IR 05000334/2021010

From kanterella
Jump to navigation Jump to search
Triennial Fire Protection Inspection Report 05000334/2021010 and 05000412/2021010
ML21272A232
Person / Time
Site: Beaver Valley
Issue date: 09/29/2021
From: Glenn Dentel
NRC/RGN-I/DORS
To: Grabnar J
Energy Harbor Nuclear Corp
Dentel G
References
IR 2021010
Download: ML21272A232 (10)


Text

September 29, 2021

SUBJECT:

BEAVER VALLEY POWER STATION, UNITS 1 AND 2 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000334/2021010 AND 05000412/2021010

Dear Mr. Grabnar:

On September 16, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Beaver Valley Power Station, Units 1 and 2 and discussed the results of this inspection with Mr. Matthew Enos, General Plant Manager, Nuclear, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Digitally signed by Glenn T.

Glenn T. Dentel Dentel Date: 2021.09.29 14:34:54-04'00'

Glenn T. Dentel, Chief Engineering Branch 2 Division of Operating Reactor Safety Docket Nos. 05000334 and 05000412 License Nos. DPR-66 and NPF-73

Enclosure:

As stated

Inspection Report

Docket Numbers: 05000334 and 05000412 License Numbers: DPR-66 and NPF-73 Report Numbers: 05000334/2021010 and 05000412/2021010 Enterprise Identifier: I-2021-010-0017 Licensee: Energy Harbor Nuclear Corporation Facility: Beaver Valley Power Station, Units 1 and 2 Location: Shippingport, PA 15077 Inspection Dates: August 30, 2021 to September 16, 2021 Inspectors: E. Dipaolo, Senior Reactor Inspector L. Dumont, Reactor Inspector D. Kern, Senior Reactor Inspector Approved By: Glenn T. Dentel, Chief Engineering Branch 2 Division of Operating Reactor Safety Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Beaver Valley Power Station,

Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site.

However, all the inspection activities were performed onsite. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.21N.05 - Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)

The inspectors verified that the following systems credited in the approved fire protection program could perform their licensing basis function:

(1) Fire Protection Water Supply System
(2) Auxiliary Feedwater System
(3) Chemical Volume Control System
(4) Fire Barriers

Fire Protection Program Administrative Controls (IP Section 03.02) (2 Samples)

The inspectors verified that the selected fire protection administrative controls were implemented in accordance with the current licensing basis. The inspectors verified that the controls were properly implemented with adequate procedures and that the controls met committed industry standards. The following fire protection administrative controls were reviewed:

(1) Control of Transient Combustible Material
(2) National Fire Protection Association (NFPA) 805 Monitoring Program

Fire Protection Program Changes/Modifications (IP Section 03.03) (2 Samples)

The inspectors reviewed fire protection changes/modifications to ensure that they did not constitute an adverse effect on the ability to safely shutdown post-fire and did not degrade assumptions and performance capability stated in the in the safe shutdown analysis. The inspectors verified that fire protection program documents and procedures affected by the changes were updated. The following fire protections program changes/modifications were reviewed:

(1) Engineering Change Package (ECP) 15-0450-000, Unit 1 Early Warning Fire Detection Initiating Device Replacement
(2) ECP 18-0090-000 - Unit 2 Residual Heat Removal System Pump Breaker Normal System Alignment Change

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On September 16, 2021, the inspectors presented the triennial fire protection inspection results to Mr. Matthew Enos, General Plant Manager, Nuclear, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.21N.05 Calculations ARS-BV1-18-217 BVPS-1 Fire Protection SSD Recovery Action Report 2

ARS-BV2-18-219 BVPS-2 Fire Protection SSD Recovery Action Report 2

Calibration CR-2021-05522

Records

Corrective Action CR-2018-07052

Documents CR-2018-08406

CR-2019-02500

CR-2019-05145

CR-2019-09822

CR-2020-00074

CR-2020-00079

CR-2020-07579

CR-2020-08721

CR-2021-00202

CR-2021-00578

CR-2021-00871

CR-2021-02372

CR-2021-03186

CR-2021-05523

Corrective Action CR-2021-06269

Documents CR-2021-06588

Resulting from CR-2021-06600

Inspection CR-2021-06615

CR-2021-06639

CR-2021-06645

CR-2021-06677

CR-2021-06683

CR-2021-06685

CR-2021-06686

CR-2021-06692

CR-2021-06837

Inspection Type Designation Description or Title Revision or

Procedure Date

CR-2021-06844

CR-2021-06868

CR-2021-06886

CR-2021-06906

CR-2021-06950

CR-2021-06954

CR-2021-06966

CR-2021-06973

Drawings OP Manual Fire Protection-Water 22

Figure No. 33-1

OP Manual Fire Protection-Water 24

Figure No. 33-2

Engineering ECP 18-0090- Unit 2 Residual Heat Removal System Pump Breaker 0

Changes 000 Normal System Alignment Change

Engineering 10080-DMC- Beaver Valley Unit 1 and Unit 2 Fire Water Analysis 0

Evaluations 0915

Engineering

Evaluation

Request

601155097

Fire Protection NFPA 20 Code Compliance Review 1

Program Change

Evaluation

(FPPCE)15-025

FPPCE 15-026 Engineering Evaluation of Specified NFPA 24 0

Requirements

FPPCE 18-085 Unit 2 RHS Pump Breaker NSA Chan 0

FPPCE 21-019 Pre-NRC Fire Protection Inspection Self-Assessment-No 0

Surveillance Test that Document Sprinkler System

Inspections

FPPCE 21-021 Fire Alarm and Halon Discharge in Unit 1 Cable Tunnel 1- 1

CV-3

PRA-BV1-21- BVPS-1 Configuration Risk Determination for Both Normal 0

001-R00 Fire Pumps Out of Service

Inspection Type Designation Description or Title Revision or

Procedure Date

PRA-BV2-21- BVPS-2 Configuration Risk Determination for Both Normal 0

2-R00 Fire Pumps Out of Service

Miscellaneous Beaver Valley Power Station Unit 1 Updated Final Safety 32

Analysis Report

Beaver Valley Power Station Unit 2 Updated Final Safety 25

Analysis Report

Beaver Valley Power Station Units 1 and 2 Fire Safety 1

Analysis

Fire Protection Program Health Report, January-June

21

1/2OST-33.12 Fire Pump Flow Test 11/21/2019

and

06/23/2021

1OST-33.34 GDC Diesel Driven Fire Pump Operation Test 08/12/2021

1OST-33.7 Motor Driven Fire Pump Operation Test 03/26/2021

and

05/15/2021

1OST-33.8 Diesel Engine Driven Fire Pump Operation Test 07/17/2021

and

08/14/2021

2OM-10.3 Power Supply and Control Switch List 7

Procedures 1/2-ADM-1900 Fire Protection Program 47

1/2-ADM-1906 Control of Transient Combustible and Flammable 18

Materials

1/2-ADM-1908 Fire Protection Performance Monitoring Program 4

1/2OM-56B.4A.E Safe Shutdown Intent and Methodology 9

1OM-33.4.G Motor-Driven Fire Pump 7

1OM-33.4.H Engine-Driven Fire Pump 7

1OM-56B.4.CR1 Unit 1 Control Room Fire 1

1OM-56B.4.NS1 Unit 1 Normal Switchgear Room Fire 1

2OM-10.4.A Residual Heat Removal System Startup 45

2OM-10.4.C Residual Heat Removal System Shutdown 42

2OM-56B.4.CB1 Unit 2 Instrumentation and Relay Area 0

BVBP-OPS-0043 Control of Time Sensitive Actions 1

Inspection Type Designation Description or Title Revision or

Procedure Date

NOBP-OP-1113 Control of Time Sensitive Operator Actions 2

Self- ATA-2021-8471 Beaver Valley Power Station Pre-NRC Fire Prevention 08/20/2021

Assessments Inspection Self-Assessment

Work Orders 200531720

200531721

200531725

200531735

200713993

200713997

200715299

200715317

200716516

200716518

8