IR 05000334/2023401

From kanterella
Jump to navigation Jump to search
Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only)
ML23264A088
Person / Time
Site: Beaver Valley
Issue date: 09/21/2023
From: Glenn Dentel
NRC/RGN-I/DORS
To: Blair B
Energy Harbor Nuclear Corp
References
IR 2023401
Download: ML23264A088 (1)


Text

September 21, 2023

SUBJECT:

BEAVER VALLEY POWER STATION, UNITS 1 AND 2 - CYBERSECURITY INSPECTION REPORT 05000334/2023401 AND 05000412/2023401

Dear Barry Blair:

On August 11, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Beaver Valley Power Station, Units 1 and 2 and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Three findings of very low security significance (Green) are documented in this report. Three of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at Beaver Valley Power Station, Units 1 and 2.

The following cross cutting aspects were assigned to findings using Inspection Manual Chapter 0310 Aspects Within Cross Cutting Areas: one [H.1] - Resources, one [H.14] - Conservative Bias, and one [H.5] - Work Management.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at Beaver Valley Power Station, Units 1 and 2. This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

The enclosed report contains Security-Related Information, so the enclosed report will not be made publicly available in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).

Sincerely, Digitally signed by Glenn Glenn T. T. Dentel Date: 2023.09.21 Dentel 14:08:38 -04'00'

Glenn T. Dentel, Chief Engineering Branch 2 Division of Operating Reactor Safety Docket Nos. 05000334 and 05000412 License Nos. DPR-66 and NPF-73 Enclosure:

As stated cc w/o encl: Distribution via LISTSERV cc w/encl:

DShearer, Director, Bureau of Radiation Protection, PA Department of Environmental Protection WDeHaas, Bureau of Radiation Protection, PA Department of Environmental Protection JSharpless, Superintendent Security Operations ML23264A090 (Cover letter w/ enclosure(s))

ADAMS ACCESSION NUMBER: ML23264A088 (Cover letter)

Entire Report: Non-Sensitive Publicly Available x SUNSI Review x Sensitive x Non-Publicly Available Cover Letter Only: x Non-Sensitive x Publicly Available x SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DORS RI/DORS RI/DORS RI/DORS NAME MYoung DWerkheiser LDumont GDentel DATE 9/21/2023 9/21/2023 9/21/2023 9/21/2023