Letter Sequence Approval |
---|
EPID:L-2023-LLR-0021, 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations (Approved, Closed) |
|
|
|
---|
Category:Code Relief or Alternative
MONTHYEARML24226A3652024-05-13013 May 2024 Approval of Request for Alternative from Certain Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code ML23249A1842023-09-18018 September 2023 Authorization and Safety Evaluation for Alternative Request No. 2-TYP-4-RV-06 ML22082A2532022-03-29029 March 2022 Correction Letter - Issuance of Authorization of Proposed Alternative to Use ASME OM Code Case OMN-27 ML22012A2972022-01-21021 January 2022 Proposed Alternative to Use ASME OM Code Case OMN-27 L-20-256, Request to Use Provision in Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2020-09-28028 September 2020 Request to Use Provision in Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI ML20223A0142020-08-20020 August 2020 Issuance of Relief Request SSR-1, Revision 0, from the Requirements of the ASME Code (EPID L-2020-LLR-0050 (COVID-19)) ML20206K8652020-08-0707 August 2020 Relief Requests 2-TYP-4-RV-06 and 2-TYP-4-RV-07 from the Requirements of the ASME Code (EPID L-2020-LLR-0053 and EPID L-2020-LLR-0054 (COVID-19)) ML20145A0002020-06-0303 June 2020 Relief from the Requirements of the ASME Code for Requests VRR6 and VRR5 (EPID L-2020-LLR-0049 and EPID L-2020-LLR-0051 (COVID-19)) ML20100N3222020-04-0909 April 2020 Verbal Relief for Penetration Evaluation and Hot Leg Nozzles - Delivered 4/9/2020 at 10:00 Am ML20099B2572020-04-0808 April 2020 Verbal Relief Unit 2 CIV ML20098F3012020-04-0707 April 2020 Verbal Relief for Appendix I Safety Relief Valves ML20095J2192020-04-0404 April 2020 Email Beaver Valley Power Station, Unit 2 - Verbal Relief for MOVs - Delivered 4/4/2020 at 4:00 Pm ML20095J0992020-04-0404 April 2020 Email Beaver Valley Power Station, Unit 2 - Verbal Relief for Snubbers - Delivered 4/4/2020 at 4:00 P.M L-20-117, 10 CFR 50.55a Request Number 2-TYP-4-RV-06, Hardship for Hot Leg Nozzle Inspections2020-04-0303 April 2020 10 CFR 50.55a Request Number 2-TYP-4-RV-06, Hardship for Hot Leg Nozzle Inspections L-20-118, CFR 50.55a Request Number SRR-1, Revision 0, Snubber Testing2020-04-0303 April 2020 CFR 50.55a Request Number SRR-1, Revision 0, Snubber Testing L-20-060, CFR 50.55a Request Number: VRR4, Revision 0, Containment Isolation Valve Test Frequency2020-04-0202 April 2020 CFR 50.55a Request Number: VRR4, Revision 0, Containment Isolation Valve Test Frequency L-20-116, CFR 50.55a Request Number VRR6, Revision 0, Motor-Operated Valve Test Frequency2020-04-0101 April 2020 CFR 50.55a Request Number VRR6, Revision 0, Motor-Operated Valve Test Frequency ML20079F8162020-03-26026 March 2020 Relief Requests 1-TYP-4-C2.21-1 and 1-TYP-4-RA-1 Regarding Weld Examination Coverage for the Fourth Inservice Inspection Interval ML19275E2942019-10-16016 October 2019 Issuance of Relief Request Proposed Alternative to Reactor Vessel Nozzle Weld Examination Frequency Requirements in Lieu of Specific ASME Code Requirements L-19-107, Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements2019-08-27027 August 2019 Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements ML19051A1082019-02-20020 February 2019 Request Alternative Examination Frequency for Reactor Vessel Nozzle to Safe-End Welds (Request 2-TYP-4-RV-05, Revision 0) ML18227A7332018-08-27027 August 2018 Request for Relief from the Requirements of the ASME Code ML18004A1222018-01-22022 January 2018 FENOC-Beaver Valley, Davis-Besse, and Perry - Alternative for the Use of ASME Code Case N-513-4 (CAC Nos. MG0120, MG0121, MG0122, and MG0123; EPID L-2017-LLR-0088) L-17-317, Request to Extend Certain Reactor Vessel Inspections from 10 to 20 Years (Request 1-TYP-4-BN-01)2017-11-15015 November 2017 Request to Extend Certain Reactor Vessel Inspections from 10 to 20 Years (Request 1-TYP-4-BN-01) L-17-308, 10 CFR 50.55a Request for Alternate Reactor Vessel Nozzle Flaw Depth Sizing Criteria (Request 2-TYP-4-RVSE-2)2017-10-25025 October 2017 10 CFR 50.55a Request for Alternate Reactor Vessel Nozzle Flaw Depth Sizing Criteria (Request 2-TYP-4-RVSE-2) ML17167A0672017-06-26026 June 2017 Requests for Alternatives and Requests for Relief Fourth 10-Year Inservice Test Program Interval (CAC Nos. MF8333-MF8356). Note: Correction Safety Evaluation See ML17255A526 ML17159A4422017-06-26026 June 2017 Requests for Alternatives and Requests for Relief Fifth 10-Year Inservice Testing Program Interval (CAC Nos. MF8332 Through MF8357). Note: Correction Safety Evaluation See ML17255A508 ML17047A6102017-03-0202 March 2017 Relief from the Requirements of the American Society of Mechanical Engineers Code ML17041A1852017-03-0202 March 2017 Relief from the Requirements of the ASME Code ML17048A0042017-03-0202 March 2017 Relief from the Requirements of the ASME Code ML16328A1252017-01-23023 January 2017 Relief from the Requirements of the American Society of Mechanical Engineers (ASME) Code for Operation and Maintenance of Nuclear Power Plants (OM Code) (TAC No. MF7780 - MF7783) ML16190A1332016-12-27027 December 2016 Relief from the Requirements of the ASME Code ML16319A0572016-12-0101 December 2016 Acceptance of Requested Licensing Action Relief Request for Proposed Alternative to Perform As-Found Set-Pressure Test ML16257A6212016-11-21021 November 2016 Relief Request BV2-PZR-01, Regarding Alternative to Requirements for Components Connected to the Steam Side of the Pressurizer ML16228A4082016-10-21021 October 2016 Correction to Relief Request 2-TYP-3-RV-04, Revision 0, Regarding Repair Activities for Reactor Vessel Head Penetration Nozzles and Associated J-Groove Welds ML16147A3622016-06-17017 June 2016 Relief Request No. 2-TYP-3-RV-04, Revision 0, Regarding Repair Activities for Reactor Vessel Head Penetration Nozzles and Associated J-Groove Welds ML14363A4092015-01-28028 January 2015 Relief Request No. 1-TYP-4-RV-04 Regarding the Examination Requirements of Code Case N-729-1 ML1202702982012-02-0707 February 2012 Relief Request VRR3 Regarding Solenoid Operated Valve Remote Position Verification Frequency ML1131304282011-11-22022 November 2011 Relief Request VRR5 Regarding Turbine Driven Auxiliary Feedwater Valve Test Frequency for the 10-Year Inservice Testing Program Interval ML1126404122011-09-20020 September 2011 Acceptance Review Results for VC Summer Relief Request (ME6879) ML1107705512011-04-26026 April 2011 Relief Request VRR2 Regarding the 10-Year Inservice Testing Program Interval ML1104705572011-02-25025 February 2011 Relief Request Regarding an Alternative Weld Repair Method for Reactor Vessel Head Penetrations J-Groove Welds ML1006807812010-03-12012 March 2010 Third 10-Year ISI Interval Relief Request (ME2608) L-08-362, Beaver, Units 1 and 2, Proposed Alternative to American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Paragraph IWA-5244 Examination Requirements2008-12-0202 December 2008 Beaver, Units 1 and 2, Proposed Alternative to American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Paragraph IWA-5244 Examination Requirements L-08-207, Proposed Alternative to American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Inspection Period Extension Requirement2008-09-24024 September 2008 Proposed Alternative to American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Inspection Period Extension Requirement L-08-069, Impractical American Society of Mechanical Engineers Code Section XI Weld Examination Requirements (Request Nos. 1-TYP-3-RA-1, 1-TYP-3-RA-2, 1-TYP-3-RA-3)2008-04-0909 April 2008 Impractical American Society of Mechanical Engineers Code Section XI Weld Examination Requirements (Request Nos. 1-TYP-3-RA-1, 1-TYP-3-RA-2, 1-TYP-3-RA-3) ML0720504882007-09-17017 September 2007 Relief Request No. BV1-PZR-01 Regarding Weld Overlay Repairs on Pressurizer Nozzle Welds ML0705905552007-04-30030 April 2007 Relief, Relief Request No. BV2-PZR-01 Regarding Weld Overlay Repairs on Pressurizer Nozzle Welds L-07-056, Requests Approval of Proposed Alternatives and Relief for Inservice Testing Program Ten-Year Update2007-03-28028 March 2007 Requests Approval of Proposed Alternatives and Relief for Inservice Testing Program Ten-Year Update ML0625801202006-10-0202 October 2006 (BVPS-1 and 2), Inservice Inspection (ISI) Program, Alternative Examination of Reactor Coolant Pipe Welds, Request for Relief No. BV3-RV-2 2024-05-13
[Table view] Category:Letter
MONTHYEARIR 05000334/20240112024-10-17017 October 2024 License Renewal Phase IV Inspection Report 05000334/2024011 L-24-038, License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References2024-09-17017 September 2024 License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References L-24-015, Twenty-Ninth Refueling Outage Inservice Inspection Summary Report2024-09-17017 September 2024 Twenty-Ninth Refueling Outage Inservice Inspection Summary Report ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24260A1912024-09-16016 September 2024 Operator Licensing Examination Approval IR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 L-24-199, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-08-22022 August 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 ML24208A0462024-07-26026 July 2024 NRC Office of Investigations Case No. 1-2023-005 L-24-182, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-23023 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-161, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-19019 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 05000334/LER-2024-004, Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control2024-07-17017 July 2024 Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control L-24-014, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models2024-07-16016 July 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models ML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 05000334/LER-2024-003, Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping2024-07-0202 July 2024 Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping L-24-164, BV-2, Post Accident Monitor Report2024-06-27027 June 2024 BV-2, Post Accident Monitor Report IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) L-24-094, Reactor Vessel Surveillance Capsule Withdrawal Schedule2024-06-24024 June 2024 Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-152, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-06-17017 June 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations 05000334/LER-2024-002, Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation2024-06-11011 June 2024 Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation 05000334/LER-2024-001, Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification2024-06-0606 June 2024 Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports L-24-021, Cycle 30 Core Operating Limits Report2024-05-23023 May 2024 Cycle 30 Core Operating Limits Report L-24-121, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-05-23023 May 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24141A1052024-05-20020 May 2024 Senior Reactor and Reactor Operator Initial License Examinations IR 05000334/20240102024-05-15015 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000334/2024010 and 05000412/2024010 L-24-107, CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair2024-05-13013 May 2024 CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair IR 05000334/20240012024-05-0808 May 2024 Integrated Inspection Report 05000334/2024001 and 05000412/2024001 L-23-269, Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2024-05-0707 May 2024 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions L-24-054, Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological)2024-04-29029 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological) L-24-089, Emergency Preparedness Plan2024-04-23023 April 2024 Emergency Preparedness Plan L-24-088, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 20242024-04-22022 April 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 2024 ML24101A2752024-04-10010 April 2024 Response to Request for Additional Information Regarding Spring 2023 180-Day Steam Generator Tube Inspection Report L-24-082, Withdrawal of Exemption Request2024-04-0303 April 2024 Withdrawal of Exemption Request L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-24-064, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152024-03-13013 March 2024 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24044A0662024-03-0404 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0083 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24057A0752024-03-0101 March 2024 The Associated Independent Spent Fuel Storage Installations IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee 05000412/LER-2023-003-01, Missile Barrier Door Left Open Resulting in a Loss of Safety Function2024-02-20020 February 2024 Missile Barrier Door Left Open Resulting in a Loss of Safety Function IR 05000334/20230042024-02-12012 February 2024 Integrated Inspection Report 05000334/2023004 and 05000412/2023004 ML24025A0922024-01-25025 January 2024 Requalification Program Inspection 2024-09-17
[Table view] Category:Safety Evaluation
MONTHYEARML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule ML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML23249A1842023-09-18018 September 2023 Authorization and Safety Evaluation for Alternative Request No. 2-TYP-4-RV-06 ML23188A0982023-07-17017 July 2023 – Correction to the Safety Evaluation Issued Related to Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23019A0032023-03-16016 March 2023 – Issuance of Amendment Nos. 320 and 210 Adoption of Technical Specifications Task Force (Tstf) Traveler Tstf-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23062A5212023-03-0606 March 2023 – Issuance of Amendment No. 319 Revise Technical Specification (TS) 3.5.2, ECCS – Operating, Limiting Condition for Operation (LCO) 3.5.2, ML22277A8142022-10-0707 October 2022 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 315 and 205 Regarding Changes to the Emergency Preparedness Plan ML22210A0102022-09-16016 September 2022 Energy Harbor Fleet- Issuance of Amendments Regarding Adoption of TSTF 554, Revise Reactor Coolant Leakage Requirements ML22235A7672022-09-0101 September 2022 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 315 and 205 Regarding Changes to the Emergency Preparedness Plan ML22222A0862022-09-0101 September 2022 Issuance of Amendment Nos. 317 and 208 Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start and Bus Separation Instrumentation ML22202A4642022-06-29029 June 2022 Emergency Plan Safety Evaluation ML22140A2092022-06-28028 June 2022 Issuance of Amendment No. 207 Correct TS 3.1.7 Change Made by TSTF-547 ML22095A2352022-05-10010 May 2022 Issuance of Amendment Nos. 316 and 206 Revise Technical Specification 5.6.3, Core Operating Limits Report (COLR) ML21286A7822022-05-0606 May 2022 Issuance of Amendment Nos. 315 and 205 Regarding Changes to the Emergency Plan ML22077A1342022-05-0202 May 2022 Issuance of Amendment Nos. 314 and 204 Revise Technical Specifications to Adopt TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML22082A2532022-03-29029 March 2022 Correction Letter - Issuance of Authorization of Proposed Alternative to Use ASME OM Code Case OMN-27 ML22012A2972022-01-21021 January 2022 Proposed Alternative to Use ASME OM Code Case OMN-27 ML21197A0092021-11-0101 November 2021 Issuance of Amendment Nos. 313 and 203 Reactor Coolant System, Pressure and Temperature Limits Report ML21214A2752021-10-15015 October 2021 Issuance of Amendment Nos. 312 and 202 Atmospheric Dump Valves ML21153A1762021-06-30030 June 2021 Issuance of Amendment No. 201 Revision of Technical Specifications Related to Steam Generator Tube Inspection, and Repair Methods ML21075A1132021-04-16016 April 2021 Issuance of Amendment Nos. 311, 200, and 302 to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff, Into the Technical Specifications ML21070A0002021-03-22022 March 2021 Issuance of Amendment 310, Revise Technical Specification 5.5.5.1, Unit 1 SG Program, to Defer Spring 2021 Refueling Outage Steam Generator Inspections to Fall 2022 Refueling Outage ML20346A0222021-03-10010 March 2021 Issuance of Amendment Nos. 309 and 199 to Change Technical Specifications to Implement New Surveillance Methods for the Heat Flux Hot Channel Factor ML20335A0522021-02-18018 February 2021 Issuance of Amendment Nos. 308 and 198 to Modify Certified Fuel Handler Related Technical Specifications for Permanently Defueled Condition ML20345A2362021-01-28028 January 2021 Issuance of Amendment Nos. 307 and 197 to Add Containment Sump Technical Specifications to Address GSI-191 Issues ML20335A0232020-12-28028 December 2020 Issuance of Amendment Nos. 306 and 196 to Remove License Conditions B and C Related to the Irradiated Fuel Management Plans ML20285A2662020-10-21021 October 2020 Correction to Safety Evaluation for Amendment Nos. 305 and 195 Issued September 23, 2020, Modify Primary and Secondary Coolant Activity Technical Specifications ML20279A4402020-10-0808 October 2020 Energy Harbor Fleet-Beaver Valley Power Station; Davis-Besse Nuclear Power Station, and Perry Nuclear Power Plant - Request to Use a Provision of a Later Edition of the ASME Engineers Boiler and Pressure Vessel Code, Section XI ML20213A7312020-09-23023 September 2020 Issuance of Amendment Nos. 305 and 195 to Modify Primary and Secondary Coolant Activity Technical Specifications ML20223A0142020-08-20020 August 2020 Issuance of Relief Request SSR-1, Revision 0, from the Requirements of the ASME Code (EPID L-2020-LLR-0050 (COVID-19)) ML20206K8652020-08-0707 August 2020 Relief Requests 2-TYP-4-RV-06 and 2-TYP-4-RV-07 from the Requirements of the ASME Code (EPID L-2020-LLR-0053 and EPID L-2020-LLR-0054 (COVID-19)) ML20153A0142020-07-16016 July 2020 Relief from the Requirements of the American Society of Mechanical Engineers Code Regarding Request VRR4 (EPID L-2020-LLR-0052 (COVID-19)) ML20145A0002020-06-0303 June 2020 Relief from the Requirements of the ASME Code for Requests VRR6 and VRR5 (EPID L-2020-LLR-0049 and EPID L-2020-LLR-0051 (COVID-19)) ML20080J7892020-04-28028 April 2020 Relief Requests 2 TYP-3-B3.110-1, 2-TYP-3-C2.21-1, 2-TYP-3-C1.30-1, and 2-TYP-3-RA-1 Regarding Weld Examination Coverage for the Third Inservice Inspection Interval ML20079F8162020-03-26026 March 2020 Relief Requests 1-TYP-4-C2.21-1 and 1-TYP-4-RA-1 Regarding Weld Examination Coverage for the Fourth Inservice Inspection Interval ML19336A0282019-12-18018 December 2019 Safety Evaluation Irradiated Fuel Management Plans ML19305B1312019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Enclosure 6, Non-Proprietary Safety Evaluation, Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley Units 1 and 2, Davis-Besse Unit 1, and Perry Unit 1 ML19275E2942019-10-16016 October 2019 Issuance of Relief Request Proposed Alternative to Reactor Vessel Nozzle Weld Examination Frequency Requirements in Lieu of Specific ASME Code Requirements ML19028A0302019-04-11011 April 2019 FENOC - Beaver Valley Power Station, Unit 1 & 2; Davis-Besse Nuclear Power Station Unit 1; and Perry Nuclear Power Plant Unit 1 - Approval of Certified Fuel Handler Training and Retraining Program ML18348B2062019-02-25025 February 2019 Issuance of Amendment No. 193 Revise Steam Generator Technical Specifications ML18249A1692018-09-0707 September 2018 Seismic Hazard Mitigation Strategies Assessment (CAC Nos. MF7800 and MF7801; EPID L-2016-JLD-0006) ML18227A7332018-08-27027 August 2018 Request for Relief from the Requirements of the ASME Code ML18205A2922018-08-10010 August 2018 Correction of Errors in Safety Evaluation Associated with Relief Request 2-TYP-4-RV-02 ML18179A4672018-07-30030 July 2018 FENOC-Beaver Valley Power Station, Unit No. 1 and 2; Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 - Issuance of Amendments Request to Adopt TSTF-529, Clarify Use and Application Rules ML18178A1122018-07-0202 July 2018 Relief Request No. 2-TYP-4-RV-02 Regarding the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-729-4 Examination Requirements ML18065A4032018-04-0505 April 2018 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 301 and 190 ML18073A1062018-03-28028 March 2018 Safety Evaluation of Proposed Alternatives 1-TYP-4-BA-01 and TYP-4-BN-01 Regarding the Fourth 10- Year Interval of the Inservice Inspection Program 2024-07-16
[Table view] |
Text
September 18, 2023
BEAVER VALLEY POWER STATION, UNIT NO. 2
AUTHORIZATION AND SAFETY EVALUATION FOR
ALTERNATIVE REQUEST NO. 2-TYP-4-RV-06
(EPID L-2023-LLR-0021)
LICENSEE INFORMATION
Recipients Name and Address :
Mr. Barry N. Blair Site Vice President Energy Harbor Nuclear Corp.
Beaver Valley Power Station Mail Stop P-BV-SSEB P.O. Box 4, Route 168 Shippingport, PA 15077-0004
Licensee: Energy Harbor Nuclear Corp.
Plant Name and Unit: Beaver Valley, Unit 2
Docket No.: 50-412
APPLICATION INFORMATION
Submittal Date: April 28, 2023
Submittal Agencywide Documents Access and Management System (ADAMS) Accession No.: ML23118A381
Supplement Date: May 5, 2023
Supplement ADAMS Accession No.: ML23125A290
Applicable Inservice Inspection (ISI) Interval and Interval Start/End Dates: The Fourth 10-year ISI interval at Beaver Valley Power Station, Unit 2, (BVPS-2) started on August 29, 2018, and is scheduled to end on August 28, 2028.
Alternative Provision: The applicant requested an alternative under Title 10 of the Code of Federal Regulations (10 CFR), paragraph 50.55a(z)(2), Hardship without a compensating increase in quality and safety.
ISI Requirement: Energy Harbor Nuclear Corp. (licensee) conducts inspections of BVPS-2 reactor vessel head (RVH) in accordance with the American Society of American Engineers
(ASME) Code Case N-729-6, Alternative Examination Requirements for PWR [pressurized-water reactor] Reactor Vessel Upper Heads With Nozzles Having Pressure-Retaining Partial-Penetration Welds, with conditions specified in 10 CFR 50.55a(g)(6)(ii)(D), Augmented ISI requirements: Reactor vessel head inspections.
Applicable Code Edition and Addenda: The applicable code of record for inservice inspection and repair/replacement program at BVPS-2 is ASME Boiler and Pressure Vessel Code (ASME Code),Section XI, 2013 Edition with no Addenda. The construction code for BVPS-2 is ASME Code Section III, 1971 Edition, 1973 Winter Addenda and the BVPS-2 reactor vessel construction code is ASME Section III, 1971 Edition, Summer 1972 Addenda.
Brief Description of the Proposed Alternative: During the spring 2023 refueling outage at BVPS-2, the licensee submitted a proposed alternative, 2-TYP-4-RV-06, for U.S. Nuclear Regulatory Commission (NRC) review and approval to support repair of two unacceptable flaw indications in the RVH vent penetration tube material and associated partial penetration weld at BVPS-2. The licensee stated that its repair will be in accordance with ASME Code,Section XI, IWA-4311, Material, Design or Configuration Changes, and ASME Code Case N-638-10, Similar and Dissimilar Metal Welding Using Ambient Temperature Machine GTAW [Gas Tungsten Arc Weld] Temper Bead Technique, with two specific exceptions to N-638-10 to eliminate the 48-hour hold time for final examination after the completion of temper bead welding, and to allow use of progressive liquid penetrant tests in lieu of volumetric examination.
Specifically, pursuant to 10 CFR 50.55a(z)(2), the licensee submitted the proposed alternative 2-TYP-4-RV-06 on the basis that complying with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
The licensee requested approval of this proposed alternative until the RVH is replaced.
The NRC staff verbally approved proposed alternative 2-TYP-4-RV-06 on May 8, 2023, as documented by email dated May 9, 2023 (M L23129A312). This document provides the NRC staffs formal safety evaluation.
For additional details on the licensees request, please refer to the documents located at the ADAMS Accession Nos. identified above.
STAFF EVALUATION
The NRC staff reviewed and evaluated the licen sees request on the basis of 10 CFR 50.55a(z)(2), such that compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety. The licensee stated that this repair is located in a high dose area and explained the hardship associated with this requirement was due to the limited geometry of the repair cavity. As such, meaningful volumetric examination results could not be obtained and alternative methods, such as eddy current examination, were not readily available. The NRC staff finds the licensees assessment of high radiological dose area and limited geometry meets the hardship requirement of 10 CFR 50.55a(z)(2).
The NRC staff reviewed the level of quality and safety of the licensees proposed alternative.
The licensees proposed repair includes removal of defect, verification of defect removal with surface examination, applying an intermediate weld buffer layer on cladding on the outer parameter of the weld excavation to provide is olation from contaminants in the cladding from affecting weld quality, followed by temper bead weld repair of the excavation with progressive surface examination of first three layers and each 3/16-inch weld deposit after that, followed by a final inspection. The NRC staff notes, as explained by the licensee, that the NRC has previously approved liquid penetrant examination in lieu of volumetric examination for temper
bead welding applications (ML23073A156). NRC-approved 2019 Edition of ASME Code,Section III allows progressive surface examinati on for temper bead repairs to partial penetration welds in lieu of volumetric examination if meaningful results cannot be obtained. Therefore, the NRC staff finds the licensees proposed alternative for progressive liquid penetrant tests in lieu of volumetric examination to be acceptable.
The NRC staff reviewed the licensees technical ju stification to eliminate the 48-hour hold time when using austenitic filler materials in the temper bead welding process for P-1 and P-3 ferritic materials. The licensee provided a white paper with detailed technical discussion, industrys operational experience, and list of similar repairs in support for justification of their technical bases for the request to eliminate the 48-hour hold for final nondestructive inspection. The NRC staff found the licensees basis for the proposed repair to be consistent with previous NRC approvals for the elimination of the 48-hour hold time (ML23090A130). The NRC staff is also unaware of any instances of hydrogen induced cracking, the primary concern for the 48-hour hold time, in the hundreds of welds that have been completed by the nuclear industry using various revisions of ASME Code Case N-638. Given this basis, the staff finds the elimination of the 48-hour hold time requirements of ASME Code Case N-638-10 to be acceptable.
The NRC staff reviewed the licensees proposed futu re examinations of the vent line penetration nozzle and associated weld. The NRC staff finds the licensees current understanding of the requirements under 10 CFR 50.55a(g)(6)(ii)(D) to perform a surface examination of the head vent penetration inside diameter combined with a surface examination of the attaching J-groove weld adequate. Given these examinations, including the bare metal visual examinations of the RVH each refueling outage, will be performed throughout the remaining life of the current RVH at BVPS-2, the NRC staff finds reasonable assurance of the continued monitoring of the structural integrity of this component for the remaining life of the current RVH at BVPS-2.
Based on the above evaluation, the NRC staff finds that the licensees proposed alternative 2-TYP-4-RV-06 provides reasonable assurance of structural integrity of the RVH vent line and associated weld for the duration of the proposed alternative. Given the hardship, the NRC staff finds that the complying with the current volumetric examination requirement and 48-hour hold time requirement to be in compliance with ASME Code Case N-638-10 would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety in accordance with 10 CFR 50.55a(z)(2).
CONCLUSION
The NRC staff has determined that complying with the specified requirements described in the licensees request referenced above would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
The proposed alternative provides reasonable assurance of structural integrity of the RVH.
The NRC staff concludes that the licensee has adequately addressed the regulatory requirements set forth in 10 CFR 50.55a(z)(2).
The NRC staff authorizes the use of proposed alternative 2-TYP-4-RV-06 at BVPS-2 for the remaining life of the current RVH, until its replacement.
All other ASME BPV Code,Section XI, requirements for which an alternative was not specifically requested and authorized remain applicable, including third-party review by the Authorized Nuclear Inservice Inspector.
Principal Contributors: Omar Khan, Jay Collins
Date: September 18, 2023
Hipólito J. González, Chief Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
cc: Listserv
ML23249A184 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NRR/DNRL/NPHP/BC NAME VSreenivas KZeleznock (ABaxter for) SCumblidge DATE 09/05/2023 09/14/2023 09/05/2023 OFFICE NRR/DORL/LPL1/BC NAME HGonzález DATE 09/18/2023