IR 05000334/2021010

From kanterella
Jump to navigation Jump to search
Triennial Fire Protection Inspection Report 05000334/2021010 and 05000412/2021010
ML21272A232
Person / Time
Site: Beaver Valley
Issue date: 09/29/2021
From: Glenn Dentel
Division of Operating Reactors
To: Grabnar J
Energy Harbor Nuclear Corp
Dentel G
References
IR 2021010
Download: ML21272A232 (10)


Text

September 29, 2021

SUBJECT:

BEAVER VALLEY POWER STATION, UNITS 1 AND 2 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000334/2021010 AND 05000412/2021010

Dear Mr. Grabnar:

On September 16, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Beaver Valley Power Station, Units 1 and 2 and discussed the results of this inspection with Mr. Matthew Enos, General Plant Manager, Nuclear, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Glenn T. Dentel, Chief Engineering Branch 2 Division of Operating Reactor Safety

Docket Nos. 05000334 and 05000412 License Nos. DPR-66 and NPF-73

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000334 and 05000412

License Numbers:

DPR-66 and NPF-73

Report Numbers:

05000334/2021010 and 05000412/2021010

Enterprise Identifier: I-2021-010-0017

Licensee:

Energy Harbor Nuclear Corporation

Facility:

Beaver Valley Power Station, Units 1 and 2

Location:

Shippingport, PA 15077

Inspection Dates:

August 30, 2021 to September 16, 2021

Inspectors:

E. Dipaolo, Senior Reactor Inspector

L. Dumont, Reactor Inspector

D. Kern, Senior Reactor Inspector

Approved By:

Glenn T. Dentel, Chief

Engineering Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Beaver Valley Power Station,

Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site.

However, all the inspection activities were performed onsite. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

===71111.21N.05 - Fire Protection Team Inspection (FPTI)

Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)===

The inspectors verified that the following systems credited in the approved fire protection program could perform their licensing basis function:

(1) Fire Protection Water Supply System
(2) Auxiliary Feedwater System
(3) Chemical Volume Control System
(4) Fire Barriers

Fire Protection Program Administrative Controls (IP Section 03.02) (2 Samples)

The inspectors verified that the selected fire protection administrative controls were implemented in accordance with the current licensing basis. The inspectors verified that the controls were properly implemented with adequate procedures and that the controls met committed industry standards. The following fire protection administrative controls were reviewed:

(1) Control of Transient Combustible Material
(2) National Fire Protection Association (NFPA) 805 Monitoring Program

Fire Protection Program Changes/Modifications (IP Section 03.03) (2 Samples)

The inspectors reviewed fire protection changes/modifications to ensure that they did not constitute an adverse effect on the ability to safely shutdown post-fire and did not degrade assumptions and performance capability stated in the in the safe shutdown analysis. The inspectors verified that fire protection program documents and procedures affected by the changes were updated. The following fire protections program changes/modifications were reviewed:

(1) Engineering Change Package (ECP) 15-0450-000, Unit 1 Early Warning Fire Detection Initiating Device Replacement
(2) ECP 18-0090-000 - Unit 2 Residual Heat Removal System Pump Breaker Normal System Alignment Change

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On September 16, 2021, the inspectors presented the triennial fire protection inspection results to Mr. Matthew Enos, General Plant Manager, Nuclear, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.05 Calculations

ARS-BV1-18-217

BVPS-1 Fire Protection SSD Recovery Action Report

ARS-BV2-18-219

BVPS-2 Fire Protection SSD Recovery Action Report

Calibration

Records

CR-2021-05522

Corrective Action

Documents

CR-2018-07052

CR-2018-08406

CR-2019-02500

CR-2019-05145

CR-2019-09822

CR-2020-00074

CR-2020-00079

CR-2020-07579

CR-2020-08721

CR-2021-00202

CR-2021-00578

CR-2021-00871

CR-2021-02372

CR-2021-03186

CR-2021-05523

Corrective Action

Documents

Resulting from

Inspection

CR-2021-06269

CR-2021-06588

CR-2021-06600

CR-2021-06615

CR-2021-06639

CR-2021-06645

CR-2021-06677

CR-2021-06683

CR-2021-06685

CR-2021-06686

CR-2021-06692

CR-2021-06837

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-2021-06844

CR-2021-06868

CR-2021-06886

CR-2021-06906

CR-2021-06950

CR-2021-06954

CR-2021-06966

CR-2021-06973

Drawings

OP Manual

Figure No. 33-1

Fire Protection-Water

OP Manual

Figure No. 33-2

Fire Protection-Water

Engineering

Changes

ECP 18-0090-

000

Unit 2 Residual Heat Removal System Pump Breaker

Normal System Alignment Change

Engineering

Evaluations

10080-DMC-

0915

Beaver Valley Unit 1 and Unit 2 Fire Water Analysis

Engineering

Evaluation

Request

601155097

Fire Protection

Program Change

Evaluation

(FPPCE)15-025

NFPA 20 Code Compliance Review

FPPCE 15-026

Engineering Evaluation of Specified NFPA 24

Requirements

FPPCE 18-085

Unit 2 RHS Pump Breaker NSA Chan

FPPCE 21-019

Pre-NRC Fire Protection Inspection Self-Assessment-No

Surveillance Test that Document Sprinkler System

Inspections

FPPCE 21-021

Fire Alarm and Halon Discharge in Unit 1 Cable Tunnel 1-

CV-3

PRA-BV1-21-

001-R00

BVPS-1 Configuration Risk Determination for Both Normal

Fire Pumps Out of Service

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PRA-BV2-21-

2-R00

BVPS-2 Configuration Risk Determination for Both Normal

Fire Pumps Out of Service

Miscellaneous

Beaver Valley Power Station Unit 1 Updated Final Safety

Analysis Report

Beaver Valley Power Station Unit 2 Updated Final Safety

Analysis Report

Beaver Valley Power Station Units 1 and 2 Fire Safety

Analysis

Fire Protection Program Health Report, January-June

21

1/2OST-33.12

Fire Pump Flow Test

11/21/2019

and

06/23/2021

1OST-33.34

GDC Diesel Driven Fire Pump Operation Test

08/12/2021

1OST-33.7

Motor Driven Fire Pump Operation Test

03/26/2021

and

05/15/2021

1OST-33.8

Diesel Engine Driven Fire Pump Operation Test

07/17/2021

and

08/14/2021

2OM-10.3

Power Supply and Control Switch List

Procedures

1/2-ADM-1900

Fire Protection Program

1/2-ADM-1906

Control of Transient Combustible and Flammable

Materials

1/2-ADM-1908

Fire Protection Performance Monitoring Program

1/2OM-56B.4A.E

Safe Shutdown Intent and Methodology

1OM-33.4.G

Motor-Driven Fire Pump

1OM-33.4.H

Engine-Driven Fire Pump

1OM-56B.4.CR1

Unit 1 Control Room Fire

1OM-56B.4.NS1

Unit 1 Normal Switchgear Room Fire

2OM-10.4.A

Residual Heat Removal System Startup

2OM-10.4.C

Residual Heat Removal System Shutdown

2OM-56B.4.CB1

Unit 2 Instrumentation and Relay Area

BVBP-OPS-0043

Control of Time Sensitive Actions

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NOBP-OP-1113

Control of Time Sensitive Operator Actions

Self-

Assessments

ATA-2021-8471

Beaver Valley Power Station Pre-NRC Fire Prevention

Inspection Self-Assessment

08/20/2021

Work Orders

200531720

200531721

200531725

200531735

200713993

200713997

200715299

200715317

200716516

200716518