rev. 1

DMC-2219, Water Volume (PDDWST) Required for 9hrs at Hot Standby Following a LOOP,

Rev. 2

SCE-785-2, Issue 2, Stress Analysis For Small Bore Pipe And Supports, 8/15/86

Completed Surveillance and Modification Acceptance Testing:

1/2-PMP-E-75-202, 480 VAC Motor Inspection and Lubrication, Rev. 8, performed 10/25/04

1/2-CMP-39BYS/DC-BATTERY-1E, Station Battery Corrective Maintenance, Rev. 8, performed

5/05/08

1/2-CMP-39DC-BAT-1-2-3-4-4E, Charging Individual Battery Cells, Rev. 2, performed 5/04/08

1/2-CMP-75-480V-MOTOR-TERM-1E, 480V Motor/Miscellaneous Equipment Termination,

Rev. 9, performed 3/09/06

1/2-CMP-75-MCB-1E, Testing of Westinghouse and Cutler-Hammer Molded Case Circuit

Breakers, Rev. 8, performed 3/09/06

1/2-CMP-75-MCC-OHR-1E, Inspection, Verification, and Calibration Testing of Westinghouse

480V MCC Overload Heater Relays, Rev. 1, performed 3/09/06

1/2-CMP-E-39-366, Station Battery Jumper Installation and Restoration, Rev. 4, performed

9/28/07

1/2-CMP-E-75-021, Testing of Motor Operated Valves, Rev. 6, performed 02/20/06 & 04/23/08

1/2-OST-30.19E, Alternate Intake Structure A Bay Silt Check and Bay Cleaning, performed

6/15/08, 01/15/08, 04/4/07 & 01/28/07

1/2-OST-30.19F, Alternate Intake Structure B Bay Silt Check and Bay Cleaning, performed

6/19/08, 04/23/07 & 01/30/07

1/2-PMP-75VS-VNT-3M, Ventilation System Damper Maintenance, Rev. 12, performed 3/16/06,

3/24/06, & 4/06/06

1/2-PMP-75VS-VNT-4M, Ventilation System Fire Damper Maintenance and Trip Check,

Rev. 10, performed 9/25/06

1BVT 1.47.5, Type C leak Test, Issue 1, Rev. 16, performed 11/07/04, 04/04/05, 02/21/06,

10/02/06, 04/29/07 & 04/14/08

1BVT-1.44.8, Diesel Generator Building Ventilation Test, Rev. 4, performed 8/07/06

1MSP-36.41-E, 1AE 4KV Emergency Bus Degraded Voltage Relays, 27-VE2100AB and

27-VE2100BC Test, Rev. 21, performed 7/22/08

1MSP-36.45-E, 1AE 4KV Emergency Bus Loss of Voltage, Rev. 22, performed 7/22/08

1MSP-36.47B-E, 1AE 4KV Emergency Bus Loss of Voltage, Time Delay Relay 62-VE2100,

Rev. 7, performed 10/17/07

1MSP-36.49A-E, 1AE 4KV Emergency Bus Degraded Voltage Relays, 27-VE2100AB and

27-VE2100BC Calibration, Rev. 13, performed 10/17/07

Attachment

A-4

1MSP-36.81-E, Functional Test of 1AE 4KV Emergency Bus Loss of Voltage Relay 27-VE-100

and Diesel Start Loss of Voltage Relay 27-VE-1100, Rev. 7, performed 7/22/08

1OST-13.2, Quench Spray Pump Test, performed 07/16/08

1OST-24.1, SG Aux Feed Pumps Discharge Valves Exercise, Rev. 14, performed 9/16/08

1OST-30.1A, Auxiliary River Water Pump Test, performed 08/01/08

1OST-30.1B, Auxiliary River Water Pump Test, performed 06/22/08

1OST-33.13C, Ten Ton CO2 Fire Protection System Test, Rev. 9, performed 3/01/08

1OST-36.5A, Emergency Switchgear Operation Test, Rev. 6, performed 9/23/07

1OST-39.3, 125 VDC Distribution Panels Check, Rev. 4, performed 9/28/08

1OST-6.12, Power Operated Relief Valve Test, performed 10/18/07, 03/21/06, & 10/18/04

1PMP-39DC-BKR-1E, Battery Air Circuit Breaker Inspection, Rev. 14, performed 4/20/07

2BVT-1.39.01, Station Battery Service Test, Rev.6, performed 5/06/08

2BVT-1.39.06, Station Battery Performance Discharge Test, Rev. 3, performed 4/06/05

2BVT-1.39.13, Spare Battery Charger Load Test, Rev. 6, performed 4/10/08

2BVT-1.39.14, Battery Charger Load Test, Rev. 4, performed 5/07/08

2CMP-13RSS-E-21A-B-C-D-1M, Recirculation Spray Heat Exchanger Maintenance, Rev. 4,

performed 05/05/08 & 10/14/06

2LCP-24-L104A1, PPDWST 2FWE-TK210, Level Loop Calibration, performed 07/23/07

2LCP-24-L104A2, PPDWST 2FWE-TK210, Level Loop Calibration, performed 08/15/08

2MSP-39.05-E, Battery No. 2-1 Inspection and Interconnection Resistance Check, Rev. 6,

performed 7/29/07

2MSP-E-39-001, Vital Bus Batteries, Test and Inspection, Rev. 18, performed 6/23/08

2-MSP-E-39-300, Vital Bus Weekly Battery Inspection, Rev. 19, performed 8/27/08

2OST-24.2, Motor Driven Aux Feedwater Pump (2FWE*P23A) Test, performed 06/20/08

2OST-24.4, Steam Driven Aux Feedwater Pump (2FWE-P22) Quarterly Test, performed

10/17/08

2OST-24.4A, Steam Driven AFW Pump Full Flow Test, performed 04/05/08

2OST-24.6A, 23A AFW Pump Check Valves and Flow Test, performed 04/22/08

2OST-24.9, Overspeed Trip Test of TDAFW Pump, performed 05/11/08

2OST-30.13B, Train A Service Water System Full Flow Test, Rev. 24, performed 04/03/08

2OST-30.20A, Train A RSS Heat Exchangers and Supply Header Dry Layup Check, Rev. 3,

performed 08/27/08

2OST-39.1A, Weekly Station Battery Check, Rev. 18, performed 9/15/08

2OST-39.5, Station Battery Check, Rev. 4, performed 3/07/08

2PMP-39BYS-BAT-5-6-5E, Station Battery Inspection and Interconnection Resistance Check,

Rev. 4, performed 8/23/08

BV-L-1WT-104A1, Primary Plant Demineralized Water Storage Tank Level Loop Calibration,

performed 3/18/08

BV-L-1WT-104A2, Primary Plant Demineralized Water Storage Tank Level Loop Calibration,

performed 3/22/08

Corrective Action Documents:

02-09460 04-09194 05-07274 06-02800 07-13491

03-12509 05-00382 05-07971 06-03041 07-15302

04-01276 05-01577 05-08084 06-03527 07-17078

04-03210 05-02265 06-00231 06-03595 07-17292

04-06804 05-05496 06-00618 06-03595 07-23490

04-07609 05-05799 06-01112 06-03610 07-23540

04-08896 05-06712 06-02770 06-93990 07-23874

Attachment

A-5

07-24309 08-36809 08-44138 08-46518* 08-47469*

07-24330 08-36944 08-44446 08-46554* 08-47505*

07-26192 08-37313 08-44733 08-46560* 08-47514*

07-26632 08-37924 08-44734 08-47121* 08-47517*

08-33220 08-38792 08-45220 08-47159* 08-47519*

08-33408 08-39480 08-46379* 08-47175* 08-47544*

08-34360 08-40050 08-46381* 08-47247* 08-47552*

08-34677 08-43553 08-46426* 08-47257* 08-47622*

08-34854 08-43941 08-46456* 08-47302* 08-47692*

08-35713 08-43973 08-46508* 08-47337* 99-01531

Notifications

600461117

60049445*

  • Identified during inspection

Drawings:

08700-06.048-0038, Limitorque Operator Outline and Dimensions, Rev. E

08700-06.048-0061, 10 150 lb. Stainless Steel Globe Valve Welded Ends with Limitorque

Operator, Rev. G

10080-E-5DE, Elementary Diagram Gen. Aux. Pump 2FWE*P23A, Rev. 27

10080-RB-84A, Flow Diagram Ventilation and Air Conditioning, Sht. 1, Rev. 6

10080-RB-84B, Flow Diagram Ventilation and Air Conditioning, Sht. 2, Rev. 11

10080-RB-84K, Flow Diagram Ventilation and Air Conditioning, Sht. 10, Rev. 7

10080-RE-1AR, 125V DC One Line Diagram, Sht. 1, Rev. 20

10080-RE-1B, Main One Line Diagram, Sht. 2, Rev. 16

10080-RE-1C, Equipment One Line Diagram, Rev. 14

10080-RE-1D, 4160V One Line Diagram, Sht. 1, Rev. 9

10080-RE-1F, 4160V One Line Diagram, Sht. 3, Rev. 20

10080-RE-21AP, Elementary Diagram SSSXfmr. 2A AC Schematic, Rev. 1

10080-RE-21AR, Elementary Diagram SSSXfmr. 2A LTC Schematic, Rev. 1

10080-RE-21B, Three Line Current Diagram Sys. Sta. Svce. Xfmr. 2A, Rev. 10

10080-RE-30C, Arrangement System Station Service Transformer 2A, Rev. 5

10080-RM-0045B, Auxiliary Feedwater Piping, Rev. 17

10080-RM-0079D, Flow Diagram Chemical & Volume Control Piping, Sht. 4, Rev. 39

10080-RM-0082A, Flow Diagram - Fuel Pool Cooling Purification Piping, Rev. 31

10080-RM-0087A, Flow Diagram - Safety Injection Piping, Sht. 1, Rev. 28

10080-RM-0407-001A, Chemical and Volume Control, Sht. 1, Rev. 18

10080-RM-0413-002, Quench Spray System, Rev. 16

10080-RM-0424-003, Auxiliary Feedwater, Rev. 11

10080-RM-420-1, Fuel Pool Cooling and Purification, Rev. 10

10080-RM-424-5, Aux Feed Pumps Lube Oil System, Rev. 2

10080-RM-85A, Flow Diagram Containment Depressurization Piping, Rev. 27

10080-RP-16A, Main Steam to AFW and AFW Piping - Safeguards Area, Sht. 1, Rev. 8

10080-RP-77B, Fuel and Decon Building Piping, Sht. 2, Rev. 5

10080-RP-77B, Fuel and Decon Building Piping, Sht. 4, Rev. 6

10080-RT-113C, Tubesheet Map for Heat Exchanger 2RSS-E21C, Rev. 5

10-108763, 100A Battery Charger, Sht. 1, Rev. C

Attachment

A-6

11700-ESK-115G1, Incoming Supply to 4160V Bus 1AE from 4160V Bus 1A, Rev. 1

11700-ESK-115L, 1000/1333KVA 1-8N and 1-8N1 Feeder to 480V Sub 1-8, Rev. 1

11700-ESK-129E, 1QS-P-1B Breaker 9P5 Time-Current Curves, 10/6/06

11700-LSK-22-5A, 4160V Power System Emergency Logic Diagram, Rev. 4

11700-LSK-22-5B, 4160V Power System Emergency Logic Diagram, Rev. 5

11700-LSK-5, Logic Diagram, Aux. Feedwater Pump, Rev. 13D

11700-RE-1W, 125 VDC One Line Diagram Sht. 2, Rev. 5

12241-ESK-112D, Incoming 4160V Supply to Bus 2B, SSST 2A, Time-Current Curves, Rev. 8

12241-ESK-115G, Incoming Supply From Bus 2A, 4160V, Time-Current Curves, Rev. 7

12241-ESK-115R, 4160V Bus 2AE, BKR 2E18, Time-Current Curves, 2FWE-P23A, 9/29/88

1WT-TK-10, Demineralized Water Storage Tank Capacity Curve, Rev. 1

2004.210-012-003, Recirc Spray Coolers 34 O.D. x 42-13/16 O.A.H. Details, Sht. 2, Rev. 10

2006.300-001-176, Motor Op Gate Valve Model 08000GM82FBB0J0, Rev. E

2D74749, Motor Op Gate Valve Model 08000GM82FBBOJO - 2SIS-MOV863A, Rev. E

8700-3.22-141A, Unit 1 WT-TK-10 Demineralized Water Storage Tank, 1/4/72

8700-RB-2E, Flow Diagram Ventilation and Air Conditioning, Sht. 3, Rev. 13

8700-RE-100A, 4KV Station Service System, Rev. 8

8700-RE-1A, Main One Line Diagram, Sht. 1, Rev. 25

8700-RE-1AR, 125 VDC One Line Diagram, Sht. 1, Rev. 20

8700-RE-1B, Main One Line Diagram, Sht. 2, Rev. 25

8700-RE-1C, Equipment One Line Diagram, Rev. 25

8700-RE-1D, 4160V One Line Diagram, Sht. 1, Rev. 18

8700-RE-1F, 4160V One Line Diagram, Sht. 2, Rev. 19

8700-RE-1K, 480V One Line Diagram, Sht. 4, Rev. 28

8700-RE-1V, 125 VDC One Line Diagram, Sht. 1, Rev. 27

8700-RE-1Z, Vital Bus and DC One Line Diagram, Sht. 1, Rev. 27

8700-RE-21CF, Elementary Diagram 4KV Elec. System, Sht. 1, Rev. 8

8700-RE-21GX, Elementary Diagram Fire Protection, Sht. 6, Rev. 11

8700-RE-21HD, Elementary Diagram Feed Water, Sht. 507, Rev. 18

8700-RE-21JK, Elementary Diagram Quench Spray, Rev. 15

8700-RE-21KY, Elementary Diagram River Water, Sht. 3, Rev. 3

8700-RE-21MP, Elementary Diagram Ventilation System, Sht. 4, Rev. 4

8700-RE-21PY, Elementary Diagram Annunciator, Sht. 1, Rev. 13

8700-RE-21QA, Elementary Diagram Annunciator A6, Sht. 3, Rev. 13

8700-RE-22AW, Instrument Power Supplies in the Vertical and Benchboards, Sht. 1, Rev. 9

8700-RE-9AY, Wiring Diagram, 480V Substation 1-8, Bus N, Sht. 47, Rev. 11

8700-RE-9AZ, Wiring Diagram, 480V Substation 1-8, Bus N, Sht. 48, Rev. 17

8700-RM-0018A, Feed Water, Rev. 47

8700-RM-0413-001, Containment Depressurization System, Rev. 22

8700-RM-0430-001, River Water System, Rev. 29

8700-RM-37B, Reactor Coolant System, Rev. 38

8700-RM-406-2, Reactor Coolant System, Rev. 20

8700-RM-424-2, Feed Water System, Rev. 12

8700-RM-533-3, Flow Diagram Fire Protection CO2, Sht. 1, Rev. 7

8700-RP-0061D, Containment Recirculation Spray and Low Head Safety Injection External

Stems, Sht. 4, Rev. 9

D-79-7546, Demineralized Water Storage Tank, Rev. 6

Attachment

A-7

Licensing and Design Basis Documents:

1DBD-06, Reactor Coolant System, Rev. 7

1DBD-13, Unit 1 Design Basis Document for Containment Depressurization System, Rev. 15

1DBD-24B, Design Basis Document for Auxiliary Feedwater System, Rev. 10

1DBD-30, River Water, Auxiliary River Water, and Raw Water Systems, Rev. 15

1DBD-33B, Unit 1 4.16KV Power Distribution System, Rev. 7

1DBD-37, Unit 1 480V Distribution System, Rev. 7

1DBD-39, 125 VDC Power System, Rev. 6

2DBD-07, Unit 2 Design Basis document for Chemical and Volume Control System, Rev. 12

2DBD-13, Unit 2 Design Basis Document for Containment Depressurization System, Rev. 11

2DBD-24B, Auxiliary Feedwater System, Rev. 12

2DBD-39, 125 VDC Power System, Rev. 7

2DBD-M-003, Piping Design & Piping, Tubing, and Duct Stress Analysis, Rev. 1

BVPS Technical Specifications

BVPS UFSAR, Unit 1 and 2

BVPS-1 License Requirement Manual, Rev. 59

BVPS-2 License Requirement Manual, Rev. 54

Duquesne Light Company letter dated 03/17/97, 180-Day Response to Generic Letter 96-05

L-05-090, Commitment Changes and Report of Facility Changes, Test and Experiments,

05/13/05

L-05-148, Commitment Changes and Report of Facility Changes, Test and Experiments,

08/29/05

L-98-072, Updated Response to Safety Evaluation-Joint Owners Group Program on Periodic

Verification of Motor-Operated Valves, 04/13/98

L-99-046, Response to Request for Additional Information on Generic Letter 96-05, 03/19/99

Letter from J. D. Sieber, DLC to USNRC, Reference: Beaver Valley NRC Bulletin Number

88-04, Potential Safety Related Pump Loss, 08/08/88

Letter from NRC (A. W. De Agazio0 to DLC (Mr. Sieber), DLC Confirmation Related to Actions

Required by NRC Generic Letter 88-14, dated 08/19/91

Response to Generic Letter 89-13, Service Water System Problems Affecting Safety-Related

Equipment, 01/29/90

Safety Evaluation Report Related to Operations at Beaver Valley Power Station Unit 2, Docket

Number 50-412, October 1985

Second Response to Generic Letter 89-13, Service Water System Problems Affecting Safety-

Related Equipment, 06/27/91

Miscellaneous:

138KV Voltage Profile, BV1 SSST & ERFS-3B Phase A Voltage, 10/8/08

2DLS-13027, Stone & Webster correspondence, 12/22/81

8700-3.22-193A, Lasalle Hydraulic Laboratory Ltd., Hydraulic Model Study of Quench Spray

Inlets, January 1980

Beaver Valley Unit 2, Weekly Maintenance Risk Summary (August 18, 2008), Rev. 1

BE-VBE-8, Electrical Protective Device Setting Sheet, ITE-51E, 1/15/01

BV1-RPB-6, Electrical Protective Device Setting Sheet, 11/30/06

BV1-VBE-2, Electrical Protective Device Setting Sheet, 11/28/88

BV2-TA-1, Electrical Protective Device Setting Sheet, ITE-47H, 5/16/83

BV2-TA-11, Electrical Protective Device Setting Sheet, 1/27/97

BV2-TA-14, Electrical Protective Device Setting Sheet, 12/6/91

Attachment

A-8

BV2-TA-2, Electrical Protective Device Setting Sheet, HU-1, 11/2/84

BV2-TA-3, Electrical Protective Device Setting Sheet, ITE-47H, 5/16/83

BV2-TA-4, Electrical Protective Device Setting Sheet, ITE-51D, 9/9/83

BV2-VBE-20, Electrical Protective Device Setting Sheet, ITE-51L, 11/28/88

BVPS-1 Stone & Webster Specification BVS-374, Rev. 3

BVS-162, QS-P-1A, QS-P-1B Induction Motor Data, 5/29/69

ES-E-003, Protective Relaying Philosophy for Unit 2, Rev. 4

ES-E-004, Protective Relaying Philosophy for BVPS Unit 1, Rev. 7

Human Reliability Assessment (Unit 1), 6/2/06

Human Reliability Assessment (Unit 2), 4/2/07

IR Surveys of Unit 2 SSS Transformer TR-2A conducted on 4/29/05 and 9/3/08

IST Program for Pumps and Valves, Unit 1, Rev. 1

IST Program for Pumps and Valves, Unit 2, Rev. 2

NRC Information Notice (IN) 2002-29, Recent Design Problems in Safety Functions of

Pneumatic Systems

NRC Information Notice (IN) 2004-01, Auxiliary Feedwater Pump Recirculation Line Orifice

Fouling - Potential Common Cause Failure

Specification for Free Standing Power Distribution Panel Unit 1, Rev. 2

System Health Report, Unit 1 125 VDC Distribution System, 2nd quarter 2008

System Health Report, Unit 1 Area Ventilation Systems - Miscellaneous, 2nd quarter 2008

System Health Report, Unit 1 Containment Depressurization System, 2nd Quarter 2008

System Health Report, Unit 1 Reactor Coolant System, 2nd Quarter 2008

System Health Report, Unit 1 River Water System, 2nd Quarter 2008

System Health Report, Unit 2 125 VDC Distribution System, 2nd quarter 2008

System Health Report, Unit 2 AFW System, 2nd Quarter 2008

System Health Report, Unit 2 Chemical and Volume Control System, 2nd quarter 2008

System Health Report, Unit 2 Containment Depressurization System, 2nd quarter 2008

TER 13630, Evaluate the Addition of Individual Cell Equalizers to the Station Batteries, Rev. 0

Unit 1 & Unit 2 Inservice Testing (IST) Program for Pumps and Valves, Issue 4, Rev. 1

Unit 1 Feedwater/Aux Feedwater System Walkdown Checklist, performed 9/25/08

VB1-VBE-17, Electrical Protective Device Setting Sheet, 51-VE1112, 12/5/95

VB1-VBE-26, Electrical Protective Device Setting Sheet, ITE-47H, 1/23/03

VB1-VBE-5, Electrical Protective Device Setting Sheet, 51-VE105, 3/7/00

VT-2, Visual Examination Report VT-01-234, WT-TK-10, performed 10/12/01

VT-2, Visual Examination Report VT-97-235, WT-TK-10, performed 11/4/97

WCAP-16902-P, Loss of Secondary Heat Sink Upgrade Analysis for Emergency Response

Guideline FR-H.1

VB1-VBF-25, Electrical Protective Device Setting Sheet, ITE-47H, 7/12/01

Procedures:

1/2, ES-G-014, Engineering Standards Manual Units, Guidelines for MOVs, Rev. 7

1/2-ADM-1900, Fire Protection Program, Rev. 17

1/2OM-35.4A.A, Voltage Schedule Guidance, Rev. 4

1/2OM-53C.4A.35.1, Degraded Grid, Rev. 5

1/2PMP-36TR, Transformer-IE System Transformer Inspection, Rev. 3

1/2PMP-75VS-VNT-3M, Ventilation System Damper Maintenance, Rev. 13

1/2PMP-E-36-001, 4KV Bus Switchgear Inspection, Rev. 6

1/2PMP-E-36-015, ITE Med. Voltage Ckt. Breaker Inspection and Test, 5HK-250/350, Rev. 16

1/2PMP-E-75-202, 480 VAC Motor Inspection and Lubrication, Rev. 9

Attachment

A-9

1/2RCP-11-PC, Calibration of Ground Fault Relays, Types ITE/ABB GR-5 and GR-200, Rev. 5

1/2RCP-13-PC, Calibration of ABB/Westinghouse Transf. Diff. Relays type HU and HU1, Rev. 5

1/2RCP-1A-PC, Calibration of Auxiliary Relays, Rev. 8

1/2RCP-25-PC, Calibration of Westinghouse/ABB Sudden Pressure Relays type SPR, Rev. 2

1/2RCP-29A-PC, Calibration of ABB TD-5 Time Delay Relay, Rev. 1

1/2RCP-30A-PC, Calibration of Timing Relays, Rev. 3

1/2RCP-31-PC, Calibration of Auxiliary Relays, Rev. 10

1/2RCP-38A-PC, Calibration of ITE/ABB Single Phase Overcurrent Relays Type 50/51, Rev. 4

1/2RCP-38B-PC, Calibration of ITE/ABB Three Phase Overcurrent Relays Type 51, Rev. 6

1MSP-36.47A-E, 1AE 4KV Emergency Bus Loss of Voltage, Rev. 10

1MSP-36.81-E, Functional Test of 1AE 4KV Emergency Bus Loss of Voltage Relay, Rev. 7

1OM-24.2.B, Setpoints, Rev. 9

1OM-24.4.AAD, Aux. Feedwater Pump Recirc Loops A/B Low Flow, Rev. 4

1OM-24.4.AAF, Primary Plant Demin Water Storage Tank Level-Low WT 104 A1, Rev. 2

1OM-30.4.V, Auxiliary River Water System Startup, Rev. 6

1OM-30.4.W, Issue 4, Unit 1 Auxiliary River Water System Running, Rev. 0

1OM-33.4.L, Cross Connecting to River Water, Rev. 2

1OM-36.4.A, 4KV Station Service System Startup, Rev. 12

1OM-37.4.ABA, 480V Emergency Bus 1N Ground, Rev. 0

1OM-44F.1.C, Major Components, Rev. 3

1OM-52.4.R.1.F, Station Shutdown From 100% Power to Mode 6, Rev. 15

1OM-53A.1.E-0, Reactor Trip or Safety Injection, Rev. 11

1OM-53A.1.E-1, Loss of Reactor or Secondary Coolant, Rev. 12

1OM-53A.1.E-3, Steam Generator Tube Rupture, Rev. 12

1OM-53A.1.ECA-0.0(ISS1C), Issue 1C, Loss of All Emergency 4KV AC Power, Rev. 8

1OM-53A.1.ECA-3.1, SGTR with Loss of Rx Coolant - Subcooled Recovery Desired, Rev. 13

1OM-53A.1.ES-0.1, Reactor Trip Response, Rev. 6

1OM-53A.1.ES-1.2, Post LOCA Cooldown and Depressurization, Rev. 12

1OM-53A.1.ES-1.3(ISS1C), Transfer to Cold Leg Recirculation, Rev. 6

1OM-53A.1.FR-H.1, Response to Loss of Secondary Heat Sink, Rev. 11

1OM-53B.1.FR-H.1, Response to Loss of Secondary Heat Sink Background, Rev. 11

1OM-53B.5.GI-6, RCP Trip/Restart, Issue 1C, Rev. 1

1OM-53C.4.1.30.2, Unit 1 River Water/Normal Intake Structure Loss, Rev. 6

1OM-53C.4.1.36.1, Unit 1 Loss of All AC Power When Shutdown, Rev. 4

1OM-53C.4.1.36.2, Unit 1 Loss of 4KV Emergency Bus, Rev. 6

1OM-56B.4.A, Safe Shutdown Following a Serious Fire in the Primary Auxiliary Building, Rev. 6

1OM-56C.4.F-2, Transferring AFW Pump Suction to River Water, Rev. 12

1OST-6.8, Placing Overpressure Protection System (OPPS) in Service, Rev. 17

1RCP-8A-PC, Calibration of Westinghouse/ABB Overcurrent Relay Type CO, Rev. 3

2LOT-M5D18, Licensed Operator Initial Training - AOP/EOP Practice Scenarios, Rev. 8

2OM-13.1.C, Containment Depressurization System Description-Major Components, Rev. 2

2OM-13.4.AAD, Refueling Water Storage Tank Level Off Normal, Rev. 12

2OM-20.4.A, Fuel Pool Cooling/Purification System Startup and Operation, Rev. 10

2OM-24.4.AAI, Primary Plant DWST Level Low, Rev. 11

2OM-24.4.K, Operation and Shutdown of AFW System to Control SG Levels, Rev. 7

2OM-39.4.A, Startup of Batteries *2-1, *2-2, *2-3, *2-4, *2-5, *2-6 and Chargers, Rev. 7

2OM-39.4.D, Startup and Shutdown of Spare Battery Charger (Train A), Rev. 10

2OM-39.4.M, Startup and Shutdown of Spare Battery Charger (Train B), Rev. 0

2OM-53A.1.A-1.8, Makeup to PPDWST [2FWE*TK210], Rev. 2

2OM-53A.1.E-0, Reactor Trip or Safety Injection, Rev. 8

Attachment

A-10

2OM-53A.1.E-1, Loss of Reactor or Secondary Coolant, Rev. 10

2OM-53A.1.E-3, Steam Generator Tube Rupture, Rev. 13

2OM-53A.1.ECA-3.1, SGTR with Loss of Rx Coolant - Subcooled Recovery Desired, Rev. 10

2OM-53A.1.ECA-3.2, SGTR with Loss of Rx Coolant - Saturated Recovery Desired, Rev. 8

2OM-53A.1.ES-0.1, Reactor Trip Response, Rev. 5

2OM-53C.4.2.39.1A, Loss of 125Vdc Bus 2-1, Rev. 2

2OM-54.3.L5, Surveillance Verification Log, Rev. 69

2OM-7.4.O, Makeup to the Refueling Water Storage Tank, Rev. 12

2OST-39.7, Weekly DC Bus Distribution Surveillance, Rev. 0

2PMP-2FWE-P-T-22-1M, Turbine Driven Aux. Feed Pump Lubrication, Rev. 6

3LOT-M4D7/8/9, Licensed Operator Training - Shutdown From 100% to Mode 5, Rev. 4

3SQS-39.1, Licensed Operator Training - 125 Vdc Distribution System, Rev. 5

3SQS-53.5, Licensed Operator Training - Emergency Operating Procedures, Rev. 3

NOP-OP-1003, Grid Reliability Protocol, Rev. 00

Vendor Manuals:

08100-01.026-0066, Battery Breaker Switchgear, Rev. E

195B7798AL, General Electric Neutral GND Resistor Enclosure, 4/1/78

2501.240-841-006, Exide Instructions for Installing and Operating Flooded Stationary Batteries,

Rev. G

3SD-130-100CE, Unit 2 Battery Charger 2-1, Rev. 1

Bulletin 3412, Heinemann General Purpose Circuit Breakers, 7/71

BVS-215, ITE Specification for 4160V Metal Clad Switchgear, Rev. 2

H-5121-D, Auxiliary River Water Pumps (Johnston Pumps), Rev. 4A

IL 41-133.3J, ABB Type IRV Directional Overcurrent Relay for Phase Protection, 9/00

IL 41-222E, ABB Types CV, CV-8 Voltage Relay, 9/00

Spec No. 2BV-208, Steam Generator Aux. Feedwater Pumps, 04/27/78

VTM 2502.180-208-001, Turbine Driven Aux. Feedwater Pump Instruction Manual, Revision AF

VTM 2502.400-208-005, Installation, Operation, and Maintenance Manual-Motor Driven

Auxiliary Feedwater Pump, Revision W

Work Orders:

200071985 200165183 200210880 200249658

200074178 200165219 200215990 200263740

200075905 200165220 200221730 200267943

200077832 200165221 200221865 200275504

200099221 200191083 200240006 200276191

200099262 200191084 200240168 200276192

200115000 200196133 200248055 200276194

200135367 200196167 200248165 200281370

200135369 200206668 200249086 600242815

200135459 200206669 200249087 ECP 04-0440-02

200143974 200206673 200249088 ECP-04-0134

200151460 200209796 200249089 ECP-05-0059

200158455 200209800 200249657 ECP-06-0091

Attachment

A-11

LIST OF ACRONYMS

AC Alternating Current

AFW Auxiliary Feedwater

ARW Auxiliary River Water

BVPS Beaver Valley Power Station

CDF Core Damage Frequency

CFR Code of Federal Regulations

CO2 Carbon Dioxide

CR Condition Report

DC Direct Current

DBD Design Basis Document

DBE Design Basis Event

EDG Emergency Diesel Generator

FENOC FirstEnergy Nuclear Operating Company

GL Generic Letter

HRA Human Reliability Analysis

IEEE Institute of Electrical and Electronics Engineers

IMC Inspection Manual Chapter

IN Information Notice

IST Inservice Testing

kV Kilo-volts

LTOP Low Temperature Overpressure Protection

MOV Motor Operated Valve

MDAFW Motor Driven Auxiliary Feedwater

NCV Non-cited Violation

NRC Nuclear Regulatory Commission

PORV Power Operated Relief Valve

PPDWST Primary Plant Demineralized Water Storage Tank

PRA Probabilistic Risk Assessment

QS Quench Spray

RAW Risk Achievement Worth

RCS Reactor Coolant System

RRW Risk Reduction Worth

RW River Water

RWST Refuel Water Storage Tank

SBO Station Blackout

SDP Significance Determination Process

SER Safety Evaluation Report

SPAR Standardized Plant Analysis Risk

SW Service Water

TDAFW Turbine Driven Auxiliary Feedwater

TS Technical Specifications

UFSAR Updated Final Safety Analysis Report

Vac Volts, Alternating Current

Vdc Volts, Direct Current

Attachment